Element of Cost overrun and Delay in Construction: A Review
Jeel Yogeshkumar Soni1, Dr. J. R. Pitroda2, Prof. A. N. Bhavsar3
1M.Tech. (Civil) Construction Engineering and Management, BVM Engineering College, Vallabh Vidyanagar,
Gujarat
2Associate Professor, PG Coordinator Construction Engineering and Management, Civil Engineering Department,
BVM Engineering College, Vallabh Vidyanagar,Gujarat. ORCID: 0000-0002-2869-3158
3Associate Professor, Construction Engineering and Management Civil Engineering Dept.
BVM Engineering College Vallabh Vidyanagar, Gujarat
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - In many advanced and emerging countries, delays and cost overruns are common problems in the construction
industry. Time and cost are the main elements of the completion of the project. And our country has a problem regarding
cost and time overrun in the project. The main aim of this study is to assess the risk of various factors that cause time and
cost overruns throughout the life cycle of the construction project. The objective of the study was achieved through a valid
questionnaire. The study clarified which factor is more affected by the cost overrun and delay in construction projects by
using the lower scale analysis and higher scale analysis. And they also give the ranking of the factors.
Key Words: Cost overrun, Time overrun, Factors, Construction project
1.INTRODUCTION
Changes are realities of the development cycle. They are given to answer recently created conditions. Broad and
inadequately oversaw changes might adversely affect project time and cost exhibitions. Two significant issues confronting
the development business are project deferrals and cost invades. In the present profoundly serious monetary climate, the
requirement for finishing development projects inside the specified expense, time outline, and expected execution
assumptions is turning out to be progressively significant. [1]
The advancement business accepts a vital occupation in the arrangement of any nation's wealth. Making economies
approaches the underpinning of general endeavors. There are for the most part three segments in the advancement of
business land improvement which consolidates private and business improvement; system building which joins roads,
railways, control, etc.; and current improvement which contains oil and gas treatment facilities, pipelines, materials, etc.
With the current emphasis on making an actual system, the enormous theory is organized in this part. The Planning
Commission has assessed that theory needs in established to the tune of around 14,500 billion or US$320 billion amid the
11th Five Year Plan period. The parts backing of Indian improvement Industry is the openness of trashy work, availability of
qualified specialists, the immense number of advancement associations (just about 28,000 figured out associations and 75
gigantic contracting associations), serious lack of housing, help from the assembly, and advancement in the mechanical
region. [2]
The improvements of the designs are bringing about the assessment of the development business to confront the
difficulties in the advancement of the assets, cost, and time expected for the development project. The requirement for time
is to conquer the issues related to the development of the board. The forthcoming common designs are more difficult to
build than the antiquated ones. There are different gifted specialists expected to finish such ventures. The division of the
work assists each group with focusing on a particular assignment at a time. It saves time as well as upgrades the nature of
the work done. It helps in the genuine period culmination of the task and decreases the expense in question. [3]
1.1 Need of study
Time and cost are the main elements to the completion of the project and our country has problems regarding the cost
and time overrun in the project so this study is important for analyzing the main causes of the time and cost overrun in
construction management.
1.2 Objective of the study
Below are the study’s objectives:
1. To identify the main factor causing delays and cost overrun in construction project and their impact on a
construction project.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1085
2. To undertake a questionnaire to investigate the existence and the reasons for time and cost overrun.
3. To provide the rank of factors with the help of the scale analysis method.
2. literature review
Bystudying literaturereviews from variousauthorssomewere concluded which are follows:
2.1 Time overruns
Aftab Hameed Memon et al. (2011) It very well may be resolved that the results from this study are calmly like
the disclosures of different examinations. PMC believes that workers for hire are liable for a time overwhelmed issues in a
development project. To arrive at project consummation on schedule, workers for hire are essential to achieve their income
and utilize their monetary assets all the more astoundingly. Additionally, powerful readiness and booking are generally
required and the venture plan necessities to be modernized routinely and gifted staff is utilized so that undertaking can be
overseen accurately and successfully. In light of the finish of the review, the creators suggest that workers for hire are
required,
 To have a good income plan,
 Accomplish Financial assets
 Progress site the executives by recruiting talented staff
 Great preparation and booking is done,
 Plan to be refreshed more than once
The aftereffects of this study can assist with understanding the powerful factors that caused the time invasion and
consequently, an opportunity to foster some framework to diminish the reasons for time overwhelm.[4]
D.A.R. Dolage et al. (2013) The exploration makes references overall and generally to every one of the gatherings
for advocating factors causing time to overwhelm given well-qualified assessment. The references are made with regards to
building development projects taken on by the DOES. As the administration frameworks and executing activities are
comparable across all the public authority organizations in Sri Lanka, the proposals could be substantial with slight changes
by other government foundations.[5]
Mulenga Mukuka et al. (2015) uncovered that there are different impacts of development projects plan invades.
Time overwhelms (augmentation of time), cost invade, debates, intervention, suit, all-out relinquishment, and privileges
were distinguished as the impacts of development plan invades from writing. From the poll overview acquired from the
respondents, it was uncovered that deferral of time, cost overwhelms, loss of benefit, questions, low quality of work because
of rushing the venture, make pressure on the customer, speed increase misfortunes, terrible standing with compression
group, claims, and postponement in getting income by the customer where the best ten known impacts of development
projects cost invade in Gauteng, South Africa. It is accordingly proposed that all individuals from development groups
should be talented and instructed on time invades to minimalize this overwhelm.[6]
Muhammad Akram Akhund1, Ali Raza Khoso et al. (2017) The question of time invasion in development
projects has been inevitable for a long time. Its belongings are various that it prompts delayed down the accomplishment of
plans of any country. The improvement of time invades causes both specialized and task the board related variables. This
