SlideShare a Scribd company logo
1 of 9
Download to read offline
Open Journal of Civil Engineering, 2013, 3, 127-135
http://dx.doi.org/10.4236/ojce.2013.33015 Published Online September 2013 (http://www.scirp.org/journal/ojce)
Using Multivariable Linear Regression Technique
for Modeling Productivity Construction in Iraq
Faiq Mohammed Sarhan Al-Zwainy1
, Mohammed Hashim Abdulmajeed2
,
Hadi Salih Mijwel Aljumaily3
1
Department of Civil Engineering, College of Engineering, Al-Nahrain University, Baghdad, Iraq
2
Ministry Industry and Minerals, State Industrial Design and Consultation Company (Sidcco), Baghdad, Iraq
3
Department of Environmental Engineering, College of Engineering, Al-Mustansiriya University, Baghdad, Iraq
Email: FAIQ_FAIQMOHMED@yahoo.com
Received June 2, 2013; revised July 2, 2013; accepted July 9, 2013
Copyright © 2013 Faiq Mohammed Sarhan Al-Zwainy et al. This is an open access article distributed under the Creative Commons
Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is
properly cited.
ABSTRACT
Productivity is a very important element in the process of construction project management especially with regard to the
estimation of the duration of the construction activities, this study aims at developing construction productivity estimat-
ing model for marble finishing works of floors using Multivariable Linear Regression technique (MLR). The model was
developed based on 100 set of data collected in Iraq for different types of projects such as residential, commercial and
educational projects. Which these are used in developing the model and evaluating its performance. Ten influencing
factors are utilized for productivity forecasting by MLR model, and they include age, experience, number of the assist
labor, height of the floor, size of the marbles tiles, security conditions, health status for the work team, weather condi-
tions, site condition, and availability of construction materials. One model was built for the prediction of the productiv-
ity of marble finishing works for floors. It was found that MLR have the ability to predict the productivity for finishing
works with excellent degree of accuracy of the coefficient of correlation (R) 90.6%, and average accuracy percentage of
96.3%. This indicates that the relationship between the independent and independent variables of the developed models
is good and the predicted values from a forecast model fit with the real-life data.
Keywords: Multivariable Linear Regression Techniques; Construction Productivity; Finishing Work; Coefficient of
Correlation
1. Introduction
Productivity rates of construction trades are the basis for
accurately estimating time and costs required to complete
a project. Productivity could be defined as “the ratio of
output of required quality to the inputs” for a specific pro-
duction situation; in the construction industry, it is gen-
erally accepted as “work output per man-hours worked”.
Improved productivity helps contractors not only to be
more efficient and profitable; knowing actual productiv-
ity levels also helps them to estimate accurately and be
more competitive during bidding for projects.
In response to the industry needs, the primary goal of
this research was to conduct an accurate measurement of
on-site construction productivity in Iraq through devel-
oping regression models for predicting the productivity
of finishing works for floors with marble. The structure
of research is consisting of Research justifications, Re-
search hypothesis, Research methodology, Literature re-
view, Factors affecting construction productivity, field
data collection, regression models for productivity, vali-
dation of models, Conclusion, recommendations and fu-
ture research.
It is widely accepted that productivity measurement
plays an important role in the construction management
process. Productivity measurement provides the neces-
sary data to analyze factors for project owners, construc-
tors, and management professionals to control construc-
tion progress, estimate the cost of future construction
projects, and determine its competitiveness in the global
market. In achieving these objectives, the researcher
hoped that it could help the Iraq construction firms stay
competitive and profitable in the global markets.
2. Research Justifications
The reasons that stand behind the adoption of this study
work are:
Copyright © 2013 SciRes. OJCE
F. M. S. AL-ZWAINY ET AL.128
1) There are different techniques currently used for
construction productivity estimation at different stages of
the project development process. Some of these methods
suffer the major disadvantages of lack of precision, aged,
slow and uncertainty.
2) Construction sector in Iraq needing for modern effi-
cient construction productivity estimation techniques that
have more advantages such as, being modern, fast, accu-
rate, flexible and easy to use is of value.
3. The Research Hypothesis
The research hypothesis is formulated as “Multivariable
Linear Regression (MLR) has strong modeling technique
with optimization mechanism and effective recognition
capabilities to estimate the production rates under any
specific condition”.
4. Research Methodology
The research objectives were achieved by using the fol-
lowing steps:
1) Literature review: A comprehensive literature re-
view was conducted to provide the previous research
studies related to the construction productivity and to
understand the current Iraq construction industry. The
review synthesized the findings from previous literature
in textbooks, journal papers, research reports, conference
proceedings, theses, dissertations, and Internet publica-
tions, and methods of productivity data analyses. The
review enabled the researcher to better understand the
current status of the field research and to perform studies
in both accuracy and practicability;
2) Data collection: The researcher conducted on-site
construction productivity measurements in the Iraq. The
data were collected from observation and recompiled to a
spreadsheet format that is suitable for statistical data
analysis by using computer software, such as Statistical
Package for the Social Sciences (SPSS);
3) Data analysis and comparison: The data analysis
were conducted by using the statistical software package,
SPSS 19.0, for determining the productivity rate charac-
teristics, and labor productivity. Various statistical analy-
sis methods, including descriptive statistics, correlation,
and nonparametric tests, were also used for modeling
throughout the research;
4) Developed Model: Based on the data analyses’ re-
sults, it will provide Multiple Linear Regression model to
predicting productivity of marble finishing works for
floors and discuses the results from training and testing
this model;
5) Validation Model: This stage, which presented the
validation of the MLR model;
6) Conclusions, recommendations and future research:
Based on the results of the data analyses developed
model and validation model, conclusions and recom-
mendations were provided for this research. The conclu-
sions included the characteristics of the labor productiv-
ity, production effectiveness. In addition, corrective ac-
tions and future research were recommended for other
researchers who are interested in further research on this
topic.
5. Available Productivity Estimation
Techniques
Labor productivity estimates are often performed by in-
dividuals using combinations of analytical techniques
and personal judgment [1]; namely, the worker hour es-
timates are usually obtained through direct interaction
with a scheduler, the site manager or related sub-con-
tractors who are knowledgeable enough to reflect the
actual conditions of a project and its constituent activities
[2]. These individuals often have a library of basic pro-
ductivity rates which are adjusted and recalculated for
each project [3], and always modify their productivity
rates for each specific estimate [4]. On the other hand,
differences in these productivity rates are always likely
and normal [5].
A number of techniques for motion and time study
such as time-lapse photography and video can be used
along with statistics for analyzing and estimating con-
struction-operation productivity [6]. Mathematical mod-
els and discrete event simulation techniques can also be
applied. This paper presents an alternative approach that
utilizes the adaptively of multivariable linear regression
to perform the complex mapping from environment and
management conditions to operation productivity.
One of the most importance techniques is statistic-
based called the multivariable linear regression. It at-
tempts to map the relationships between the influential
factors and the productivity with the explicit mathemati-
cal functions. The mapping functions are initially pre-
sumed and later evaluated. They could be linear func-
tions (multivariable linear regression) or non-linear func-
tions (multivariable non-linear regression). However, the
statistical technique could oversimplify the relationships
comparing with the neural network technique [7].
6. Previous Studies on the Construction
Productivity
Extensive research has been undertaken in construction
labor productivity in the past 35 years. These research
works can be grouped in, but be not limited to, the fol-
lowing topics: 1) productivity models and measurement
([8-11]); 2) productivity improvement ([12-15]); 3) fac-
tors affecting labor productivity ([16-23]); 4) learning
curve theory and application ([24-28]); and 5) productiv-
ity analysis for cumulative impact claims ([29-32]).
Copyright © 2013 SciRes. OJCE
F. M. S. AL-ZWAINY ET AL. 129
In Iraqi construction sector, a few studies concerned
with the subject of productivity construction. Al-Taweel
and Saeed [33] measured the averages and standard per-
formance times for work and labors productivity in some
construction work items through site studying by using
work study. Tahar [34] measured the standard productiv-
ity for the employers for some construction work items
by using the questionnaires styles distributed to different
levels of management. The researcher can immobiliza-
tion the productivity for (600) items for different works
items in construction work. Abd-allah [35] studied a
group of parameters which affect the application of in-
centive schemes in the construction companies in Iraq.
The effect of these parameters on productivity was stud-
ied through the preparation of three questionnaire sets
distributed to different levels of management. Al-Zwainy
[36] used Back-propagation Feed-forward neural net-
works for productivity estimation of the finishing works
with stone tiles for building project.
In this study, the researcher will be comparing the re-
sults of the two different methods to estimate productiv-
ity of marble finishing works for floors; these two meth-
ods are regression analysis and neural networks. For the
subject of estimation construction productivity by neural
networks has been completed as an independent research
and published in the ARPN Journal of Engineering and
Applied Sciences, by the same researcher [37]. In this
research will be to predict construction productivity for
the same work item using multiple linear regressions and
then a comparison between the two methods for the pur-
pose of determining the most accurate method.
7. Regression Analysis
Regression analysis is an extremely powerful tool that
enables the researcher to learn more about the relation-
ships within the data being studied. There are many texts
that describe this technique, and the theory behind its use
will not be discussed in detail here. The Simon [38] has
found the text by Hogg and Ledolter [39] to be particu-
larly useful.
In this instance multiple linear regression will be used
to determine the statistical relationship between a re-
sponse (e.g., actual productivity) and the explanatory
variables (e.g., experience, age). The regression model
requires a few assumptions. It is of the form
0 1 1 2 2iY X X Xp ip i          (1)
where:
1,2, ,I n  ;
Yi is the response that corresponds to the levels of the
explanatory variables 1 2, , , pX X X at the ith observa-
tion.
 0 1, , , p   are the coefficients in the linear rela-
tionship. For a single factor (p = 1), 0 is the inter-
cept, and 1 is the slope of the straight line defined.
 1 2, , , n   are errors that create scatter around the
linear relationship at each of the i = 1 to n observa-
tions. The regression model assumes that these errors
are mutually independent, normally distributed, and
with a zero mean and variance σ2
. It is important to
rate that this sometimes difficult to achieve [38].
To make estimates of the coefficients in the regression
model, the method of least squares is used for both its
mathematical convenience and its ability to provide ex-
plicit expressions for these estimates.
8. Factors Affecting Construction
Productivity
Identification and evaluation of factors affecting labour
construction productivity have become a critical issue
facing project managers for a long time in order to in-
crease productivity in construction. Understanding criti-
cal factors affecting productivity of both positive and
negative can be used to prepare a strategy to reduce inef-
ficiencies and to improve the effectiveness of project
performance. Knowledge and understanding of the vari-
ous factors affecting construction labour productivity is
needed to determine the focus of the necessary steps in
an effort to reduce project cost overrun and project com-
pletion delay, thereby increasing productivity and overall
project performance. Based on the study and survey, al-
though many researchers have been done and produce
the factors that affect productivity, there are still many
productivity problems that remain unknown and need to
be further investigated even in developed countries [40].
In addition, policies for increasing productivity are not
necessarily the same in every country. And the critical
factors in developing countries differ from that in devel-
oping countries.
The methodology used in this research to determine
the factors affecting the productivity of finishing flooring
with marble, involves; Literature survey and Preliminary
interviews.
The researcher conducted a number of personal inter-
views with five (60) engineers who have extensive ex-
perience in managing construction projects in Iraq. Some
of these engineers work as a project manager, estimators,
planners and site engineers, and they working with dif-
ferent companies at the Ministry of Construction and
Housing Iraqi. And all these engineers with experience
not less than twenty years in the field of specialization.
Relying on personal interviews and the literature re-
view, the researcher was able to identify the factors af-
fecting the construction productivity. Ten independent
variables were carefully selected and were well defined
for each construction project. These independent vari-
ables can be classified into two types: objective and sub-
jective variables as shown in Tables 1 and 2, respec-
Copyright © 2013 SciRes. OJCE
F. M. S. AL-ZWAINY ET AL.130
tively below.
The quantitative (objective) variables that can be mea-
sured, depending on the unit of measurement, such as age
is measured in years, experience is measured in years and
floor height is measured in meters.
The qualitative (subjective) variables can be measured
depending on the coding system, for example, the secu-
rity conditions can be classifies to security and non-secu-
rity and assigns them the value 1 and 2, respectively.
Also the health status for work team which specifies as
good, moderate and bad, it assigns them the values of 1,
2 and 3, respectively. While the weather condition; sunny
(1), rainy (2). The site conditions can be classifies to
complex and simple and assigns them the value 1 and 2,
respectively. Where as the scale of 1 and 2 represent near
and far, respectively about availability of construction
materials.
9. Data Collection
Researcher has identified that suitable method of data
collection influenced the accuracy of the production rates
values. However questionnaire survey is the most com-
monly data collection method adopted by the researcher
to collect information on factors and production There-
fore, direct observation method has been selected for
collecting the data in this research. Pilot study has been
done by selecting ten construction projects in different
parts of Iraq. Work sampling approach has been used to
measure the production rates at site to calculate duration
of activity on daily basis at specific time interval using
stop watch. Researcher has been able to get fifteen (15)
number of observation from each of ten (10) projects at
Table 1. The objective variables.
Objective variables Description Units
X1 Age Year
X2 Experience Year
X3 Number of the labor Number
X4 Height of the floor Length (meter)
X5 Size of the marbles tiles Area
Table 2. The subjective variables.
Subjective variables Description Units
X6 The security conditions Category
X7 The health status for the work team Category
X8 Weather conditions Category
X9 Site condition Category
X10 Availability of construction materials Category
different intervals. Among ten projects five residential,
commercial and educational projects are from Baghdad,
four residential projects is from Arbil and one commer-
cial project is from Babylon as shown in Table 3. There-
fore total one hundred and fifty (150) number of data
samples has been gathered.
10. Development of Multivariable Linear
Regression Model
Several functions can be used for studying the relation-
ships among the variables of a given data which were
stated previously at previous section. Multivariable Lin-
ear Regression (MLR) is adopted in the research since
the MLR is the most widely used type and using the pro-
ject characteristics (parameters) in a mathematical model
to predict construction productivity.
The Statistical Product and Solutions Services (SPSS)
software; Vertion. 19 is used to develop the model, and
the results of the statistical analysis are shown in Table 4
and Table 5 below.
The correlation among input variables is tested; the
results are shown in Table 4. The results of r (coefficient
of correlation) and r2
(coefficient of determination) show
that there is a high correlation between construction pro-
ductivity and other input variables. This indicates a good
relationship between dependent and independent vari-
ables.
Table 3. Construction project visited for measuring labor
productivity rates.
Project No. Location Sample data Type of project
Prj.1 Baghdad City 15 residential project
Prj.2 Baghdad City 15 residential projects
Prj.3 Baghdad City 15 educational projects
Prj.4 Baghdad City 15 educational projects
Prj.5 Baghdad City 15 commercial project
Prj.6 Erbil City 15 residential projects
Prj.7 Erbil City 15 residential projects
Prj.8 Erbil City 15 residential projects
Prj.9 Erbil City 15 residential projects
Prj.10 Babylon City 15 commercial project
Table 4. Model Summary.
Model R R square Adjusted R square Std. error of the estimate
1 0.906a
0.821 0.801 2.45965
a
Predictors: (Constant), area, material, site, age, security, weather, labour,
height, experiences, health.
Copyright © 2013 SciRes. OJCE
F. M. S. AL-ZWAINY ET AL. 131
Table 5. Uonstandard coefficients of variables.
Unstandardized coefficients
Model
B Std. error
(Constant) 39.233 5.201
age 0.038 0.044
experiences −0.056 0.052
health status of work team −8.026 1.371
Weather condition −1.447 0.818
Height of the floor −1.523 0.801
No. of labour −0.560 0.552
Security conditions 0.489 1.860
Site condition 0.822 0.577
Material available −0.066 0.674
1
Size marble 46.901 13.585
The values above indicate that at least one of the
model coefficients is nonzero. The model appears to be
useful for predicting the construction productivity. This
model included all the potential independent variables
that have been identified. The model obtained is:
39 233 0 038 1 0 056 2 0 560 3
1 523 4 46 901 5 0 489 6
8 026 7 1 447 8 0 822 9 0 066 10
P . . X . X . X
. X . X . X
. X . X . X . X
   
