Causes of construction delay: traditional contracts
Abdalla M. Odeh a,
*, Hussien T. Battaineh b
a
Jordan University of Science and Technology, PO Box 3030, Irbid 22110, Jordan
b
College of Engineering and Applied Science, Western Michigan University, Kalamazoo, MI 49008, USA
Abstract
Many projects experience extensive delays and thereby exceed initial time and cost estimates. In addition to imparting the eco-
nomic feasibility of capital projects, extensive delays provide a fertile ground for costly disputes and claims. This paper presents the
®ndings of a survey aimed at identifying the most important causes of delays in construction projects with traditional type contracts
from the viewpoint of construction contractors and consultants. Results of the survey indicate that contractors and consultants
agreed that owner interference, inadequate contractor experience, ®nancing and payments, labor productivity, slow decision mak-
ing, improper planning, and subcontractors are among the top ten most important factors. It is hoped that these ®ndings will guide
e€orts to improve the performance of the construction industry, and will be useful to international engineering and construction
®rms seeking a share in the Jordanian and the regional markets. # 2001 Elsevier Science Ltd and IPMA. All rights reserved.
Keywords: Construction management; Construction in Jordan; Construction delays
1. Introduction
The successful execution of construction projects and
keeping them within estimated cost and prescribed
schedules depend on a methodology that requires sound
engineering judgment [1]. To the dislike of owners,
contractors and consultants, however, many rojects
experience extensive delays and thereby exceed initial
time and cost estimates. This problem is more evident in
the traditional or adversarial type of contracts in which
the contract is awarded to the lowest bidder Ð the
awarding strategy of the majority of public projects in
developing countries including Jordan.
Although the construction industry in the Middle
East has su€ered ever since the Gulf war, recent events in
the region coupled with the restructuring of economies,
joining regional and global free trade organizations, and
attracting foreign investments are expected to yield an
unprecedented growth in the construction activities. The
region is in desperate need for development projects in
many areas, especially in the ®elds of water collection
and distribution, tourism and housing. As a result, an
unprecedented number of large-scale projects are currently
under construction and in the planning and contract
awarding stages. In Jordan, for example, the volume of
construction projects awarded in 1998 was 944 million
Jordanian Dinar1
(JD) of which 155 millions went to
international contractors [2]. These projects include
three dams with contract values of over 87.7 million JD.
Another dam with an estimated cost of 200 million JD
is in the contract award phase. A major water transport
pipeline extending over 300 km with an estimated cost
of 100 million JD is in the ®nal design stage.
Unfortunately, the construction industry in Jordan is not
adequately prepared for the project management problems
accompanying the anticipated boom in construction activ-
ities and the increasing complexity of projects. Recent
®ndings [3,4] revealed that delays in public projects in
Jordan are extensive and warrant further investigation. It
is imperative to understand the underlying causes of such
delays for any corrective actions to be e€ective.
2. Related work
Leishman [5] presented the legal consequences of
delays in construction. Herbsman et al.[6] studied the
e€ect of delays on cost and quality. Yates [7] developed
a decision support system for construction delay analy-
sis called (DAS). The main categories of delays in DAS
0263-7863/01/$20.00 # 2001 Elsevier Science Ltd and IPMA. All rights reserved.
PII: S0263-7863(00)00037-5
International Journal of Project Management 20 (2002) 67±73
www.elsevier.com/locate/ijproman
1
1 JD=$1.424, the rate of exchange on 1 June 2000.* Corresponding author.
include engineering, equipment, external delays, labor,
management, material, owner, subcontractors, and
weather.
Ogunlana et al. [8] studied the delays in building project
in Thailand, as an example of developing economies. They
concluded that the problems of the construction industry
in developing economies can be nested in three layers:
(1) problem of shortages or inadequacies in industry
infrastructure, mainly supply of resources; (2) problems
caused by clients and consultants; and (3) problems
caused by incompetence of contractors. Kumaraswamy et
al. [9] surveyed the causes of construction delays in Hong
Kong as seen by clients, contractors and consultants, and
examined the factors a€ecting productivity. The survey
revealed di€erences in perceptions of the relative sig-
ni®cance of factors between the three groups, indicative
of their experiences, possible prejudices and lack of
e€ective communication. Mans®eld et al. [10] studied
the causes of delay and cost overrun in construction
projects in Nigeria. The results showed that the most
important factors are ®nancing and payment for com-
pleted works, poor contract management, changes in site
conditions, shortage of material, and improper planing.
Assaf et al. [11] studied the causes of delay in large
building construction projects in Saudi Arabia. The
most important causes of delay included approval of
shop drawings, delays in payments to contractors and
the resulting cash problems during construction, design
changes, con¯icts in work schedules of subcontractors,
slow decision making and executive bureaucracy in the
owners' organizations, design errors, labor shortage and
inadequate labor skills. Mezher et al. [12] conducted a
survey of the causes of delays in the construction
industry in Lebanon from the viewpoint of owners,
contractors and architectural/engineering ®rms. It was
found that owners had more concerns with regard to
®nancial issues, contractors regarded contractual relation-
ships the most important, while consultants considered
project management issues to be the most important
causes of delays.
Battaineh [3] evaluated the progress reports of 164
building and 28 highway projects constructed during the
period 1996±1999 in Jordan. The results indicate that
delays are extensive: the average ratio of actual com-
pletion time to the planned contract duration is 160.5%
for road projects and 120.3% for building projects.
Al-Momani [4] conducted a quantitative analysis of
construction delays by examining the records of 130
public building projects constructed in Jordan during
the period of 1990±1997. The researcher presented
regression models of the relationship between actual
and planned project duration for di€erent types of
building facilities. The analysis also included the reported
frequencies of time extensions for the di€erent causes of
delays. The researcher concluded that the main causes
of delay in construction projects relate to designers, user
changes, weather, site conditions, late deliveries, eco-
nomic conditions, and increase in quantities. However,
such conclusion can be misleading. First, they included
causes which are limited to those for which contractors
are entitled to time extension. The analysis does not
cover causes of delay for which the contractor is
responsible, such as those related to labor and equipment,
planning and site management, construction methods,
adequacy and capability of contractor. Second, they are
based on the reported number of time extensions not on
the extent of delay attributed to the di€erent causes of
delay. Despite the moderate weather in Jordan, for
example, it was ®gured among the major causes of delay
because a time extension was granted for all public
projects under construction in the winter of 1991 as a
result of an unprecedented severe storm that had a very
low probability of occurrence. Third, they are drawn
from records of public building projects and one would
question their validity to other types of construction
projects such as industrial facilities, water collection
treatment and distribution, and highway construction.
3. Research design and objectives
The objective of this research is to identify the major
causes of delay in the construction industry and to
assess the relative importance of these causes for the
traditional adversarial type of contracts from the viewpoint
of construction contractors and consultants. First, a survey
questionnaire was developed to assess the perceptions of
contractors and consultants of the relative importance of
construction delay causes. Second, the questionnaire
was distributed to a random sample of contractors and
consultants working on large projects in Jordan. Responses
to the questionnaire were then collected and analyzed.
The analysis included ranking the di€erent causes
according to the relative importance indexes for both
contractors and consultants responses. The Spearman's
rank correlation coecient was then used to test associa-
tion between the contractors and consultants ranking.
4. Causes of delay
The survey is based on 28 well recognized causes of
delay to which participants were asked to indicate their
level of importance of each cause. These causes were
categorized into the following 8 major groups:
1. Client related factors include ®nance and pay-
ments of completed work, owner interference, slow
decision making and unrealistic contract duration
imposed by owners.
2. Contractor related factors include site manage-
ment, improper planning, inadequate contractor
68 A.M. Odeh, H.T. Battaineh / International Journal of Project Management 20 (2002) 67±73
experience, mistakes during construction, impro-
per construction methods and delays caused by
subcontractors. Delays caused by subcontractors
are included among the contractor's factors
because the latter is fully responsible for the delays
caused by his subcontractors.
3. Consultant related factors include contract man-
agement, preparation and approval of drawings,
quality assurance/control, and long waiting time
for approval of tests and inspections.
4. Material factors include quality and shortage.
5. Labor and equipment factors include labor supply,
labor productivity, and equipment availability and
failure.
6. Contract factors include changed orders and mis-
takes and discrepancies in contract documents.
7. Contractual relationships factors include major
disputes and negotiations during construction,
inappropriate organizational structure linking all
parties involved in the project, and lack of com-
munication between these parties.
8. External factors include weather conditions, chan-
ges in regulations, problems with neighbors and
site conditions.
Other signi®cant issues of concern such as political,
socio-economical and religious factors are dismissed
because it is felt that people in this part of the world are
very sensitive to these issues to a degree that might pre-
judice their responses.
5. Survey methodology
The scope of the research included large public and
private buildings, roads, and water and sewer projects in
Jordan. Given this scope, the questionnaire was dis-
tributed to a random sample of 100 contractors and 50
consultants representing the di€erent specialization of
contractors and consultants working on large projects
(contract value>1 million JD). Tables 1 and 2 show the
distribution of the population, sample, and respondents
among the di€erent specializations of contractors and
consultants classi®ed by the Ministry of Public Works
and Housing to take on large projects. The sample size
of each specialization is proportional to the distribution
of the population of the di€erent specializations. Given
the sample size, the samples were selected randomly
from the population in each specialization.
The respondents were asked to express their percep-
tion of the relative importance of each of the 28 causes
of delays as either: extreme, very, moderate, slight, or
not important. The questionnaire was personally handed
over to respondents, and an interviewer was available to
answer questions about the questionnaire and to ensure
that the questionnaire is administered by VPs or project
managers. This mode of follow-up communication led
to the return of 82 completed questionnaires: 63 con-
tractors and 19 consultants.
6. Analysis of responses
To determine the ranking of di€erent causes from the
point of view of contractors and of consultants, the
relative importance index (I) was computed as:
I ˆ
P5
iˆ1
WiXi
P5
iˆ1
Xi
where:
i =response category index=1, 2, 3, 4, and 5 for
not-, slightly-, moderately-, very-, and extremely-
important, respectively.
Wi =the weight assigned to the ith response=0, 1, 2, 3,
4, respectively.
Xi =frequency of the ith response given as percentage
of the total responses for each cause.
The indexes were then ranked, and the results are
shown in Table 3. Calculating the average indexes of the
causes in each group gives the relative importance index
of the mean groups. The mean indexes and the ranking
of all groups are shown in Table 4. The Spearman's
correlation coecients of the ranking of contractors
and consultants for all the causes and for the main
Table 1
Distribution of population, sample and respondents of the di€erent
specializations of contractors
Specialization of contractors
Buildings Roads Water and sewer Total
Population 222 141 80 265
Sample 50 32 18 100
Respondents 39 27 16 82
Table 2
Distribution of population, sample and respondents of the di€erent
specializations of consultants
Specialization of consultants
Buildings Roads Water and Sewer Total
Population 42 22 16 80
Sample 26 14 10 50
Respondents 9 5 5 19
A.M. Odeh, H.T. Battaineh / International Journal of Project Management 20 (2002) 67±73 69
categories of delays are 0.789 and 0.762, respectively.
These correlation coecients are calculated for the
ranking shown in Tables 3 and 4 using the following
equation [13]:
rS ˆ 1 À
6
P
d2
N…N2 À 1†
where:
rS=Spearman's rank correlation coecient.
d =the di€erence in ranking between the contractors and
the consultants, and
N=the number of variables, equals to 28 and 8 for all the
causes and for the main categories of causes of delay,
respectively.
The somewhat high values of rank correlation coe-
cients indicate strong agreement between contractors
and consultants on the ranking of all the factors and of
the main groups of factors. This association between the
ranking of contractors and consultants is veri®ed by a
hypothesis testing at 95% signi®cance where Z ˆ
rS

