SlideShare a Scribd company logo
1 of 63
1
PREPARED BY : ASST. PROF. VATSAL D. PATEL
MAHATMA GANDHI INSTITUTE OF
TECHNICAL EDUCATION &
RESEARCH CENTRE, NAVSARI.
A pile is a slender structural member mad of steel, concrete, wood
or composite material.
A pile is either driven into the soil or formed in-site by excavating a hole
and filling it with concrete.
In case, the strata of good bearing capacity is not available near the ground,
the foundation of the structure has to be taken deep with the purpose of
attaining a bearing stratum which is suitable in all aspects.
The most common forms of deep foundations are:
1. Pile foundation
2. Cassions or well foundations
3. cofferdams
The load of the superstructure is heavy and its distribution is uneven.
The top soil has poor bearing capacity.
The subsoil water is high so that pumping of water from the open trenches
for the shallow foundation is difficult and uneconomical.
There is large fluctuation in subsoil water level.
Where timbering to the trenches is difficult and costly.
The structure is situated on the sea shore or river bed, where there is danger
in scouring action of water.
Canal or deep drainage lines exist near the foundation,
The top soil is of expensive nature.
Piles are used for the limit foundation of transmission towers, off-shore
platforms which are subjected to uplift forces.
1. Nature of structure
2. Loading condition
3. Availability of funds
4. Availability of materials and equipments
5. Type of soil and its properties
6. Ground water table
7. Self weight of pile
8. Durability of pile
9. Cost of pile
10. Maintenance cost
11. Length of pile required
12. Number of pile required
13. Case study of adjacent building
14. Facilities available for pile driving
15. Difficulties in pile driving
16. Adaptability to varying length
17. Presence of acids and other material in the soil that would injure the pile
18. Erosion of soil near the structure
12. Number of pile required
13. Case study of adjacent building
14. Facilities available for pile driving
15. Difficulties in pile driving
16. Adaptability to varying length
17. Presence of acids and other material in the soil that would injure the pile
18. Erosion of soil near the structure
For the structures on the land, the driven and cast-in place piles are usually
the cheapest for moderate loadings and unhampered site conditions.
For the foundations of wharf- structures and jetties on sea shore, the driven
piles or driven and cast-in –place cased piles are preferred.
In case of piling is to be done very near to some existing structure,
open ended tube piles or H-piles may work out to good choice.
Piles used to support marine structures or structure above open water should
precast type.
The jacked piles are suitable for under-pinning existing structures.
For heavy structure, large diameter bored piles are the most economical
type.
If the subsoil consists of silt on alluvium for appreciable depth, the pile will
act as friction pile.
In case the ground is very weak or loose and it is intended to use cast-in-situ
pile, casting will be required to prevent the inflow of soil into the pile hole.
In adverse condition, where the ground water flow is strong, pile with
permanent casing should be used. Alternatively, precast piles may be used.
In case the soil strata is comparatively firm uncased cast-in-situ piles
or precast pile may be selected.
For reducing the length of pile in the firm strata, pedestal pile will be more
effective.
In situation where it is necessary that the pile should penetrate into rock for
some depth, H-piles may work out to be good selection.
In case the soil is firm clay, drilled piles with or without enlarged base, may
work out to be a economical choice.
In situation where there is possibility of the soil being chemically
aggressive, high quality precast concrete piles should be selected.
Timber piles may work out to be economical if they are used for the
foundation of timber trestles structures with moderate loads or If the piles
are to be used for protecting concrete docks, etc.
Timber piles are not suitable from marine conditions as they are likely to
be affected by borers or insects.
While selecting a particular type of pile, the cost of pile, cost of driving,
cost of maintenance of pile and availability of fund should given due
consideration.
1. End bearing pile
2. Friction pile
3. Compaction pile
4. Tension pile
5. Anchor pile
6. Fender pile
7. Better pile
8. Sheet pile
These piles penetrate through the soft soil and their bottoms or tips rest on a
hard stratum.
These piles act as columns.
The soft material surrounding the pile provides some lateral support.
When loose soil extends to a great depth, piles are driven up to such a depth
that frictional resistance developed at the sides of the piles equal the load
coming on the piles.
Friction piles are used when a hard stratum is available at greater depth. The
total frictional resistance can be increased in following ways:
By increasing the length of pile
By increasing the diameter of pile
By making the surface of the pile rough
By placing the piles closely
By grouping the piles.
When piles are driven in loose granular soil with aim of increasing the
bearing capacity of soil, the piles are termed as compaction plies.
These piles themselves do not carry any load.
These piles anchor down the structure subjected to uplift due to hydrostatic
pressure or due to overturning moment.
It is also called uplift pile.
Turning
force
Friction
force
Anchor piles provide anchorage against horizontal pull from sheet piling or
other pulling force.
Fender piles are used to protect water front structures against impact from
ships or other floating objects.
Better piles are used to resist large horizontal forces or inclined forces.
Sheet piles are used as bulk heads or as impervious cutoff to reduce seepage
and uplift under hydraulic structures.
Timber piles
Steel piles
Concrete piles
Composite piles
Timber piles are made of-tree trunks driven with small end as a point. They
may be circular or square.
They are 30 to 50 cm in diameter with a length not exceeding 20 times its
top width.
At the bottom, a cast-iron shoe is provided and the top a steel plate is fixed.
They have small bearing capacity and are not permanent unless treated.
Economical where timber is easily available.
Can be driven rapidly & as such saves time.
Because of elasticity, timber piles are recommended for sites subjected to
unusual lateral forces e.g. ship, ferry terminals.
Do not need heavy machinery and elaborate technical supervision.
Being light, they can be easily handled.
They can be easily withdrawn if needed.
This pile cannot take heavy loads and are unsuitable for use as end
bearing pile.
Liable to decay or deteriorate by salt water/insects.
Restricted length. It is rather difficult to procure piles in required size
and length.
It is difficult or rather impossible to drive these piles into hard stratum.
Steel piles are usually of rolled H-sections or thick pipe sections.
These piles are used to withstand large impact stresses and where less
distribution from driving is desired.
Steel sheet piles and H-piles are generally used to support the open
excavation and to provide seepage barrier.
Concrete piles are either precast or cast in situ.
Precast piles are cast and cured at the casting site and then transported to
the site for installation.
These piles are adequately reinforced to with stand handling stresses
along with working stresses.
Precast piles are normally suitable for short lengths.
Cast-in-situ piles are constructed by drilling hole in the ground and then
filling the hole by concrete after placing the reinforcement.
Pre-cast piles are those which are manufactured in factory or at a place
away from construction site, and then driven into the ground at the place
required.
These piles require heavy pile driving machinery.