advancement may likewise advance the impact of human perspectives, conduct, abilities, and mindset. Essentially, taking
similar issues and challenges the defer network has been future from an alternate point as displayed in figure 2. The goal of
this study is to give positive and negative elements which cause the time to overwhelm in development projects by the
hypothetical structure for the impending review. Validate the meaning of the system it is fundamental to the unwavering
quality and essentialness of the structure.[7]
Nasir Shafiq et al. (2017) The central issues of this exploration are to group the issues and factors that are tested
by the workers for hire, experts, and customers because of the time overwhelm, inspect the reasons for such issues, and
propose a few ideas for an impending exhibition in term of time effectively. Results from this exploration depend on the
answer from the respondent which was formerly being spread during this examination. Additionally, toward the finish of
this examination, the creator might want to underscore fun time usage control in development projects as it would
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1086
guarantee the productivity of a task. Given the examination is complete, improvements in many highlights should be
thought of and checked routinely to guarantee the importance of time introduced in a development project. Defense
methodology that can be applied are outside variables, for example, understaffing ought not to be an issue except if the
organization recently applied to have all the more yet not yet accomplishment, they needed to have a decent arrangement to
utilize and upgrade all the staff. Project chiefs ought to be seriously tolerating and capable. Capacity here is about addition
to correspondence and thinking abilities. To be sure, we concur with individuals which have different foundations thus it is
critical for that person to be adaptable and can deal with the assignments given.[8]
2.2 Cost Overrun
Serdar Durdyev et al. (2012) The principal study of venture the executive’s experts, workers for hire, and
proprietors/customers as talked about in this article connects with the development of private activities in Turkey. The
study zeroed in on distinguishing and positioning arranged by significance, the fundamental variables causing cost
overwhelms. 40 sub-factors have been recognized under 5 gatherings, which are macroeconomic, labor force, project
finance, project the executives, and other outer elements. The principle finishes of the review are as per the following:
• The general positioning outcomes show that the three gatherings felt that the main factors that can cause exorbitant
private tasks cost invades in Turkey are inappropriate preparation, off base venture cost assessment, the significant
expense of required assets (cash, men, materials, and apparatus), absence of gifted labor force, cost of development
materials and high land costs.
• Other sub-factors that arose as not vital, however of interest, are the absence of coordination, cost of the revamps,
deficient term of the agreement time frame, absence of correspondence among gatherings, and poor location of the
executives.
• The outcomes show that a large portion of the issues in private development projects are started from helpless assets
on the board (human, specialized, and material).
The venture group/proprietors could be directed well in their endeavors to address the variables in a savvy way.[9]
Ghaleb J. Sweis et al. (2013) Cost is the fundamental piece of any development project. It is seen that cost
overwhelm is one of the most often happening issues in development projects worldwide and it is more serious in non-
industrial nations. In the same way, as in other emerging nations, the development business in Jordan is likewise impacted
by the expense overwhelm. To decrease development costs, invade, the initial step is to recognize and investigate the main
drivers and variables answerable for this issue. Hence, this paper expects to recognize the variables that play significant
parts in influencing the ventures' expenses so these elements can be mitigated later on. Factors influencing cost overwhelm
were distinguished from the writing and positioned by their needs. This study includes a poll study of 30 architects working
in Jordanian development ventures and optional information from the Ministry of Housing and Public Works connecting
with 57 significant public development projects. Consequences of the poll review showed that the plan changes, absence of
involvement of undertaking type, and area were the principal factors influencing cost invasion. While given the auxiliary
information the main considerations that cause the cost to overwhelm were administrative deferrals, extreme climate
conditions, and configuration changes.[10]
U.Sindhu Vaardini et al. (2016) Cost overwhelms is one of the basic issues looked at in the development
business. A venture might be viewed as an effective undertaking just when it is finished inside the planned expense. In
light of the different writing audits different elements causing cost invasion can be distinguished. What's more with the
proper strategy for information investigation, the main elements impacting the expense overwhelms can be broken down.
In light of the audits, it was recognized that poor climatic conditions, ill-advised preparation, and planning, changes in the
material rate, absence of appropriate site the executives, checking and controlling, ill-advised administration of assets in
development tasks, and poor monetary control in the site can respect cost invades. Future investigations should be
possible on various sorts of ventures like framework projects, water supply, modern, and other specific undertakings.
Furthermore, different examinations should be possible to foresee the genuine expense of an undertaking given the critical
postponed factors by building an expectation model.[11]
Shaiful Amri Mansur et al. (2019) There were 43 general variables distinguished from past examinations as the
conceivable reasons for cost invasion in development projects. They were a gathering of work-related, material-related,
hardware-related, and subcontractor-related variables. There were critical contrasts among the various parts of cost in the
development business of China. The review showed that material expense is the most elevated part, which is trailed by gear,
work, and subcontractor costs, individually. They range from 10% to 30% of the absolute expense. The investigation
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1087
likewise discovered that the normal top-ten expenses things as work, material, gear, and subcontractors are between 79%
to 86% of every part cost. This exhibited the best ten expense things for each cost part are without a doubt the fundamental
supporters of cost invade in development tasks of China when contrasted with different elements.[12]
R Susanti et al. (2020) concentrate on observed 15 variables causing cost to overwhelm in development projects
for example site accessibility delay; site conditions; social site conditions; change request; adjust; subcontractors' or
potentially merchants' exhibition; endorsement/grant delay; incorrectness in planning, booking and asset arranging;