N À 1
p
Table 3
Relative importance index and ranking of delay factors
Contractors Consultants
Category Factor Index Rank Index Rank
Client Finance and payments of completed work 3.30 4 3.32 2
Owner interference 3.51 2 3.21 4
Slow decision-making by owners 3.24 8 3.16 5
Unrealistic imposed contract duration 3.08 13 3.11 6
Contractor Subcontractors 3.21 9 3.26 3
Site management 3.29 5 2.58 13
Construction methods 3.29 5 2.37 17
Improper planning 3.14 10 2.95 8
Mistakes during construction 2.56 17 2.74 11
Inadequate contractor experience 3.37 3 3.37 1
Consultant Contract management 3.10 12 3.00 7
Preparation and approval of drawings 2.32 21 2.21 19
Quality assurance/control 2.06 25 2.11 21
Waiting time for approval of tests and inspections 2.46 18 2.47 15
Material Quality of material 1.75 26 2.00 23
Shortage in material 3.11 11 2.79 10
Labor and equipment Labor supply 2.63 16 2.63 12
Labor productivity 3.60 1 2.89 9
Equipment availability and failure 3.25 7 2.42 16
Contract Change orders 2.40 19 1.79 26
Mistakes and discrepancies in contract documents 3.05 14 2.05 22
Contractual relationships Major disputes and negotiations 2.94 15 2.16 20
Inappropriate overall organizational structure linking all parties to the project 2.27 22 2.26 18
Lack of communication between the parties 2.38 20 2.53 14
External factors Weather condition 2.19 23 1.95 24
Regulatory changes and building Code 1.70 27 1.16 28
Problems with neighbors 1.59 28 1.58 27
Unforeseen ground conditions 2.10 24 1.84 25
Table 4
Importance index and ranking of major delay categories
Contractors Consultants
Category Index Rank Index Rank
Client 3.28 1 3.20 1
Contractor 3.14 3 2.88 2
Consultant 2.48 6 2.45 4
Material 2.43 7 2.39 5
Labor and equipment 3.16 2 2.65 3
Contract 2.72 4 1.92 7
Contractual relationships 2.53 5 2.32 6
External factors 1.89 8 1.63 8
70 A.M. Odeh, H.T. Battaineh / International Journal of Project Management 20 (2002) 67±73
7. Discussion of results
The ranking of the relative importance of the delay
factors, Table 3, shows that owner interference, inadequate
contractor experience, and ®nancing and payments of
completed work made the top ®ve signi®cant factors for
both contractors and consultants. Moreover, labor pro-
ductivity, site management, slow decision making, con-
struction methods, improper planning and subcontractors
are among the top ten ranked factors of both groups.
The following is a brief discussion of the ranking of
the relative importance of the groups of delay factors, as
deducted from Tables 3 and 4.
7.1. Client
The client related group of delay factors was the most
important group to both contractors and consultants.
This is mainly due to ®nancing issues and owner inter-
ference, which are considered very important by both
parties. It was interesting to ®nd out that slow decision
by owners and unrealistic contract duration are of more
importance to consultants than to contractors. This is
because contractors considered operational issues, such
as labor productivity and equipment availability and
failure, of more importance. Unlike contractors, however,
consultants considered the client related factors to be
more important than operational ones.
7.2. Contractor
Both contractors and consultants ranked this group
of causes very high. It is worth noticing that consultants
are mainly concerned with technical factors such as inade-
quate contractors experience, delays caused by subcon-
tractors, and improper planning, while contractors are
more concerned with managerial and operational factors
such as site management and construction methods.
Inadequate contractor experience was the most
important factor in this group. This can be attributed to
the contract awarding procedure where most projects
are awarded to the lowest bidder. Moreover, local con-
tractors, solely or through joint ventures, are being
awarded large and complex projects in which they have
little experience because such projects were virtually
limited to international contractors in the past.
Delays caused by subcontractors are also of high
importance to consultants. This can be attributed to
inadequate experience of subcontractors, the bid shopping
practice of general contractors, and to improper plan-
ning and coordination.
Improper planning is also troublesome to contractors
and consultants. Local contractors are reluctant to use
scheduling techniques and to update schedules on a
regular basis. Despite the fact that contractors are
required to provide work schedules on most projects,
the schedule is often a summary schedule that is hardly
updated during construction. This is substantiated by the
fact that only 8 of the 63 sampled contractors responded
positively to updating schedules on their projects.
Delays caused by improper construction methods are
more important to contractors than to consultants.
Fluctuation in the construction market and the seasonal
nature of the industry has forced many contractors towards
diversity. As a result, they do not focus on one line-of-work
and try to adopt advanced methods and techniques.
Site management is another important cause of delay to
contractors. This is due to the reluctance of contractors to
invest in planning and control and to the lack of pro-
fessional construction managers. The majority of site
managers are civil engineers with a good work experi-
ence but little training or education in management.
7.3. Consultants
Neither contractors nor consultants ranked this group of
factors high among the major groups of delay causing fac-
tors. Contrary to what is expected, consultants consistently
ranked each of these causes higher than contractors. The
highest ranked factor among these causes was contract
management. This could be attributed to the lack of
authority the owners are willing to delegate to consultants
enabling them to manage the contract e€ectively. This
®nding is consistent with the high ranking of owner
interference and the low ranking of factors over which the
consultants are usually granted authority. The latter factors
include preparation and approval of drawings, quality
assurance/control, and approval of tests and inspections.
7.4. Material
The group of material related causes received low
ranking by both contractors and consultants. Quality of
material was among the least important causes because
most of the available material is local with little variation
in quality, especially for cement, steel, and asphalt that
are produced by a limited number of producers. Shortage
of material received higher ranking than quality. This is
particularly true for imported material that may take a
considerable time to procure.
7.5. Labor and equipment
This group of causes were ranked high, second by
contractors and third by consultants. As expected, this
group of causes is more important to contractors than
to consultants. This was true for labor productivity and
for equipment availability and failure. While labor supply
is not that important considering the relatively inex-
pensive ¯ux of foreign and local laborers, the pro-
ductivity of the labor forces was the top ranked factor
for contractors. This may be attributed to lack of
A.M. Odeh, H.T. Battaineh / International Journal of Project Management 20 (2002) 67±73 71
incentives for higher productivity, lack of or improper
training, and absence of trade unions or associations
that regulate, train, and classify construction trades.
The high ranking of contractors of equipment avail-
ability and failure indicate problems associated with
ownership of new equipment, maintenance and repair,
and availability and reliability of the rental option.
7.6. External factors
External factors were the lowest ranked group of factors
by both parties. It seems that all parties are familiar with
these factors and are able to deal with them e€ectively
without causing any major delays. Of course, the moder-
ate weather conditions in Jordan coupled with low levels
of water tables in addition to well established regulations
and building code contribute to this low ranking.
7.7. Contract
This group of causes had more di€erence in ranking
than any other group. While it was considered important
and ranked fourth by contractors, it was unimportant
and ranked only seventh by consultants. Contrary to
contractors, consultants who are usually empowered to
issue changed orders and to correct mistakes and dis-
crepancies in contract documents are less critical of their
role in causing such delays.
7.8. Contractual relationships
This group of causes was ranked low by contractors and
consultants. Relatively, factors relating to organization
and communication were more important to con-
sultants than to contractors. Delays caused by disputes
and negotiations were more important to contractors,
especially for public projects in Jordan where arbitra-
tion is not allowed and where legal recourse through
courts takes a considerable time.
8. Conclusions and recommendations
According to contractors, labor productivity was the
most important delay factor. Inadequate contractor
experience, however, was the most important delay factor
to consultants. All parties generally agreed on the ranking
of the individual delay factors. They agreed that inade-
quate contractor experience, owner interference, and
®nancing of work were among the top ®ve most important
factors. Moreover, delays caused by subcontractors, slow
decision making by owners, improper planning, and
labor productivity were among the top ten most impor-
tant factors for both parties.
Operational factors such as labor productivity, con-
struction methods, site management, and equipment
availability and failure were more important to con-
tractors than to consultants. Contractors were also
more concerned with factors related to contract clauses
that may alter their contractual obligations and rights.
These factors include changed orders, mistakes and
discrepancies in contract documents and major disputes
and negotiations. However, factors dealing with sub-
contracting, planning, organizing and communicating
were more important to consultants than to contractors.
Delays are costly and often result in disputes and
claims, impair the feasibility for project owners, and
retard the development of the construction industry. To
improve the situation, the ®ndings of this research must
be addressed by a joint e€ort of all participants in the
construction industry. This calls for:
1. Enforcing liquidated damage clauses and o€ering
incentives for early completion.
2. Developing human resources in the construction
industry through proper training and classifying of
craftsmen. This calls for providing incentives such as
o€ering a tax deduction on money spent on training,
and for authorizing trade unions or other agencies to
regulate, follow-up on training, and classify trades.
Developing human resources also applies to construc-
tion engineers who usually lack adequate managerial
skills. There is an urgent need for o€ering training
courses in scheduling, time and cost control, inform-
ation systems, and management of human resources.
3. Adopting a new approach to contract award pro-
cedure by giving less weight to prices and more
weight to the capabilities and past performance of
contractors.
4. Adopting new approaches to contracting, such as
design-build and construction management (CM)
types of contracts. Such contracts reduce delays by
limiting owner interference, improving the design,
and improving the contractual relationships
among all parties to the project.
References
[1] Hancher DE, Rowings IE. Setting highway construction contract
duration. Journal of Construction Engineering and Management,
ASCE 1981;107(2):169±79.
[2] Department of public contracts. The Annual book, the Ministry
of Public Works and Housing, Jordan, 1998.
[3] Battaineh HT. Information system of progress evaluation of
public projects in Jordan, MSc thesis, Dept. of Civil Engineering,
Jordan Univ. of Science and Technology, Irbid, Jordan, 1999.
[4] Al-Moumani HA. Construction delay:a quantitative analysis.
International Journal of Project Management 2000;18:51±9.
[5] Leishman DM. Protecting engineer against construction delay claims:
NDC. Journal of Management in Engineering 1991;7(3):319±33.
[6] Herbsman ZJ, Chen WT, Epstein WC. Time is money:innovative
contracting methods in highway construction. Journal of Construc-
tion Engineering and Management, ASCE 1995;121(3):273±81.
[7] Yates J. Construction decision support system for delay analysis.
Journal of Construction Engineering and Management, ASCE
1993;119(2):226±44.
72 A.M. Odeh, H.T. Battaineh / International Journal of Project Management 20 (2002) 67±73
[8] Ogunlana SO, Promkuntong K. Construction delays in a fast-
growing economy: comparing Thailand with other economies.
International Journal of Project Management 1996;14(1):37±45.
[9] Kumaraswamy MM ChanWM. Contributors to construction
delays. Construction Management and Economics 1998;16:17±29.
[10] Mans®eld NR, Ugwu OO, Doran T. Causes of delay and cost
overruns in Nigerian construction projects. International Journal
of Project Management 1994;12(4):254±60.
[11] Assaf SA, Al-Khalil M, Al-Hazmi M. Causes of delay in large
building construction projects. Journal of Management in Engi-
neering ASCE 1995;11(2):45±50.
[12] Mezher TM, Tawil W. Causes of delays in the construction
industry in Lebanon. Engineering Construction and Archi-
tectural Management Journal 1998;5(3):251±60.
[13] Dowdy S, Wearden S. Statistics for research. 2nd Ed. New York:
John Wiley & Sons, 1985.
A.M. Odeh, H.T. Battaineh / International Journal of Project Management 20 (2002) 67±73 73

