SlideShare a Scribd company logo
1
STUDY IN RISK MANAGEMENT
OF STEEL PLANT PROJECTS
PRESENTED BY :-
DILPREET SINGH
NICMAR PEM-9 (2013-15)
2
OVERVIEW
 INTRODUCTION
 REVIEW OF LITERATURE
 RESEARCH METHODOLOGY
METHOD - I (Quantitative Analysis)
METHOD - II (Qualitative Analysis)
 FINDINGS FROM METHOD I & II
 CONCLUSION
 LIMITATIONS
 REFERENCES 3
INTRODUCTION
 The Steel industry is being faced by myriad challenges such as
volatility, shifting demand centers, complex supply chains,
productivity and cost efficiency.
 It incorporates different phases of steel plant projects such as
Development phase, Execution phase and Operation phase.
 The scope of study includes qualitative and quantitative
analysis which helps in consolidating decision making under
uncertainty.
4
5
S.No. Company Location State
Current
approximate
Capacity*
1 Steel Authority of India Limited IISCO, Burnpur West Bengal 0.5
2 Steel Authority of India Limited Bokaro Jharkhand 4.36
3 Steel Authority of India Limited Bhilai Chhattisgarh 3.93
4 Steel Authority of India Limited Rourkela Orissa 1.9
5 Steel Authority of India Limited Durgapur West Bengal 1.8
6 RashtriyaIspat Nigam Limited Visakhapatanam Andhra Aradesh 2.9
7 Tata Steel Limited Jamshedpur Jharkhand 6.8
8 Essar Steel Limited Hazira Gujarat 4.6
9 JSW Steel Limited Vijayanagar Karnataka 6.6
10 Jindal Steel & Power Limited Raigarh Chhattisgarh 2.4
11 Ispat Industries Limited Dolvi Maharastra 3
12 Bhushan Power & Steel Limited Jharsugda Orissa 1.2
13 Bhushan Steel Limited Angul-Dhenkanal Orissa 1.56
NUMBERS OF STEEL PLANT IN INDIA WITH THEIR CAPACITY
SOURCE: http://pib.nic.in/newsite/erelease.aspx?relid=77494
OBJECTIVES
 To study the risks involved in Steel Plant Project and to
identify the benefits of application of the risk management.
 To identify the principles of Risk Management.
 To find the most critical risks which were quantified with the
help of @RISK software and as per the tornedo chart the
results are interpreted. .
 To assess and mitigate the risk involved in Steel Plant Projects
and arriving at a conclusion
7
REVIEW OF LITERATURE
 Steel demand and production outlook for indian steel.
 Steel consumption scenarios.
 Global outlook for Steel.
8
PROJECT RISK MANAGEMENT
PROCESS
9
QUANTITATIVE ANALYSIS
 Questionnaire
 Risk Rating
 Responses
 Tornado Graph
 Interpretation
 Identification of critical risks
 Mitigation Plans
10
VARIABLES
11
  Development Phase
1 Significant swings in the demand for steel.
2
Decline in Profit Margin in downstream
processing.
3 Difficulties in financing project.
4 Unrealistic contract duration.
5 Scarcity of raw materials.
6 Market risk.
7 Political risk.
8 Delay in land acquisition.
9 Delay in obtaining permissions.
10 Energy Scarcity Risks.
11 Risk of Exchange Rate Fluctuations
12 Business Competition Risk.
CONTINUED…..
  Construction Phase
13 Lack of decision making involving all project teams.
14 Unforeseen ground conditions.
15 Change in soil condition.
16 Lack of technical feasibility.
17 Changes in rules & regulations.
18 Severe weather conditions.
19 Safety Risk.
20 Non-availability of utilities on site.
21 Lack of effeicient technology.
22 Inadequate code provision.
23 Delay in payments by owner.
24 Delay in supply of equipments
25 Lack of information available.
26 Non-availability of utilities on site.
27 Failure of construction equipment.
28 Interrupted cash flow.
12
CONTINUED…..
 