Precast piles may be square, octagonal or circular in cross section, and
may be tapered or parallel sided longitudinally.
The size of pile may vary from 30cm to 50cm in cross sectional
dimension, and up to 20m or more in length.
The reinforcement may consists of longitudinal steel bars of 20mm to
40mm in diameter, 4 to 8 nos. with ties of 6 to 10 mm diameter at
100mm c/c spacing for top and bottom 1m length and 300mm c/c
spacing for middle length.
A concrete cover of at least 50mm is provided.
The grade of concrete should be M20.
1. The formwork for the pile is prepared and it is coated with soap
solution or oil to prevent adhesion.
2. The cage of reinforcement is prepared as per design and this cage is
then placed in the formwork. A concrete cover of at least 50mm is
provided.
3. A concrete grade M20 is prepared with proportion 1:1.5:3. The size
of coarse aggregate varies from 10mm to 25mm.
4. The concrete is laid in the formwork and well compacted using
vibrators.
5. The forms are removed after 3days and the piles are kept in the same
position for about 7 days or so.
6. The piles are then shifted to a curing tank and after a period of about
three or four weeks, they become ready for use.
They will be cast well before the commencement of the work resulting in
rapid execution of work.
The position of reinforcement in pile is not disturbed from its original
position.
They can driven under water.
The piles can be loaded soon after they have been driven to desire depth.
Any numbers of piles can be manufactured at a convenient place and this
may prove to be economical.
These piles are highly resistant to biological and chemical actions of the
subsoil.
These piles are heavy. Therefore they require special equipment for
handling and transportation.
If sufficient care is not taken, these piles may break during transport or
driving.
They require heavy pile driving equipment.
Extra reinforcement is require to bear handling and driving stresses.
Hence these piles are costly.
The length of the pile is restricted since it is depends upon the transport
facilities.
It is difficult to increase the length of the pile previously estimated on the
basis of bore holes.
If the pile is found to be too long during driving, it is difficult and
uneconomical to cut the pile.
The Raymond standard pile is used primarily as a friction pile.
It is provided with uniform taper of 1 in 30 resulting in shorter piles.
The length of pile vary from 6 to 12m. The diameter of piles vary from
40 to 60 cm at the top and 20 to 30 at the bottom.
the shell is driven into the ground with a collapsible steel mandrel or
core in it having the same paper.
The shell is gradually filled with concrete up to the top.
Mac Arthur is a pile of uniform diameter using the corrugated steel shell
which remains in place as in Raymond piles.
A heavy steel casing with a core is driven into the ground.
When the desired depth is reached the core is withdrawn and a
corrugated steel shell is placed in the casing.
Concrete is placed in the shell by gradually compacting it and
withdrawing the steel casing.
This pile consists of helically welded shell of steel plate. A concrete plug
is provided at the bottom of the shell.
Driving Is done by allowing pile hammer to fall on the concrete plug.
The casing is driving to the desired depth and then it is filled with
concrete
Swage piles are used with advantage in some soils where the driving is
very hard or where it is desired to leave water tight shell, for some time
before filling the concrete.
In the first stage a steel shell is placed on a precast concrete plug and a
steel core which is not long enough to reach the plug is inserted in the
plug.
In the second stage the pipe is driven over the plug until the core reaches
the plug the pipe is swaged out by the taper of the plug thus forming a
water tight joint.
In the third stage the pipe is driven to a specified depth.
In the fourth stage after the pipe was reached the desired depth the core
is removed and the pipe is filled with concrete.
These piles are used in locations where increase in the end bearing area
is desired. The pile uses a concrete plug of shape of button.
There piles have been used up to lengths of about 23 m and for loads up
to 50 tonnes.
In the 1st stage a steel pipe with 12mm thick walls is set on the concrete
button. The concrete button has a diameter about 25mm larger than the
pipe.
In the 2nd stage the pipe and button are driven to a specified depth.
In the 3rd stage a corrugated steel shell is inserted in the pipe resting on
the button.
In the 4th stage the casing is withdrawn leaving the button in place and
the shell is filled with concrete. Reinforcement may be used if
necessary.
Advantages:
These piles are cheap as no casing will be left in the ground.
Special handling equipment is not required.
Concrete is not liable to damage from driving.
Cutting of excess lengths is not required .
Storage space not required.
Disadvantages:
Great skill is required.
It is likely to be damaged from subsoil pressure and ground movements
which result from pile driving and obstruction in ground.
Simplex piles can be driven through soft or hard soils.
In this type of piles a steel tube fitted with a cast iron shoe is driven into the
ground up to the desired depth.
Reinforcement if necessary is put inside the tube concrete is then poured
into the tube and the tube is slowly withdrawn concrete being tamped
leaving behind the cast iron shoe.
In this type of pile a plug of dry concrete gravel is formed on the ground by
heavy removable pipe shell.
A diesel operated drop hammer of 20 to 30 KN weight is driven on the
concrete plug.
When the tube has reduced the desired depth the tube is held in position by
cables and the hammer is applied to the concrete plug forcing it down and
outward.
In the next stage the shaft is formed by introducing successive charges of
concrete ramming each in turn and withdrawn the casing gradually about
300mm at a time.
The pile diameter in franki piles vary from 50cm to 60cm while the
enlarged base may have a diameter of about 90cm.
The pile has a load carrying capacity of 60 to 90 tonnes.
These pile are used where the ground is soft thus offering little frictional
resistance to the flow of concrete. Both standard and expanded piles are
formed by the vibro-process.
These piles are formed by driven a steel tube and shoe filling with concrete
and withdrawing the steel tube.
Standard vibro piles are made in size of 35,45,50cm diameter for loads of
60 to 70 tonnes.
A steel tube fitted with a cast iron shoe is driven in the ground by 2 to 2.5
tonnes hammer operated by steam or compressed air delivering up to 40
blow per minute with a stroke of about 1.4m.
This type of pile are used where thin bearing stratum is reached with
reasonable depth.
The core and casing are driven together into the ground till they reach the
desired level.
The core is taken out and a charge of concrete is placed in the tube. The
core is again placed in the casing to rest on the of poured concrete.
Pressure is applied on the concrete through the core and as the same time
the casing is withdrawn.
The process is repeated till the casing is completely removed.
These are formed wit the help of a casing tube boring auger and compressed
air equipment. These piles are especially suitable for those congested sites
where heavy vibrations and noise are not permissible.
A hole is bored into the ground by means of an auger and as the boring
proceeds the hole is lined by a steel tube.
When the tube reaches the required depth the boring tool is withdrawn.
In the 2nd stage a layer of concrete is laid and pressure cap is provided at
the top of the tube.
The process is repeated till the pile is completed.
These piles are developed by C.B.R.I., Roorkee (U.P) for serving as
