SlideShare a Scribd company logo
Gauff Ingenieure
Internal Report 1/5 Signature
Gauff Ingenieure
PIPE CULVERTS COMPLETED DURING THE MONTH OF FEBRUARY.
- Surround:-km 36.859
- Bed and surround – 35.579 (1x900mm diameter),32.740 (1x900mm diameter), 31.249 (2x1200mm
diameter)
BOX CULVERTS COMPLETED DURING THE MONTH.
- Top deck – km 21.824
- Bottom slab and Top deck:- km 21.566/9.115
BRIDGES COMPLETED DURING THE MONTH.
- Walling/Shaft:- km-4.843(2nd
lift abutment 2)/ 52.160 (Abutment 1 and 2, Pier head capping 1
- Top deck:-NILL
Internal Report 2/5 Signature
Gauff Ingenieure
STRUCTURAL BRIEF FOR THE MONTH OF FEBRUARY
BILL No 8. Culverts and drainage works.
Pipe culverts
Km 36.859(2x1200mm)
- Formwork erection for surround, wing walls and head walls including and pouring of concrete class
25/20.
- Stripping of formwork for wing walls, head beam and surround.
- Back filling both sides of access pipe culverts 1st to 8th layers
Km 36.573 (1x900mm)
- Excavation, filling under structures and pouring of blinding concrete
- Fixing of formwork for bottom slab including Pouring of concrete class 25/20.
- Formwork erection for surround, wing walls and head walls including pouring of concrete for surround
class 25/20.
- Stripping of formwork for wing walls, head beam and surround.
- Backfilling to 7th
layer completed
Km 32.740 (1x900mm)
- Excavation, filling under structures and pouring of blinding concrete
- Fixing of formwork for bottom slab including Pouring of concrete class 25/20.
- Formwork erection for surround, wing walls and head walls including placing of concrete for surround
class 25/20.
- Stripping of formwork for wing walls, head beam and surround.
Km 31.249 (2x1200mm)
- Excavation, filling under structures and pouring of blinding concrete
- Fixing of formwork for bottom slab including Pouring of concrete class 25/20.
- Formwork erection for surround, wing walls and head walls including placing of concrete for surround
class 25/20 Stripping of formwork for wing walls, head beam and surround.
- Stripping of formwork for wing walls, head beam and surround.
Backfilling of completed cross pipe culverts:-
- 39.112/37.075/36.859/36.573/36.294/35.979/35.880
Stone pitching for protection of side slopes to cross pipe culverts
- 50.704/49.206/48.358/48.168/48.138
Setting out of pipe culverts:-
- 27.620/26.160/
Lorry park traffic island and footpath at km 70.880RHS and 70.600LHS (Log logo)
- Setting out of both traffic island and footpath.
- Excavation, placing and concreting of reinforced concrete bollards to the traffic island
- Erection of formwork and fixing reinforcements BRC MeshA252 double layer to the base of both traffic
island and footpath.
- Pouring of concrete class 25/20 to traffic island and footpath, curing and removal of formwork.
Box culverts
- Stone pitching and gabion protection works completed on the following box culverts:-
55.659/55.742/55.820/54.398/54.718/64.880/64.956/61.171/61.376/54.718/54.398/63.350.
- Stone pitching and gabion protection in progress at km 67.050
Internal Report 3/5 Signature
Gauff Ingenieure
Km 30.675 (5cell 3.0x2.5m).
- Backfilling to both sides of walls and wing walls side (1st
and 12th
layer.)
Km 29.658(2 cell 2.0x1.5m).
- Backfilling to both sides of walls and wing walls side (1st
and 8th
layer.)
Km 0.447 (3 cell 3.0x2.0m)
- Removal of existing Armco pipe culvert
- Setting out and excavation done.
- Back filling of under structures 1 and 2nd
layers done.
Km 1.477 (4 cell 3.0x2.0m)
- Removal of existing Armco/concrete pipe culvert
- Setting out and excavation done.
- Back filling under structures with selected material done (1 Layer)
Km 22.824 (1 cell 3.0x2.0m)
- Formwork erection of shear walls, wing walls, winglets, top deck and headwalls including pouring of
structural concrete class 30/20.
- Removal of external formwork.
Km 21.566 (2 cell 3.0x2.0m)
- Formwork erection for the base slab and pouring of structural concrete class 30/20
- Erection of formwork for shear wall, wing walls, winglets and top deck.
- Pouring of structural concrete class 30/20 for the walls and top deck slab.
- External formwork removal done.
Km 9.115 (2 cell 2.0x1.5m)
- Excavation, backfilling under structures and compaction.
- Pouring of non-structural concrete class 15/20 for blinding
- Erection of formwork for the base lab and pouring of structural concrete class 30/20
- Erection of formwork for the shear walls, wing walls, winglets and top deck including pouring of
structural concrete class 30/20.
BILL No 21. Bridge works
New bridge at km 52.160
- Fixing of formwork, steel for pier head of bridge pier 1 Merille side and placing in position of stainless
dowel including pouring of concrete class 30/20.
- Fixing of formwork, steel reinforcement bars for bearing beam capping/placing in position of stainless
dowel bars, Parapet walls and wing walls for both abutment 1 and 2 including pouring of structural
concrete class 30/20.
New bridge at km 20.600
- NIL
New bridge at km 4.843
- Erection of formwork and fixing of steel reinforcement bars for the 2nd
lift of abutment 2 Marsabit side
Internal Report 4/5 Signature
Gauff Ingenieure
and pouring of structural concrete class 30/20
- Erection of formwork and steel reinforcement bars for the bearing beam capping of abutment 2
Marsabit side (3rd
lift)
- Fixing of steel reinforcement bars for the 2nd
lift of abutment 1 Merille side in progress.
-
Internal Report 5/5 Signature
Gauff Ingenieure
and pouring of structural concrete class 30/20
- Erection of formwork and steel reinforcement bars for the bearing beam capping of abutment 2
Marsabit side (3rd
lift)
- Fixing of steel reinforcement bars for the 2nd
lift of abutment 1 Merille side in progress.
-
Internal Report 5/5 Signature