materials value variances; rules and guidelines; proprietor's extra prerequisites; expansion; delay in installment; feeble
income and terrible climate. From the absolute 15 variables recognized, the two proprietors and workers for hire concurred
that "Revise" was the most compelling element causing cost to invade development projects in Indonesia.[13]
2.3 Cost overrun and Delay
Dr.Narayanan Sambu Potty et al. (2011) The variables inciting Time deferrals and cost invade because of a few
gatherings related to development are perceived and planned a survey to look at the rating and positioning of the element.
The investigation of the poll overview will uncover discoveries that are fitting for industry professionals all through
Malaysia. Fumble of undertaking from the three party's project worker, specialist, and proprietor boss to time and cost
invades, Deficiency and need quality materials and proper hardware in the neighborhood market, no material vehicle plan
prepared by the worker for hire, Delay in materials, drawing and proposition endorsements by the advisor and Evil
climate conditions are the downside factors chose from the contextual analysis discoveries. This unbiased and
commonsense outcome delivered will give readiness in the administration of hazard causing factors. Either to take it if
inside the resilience or to be prepared with the right Risk reaction plan for the venture.[14]
S. Shanmugapriya et al. (2013) Time and cost overwhelm are a basic issue looked at by enormous development
ventures in India. It results from different elements which had been known in this review. An aggregate of 70 examples was
found substantial and inspected measurably utilizing the overall significance list strategy on 76 and 54 elements on
schedule and cost invade. It was made that the five most critical variables causing time and cost invades in Indian
development are material market rate, contract change, a significant degree of value prerequisite, project area, relies upon
the freshers to bear the entire obligation for time overwhelms and high transportation cost, change in material detail,
acceleration of material charge, the regular disappointment of development plants and gears, and reconsider for cost
overwhelms. So, this demonstrates that a need for dire consideration is to be placed on these elements to stay away from
time and cost invades.[15]
Nabil Al-Hazim et al. (2015) Most Road development projects in Jordan are ordered by deferral and invade in
cost. Many records and last reports for certain, projects were inspected. The outcomes show that the greater part of the
genuine elements is: Terrain conditions, climate conditions, variety of the request, and accessibility of work. An
exceptionally huge irregularity among anticipated and finishing up costs going from 101% to 600% with a normal of 214%.
Then again, the defer time goes from 125% to 455% with a normal of 226%. To sanction these discoveries, further
exploration is proposed with projects from various topographical destinations and proprietors. In addition, it is prescribed
that different elements ought to must be perceived that give to the development cost, and timetable overwhelms in broad
daylight work projects.[16]
Vaibhav Y Katre et al. (2016) This study is coordinated to inspect the expense overwhelm in Palestinian structure
development projects from specialists' perspective through a poll overview. The examination of the members' answers
uncovered that the expense invade in building development projects is a serious precarious. 100 percent of the respondents
assigned that the normal expense overwhelm that they have talented is somewhere in the range of 10% and 30% of the
undertaking's assessed cost Inputs of the specialists accentuate that the main five elements influencing cost invade in
building development projects are: political circumstance, variety of costs of materials, level of hopefuls, cash trade, and
financial inconstancy. There is great information steadiness and agreement between advisors on the cruelty and recurrence
of the distinguished expense invade factors. It likewise shows that the members are exceptionally endorsed on the effect
and recurrence of the top influencing factors. In light of the review discoveries, the accompanying focuses are prescribed to
limit and control cost overwhelm in building development projects.
• Instructional classes and studios ought to be coordinated to advance the administrative abilities of undertaking
members.
• Material costs and work rates ought to be modernized persistently.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1088
• Enough time should be given for making practicality studies, arranging, planning, data documentation, and delicate
accommodation. This stays away from or limits late varieties.
• Improvement installment should be paid on schedule.
• More correspondence and coordination between project members during all venture stages.
• Top administration should respond totally to political and natural changes through administrative and monetary
systems.[17]
Tabish et al. (2011) has utilized GCC (General Conditions of Contract) 2005 Form CPWD (Central Public Works
Department) 7/8 is used for the study as most of the projects in India are being executed using this form. In the first stage
questionnaire, 50 clauses were used and respondents were asked to indicate how serious is the impact of these 50 contract
clauses on the schedule performance criteria on a 0-3 scale. A total of 130 questionnaires were sent and about 38 responses
were received. All the 50 clauses in the first stage were ranked according to their mean score. It is found that 16 clauses
appear to have a medium impact on the schedule performance of a construction project and the rest 34 clauses have low or
no impact on the schedule performance of construction. Further based on the result of the t-test for a value of 2.5 and alpha
value of 0.01 the 16 clauses were classified into two categories having a low impact value of µ2.5. A total of five clauses cl-3,
cl-7, cl-13.cl-14, and cl-38 emerged in the first category while the remaining 11 clauses were having an average impact. A
graph is plotted of impact value of the contract clauses versus the frequency of cases affecting the schedule are plotted, the
clusters were formed and they can be named as:(low frequency-no impact, low frequency-low impact, and so on). Finally,
the author concluded Deviations, Measurements, and Escalation related clauses occupy the top ranking in terms of their
effect on influencing the schedule performance of construction projects and the author has observed a high degree of
agreement between the responses from employers organizations and contractors’ organizations.[18]
4. Case Study
Surabattuni Murali, Sanjeet Kumar “Factors Affecting Overruns Construction Time and Cost: A case
study”.
This work identifies the principal explanations behind time and cost invades in structure projects in light of the overview
arranged, for the people who are working in the Shan-E Awadh project for ground mooring and the mandate on disclosure
of the essential elements of venture schedule postponement and cost overwhelms. The fundamental decisions of the
review are material administration, site conditions, untalented work/work strikes, project worker monetary troubles,
machines, and device hardships. In each of the 81 elements, the previously mentioned five elements are the taking the