foundations for black cotton soils, filled up ground and other types of soils
having poor bearing capacity.
An under-reamed pile is a bored cast-in-situ concrete pile having one or
more bulbs or under-reams in its lower portion.
The bulbs or under-reams are formed by under reaming tool.
The diameter of under remed pile varies from 20 cm to 50 cm and that of
bulb varies from 2 to 3 times the diameter of pile.
The length of under reamed piles is about 3 m to 8 m.
The spacing of piles mat vary from 2m to 4m.
The under reamed piles can also be used for sandy soils with high water
table.
The load carrying capacity of under reamed piles can be increased by
adopting piles of larger diameter or by extending the length of piles or by
making more bulbs at the base.
A single under reamed pile has only one bulb at the bottom.
When two or more bulbs are provided at the base, it is known as multi-bulb
under reamed pile.
The vertical spacing between two bulbs varies from 1.25 to 1.50 times the
diameter of bulb.
 The center to center distance of successive piles is known as pile spacing.
 It has to be carefully designed by considering the following factors,
 Types of piles and Material of piles
 Length of piles
 Grouping of piles
 Load coming on piles
 Obstruction during pile driving
 Nature of soil through which piles are passing.
 The spacing between piles in a group can be assumed based on
the following:
 1- Friction piles need higher spacing than bearing piles.
 2- Minimum spacing (S) between piles is 2.5.
 3- Maximum spacing (S) between piles is 8.0.
S
47
S
2
Piles
3
Piles
S
4
Piles
5
Piles
S 6
S
Piles S S
7
Piles
 Most pile foundations contain group of
piles instead of single pile.
 The piles forming the group of piles may be
arranged in square, rectangular, triangular or
circular as per the requirement.
 The bearing capacity of pile group may not be
necessarily equal the sum of the bearing capacity
of individual piles forming a group.
 The efficiency of a pile group is define as the ratio of the load carrying capacity of
the pile group to the sum of the load carrying capacities of the individual piles.
 Factors of Group Efficiency:
 The number, length, diameter, and spacing of the piles
 The load transfer mode (friction vs. bearing)
 The sequence of installation
 The soil type
 The interaction, if any, between the pile cap and the soil
 The direction of the applied load
 The process of forcing the piles into the ground without excavation is termed as
the pile driving.
 The piles should be driven vertically.
 However, a tolerance of eccentricity of 2% of the pile length is permissible.
 The eccentricity is measured by means of plumb bob.
 The hammer is guided between two parallel steel members known as leads.
Boom
Crane
Pile
Lead
Hammer
Helmet
Pile Gate
Stabbing
Points
 Drop hammer.
 Single acting hammer.
 Double acting hammer.
 Diesel hammer.
 Vibratory hammer.
53
Driving
shoe
hammer
Drop Hammer
Hammer Guide
Pile (pre cast/cast in situ)
Soil
 Low operation
 Low equipment cost
 Simple
 A hammer (or ram or monkey) is raised
by winch and allowed to fall or drop by
gravity on the top of the pile.
 The drop hammer is provided with lugs
so that it can slide in the leads.
 A lifting eye or hook is provided to tie it
with the rope.
 The weight of drop hammer varies from
0.5 to 2 tones (5 to 20 kN).
 The height of fall may vary from 1.5 to 3
meters.
 The number of blows that can be
imparted varies from 4 to 8 per minute.
 If the hammer is raised by steam, compressed air or internal combustion, but is
allowed to fall by gravity along, it is called a single acting hammer.
 The energy of such hammer is equal to the weight of the ram times the height of
fall.
 The weight of single acting hammer is about 2 tonnes (20kN).
 The fall is about 1 meter.
 the number of blows of the hammer may vary from 50 to
60 per minute.
57
Piston
Ram
Helmet
Pile
 The double acting hammer employs steam or air for lifting the ram and for
accelerating the downward stroke.
 The weight of the hammer is only 500 kg (5 kN) but because of accelerating effect
of steam (or air) pressure, it has an effect of a weight of 3 tonnes (30.kN).
 It operates with succession of rapid blows,the number varying from 100 to 200
blows perminute.
 For light hammers, the number of blows may be even as high as 300 per minute.
 The pile driving is very quick.
 These hammers are very useful for driving piles under water.
59
 The total driving energy is the sum of
the impact of the ram plus the energy
delivered by explosion.
 The diesel hammer is a small, light
weight self-contained and self-acting
type, using gasoline for fuel.
 If the driving has to be carried out by hammer, then following factors should be take
into consideration.
 The size and weight of the pile.
 The driving resistance which has to be overcome to achieve the desired
penetration.
 The available space and head room in the site because the hammer has to be
dropped from certain height.
 The availability of cranes.
 The noise restrictions which may be in force in the locality.
 The ultimate load carrying capacity, or ultimate bearing capacity (Qf) of a pile is
defined as the maximum load which can be carried by a pile and at which the pile
continues to sink without further increase of load.
 The allowable load Qa is the safe load which the pile can
carry safely and is determined on the basis of
 Ultimate bearing, resistance divided by appropriate factor of safety.
 The permissible settlement,
 Overall stability of the pile foundation.
 The load carrying capacity of a pile can be determined by the following methods.
 Dynamic formulae
 Static formulae
 Used for precast concrete piles.
 When a pile hammer hits the pile, the total driving energy is equal to the weight
of hammer times the height of drop or stroke.
 In addition to this, in the case of double acting hammers, some energy is also
imparted by the steam pressure during the return stroke.
 The total downward energy is consumed by the work done in penetrating the pile
and by certain losses.
 The various dynamic formulae are essentially based on this assumption.
Engineering New Formula:
Qa = allowable load
W = weight of hammer (KG)
H = height of fall (CM)
F = factor of safety = 6
S = final set (penetration) per blow,
(Usually taken as average penetration, cm per blow for
the last 5 Blows of hammer or last 20 blows for steam
hammer.)
C = empirical constant.
= 2.5 cm for drop hammers, and
= 0.25
hammers.
For single acting steam
hammer
For drop hammer
cm for single or double acting
For double acting
hammer
a= effective area of piston (cm2)
P=mean effective steam pressure (kg/cm
Hiley's Formula (IS formula):
 Indian standard IS: 2911(Part I): 1964 gives the following formula based on
original expression by Hiley :
Qf = ultimate load on pile.
W = weight of hammer in kg
H = height on drop of hammer, in cm
S = penetration or set, in cm, per blow
C = total elastic compression= C1 + C2 + C3
C1,C2, C3 = temporary elastic compression of dolly and packing, pile and soil
respectively.
h = efficiency of hammer, variable from 65 percent for same double acing steam
hammers to 100 percent for drop hammers released by trigger.
b = efficiency of hammer blows (i.e. ratio of the energy after impact to striking energy of
ram).
 The static formulae are based on the assumption that the ultimate bearing capacity
Qf of a pile is the sum of the total ultimate skin friction Rf and total ultimate point
or end bearing resistance Rp.
As = surface area of pile upon which the skin friction acts
Ap = area of cross-section of the pile on which bearing resistance acts. For
tapered piles, Ap may be taken as the cross-sectional area at the lower one-third
of the embedded length.
rf = average unit skin friction, which may be taken equal to unit cohesion for
cohesive soils.
rp = unit point or toe resistance, which may be taken as 9c for cohesive soils.
63