More Related Content

What's hot

ACH 216 Lecture 01 (Intro To CM)
ACH 216 Lecture 01 (Intro To CM)ACH 216 Lecture 01 (Intro To CM)
ACH 216 Lecture 01 (Intro To CM)
Anne Arundel Community College
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
IJMREMJournal
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
IJERA Editor
 
Management of government funded construction projects in ghana
Management of government funded construction projects in ghanaManagement of government funded construction projects in ghana
Management of government funded construction projects in ghana
Alexander Decker
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
eSAT Journals
 
20141016 recruitment of engineers in romania
20141016 recruitment of engineers in romania20141016 recruitment of engineers in romania
20141016 recruitment of engineers in romania
Freddy Jacobs
 
Green Building Effect in Commercial Building
Green Building Effect in Commercial Building Green Building Effect in Commercial Building
Green Building Effect in Commercial Building
vivatechijri
 
Ashworth 5e chapter 1 web ready
Ashworth 5e   chapter 1 web readyAshworth 5e   chapter 1 web ready
Ashworth 5e chapter 1 web ready
Sumit Gupta
 
CAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIES
CAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIESCAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIES
CAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIES
Muizz Anibire
 
IJSRED-V2I3P74
IJSRED-V2I3P74IJSRED-V2I3P74
IJSRED-V2I3P74
IJSRED
 
Economics in Civil Engineering (Or any field of Engineering).
Economics in Civil Engineering (Or any field of Engineering).Economics in Civil Engineering (Or any field of Engineering).
Economics in Civil Engineering (Or any field of Engineering).
Faisal F Rafat
 
Green buildings and role of projects Manager in success of project
Green buildings and role of projects Manager in success of project Green buildings and role of projects Manager in success of project
Green buildings and role of projects Manager in success of project
Tehmas Saeed
 
Chapter 4
Chapter 4Chapter 4
Project identification (report)
Project identification (report)Project identification (report)
Project identification (report)
christopher abne
 
professional practic
professional practicprofessional practic
professional practic
arvikassaini011
 
BARRIERS TO GOOD OCCUPATIONAL HEALTH & SAFETY (OHS) PRACTICES BY SMALL CONSTR...
BARRIERS TO GOOD OCCUPATIONAL HEALTH & SAFETY (OHS) PRACTICES BY SMALL CONSTR...BARRIERS TO GOOD OCCUPATIONAL HEALTH & SAFETY (OHS) PRACTICES BY SMALL CONSTR...
BARRIERS TO GOOD OCCUPATIONAL HEALTH & SAFETY (OHS) PRACTICES BY SMALL CONSTR...
Sagar Kaptan
 
Bryce book notes
Bryce book notesBryce book notes
Bryce book notes
Kinshook Chaturvedi
 

What's hot (17)

ACH 216 Lecture 01 (Intro To CM)
ACH 216 Lecture 01 (Intro To CM)ACH 216 Lecture 01 (Intro To CM)
ACH 216 Lecture 01 (Intro To CM)
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
 
Management of government funded construction projects in ghana
Management of government funded construction projects in ghanaManagement of government funded construction projects in ghana
Management of government funded construction projects in ghana
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
20141016 recruitment of engineers in romania
20141016 recruitment of engineers in romania20141016 recruitment of engineers in romania
20141016 recruitment of engineers in romania
 
Green Building Effect in Commercial Building
Green Building Effect in Commercial Building Green Building Effect in Commercial Building
Green Building Effect in Commercial Building
 
Ashworth 5e chapter 1 web ready
Ashworth 5e   chapter 1 web readyAshworth 5e   chapter 1 web ready
Ashworth 5e chapter 1 web ready
 
CAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIES
CAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIESCAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIES
CAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIES
 
IJSRED-V2I3P74
IJSRED-V2I3P74IJSRED-V2I3P74
IJSRED-V2I3P74
 
Economics in Civil Engineering (Or any field of Engineering).
Economics in Civil Engineering (Or any field of Engineering).Economics in Civil Engineering (Or any field of Engineering).
Economics in Civil Engineering (Or any field of Engineering).
 
Green buildings and role of projects Manager in success of project
Green buildings and role of projects Manager in success of project Green buildings and role of projects Manager in success of project
Green buildings and role of projects Manager in success of project
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Project identification (report)
Project identification (report)Project identification (report)
Project identification (report)
 
professional practic
professional practicprofessional practic
professional practic
 
BARRIERS TO GOOD OCCUPATIONAL HEALTH & SAFETY (OHS) PRACTICES BY SMALL CONSTR...
BARRIERS TO GOOD OCCUPATIONAL HEALTH & SAFETY (OHS) PRACTICES BY SMALL CONSTR...BARRIERS TO GOOD OCCUPATIONAL HEALTH & SAFETY (OHS) PRACTICES BY SMALL CONSTR...
BARRIERS TO GOOD OCCUPATIONAL HEALTH & SAFETY (OHS) PRACTICES BY SMALL CONSTR...
 