More Related Content

What's hot

Method Statement Kota Kasablanka 3
Method Statement Kota Kasablanka 3Method Statement Kota Kasablanka 3
Method Statement Kota Kasablanka 3
Panji Krisnamurti
 
Design basis report on-14.11.2016
Design basis report  on-14.11.2016Design basis report  on-14.11.2016
Design basis report on-14.11.2016
bhavesh raysoni
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
Minh Bui Si
 
Site design slides final presentation
Site design slides final presentationSite design slides final presentation
Site design slides final presentation
Cory Barnes
 
Structural analysis
Structural analysisStructural analysis
Structural analysis
Jil Sheth
 
Project bowstring : A perspective on revitalizing Janata Bazaar
Project bowstring : A perspective on revitalizing Janata BazaarProject bowstring : A perspective on revitalizing Janata Bazaar
Project bowstring : A perspective on revitalizing Janata Bazaar
Nishanth Patil
 

What's hot (20)

Method Statement Kota Kasablanka 3
Method Statement Kota Kasablanka 3Method Statement Kota Kasablanka 3
Method Statement Kota Kasablanka 3
 
DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)
 
Cj32534539
Cj32534539Cj32534539
Cj32534539
 
Industrial training seminar PPT
Industrial training seminar PPTIndustrial training seminar PPT
Industrial training seminar PPT
 
Document
DocumentDocument
Document
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report final
 
GRC Cable Trough & Elevated Channel - Rail Cable Protection & Support
GRC Cable Trough & Elevated Channel - Rail Cable Protection & SupportGRC Cable Trough & Elevated Channel - Rail Cable Protection & Support
GRC Cable Trough & Elevated Channel - Rail Cable Protection & Support
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Design basis report on-14.11.2016
Design basis report  on-14.11.2016Design basis report  on-14.11.2016
Design basis report on-14.11.2016
 