More Related Content

What's hot

Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavementsHARITSEHRAWAT
 
Chapter 3 building foundation
Chapter 3 building foundationChapter 3 building foundation
Chapter 3 building foundationAmiRul AFiq
 
Aggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limitsAggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limitslalitha moorthy
 
Footing and Its Types
Footing and Its TypesFooting and Its Types
Footing and Its TypesAbid Javaid
 
Stone columns - an overview(Ground improvement)
Stone columns -  an overview(Ground improvement)Stone columns -  an overview(Ground improvement)
Stone columns - an overview(Ground improvement)Tarachand Veeragattapu
 
Stone column
Stone columnStone column
Stone columnGEOMIND
 
Type of caissons
Type of caissonsType of caissons
Type of caissonsAB MAKASANA
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundationsDar Hilal
 
Load carrying capacity of piles
Load carrying capacity of pilesLoad carrying capacity of piles
Load carrying capacity of pilesLatif Hyder Wadho
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing TechniqueSeminar Links
 
Well foundations
Well foundationsWell foundations
Well foundationsganesh6561
 

What's hot (20)

Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
 
Chapter 3 building foundation
Chapter 3 building foundationChapter 3 building foundation
Chapter 3 building foundation
 
Standard penetration test
Standard penetration testStandard penetration test
Standard penetration test
 
Aggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limitsAggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limits
 
Footing and Its Types
Footing and Its TypesFooting and Its Types
Footing and Its Types
 
Stone columns - an overview(Ground improvement)
Stone columns -  an overview(Ground improvement)Stone columns -  an overview(Ground improvement)
Stone columns - an overview(Ground improvement)
 
Stone column
Stone columnStone column
Stone column
 
Type of caissons
Type of caissonsType of caissons
Type of caissons
 
Interface treatment
Interface treatmentInterface treatment
Interface treatment
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
Pile integrity test
Pile integrity testPile integrity test
Pile integrity test
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
 
Well foundation
Well foundationWell foundation
Well foundation
 
water bound macadam road
water bound macadam roadwater bound macadam road
water bound macadam road
 
Concrete Mix Design
Concrete Mix DesignConcrete Mix Design
Concrete Mix Design
 
Load carrying capacity of piles
Load carrying capacity of pilesLoad carrying capacity of piles
Load carrying capacity of piles
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
Micropile
MicropileMicropile
Micropile
 
Well foundations
Well foundationsWell foundations
Well foundations
 

Similar to 1.PILE FOUNDATION (ACE) 2160601 GTU

Advance Construction & Equipment
Advance Construction & EquipmentAdvance Construction & Equipment
Advance Construction & EquipmentAditya Mistry
 
Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)
Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)
Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)Pratik Solanki
 
ALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONSALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONSjagrutib22
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Make Mannan
 
Pile foundation
Pile foundationPile foundation
Pile foundationJNTUK
 
Construction-methods-and-techniques.pptx
Construction-methods-and-techniques.pptxConstruction-methods-and-techniques.pptx
Construction-methods-and-techniques.pptxLyrittSazellebb
 
Pile foundation power point ptesentation
Pile foundation power point ptesentationPile foundation power point ptesentation
Pile foundation power point ptesentationMohammad zuha
 
CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
CHAPTER 5 DEEP FOUNDATION (2)7788788.pptCHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
CHAPTER 5 DEEP FOUNDATION (2)7788788.pptbryankalindo888
 
Pile foundation
Pile foundationPile foundation
Pile foundationaranjalisp
 
Lec 7 pile foundation
Lec 7 pile foundationLec 7 pile foundation
Lec 7 pile foundationGhulam Yasin
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptxDUAASALAH5
 

Similar to 1.PILE FOUNDATION (ACE) 2160601 GTU (20)

Advance Construction & Equipment
Advance Construction & EquipmentAdvance Construction & Equipment
Advance Construction & Equipment
 
Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)
Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)
Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)
 
ALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONSALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONS
 
Deep foundation
Deep foundationDeep foundation
Deep foundation
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
 
Chapter 15
Chapter 15Chapter 15
Chapter 15
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Pile footing.pptx
Pile footing.pptxPile footing.pptx
Pile footing.pptx
 
Different types of pile
Different types of pile Different types of pile
Different types of pile
 
foundation.pptx
foundation.pptxfoundation.pptx
foundation.pptx
 
Construction-methods-and-techniques.pptx
Construction-methods-and-techniques.pptxConstruction-methods-and-techniques.pptx
Construction-methods-and-techniques.pptx
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
LECT 6 UPDATE.pdf
LECT  6 UPDATE.pdfLECT  6 UPDATE.pdf
LECT 6 UPDATE.pdf
 