higher rightness. Different variables were too pieces of inspiration to schedule deferrals and cost invades to the task,
however not as much position of those over five elements. The outcome shows that a significant number of the issues in-
ground securing projects regularly come from the execution of the undertaking; project execution necessities that control
these sorts of variables to beat these invades, project the board techniques for arranging, coordinating, controlling,
observing, the methodology is needed to carry out.[19]
Chitranjan Kumar, chhavi Gupta “Study of Factors Causing Cost and Time Overrun in Construction
Projects”.
It presents the significant ends drawn from the investigation of insight concerning the documentation and computation
of variables influencing time and cost overwhelms in the design projects. The best five elements for cost invade in the list of
positions coming from 57.55 percent-50.28 percent are locked in as the fundamental elements from the arithmetical
outcomes. From the above outcomes, it is resolved that the primary elements are 'Progress and development of material
value', 'Distinction in the venture by proprietor', 'High transportation cost', 'successive breakdown of the developing plant
and gear, and 'modify because of mistakes all through development.[20]
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1089
Table- 1: Factors of Cost and Time overruns identified in different research papers
Aftab
Mem0n
(2011)
Tabish
(2011)
Gulebi
sweis
(2013)
D.A.R
collage
(2013)
Mulenga
mutuka
(2015)
Nabil
al.Hazim
(2015)
Vaibhav
y.katre
(2016)
Ali Raza
(2017)
R.
sushanti
(2020)
Poor-site
management
* * *
Delay of
payment
* *
Low
productivity
of labor
* * * *
Poor material
management
* *
Skilled labor
shortage
* * * *
Price
fluctuation
* * *
Poor
economic
condition
* *
Lack of client
experience
* * *
Change in
scope
* *
Increase in
quantity of
work
* *
Weather
condition
* * * *
4. CONCLUSION
Following are the conclusions from the review study:
1. India has the major problem of time and costs in the construction industry.
2. This study examines the key reasons for time and cost overruns in construction projects and finds the factors which
affect the greatest to the construction by collection from the questionnaire survey and the rank of the features by
using the lower scale analysis/higher scale analysis.
3. Some of the factors like weather conditions, terrain conditions, poor site management, etc. are the main elements
affecting the project.
REFERENCES
[1] Senouci, A., Ismail, A., & Eldin, N. (2016). Time Delay and Cost Overrun in Qatari Public Construction Projects.
Procedia Engineering, 164, 368–375. https://doi.org/10.1016/j.proeng.2016.11.632.
[2] Bhatt, R., & Patel, A. D. (2019). An analysis of cost overruns and time overruns for construction projects: A REVIEW.
www.jetir.org.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1090
[3] Karnavat, A. (2019). Novateur publications international journal of innovations in engineering research and
technology [ijiert] elements of cost overruns, delays and risk in construction management. 6.
[4] Memon, A. H., Abdul Rahman, I., Abdullah, M. R., & Abdul Aziz, A. A. (2011). Time Overrun in Construction Projects
from the Perspective of Project Management Consultant (PMC). Journal of Surveying, Construction & Property, 2(1),
1–13. https://doi.org/10.22452/jscp.vol2no1.4.
[5] Dolage, D. A. R., & Rathnamali, D. L. (n.d.). Causes of Time Overrun in Construction Phase of Building Projects A Case
Study on Department of Engineering Services of Sabaragamuwa Provincial Council: Vol. XXXVI (Issue 03).
[6] Mukuka, M., Aigbavboa, C., & Thwala, W. (2015). Effects of Construction Projects Schedule Overruns: A Case of the
Gauteng Province, South Africa. Procedia Manufacturing, 3, 1690–1695.
https://doi.org/10.1016/j.promfg.2015.07.989.
[7] Akhund, M. A., Khoso, A. R., Memon, U., Khahro, S. H., Akram Akhund, M., Raza Khoso, A., & Khahro, S. H. (2017).
Time Overrun in Construction Projects of Developing Countries Effective Teaching Practices View project Time
Overrun in Construction Projects of Developing Countries. Imperial Journal of Interdisciplinary Research (IJIR), 3.
[8] Othman, I., Shafiq, N., & Nuruddin, M. F. (2018). Time Overrun in Construction Project. IOP Conference Series:
Materials Science and Engineering, 291(1). https://doi.org/10.1088/1757-899X/291/1/012016.
[9] Durdyev, S. (2012). Factors causing cost overruns in construction of residential projects; case study of turkey Special
Issue “Moving Towards Digitalization in Building Energy Modeling” View project Majoring in AEC: The factors
influencing students’ choice View project. https://www.researchgate.net/publication/327560967.
[10]Sweis, G., Sweis, R. J., Dahiyat, S. E., Sweis, G. J., Sweis, R., Rumman, M. A., Hussein, R. A., Dahiyat, S. E., Ghaleb, [,
Sweis, J., & Dahiyat, E. (2013). Cost Overruns in Public Construction Projects: The Case of Jordan. In J Am Sci (Vol.
9, Issue 7s).
http://www.jofamericanscience.orghttp://www.jofamericanscience.orgeditor@americanscience.org134http://w
ww.jofamericanscience.org.20.
[11]Vaardini, S. (2016). Study on cost overruns in construction projects-a review.
https://www.researchgate.net/publication/303459769.
[12]Mansur, S. A., Zin, R. M., & Linbo, L. (2019). Components of Cost Overrun in China Construction Projects. IOP
Conference Series: Materials Science and Engineering, 620(1). https://doi.org/10.1088/1757-
899X/620/1/012081.
[13]Susanti, R., & Nurdiana, A. (2020). Cost Overrun in Construction Projects in Indonesia. IOP Conference Series: Earth
and Environmental Science, 506(1). https://doi.org/10.1088/1755-1315/506/1/012039.
[14]Dr.Narayanan Sambu Potty (2011) “Analysis of time and cost overrun in Malaysia construction”
DOI:10.4028/www.scientific.net/AMR.452-453.1002.
[15]Sundarrajan, S., Subramanian, K., Www, W. :, & Shanmugapriya, S. (2008). Investigation of Significant factors
influencing Time and Cost Overruns in Indian Construction Projects Waste Management and Applications of BIM
View project pavement engineering View project International Journal of Emerging Technology and Advanced
Engineering Investigation of Significant Factors Influencing Time and Cost Overruns in Indian Construction
Projects. In Certified Journal (Vol. 9001, Issue 10). https://www.researchgate.net/publication/260420132.
[16]Al-Hazim, N., & Abusalem, Z. (2015). Delay and cost overrun in road construction projects in Jordan. International
Journal of Engineering & Technology, 4(2), 288. https://doi.org/10.14419/ijet.v4i2.4409.
[17]IJSR-INTERNATIONAL JOURNAL OF SCIENTIFIC RESEARCH Engineering Elements of Cost Overruns, Delays and Risk
Involved in Construction Management. (n.d.).
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1091
[18]T.Subramani , P S Sruthi , M.Kavitha, “ Causes of Cost Overrun In Construction” IOSR Journal of Engineering
(IOSRJEN) www.iosrjen.org ISSN (e): 2250-3021, ISSN (p): 2278-8719 Vol. 04, Issue 06 (June. 2014), ||V3|| PP 01-
07.
[19]Kumar, S. (2019). Factors Affecting Overruns Construction Time and Cost: A Case Study Academic View project. In
International Journal of Recent Technology and Engineering (IJRTE) (Issue 7).
https://www.researchgate.net/publication/351248320.
[20]Gupta, C., & Kumar, C. (n.d.). Study of Factors Causing Cost and Time Overrun in Construction Projects.
www.ijert.org.