  
   
(2)
where:
P: productivity of marble finishing works for floors as
output (dependent) variable;
X1, X2, X3, X4, X5, X6, X7, X8, X9, X10: Input (inde-
pendent) variables are shown in Tables 1 and 2.
11. Validation Model
There are several basic ways of validating a regression
model. They are:
1) Statistical test on “r” value.
2) Collection of new data to check the model and its
predictive ability for comparison of results with the ac-
tual productivity of marble finishing works for floors and
the predicted productivity values
11.1 Statistical Test on “R” Value
The following statistical tests were conducted on “R”
(the coefficient of correlation) value for model 1, where
R2
= 0.821, N = 100:
1) Probable Error (P.E.) in “R” value
 2
1
0 6745
R
P.E. .
N
 

 
 
P.E. = 0.01207355 therefore, R = 0.906 ± 0.01207355.
According to Gupta [41]; the probable error is re-
garded as a measure of significance of Karl Person’s co-
efficient of correlation (R), and if the probable error is
small (compared with R), correlation directly exists
where R > 0.5.
Hence, the correlation of the studied productivity
equation is existing.
2) Standard Error (S.E.) in “R” value
2
1 R
S.E.
N
 
 
 
 (4)
S.E. = 0.1906.
Hence, the correlation is accepted for R = 0.906, and
100 observations.
3) Test of significance
Gupta [41]; indicates that the correlation may be ac-
cepted when R > 0.22 (for 100 observations).
Again, the correlation is accepted for R = 0.906, and
100 observations.
4) A simple method of testing whether “R” differs sig-
nificantly from “zero”
Taking null hypothesis that there is no correlation be-
tween the two variables, provided “N” is large:
3
N
(5)
IF the value arrived at by this test is greater than the
observed or computed value of correlation coefficient
(R <
3
N
) correlation is not significant [41];
3 3
0 3 0 906
100
. .
N
   (6)
Hence, coefficient of correlation can be taken as sig-
nificant.
11.2. Collection of New Data to Check the Model
and Its Predictive Ability
In this research, the second method is employed also.
Ten new observations for each concerning variables were
collected as shown in Table 6. These observations which
were not included in the model calibration procedures
were used as independent verification check. While the
actual productivity of marble finishing works for floors
and the predicted values are presented in Table 7.
Table 7 shows that the predicted productivity (by sug-
gested productivity estimation function) predicts an av-
erage difference of 1.291% of the actual productivity.
and the correlation coefficient between them equal to
0.862. also the analyzed results indicates that the produc-
 (3)
Copyright © 2013 SciRes. OJCE
F. M. S. AL-ZWAINY ET AL.132
Table 6. Number of observations for each variable.
No. observations
Variables
1 2 3 4 5 6 7 8 9 10
X1 45 40 40 40 50 50 35 38 45 40
X2 20 15 20 20 18 18 15 22 35 35
X3 1 2 2 2 2 1 2 1 1 1
X4 1 1 1 2 1 2 1 1 1 1
X5 1 3 3 2 2 1 2 1 1 1
X6 4 3 3 3 3 4 3 4 4 3
X7 1 1 2 1 2 1 2 1 1 1
X8 1 1 2 1 2 1 2 1 1 1
X9 1 1 1 1 1 1 1 1 2 1
X10 0.18 0.18 0.18 0.15 0.15 0.15 0.21 0.21 0.21 0.21
Table 7. The actual productivity and the predicted predi-
cated.
No.
observations
Actual
productivity
Predicated
productivity
ABS(A-P)/A
1 35 36.27 0.036405
2 21 25.85 0.231056
3 21 26.88 0.280151
4 28 24.24 0.134245
5 21 27.49 0.309102
6 31.5 33.72 0.070544
7 28 26.6 0.049995
8 35 37.30 0.065806
9 35 36.77 0.05072
10 35 37.21 0.063177
tivity of marble finishing works for floors by suggested
productivity estimation function are closer to the actual
productivity.
12. Accuracy of the Developed Multivariable
Linear Regression Models
The statistical measures used to measure the performance
of the models included [41]:
1) Mean Absolute Percentage Error (MAPE),
1
MAPE 100%
n
i
A E
n
A
  
