SlideShare a Scribd company logo
1a. 1b 1c. 1d. 2a. 2b. 2c. 3a 3b
S/N Work activity Hazard Possible Accident/ Ill health to
persons, fire or property loss
Severity Likelihood RPN* Additional Risk Control Measures Remarks
D1 Design Errors and Omissions
Delay in construction and
installation of equipment
4 3 12
Design Review by Lead Engineers in
all Disciplines
D2
Failure to carry out the works in
accordance with the contract
Construction Deadline
Extension
3 3 9
Carefully Review of Contract Terms,
engage more people and
equipment
EX1 Laws and local standards change Interruption in construction 3 1 3
Constant review of standards and
laws by QM Engineer
EX2 Climate Conditions
Delay in Tasks, Impact on
Health of Personnel
4 3 12
Planning Tasks and Deadlines
according to Climate Conditions
EX3 Tax change Budget Overruns 4 1 4 Include this in Contract
EX4 Contracting
Long Delays in Contract Negotiations or
Award
Delay of Construction 4 4 16 Move Construction Deadline
EN1 Environmental analysis incomplete Delay in Permit Obtaining 4 2 8 Engage local experts
EN2
Laws and environmental standards
change
Delay in Permit Obtaining 3 1 3
Constant review of standards and
laws by QM Engineer
EN3
New alternatives required to avoid,
mitigate or minimize environmental
impact
Delay in Permit Obtaining 4 2 8 Engage local experts
O1
Inexperienced workforce and staff
turnover
Skill shortage 3 3 9
Conduct technical training or
workshop to increase local
workforce skill and knowledge
O2 Lack of protection on a construction site
Incidents and Accidents -
Labour and Equipment
2 1 2
HSEQ Weekly Supervising and HSEQ
Training of Personnel
O3 Procurement Delayed deliveries
Delay in Installation of
Equipment
3 3 9
Choosing Local Vendor with Short
Delivery Time
O4 Commissioning Delayed commissioning
Delay in completing of all
parts of line
4 2 8
Choosing Competent Working
Commission and Project Control
Engineer
PM1 Project Quality Control
Failure to comply with contractual quality
requirements
Accidents with equipment 3 3 9
Continuous Quality Control of all
Project Activities and Assets
PM2 Scheduling and Planning Scheduling errors, contractor delays
Accidents with personnel in
attempt to perform tasks
faster
4 2 8
Planning Carefully, Engage more
workers for some activities
PM3 Choosing Project Team Project team conflict
Accidents with personnel and
assets
3 2 6
Carefully choose personnel, Team
Building Activities
R1 Obtain Required Design Permits Expired temporary construction permits
Stop of construction work by
regulatory bodies
4 1 4
Continuous control of all permits
and regulatory acts and promptly
react to any change
R2
Engineering, Construction
Related Engineering and
Adaptation of the drawings
Contradictions in the construction
documents
Delay in construction works,
possible property losses
4 3 12
Review of all design drawings by
Design Supervisor and Correction of
all contradictions, as well as all
calculations
C1 Construction cost overruns Budget Overruns 4 4 16
Cost Control Engineer Day-to-Day
tracking of all Site Costs and On-
Time warning of possible Budget
Overruns
C2 Technology changes Project Late, Budget Overruns 4 2 8
Choosing latest technology before
construction start, if client change
technology during construction,
insist on Scope of Change and
Changing Schedule and Budget
*RPN - Risk Prioritization Number
RISK ASSESSMENT PLAN
Department & Exact Location Of The Work Performed: Project / Work Description:
Risk Assessment Team (Name/s): Approved By Supervisor / Reporting Officer:
(Name, Date & Signature)
Date Conducted: Next Review Date:
Hazard Identification Risk Assessment Risk Control
DESIGN RISKS
EXTERNAL RISKS
ENVIRONMENTAL RISKS
ORGANIZATIONAL RISKS
Construction
Construction
PROJECT MANAGEMENT RISKS
RIGHT OF WAY RISKS
CONSTRUCTION RISKS
Project Design
Construction
Obtain Environment Emission
Permit
Risk Assessment Matrix
Risk level Determination - 5 x 5 Matrix
Critical
(5)
Very Serious
(4)
Serious
(3)
Marginal
(2)
Negligible
(1)
Frequent
(5)
Moderate
(4)
EX4
Occasional
(3)
D1, EX2, R2 D2, O1, O3, PM1
Remote
(2)
EN1, EN3, O4,
PM2, C2
PM3
Unlikely
(1)
EX3, R1 EX1, EN2 O2
Action Table
Colour Score Risks
16 - 25 High
12 - 15 Warning
8 -10 Medium
1 - 6 Warning
SEVERITY
LIKELIHOOD
Take remedial action at appropriate time
Proceed with care. Additional control is advised. Review shall be
implemented within 30 days.
Risk acceptable: Residual risk
If possible, risk reduction should be further considered,
particularly severity.
There are no imminent dangers. Frequent review shall be in place
especially changes in procedures, materials or environment.
Action
Operation not Permissible
Stop operation & review controls. If necessary abort
experimentation.
High priority remedial action
Proceed with extreme caution with PI present at all times.
Implement additional (secondary) controls immediately. Review
within 7 days. Emergency control measures shall be in place.