More Related Content

Similar to Element of Cost overrun and Delay in Construction: A Review

IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
IRJET Journal
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
IRJET Journal
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET Journal
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET Journal
 
The Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessThe Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project Success
IRJET Journal
 
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET- 	  Review: Factors Affecting Scheduling of Multiple ProjectsIRJET- 	  Review: Factors Affecting Scheduling of Multiple Projects
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET Journal
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET Journal
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET Journal
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET Journal
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
IRJET Journal
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
iosrjce
 
I012646171
I012646171I012646171
I012646171
IOSR Journals
 
I012646171
I012646171I012646171
I012646171
IOSR Journals
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET Journal
 
Management For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayManagement For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of Delay
IRJET Journal
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET Journal
 
Delay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential ProjectDelay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential Project
IRJET Journal
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
IJERA Editor
 
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Associate Professor in VSB Coimbatore
 

Similar to Element of Cost overrun and Delay in Construction: A Review (20)

IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
The Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessThe Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project Success
 
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET- 	  Review: Factors Affecting Scheduling of Multiple ProjectsIRJET- 	  Review: Factors Affecting Scheduling of Multiple Projects
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
Management For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayManagement For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of Delay
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
Delay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential ProjectDelay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential Project
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
 
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
HODECEDSIET
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
zubairahmad848137
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 

Recently uploaded (20)