 
 

2) Average Accuracy Percentage (AA%)
AA% 100% MAPE  (8)
3) The Coefficient of Determination (R2
);
4) The Coefficient of Correlation (R);
Table 8 shows a summary of the developed regression
models in the study, the results of the comparative study
are given in Table 8. The MAPE and Average Accuracy
Percentage generated by MLR model were found to be
(3.74%) and (96.3%) respectively. Therefore, it can be
concluded that the MLR model show very good agree-
ment with the actual measurements.
The comparison between the predicated and measured
the productivity of marble finishing works for floors is
plotted in Figure 1. It is clear from this figure, the ability
of multivariable linear regression technique to predict the
productivity of marble finishing works for floors for any
of data set within the range data used in developing the
multivariable linear regression approach.
The coefficient of determination (R2
) is (82.13%), as
shown in Figure 1, therefore it can be concluded that
ANN models show very good agreement with actual
measurements.
Comparison of Productivity Modeling between
MLR Technique and ANN
Artificial Neural Networks (ANN) are sophisticated
methods that are used to estimation the construction
productivity in the construction sector, and the researcher
using the results of a previous study prepared by Al-
Zwainy et al. 2012, for the purposes of comparison with
the results of this study. The estimation performances of
Table 8. Statistical measures results.
Measures MAPE% AA% R R2
Results 3.74 96.3 0.906 0.821
 (7) Figure 1. Comparison of pred ted and observed productiv-ic
ity.
Copyright © 2013 SciRes. OJCE
F. M. S. AL-ZWAINY ET AL. 133
the two techniques are compared using four measure-
n this research, the followi
developing construction pro-
du
gression (MLR) can be
to
bles used
ve
the technique of Multivari
Table 9. Estimation performances of the MLR and ANN
Productivity of marble finishing works for floors models
able L Regression was acc n ral
REFERENCES
[1] J. Portas and etwork Model for
Estimating Con ,” Journal of Con-
ments as shown in Table 9. The results can be seen that
the MLR technique gives insignificantly better results
than the NN technique in almost all comparisons. The
findings showed that the two models were able to map
the underlying relationship between the independent fac-
tors and the construction productivity during and main-
tained average accuracy percentages of 90.9% and 96.3%
for neural nets and regression respectively. On the other
hand, these results indicate that there is no significant
difference in the average accuracy achieved by the two
techniques. The high levels of accuracy obtained by the
two models can be attributed to the high correlation coef-
ficients between the construction productivity and the
effect factors.
13. Conclusions
From the results presented i ng
conclusions can be made:
1) This study aimed at
ctivity estimating model for marble finishing works of
floors using multiple regression techniques. The model
was developed based on 100 set of data collected in Iraq.
Such types of models are very useful, especially in its
simplicity and ability to be handled by calculator or a
simple computer program.
2) Multivariable Linear Re used
examine several variables at once and the interrela-
tionships between them. And MLR has the ability to pre-
dict the productivity of marble finishing works for floors
with high degree of accuracy with 96.3% and the coeffi-
cients of determination R2
for the developed models
equal to 0.8213. This indicates that the relationship be-
tween the independent and independent variables of the
developed models is good and the predicted values from
a forecast model fit with the real-life data.
3) In this research, ten influential varia de-
loping construction productivity estimating model. Size
marbles have most significant effect on the productivity
of marble finishing works for floors equal to 46.901 as an
unstandardized coefficients. While the other input vari-
ables have moderate impact on the productivity such as
health status of work team.
4) This study showed that
techniques.
Types of model AA% MAPE% R% R %2
ANN 90.9 9.1 89.55 80.19
MLR 96.3 3.743 90.6 82.13
inear more urate tha Neu
Networks, because the degree of accuracy reached 96.3%
for Multivariable Linear Regression, while the degree of
accuracy reached 96.3% for Neural Networks.
S. AbouRizk, “Neural N
struction Productivity
struction Engineering and Management, Vol. 123, No. 4,
1997, pp. 399-410.
doi:10.1061/(ASCE)0733-9364(1997)123:4(399)
[2] D. Arditi, O. B. Tokdemir and K. Suh, “Effect of
ing-of-Balance Scheduling,” International Journal of Pro-
Learn-
ject Management, Vol. 19, No. 5, 2001, pp. 265-277.
doi:10.1016/S0263-7863(99)00079-4
[3] D. G. Proverbs, G. D. Holt and P. O. Olomolaiye, “A
Comparative Evaluation of Planning Engineers’ Form-
work Productivity Rates in European Construction,” Build-
ing and Environment, Vol. 33, No. 4, 1998, pp. 181-187.
doi:10.1016/S0360-1323(97)00035-8
[4] J. Christian and D. Hachey, “Effects of Delay Times on
Production Rates in Construction,” Journal of Construc-
tion Engineering and Management, Vol. 121, No. 1, 1995,
pp. 20-26.
doi:10.1061/(ASCE)0733-9364(1995)121:1(20)
[5] A. Kazaz and S. Ulubeyli, “A Different Approach
struction Labour in Turkey: Comparative Pro
Tocon-
ductivity
Analysis,” Building and Environment, Vol. 39, No. 1,
2004, pp. 93-100. doi:10.1016/j.buildenv.2003.08.004
[6] C. H. Oglesby, H. W. Parker and G. A. Howell, “Produc-
tivity Improvement in Construction,” McGraw-Hill Book
th Neural Networks,” Journal of
Co., New York, 1989.
[7] R. Sonmez and J. E. Rowings, “Construction Labor Pro-
ductivity Modeling wi
Construction Engineering and Management, Vol. 124,
No. 6, 1998, pp. 498-504.
doi:10.1061/(ASCE)0733-9364(1998)124:6(498)
[8] J. C. Kellogg, G. E. Howell and D. C. Taylor, “Hi
Model of Construction Productivity,” Journal of th
erarchy
e Con-
w
uctivity,” Journal of Construction Engi-
struction Division, Vol. 107, No. 1, 1981, pp. 137-152.
[9] Business Roundtable, “Construction Productivity Meas-
urement,” Report No. A-1, Business Roundtable, Ne
York, 1982.
[10] H. R. Thomas and I. Yiakoumis, “Factor Model of Con-
struction Prod
neering and Management, Vol. 113, No. 4, 1987, pp.
626-639.
doi:10.1061/(ASCE)0733-9364(1987)113:4(623)
[11] H. R. Thomas, W. F. Maloney, R. M. W. Horner
Smith, V. K. Handa and S. R. Sanders, “Modelin
, G. R.
g Con-
struction Labor Productivity,” Journal of Construction
Engineering and Management, Vol. 116, No. 4, 1990, pp.
705-726.
doi:10.1061/(ASCE)0733-9364(1990)116:4(705)
[12] J. D. Borcherding, “Improving Productivity in Industrial
Construction,” Journal of the Construction Division, Vol.
102, No. 4, 1976, pp. 599-613.
Copyright © 2013 SciRes. OJCE
F. M. S. AL-ZWAINY ET AL.134
[13] J. D. Borcherding, S. J. Sebastian and N. M. Samelson,
“Improving Motivation and Productivity on Large Pro-
rnal of Construction Engineering and
jects,” Journal of the Construction Division, Vol. 106, No.
1, 1980, pp. 73-89.
[14] W. F. Maloney, “Productivity Improvement: The Influ-
ence of Labor,” Jou
Management, Vol. 109, No. 3, 1983, pp. 321-334.
doi:10.1061/(ASCE)0733-9364(1983)109:3(321)
[15] C. H. Oglesby, H. W. Parker and G. A. Howell, “Pr
tivity Improvement in Construction,” McGraw-Hill,
oduc-
ity,” Journal of the Construction Divi-
ivity—A Case
Inc.,
New York, 1989.
[16] R. D. Logcher and W. C. Collins, “Management Impacts
on Labor Productiv
sion, Vol. 104, No. 4, 1978, pp. 447-461.
[17] H. R. Thomas, V. E. Sanvido and S. R. Sanders, “Impact
of Material Management on Product
Study,” Journal of Construction Engineering and Man-
agement, Vol. 115, No. 3, 1989, pp. 370-384.
doi:10.1061/(ASCE)0733-9364(1989)115:3(370)
[18] C. W. Ibbs and W. E. Allen, “Quantitative I
Project Change,” Source Document 108, Cons
mpa
truction
cts of
Industry Institute, University of Texas at Austin, 1995.
[19] C. W. Ibbs, “Quantitative Impacts of Project Change:
Size Issues,” Journal of Construction Engineering and
Management, Vol. 123, No. 3, 1997, pp. 308-311.
doi:10.1061/(ASCE)0733-9364(1997)123:3(308)
[20] A. S. Hanna, J. S. Russell, T. W. Gotzion and E. V. Nord-
heim, “Impact of Change Orders on Labor Efficiency for
Mechanical Construction,” Journal of Construction En-
gineering and Management, Vol. 125, No. 3, 1999, pp.
176-184.
doi:10.1061/(ASCE)0733-9364(1999)125:3(176)
[21] H. R. Thom
Labor Productivity Due to Delivery Methods an
as, D. R. Riley and V. E. Sanvido, “Loss of
d Wea-
ther,” Journal of Construction Engineering and Man-
agement, Vol. 125, No. 1, 1999, pp. 39-46.
doi:10.1061/(ASCE)0733-9364(1999)125:1(39)
[22] W. Ibbs, “Impact of Change’s Timing on La
tivity,” Journal of Construction Engineering an
bor Produc-
d Man-
agement, Vol. 131, No. 11, 2005, pp. 1219-1229.
doi:10.1061/(ASCE)0733-9364(2005)131:11(1219)
[23] A. S. Hanna, C. K. Chang, J. A. Lackney and K. T.
van, “Impact of Overmanning on Mechanical and S
Sulli-
heet
Metal Labor Productivity,” Journal of Construction En-
gineering and Management, Vol. 133, No. 1, 2007, pp.
22-28. doi:10.1061/(ASCE)0733-9364(2007)133:1(22)
[24] H. R. Thomas, C. T. Mathews and J. G. Ward, “Learning
Curve Models of Construction Productivity,” Journal of
Construction Engineering and Management, Vol. 112,
No. 2, 1986, pp. 245-258.
doi:10.1061/(ASCE)0733-9364(1986)112:2(245)
[25] J. G. Everett and S. Farghal
for Construction Field Operations,” Journal of Construc-
, “Learning Curve Predictors
tion Engineering and Management, Vol. 120, No. 3, 1994,
pp. 603-616.
doi:10.1061/(ASCE)0733-9364(1994)120:3(603)
[26] J. P. Couto and
Learning Curve Effect on Highrise Floor Constru
J. C. Teixeira, “Using Linear Model for
ction,”
Construction Management & Economics, Vol. 23, No. 4,
2005, pp. 355-364. doi:10.1080/01446190500040505
[27] A. M. Jarkas, “Critical Investigation into Applicability of
the Learning Curve Theory to Rebar Fixing Labor Pro-
ductivity,” Journal of Construction Engineering and Ma-
nagement, Vol. 136, No. 12, 2010, pp. 1279-1288.
doi:10.1061/(ASCE)CO.1943-7862.0000236
[28] A. M. Jarkas and M. Horner, “Revisiting the Applic
ity of Learning Curve Theory to Formwork Labour
abil-
Pro-
ductivity,” Construction Management & Economics, Vol.
29, No. 5, 2011, pp. 483-493.
doi:10.1080/01446193.2011.562911
[29] H. R. Thomas and I. Zavrski, “Co
Productivity: Theory and Practice,” Jo
nstruction Baseline
urnal of Construc-
tion Engineering and Management, Vol. 125, No. 5, 1999,
pp. 295-303.
doi:10.1061/(ASCE)0733-9364(1999)125:5(295)
[30] H. R. Thomas and V. E. Sanvido, “Quantification of
Losses Caused by Labor Inefficiencies: Where Is the Elu-
truction Engineering and
sive Measured Mile?” Construction Law and Business,
Vol. 1, No. 3, 2000, pp. 1-14.
[31] W. Ibbs and M. Liu, “Improved Measured Mile Analysis
Technique,” Journal of Cons
Management, Vol. 131, No. 12, 2005, pp. 1249-1256.
doi:10.1061/(ASCE)0733-9364(2005)131:12(1249)
[32] L. D. Nguyen and W. Ibbs, “Case Law and Variations
Cumulative Impact Productivity Claims,” Journal of Con-
in
struction Engineering and Management, Vol. 136, No. 8,
2010, pp. 826-833.
doi:10.1061/(ASCE)CO.1943-7862.0000193
[33] N. Al-Taweel and M. A. Saeed, “Measuring
Times for Labors Productivity for a Number
Standard
of Different
,” Msc. Thesis,
tor in Iraq,” Master
ing Stone
Using
Floors
entists,” 2nd Edition, Macmillan,
es,” Journal of Construction Engineer-
Work Items,” Journal in Engineering and Technology,
Vol. 10, No. 2, 2005, 1991, pp. 249-256.
[34] A. J. Tahar, “Studying Labour Productivity for Some
Working Items in Construction Projects
University of Technology, Iraq, 1995.
[35] A. Abd-allah, “Effect of Wages and Incentives on La-
bours Productivity in Construction Sec
Thesis, University of Technology, Iraq, 1999.
[36] F. M. S. Al-Zwainy, “The Use of Artificial Neural Net-
works for Productivity Estimation of finish
Works for Building Projects,” Journal of Engineering
and Development, Vol. 16, No. 2, 2012, pp. 42-60.
http://www.iasj.net/iasj?func=fulltext&aId=68252
[37] F. M. S. Al-Zwainy, A. R. Hatem and F. I. Huda, “
Artificial Neural Network for Finishing Works for
with Marble,” ARPN Journal of Engineering and Applied
Sciences, Vol. 7, No. 6, 2012, pp. 714-722.
http://www.arpnjournals.com/jeas/research_papers/rp_20
12/jeas_0612_714.pdf
[38] R. V. Hogg and J. Ledolter, “Applied Statistics for Engi-
neers and Physical Sci
New York, 1992.
[39] S. D. Smith, “Earthmoving Productivity Using Linear Re-
gression Techniqu
ing and Management, Vol. 125, No. 3, 1999, pp. 133-141.
doi:10.1061/(ASCE)0733-9364(1999)125:3(133)
Copyright © 2013 SciRes. OJCE
F. M. S. AL-ZWAINY ET AL.
Copyright © 2013 SciRes. OJCE
135
,” Jour-
[40] A. Makulsawatudom and M. Emsley, “Critical Factors
Influencing Construction Productivity in Thailand
nal of KMITNB, Vol. 14, No. 3, 2004, pp. 1-6.
[41] B. N. Gupta, “An Introduction to Modern Statistics,”
Indian Institution of Public Administration, New Delhi,
1973.