Pile foundation power point ptesentation
Pile foundation power point ptesentationPile foundation power point ptesentation
Pile foundation power point ptesentation
 
Deep Foundation
Deep FoundationDeep Foundation
Deep Foundation
 
CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
CHAPTER 5 DEEP FOUNDATION (2)7788788.pptCHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Lec 7 pile foundation
Lec 7 pile foundationLec 7 pile foundation
Lec 7 pile foundation
 
DEEP FOUNDATION
DEEP FOUNDATIONDEEP FOUNDATION
DEEP FOUNDATION
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
 

More from VATSAL PATEL

5. AIR TRANSPORTATION (TRE) GTU 3150611
5. AIR TRANSPORTATION (TRE) GTU 31506115. AIR TRANSPORTATION (TRE) GTU 3150611
5. AIR TRANSPORTATION (TRE) GTU 3150611VATSAL PATEL
 
3. RAIL TRANSPORTATION (TRE) GTU 3150611
3. RAIL TRANSPORTATION (TRE) GTU 31506113. RAIL TRANSPORTATION (TRE) GTU 3150611
3. RAIL TRANSPORTATION (TRE) GTU 3150611VATSAL PATEL
 
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTUVATSAL PATEL
 
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...VATSAL PATEL
 
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTUVATSAL PATEL
 
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...VATSAL PATEL
 
2. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 31706232. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 3170623VATSAL PATEL
 
4. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 31506114. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 3150611VATSAL PATEL
 
8. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 31706238. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 3170623VATSAL PATEL
 
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTUVATSAL PATEL
 
7. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 31706237. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 3170623VATSAL PATEL
 
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 31706236. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 3170623VATSAL PATEL
 
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 31706235. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623VATSAL PATEL
 
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 31706234. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623VATSAL PATEL
 
3. NATURAL PHENOMENA (PHE) GTU 3170623
3. NATURAL PHENOMENA (PHE) GTU 31706233. NATURAL PHENOMENA (PHE) GTU 3170623
3. NATURAL PHENOMENA (PHE) GTU 3170623VATSAL PATEL
 
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTUVATSAL PATEL
 
1. INTRODUCTION TO WATER TRANSPORTATION (PHE) GTU 3170623
1. INTRODUCTION  TO WATER TRANSPORTATION (PHE) GTU 31706231. INTRODUCTION  TO WATER TRANSPORTATION (PHE) GTU 3170623
1. INTRODUCTION TO WATER TRANSPORTATION (PHE) GTU 3170623VATSAL PATEL
 
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTUVATSAL PATEL
 
1. INTRODUCTION (TRE) 3150611 GTU
1. INTRODUCTION (TRE) 3150611 GTU1. INTRODUCTION (TRE) 3150611 GTU
1. INTRODUCTION (TRE) 3150611 GTUVATSAL PATEL
 
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTUVATSAL PATEL
 

More from VATSAL PATEL (20)

5. AIR TRANSPORTATION (TRE) GTU 3150611
5. AIR TRANSPORTATION (TRE) GTU 31506115. AIR TRANSPORTATION (TRE) GTU 3150611
5. AIR TRANSPORTATION (TRE) GTU 3150611
 
3. RAIL TRANSPORTATION (TRE) GTU 3150611
3. RAIL TRANSPORTATION (TRE) GTU 31506113. RAIL TRANSPORTATION (TRE) GTU 3150611
3. RAIL TRANSPORTATION (TRE) GTU 3150611
 
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
 
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
 
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
 
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
 
2. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 31706232. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 3170623
 
4. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 31506114. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 3150611
 
8. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 31706238. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 3170623
 
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
 
7. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 31706237. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 3170623
 
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 31706236. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
 
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 31706235. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
 
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 31706234. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
 
3. NATURAL PHENOMENA (PHE) GTU 3170623
3. NATURAL PHENOMENA (PHE) GTU 31706233. NATURAL PHENOMENA (PHE) GTU 3170623
3. NATURAL PHENOMENA (PHE) GTU 3170623
 
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
 
1. INTRODUCTION TO WATER TRANSPORTATION (PHE) GTU 3170623
1. INTRODUCTION  TO WATER TRANSPORTATION (PHE) GTU 31706231. INTRODUCTION  TO WATER TRANSPORTATION (PHE) GTU 3170623
1. INTRODUCTION TO WATER TRANSPORTATION (PHE) GTU 3170623
 
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
 
1. INTRODUCTION (TRE) 3150611 GTU
1. INTRODUCTION (TRE) 3150611 GTU1. INTRODUCTION (TRE) 3150611 GTU
1. INTRODUCTION (TRE) 3150611 GTU
 
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
 

Recently uploaded

Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfsumitt6_25730773
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...ppkakm
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxMustafa Ahmed
 
8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessorAshwiniTodkar4
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...ssuserdfc773
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxhublikarsn
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdfKamal Acharya
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelDrAjayKumarYadav4
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 

Recently uploaded (20)

Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdf
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 