Metro Construction
Metro ConstructionMetro Construction
Metro Construction
 
Expansion joint
Expansion joint Expansion joint
Expansion joint
 
Project Management - Marina bay Sands
Project Management - Marina bay SandsProject Management - Marina bay Sands
Project Management - Marina bay Sands
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
industrial training report
industrial training reportindustrial training report
industrial training report
 
Site design slides final presentation
Site design slides final presentationSite design slides final presentation
Site design slides final presentation
 
Structural analysis
Structural analysisStructural analysis
Structural analysis
 
Closure Report
Closure ReportClosure Report
Closure Report
 
Project bowstring : A perspective on revitalizing Janata Bazaar
Project bowstring : A perspective on revitalizing Janata BazaarProject bowstring : A perspective on revitalizing Janata Bazaar
Project bowstring : A perspective on revitalizing Janata Bazaar
 
Drawings Required
Drawings RequiredDrawings Required
Drawings Required
 
U-BOOT BETON TECHNOLOGY
U-BOOT BETON TECHNOLOGYU-BOOT BETON TECHNOLOGY
U-BOOT BETON TECHNOLOGY
 

Viewers also liked (13)

Mean girls productions presents2
Mean girls productions presents2Mean girls productions presents2
Mean girls productions presents2
 
Presentation 1
Presentation 1 Presentation 1
Presentation 1
 
Presentation MGEV Group D
Presentation MGEV Group DPresentation MGEV Group D
Presentation MGEV Group D
 
Rhdzz
RhdzzRhdzz
Rhdzz
 
Yelti princes girl
Yelti princes girlYelti princes girl
Yelti princes girl
 
Pc fan presentation
Pc fan presentationPc fan presentation
Pc fan presentation
 
Call yurni rusdiana
Call yurni rusdianaCall yurni rusdiana
Call yurni rusdiana
 
Siste Digital Logika Gate
Siste Digital Logika GateSiste Digital Logika Gate
Siste Digital Logika Gate
 
Akibat merokok
Akibat merokokAkibat merokok
Akibat merokok
 
Mql4 manual
Mql4 manualMql4 manual
Mql4 manual
 
Griffin chap07
Griffin chap07Griffin chap07
Griffin chap07
 
Griffin chap03
Griffin chap03Griffin chap03
Griffin chap03
 
One minute manager
One minute managerOne minute manager
One minute manager
 

Similar to Monthly brief for structures in april (leisamis sde)

SW Presentation-SC (05.09.2021).pptx
SW Presentation-SC (05.09.2021).pptxSW Presentation-SC (05.09.2021).pptx
SW Presentation-SC (05.09.2021).pptx
LeDuc49898
 
Road work construction proxy(2)
Road work   construction proxy(2)Road work   construction proxy(2)
Road work construction proxy(2)
FeteneBefekadu
 
WS RC Tank Debeljaca (700m3)
WS RC Tank Debeljaca (700m3)WS RC Tank Debeljaca (700m3)
WS RC Tank Debeljaca (700m3)
Vladimir Popovic
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
kiransuresh7
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design Presentation
Keith Kong
 
Ilias Michalis PMV Workshop Dubai 2014
Ilias Michalis PMV Workshop Dubai 2014Ilias Michalis PMV Workshop Dubai 2014
Ilias Michalis PMV Workshop Dubai 2014
ILIAS MICHALIS
 
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdfTender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
ssuserd43de8
 

Similar to Monthly brief for structures in april (leisamis sde) (20)

Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problem
 
SW Presentation-SC (05.09.2021).pptx
SW Presentation-SC (05.09.2021).pptxSW Presentation-SC (05.09.2021).pptx
SW Presentation-SC (05.09.2021).pptx
 
Road work construction proxy(2)
Road work   construction proxy(2)Road work   construction proxy(2)
Road work construction proxy(2)
 
What are Highways Works, Street works, Road works and Diversionary Works
What are Highways Works, Street works, Road works and Diversionary WorksWhat are Highways Works, Street works, Road works and Diversionary Works
What are Highways Works, Street works, Road works and Diversionary Works
 