Bryce book notes
Bryce book notesBryce book notes
Bryce book notes
 

Viewers also liked

Recull de premsa #Figueres - 13/01/2017
Recull de premsa #Figueres - 13/01/2017Recull de premsa #Figueres - 13/01/2017
Recull de premsa #Figueres - 13/01/2017
Ajuntament de Figueres
 
Physiochemical characterization of starch from different sorghum varieties
Physiochemical characterization of starch from different sorghum varietiesPhysiochemical characterization of starch from different sorghum varieties
Physiochemical characterization of starch from different sorghum varieties
Alexis Prillhart
 
Poems
PoemsPoems
κύκλος ζωής φυτού 16.03
κύκλος ζωής φυτού 16.03κύκλος ζωής φυτού 16.03
κύκλος ζωής φυτού 16.03
marianna angelopoulou
 
Working with Designers
Working with DesignersWorking with Designers
Working with Designers
Jeremy Horn
 
Recull de premsa #Figueres - 17/01/2017
Recull de premsa #Figueres - 17/01/2017Recull de premsa #Figueres - 17/01/2017
Recull de premsa #Figueres - 17/01/2017
Ajuntament de Figueres
 
LES AUTEURS HUMANISTES : Michel de Montaigne
LES AUTEURS HUMANISTES : Michel de MontaigneLES AUTEURS HUMANISTES : Michel de Montaigne
LES AUTEURS HUMANISTES : Michel de Montaigne
eciudad2
 
SCMHK newsletter 2014 DEC
SCMHK newsletter 2014 DECSCMHK newsletter 2014 DEC
SCMHK newsletter 2014 DEC
可樂 陳
 
App salud responde
App salud respondeApp salud responde
App salud responde
Guadalinfo Laujar de Andarax
 
Fiesta del otoño 2016
Fiesta del otoño 2016Fiesta del otoño 2016
Fiesta del otoño 2016
Montserrat Navarro Morales
 
Auteurs humanistes : PIERRE DE RONSARD
Auteurs humanistes : PIERRE DE RONSARDAuteurs humanistes : PIERRE DE RONSARD
Auteurs humanistes : PIERRE DE RONSARD
eciudad2
 
How does ups works
How does ups worksHow does ups works
How does ups works
Mary Anne Ramos
 
Community Building in “Beta Brooklyn” - Kika Gilbert
Community Building in “Beta Brooklyn” - Kika GilbertCommunity Building in “Beta Brooklyn” - Kika Gilbert
Community Building in “Beta Brooklyn” - Kika Gilbert
DesignBloggersConference
 
ΕΛΙΑ, ΤΟ ΔΕΝΤΡΟ ΤΗΣ ΖΩΗΣ
ΕΛΙΑ, ΤΟ ΔΕΝΤΡΟ ΤΗΣ ΖΩΗΣΕΛΙΑ, ΤΟ ΔΕΝΤΡΟ ΤΗΣ ΖΩΗΣ
ΕΛΙΑ, ΤΟ ΔΕΝΤΡΟ ΤΗΣ ΖΩΗΣ
xripappa
 
“Visual Web” Marketing + Instagram Power Tips by Adam Japko
“Visual Web” Marketing + Instagram Power Tips by Adam Japko“Visual Web” Marketing + Instagram Power Tips by Adam Japko
“Visual Web” Marketing + Instagram Power Tips by Adam Japko
DesignBloggersConference
 

Viewers also liked (15)

Recull de premsa #Figueres - 13/01/2017
Recull de premsa #Figueres - 13/01/2017Recull de premsa #Figueres - 13/01/2017
Recull de premsa #Figueres - 13/01/2017
 
Physiochemical characterization of starch from different sorghum varieties
Physiochemical characterization of starch from different sorghum varietiesPhysiochemical characterization of starch from different sorghum varieties
Physiochemical characterization of starch from different sorghum varieties
 
Poems
PoemsPoems
Poems
 
κύκλος ζωής φυτού 16.03
κύκλος ζωής φυτού 16.03κύκλος ζωής φυτού 16.03
κύκλος ζωής φυτού 16.03
 
Working with Designers
Working with DesignersWorking with Designers
Working with Designers
 
Recull de premsa #Figueres - 17/01/2017
Recull de premsa #Figueres - 17/01/2017Recull de premsa #Figueres - 17/01/2017
Recull de premsa #Figueres - 17/01/2017
 
LES AUTEURS HUMANISTES : Michel de Montaigne
LES AUTEURS HUMANISTES : Michel de MontaigneLES AUTEURS HUMANISTES : Michel de Montaigne
LES AUTEURS HUMANISTES : Michel de Montaigne
 
SCMHK newsletter 2014 DEC
SCMHK newsletter 2014 DECSCMHK newsletter 2014 DEC
SCMHK newsletter 2014 DEC
 
App salud responde
App salud respondeApp salud responde
App salud responde
 
Fiesta del otoño 2016
Fiesta del otoño 2016Fiesta del otoño 2016
Fiesta del otoño 2016
 
Auteurs humanistes : PIERRE DE RONSARD
Auteurs humanistes : PIERRE DE RONSARDAuteurs humanistes : PIERRE DE RONSARD
Auteurs humanistes : PIERRE DE RONSARD
 
How does ups works
How does ups worksHow does ups works
How does ups works
 
Community Building in “Beta Brooklyn” - Kika Gilbert
Community Building in “Beta Brooklyn” - Kika GilbertCommunity Building in “Beta Brooklyn” - Kika Gilbert
Community Building in “Beta Brooklyn” - Kika Gilbert
 
ΕΛΙΑ, ΤΟ ΔΕΝΤΡΟ ΤΗΣ ΖΩΗΣ
ΕΛΙΑ, ΤΟ ΔΕΝΤΡΟ ΤΗΣ ΖΩΗΣΕΛΙΑ, ΤΟ ΔΕΝΤΡΟ ΤΗΣ ΖΩΗΣ
ΕΛΙΑ, ΤΟ ΔΕΝΤΡΟ ΤΗΣ ΖΩΗΣ
 
“Visual Web” Marketing + Instagram Power Tips by Adam Japko
“Visual Web” Marketing + Instagram Power Tips by Adam Japko“Visual Web” Marketing + Instagram Power Tips by Adam Japko
“Visual Web” Marketing + Instagram Power Tips by Adam Japko
 

Similar to CSCM Causes of project delay

An Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainAn Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in Bahrain
IJRES Journal
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
IAEME Publication
 
Risk management
Risk managementRisk management
Risk management
nashaat algrara
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
Rick Vogel
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET Journal
 
10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx
EbrahimJemal4
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
Joseph Sangpang
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET Journal
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
IJMER
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
iosrjce
 
I012646171
I012646171I012646171
I012646171
IOSR Journals
 
I012646171
I012646171I012646171
I012646171
IOSR Journals
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET Journal
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
Dr. Amarjeet Singh
 
2.Abstract.pdf
2.Abstract.pdf2.Abstract.pdf
2.Abstract.pdf
estermanik9
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET Journal
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
IRJET Journal
 
Causes of Variation Orders 1268
Causes of Variation Orders 1268Causes of Variation Orders 1268
Causes of Variation Orders 1268
HASHIM HANIF
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
IJMREMJournal
 

Similar to CSCM Causes of project delay (20)

An Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainAn Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in Bahrain
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
 
Risk management
Risk managementRisk management
Risk management
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
 
10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
2.Abstract.pdf
2.Abstract.pdf2.Abstract.pdf
2.Abstract.pdf
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Causes of Variation Orders 1268
Causes of Variation Orders 1268Causes of Variation Orders 1268
Causes of Variation Orders 1268
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
 

More from Est

SABD PROGRAMME GUIDE 2017
SABD PROGRAMME GUIDE 2017SABD PROGRAMME GUIDE 2017
SABD PROGRAMME GUIDE 2017
Est
 
Sabd undergraduate pg draft v3
Sabd undergraduate pg draft   v3Sabd undergraduate pg draft   v3
Sabd undergraduate pg draft v3
Est
 
BS 2 Fire protection 4
BS 2 Fire protection 4BS 2 Fire protection 4
BS 2 Fire protection 4
Est
 
CSCM Chapter 11 relationship management cscm
CSCM Chapter 11 relationship management cscmCSCM Chapter 11 relationship management cscm
CSCM Chapter 11 relationship management cscm
Est
 
CSCM Partnering
CSCM PartneringCSCM Partnering
CSCM Partnering
Est
 
CSCM Communication in construction
CSCM Communication in constructionCSCM Communication in construction
CSCM Communication in construction
Est
 
CSCM Material delivery problems cscm
CSCM Material delivery problems cscmCSCM Material delivery problems cscm
CSCM Material delivery problems cscm
Est
 
BS 2 Escalators arrangement
BS 2 Escalators arrangementBS 2 Escalators arrangement
BS 2 Escalators arrangement
Est
 
BS 2 Escalators 1of 2
BS 2 Escalators 1of 2BS 2 Escalators 1of 2
BS 2 Escalators 1of 2
Est
 
BS 2 Group assignment brief question august 2016
BS 2 Group assignment brief  question august 2016BS 2 Group assignment brief  question august 2016
BS 2 Group assignment brief question august 2016
Est
 
BS 2 Variable air volume systems
BS 2 Variable air volume systemsBS 2 Variable air volume systems
BS 2 Variable air volume systems
Est
 
CSCM Supply chain management 312 cscm
CSCM Supply chain management 312 cscmCSCM Supply chain management 312 cscm
CSCM Supply chain management 312 cscm
Est
 
CSCM Bim group assignment.docx
CSCM Bim group assignment.docxCSCM Bim group assignment.docx
CSCM Bim group assignment.docx
Est
 
CSCM individual assignment
CSCM individual assignmentCSCM individual assignment
CSCM individual assignment
Est
 
Management science group assignment MS
Management science group assignment MSManagement science group assignment MS
Management science group assignment MS
Est
 