1.PILE FOUNDATION (ACE) 2160601 GTU

  • 1. 1 PREPARED BY : ASST. PROF. VATSAL D. PATEL MAHATMA GANDHI INSTITUTE OF TECHNICAL EDUCATION & RESEARCH CENTRE, NAVSARI.
  • 2. A pile is a slender structural member mad of steel, concrete, wood or composite material. A pile is either driven into the soil or formed in-site by excavating a hole and filling it with concrete. In case, the strata of good bearing capacity is not available near the ground, the foundation of the structure has to be taken deep with the purpose of attaining a bearing stratum which is suitable in all aspects. The most common forms of deep foundations are: 1. Pile foundation 2. Cassions or well foundations 3. cofferdams
  • 3. The load of the superstructure is heavy and its distribution is uneven. The top soil has poor bearing capacity. The subsoil water is high so that pumping of water from the open trenches for the shallow foundation is difficult and uneconomical. There is large fluctuation in subsoil water level. Where timbering to the trenches is difficult and costly. The structure is situated on the sea shore or river bed, where there is danger in scouring action of water. Canal or deep drainage lines exist near the foundation, The top soil is of expensive nature. Piles are used for the limit foundation of transmission towers, off-shore platforms which are subjected to uplift forces.
  • 4. 1. Nature of structure 2. Loading condition 3. Availability of funds 4. Availability of materials and equipments 5. Type of soil and its properties 6. Ground water table 7. Self weight of pile 8. Durability of pile 9. Cost of pile 10. Maintenance cost 11. Length of pile required
  • 5. 12. Number of pile required 13. Case study of adjacent building 14. Facilities available for pile driving 15. Difficulties in pile driving 16. Adaptability to varying length 17. Presence of acids and other material in the soil that would injure the pile 18. Erosion of soil near the structure
  • 6. 12. Number of pile required 13. Case study of adjacent building 14. Facilities available for pile driving 15. Difficulties in pile driving 16. Adaptability to varying length 17. Presence of acids and other material in the soil that would injure the pile 18. Erosion of soil near the structure
  • 7. For the structures on the land, the driven and cast-in place piles are usually the cheapest for moderate loadings and unhampered site conditions. For the foundations of wharf- structures and jetties on sea shore, the driven piles or driven and cast-in –place cased piles are preferred. In case of piling is to be done very near to some existing structure, open ended tube piles or H-piles may work out to good choice. Piles used to support marine structures or structure above open water should precast type. The jacked piles are suitable for under-pinning existing structures. For heavy structure, large diameter bored piles are the most economical type.
  • 8. If the subsoil consists of silt on alluvium for appreciable depth, the pile will act as friction pile. In case the ground is very weak or loose and it is intended to use cast-in-situ pile, casting will be required to prevent the inflow of soil into the pile hole. In adverse condition, where the ground water flow is strong, pile with permanent casing should be used. Alternatively, precast piles may be used. In case the soil strata is comparatively firm uncased cast-in-situ piles or precast pile may be selected. For reducing the length of pile in the firm strata, pedestal pile will be more effective. In situation where it is necessary that the pile should penetrate into rock for some depth, H-piles may work out to be good selection. In case the soil is firm clay, drilled piles with or without enlarged base, may work out to be a economical choice.
  • 9. In situation where there is possibility of the soil being chemically aggressive, high quality precast concrete piles should be selected. Timber piles may work out to be economical if they are used for the foundation of timber trestles structures with moderate loads or If the piles are to be used for protecting concrete docks, etc. Timber piles are not suitable from marine conditions as they are likely to be affected by borers or insects.
  • 10. While selecting a particular type of pile, the cost of pile, cost of driving, cost of maintenance of pile and availability of fund should given due consideration.
  • 11. 1. End bearing pile 2. Friction pile 3. Compaction pile 4. Tension pile 5. Anchor pile 6. Fender pile 7. Better pile 8. Sheet pile
  • 12. These piles penetrate through the soft soil and their bottoms or tips rest on a hard stratum. These piles act as columns. The soft material surrounding the pile provides some lateral support.
  • 13. When loose soil extends to a great depth, piles are driven up to such a depth that frictional resistance developed at the sides of the piles equal the load coming on the piles. Friction piles are used when a hard stratum is available at greater depth. The total frictional resistance can be increased in following ways: By increasing the length of pile By increasing the diameter of pile By making the surface of the pile rough By placing the piles closely By grouping the piles.
  • 14. When piles are driven in loose granular soil with aim of increasing the bearing capacity of soil, the piles are termed as compaction plies. These piles themselves do not carry any load.
  • 15. These piles anchor down the structure subjected to uplift due to hydrostatic pressure or due to overturning moment. It is also called uplift pile. Turning force Friction force
  • 16. Anchor piles provide anchorage against horizontal pull from sheet piling or other pulling force. Fender piles are used to protect water front structures against impact from ships or other floating objects. Better piles are used to resist large horizontal forces or inclined forces. Sheet piles are used as bulk heads or as impervious cutoff to reduce seepage and uplift under hydraulic structures.
  • 17. Timber piles Steel piles Concrete piles Composite piles
  • 18. Timber piles are made of-tree trunks driven with small end as a point. They may be circular or square. They are 30 to 50 cm in diameter with a length not exceeding 20 times its top width. At the bottom, a cast-iron shoe is provided and the top a steel plate is fixed. They have small bearing capacity and are not permanent unless treated.
  • 19. Economical where timber is easily available. Can be driven rapidly & as such saves time. Because of elasticity, timber piles are recommended for sites subjected to unusual lateral forces e.g. ship, ferry terminals. Do not need heavy machinery and elaborate technical supervision. Being light, they can be easily handled. They can be easily withdrawn if needed.
  • 20. This pile cannot take heavy loads and are unsuitable for use as end bearing pile. Liable to decay or deteriorate by salt water/insects. Restricted length. It is rather difficult to procure piles in required size and length. It is difficult or rather impossible to drive these piles into hard stratum.
  • 21. Steel piles are usually of rolled H-sections or thick pipe sections. These piles are used to withstand large impact stresses and where less distribution from driving is desired. Steel sheet piles and H-piles are generally used to support the open excavation and to provide seepage barrier.
  • 22. Concrete piles are either precast or cast in situ. Precast piles are cast and cured at the casting site and then transported to the site for installation. These piles are adequately reinforced to with stand handling stresses along with working stresses. Precast piles are normally suitable for short lengths. Cast-in-situ piles are constructed by drilling hole in the ground and then filling the hole by concrete after placing the reinforcement.