Operation Phase
29 Fuel supply risk.
30 Improper estimation for maintenance&operationcost.
31 Overproduction of steel.
32 Incorrect manufacturing processes.
33 Ineffecient quality standards.
34 Inadequate safety measures.
35 Ineffeciency of subcontractor company.
13
WHY @RISK SOFTWARE
 Uses monte carlo simulation
 Shows many possible outcomes for a problem
under consideration
 It tracks many possible future scenarios,
 Its probability
 The risks associated with each different
scenarios.
 Allows the user to judge upon the risks which one
to take or which one to avoid
14
MONTE CARLO SIMULATION
A computerized mathematical technique
For quantitative analysis
For decision making
Generates all the possible outcomes
With their impact of risk
15
@RISK FLOW
CHART
16
TORNADO CHART
 Shows the spread of every parameter.
 Gives the critical parameters carrying the high potential
of uncertainty.
 The tornado spread gives the critical parameter.
17
TORNADO CHART
18
FINDINGS
 Critical parameters:
 Significant swings in the demand of steel
(Development phase)
 Decline in profit margin in the downstream
process(Development phase)
 Unforeseen ground conditions(Construction
Phase)
 Difficulty in financing project(Development
Phase)
 Delay in obtaining permission.(Development
Phase)
19
QUALITATIVE ANALYSIS
Phase Of Project Risk Involved
IISCO,Burnpu
r
JINDAL SAW
LTD,Mundra
SUNFLAG
STEEL
,Bhandara
DEVELOPMENT PHASE
DEFAULT IN MOU      
1.default in mou provisions by
government
Y    
DELAY IN LAND ACQUISITION:      
1. political interference/patronage   Y  
2.policy restriction for change in land
use pattern
Y    
PERMIT/APPROVAL RISK:      
1.delay in contractual clearances Y   Y
2.delay in project specific
orders/approvals
     
3.delay in statutory
clearance(environmental, forest, etc)
Y Y Y
4.improper feasibility report,
documentations
     
MARKET RISKS      
1.Drastic change in market.      
2.Competitors threat.      
FINANCIAL RISK      
1.project cost overrun Y    
2.project not bankable   Y  
3.failure to arrange equity in time     Y
DELAY RISKS      
1. Delay in submission of drawing Y    
2.Delay in handing over the site to
contractors
Y Y  
3. Delay in mobilizing the required
resources in time
  Y  
4. Co-ordination and managerial
     
20
Phase Of Project Risk Involved
IISCO,Burnpu
r
JINDAL SAW
LTD,Mundra
SUNFLAG
STEEL ,Bhandara
CONSTRUCTION PHASE
TECHNOLOGY RISK      
1. lack of technical feasibility.      
2. technology failure   Y  
DESIGN RISK      
1.Design changes Y Y  
2.loss due to faulty design Y    
3. Delays due to submission and
approval of design and drawing
     
4.insufficient design documentation      
DELAYS DUE TO UNBALANCED
CONTRACT
     
1. Risk is unilaterally transferred to
one side.
    Y
2.change in scope of project      
3. Delay in settlement of claim      
4.Delay in arbitration proceedings
during the execution of project.
Y    
5.Delay in settlement of rates for
extra items, additional items and
revision of rates.
     
OTHER RISKS      
1.Co-ordination and managerial
problems of the owner.
     
2.Delay in issue of drawings by the
owner in construction contracts.
Y   Y
3. Health hazards and non-
availability of medical facilities.
     
4.Political problems, riots, agitations Y Y  
5. Inter-state disputes.      
6.Delay in releasing payments leading
to cash-flow problems to the
contractors.
     
7.Local problems, obstruction by local
Y    
21
Phase Of Project Risk Involved
IISCO,Bur
npur
JINDAL SAW
LTD,Mundra
SUNFLAG
STEEL
,Bhandara
OPERATION PHASE
OPERATION RISK:      
1.Transportation risks      
2.improper estimation for
maintenance and operation
cost
Y Y  
3.Poor workmanship      
4.Poor quality      
5.Non availability of man,
material, machinery,
money
     
6.Lack of political will      
7.Breakdown Problems   Y  
 
8.Lack of management
expertise      
 
9.Non sequential supply of
equipments Y    
 
10.Non availability of spares
in stores   Y  
22
CONCLUSION
 Qualitative and Quantitative have given the same
results and hence the methodology can be validated.
 The research methodology can be taken as a
reference for further research work in Steel Plant
project or in similar researches for other
infrastructure projects.
 Most of the risks that are identified and which have
to be mitigated are from development phase .These
risks are to be taken into considerations for future
steel plant projects
23
THANK YOU.
24

More Related Content

What's hot

Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)Serdar Temiz
 
Risk Management Plan Analysis PowerPoint Presentation Slides
Risk Management Plan Analysis PowerPoint Presentation Slides Risk Management Plan Analysis PowerPoint Presentation Slides
Risk Management Plan Analysis PowerPoint Presentation Slides
SlideTeam
 