More Related Content

What's hot

Effect of project cost and time monitoring on
Effect of project cost and time monitoring onEffect of project cost and time monitoring on
Effect of project cost and time monitoring oneSAT Publishing House
 
Effect of project cost and time monitoring on progress of construction projct
Effect of project cost and time monitoring on progress of construction projctEffect of project cost and time monitoring on progress of construction projct
Effect of project cost and time monitoring on progress of construction projcteSAT Journals
 
Diagnose the causes of cost deviation in highway construction
Diagnose the causes of cost deviation in highway constructionDiagnose the causes of cost deviation in highway construction
Diagnose the causes of cost deviation in highway constructionFaiq M. S. Al-Zwainy
 
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...IRJET Journal
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET Journal
 
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...IRJET Journal
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET Journal
 
EFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTION
EFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTIONEFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTION
EFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTIONIAEME Publication
 
Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...IJLT EMAS
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET Journal
 
Manufacturing Process Simulation Based Geometrical Design for Complicated Parts
Manufacturing Process Simulation Based Geometrical Design for Complicated PartsManufacturing Process Simulation Based Geometrical Design for Complicated Parts
Manufacturing Process Simulation Based Geometrical Design for Complicated PartsLiu PeiLing
 
A Review on Productivity Improvement in Construction Industry
A Review on Productivity Improvement in Construction IndustryA Review on Productivity Improvement in Construction Industry
A Review on Productivity Improvement in Construction IndustryIRJET Journal
 
BIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building ConstructionBIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building ConstructionIJERA Editor
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET Journal
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...IAEME Publication
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementIAEME Publication
 
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...IJSRED
 

What's hot (20)

A9 r30d0
A9 r30d0A9 r30d0
A9 r30d0
 
Effect of project cost and time monitoring on
Effect of project cost and time monitoring onEffect of project cost and time monitoring on
Effect of project cost and time monitoring on
 
Effect of project cost and time monitoring on progress of construction projct
Effect of project cost and time monitoring on progress of construction projctEffect of project cost and time monitoring on progress of construction projct
Effect of project cost and time monitoring on progress of construction projct
 
Design and Development of Stamping Bracket of Snowmobile Using Computer Aided...
Design and Development of Stamping Bracket of Snowmobile Using Computer Aided...Design and Development of Stamping Bracket of Snowmobile Using Computer Aided...
Design and Development of Stamping Bracket of Snowmobile Using Computer Aided...
 
Diagnose the causes of cost deviation in highway construction
Diagnose the causes of cost deviation in highway constructionDiagnose the causes of cost deviation in highway construction
Diagnose the causes of cost deviation in highway construction
 
Tp96 pub102
Tp96 pub102Tp96 pub102
Tp96 pub102
 
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
 
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
 
EFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTION
EFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTIONEFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTION
EFFICIENT COST MANAGEMENT OF MATERIALS IN CONVENTIONAL AND PRECAST CONSTRUCTION
 
Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
Manufacturing Process Simulation Based Geometrical Design for Complicated Parts
Manufacturing Process Simulation Based Geometrical Design for Complicated PartsManufacturing Process Simulation Based Geometrical Design for Complicated Parts
Manufacturing Process Simulation Based Geometrical Design for Complicated Parts
 
A Review on Productivity Improvement in Construction Industry
A Review on Productivity Improvement in Construction IndustryA Review on Productivity Improvement in Construction Industry
A Review on Productivity Improvement in Construction Industry
 
BIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building ConstructionBIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building Construction
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurement
 
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
 

Similar to Using multivariable linear regression technique

Study of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A ReviewStudy of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A ReviewIRJET Journal
 
A systematic mapping study of performance analysis and modelling of cloud sys...
A systematic mapping study of performance analysis and modelling of cloud sys...A systematic mapping study of performance analysis and modelling of cloud sys...
A systematic mapping study of performance analysis and modelling of cloud sys...IJECEIAES
 
AN ARTIFICIAL NEURAL NETWORK-BASED APPROACH COUPLED WITH TAGUCHI'S METHOD FOR...
AN ARTIFICIAL NEURAL NETWORK-BASED APPROACH COUPLED WITH TAGUCHI'S METHOD FOR...AN ARTIFICIAL NEURAL NETWORK-BASED APPROACH COUPLED WITH TAGUCHI'S METHOD FOR...
AN ARTIFICIAL NEURAL NETWORK-BASED APPROACH COUPLED WITH TAGUCHI'S METHOD FOR...IAEME Publication
 
PREDICTION OF AVERAGE TOTAL PROJECT DURATION USING ARTIFICIAL NEURAL NETWORKS...
PREDICTION OF AVERAGE TOTAL PROJECT DURATION USING ARTIFICIAL NEURAL NETWORKS...PREDICTION OF AVERAGE TOTAL PROJECT DURATION USING ARTIFICIAL NEURAL NETWORKS...
PREDICTION OF AVERAGE TOTAL PROJECT DURATION USING ARTIFICIAL NEURAL NETWORKS...IAEME Publication
 
Application of ANFIS in Civil Engineering- A Critical Review
Application of ANFIS in Civil Engineering- A Critical ReviewApplication of ANFIS in Civil Engineering- A Critical Review
Application of ANFIS in Civil Engineering- A Critical ReviewIRJET Journal
 