MS Tutorial 12 hrm
MS Tutorial 12 hrmMS Tutorial 12 hrm
MS Tutorial 12 hrm
Est
 
MS Case study development for entrepreneur mark zuckerberg
MS Case study development for entrepreneur mark zuckerbergMS Case study development for entrepreneur mark zuckerberg
MS Case study development for entrepreneur mark zuckerberg
Est
 
MS Lecture 7 leadership and motivation
MS Lecture 7 leadership and motivationMS Lecture 7 leadership and motivation
MS Lecture 7 leadership and motivation
Est
 
MS Lecture 8 communication
MS Lecture 8 communicationMS Lecture 8 communication
MS Lecture 8 communication
Est
 
MS Qsb 2413 group project 2016
MS Qsb 2413 group project 2016MS Qsb 2413 group project 2016
MS Qsb 2413 group project 2016
Est
 

More from Est (20)

SABD PROGRAMME GUIDE 2017
SABD PROGRAMME GUIDE 2017SABD PROGRAMME GUIDE 2017
SABD PROGRAMME GUIDE 2017
 
Sabd undergraduate pg draft v3
Sabd undergraduate pg draft   v3Sabd undergraduate pg draft   v3
Sabd undergraduate pg draft v3
 
BS 2 Fire protection 4
BS 2 Fire protection 4BS 2 Fire protection 4
BS 2 Fire protection 4
 
CSCM Chapter 11 relationship management cscm
CSCM Chapter 11 relationship management cscmCSCM Chapter 11 relationship management cscm
CSCM Chapter 11 relationship management cscm
 
CSCM Partnering
CSCM PartneringCSCM Partnering
CSCM Partnering
 
CSCM Communication in construction
CSCM Communication in constructionCSCM Communication in construction
CSCM Communication in construction
 
CSCM Material delivery problems cscm
CSCM Material delivery problems cscmCSCM Material delivery problems cscm
CSCM Material delivery problems cscm
 
BS 2 Escalators arrangement
BS 2 Escalators arrangementBS 2 Escalators arrangement
BS 2 Escalators arrangement
 
BS 2 Escalators 1of 2
BS 2 Escalators 1of 2BS 2 Escalators 1of 2
BS 2 Escalators 1of 2
 
BS 2 Group assignment brief question august 2016
BS 2 Group assignment brief  question august 2016BS 2 Group assignment brief  question august 2016
BS 2 Group assignment brief question august 2016
 
BS 2 Variable air volume systems
BS 2 Variable air volume systemsBS 2 Variable air volume systems
BS 2 Variable air volume systems
 
CSCM Supply chain management 312 cscm
CSCM Supply chain management 312 cscmCSCM Supply chain management 312 cscm
CSCM Supply chain management 312 cscm
 
CSCM Bim group assignment.docx
CSCM Bim group assignment.docxCSCM Bim group assignment.docx
CSCM Bim group assignment.docx
 
CSCM individual assignment
CSCM individual assignmentCSCM individual assignment
CSCM individual assignment
 
Management science group assignment MS
Management science group assignment MSManagement science group assignment MS
Management science group assignment MS
 
MS Tutorial 12 hrm
MS Tutorial 12 hrmMS Tutorial 12 hrm
MS Tutorial 12 hrm
 
MS Case study development for entrepreneur mark zuckerberg
MS Case study development for entrepreneur mark zuckerbergMS Case study development for entrepreneur mark zuckerberg
MS Case study development for entrepreneur mark zuckerberg
 
MS Lecture 7 leadership and motivation
MS Lecture 7 leadership and motivationMS Lecture 7 leadership and motivation
MS Lecture 7 leadership and motivation
 
MS Lecture 8 communication
MS Lecture 8 communicationMS Lecture 8 communication
MS Lecture 8 communication
 
MS Qsb 2413 group project 2016
MS Qsb 2413 group project 2016MS Qsb 2413 group project 2016
MS Qsb 2413 group project 2016
 

Recently uploaded

原版制作(Exeter毕业证书)埃克塞特大学毕业证完成信一模一样
原版制作(Exeter毕业证书)埃克塞特大学毕业证完成信一模一样原版制作(Exeter毕业证书)埃克塞特大学毕业证完成信一模一样
原版制作(Exeter毕业证书)埃克塞特大学毕业证完成信一模一样
78tq3hi2
 
一比一原版(AIS毕业证)奥克兰商学院毕业证成绩单如何办理
一比一原版(AIS毕业证)奥克兰商学院毕业证成绩单如何办理一比一原版(AIS毕业证)奥克兰商学院毕业证成绩单如何办理
一比一原版(AIS毕业证)奥克兰商学院毕业证成绩单如何办理
eygkup
 
TRAINEES-RECORD-BOOK- electronics and electrical
TRAINEES-RECORD-BOOK- electronics and electricalTRAINEES-RECORD-BOOK- electronics and electrical
TRAINEES-RECORD-BOOK- electronics and electrical
JohnCarloPajarilloKa
 
一比一原版(AUT毕业证)奥克兰理工大学毕业证成绩单如何办理
一比一原版(AUT毕业证)奥克兰理工大学毕业证成绩单如何办理一比一原版(AUT毕业证)奥克兰理工大学毕业证成绩单如何办理
一比一原版(AUT毕业证)奥克兰理工大学毕业证成绩单如何办理
mymwpc
 
Hand Gesture Control Robotic Arm using image processing.pptx
Hand Gesture Control Robotic Arm using image processing.pptxHand Gesture Control Robotic Arm using image processing.pptx
Hand Gesture Control Robotic Arm using image processing.pptx
wstatus456
 
What do the symbols on vehicle dashboard mean?
What do the symbols on vehicle dashboard mean?What do the symbols on vehicle dashboard mean?
What do the symbols on vehicle dashboard mean?
Hyundai Motor Group
 
EV Charging at Multifamily Properties by Kevin Donnelly
EV Charging at Multifamily Properties by Kevin DonnellyEV Charging at Multifamily Properties by Kevin Donnelly
EV Charging at Multifamily Properties by Kevin Donnelly
Forth
 
一比一原版(UNITEC毕业证)UNITEC理工学院毕业证成绩单如何办理
一比一原版(UNITEC毕业证)UNITEC理工学院毕业证成绩单如何办理一比一原版(UNITEC毕业证)UNITEC理工学院毕业证成绩单如何办理
一比一原版(UNITEC毕业证)UNITEC理工学院毕业证成绩单如何办理
bouvoy
 
new-HIFLY-TBR-catalogue size specification
new-HIFLY-TBR-catalogue size specificationnew-HIFLY-TBR-catalogue size specification
new-HIFLY-TBR-catalogue size specification
bosscmn
 
Globalfleet - global fleet survey 2021 full results
Globalfleet - global fleet survey 2021 full resultsGlobalfleet - global fleet survey 2021 full results
Globalfleet - global fleet survey 2021 full results
vaterland
 
一比一原版(Columbia文凭证书)哥伦比亚大学毕业证如何办理
一比一原版(Columbia文凭证书)哥伦比亚大学毕业证如何办理一比一原版(Columbia文凭证书)哥伦比亚大学毕业证如何办理
一比一原版(Columbia文凭证书)哥伦比亚大学毕业证如何办理
afkxen
 
AadiShakti Projects ( Asp Cranes ) Raipur
AadiShakti Projects ( Asp Cranes ) RaipurAadiShakti Projects ( Asp Cranes ) Raipur
AadiShakti Projects ( Asp Cranes ) Raipur
AadiShakti Projects
 
Manual despiece Yamaha fuera de borda pc_e40x_02.pdf
Manual despiece Yamaha fuera de borda pc_e40x_02.pdfManual despiece Yamaha fuera de borda pc_e40x_02.pdf
Manual despiece Yamaha fuera de borda pc_e40x_02.pdf
GermanValentini1
 
快速办理(napier毕业证书)英国龙比亚大学毕业证在读证明一模一样
快速办理(napier毕业证书)英国龙比亚大学毕业证在读证明一模一样快速办理(napier毕业证书)英国龙比亚大学毕业证在读证明一模一样
快速办理(napier毕业证书)英国龙比亚大学毕业证在读证明一模一样
78tq3hi2
 
53286592-Global-Entrepreneurship-and-the-Successful-Growth-Strategies-of-Earl...
53286592-Global-Entrepreneurship-and-the-Successful-Growth-Strategies-of-Earl...53286592-Global-Entrepreneurship-and-the-Successful-Growth-Strategies-of-Earl...
53286592-Global-Entrepreneurship-and-the-Successful-Growth-Strategies-of-Earl...
MarynaYurchenko2
 
Skoda Octavia Rs for Sale Perth | Skoda Perth
Skoda Octavia Rs for Sale Perth | Skoda PerthSkoda Octavia Rs for Sale Perth | Skoda Perth
Skoda Octavia Rs for Sale Perth | Skoda Perth
Perth City Skoda
 
Kaizen SMT_MI_PCBA for Quality Engineerspptx
Kaizen SMT_MI_PCBA for Quality EngineerspptxKaizen SMT_MI_PCBA for Quality Engineerspptx
Kaizen SMT_MI_PCBA for Quality Engineerspptx
vaibhavsrivastava482521
 
Digital Fleet Management - Why Your Business Need It?
Digital Fleet Management - Why Your Business Need It?Digital Fleet Management - Why Your Business Need It?
Digital Fleet Management - Why Your Business Need It?
jennifermiller8137
 
Here's Why Every Semi-Truck Should Have ELDs
Here's Why Every Semi-Truck Should Have ELDsHere's Why Every Semi-Truck Should Have ELDs
Here's Why Every Semi-Truck Should Have ELDs
jennifermiller8137
 