Risk assessment plan example
Risk assessment plan exampleRisk assessment plan example
Risk assessment plan example
Јелена Добановачки
 
Project risk analysis
Project risk analysisProject risk analysis
Project risk analysis
Akanksha Sinha
 
Project charter presentation
Project charter presentationProject charter presentation
Project charter presentation
Kunal Gudwani
 
Sample Due diligence report
Sample Due diligence reportSample Due diligence report
Sample Due diligence reportRohit Pinto
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
Aswin prakash i , Xantus Technologies
 
Quality Control Proposal
Quality Control ProposalQuality Control Proposal
Quality Control Proposal
Maia Reshef
 
Project Risk Management - PMBOK5
Project Risk Management - PMBOK5Project Risk Management - PMBOK5
Project Risk Management - PMBOK5
pankajsh10
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
SAJJAD KHUDHUR ABBAS
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
Markos Mulat G
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
Kris Kimmerle
 
Project Management Methodology
Project Management MethodologyProject Management Methodology
Project Management Methodology
Mohammed Al-Taee
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
Barun_agnihotri
 
Project Risk Management
Project Risk ManagementProject Risk Management
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
claimsconsultancy
 
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Divyanshu Dayal
 
Project management-Report
Project management-ReportProject management-Report
Project management-Report
SYEDA KANWAL NOREEN
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
Mohamed Loey
 

What's hot (20)

Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)
 
Risk Management Plan Analysis PowerPoint Presentation Slides
Risk Management Plan Analysis PowerPoint Presentation Slides Risk Management Plan Analysis PowerPoint Presentation Slides
Risk Management Plan Analysis PowerPoint Presentation Slides
 
Risk assessment plan example
Risk assessment plan exampleRisk assessment plan example
Risk assessment plan example
 
Project risk analysis
Project risk analysisProject risk analysis
Project risk analysis
 
Project charter presentation
Project charter presentationProject charter presentation
Project charter presentation
 
Sample Due diligence report
Sample Due diligence reportSample Due diligence report
Sample Due diligence report
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
 
Quality Control Proposal
Quality Control ProposalQuality Control Proposal
Quality Control Proposal
 
Project Risk Management - PMBOK5
Project Risk Management - PMBOK5Project Risk Management - PMBOK5
Project Risk Management - PMBOK5
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Project Management Methodology
Project Management MethodologyProject Management Methodology
Project Management Methodology
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
 
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
 
Project management-Report
Project management-ReportProject management-Report
Project management-Report
 
Financial feasibility of a new business
Financial feasibility of a new businessFinancial feasibility of a new business
Financial feasibility of a new business
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
 

Viewers also liked

Risk Assessment
Risk Assessment Risk Assessment
Risk Assessment
Sri Ram Srinivas Dudala
 
Summer Internship Presentation
Summer Internship PresentationSummer Internship Presentation
Summer Internship Presentation
Piyush Verma
 
BHP-RISK ASSESSMENT - DALF R1
BHP-RISK ASSESSMENT - DALF R1BHP-RISK ASSESSMENT - DALF R1
BHP-RISK ASSESSMENT - DALF R1Dennis J Morgan
 
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
pierdole
 
Nebosh unit ic questions matrix - ans
Nebosh unit ic questions matrix - ansNebosh unit ic questions matrix - ans
Nebosh unit ic questions matrix - ans
Mumtaz A. Khan CMIOSH, IDipNEBOSH
 
Blast furnace presentation
Blast furnace presentation Blast furnace presentation
Blast furnace presentation
Muzzamil Eatoo
 
Fmc close out repot hse dept. rev.000
Fmc close out repot hse dept. rev.000Fmc close out repot hse dept. rev.000
Fmc close out repot hse dept. rev.000
Fitri Ifony
 
Operational Risk Management
Operational Risk ManagementOperational Risk Management
Operational Risk Managementarsqureshi
 
Risk assessment for blast furnace using fmea
Risk assessment for blast furnace using fmeaRisk assessment for blast furnace using fmea
Risk assessment for blast furnace using fmea
eSAT Publishing House
 
Manufacturing of steel
Manufacturing of steelManufacturing of steel
Manufacturing of steel
Cholan PK
 

Viewers also liked (10)

Risk Assessment
Risk Assessment Risk Assessment
Risk Assessment
 
Summer Internship Presentation
Summer Internship PresentationSummer Internship Presentation
Summer Internship Presentation
 