IRJET- Development of a Neural Network based Model for Construction Proje...
IRJET-  	  Development of a Neural Network based Model for Construction Proje...IRJET-  	  Development of a Neural Network based Model for Construction Proje...
IRJET- Development of a Neural Network based Model for Construction Proje...IRJET Journal
 
IRJET- Improvement of Labour Productivity in Construction Industry- Review
IRJET- Improvement of Labour Productivity in Construction Industry- ReviewIRJET- Improvement of Labour Productivity in Construction Industry- Review
IRJET- Improvement of Labour Productivity in Construction Industry- ReviewIRJET Journal
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsIRJET Journal
 
Modeling final costs of iraqi public school projects
Modeling final costs of iraqi public school projectsModeling final costs of iraqi public school projects
Modeling final costs of iraqi public school projectsGafel Kareem
 
Optimization of Assembly Line and Plant Layout in a Mass Production Industry...
	Optimization of Assembly Line and Plant Layout in a Mass Production Industry...	Optimization of Assembly Line and Plant Layout in a Mass Production Industry...
Optimization of Assembly Line and Plant Layout in a Mass Production Industry...inventionjournals
 
Optimizing Facility Layout Through Simulation
Optimizing Facility Layout Through SimulationOptimizing Facility Layout Through Simulation
Optimizing Facility Layout Through SimulationIRJET Journal
 
IRJET- Integrated Optimization of Multi-Period Supply Chains and Commonality ...
IRJET- Integrated Optimization of Multi-Period Supply Chains and Commonality ...IRJET- Integrated Optimization of Multi-Period Supply Chains and Commonality ...
IRJET- Integrated Optimization of Multi-Period Supply Chains and Commonality ...IRJET Journal
 
A value added predictive defect type distribution model
A value added predictive defect type distribution modelA value added predictive defect type distribution model
A value added predictive defect type distribution modelUmeshchandraYadav5
 
IRJET- Productivity Improvement in Construction Industry using Automation Tec...
IRJET- Productivity Improvement in Construction Industry using Automation Tec...IRJET- Productivity Improvement in Construction Industry using Automation Tec...
IRJET- Productivity Improvement in Construction Industry using Automation Tec...IRJET Journal
 
Opportunities and Challenges of Modular Coordination: A Review
Opportunities and Challenges of Modular Coordination: A ReviewOpportunities and Challenges of Modular Coordination: A Review
Opportunities and Challenges of Modular Coordination: A ReviewIRJET Journal
 

Similar to Using multivariable linear regression technique (20)

Study of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A ReviewStudy of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A Review
 
A systematic mapping study of performance analysis and modelling of cloud sys...
A systematic mapping study of performance analysis and modelling of cloud sys...A systematic mapping study of performance analysis and modelling of cloud sys...
A systematic mapping study of performance analysis and modelling of cloud sys...
 
AN ARTIFICIAL NEURAL NETWORK-BASED APPROACH COUPLED WITH TAGUCHI'S METHOD FOR...
AN ARTIFICIAL NEURAL NETWORK-BASED APPROACH COUPLED WITH TAGUCHI'S METHOD FOR...AN ARTIFICIAL NEURAL NETWORK-BASED APPROACH COUPLED WITH TAGUCHI'S METHOD FOR...
AN ARTIFICIAL NEURAL NETWORK-BASED APPROACH COUPLED WITH TAGUCHI'S METHOD FOR...
 
PREDICTION OF AVERAGE TOTAL PROJECT DURATION USING ARTIFICIAL NEURAL NETWORKS...
PREDICTION OF AVERAGE TOTAL PROJECT DURATION USING ARTIFICIAL NEURAL NETWORKS...PREDICTION OF AVERAGE TOTAL PROJECT DURATION USING ARTIFICIAL NEURAL NETWORKS...
PREDICTION OF AVERAGE TOTAL PROJECT DURATION USING ARTIFICIAL NEURAL NETWORKS...
 
Application of ANFIS in Civil Engineering- A Critical Review
Application of ANFIS in Civil Engineering- A Critical ReviewApplication of ANFIS in Civil Engineering- A Critical Review
Application of ANFIS in Civil Engineering- A Critical Review
 
IRJET- Development of a Neural Network based Model for Construction Proje...
IRJET-  	  Development of a Neural Network based Model for Construction Proje...IRJET-  	  Development of a Neural Network based Model for Construction Proje...
IRJET- Development of a Neural Network based Model for Construction Proje...
 
IRJET- Improvement of Labour Productivity in Construction Industry- Review
IRJET- Improvement of Labour Productivity in Construction Industry- ReviewIRJET- Improvement of Labour Productivity in Construction Industry- Review
IRJET- Improvement of Labour Productivity in Construction Industry- Review
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
Modeling final costs of iraqi public school projects
Modeling final costs of iraqi public school projectsModeling final costs of iraqi public school projects
Modeling final costs of iraqi public school projects
 
20320140507006
2032014050700620320140507006
20320140507006
 
20320140507006 2-3
20320140507006 2-320320140507006 2-3
20320140507006 2-3
 
Optimization of Assembly Line and Plant Layout in a Mass Production Industry...
	Optimization of Assembly Line and Plant Layout in a Mass Production Industry...	Optimization of Assembly Line and Plant Layout in a Mass Production Industry...
Optimization of Assembly Line and Plant Layout in a Mass Production Industry...
 
Optimizing Facility Layout Through Simulation
Optimizing Facility Layout Through SimulationOptimizing Facility Layout Through Simulation
Optimizing Facility Layout Through Simulation
 
IRJET- Integrated Optimization of Multi-Period Supply Chains and Commonality ...
IRJET- Integrated Optimization of Multi-Period Supply Chains and Commonality ...IRJET- Integrated Optimization of Multi-Period Supply Chains and Commonality ...
IRJET- Integrated Optimization of Multi-Period Supply Chains and Commonality ...
 
A value added predictive defect type distribution model
A value added predictive defect type distribution modelA value added predictive defect type distribution model
A value added predictive defect type distribution model
 
4213ijsea01 (1)
4213ijsea01 (1)4213ijsea01 (1)
4213ijsea01 (1)
 
IRJET- Productivity Improvement in Construction Industry using Automation Tec...
IRJET- Productivity Improvement in Construction Industry using Automation Tec...IRJET- Productivity Improvement in Construction Industry using Automation Tec...
IRJET- Productivity Improvement in Construction Industry using Automation Tec...
 
50120130405029
5012013040502950120130405029
50120130405029
 
Opportunities and Challenges of Modular Coordination: A Review
Opportunities and Challenges of Modular Coordination: A ReviewOpportunities and Challenges of Modular Coordination: A Review
Opportunities and Challenges of Modular Coordination: A Review
 
Ijmet 10 01_022
Ijmet 10 01_022Ijmet 10 01_022
Ijmet 10 01_022
 

Recently uploaded

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 

Recently uploaded (20)