  • 23. Pre-cast piles are those which are manufactured in factory or at a place away from construction site, and then driven into the ground at the place required. These piles require heavy pile driving machinery. Precast piles may be square, octagonal or circular in cross section, and may be tapered or parallel sided longitudinally.
  • 24. The size of pile may vary from 30cm to 50cm in cross sectional dimension, and up to 20m or more in length. The reinforcement may consists of longitudinal steel bars of 20mm to 40mm in diameter, 4 to 8 nos. with ties of 6 to 10 mm diameter at 100mm c/c spacing for top and bottom 1m length and 300mm c/c spacing for middle length. A concrete cover of at least 50mm is provided. The grade of concrete should be M20.
  • 25. 1. The formwork for the pile is prepared and it is coated with soap solution or oil to prevent adhesion. 2. The cage of reinforcement is prepared as per design and this cage is then placed in the formwork. A concrete cover of at least 50mm is provided. 3. A concrete grade M20 is prepared with proportion 1:1.5:3. The size of coarse aggregate varies from 10mm to 25mm. 4. The concrete is laid in the formwork and well compacted using vibrators. 5. The forms are removed after 3days and the piles are kept in the same position for about 7 days or so. 6. The piles are then shifted to a curing tank and after a period of about three or four weeks, they become ready for use.
  • 26. They will be cast well before the commencement of the work resulting in rapid execution of work. The position of reinforcement in pile is not disturbed from its original position. They can driven under water. The piles can be loaded soon after they have been driven to desire depth. Any numbers of piles can be manufactured at a convenient place and this may prove to be economical. These piles are highly resistant to biological and chemical actions of the subsoil.
  • 27. These piles are heavy. Therefore they require special equipment for handling and transportation. If sufficient care is not taken, these piles may break during transport or driving. They require heavy pile driving equipment. Extra reinforcement is require to bear handling and driving stresses. Hence these piles are costly. The length of the pile is restricted since it is depends upon the transport facilities. It is difficult to increase the length of the pile previously estimated on the basis of bore holes. If the pile is found to be too long during driving, it is difficult and uneconomical to cut the pile.
  • 28. The Raymond standard pile is used primarily as a friction pile. It is provided with uniform taper of 1 in 30 resulting in shorter piles. The length of pile vary from 6 to 12m. The diameter of piles vary from 40 to 60 cm at the top and 20 to 30 at the bottom. the shell is driven into the ground with a collapsible steel mandrel or core in it having the same paper. The shell is gradually filled with concrete up to the top.
  • 29. Mac Arthur is a pile of uniform diameter using the corrugated steel shell which remains in place as in Raymond piles. A heavy steel casing with a core is driven into the ground. When the desired depth is reached the core is withdrawn and a corrugated steel shell is placed in the casing. Concrete is placed in the shell by gradually compacting it and withdrawing the steel casing.
  • 30. This pile consists of helically welded shell of steel plate. A concrete plug is provided at the bottom of the shell. Driving Is done by allowing pile hammer to fall on the concrete plug. The casing is driving to the desired depth and then it is filled with concrete
  • 31. Swage piles are used with advantage in some soils where the driving is very hard or where it is desired to leave water tight shell, for some time before filling the concrete. In the first stage a steel shell is placed on a precast concrete plug and a steel core which is not long enough to reach the plug is inserted in the plug. In the second stage the pipe is driven over the plug until the core reaches the plug the pipe is swaged out by the taper of the plug thus forming a water tight joint. In the third stage the pipe is driven to a specified depth. In the fourth stage after the pipe was reached the desired depth the core is removed and the pipe is filled with concrete.
  • 32. These piles are used in locations where increase in the end bearing area is desired. The pile uses a concrete plug of shape of button. There piles have been used up to lengths of about 23 m and for loads up to 50 tonnes. In the 1st stage a steel pipe with 12mm thick walls is set on the concrete button. The concrete button has a diameter about 25mm larger than the pipe. In the 2nd stage the pipe and button are driven to a specified depth. In the 3rd stage a corrugated steel shell is inserted in the pipe resting on the button. In the 4th stage the casing is withdrawn leaving the button in place and the shell is filled with concrete. Reinforcement may be used if necessary.
  • 33. Advantages: These piles are cheap as no casing will be left in the ground. Special handling equipment is not required. Concrete is not liable to damage from driving. Cutting of excess lengths is not required . Storage space not required. Disadvantages: Great skill is required. It is likely to be damaged from subsoil pressure and ground movements which result from pile driving and obstruction in ground.
  • 34. Simplex piles can be driven through soft or hard soils. In this type of piles a steel tube fitted with a cast iron shoe is driven into the ground up to the desired depth. Reinforcement if necessary is put inside the tube concrete is then poured into the tube and the tube is slowly withdrawn concrete being tamped leaving behind the cast iron shoe.
  • 35. In this type of pile a plug of dry concrete gravel is formed on the ground by heavy removable pipe shell. A diesel operated drop hammer of 20 to 30 KN weight is driven on the concrete plug. When the tube has reduced the desired depth the tube is held in position by cables and the hammer is applied to the concrete plug forcing it down and outward. In the next stage the shaft is formed by introducing successive charges of concrete ramming each in turn and withdrawn the casing gradually about 300mm at a time. The pile diameter in franki piles vary from 50cm to 60cm while the enlarged base may have a diameter of about 90cm. The pile has a load carrying capacity of 60 to 90 tonnes.
  • 36. These pile are used where the ground is soft thus offering little frictional resistance to the flow of concrete. Both standard and expanded piles are formed by the vibro-process. These piles are formed by driven a steel tube and shoe filling with concrete and withdrawing the steel tube. Standard vibro piles are made in size of 35,45,50cm diameter for loads of 60 to 70 tonnes. A steel tube fitted with a cast iron shoe is driven in the ground by 2 to 2.5 tonnes hammer operated by steam or compressed air delivering up to 40 blow per minute with a stroke of about 1.4m.
  • 37. This type of pile are used where thin bearing stratum is reached with reasonable depth. The core and casing are driven together into the ground till they reach the desired level. The core is taken out and a charge of concrete is placed in the tube. The core is again placed in the casing to rest on the of poured concrete. Pressure is applied on the concrete through the core and as the same time the casing is withdrawn. The process is repeated till the casing is completely removed.
  • 38. These are formed wit the help of a casing tube boring auger and compressed air equipment. These piles are especially suitable for those congested sites where heavy vibrations and noise are not permissible. A hole is bored into the ground by means of an auger and as the boring proceeds the hole is lined by a steel tube. When the tube reaches the required depth the boring tool is withdrawn. In the 2nd stage a layer of concrete is laid and pressure cap is provided at the top of the tube. The process is repeated till the pile is completed.