BHP-RISK ASSESSMENT - DALF R1
BHP-RISK ASSESSMENT - DALF R1BHP-RISK ASSESSMENT - DALF R1
BHP-RISK ASSESSMENT - DALF R1
 
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
 
Nebosh unit ic questions matrix - ans
Nebosh unit ic questions matrix - ansNebosh unit ic questions matrix - ans
Nebosh unit ic questions matrix - ans
 
Blast furnace presentation
Blast furnace presentation Blast furnace presentation
Blast furnace presentation
 
Fmc close out repot hse dept. rev.000
Fmc close out repot hse dept. rev.000Fmc close out repot hse dept. rev.000
Fmc close out repot hse dept. rev.000
 
Operational Risk Management
Operational Risk ManagementOperational Risk Management
Operational Risk Management
 
Risk assessment for blast furnace using fmea
Risk assessment for blast furnace using fmeaRisk assessment for blast furnace using fmea
Risk assessment for blast furnace using fmea
 
Manufacturing of steel
Manufacturing of steelManufacturing of steel
Manufacturing of steel
 

Similar to “Study in Risk Management of Steel Plant Projects”

Excelsior presentation
Excelsior presentationExcelsior presentation
Excelsior presentation
Shawn Westcott
 
The significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential projectThe significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential project
IOSR Journals
 
Capacity Expansion Banes in Indian Steel Industry
Capacity Expansion Banes in Indian Steel IndustryCapacity Expansion Banes in Indian Steel Industry
Capacity Expansion Banes in Indian Steel Industry
Dr. Amarjeet Singh
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
B012140812
B012140812B012140812
B012140812
IOSR Journals
 
CRU World Copper Conference 2017
CRU World Copper Conference 2017CRU World Copper Conference 2017
CRU World Copper Conference 2017
TeckResourcesLtd
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
iosrjce
 
I012646171
I012646171I012646171
I012646171
IOSR Journals
 
I012646171
I012646171I012646171
I012646171
IOSR Journals
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delay
Est
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
IRJET Journal
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
Rick Vogel
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET Journal
 
Strategic Resources - Corporate Presentation December 2023
Strategic Resources - Corporate Presentation December 2023Strategic Resources - Corporate Presentation December 2023
Strategic Resources - Corporate Presentation December 2023
AdnetNew
 
Rubicon Minerals 2018 Fact Sheet
Rubicon Minerals 2018 Fact SheetRubicon Minerals 2018 Fact Sheet
Rubicon Minerals 2018 Fact Sheet
Rubicon Minerals Corporation
 
Strategic Resources - Corporate Presentation October 2023
Strategic Resources - Corporate Presentation October 2023Strategic Resources - Corporate Presentation October 2023
Strategic Resources - Corporate Presentation October 2023
Adnet Communications
 
Identification of Project Risks & Risk Breakdown Structure In Manufacture of ...
Identification of Project Risks & Risk Breakdown Structure In Manufacture of ...Identification of Project Risks & Risk Breakdown Structure In Manufacture of ...
Identification of Project Risks & Risk Breakdown Structure In Manufacture of ...
IJERA Editor
 
Strategic Resources Corporate Presentation
Strategic Resources Corporate PresentationStrategic Resources Corporate Presentation
Strategic Resources Corporate Presentation
Adnet Communications
 

Similar to “Study in Risk Management of Steel Plant Projects” (20)

Excelsior presentation
Excelsior presentationExcelsior presentation
Excelsior presentation
 
The significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential projectThe significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential project
 
Capacity Expansion Banes in Indian Steel Industry
Capacity Expansion Banes in Indian Steel IndustryCapacity Expansion Banes in Indian Steel Industry
Capacity Expansion Banes in Indian Steel Industry
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
B012140812
B012140812B012140812
B012140812
 
CRU World Copper Conference 2017
CRU World Copper Conference 2017CRU World Copper Conference 2017
CRU World Copper Conference 2017
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delay
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
 
Strategic Resources - Corporate Presentation December 2023
Strategic Resources - Corporate Presentation December 2023Strategic Resources - Corporate Presentation December 2023
Strategic Resources - Corporate Presentation December 2023
 
Rubicon Minerals 2018 Fact Sheet
Rubicon Minerals 2018 Fact SheetRubicon Minerals 2018 Fact Sheet
Rubicon Minerals 2018 Fact Sheet
 
Strategic Resources - Corporate Presentation October 2023
Strategic Resources - Corporate Presentation October 2023Strategic Resources - Corporate Presentation October 2023
Strategic Resources - Corporate Presentation October 2023
 
Identification of Project Risks & Risk Breakdown Structure In Manufacture of ...
Identification of Project Risks & Risk Breakdown Structure In Manufacture of ...Identification of Project Risks & Risk Breakdown Structure In Manufacture of ...
Identification of Project Risks & Risk Breakdown Structure In Manufacture of ...
 