More Related Content

What's hot

Project integration management
Project integration management Project integration management
Project integration management
KU Leuven
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11
PMA Consultants
 
Pmbok6 to 7 transformation
Pmbok6 to 7 transformationPmbok6 to 7 transformation
Pmbok6 to 7 transformation
Zaur Ahmadov, PMP
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
Loay Ghazaleh MBA, BSc Civil Eng.
 
Construction project management
Construction project managementConstruction project management
Construction project management
saif hasan
 
Bid Evaluation
Bid EvaluationBid Evaluation
Bid Evaluation
Vj NiroSh
 
Project management procurement
Project management  procurementProject management  procurement
Project management procurement
Malcolm Peart
 
PMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th EditionPMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th Edition
Ricardo Viana Vargas
 
PMP - Risk Management plan & template
PMP - Risk Management plan & templatePMP - Risk Management plan & template
PMP - Risk Management plan & template
Allie Gentry
 
Governance - Project Management Office Professional Services
Governance - Project Management Office Professional ServicesGovernance - Project Management Office Professional Services
Governance - Project Management Office Professional Services
Mark S. Mahre
 
construction project planing
 construction project planing construction project planing
construction project planing
SANJEEV Wazir
 
Advanced Work Packaging in Construction: An Introduction
Advanced Work Packaging in Construction: An IntroductionAdvanced Work Packaging in Construction: An Introduction
Advanced Work Packaging in Construction: An Introduction
The Advanced Work Packaging Institute
 
PMP Process Chart - 6th Edition
PMP Process Chart - 6th EditionPMP Process Chart - 6th Edition
PMP Process Chart - 6th Edition
Nasser Al mohimeed,PMP
 
Excel Project Management
Excel Project ManagementExcel Project Management
Excel Project Management
project management
 
Introduction to contract management
Introduction to contract managementIntroduction to contract management
Introduction to contract management
Berkman Solutions
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
Agus Suhanto
 
Pre bid meeting presentation
Pre bid meeting presentationPre bid meeting presentation
Pre bid meeting presentation
Riaz Zalil
 
Avenew Project Management Fundamental
Avenew Project Management FundamentalAvenew Project Management Fundamental
Avenew Project Management Fundamental
AVENEW INDONESIA
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
Francis Ho
 
Procurement management
Procurement managementProcurement management
Procurement management
Mostafa Elgamala
 

What's hot (20)

Project integration management
Project integration management Project integration management
Project integration management
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11
 
Pmbok6 to 7 transformation
Pmbok6 to 7 transformationPmbok6 to 7 transformation
Pmbok6 to 7 transformation
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Bid Evaluation
Bid EvaluationBid Evaluation
Bid Evaluation
 
Project management procurement
Project management  procurementProject management  procurement
Project management procurement
 
PMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th EditionPMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th Edition
 
PMP - Risk Management plan & template
PMP - Risk Management plan & templatePMP - Risk Management plan & template
PMP - Risk Management plan & template
 
Governance - Project Management Office Professional Services
Governance - Project Management Office Professional ServicesGovernance - Project Management Office Professional Services
Governance - Project Management Office Professional Services
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Advanced Work Packaging in Construction: An Introduction
Advanced Work Packaging in Construction: An IntroductionAdvanced Work Packaging in Construction: An Introduction
Advanced Work Packaging in Construction: An Introduction
 
PMP Process Chart - 6th Edition
PMP Process Chart - 6th EditionPMP Process Chart - 6th Edition
PMP Process Chart - 6th Edition
 