  • 39. These piles are developed by C.B.R.I., Roorkee (U.P) for serving as foundations for black cotton soils, filled up ground and other types of soils having poor bearing capacity. An under-reamed pile is a bored cast-in-situ concrete pile having one or more bulbs or under-reams in its lower portion. The bulbs or under-reams are formed by under reaming tool. The diameter of under remed pile varies from 20 cm to 50 cm and that of bulb varies from 2 to 3 times the diameter of pile. The length of under reamed piles is about 3 m to 8 m. The spacing of piles mat vary from 2m to 4m. The under reamed piles can also be used for sandy soils with high water table.
  • 40. The load carrying capacity of under reamed piles can be increased by adopting piles of larger diameter or by extending the length of piles or by making more bulbs at the base. A single under reamed pile has only one bulb at the bottom. When two or more bulbs are provided at the base, it is known as multi-bulb under reamed pile. The vertical spacing between two bulbs varies from 1.25 to 1.50 times the diameter of bulb.
  • 41.  The center to center distance of successive piles is known as pile spacing.  It has to be carefully designed by considering the following factors,  Types of piles and Material of piles  Length of piles  Grouping of piles  Load coming on piles  Obstruction during pile driving  Nature of soil through which piles are passing.  The spacing between piles in a group can be assumed based on the following:  1- Friction piles need higher spacing than bearing piles.  2- Minimum spacing (S) between piles is 2.5.  3- Maximum spacing (S) between piles is 8.0. S
  • 43.  Most pile foundations contain group of piles instead of single pile.  The piles forming the group of piles may be arranged in square, rectangular, triangular or circular as per the requirement.  The bearing capacity of pile group may not be necessarily equal the sum of the bearing capacity of individual piles forming a group.
  • 44.  The efficiency of a pile group is define as the ratio of the load carrying capacity of the pile group to the sum of the load carrying capacities of the individual piles.  Factors of Group Efficiency:  The number, length, diameter, and spacing of the piles  The load transfer mode (friction vs. bearing)  The sequence of installation  The soil type  The interaction, if any, between the pile cap and the soil  The direction of the applied load
  • 45.  The process of forcing the piles into the ground without excavation is termed as the pile driving.  The piles should be driven vertically.  However, a tolerance of eccentricity of 2% of the pile length is permissible.  The eccentricity is measured by means of plumb bob.  The hammer is guided between two parallel steel members known as leads.
  • 47.  Drop hammer.  Single acting hammer.  Double acting hammer.  Diesel hammer.  Vibratory hammer.
  • 49.  Low operation  Low equipment cost  Simple
  • 50.  A hammer (or ram or monkey) is raised by winch and allowed to fall or drop by gravity on the top of the pile.  The drop hammer is provided with lugs so that it can slide in the leads.  A lifting eye or hook is provided to tie it with the rope.  The weight of drop hammer varies from 0.5 to 2 tones (5 to 20 kN).  The height of fall may vary from 1.5 to 3 meters.  The number of blows that can be imparted varies from 4 to 8 per minute.
  • 51.  If the hammer is raised by steam, compressed air or internal combustion, but is allowed to fall by gravity along, it is called a single acting hammer.  The energy of such hammer is equal to the weight of the ram times the height of fall.  The weight of single acting hammer is about 2 tonnes (20kN).  The fall is about 1 meter.  the number of blows of the hammer may vary from 50 to 60 per minute.
  • 53.  The double acting hammer employs steam or air for lifting the ram and for accelerating the downward stroke.  The weight of the hammer is only 500 kg (5 kN) but because of accelerating effect of steam (or air) pressure, it has an effect of a weight of 3 tonnes (30.kN).  It operates with succession of rapid blows,the number varying from 100 to 200 blows perminute.  For light hammers, the number of blows may be even as high as 300 per minute.  The pile driving is very quick.  These hammers are very useful for driving piles under water.
  • 54. 59
  • 55.  The total driving energy is the sum of the impact of the ram plus the energy delivered by explosion.  The diesel hammer is a small, light weight self-contained and self-acting type, using gasoline for fuel.
  • 56.
  • 57.  If the driving has to be carried out by hammer, then following factors should be take into consideration.  The size and weight of the pile.  The driving resistance which has to be overcome to achieve the desired penetration.  The available space and head room in the site because the hammer has to be dropped from certain height.  The availability of cranes.  The noise restrictions which may be in force in the locality.
  • 58.  The ultimate load carrying capacity, or ultimate bearing capacity (Qf) of a pile is defined as the maximum load which can be carried by a pile and at which the pile continues to sink without further increase of load.  The allowable load Qa is the safe load which the pile can carry safely and is determined on the basis of  Ultimate bearing, resistance divided by appropriate factor of safety.  The permissible settlement,  Overall stability of the pile foundation.  The load carrying capacity of a pile can be determined by the following methods.  Dynamic formulae  Static formulae
  • 59.  Used for precast concrete piles.  When a pile hammer hits the pile, the total driving energy is equal to the weight of hammer times the height of drop or stroke.  In addition to this, in the case of double acting hammers, some energy is also imparted by the steam pressure during the return stroke.  The total downward energy is consumed by the work done in penetrating the pile and by certain losses.  The various dynamic formulae are essentially based on this assumption.
  • 60. Engineering New Formula: Qa = allowable load W = weight of hammer (KG) H = height of fall (CM) F = factor of safety = 6 S = final set (penetration) per blow, (Usually taken as average penetration, cm per blow for the last 5 Blows of hammer or last 20 blows for steam hammer.) C = empirical constant. = 2.5 cm for drop hammers, and = 0.25 hammers. For single acting steam hammer For drop hammer cm for single or double acting For double acting hammer a= effective area of piston (cm2) P=mean effective steam pressure (kg/cm
  • 61. Hiley's Formula (IS formula):  Indian standard IS: 2911(Part I): 1964 gives the following formula based on original expression by Hiley : Qf = ultimate load on pile. W = weight of hammer in kg H = height on drop of hammer, in cm S = penetration or set, in cm, per blow C = total elastic compression= C1 + C2 + C3 C1,C2, C3 = temporary elastic compression of dolly and packing, pile and soil respectively. h = efficiency of hammer, variable from 65 percent for same double acing steam hammers to 100 percent for drop hammers released by trigger. b = efficiency of hammer blows (i.e. ratio of the energy after impact to striking energy of ram).
  • 62.  The static formulae are based on the assumption that the ultimate bearing capacity Qf of a pile is the sum of the total ultimate skin friction Rf and total ultimate point or end bearing resistance Rp. As = surface area of pile upon which the skin friction acts Ap = area of cross-section of the pile on which bearing resistance acts. For tapered piles, Ap may be taken as the cross-sectional area at the lower one-third of the embedded length. rf = average unit skin friction, which may be taken equal to unit cohesion for cohesive soils. rp = unit point or toe resistance, which may be taken as 9c for cohesive soils.
  • 63. 63