Strategic Resources Corporate Presentation
Strategic Resources Corporate PresentationStrategic Resources Corporate Presentation
Strategic Resources Corporate Presentation
 

Recently uploaded

Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 

Recently uploaded (20)

Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 

“Study in Risk Management of Steel Plant Projects”

  • 1. 1
  • 2. STUDY IN RISK MANAGEMENT OF STEEL PLANT PROJECTS PRESENTED BY :- DILPREET SINGH NICMAR PEM-9 (2013-15) 2
  • 3. OVERVIEW  INTRODUCTION  REVIEW OF LITERATURE  RESEARCH METHODOLOGY METHOD - I (Quantitative Analysis) METHOD - II (Qualitative Analysis)  FINDINGS FROM METHOD I & II  CONCLUSION  LIMITATIONS  REFERENCES 3
  • 4. INTRODUCTION  The Steel industry is being faced by myriad challenges such as volatility, shifting demand centers, complex supply chains, productivity and cost efficiency.  It incorporates different phases of steel plant projects such as Development phase, Execution phase and Operation phase.  The scope of study includes qualitative and quantitative analysis which helps in consolidating decision making under uncertainty. 4
  • 5. 5
  • 6. S.No. Company Location State Current approximate Capacity* 1 Steel Authority of India Limited IISCO, Burnpur West Bengal 0.5 2 Steel Authority of India Limited Bokaro Jharkhand 4.36 3 Steel Authority of India Limited Bhilai Chhattisgarh 3.93 4 Steel Authority of India Limited Rourkela Orissa 1.9 5 Steel Authority of India Limited Durgapur West Bengal 1.8 6 RashtriyaIspat Nigam Limited Visakhapatanam Andhra Aradesh 2.9 7 Tata Steel Limited Jamshedpur Jharkhand 6.8 8 Essar Steel Limited Hazira Gujarat 4.6 9 JSW Steel Limited Vijayanagar Karnataka 6.6 10 Jindal Steel & Power Limited Raigarh Chhattisgarh 2.4 11 Ispat Industries Limited Dolvi Maharastra 3 12 Bhushan Power & Steel Limited Jharsugda Orissa 1.2 13 Bhushan Steel Limited Angul-Dhenkanal Orissa 1.56 NUMBERS OF STEEL PLANT IN INDIA WITH THEIR CAPACITY SOURCE: http://pib.nic.in/newsite/erelease.aspx?relid=77494
  • 7. OBJECTIVES  To study the risks involved in Steel Plant Project and to identify the benefits of application of the risk management.  To identify the principles of Risk Management.  To find the most critical risks which were quantified with the help of @RISK software and as per the tornedo chart the results are interpreted. .  To assess and mitigate the risk involved in Steel Plant Projects and arriving at a conclusion 7
  • 8. REVIEW OF LITERATURE  Steel demand and production outlook for indian steel.  Steel consumption scenarios.  Global outlook for Steel. 8
  • 10. QUANTITATIVE ANALYSIS  Questionnaire  Risk Rating  Responses  Tornado Graph  Interpretation  Identification of critical risks  Mitigation Plans 10
  • 11. VARIABLES 11   Development Phase 1 Significant swings in the demand for steel. 2 Decline in Profit Margin in downstream processing. 3 Difficulties in financing project. 4 Unrealistic contract duration. 5 Scarcity of raw materials. 6 Market risk. 7 Political risk. 8 Delay in land acquisition. 9 Delay in obtaining permissions. 10 Energy Scarcity Risks. 11 Risk of Exchange Rate Fluctuations 12 Business Competition Risk.
  • 12. CONTINUED…..   Construction Phase 13 Lack of decision making involving all project teams. 14 Unforeseen ground conditions. 15 Change in soil condition. 16 Lack of technical feasibility. 17 Changes in rules & regulations. 18 Severe weather conditions. 19 Safety Risk. 20 Non-availability of utilities on site. 21 Lack of effeicient technology. 22 Inadequate code provision. 23 Delay in payments by owner. 24 Delay in supply of equipments 25 Lack of information available. 26 Non-availability of utilities on site. 27 Failure of construction equipment. 28 Interrupted cash flow. 12
  • 13. CONTINUED…..   Operation Phase 29 Fuel supply risk. 30 Improper estimation for maintenance&operationcost. 31 Overproduction of steel. 32 Incorrect manufacturing processes. 33 Ineffecient quality standards. 34 Inadequate safety measures. 35 Ineffeciency of subcontractor company. 13