WS RC Tank Debeljaca (700m3)
WS RC Tank Debeljaca (700m3)WS RC Tank Debeljaca (700m3)
WS RC Tank Debeljaca (700m3)
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design Presentation
 
Car park bq
Car park bqCar park bq
Car park bq
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Niand work profile
Niand work profileNiand work profile
Niand work profile
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
 
superstructure ppt.ppt
superstructure ppt.pptsuperstructure ppt.ppt
superstructure ppt.ppt
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical Design
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
IRJET- A Study on Seismic Analysis of RC Framed Structures on Varying Slo...
IRJET-  	  A Study on Seismic Analysis of RC Framed Structures on Varying Slo...IRJET-  	  A Study on Seismic Analysis of RC Framed Structures on Varying Slo...
IRJET- A Study on Seismic Analysis of RC Framed Structures on Varying Slo...
 
Ilias Michalis PMV Workshop Dubai 2014
Ilias Michalis PMV Workshop Dubai 2014Ilias Michalis PMV Workshop Dubai 2014
Ilias Michalis PMV Workshop Dubai 2014
 
TECHNICAL SEMINAR.pptx
TECHNICAL SEMINAR.pptxTECHNICAL SEMINAR.pptx
TECHNICAL SEMINAR.pptx
 
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdfTender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
 

Recently uploaded

Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
Kamal Acharya
 
School management system project report.pdf
School management system project report.pdfSchool management system project report.pdf
School management system project report.pdf
Kamal Acharya
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdfONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdf
Kamal Acharya
 

Recently uploaded (20)

ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Kraków
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
School management system project report.pdf
School management system project report.pdfSchool management system project report.pdf
School management system project report.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Pharmacy management system project report..pdf
Pharmacy management system project report..pdfPharmacy management system project report..pdf
Pharmacy management system project report..pdf
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
 
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...
NO1 Pandit Black Magic Removal in Uk kala jadu Specialist kala jadu for Love ...
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Arduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectArduino based vehicle speed tracker project
Arduino based vehicle speed tracker project
 
Introduction to Casting Processes in Manufacturing
Introduction to Casting Processes in ManufacturingIntroduction to Casting Processes in Manufacturing
Introduction to Casting Processes in Manufacturing
 
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdfONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
 
shape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxshape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptx
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptx
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdf
 

Monthly brief for structures in april (leisamis sde)