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 

Using multivariable linear regression technique

  • 1. Open Journal of Civil Engineering, 2013, 3, 127-135 http://dx.doi.org/10.4236/ojce.2013.33015 Published Online September 2013 (http://www.scirp.org/journal/ojce) Using Multivariable Linear Regression Technique for Modeling Productivity Construction in Iraq Faiq Mohammed Sarhan Al-Zwainy1 , Mohammed Hashim Abdulmajeed2 , Hadi Salih Mijwel Aljumaily3 1 Department of Civil Engineering, College of Engineering, Al-Nahrain University, Baghdad, Iraq 2 Ministry Industry and Minerals, State Industrial Design and Consultation Company (Sidcco), Baghdad, Iraq 3 Department of Environmental Engineering, College of Engineering, Al-Mustansiriya University, Baghdad, Iraq Email: FAIQ_FAIQMOHMED@yahoo.com Received June 2, 2013; revised July 2, 2013; accepted July 9, 2013 Copyright © 2013 Faiq Mohammed Sarhan Al-Zwainy et al. This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. ABSTRACT Productivity is a very important element in the process of construction project management especially with regard to the estimation of the duration of the construction activities, this study aims at developing construction productivity estimat- ing model for marble finishing works of floors using Multivariable Linear Regression technique (MLR). The model was developed based on 100 set of data collected in Iraq for different types of projects such as residential, commercial and educational projects. Which these are used in developing the model and evaluating its performance. Ten influencing factors are utilized for productivity forecasting by MLR model, and they include age, experience, number of the assist labor, height of the floor, size of the marbles tiles, security conditions, health status for the work team, weather condi- tions, site condition, and availability of construction materials. One model was built for the prediction of the productiv- ity of marble finishing works for floors. It was found that MLR have the ability to predict the productivity for finishing works with excellent degree of accuracy of the coefficient of correlation (R) 90.6%, and average accuracy percentage of 96.3%. This indicates that the relationship between the independent and independent variables of the developed models is good and the predicted values from a forecast model fit with the real-life data. Keywords: Multivariable Linear Regression Techniques; Construction Productivity; Finishing Work; Coefficient of Correlation 1. Introduction Productivity rates of construction trades are the basis for accurately estimating time and costs required to complete a project. Productivity could be defined as “the ratio of output of required quality to the inputs” for a specific pro- duction situation; in the construction industry, it is gen- erally accepted as “work output per man-hours worked”. Improved productivity helps contractors not only to be more efficient and profitable; knowing actual productiv- ity levels also helps them to estimate accurately and be more competitive during bidding for projects. In response to the industry needs, the primary goal of this research was to conduct an accurate measurement of on-site construction productivity in Iraq through devel- oping regression models for predicting the productivity of finishing works for floors with marble. The structure of research is consisting of Research justifications, Re- search hypothesis, Research methodology, Literature re- view, Factors affecting construction productivity, field data collection, regression models for productivity, vali- dation of models, Conclusion, recommendations and fu- ture research. It is widely accepted that productivity measurement plays an important role in the construction management process. Productivity measurement provides the neces- sary data to analyze factors for project owners, construc- tors, and management professionals to control construc- tion progress, estimate the cost of future construction projects, and determine its competitiveness in the global market. In achieving these objectives, the researcher hoped that it could help the Iraq construction firms stay competitive and profitable in the global markets. 2. Research Justifications The reasons that stand behind the adoption of this study work are: Copyright © 2013 SciRes. OJCE
  • 2. F. M. S. AL-ZWAINY ET AL.128 1) There are different techniques currently used for construction productivity estimation at different stages of the project development process. Some of these methods suffer the major disadvantages of lack of precision, aged, slow and uncertainty. 2) Construction sector in Iraq needing for modern effi- cient construction productivity estimation techniques that have more advantages such as, being modern, fast, accu- rate, flexible and easy to use is of value. 3. The Research Hypothesis The research hypothesis is formulated as “Multivariable Linear Regression (MLR) has strong modeling technique with optimization mechanism and effective recognition capabilities to estimate the production rates under any specific condition”. 4. Research Methodology The research objectives were achieved by using the fol- lowing steps: 1) Literature review: A comprehensive literature re- view was conducted to provide the previous research studies related to the construction productivity and to understand the current Iraq construction industry. The review synthesized the findings from previous literature in textbooks, journal papers, research reports, conference proceedings, theses, dissertations, and Internet publica- tions, and methods of productivity data analyses. The review enabled the researcher to better understand the current status of the field research and to perform studies in both accuracy and practicability; 2) Data collection: The researcher conducted on-site construction productivity measurements in the Iraq. The data were collected from observation and recompiled to a spreadsheet format that is suitable for statistical data analysis by using computer software, such as Statistical Package for the Social Sciences (SPSS); 3) Data analysis and comparison: The data analysis were conducted by using the statistical software package, SPSS 19.0, for determining the productivity rate charac- teristics, and labor productivity. Various statistical analy- sis methods, including descriptive statistics, correlation, and nonparametric tests, were also used for modeling throughout the research; 4) Developed Model: Based on the data analyses’ re- sults, it will provide Multiple Linear Regression model to predicting productivity of marble finishing works for floors and discuses the results from training and testing this model; 5) Validation Model: This stage, which presented the validation of the MLR model; 6) Conclusions, recommendations and future research: Based on the results of the data analyses developed model and validation model, conclusions and recom- mendations were provided for this research. The conclu- sions included the characteristics of the labor productiv- ity, production effectiveness. In addition, corrective ac- tions and future research were recommended for other researchers who are interested in further research on this topic. 5. Available Productivity Estimation Techniques Labor productivity estimates are often performed by in- dividuals using combinations of analytical techniques and personal judgment [1]; namely, the worker hour es- timates are usually obtained through direct interaction with a scheduler, the site manager or related sub-con- tractors who are knowledgeable enough to reflect the actual conditions of a project and its constituent activities [2]. These individuals often have a library of basic pro- ductivity rates which are adjusted and recalculated for each project [3], and always modify their productivity rates for each specific estimate [4]. On the other hand, differences in these productivity rates are always likely and normal [5]. A number of techniques for motion and time study such as time-lapse photography and video can be used along with statistics for analyzing and estimating con- struction-operation productivity [6]. Mathematical mod- els and discrete event simulation techniques can also be applied. This paper presents an alternative approach that utilizes the adaptively of multivariable linear regression to perform the complex mapping from environment and management conditions to operation productivity. One of the most importance techniques is statistic- based called the multivariable linear regression. It at- tempts to map the relationships between the influential factors and the productivity with the explicit mathemati- cal functions. The mapping functions are initially pre- sumed and later evaluated. They could be linear func- tions (multivariable linear regression) or non-linear func- tions (multivariable non-linear regression). However, the statistical technique could oversimplify the relationships comparing with the neural network technique [7]. 6. Previous Studies on the Construction Productivity Extensive research has been undertaken in construction labor productivity in the past 35 years. These research works can be grouped in, but be not limited to, the fol- lowing topics: 1) productivity models and measurement ([8-11]); 2) productivity improvement ([12-15]); 3) fac- tors affecting labor productivity ([16-23]); 4) learning curve theory and application ([24-28]); and 5) productiv- ity analysis for cumulative impact claims ([29-32]). Copyright © 2013 SciRes. OJCE
  • 3. F. M. S. AL-ZWAINY ET AL. 129 In Iraqi construction sector, a few studies concerned with the subject of productivity construction. Al-Taweel and Saeed [33] measured the averages and standard per- formance times for work and labors productivity in some construction work items through site studying by using work study. Tahar [34] measured the standard productiv- ity for the employers for some construction work items by using the questionnaires styles distributed to different levels of management. The researcher can immobiliza- tion the productivity for (600) items for different works items in construction work. Abd-allah [35] studied a group of parameters which affect the application of in- centive schemes in the construction companies in Iraq. The effect of these parameters on productivity was stud- ied through the preparation of three questionnaire sets distributed to different levels of management. Al-Zwainy [36] used Back-propagation Feed-forward neural net- works for productivity estimation of the finishing works with stone tiles for building project. In this study, the researcher will be comparing the re- sults of the two different methods to estimate productiv- ity of marble finishing works for floors; these two meth- ods are regression analysis and neural networks. For the subject of estimation construction productivity by neural networks has been completed as an independent research and published in the ARPN Journal of Engineering and Applied Sciences, by the same researcher [37]. In this research will be to predict construction productivity for the same work item using multiple linear regressions and then a comparison between the two methods for the pur- pose of determining the most accurate method. 7. Regression Analysis Regression analysis is an extremely powerful tool that enables the researcher to learn more about the relation- ships within the data being studied. There are many texts that describe this technique, and the theory behind its use will not be discussed in detail here. The Simon [38] has found the text by Hogg and Ledolter [39] to be particu- larly useful. In this instance multiple linear regression will be used to determine the statistical relationship between a re- sponse (e.g., actual productivity) and the explanatory variables (e.g., experience, age). The regression model requires a few assumptions. It is of the form 0 1 1 2 2iY X X Xp ip i          (1) where: 1,2, ,I n  ; Yi is the response that corresponds to the levels of the explanatory variables 1 2, , , pX X X at the ith observa- tion.  0 1, , , p   are the coefficients in the linear rela- tionship. For a single factor (p = 1), 0 is the inter- cept, and 1 is the slope of the straight line defined.  