New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 

Element of Cost overrun and Delay in Construction: A Review

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1084 Element of Cost overrun and Delay in Construction: A Review Jeel Yogeshkumar Soni1, Dr. J. R. Pitroda2, Prof. A. N. Bhavsar3 1M.Tech. (Civil) Construction Engineering and Management, BVM Engineering College, Vallabh Vidyanagar, Gujarat 2Associate Professor, PG Coordinator Construction Engineering and Management, Civil Engineering Department, BVM Engineering College, Vallabh Vidyanagar,Gujarat. ORCID: 0000-0002-2869-3158 3Associate Professor, Construction Engineering and Management Civil Engineering Dept. BVM Engineering College Vallabh Vidyanagar, Gujarat ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - In many advanced and emerging countries, delays and cost overruns are common problems in the construction industry. Time and cost are the main elements of the completion of the project. And our country has a problem regarding cost and time overrun in the project. The main aim of this study is to assess the risk of various factors that cause time and cost overruns throughout the life cycle of the construction project. The objective of the study was achieved through a valid questionnaire. The study clarified which factor is more affected by the cost overrun and delay in construction projects by using the lower scale analysis and higher scale analysis. And they also give the ranking of the factors. Key Words: Cost overrun, Time overrun, Factors, Construction project 1.INTRODUCTION Changes are realities of the development cycle. They are given to answer recently created conditions. Broad and inadequately oversaw changes might adversely affect project time and cost exhibitions. Two significant issues confronting the development business are project deferrals and cost invades. In the present profoundly serious monetary climate, the requirement for finishing development projects inside the specified expense, time outline, and expected execution assumptions is turning out to be progressively significant. [1] The advancement business accepts a vital occupation in the arrangement of any nation's wealth. Making economies approaches the underpinning of general endeavors. There are for the most part three segments in the advancement of business land improvement which consolidates private and business improvement; system building which joins roads, railways, control, etc.; and current improvement which contains oil and gas treatment facilities, pipelines, materials, etc. With the current emphasis on making an actual system, the enormous theory is organized in this part. The Planning Commission has assessed that theory needs in established to the tune of around 14,500 billion or US$320 billion amid the 11th Five Year Plan period. The parts backing of Indian improvement Industry is the openness of trashy work, availability of qualified specialists, the immense number of advancement associations (just about 28,000 figured out associations and 75 gigantic contracting associations), serious lack of housing, help from the assembly, and advancement in the mechanical region. [2] The improvements of the designs are bringing about the assessment of the development business to confront the difficulties in the advancement of the assets, cost, and time expected for the development project. The requirement for time is to conquer the issues related to the development of the board. The forthcoming common designs are more difficult to build than the antiquated ones. There are different gifted specialists expected to finish such ventures. The division of the work assists each group with focusing on a particular assignment at a time. It saves time as well as upgrades the nature of the work done. It helps in the genuine period culmination of the task and decreases the expense in question. [3] 1.1 Need of study Time and cost are the main elements to the completion of the project and our country has problems regarding the cost and time overrun in the project so this study is important for analyzing the main causes of the time and cost overrun in construction management. 1.2 Objective of the study Below are the study’s objectives: 1. To identify the main factor causing delays and cost overrun in construction project and their impact on a construction project.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1085 2. To undertake a questionnaire to investigate the existence and the reasons for time and cost overrun. 3. To provide the rank of factors with the help of the scale analysis method. 2. literature review Bystudying literaturereviews from variousauthorssomewere concluded which are follows: 2.1 Time overruns Aftab Hameed Memon et al. (2011) It very well may be resolved that the results from this study are calmly like the disclosures of different examinations. PMC believes that workers for hire are liable for a time overwhelmed issues in a development project. To arrive at project consummation on schedule, workers for hire are essential to achieve their income and utilize their monetary assets all the more astoundingly. Additionally, powerful readiness and booking are generally required and the venture plan necessities to be modernized routinely and gifted staff is utilized so that undertaking can be overseen accurately and successfully. In light of the finish of the review, the creators suggest that workers for hire are required,  To have a good income plan,  Accomplish Financial assets  Progress site the executives by recruiting talented staff  Great preparation and booking is done,  Plan to be refreshed more than once The aftereffects of this study can assist with understanding the powerful factors that caused the time invasion and consequently, an opportunity to foster some framework to diminish the reasons for time overwhelm.[4] D.A.R. Dolage et al. (2013) The exploration makes references overall and generally to every one of the gatherings for advocating factors causing time to overwhelm given well-qualified assessment. The references are made with regards to building development projects taken on by the DOES. As the administration frameworks and executing activities are comparable across all the public authority organizations in Sri Lanka, the proposals could be substantial with slight changes by other government foundations.[5] Mulenga Mukuka et al. (2015) uncovered that there are different impacts of development projects plan invades. Time overwhelms (augmentation of time), cost invade, debates, intervention, suit, all-out relinquishment, and privileges were distinguished as the impacts of development plan invades from writing. From the poll overview acquired from the respondents, it was uncovered that deferral of time, cost overwhelms, loss of benefit, questions, low quality of work because of rushing the venture, make pressure on the customer, speed increase misfortunes, terrible standing with compression group, claims, and postponement in getting income by the customer where the best ten known impacts of development projects cost invade in Gauteng, South Africa. It is accordingly proposed that all individuals from development groups should be talented and instructed on time invades to minimalize this overwhelm.[6] Muhammad Akram Akhund1, Ali Raza Khoso et al. (2017) The question of time invasion in development projects has been inevitable for a long time. Its belongings are various that it prompts delayed down the accomplishment of plans of any country. The improvement of time invades causes both specialized and task the board related variables. This advancement may likewise advance the impact of human perspectives, conduct, abilities, and mindset. Essentially, taking similar issues and challenges the defer network has been future from an alternate point as displayed in figure 2. The goal of this study is to give positive and negative elements which cause the time to overwhelm in development projects by the hypothetical structure for the impending review. Validate the meaning of the system it is fundamental to the unwavering quality and essentialness of the structure.[7] Nasir Shafiq et al. (2017) The central issues of this exploration are to group the issues and factors that are tested by the workers for hire, experts, and customers because of the time overwhelm, inspect the reasons for such issues, and propose a few ideas for an impending exhibition in term of time effectively. Results from this exploration depend on the answer from the respondent which was formerly being spread during this examination. Additionally, toward the finish of this examination, the creator might want to underscore fun time usage control in development projects as it would