  • 2. Gauff Ingenieure PIPE CULVERTS COMPLETED DURING THE MONTH OF FEBRUARY. - Surround:-km 36.859 - Bed and surround – 35.579 (1x900mm diameter),32.740 (1x900mm diameter), 31.249 (2x1200mm diameter) BOX CULVERTS COMPLETED DURING THE MONTH. - Top deck – km 21.824 - Bottom slab and Top deck:- km 21.566/9.115 BRIDGES COMPLETED DURING THE MONTH. - Walling/Shaft:- km-4.843(2nd lift abutment 2)/ 52.160 (Abutment 1 and 2, Pier head capping 1 - Top deck:-NILL Internal Report 2/5 Signature
  • 3. Gauff Ingenieure STRUCTURAL BRIEF FOR THE MONTH OF FEBRUARY BILL No 8. Culverts and drainage works. Pipe culverts Km 36.859(2x1200mm) - Formwork erection for surround, wing walls and head walls including and pouring of concrete class 25/20. - Stripping of formwork for wing walls, head beam and surround. - Back filling both sides of access pipe culverts 1st to 8th layers Km 36.573 (1x900mm) - Excavation, filling under structures and pouring of blinding concrete - Fixing of formwork for bottom slab including Pouring of concrete class 25/20. - Formwork erection for surround, wing walls and head walls including pouring of concrete for surround class 25/20. - Stripping of formwork for wing walls, head beam and surround. - Backfilling to 7th layer completed Km 32.740 (1x900mm) - Excavation, filling under structures and pouring of blinding concrete - Fixing of formwork for bottom slab including Pouring of concrete class 25/20. - Formwork erection for surround, wing walls and head walls including placing of concrete for surround class 25/20. - Stripping of formwork for wing walls, head beam and surround. Km 31.249 (2x1200mm) - Excavation, filling under structures and pouring of blinding concrete - Fixing of formwork for bottom slab including Pouring of concrete class 25/20. - Formwork erection for surround, wing walls and head walls including placing of concrete for surround class 25/20 Stripping of formwork for wing walls, head beam and surround. - Stripping of formwork for wing walls, head beam and surround. Backfilling of completed cross pipe culverts:- - 39.112/37.075/36.859/36.573/36.294/35.979/35.880 Stone pitching for protection of side slopes to cross pipe culverts - 50.704/49.206/48.358/48.168/48.138 Setting out of pipe culverts:- - 27.620/26.160/ Lorry park traffic island and footpath at km 70.880RHS and 70.600LHS (Log logo) - Setting out of both traffic island and footpath. - Excavation, placing and concreting of reinforced concrete bollards to the traffic island - Erection of formwork and fixing reinforcements BRC MeshA252 double layer to the base of both traffic island and footpath. - Pouring of concrete class 25/20 to traffic island and footpath, curing and removal of formwork. Box culverts - Stone pitching and gabion protection works completed on the following box culverts:- 55.659/55.742/55.820/54.398/54.718/64.880/64.956/61.171/61.376/54.718/54.398/63.350. - Stone pitching and gabion protection in progress at km 67.050 Internal Report 3/5 Signature
  • 4. Gauff Ingenieure Km 30.675 (5cell 3.0x2.5m). - Backfilling to both sides of walls and wing walls side (1st and 12th layer.) Km 29.658(2 cell 2.0x1.5m). - Backfilling to both sides of walls and wing walls side (1st and 8th layer.) Km 0.447 (3 cell 3.0x2.0m) - Removal of existing Armco pipe culvert - Setting out and excavation done. - Back filling of under structures 1 and 2nd layers done. Km 1.477 (4 cell 3.0x2.0m) - Removal of existing Armco/concrete pipe culvert - Setting out and excavation done. - Back filling under structures with selected material done (1 Layer) Km 22.824 (1 cell 3.0x2.0m) - Formwork erection of shear walls, wing walls, winglets, top deck and headwalls including pouring of structural concrete class 30/20. - Removal of external formwork. Km 21.566 (2 cell 3.0x2.0m) - Formwork erection for the base slab and pouring of structural concrete class 30/20 - Erection of formwork for shear wall, wing walls, winglets and top deck. - Pouring of structural concrete class 30/20 for the walls and top deck slab. - External formwork removal done. Km 9.115 (2 cell 2.0x1.5m) - Excavation, backfilling under structures and compaction. - Pouring of non-structural concrete class 15/20 for blinding - Erection of formwork for the base lab and pouring of structural concrete class 30/20 - Erection of formwork for the shear walls, wing walls, winglets and top deck including pouring of structural concrete class 30/20. BILL No 21. Bridge works New bridge at km 52.160 - Fixing of formwork, steel for pier head of bridge pier 1 Merille side and placing in position of stainless dowel including pouring of concrete class 30/20. - Fixing of formwork, steel reinforcement bars for bearing beam capping/placing in position of stainless dowel bars, Parapet walls and wing walls for both abutment 1 and 2 including pouring of structural concrete class 30/20. New bridge at km 20.600 - NIL New bridge at km 4.843 - Erection of formwork and fixing of steel reinforcement bars for the 2nd lift of abutment 2 Marsabit side Internal Report 4/5 Signature
  • 5. Gauff Ingenieure and pouring of structural concrete class 30/20 - Erection of formwork and steel reinforcement bars for the bearing beam capping of abutment 2 Marsabit side (3rd lift) - Fixing of steel reinforcement bars for the 2nd lift of abutment 1 Merille side in progress. - Internal Report 5/5 Signature
  • 6. Gauff Ingenieure and pouring of structural concrete class 30/20 - Erection of formwork and steel reinforcement bars for the bearing beam capping of abutment 2 Marsabit side (3rd lift) - Fixing of steel reinforcement bars for the 2nd lift of abutment 1 Merille side in progress. - Internal Report 5/5 Signature