Excel Project Management
Excel Project ManagementExcel Project Management
Excel Project Management
 
Introduction to contract management
Introduction to contract managementIntroduction to contract management
Introduction to contract management
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
Pre bid meeting presentation
Pre bid meeting presentationPre bid meeting presentation
Pre bid meeting presentation
 
Avenew Project Management Fundamental
Avenew Project Management FundamentalAvenew Project Management Fundamental
Avenew Project Management Fundamental
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 
Procurement management
Procurement managementProcurement management
Procurement management
 

Similar to Risk assessment plan example

Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
B012140812
B012140812B012140812
B012140812
IOSR Journals
 
Project Planning
Project PlanningProject Planning
Project Planning
Rana Taimoor
 
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16
Cong Danh Tran
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
JBC BoNA Zeta Project (Risk Management Plan)
JBC BoNA Zeta Project (Risk Management Plan)JBC BoNA Zeta Project (Risk Management Plan)
JBC BoNA Zeta Project (Risk Management Plan)
ArshdeepKaur140
 
Final TEAM SLIDE PRESENTATION (1)
Final TEAM  SLIDE PRESENTATION (1)Final TEAM  SLIDE PRESENTATION (1)
Final TEAM SLIDE PRESENTATION (1)
University of Regina
 
Programmatic Environmental Compliance Management
Programmatic Environmental Compliance ManagementProgrammatic Environmental Compliance Management
Programmatic Environmental Compliance Management
msweesy
 
A Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential StructuresA Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential Structures
IRJESJOURNAL
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
ASHISH KUMAR SINGH
 
COE
COECOE
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
HossamNegidaPMPRMPPS
 
1.1 1.3 epc-project-rev
1.1 1.3 epc-project-rev1.1 1.3 epc-project-rev
1.1 1.3 epc-project-rev
Viktor Yakovlev
 
MY CV AB - Lng-2014
MY  CV AB - Lng-2014MY  CV AB - Lng-2014
MY CV AB - Lng-2014
ALBERT AUDU
 
Claim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINALClaim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINAL
Hossein Khodaverdi M.Eng
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
IRJET Journal
 
Student Project
Student ProjectStudent Project
Student Project
Robin S Teller
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
Rick Vogel
 

Similar to Risk assessment plan example (20)

Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
B012140812
B012140812B012140812
B012140812
 
Project Planning
Project PlanningProject Planning
Project Planning
 
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
JBC BoNA Zeta Project (Risk Management Plan)
JBC BoNA Zeta Project (Risk Management Plan)JBC BoNA Zeta Project (Risk Management Plan)
JBC BoNA Zeta Project (Risk Management Plan)
 
Final TEAM SLIDE PRESENTATION (1)
Final TEAM  SLIDE PRESENTATION (1)Final TEAM  SLIDE PRESENTATION (1)
Final TEAM SLIDE PRESENTATION (1)
 
Programmatic Environmental Compliance Management
Programmatic Environmental Compliance ManagementProgrammatic Environmental Compliance Management
Programmatic Environmental Compliance Management
 
A Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential StructuresA Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential Structures
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
COE
COECOE
COE
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
1.1 1.3 epc-project-rev
1.1 1.3 epc-project-rev1.1 1.3 epc-project-rev
1.1 1.3 epc-project-rev
 
MY CV AB - Lng-2014
MY  CV AB - Lng-2014MY  CV AB - Lng-2014
MY CV AB - Lng-2014
 
Claim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINALClaim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINAL
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
Student Project
Student ProjectStudent Project
Student Project
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 

Recently uploaded

New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
enizeyimana36
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Recycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part IIRecycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part II
Aditya Rajan Patra
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
mamamaam477
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
zubairahmad848137
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 

Recently uploaded (20)

New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Recycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part IIRecycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part II
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 