What Could Be Behind Your Mercedes Sprinter's Power Loss on Uphill Roads
What Could Be Behind Your Mercedes Sprinter's Power Loss on Uphill RoadsWhat Could Be Behind Your Mercedes Sprinter's Power Loss on Uphill Roads
What Could Be Behind Your Mercedes Sprinter's Power Loss on Uphill Roads
Sprinter Gurus
 

Recently uploaded (20)

原版制作(Exeter毕业证书)埃克塞特大学毕业证完成信一模一样
原版制作(Exeter毕业证书)埃克塞特大学毕业证完成信一模一样原版制作(Exeter毕业证书)埃克塞特大学毕业证完成信一模一样
原版制作(Exeter毕业证书)埃克塞特大学毕业证完成信一模一样
 
一比一原版(AIS毕业证)奥克兰商学院毕业证成绩单如何办理
一比一原版(AIS毕业证)奥克兰商学院毕业证成绩单如何办理一比一原版(AIS毕业证)奥克兰商学院毕业证成绩单如何办理
一比一原版(AIS毕业证)奥克兰商学院毕业证成绩单如何办理
 
TRAINEES-RECORD-BOOK- electronics and electrical
TRAINEES-RECORD-BOOK- electronics and electricalTRAINEES-RECORD-BOOK- electronics and electrical
TRAINEES-RECORD-BOOK- electronics and electrical
 
一比一原版(AUT毕业证)奥克兰理工大学毕业证成绩单如何办理
一比一原版(AUT毕业证)奥克兰理工大学毕业证成绩单如何办理一比一原版(AUT毕业证)奥克兰理工大学毕业证成绩单如何办理
一比一原版(AUT毕业证)奥克兰理工大学毕业证成绩单如何办理
 
Hand Gesture Control Robotic Arm using image processing.pptx
Hand Gesture Control Robotic Arm using image processing.pptxHand Gesture Control Robotic Arm using image processing.pptx
Hand Gesture Control Robotic Arm using image processing.pptx
 
What do the symbols on vehicle dashboard mean?
What do the symbols on vehicle dashboard mean?What do the symbols on vehicle dashboard mean?
What do the symbols on vehicle dashboard mean?
 
EV Charging at Multifamily Properties by Kevin Donnelly
EV Charging at Multifamily Properties by Kevin DonnellyEV Charging at Multifamily Properties by Kevin Donnelly
EV Charging at Multifamily Properties by Kevin Donnelly
 
一比一原版(UNITEC毕业证)UNITEC理工学院毕业证成绩单如何办理
一比一原版(UNITEC毕业证)UNITEC理工学院毕业证成绩单如何办理一比一原版(UNITEC毕业证)UNITEC理工学院毕业证成绩单如何办理
一比一原版(UNITEC毕业证)UNITEC理工学院毕业证成绩单如何办理
 
new-HIFLY-TBR-catalogue size specification
new-HIFLY-TBR-catalogue size specificationnew-HIFLY-TBR-catalogue size specification
new-HIFLY-TBR-catalogue size specification
 
Globalfleet - global fleet survey 2021 full results
Globalfleet - global fleet survey 2021 full resultsGlobalfleet - global fleet survey 2021 full results
Globalfleet - global fleet survey 2021 full results
 
一比一原版(Columbia文凭证书)哥伦比亚大学毕业证如何办理
一比一原版(Columbia文凭证书)哥伦比亚大学毕业证如何办理一比一原版(Columbia文凭证书)哥伦比亚大学毕业证如何办理
一比一原版(Columbia文凭证书)哥伦比亚大学毕业证如何办理
 
AadiShakti Projects ( Asp Cranes ) Raipur
AadiShakti Projects ( Asp Cranes ) RaipurAadiShakti Projects ( Asp Cranes ) Raipur
AadiShakti Projects ( Asp Cranes ) Raipur
 
Manual despiece Yamaha fuera de borda pc_e40x_02.pdf
Manual despiece Yamaha fuera de borda pc_e40x_02.pdfManual despiece Yamaha fuera de borda pc_e40x_02.pdf
Manual despiece Yamaha fuera de borda pc_e40x_02.pdf
 
快速办理(napier毕业证书)英国龙比亚大学毕业证在读证明一模一样
快速办理(napier毕业证书)英国龙比亚大学毕业证在读证明一模一样快速办理(napier毕业证书)英国龙比亚大学毕业证在读证明一模一样
快速办理(napier毕业证书)英国龙比亚大学毕业证在读证明一模一样
 
53286592-Global-Entrepreneurship-and-the-Successful-Growth-Strategies-of-Earl...
53286592-Global-Entrepreneurship-and-the-Successful-Growth-Strategies-of-Earl...53286592-Global-Entrepreneurship-and-the-Successful-Growth-Strategies-of-Earl...
53286592-Global-Entrepreneurship-and-the-Successful-Growth-Strategies-of-Earl...
 
Skoda Octavia Rs for Sale Perth | Skoda Perth
Skoda Octavia Rs for Sale Perth | Skoda PerthSkoda Octavia Rs for Sale Perth | Skoda Perth
Skoda Octavia Rs for Sale Perth | Skoda Perth
 
Kaizen SMT_MI_PCBA for Quality Engineerspptx
Kaizen SMT_MI_PCBA for Quality EngineerspptxKaizen SMT_MI_PCBA for Quality Engineerspptx
Kaizen SMT_MI_PCBA for Quality Engineerspptx
 
Digital Fleet Management - Why Your Business Need It?
Digital Fleet Management - Why Your Business Need It?Digital Fleet Management - Why Your Business Need It?
Digital Fleet Management - Why Your Business Need It?
 
Here's Why Every Semi-Truck Should Have ELDs
Here's Why Every Semi-Truck Should Have ELDsHere's Why Every Semi-Truck Should Have ELDs
Here's Why Every Semi-Truck Should Have ELDs
 
What Could Be Behind Your Mercedes Sprinter's Power Loss on Uphill Roads
What Could Be Behind Your Mercedes Sprinter's Power Loss on Uphill RoadsWhat Could Be Behind Your Mercedes Sprinter's Power Loss on Uphill Roads
What Could Be Behind Your Mercedes Sprinter's Power Loss on Uphill Roads
 

