This document analyzes the causes of delay in the construction of bridge girders for three spans of a major bridge across the Sabarmati River in Gandhinagar, Gujarat, India. Data was collected on the planned versus actual construction schedules. The total delay was found to be 75 days, with various activities like staging work, shuttering work, and reinforcement fixing experiencing delays. Major causes of delay included insufficient equipment capacity, lack of materials and skilled labor, delays in design drawings, poor site management, and labor issues. The contractor was found to be primarily responsible for these delays through inadequate site planning, labor inefficiencies, and lack of supervision and expertise.