  • 14. WHY @RISK SOFTWARE  Uses monte carlo simulation  Shows many possible outcomes for a problem under consideration  It tracks many possible future scenarios,  Its probability  The risks associated with each different scenarios.  Allows the user to judge upon the risks which one to take or which one to avoid 14
  • 15. MONTE CARLO SIMULATION A computerized mathematical technique For quantitative analysis For decision making Generates all the possible outcomes With their impact of risk 15
  • 17. TORNADO CHART  Shows the spread of every parameter.  Gives the critical parameters carrying the high potential of uncertainty.  The tornado spread gives the critical parameter. 17
  • 19. FINDINGS  Critical parameters:  Significant swings in the demand of steel (Development phase)  Decline in profit margin in the downstream process(Development phase)  Unforeseen ground conditions(Construction Phase)  Difficulty in financing project(Development Phase)  Delay in obtaining permission.(Development Phase) 19
  • 20. QUALITATIVE ANALYSIS Phase Of Project Risk Involved IISCO,Burnpu r JINDAL SAW LTD,Mundra SUNFLAG STEEL ,Bhandara DEVELOPMENT PHASE DEFAULT IN MOU       1.default in mou provisions by government Y     DELAY IN LAND ACQUISITION:       1. political interference/patronage   Y   2.policy restriction for change in land use pattern Y     PERMIT/APPROVAL RISK:       1.delay in contractual clearances Y   Y 2.delay in project specific orders/approvals       3.delay in statutory clearance(environmental, forest, etc) Y Y Y 4.improper feasibility report, documentations       MARKET RISKS       1.Drastic change in market.       2.Competitors threat.       FINANCIAL RISK       1.project cost overrun Y     2.project not bankable   Y   3.failure to arrange equity in time     Y DELAY RISKS       1. Delay in submission of drawing Y     2.Delay in handing over the site to contractors Y Y   3. Delay in mobilizing the required resources in time   Y   4. Co-ordination and managerial       20
  • 21. Phase Of Project Risk Involved IISCO,Burnpu r JINDAL SAW LTD,Mundra SUNFLAG STEEL ,Bhandara CONSTRUCTION PHASE TECHNOLOGY RISK       1. lack of technical feasibility.       2. technology failure   Y   DESIGN RISK       1.Design changes Y Y   2.loss due to faulty design Y     3. Delays due to submission and approval of design and drawing       4.insufficient design documentation       DELAYS DUE TO UNBALANCED CONTRACT       1. Risk is unilaterally transferred to one side.     Y 2.change in scope of project       3. Delay in settlement of claim       4.Delay in arbitration proceedings during the execution of project. Y     5.Delay in settlement of rates for extra items, additional items and revision of rates.       OTHER RISKS       1.Co-ordination and managerial problems of the owner.       2.Delay in issue of drawings by the owner in construction contracts. Y   Y 3. Health hazards and non- availability of medical facilities.       4.Political problems, riots, agitations Y Y   5. Inter-state disputes.       6.Delay in releasing payments leading to cash-flow problems to the contractors.       7.Local problems, obstruction by local Y     21
  • 22. Phase Of Project Risk Involved IISCO,Bur npur JINDAL SAW LTD,Mundra SUNFLAG STEEL ,Bhandara OPERATION PHASE OPERATION RISK:       1.Transportation risks       2.improper estimation for maintenance and operation cost Y Y   3.Poor workmanship       4.Poor quality       5.Non availability of man, material, machinery, money       6.Lack of political will       7.Breakdown Problems   Y     8.Lack of management expertise         9.Non sequential supply of equipments Y       10.Non availability of spares in stores   Y   22
  • 23. CONCLUSION  Qualitative and Quantitative have given the same results and hence the methodology can be validated.  The research methodology can be taken as a reference for further research work in Steel Plant project or in similar researches for other infrastructure projects.  Most of the risks that are identified and which have to be mitigated are from development phase .These risks are to be taken into considerations for future steel plant projects 23