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1086 guarantee the productivity of a task. Given the examination is complete, improvements in many highlights should be thought of and checked routinely to guarantee the importance of time introduced in a development project. Defense methodology that can be applied are outside variables, for example, understaffing ought not to be an issue except if the organization recently applied to have all the more yet not yet accomplishment, they needed to have a decent arrangement to utilize and upgrade all the staff. Project chiefs ought to be seriously tolerating and capable. Capacity here is about addition to correspondence and thinking abilities. To be sure, we concur with individuals which have different foundations thus it is critical for that person to be adaptable and can deal with the assignments given.[8] 2.2 Cost Overrun Serdar Durdyev et al. (2012) The principal study of venture the executive’s experts, workers for hire, and proprietors/customers as talked about in this article connects with the development of private activities in Turkey. The study zeroed in on distinguishing and positioning arranged by significance, the fundamental variables causing cost overwhelms. 40 sub-factors have been recognized under 5 gatherings, which are macroeconomic, labor force, project finance, project the executives, and other outer elements. The principle finishes of the review are as per the following: • The general positioning outcomes show that the three gatherings felt that the main factors that can cause exorbitant private tasks cost invades in Turkey are inappropriate preparation, off base venture cost assessment, the significant expense of required assets (cash, men, materials, and apparatus), absence of gifted labor force, cost of development materials and high land costs. • Other sub-factors that arose as not vital, however of interest, are the absence of coordination, cost of the revamps, deficient term of the agreement time frame, absence of correspondence among gatherings, and poor location of the executives. • The outcomes show that a large portion of the issues in private development projects are started from helpless assets on the board (human, specialized, and material). The venture group/proprietors could be directed well in their endeavors to address the variables in a savvy way.[9] Ghaleb J. Sweis et al. (2013) Cost is the fundamental piece of any development project. It is seen that cost overwhelm is one of the most often happening issues in development projects worldwide and it is more serious in non- industrial nations. In the same way, as in other emerging nations, the development business in Jordan is likewise impacted by the expense overwhelm. To decrease development costs, invade, the initial step is to recognize and investigate the main drivers and variables answerable for this issue. Hence, this paper expects to recognize the variables that play significant parts in influencing the ventures' expenses so these elements can be mitigated later on. Factors influencing cost overwhelm were distinguished from the writing and positioned by their needs. This study includes a poll study of 30 architects working in Jordanian development ventures and optional information from the Ministry of Housing and Public Works connecting with 57 significant public development projects. Consequences of the poll review showed that the plan changes, absence of involvement of undertaking type, and area were the principal factors influencing cost invasion. While given the auxiliary information the main considerations that cause the cost to overwhelm were administrative deferrals, extreme climate conditions, and configuration changes.[10] U.Sindhu Vaardini et al. (2016) Cost overwhelms is one of the basic issues looked at in the development business. A venture might be viewed as an effective undertaking just when it is finished inside the planned expense. In light of the different writing audits different elements causing cost invasion can be distinguished. What's more with the proper strategy for information investigation, the main elements impacting the expense overwhelms can be broken down. In light of the audits, it was recognized that poor climatic conditions, ill-advised preparation, and planning, changes in the material rate, absence of appropriate site the executives, checking and controlling, ill-advised administration of assets in development tasks, and poor monetary control in the site can respect cost invades. Future investigations should be possible on various sorts of ventures like framework projects, water supply, modern, and other specific undertakings. Furthermore, different examinations should be possible to foresee the genuine expense of an undertaking given the critical postponed factors by building an expectation model.[11] Shaiful Amri Mansur et al. (2019) There were 43 general variables distinguished from past examinations as the conceivable reasons for cost invasion in development projects. They were a gathering of work-related, material-related, hardware-related, and subcontractor-related variables. There were critical contrasts among the various parts of cost in the development business of China. The review showed that material expense is the most elevated part, which is trailed by gear, work, and subcontractor costs, individually. They range from 10% to 30% of the absolute expense. The investigation
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1087 likewise discovered that the normal top-ten expenses things as work, material, gear, and subcontractors are between 79% to 86% of every part cost. This exhibited the best ten expense things for each cost part are without a doubt the fundamental supporters of cost invade in development tasks of China when contrasted with different elements.[12] R Susanti et al. (2020) concentrate on observed 15 variables causing cost to overwhelm in development projects for example site accessibility delay; site conditions; social site conditions; change request; adjust; subcontractors' or potentially merchants' exhibition; endorsement/grant delay; incorrectness in planning, booking and asset arranging; materials value variances; rules and guidelines; proprietor's extra prerequisites; expansion; delay in installment; feeble income and terrible climate. From the absolute 15 variables recognized, the two proprietors and workers for hire concurred that "Revise" was the most compelling element causing cost to invade development projects in Indonesia.[13] 2.3 Cost overrun and Delay Dr.Narayanan Sambu Potty et al. (2011) The variables inciting Time deferrals and cost invade because of a few gatherings related to development are perceived and planned a survey to look at the rating and positioning of the element. The investigation of the poll overview will uncover discoveries that are fitting for industry professionals all through Malaysia. Fumble of undertaking from the three party's project worker, specialist, and proprietor boss to time and cost invades, Deficiency and need quality materials and proper hardware in the neighborhood market, no material vehicle plan prepared by the worker for hire, Delay in materials, drawing and proposition endorsements by the advisor and Evil climate conditions are the downside factors chose from the contextual analysis discoveries. This unbiased and commonsense outcome delivered will give readiness in the administration of hazard causing factors. Either to take it if inside the resilience or to be prepared with the right Risk reaction plan for the venture.[14] S. Shanmugapriya et al. (2013) Time and cost overwhelm are a basic issue looked at by enormous development ventures in India. It results from different elements which had been known in this review. An aggregate of 70 examples was found substantial and inspected measurably utilizing the overall significance list strategy on 76 and 54 elements on schedule and cost invade. It was made that the five most critical variables causing time and cost invades in Indian development are material market rate, contract change, a significant degree of value prerequisite, project area, relies upon the freshers to bear the entire obligation for time overwhelms and high transportation cost, change in material detail, acceleration of material charge, the regular disappointment of development plants and gears, and reconsider for cost overwhelms. So, this demonstrates that a need for dire consideration is to be placed on these elements to stay away from time and cost invades.[15] Nabil Al-Hazim et al. (2015) Most Road development projects in Jordan are ordered by deferral and invade in cost. Many records and last reports for certain, projects were inspected. The outcomes show that the greater part of the genuine elements is: Terrain conditions, climate conditions, variety of the request, and accessibility of work. An exceptionally huge irregularity among anticipated and finishing up costs going from 101% to 600% with a normal of 214%. Then again, the defer time goes from 125% to 455% with a normal of 226%. To sanction these discoveries, further exploration is proposed with projects from various topographical destinations and proprietors. In addition, it is prescribed that different elements ought to must be perceived that give to the development cost, and timetable overwhelms in broad daylight work projects.[16] Vaibhav Y Katre et al. (2016) This study is coordinated to inspect the expense overwhelm in Palestinian structure development projects from specialists' perspective through a poll overview. The examination of the members' answers uncovered that the expense invade in building development projects is a serious precarious. 100 percent of the respondents assigned that the normal expense overwhelm that they have talented is somewhere in the range of 10% and 30% of the undertaking's assessed cost Inputs of the specialists accentuate that the main five elements influencing cost invade in building development projects are: political circumstance, variety of costs of materials, level of hopefuls, cash trade, and financial inconstancy. There is great information steadiness and agreement between advisors on the cruelty and recurrence of the distinguished expense invade factors. It likewise shows that the members are exceptionally endorsed on the effect and recurrence of the top influencing factors. In light of the review discoveries, the accompanying focuses are prescribed to limit and control cost overwhelm in building development projects. • Instructional classes and studios ought to be coordinated to advance the administrative abilities of undertaking members. • Material costs and work rates ought to be modernized persistently.