CSCM Causes of project delay

  • 1. Causes of construction delay: traditional contracts Abdalla M. Odeh a, *, Hussien T. Battaineh b a Jordan University of Science and Technology, PO Box 3030, Irbid 22110, Jordan b College of Engineering and Applied Science, Western Michigan University, Kalamazoo, MI 49008, USA Abstract Many projects experience extensive delays and thereby exceed initial time and cost estimates. In addition to imparting the eco- nomic feasibility of capital projects, extensive delays provide a fertile ground for costly disputes and claims. This paper presents the ®ndings of a survey aimed at identifying the most important causes of delays in construction projects with traditional type contracts from the viewpoint of construction contractors and consultants. Results of the survey indicate that contractors and consultants agreed that owner interference, inadequate contractor experience, ®nancing and payments, labor productivity, slow decision mak- ing, improper planning, and subcontractors are among the top ten most important factors. It is hoped that these ®ndings will guide e€orts to improve the performance of the construction industry, and will be useful to international engineering and construction ®rms seeking a share in the Jordanian and the regional markets. # 2001 Elsevier Science Ltd and IPMA. All rights reserved. Keywords: Construction management; Construction in Jordan; Construction delays 1. Introduction The successful execution of construction projects and keeping them within estimated cost and prescribed schedules depend on a methodology that requires sound engineering judgment [1]. To the dislike of owners, contractors and consultants, however, many rojects experience extensive delays and thereby exceed initial time and cost estimates. This problem is more evident in the traditional or adversarial type of contracts in which the contract is awarded to the lowest bidder Ð the awarding strategy of the majority of public projects in developing countries including Jordan. Although the construction industry in the Middle East has su€ered ever since the Gulf war, recent events in the region coupled with the restructuring of economies, joining regional and global free trade organizations, and attracting foreign investments are expected to yield an unprecedented growth in the construction activities. The region is in desperate need for development projects in many areas, especially in the ®elds of water collection and distribution, tourism and housing. As a result, an unprecedented number of large-scale projects are currently under construction and in the planning and contract awarding stages. In Jordan, for example, the volume of construction projects awarded in 1998 was 944 million Jordanian Dinar1 (JD) of which 155 millions went to international contractors [2]. These projects include three dams with contract values of over 87.7 million JD. Another dam with an estimated cost of 200 million JD is in the contract award phase. A major water transport pipeline extending over 300 km with an estimated cost of 100 million JD is in the ®nal design stage. Unfortunately, the construction industry in Jordan is not adequately prepared for the project management problems accompanying the anticipated boom in construction activ- ities and the increasing complexity of projects. Recent ®ndings [3,4] revealed that delays in public projects in Jordan are extensive and warrant further investigation. It is imperative to understand the underlying causes of such delays for any corrective actions to be e€ective. 2. Related work Leishman [5] presented the legal consequences of delays in construction. Herbsman et al.[6] studied the e€ect of delays on cost and quality. Yates [7] developed a decision support system for construction delay analy- sis called (DAS). The main categories of delays in DAS 0263-7863/01/$20.00 # 2001 Elsevier Science Ltd and IPMA. All rights reserved. PII: S0263-7863(00)00037-5 International Journal of Project Management 20 (2002) 67±73 www.elsevier.com/locate/ijproman 1 1 JD=$1.424, the rate of exchange on 1 June 2000.* Corresponding author.
  • 2. include engineering, equipment, external delays, labor, management, material, owner, subcontractors, and weather. Ogunlana et al. [8] studied the delays in building project in Thailand, as an example of developing economies. They concluded that the problems of the construction industry in developing economies can be nested in three layers: (1) problem of shortages or inadequacies in industry infrastructure, mainly supply of resources; (2) problems caused by clients and consultants; and (3) problems caused by incompetence of contractors. Kumaraswamy et al. [9] surveyed the causes of construction delays in Hong Kong as seen by clients, contractors and consultants, and examined the factors a€ecting productivity. The survey revealed di€erences in perceptions of the relative sig- ni®cance of factors between the three groups, indicative of their experiences, possible prejudices and lack of e€ective communication. Mans®eld et al. [10] studied the causes of delay and cost overrun in construction projects in Nigeria. The results showed that the most important factors are ®nancing and payment for com- pleted works, poor contract management, changes in site conditions, shortage of material, and improper planing. Assaf et al. [11] studied the causes of delay in large building construction projects in Saudi Arabia. The most important causes of delay included approval of shop drawings, delays in payments to contractors and the resulting cash problems during construction, design changes, con¯icts in work schedules of subcontractors, slow decision making and executive bureaucracy in the owners' organizations, design errors, labor shortage and inadequate labor skills. Mezher et al. [12] conducted a survey of the causes of delays in the construction industry in Lebanon from the viewpoint of owners, contractors and architectural/engineering ®rms. It was found that owners had more concerns with regard to ®nancial issues, contractors regarded contractual relation- ships the most important, while consultants considered project management issues to be the most important causes of delays. Battaineh [3] evaluated the progress reports of 164 building and 28 highway projects constructed during the period 1996±1999 in Jordan. The results indicate that delays are extensive: the average ratio of actual com- pletion time to the planned contract duration is 160.5% for road projects and 120.3% for building projects. Al-Momani [4] conducted a quantitative analysis of construction delays by examining the records of 130 public building projects constructed in Jordan during the period of 1990±1997. The researcher presented regression models of the relationship between actual and planned project duration for di€erent types of building facilities. The analysis also included the reported frequencies of time extensions for the di€erent causes of delays. The researcher concluded that the main causes of delay in construction projects relate to designers, user changes, weather, site conditions, late deliveries, eco- nomic conditions, and increase in quantities. However, such conclusion can be misleading. First, they included causes which are limited to those for which contractors are entitled to time extension. The analysis does not cover causes of delay for which the contractor is responsible, such as those related to labor and equipment, planning and site management, construction methods, adequacy and capability of contractor. Second, they are based on the reported number of time extensions not on the extent of delay attributed to the di€erent causes of delay. Despite the moderate weather in Jordan, for example, it was ®gured among the major causes of delay because a time extension was granted for all public projects under construction in the winter of 1991 as a result of an unprecedented severe storm that had a very low probability of occurrence. Third, they are drawn from records of public building projects and one would question their validity to other types of construction projects such as industrial facilities, water collection treatment and distribution, and highway construction. 3. Research design and objectives The objective of this research is to identify the major causes of delay in the construction industry and to assess the relative importance of these causes for the traditional adversarial type of contracts from the viewpoint of construction contractors and consultants. First, a survey questionnaire was developed to assess the perceptions of contractors and consultants of the relative importance of construction delay causes. Second, the questionnaire was distributed to a random sample of contractors and consultants working on large projects in Jordan. Responses to the questionnaire were then collected and analyzed. The analysis included ranking the di€erent causes according to the relative importance indexes for both contractors and consultants responses. The Spearman's rank correlation coecient was then used to test associa- tion between the contractors and consultants ranking. 4. Causes of delay The survey is based on 28 well recognized causes of delay to which participants were asked to indicate their level of importance of each cause. These causes were categorized into the following 8 major groups: 1. Client related factors include ®nance and pay- ments of completed work, owner interference, slow decision making and unrealistic contract duration imposed by owners. 2. Contractor related factors include site manage- ment, improper planning, inadequate contractor 68 A.M. Odeh, H.T. Battaineh / International Journal of Project Management 20 (2002) 67±73
  • 3. experience, mistakes during construction, impro- per construction methods and delays caused by subcontractors. Delays caused by subcontractors are included among the contractor's factors because the latter is fully responsible for the delays caused by his subcontractors. 3. Consultant related factors include contract man- agement, preparation and approval of drawings, quality assurance/control, and long waiting time for approval of tests and inspections. 4. Material factors include quality and shortage. 5. Labor and equipment factors include labor supply, labor productivity, and equipment availability and failure. 6. Contract factors include changed orders and mis- takes and discrepancies in contract documents. 7. Contractual relationships factors include major disputes and negotiations during construction, inappropriate organizational structure linking all parties involved in the project, and lack of com- munication between these parties. 8. External factors include weather conditions, chan- ges in regulations, problems with neighbors and site conditions. Other signi®cant issues of concern such as political, socio-economical and religious factors are dismissed because it is felt that people in this part of the world are very sensitive to these issues to a degree that might pre- judice their responses. 5. Survey methodology The scope of the research included large public and private buildings, roads, and water and sewer projects in Jordan. Given this scope, the questionnaire was dis- tributed to a random sample of 100 contractors and 50 consultants representing the di€erent specialization of contractors and consultants working on large projects (contract value>1 million JD). Tables 1 and 2 show the distribution of the population, sample, and respondents among the di€erent specializations of contractors and consultants classi®ed by the Ministry of Public Works and Housing to take on large projects. The sample size of each specialization is proportional to the distribution of the population of the di€erent specializations. Given the sample size, the samples were selected randomly from the population in each specialization. The respondents were asked to express their percep- tion of the relative importance of each of the 28 causes of delays as either: extreme, very, moderate, slight, or not important. The questionnaire was personally handed over to respondents, and an interviewer was available to answer questions about the questionnaire and to ensure that the questionnaire is administered by VPs or project managers. This mode of follow-up communication led to the return of 82 completed questionnaires: 63 con- tractors and 19 consultants. 6. Analysis of responses To determine the ranking of di€erent causes from the point of view of contractors and of consultants, the relative importance index (I) was computed as: I ˆ P5 iˆ1 WiXi P5 iˆ1 Xi where: i =response category index=1, 2, 3, 4, and 5 for not-, slightly-, moderately-, very-, and extremely- important, respectively. Wi =the weight assigned to the ith response=0, 1, 2, 3, 4, respectively. Xi =frequency of the ith response given as percentage of the total responses for each cause. The indexes were then ranked, and the results are shown in Table 3. Calculating the average indexes of the causes in each group gives the relative importance index of the mean groups. The mean indexes and the ranking of all groups are shown in Table 4. The Spearman's correlation coecients of the ranking of contractors and consultants for all the causes and for the main Table 1 Distribution of population, sample and respondents of the di€erent specializations of contractors Specialization of contractors Buildings Roads Water and sewer Total Population 222 141 80 265 Sample 50 32 18 100 Respondents 39 27 16 82 Table 2 Distribution of population, sample and respondents of the di€erent specializations of consultants Specialization of consultants Buildings Roads Water and Sewer Total Population 42 22 16 80 Sample 26 14 10 50 Respondents 9 5 5 19 A.M. Odeh, H.T. Battaineh / International Journal of Project Management 20 (2002) 67±73 69
