This document contains a summary of construction progress for pipe culverts, box culverts, and bridges during the month of February. For pipe culverts, work included excavation, concrete pouring, and backfilling at several locations between km 36.859 to 31.249. For box culverts, formwork and concrete work was completed at km 22.824, 21.566, and 9.115. For bridges, concrete work continued on the second lift of an abutment at km 4.843 and the bearing beam capping of another abutment.