1 2, , , n   are errors that create scatter around the linear relationship at each of the i = 1 to n observa- tions. The regression model assumes that these errors are mutually independent, normally distributed, and with a zero mean and variance σ2 . It is important to rate that this sometimes difficult to achieve [38]. To make estimates of the coefficients in the regression model, the method of least squares is used for both its mathematical convenience and its ability to provide ex- plicit expressions for these estimates. 8. Factors Affecting Construction Productivity Identification and evaluation of factors affecting labour construction productivity have become a critical issue facing project managers for a long time in order to in- crease productivity in construction. Understanding criti- cal factors affecting productivity of both positive and negative can be used to prepare a strategy to reduce inef- ficiencies and to improve the effectiveness of project performance. Knowledge and understanding of the vari- ous factors affecting construction labour productivity is needed to determine the focus of the necessary steps in an effort to reduce project cost overrun and project com- pletion delay, thereby increasing productivity and overall project performance. Based on the study and survey, al- though many researchers have been done and produce the factors that affect productivity, there are still many productivity problems that remain unknown and need to be further investigated even in developed countries [40]. In addition, policies for increasing productivity are not necessarily the same in every country. And the critical factors in developing countries differ from that in devel- oping countries. The methodology used in this research to determine the factors affecting the productivity of finishing flooring with marble, involves; Literature survey and Preliminary interviews. The researcher conducted a number of personal inter- views with five (60) engineers who have extensive ex- perience in managing construction projects in Iraq. Some of these engineers work as a project manager, estimators, planners and site engineers, and they working with dif- ferent companies at the Ministry of Construction and Housing Iraqi. And all these engineers with experience not less than twenty years in the field of specialization. Relying on personal interviews and the literature re- view, the researcher was able to identify the factors af- fecting the construction productivity. Ten independent variables were carefully selected and were well defined for each construction project. These independent vari- ables can be classified into two types: objective and sub- jective variables as shown in Tables 1 and 2, respec- Copyright © 2013 SciRes. OJCE
  • 4. F. M. S. AL-ZWAINY ET AL.130 tively below. The quantitative (objective) variables that can be mea- sured, depending on the unit of measurement, such as age is measured in years, experience is measured in years and floor height is measured in meters. The qualitative (subjective) variables can be measured depending on the coding system, for example, the secu- rity conditions can be classifies to security and non-secu- rity and assigns them the value 1 and 2, respectively. Also the health status for work team which specifies as good, moderate and bad, it assigns them the values of 1, 2 and 3, respectively. While the weather condition; sunny (1), rainy (2). The site conditions can be classifies to complex and simple and assigns them the value 1 and 2, respectively. Where as the scale of 1 and 2 represent near and far, respectively about availability of construction materials. 9. Data Collection Researcher has identified that suitable method of data collection influenced the accuracy of the production rates values. However questionnaire survey is the most com- monly data collection method adopted by the researcher to collect information on factors and production There- fore, direct observation method has been selected for collecting the data in this research. Pilot study has been done by selecting ten construction projects in different parts of Iraq. Work sampling approach has been used to measure the production rates at site to calculate duration of activity on daily basis at specific time interval using stop watch. Researcher has been able to get fifteen (15) number of observation from each of ten (10) projects at Table 1. The objective variables. Objective variables Description Units X1 Age Year X2 Experience Year X3 Number of the labor Number X4 Height of the floor Length (meter) X5 Size of the marbles tiles Area Table 2. The subjective variables. Subjective variables Description Units X6 The security conditions Category X7 The health status for the work team Category X8 Weather conditions Category X9 Site condition Category X10 Availability of construction materials Category different intervals. Among ten projects five residential, commercial and educational projects are from Baghdad, four residential projects is from Arbil and one commer- cial project is from Babylon as shown in Table 3. There- fore total one hundred and fifty (150) number of data samples has been gathered. 10. Development of Multivariable Linear Regression Model Several functions can be used for studying the relation- ships among the variables of a given data which were stated previously at previous section. Multivariable Lin- ear Regression (MLR) is adopted in the research since the MLR is the most widely used type and using the pro- ject characteristics (parameters) in a mathematical model to predict construction productivity. The Statistical Product and Solutions Services (SPSS) software; Vertion. 19 is used to develop the model, and the results of the statistical analysis are shown in Table 4 and Table 5 below. The correlation among input variables is tested; the results are shown in Table 4. The results of r (coefficient of correlation) and r2 (coefficient of determination) show that there is a high correlation between construction pro- ductivity and other input variables. This indicates a good relationship between dependent and independent vari- ables. Table 3. Construction project visited for measuring labor productivity rates. Project No. Location Sample data Type of project Prj.1 Baghdad City 15 residential project Prj.2 Baghdad City 15 residential projects Prj.3 Baghdad City 15 educational projects Prj.4 Baghdad City 15 educational projects Prj.5 Baghdad City 15 commercial project Prj.6 Erbil City 15 residential projects Prj.7 Erbil City 15 residential projects Prj.8 Erbil City 15 residential projects Prj.9 Erbil City 15 residential projects Prj.10 Babylon City 15 commercial project Table 4. Model Summary. Model R R square Adjusted R square Std. error of the estimate 1 0.906a 0.821 0.801 2.45965 a Predictors: (Constant), area, material, site, age, security, weather, labour, height, experiences, health. Copyright © 2013 SciRes. OJCE
  • 5. F. M. S. AL-ZWAINY ET AL. 131 Table 5. Uonstandard coefficients of variables. Unstandardized coefficients Model B Std. error (Constant) 39.233 5.201 age 0.038 0.044 experiences −0.056 0.052 health status of work team −8.026 1.371 Weather condition −1.447 0.818 Height of the floor −1.523 0.801 No. of labour −0.560 0.552 Security conditions 0.489 1.860 Site condition 0.822 0.577 Material available −0.066 0.674 1 Size marble 46.901 13.585 The values above indicate that at least one of the model coefficients is nonzero. The model appears to be useful for predicting the construction productivity. This model included all the potential independent variables that have been identified. The model obtained is: 39 233 0 038 1 0 056 2 0 560 3 1 523 4 46 901 5 0 489 6 8 026 7 1 447 8 0 822 9 0 066 10 P . . X . X . X . X . X . X . X . X . X . X            (2) where: P: productivity of marble finishing works for floors as output (dependent) variable; X1, X2, X3, X4, X5, X6, X7, X8, X9, X10: Input (inde- pendent) variables are shown in Tables 1 and 2. 11. Validation Model There are several basic ways of validating a regression model. They are: 1) Statistical test on “r” value. 2) Collection of new data to check the model and its predictive ability for comparison of results with the ac- tual productivity of marble finishing works for floors and the predicted productivity values 11.1 Statistical Test on “R” Value The following statistical tests were conducted on “R” (the coefficient of correlation) value for model 1, where R2 = 0.821, N = 100: 1) Probable Error (P.E.) in “R” value  2 1 0 6745 R P.E. . N        P.E. = 0.01207355 therefore, R = 0.906 ± 0.01207355. According to Gupta [41]; the probable error is re- garded as a measure of significance of Karl Person’s co- efficient of correlation (R), and if the probable error is small (compared with R), correlation directly exists where R > 0.5. Hence, the correlation of the studied productivity equation is existing. 2) Standard Error (S.E.) in “R” value 2 1 R S.E. N        (4) S.E. = 0.1906. Hence, the correlation is accepted for R = 0.906, and 100 observations. 3) Test of significance Gupta [41]; indicates that the correlation may be ac- cepted when R > 0.22 (for 100 observations). Again, the correlation is accepted for R = 0.906, and 100 observations. 4) A simple method of testing whether “R” differs sig- nificantly from “zero” Taking null hypothesis that there is no correlation be- tween the two variables, provided “N” is large: 3 N (5) IF the value arrived at by this test is greater than the observed or computed value of correlation coefficient (R < 3 N ) correlation is not significant [41]; 3 3 0 3 0 906 100 . . N    (6) Hence, coefficient of correlation can be taken as sig- nificant. 11.2. Collection of New Data to Check the Model and Its Predictive Ability In this research, the second method is employed also. Ten new observations for each concerning variables were collected as shown in Table 6. These observations which were not included in the model calibration procedures were used as independent verification check. While the actual productivity of marble finishing works for floors and the predicted values are presented in Table 7. Table 7 shows that the predicted productivity (by sug- gested productivity estimation function) predicts an av- erage difference of 1.291% of the actual productivity. and the correlation coefficient between them equal to 0.862. also the analyzed results indicates that the produc-  (3) Copyright © 2013 SciRes. OJCE
  • 6. F. M. S. AL-ZWAINY ET AL.132 Table 6. Number of observations for each variable. No. observations Variables 1 2 3 4 5 6 7 8 9 10 X1 45 40 40 40 50 50 35 38 45 40 X2 20 15 20 20 18 18 15 22 35 35 X3 1 2 2 2 2 1 2 1 1 1 X4 1 1 1 2 1 2 1 1 1 1 X5 1 3 3 2 2 1 2 1 1 1 X6 4 3 3 3 3 4 3 4 4 3 X7 1 1 2 1 2 1 2 1 1 1 X8 1 1 2 1 2 1 2 1 1 1 X9 1 1 1 1 1 1 1 1 2 1 X10 0.18 0.18 0.18 0.15 0.15 0.15 0.21 0.21 0.21 0.21 Table 7. The actual productivity and the predicted predi- cated. No. observations Actual productivity Predicated productivity ABS(A-P)/A 1 35 36.27 0.036405 2 21 25.85 0.231056 3 21 26.88 0.280151 4 28 24.24 0.134245 5 21 27.49 0.309102 6 31.5 33.72 0.070544 7 28 26.6 0.049995 8 35 37.30 0.065806 9 35 36.77 0.05072 10 35 37.21 0.063177 tivity of marble finishing works for floors by suggested productivity estimation function are closer to the actual productivity. 12. Accuracy of the Developed Multivariable Linear Regression Models The statistical measures used to measure the performance of the models included [41]: 1) Mean Absolute Percentage Error (MAPE), 1 MAPE 100% n i A E n A         2) Average Accuracy Percentage (AA%) AA% 100% MAPE  (8) 3) The Coefficient of Determination (R2 ); 4) The Coefficient of Correlation (R); Table 8 shows a summary of the developed regression models in the study, the results of the comparative study are given in Table 8. The MAPE and Average Accuracy Percentage generated by MLR model were found to be (3.74%) and (96.3%) respectively. Therefore, it can be concluded that the MLR model show very good agree- ment with the actual measurements. The comparison between the predicated and measured the productivity of marble finishing works for floors is plotted in Figure 1. It is clear from this figure, the ability of multivariable linear regression technique to predict the productivity of marble finishing works for floors for any of data set within the range data used in developing the multivariable linear regression approach. The coefficient of determination (R2 ) is (82.13%), as shown in Figure 1, therefore it can be concluded that ANN models show very good agreement with actual measurements. Comparison of Productivity Modeling between MLR Technique and ANN Artificial Neural Networks (ANN) are sophisticated methods that are used to estimation the construction productivity in the construction sector, and the researcher using the results of a previous study prepared by Al- Zwainy et al. 2012, for the purposes of comparison with the results of this study. The estimation performances of Table 8. Statistical measures results. Measures MAPE% AA% R R2 Results 3.74 96.3 0.906 0.821  (7) Figure 1. Comparison of pred ted and observed productiv-ic ity. Copyright © 2013 SciRes. OJCE