Risk assessment plan example

  • 1. 1a. 1b 1c. 1d. 2a. 2b. 2c. 3a 3b S/N Work activity Hazard Possible Accident/ Ill health to persons, fire or property loss Severity Likelihood RPN* Additional Risk Control Measures Remarks D1 Design Errors and Omissions Delay in construction and installation of equipment 4 3 12 Design Review by Lead Engineers in all Disciplines D2 Failure to carry out the works in accordance with the contract Construction Deadline Extension 3 3 9 Carefully Review of Contract Terms, engage more people and equipment EX1 Laws and local standards change Interruption in construction 3 1 3 Constant review of standards and laws by QM Engineer EX2 Climate Conditions Delay in Tasks, Impact on Health of Personnel 4 3 12 Planning Tasks and Deadlines according to Climate Conditions EX3 Tax change Budget Overruns 4 1 4 Include this in Contract EX4 Contracting Long Delays in Contract Negotiations or Award Delay of Construction 4 4 16 Move Construction Deadline EN1 Environmental analysis incomplete Delay in Permit Obtaining 4 2 8 Engage local experts EN2 Laws and environmental standards change Delay in Permit Obtaining 3 1 3 Constant review of standards and laws by QM Engineer EN3 New alternatives required to avoid, mitigate or minimize environmental impact Delay in Permit Obtaining 4 2 8 Engage local experts O1 Inexperienced workforce and staff turnover Skill shortage 3 3 9 Conduct technical training or workshop to increase local workforce skill and knowledge O2 Lack of protection on a construction site Incidents and Accidents - Labour and Equipment 2 1 2 HSEQ Weekly Supervising and HSEQ Training of Personnel O3 Procurement Delayed deliveries Delay in Installation of Equipment 3 3 9 Choosing Local Vendor with Short Delivery Time O4 Commissioning Delayed commissioning Delay in completing of all parts of line 4 2 8 Choosing Competent Working Commission and Project Control Engineer PM1 Project Quality Control Failure to comply with contractual quality requirements Accidents with equipment 3 3 9 Continuous Quality Control of all Project Activities and Assets PM2 Scheduling and Planning Scheduling errors, contractor delays Accidents with personnel in attempt to perform tasks faster 4 2 8 Planning Carefully, Engage more workers for some activities PM3 Choosing Project Team Project team conflict Accidents with personnel and assets 3 2 6 Carefully choose personnel, Team Building Activities R1 Obtain Required Design Permits Expired temporary construction permits Stop of construction work by regulatory bodies 4 1 4 Continuous control of all permits and regulatory acts and promptly react to any change R2 Engineering, Construction Related Engineering and Adaptation of the drawings Contradictions in the construction documents Delay in construction works, possible property losses 4 3 12 Review of all design drawings by Design Supervisor and Correction of all contradictions, as well as all calculations C1 Construction cost overruns Budget Overruns 4 4 16 Cost Control Engineer Day-to-Day tracking of all Site Costs and On- Time warning of possible Budget Overruns C2 Technology changes Project Late, Budget Overruns 4 2 8 Choosing latest technology before construction start, if client change technology during construction, insist on Scope of Change and Changing Schedule and Budget *RPN - Risk Prioritization Number RISK ASSESSMENT PLAN Department & Exact Location Of The Work Performed: Project / Work Description: Risk Assessment Team (Name/s): Approved By Supervisor / Reporting Officer: (Name, Date & Signature) Date Conducted: Next Review Date: Hazard Identification Risk Assessment Risk Control DESIGN RISKS EXTERNAL RISKS ENVIRONMENTAL RISKS ORGANIZATIONAL RISKS Construction Construction PROJECT MANAGEMENT RISKS RIGHT OF WAY RISKS CONSTRUCTION RISKS Project Design Construction Obtain Environment Emission Permit
  • 2. Risk Assessment Matrix Risk level Determination - 5 x 5 Matrix Critical (5) Very Serious (4) Serious (3) Marginal (2) Negligible (1) Frequent (5) Moderate (4) EX4 Occasional (3) D1, EX2, R2 D2, O1, O3, PM1 Remote (2) EN1, EN3, O4, PM2, C2 PM3 Unlikely (1) EX3, R1 EX1, EN2 O2 Action Table Colour Score Risks 16 - 25 High 12 - 15 Warning 8 -10 Medium 1 - 6 Warning SEVERITY LIKELIHOOD Take remedial action at appropriate time Proceed with care. Additional control is advised. Review shall be implemented within 30 days. Risk acceptable: Residual risk If possible, risk reduction should be further considered, particularly severity. There are no imminent dangers. Frequent review shall be in place especially changes in procedures, materials or environment. Action Operation not Permissible Stop operation & review controls. If necessary abort experimentation. High priority remedial action Proceed with extreme caution with PI present at all times. Implement additional (secondary) controls immediately. Review within 7 days. Emergency control measures shall be in place.