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1088 • Enough time should be given for making practicality studies, arranging, planning, data documentation, and delicate accommodation. This stays away from or limits late varieties. • Improvement installment should be paid on schedule. • More correspondence and coordination between project members during all venture stages. • Top administration should respond totally to political and natural changes through administrative and monetary systems.[17] Tabish et al. (2011) has utilized GCC (General Conditions of Contract) 2005 Form CPWD (Central Public Works Department) 7/8 is used for the study as most of the projects in India are being executed using this form. In the first stage questionnaire, 50 clauses were used and respondents were asked to indicate how serious is the impact of these 50 contract clauses on the schedule performance criteria on a 0-3 scale. A total of 130 questionnaires were sent and about 38 responses were received. All the 50 clauses in the first stage were ranked according to their mean score. It is found that 16 clauses appear to have a medium impact on the schedule performance of a construction project and the rest 34 clauses have low or no impact on the schedule performance of construction. Further based on the result of the t-test for a value of 2.5 and alpha value of 0.01 the 16 clauses were classified into two categories having a low impact value of µ2.5. A total of five clauses cl-3, cl-7, cl-13.cl-14, and cl-38 emerged in the first category while the remaining 11 clauses were having an average impact. A graph is plotted of impact value of the contract clauses versus the frequency of cases affecting the schedule are plotted, the clusters were formed and they can be named as:(low frequency-no impact, low frequency-low impact, and so on). Finally, the author concluded Deviations, Measurements, and Escalation related clauses occupy the top ranking in terms of their effect on influencing the schedule performance of construction projects and the author has observed a high degree of agreement between the responses from employers organizations and contractors’ organizations.[18] 4. Case Study Surabattuni Murali, Sanjeet Kumar “Factors Affecting Overruns Construction Time and Cost: A case study”. This work identifies the principal explanations behind time and cost invades in structure projects in light of the overview arranged, for the people who are working in the Shan-E Awadh project for ground mooring and the mandate on disclosure of the essential elements of venture schedule postponement and cost overwhelms. The fundamental decisions of the review are material administration, site conditions, untalented work/work strikes, project worker monetary troubles, machines, and device hardships. In each of the 81 elements, the previously mentioned five elements are the taking the higher rightness. Different variables were too pieces of inspiration to schedule deferrals and cost invades to the task, however not as much position of those over five elements. The outcome shows that a significant number of the issues in- ground securing projects regularly come from the execution of the undertaking; project execution necessities that control these sorts of variables to beat these invades, project the board techniques for arranging, coordinating, controlling, observing, the methodology is needed to carry out.[19] Chitranjan Kumar, chhavi Gupta “Study of Factors Causing Cost and Time Overrun in Construction Projects”. It presents the significant ends drawn from the investigation of insight concerning the documentation and computation of variables influencing time and cost overwhelms in the design projects. The best five elements for cost invade in the list of positions coming from 57.55 percent-50.28 percent are locked in as the fundamental elements from the arithmetical outcomes. From the above outcomes, it is resolved that the primary elements are 'Progress and development of material value', 'Distinction in the venture by proprietor', 'High transportation cost', 'successive breakdown of the developing plant and gear, and 'modify because of mistakes all through development.[20]
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1089 Table- 1: Factors of Cost and Time overruns identified in different research papers Aftab Mem0n (2011) Tabish (2011) Gulebi sweis (2013) D.A.R collage (2013) Mulenga mutuka (2015) Nabil al.Hazim (2015) Vaibhav y.katre (2016) Ali Raza (2017) R. sushanti (2020) Poor-site management * * * Delay of payment * * Low productivity of labor * * * * Poor material management * * Skilled labor shortage * * * * Price fluctuation * * * Poor economic condition * * Lack of client experience * * * Change in scope * * Increase in quantity of work * * Weather condition * * * * 4. CONCLUSION Following are the conclusions from the review study: 1. India has the major problem of time and costs in the construction industry. 2. This study examines the key reasons for time and cost overruns in construction projects and finds the factors which affect the greatest to the construction by collection from the questionnaire survey and the rank of the features by using the lower scale analysis/higher scale analysis. 3. Some of the factors like weather conditions, terrain conditions, poor site management, etc. are the main elements affecting the project. REFERENCES [1] Senouci, A., Ismail, A., & Eldin, N. (2016). Time Delay and Cost Overrun in Qatari Public Construction Projects. Procedia Engineering, 164, 368–375. https://doi.org/10.1016/j.proeng.2016.11.632. [2] Bhatt, R., & Patel, A. D. (2019). An analysis of cost overruns and time overruns for construction projects: A REVIEW. www.jetir.org.
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1090 [3] Karnavat, A. (2019). Novateur publications international journal of innovations in engineering research and technology [ijiert] elements of cost overruns, delays and risk in construction management. 6. [4] Memon, A. H., Abdul Rahman, I., Abdullah, M. R., & Abdul Aziz, A. A. (2011). Time Overrun in Construction Projects from the Perspective of Project Management Consultant (PMC). Journal of Surveying, Construction & Property, 2(1), 1–13. https://doi.org/10.22452/jscp.vol2no1.4. [5] Dolage, D. A. R., & Rathnamali, D. L. (n.d.). Causes of Time Overrun in Construction Phase of Building Projects A Case Study on Department of Engineering Services of Sabaragamuwa Provincial Council: Vol. XXXVI (Issue 03). [6] Mukuka, M., Aigbavboa, C., & Thwala, W. (2015). Effects of Construction Projects Schedule Overruns: A Case of the Gauteng Province, South Africa. Procedia Manufacturing, 3, 1690–1695. https://doi.org/10.1016/j.promfg.2015.07.989. [7] Akhund, M. A., Khoso, A. R., Memon, U., Khahro, S. H., Akram Akhund, M., Raza Khoso, A., & Khahro, S. H. (2017). Time Overrun in Construction Projects of Developing Countries Effective Teaching Practices View project Time Overrun in Construction Projects of Developing Countries. Imperial Journal of Interdisciplinary Research (IJIR), 3. [8] Othman, I., Shafiq, N., & Nuruddin, M. F. (2018). Time Overrun in Construction Project. IOP Conference Series: Materials Science and Engineering, 291(1). https://doi.org/10.1088/1757-899X/291/1/012016. [9] Durdyev, S. (2012). Factors causing cost overruns in construction of residential projects; case study of turkey Special Issue “Moving Towards Digitalization in Building Energy Modeling” View project Majoring in AEC: The factors influencing students’ choice View project. https://www.researchgate.net/publication/327560967. [10]Sweis, G., Sweis, R. J., Dahiyat, S. E., Sweis, G. J., Sweis, R., Rumman, M. A., Hussein, R. A., Dahiyat, S. E., Ghaleb, [, Sweis, J., & Dahiyat, E. (2013). Cost Overruns in Public Construction Projects: The Case of Jordan. In J Am Sci (Vol. 9, Issue 7s). http://www.jofamericanscience.orghttp://www.jofamericanscience.orgeditor@americanscience.org134http://w ww.jofamericanscience.org.20. [11]Vaardini, S. (2016). Study on cost overruns in construction projects-a review. https://www.researchgate.net/publication/303459769. [12]Mansur, S. A., Zin, R. M., & Linbo, L. (2019). Components of Cost Overrun in China Construction Projects. IOP Conference Series: Materials Science and Engineering, 620(1). https://doi.org/10.1088/1757- 899X/620/1/012081. [13]Susanti, R., & Nurdiana, A. (2020). Cost Overrun in Construction Projects in Indonesia. IOP Conference Series: Earth and Environmental Science, 506(1). https://doi.org/10.1088/1755-1315/506/1/012039. [14]Dr.Narayanan Sambu Potty (2011) “Analysis of time and cost overrun in Malaysia construction” DOI:10.4028/www.scientific.net/AMR.452-453.1002. [15]Sundarrajan, S., Subramanian, K., Www, W. :, & Shanmugapriya, S. (2008). Investigation of Significant factors influencing Time and Cost Overruns in Indian Construction Projects Waste Management and Applications of BIM View project pavement engineering View project International Journal of Emerging Technology and Advanced Engineering Investigation of Significant Factors Influencing Time and Cost Overruns in Indian Construction Projects. In Certified Journal (Vol. 9001, Issue 10). https://www.researchgate.net/publication/260420132. [16]Al-Hazim, N., & Abusalem, Z. (2015). Delay and cost overrun in road construction projects in Jordan. International Journal of Engineering & Technology, 4(2), 288. https://doi.org/10.14419/ijet.v4i2.4409. [17]IJSR-INTERNATIONAL JOURNAL OF SCIENTIFIC RESEARCH Engineering Elements of Cost Overruns, Delays and Risk Involved in Construction Management. (n.d.).
  • 8. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 04 | Apr 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1091 [18]T.Subramani , P S Sruthi , M.Kavitha, “ Causes of Cost Overrun In Construction” IOSR Journal of Engineering (IOSRJEN) www.iosrjen.org ISSN (e): 2250-3021, ISSN (p): 2278-8719 Vol. 04, Issue 06 (June. 2014), ||V3|| PP 01- 07. [19]Kumar, S. (2019). Factors Affecting Overruns Construction Time and Cost: A Case Study Academic View project. In International Journal of Recent Technology and Engineering (IJRTE) (Issue 7). https://www.researchgate.net/publication/351248320. [20]Gupta, C., & Kumar, C. (n.d.). Study of Factors Causing Cost and Time Overrun in Construction Projects. www.ijert.org.