  • 7. F. M. S. AL-ZWAINY ET AL. 133 the two techniques are compared using four measure- n this research, the followi developing construction pro- du gression (MLR) can be to bles used ve the technique of Multivari Table 9. Estimation performances of the MLR and ANN Productivity of marble finishing works for floors models able L Regression was acc n ral REFERENCES [1] J. Portas and etwork Model for Estimating Con ,” Journal of Con- ments as shown in Table 9. The results can be seen that the MLR technique gives insignificantly better results than the NN technique in almost all comparisons. The findings showed that the two models were able to map the underlying relationship between the independent fac- tors and the construction productivity during and main- tained average accuracy percentages of 90.9% and 96.3% for neural nets and regression respectively. On the other hand, these results indicate that there is no significant difference in the average accuracy achieved by the two techniques. The high levels of accuracy obtained by the two models can be attributed to the high correlation coef- ficients between the construction productivity and the effect factors. 13. Conclusions From the results presented i ng conclusions can be made: 1) This study aimed at ctivity estimating model for marble finishing works of floors using multiple regression techniques. The model was developed based on 100 set of data collected in Iraq. Such types of models are very useful, especially in its simplicity and ability to be handled by calculator or a simple computer program. 2) Multivariable Linear Re used examine several variables at once and the interrela- tionships between them. And MLR has the ability to pre- dict the productivity of marble finishing works for floors with high degree of accuracy with 96.3% and the coeffi- cients of determination R2 for the developed models equal to 0.8213. This indicates that the relationship be- tween the independent and independent variables of the developed models is good and the predicted values from a forecast model fit with the real-life data. 3) In this research, ten influential varia de- loping construction productivity estimating model. Size marbles have most significant effect on the productivity of marble finishing works for floors equal to 46.901 as an unstandardized coefficients. While the other input vari- ables have moderate impact on the productivity such as health status of work team. 4) This study showed that techniques. Types of model AA% MAPE% R% R %2 ANN 90.9 9.1 89.55 80.19 MLR 96.3 3.743 90.6 82.13 inear more urate tha Neu Networks, because the degree of accuracy reached 96.3% for Multivariable Linear Regression, while the degree of accuracy reached 96.3% for Neural Networks. S. AbouRizk, “Neural N struction Productivity struction Engineering and Management, Vol. 123, No. 4, 1997, pp. 399-410. doi:10.1061/(ASCE)0733-9364(1997)123:4(399) [2] D. Arditi, O. B. Tokdemir and K. Suh, “Effect of ing-of-Balance Scheduling,” International Journal of Pro- Learn- ject Management, Vol. 19, No. 5, 2001, pp. 265-277. doi:10.1016/S0263-7863(99)00079-4 [3] D. G. Proverbs, G. D. Holt and P. O. Olomolaiye, “A Comparative Evaluation of Planning Engineers’ Form- work Productivity Rates in European Construction,” Build- ing and Environment, Vol. 33, No. 4, 1998, pp. 181-187. doi:10.1016/S0360-1323(97)00035-8 [4] J. Christian and D. Hachey, “Effects of Delay Times on Production Rates in Construction,” Journal of Construc- tion Engineering and Management, Vol. 121, No. 1, 1995, pp. 20-26. doi:10.1061/(ASCE)0733-9364(1995)121:1(20) [5] A. Kazaz and S. Ulubeyli, “A Different Approach struction Labour in Turkey: Comparative Pro Tocon- ductivity Analysis,” Building and Environment, Vol. 39, No. 1, 2004, pp. 93-100. doi:10.1016/j.buildenv.2003.08.004 [6] C. H. Oglesby, H. W. Parker and G. A. Howell, “Produc- tivity Improvement in Construction,” McGraw-Hill Book th Neural Networks,” Journal of Co., New York, 1989. [7] R. Sonmez and J. E. Rowings, “Construction Labor Pro- ductivity Modeling wi Construction Engineering and Management, Vol. 124, No. 6, 1998, pp. 498-504. doi:10.1061/(ASCE)0733-9364(1998)124:6(498) [8] J. C. Kellogg, G. E. Howell and D. C. Taylor, “Hi Model of Construction Productivity,” Journal of th erarchy e Con- w uctivity,” Journal of Construction Engi- struction Division, Vol. 107, No. 1, 1981, pp. 137-152. [9] Business Roundtable, “Construction Productivity Meas- urement,” Report No. A-1, Business Roundtable, Ne York, 1982. [10] H. R. Thomas and I. Yiakoumis, “Factor Model of Con- struction Prod neering and Management, Vol. 113, No. 4, 1987, pp. 626-639. doi:10.1061/(ASCE)0733-9364(1987)113:4(623) [11] H. R. Thomas, W. F. Maloney, R. M. W. Horner Smith, V. K. Handa and S. R. Sanders, “Modelin , G. R. g Con- struction Labor Productivity,” Journal of Construction Engineering and Management, Vol. 116, No. 4, 1990, pp. 705-726. doi:10.1061/(ASCE)0733-9364(1990)116:4(705) [12] J. D. Borcherding, “Improving Productivity in Industrial Construction,” Journal of the Construction Division, Vol. 102, No. 4, 1976, pp. 599-613. Copyright © 2013 SciRes. OJCE
  • 8. F. M. S. AL-ZWAINY ET AL.134 [13] J. D. Borcherding, S. J. Sebastian and N. M. Samelson, “Improving Motivation and Productivity on Large Pro- rnal of Construction Engineering and jects,” Journal of the Construction Division, Vol. 106, No. 1, 1980, pp. 73-89. [14] W. F. Maloney, “Productivity Improvement: The Influ- ence of Labor,” Jou Management, Vol. 109, No. 3, 1983, pp. 321-334. doi:10.1061/(ASCE)0733-9364(1983)109:3(321) [15] C. H. Oglesby, H. W. Parker and G. A. Howell, “Pr tivity Improvement in Construction,” McGraw-Hill, oduc- ity,” Journal of the Construction Divi- ivity—A Case Inc., New York, 1989. [16] R. D. Logcher and W. C. Collins, “Management Impacts on Labor Productiv sion, Vol. 104, No. 4, 1978, pp. 447-461. [17] H. R. Thomas, V. E. Sanvido and S. R. Sanders, “Impact of Material Management on Product Study,” Journal of Construction Engineering and Man- agement, Vol. 115, No. 3, 1989, pp. 370-384. doi:10.1061/(ASCE)0733-9364(1989)115:3(370) [18] C. W. Ibbs and W. E. Allen, “Quantitative I Project Change,” Source Document 108, Cons mpa truction cts of Industry Institute, University of Texas at Austin, 1995. [19] C. W. Ibbs, “Quantitative Impacts of Project Change: Size Issues,” Journal of Construction Engineering and Management, Vol. 123, No. 3, 1997, pp. 308-311. doi:10.1061/(ASCE)0733-9364(1997)123:3(308) [20] A. S. Hanna, J. S. Russell, T. W. Gotzion and E. V. Nord- heim, “Impact of Change Orders on Labor Efficiency for Mechanical Construction,” Journal of Construction En- gineering and Management, Vol. 125, No. 3, 1999, pp. 176-184. doi:10.1061/(ASCE)0733-9364(1999)125:3(176) [21] H. R. Thom Labor Productivity Due to Delivery Methods an as, D. R. Riley and V. E. Sanvido, “Loss of d Wea- ther,” Journal of Construction Engineering and Man- agement, Vol. 125, No. 1, 1999, pp. 39-46. doi:10.1061/(ASCE)0733-9364(1999)125:1(39) [22] W. Ibbs, “Impact of Change’s Timing on La tivity,” Journal of Construction Engineering an bor Produc- d Man- agement, Vol. 131, No. 11, 2005, pp. 1219-1229. doi:10.1061/(ASCE)0733-9364(2005)131:11(1219) [23] A. S. Hanna, C. K. Chang, J. A. Lackney and K. T. van, “Impact of Overmanning on Mechanical and S Sulli- heet Metal Labor Productivity,” Journal of Construction En- gineering and Management, Vol. 133, No. 1, 2007, pp. 22-28. doi:10.1061/(ASCE)0733-9364(2007)133:1(22) [24] H. R. Thomas, C. T. Mathews and J. G. Ward, “Learning Curve Models of Construction Productivity,” Journal of Construction Engineering and Management, Vol. 112, No. 2, 1986, pp. 245-258. doi:10.1061/(ASCE)0733-9364(1986)112:2(245) [25] J. G. Everett and S. Farghal for Construction Field Operations,” Journal of Construc- , “Learning Curve Predictors tion Engineering and Management, Vol. 120, No. 3, 1994, pp. 603-616. doi:10.1061/(ASCE)0733-9364(1994)120:3(603) [26] J. P. Couto and Learning Curve Effect on Highrise Floor Constru J. C. Teixeira, “Using Linear Model for ction,” Construction Management & Economics, Vol. 23, No. 4, 2005, pp. 355-364. doi:10.1080/01446190500040505 [27] A. M. Jarkas, “Critical Investigation into Applicability of the Learning Curve Theory to Rebar Fixing Labor Pro- ductivity,” Journal of Construction Engineering and Ma- nagement, Vol. 136, No. 12, 2010, pp. 1279-1288. doi:10.1061/(ASCE)CO.1943-7862.0000236 [28] A. M. Jarkas and M. Horner, “Revisiting the Applic ity of Learning Curve Theory to Formwork Labour abil- Pro- ductivity,” Construction Management & Economics, Vol. 29, No. 5, 2011, pp. 483-493. doi:10.1080/01446193.2011.562911 [29] H. R. Thomas and I. Zavrski, “Co Productivity: Theory and Practice,” Jo nstruction Baseline urnal of Construc- tion Engineering and Management, Vol. 125, No. 5, 1999, pp. 295-303. doi:10.1061/(ASCE)0733-9364(1999)125:5(295) [30] H. R. Thomas and V. E. Sanvido, “Quantification of Losses Caused by Labor Inefficiencies: Where Is the Elu- truction Engineering and sive Measured Mile?” Construction Law and Business, Vol. 1, No. 3, 2000, pp. 1-14. [31] W. Ibbs and M. Liu, “Improved Measured Mile Analysis Technique,” Journal of Cons Management, Vol. 131, No. 12, 2005, pp. 1249-1256. doi:10.1061/(ASCE)0733-9364(2005)131:12(1249) [32] L. D. Nguyen and W. Ibbs, “Case Law and Variations Cumulative Impact Productivity Claims,” Journal of Con- in struction Engineering and Management, Vol. 136, No. 8, 2010, pp. 826-833. doi:10.1061/(ASCE)CO.1943-7862.0000193 [33] N. Al-Taweel and M. A. Saeed, “Measuring Times for Labors Productivity for a Number Standard of Different ,” Msc. Thesis, tor in Iraq,” Master ing Stone Using Floors entists,” 2nd Edition, Macmillan, es,” Journal of Construction Engineer- Work Items,” Journal in Engineering and Technology, Vol. 10, No. 2, 2005, 1991, pp. 249-256. [34] A. J. Tahar, “Studying Labour Productivity for Some Working Items in Construction Projects University of Technology, Iraq, 1995. [35] A. Abd-allah, “Effect of Wages and Incentives on La- bours Productivity in Construction Sec Thesis, University of Technology, Iraq, 1999. [36] F. M. S. Al-Zwainy, “The Use of Artificial Neural Net- works for Productivity Estimation of finish Works for Building Projects,” Journal of Engineering and Development, Vol. 16, No. 2, 2012, pp. 42-60. http://www.iasj.net/iasj?func=fulltext&aId=68252 [37] F. M. S. Al-Zwainy, A. R. Hatem and F. I. Huda, “ Artificial Neural Network for Finishing Works for with Marble,” ARPN Journal of Engineering and Applied Sciences, Vol. 7, No. 6, 2012, pp. 714-722. http://www.arpnjournals.com/jeas/research_papers/rp_20 12/jeas_0612_714.pdf [38] R. V. Hogg and J. Ledolter, “Applied Statistics for Engi- neers and Physical Sci New York, 1992. [39] S. D. Smith, “Earthmoving Productivity Using Linear Re- gression Techniqu ing and Management, Vol. 125, No. 3, 1999, pp. 133-141. doi:10.1061/(ASCE)0733-9364(1999)125:3(133) Copyright © 2013 SciRes. OJCE
  • 9. F. M. S. AL-ZWAINY ET AL. Copyright © 2013 SciRes. OJCE 135 ,” Jour- [40] A. Makulsawatudom and M. Emsley, “Critical Factors Influencing Construction Productivity in Thailand nal of KMITNB, Vol. 14, No. 3, 2004, pp. 1-6. [41] B. N. Gupta, “An Introduction to Modern Statistics,” Indian Institution of Public Administration, New Delhi, 1973.