  • 4. categories of delays are 0.789 and 0.762, respectively. These correlation coecients are calculated for the ranking shown in Tables 3 and 4 using the following equation [13]: rS ˆ 1 À 6 P d2 N…N2 À 1† where: rS=Spearman's rank correlation coecient. d =the di€erence in ranking between the contractors and the consultants, and N=the number of variables, equals to 28 and 8 for all the causes and for the main categories of causes of delay, respectively. The somewhat high values of rank correlation coe- cients indicate strong agreement between contractors and consultants on the ranking of all the factors and of the main groups of factors. This association between the ranking of contractors and consultants is veri®ed by a hypothesis testing at 95% signi®cance where Z ˆ rS  N À 1 p Table 3 Relative importance index and ranking of delay factors Contractors Consultants Category Factor Index Rank Index Rank Client Finance and payments of completed work 3.30 4 3.32 2 Owner interference 3.51 2 3.21 4 Slow decision-making by owners 3.24 8 3.16 5 Unrealistic imposed contract duration 3.08 13 3.11 6 Contractor Subcontractors 3.21 9 3.26 3 Site management 3.29 5 2.58 13 Construction methods 3.29 5 2.37 17 Improper planning 3.14 10 2.95 8 Mistakes during construction 2.56 17 2.74 11 Inadequate contractor experience 3.37 3 3.37 1 Consultant Contract management 3.10 12 3.00 7 Preparation and approval of drawings 2.32 21 2.21 19 Quality assurance/control 2.06 25 2.11 21 Waiting time for approval of tests and inspections 2.46 18 2.47 15 Material Quality of material 1.75 26 2.00 23 Shortage in material 3.11 11 2.79 10 Labor and equipment Labor supply 2.63 16 2.63 12 Labor productivity 3.60 1 2.89 9 Equipment availability and failure 3.25 7 2.42 16 Contract Change orders 2.40 19 1.79 26 Mistakes and discrepancies in contract documents 3.05 14 2.05 22 Contractual relationships Major disputes and negotiations 2.94 15 2.16 20 Inappropriate overall organizational structure linking all parties to the project 2.27 22 2.26 18 Lack of communication between the parties 2.38 20 2.53 14 External factors Weather condition 2.19 23 1.95 24 Regulatory changes and building Code 1.70 27 1.16 28 Problems with neighbors 1.59 28 1.58 27 Unforeseen ground conditions 2.10 24 1.84 25 Table 4 Importance index and ranking of major delay categories Contractors Consultants Category Index Rank Index Rank Client 3.28 1 3.20 1 Contractor 3.14 3 2.88 2 Consultant 2.48 6 2.45 4 Material 2.43 7 2.39 5 Labor and equipment 3.16 2 2.65 3 Contract 2.72 4 1.92 7 Contractual relationships 2.53 5 2.32 6 External factors 1.89 8 1.63 8 70 A.M. Odeh, H.T. Battaineh / International Journal of Project Management 20 (2002) 67±73
  • 5. 7. Discussion of results The ranking of the relative importance of the delay factors, Table 3, shows that owner interference, inadequate contractor experience, and ®nancing and payments of completed work made the top ®ve signi®cant factors for both contractors and consultants. Moreover, labor pro- ductivity, site management, slow decision making, con- struction methods, improper planning and subcontractors are among the top ten ranked factors of both groups. The following is a brief discussion of the ranking of the relative importance of the groups of delay factors, as deducted from Tables 3 and 4. 7.1. Client The client related group of delay factors was the most important group to both contractors and consultants. This is mainly due to ®nancing issues and owner inter- ference, which are considered very important by both parties. It was interesting to ®nd out that slow decision by owners and unrealistic contract duration are of more importance to consultants than to contractors. This is because contractors considered operational issues, such as labor productivity and equipment availability and failure, of more importance. Unlike contractors, however, consultants considered the client related factors to be more important than operational ones. 7.2. Contractor Both contractors and consultants ranked this group of causes very high. It is worth noticing that consultants are mainly concerned with technical factors such as inade- quate contractors experience, delays caused by subcon- tractors, and improper planning, while contractors are more concerned with managerial and operational factors such as site management and construction methods. Inadequate contractor experience was the most important factor in this group. This can be attributed to the contract awarding procedure where most projects are awarded to the lowest bidder. Moreover, local con- tractors, solely or through joint ventures, are being awarded large and complex projects in which they have little experience because such projects were virtually limited to international contractors in the past. Delays caused by subcontractors are also of high importance to consultants. This can be attributed to inadequate experience of subcontractors, the bid shopping practice of general contractors, and to improper plan- ning and coordination. Improper planning is also troublesome to contractors and consultants. Local contractors are reluctant to use scheduling techniques and to update schedules on a regular basis. Despite the fact that contractors are required to provide work schedules on most projects, the schedule is often a summary schedule that is hardly updated during construction. This is substantiated by the fact that only 8 of the 63 sampled contractors responded positively to updating schedules on their projects. Delays caused by improper construction methods are more important to contractors than to consultants. Fluctuation in the construction market and the seasonal nature of the industry has forced many contractors towards diversity. As a result, they do not focus on one line-of-work and try to adopt advanced methods and techniques. Site management is another important cause of delay to contractors. This is due to the reluctance of contractors to invest in planning and control and to the lack of pro- fessional construction managers. The majority of site managers are civil engineers with a good work experi- ence but little training or education in management. 7.3. Consultants Neither contractors nor consultants ranked this group of factors high among the major groups of delay causing fac- tors. Contrary to what is expected, consultants consistently ranked each of these causes higher than contractors. The highest ranked factor among these causes was contract management. This could be attributed to the lack of authority the owners are willing to delegate to consultants enabling them to manage the contract e€ectively. This ®nding is consistent with the high ranking of owner interference and the low ranking of factors over which the consultants are usually granted authority. The latter factors include preparation and approval of drawings, quality assurance/control, and approval of tests and inspections. 7.4. Material The group of material related causes received low ranking by both contractors and consultants. Quality of material was among the least important causes because most of the available material is local with little variation in quality, especially for cement, steel, and asphalt that are produced by a limited number of producers. Shortage of material received higher ranking than quality. This is particularly true for imported material that may take a considerable time to procure. 7.5. Labor and equipment This group of causes were ranked high, second by contractors and third by consultants. As expected, this group of causes is more important to contractors than to consultants. This was true for labor productivity and for equipment availability and failure. While labor supply is not that important considering the relatively inex- pensive ¯ux of foreign and local laborers, the pro- ductivity of the labor forces was the top ranked factor for contractors. This may be attributed to lack of A.M. Odeh, H.T. Battaineh / International Journal of Project Management 20 (2002) 67±73 71
  • 6. incentives for higher productivity, lack of or improper training, and absence of trade unions or associations that regulate, train, and classify construction trades. The high ranking of contractors of equipment avail- ability and failure indicate problems associated with ownership of new equipment, maintenance and repair, and availability and reliability of the rental option. 7.6. External factors External factors were the lowest ranked group of factors by both parties. It seems that all parties are familiar with these factors and are able to deal with them e€ectively without causing any major delays. Of course, the moder- ate weather conditions in Jordan coupled with low levels of water tables in addition to well established regulations and building code contribute to this low ranking. 7.7. Contract This group of causes had more di€erence in ranking than any other group. While it was considered important and ranked fourth by contractors, it was unimportant and ranked only seventh by consultants. Contrary to contractors, consultants who are usually empowered to issue changed orders and to correct mistakes and dis- crepancies in contract documents are less critical of their role in causing such delays. 7.8. Contractual relationships This group of causes was ranked low by contractors and consultants. Relatively, factors relating to organization and communication were more important to con- sultants than to contractors. Delays caused by disputes and negotiations were more important to contractors, especially for public projects in Jordan where arbitra- tion is not allowed and where legal recourse through courts takes a considerable time. 8. Conclusions and recommendations According to contractors, labor productivity was the most important delay factor. Inadequate contractor experience, however, was the most important delay factor to consultants. All parties generally agreed on the ranking of the individual delay factors. They agreed that inade- quate contractor experience, owner interference, and ®nancing of work were among the top ®ve most important factors. Moreover, delays caused by subcontractors, slow decision making by owners, improper planning, and labor productivity were among the top ten most impor- tant factors for both parties. Operational factors such as labor productivity, con- struction methods, site management, and equipment availability and failure were more important to con- tractors than to consultants. Contractors were also more concerned with factors related to contract clauses that may alter their contractual obligations and rights. These factors include changed orders, mistakes and discrepancies in contract documents and major disputes and negotiations. However, factors dealing with sub- contracting, planning, organizing and communicating were more important to consultants than to contractors. Delays are costly and often result in disputes and claims, impair the feasibility for project owners, and retard the development of the construction industry. To improve the situation, the ®ndings of this research must be addressed by a joint e€ort of all participants in the construction industry. This calls for: 1. Enforcing liquidated damage clauses and o€ering incentives for early completion. 2. Developing human resources in the construction industry through proper training and classifying of craftsmen. This calls for providing incentives such as o€ering a tax deduction on money spent on training, and for authorizing trade unions or other agencies to regulate, follow-up on training, and classify trades. Developing human resources also applies to construc- tion engineers who usually lack adequate managerial skills. There is an urgent need for o€ering training courses in scheduling, time and cost control, inform- ation systems, and management of human resources. 3. Adopting a new approach to contract award pro- cedure by giving less weight to prices and more weight to the capabilities and past performance of contractors. 4. Adopting new approaches to contracting, such as design-build and construction management (CM) types of contracts. Such contracts reduce delays by limiting owner interference, improving the design, and improving the contractual relationships among all parties to the project. References [1] Hancher DE, Rowings IE. Setting highway construction contract duration. Journal of Construction Engineering and Management, ASCE 1981;107(2):169±79. [2] Department of public contracts. The Annual book, the Ministry of Public Works and Housing, Jordan, 1998. [3] Battaineh HT. Information system of progress evaluation of public projects in Jordan, MSc thesis, Dept. of Civil Engineering, Jordan Univ. of Science and Technology, Irbid, Jordan, 1999. [4] Al-Moumani HA. Construction delay:a quantitative analysis. International Journal of Project Management 2000;18:51±9. [5] Leishman DM. Protecting engineer against construction delay claims: NDC. Journal of Management in Engineering 1991;7(3):319±33. [6] Herbsman ZJ, Chen WT, Epstein WC. Time is money:innovative contracting methods in highway construction. Journal of Construc- tion Engineering and Management, ASCE 1995;121(3):273±81. [7] Yates J. Construction decision support system for delay analysis. Journal of Construction Engineering and Management, ASCE 1993;119(2):226±44. 72 A.M. Odeh, H.T. Battaineh / International Journal of Project Management 20 (2002) 67±73
  • 7. [8] Ogunlana SO, Promkuntong K. Construction delays in a fast- growing economy: comparing Thailand with other economies. International Journal of Project Management 1996;14(1):37±45. [9] Kumaraswamy MM ChanWM. Contributors to construction delays. Construction Management and Economics 1998;16:17±29. [10] Mans®eld NR, Ugwu OO, Doran T. Causes of delay and cost overruns in Nigerian construction projects. International Journal of Project Management 1994;12(4):254±60. [11] Assaf SA, Al-Khalil M, Al-Hazmi M. Causes of delay in large building construction projects. Journal of Management in Engi- neering ASCE 1995;11(2):45±50. [12] Mezher TM, Tawil W. Causes of delays in the construction industry in Lebanon. Engineering Construction and Archi- tectural Management Journal 1998;5(3):251±60. [13] Dowdy S, Wearden S. Statistics for research. 2nd Ed. New York: John Wiley & Sons, 1985. A.M. Odeh, H.T. Battaineh / International Journal of Project Management 20 (2002) 67±73 73