SlideShare a Scribd company logo
1 of 33
JAIPUR METRO
1
2
JAIPUR METRO PHASE - I
Corridor- I
Corridor-II
Sitapura to Ambabadi
(North – South)
Route Length (km.)
Elevated 18.004
UnderGround 5.095
Total 23.099
Number of Stations
Elevated 15
UnderGround 5
Total 20
Completion Cost (Rs. In
crores)
Without Taxes &
Escalation
3481
With Taxes &
Escalation
4624
Ridersh
ip
(PHPD
T)
2014 11300
2021 18200
2031 27000
Mansarovar to Badi
Chaupar (East -
West)
9.439
2.628
12.067
8
3
11
2194
2907
10000
20200
34100
Total
21.03
7.88
28.91
21
8
29
5675
7531
21300
38400
61100
As per Revised DPRPHPDT- Peak Hour Peak Direction Trips
3
INTRODUCTION
PHASE I
North-South(15.5 kilometers)
East-West (13.5 kilometers)
Totaling nearly 30 Kilometers, will be laid across the city at
an estimated cost of Rs 8,000 crores.,
The East-West corridor will be from Ramganj to Mansarover,.
A nine-km elevated track connecting Chandpole to
Mansarover be the first to be completed
The North-South corridor will connect Sanganer to Panipech
4
NEED OF METRO SYSTEM
Population growth rate of Jaipur is double the
average growth rate of other cities.
Significant reduction in environmental pollution.
Development of Delhi-Mumbai Industrial Corridor,
SEZ, International hub for Gem & Jewellery &
increasing tourist inflow will put additional burden
on transportation need.
5
ADVANTAGE OF METRO
SYSTEM
Metro systems are superior to other modes because
they provide higher carrying capacity, faster,
smoother and safer travel, occupy less space, are
non-polluting and energy-efficient.
Causes no air pollution in the city.
Causes lesser noise level.
Reduces journey time by anything between 50%
and 75% depending on road conditions. 6
READY MIX CONCRETE
Ready-mix concrete is a type of concrete is manufactured in
a factory or batching plant.
TRANSIT MIXTURE
The cylindrical portion is continuously rotating.
The rotation speed of cylindrical portion is 0-14 rpm.
7
TRANSIT MIXTURE 8
GRADE OF CONCRETE IN
CONSTRUCTION
Piles - M 35
 Pile cap - M 35
 Piers – M 50
 All precast element for station- M 45
Crash Barrier - M-35
 Cantilever piers arm- M 55
9
BOOM PLACER
10
CONSTRUCTION STEPS
Pile Foundation
Pile Cap
Pier/Column
 Pier Arm or Cross Arm
Track Level
11
CONSTRUCTION
12
PILE FOUNDATION STEP
SETTING OUT
DRIVING OF TEMPORARY CASING
BORING
REINFORCEMENT CAGE LOWERING
FLUSHING OPERATION
CONCRETING
13
PILE FOUNDATION
14
PILLING MACHINE
15
PILE CAP
A pile cap is a thick Concrete mat that rests on concrete
or timber piles that have been driven into soft or
unstable ground to provide a suitable stable foundation.
16
PIER
Grade of Concrete M- 50
The Diameter of Pier is 2000 mm from Ground level to
Concourse level and from Concourse level it is 1600
mm.
17
PIER
18
CRASH BARRIER
It is constructed around the pier to avoid the direct impact
on the pier in case of accident. The thickness of crash
barrier is225mm and consist 25mm cover. The height of
crash barrier is 165mm.The grade of concrete use in crash
barrier construction is M-35.
19
DRAINAGE
The drainage pipe is used for drain the rain water from
track level.
The diameter of drainage pipe is 200mm.
For the drain of water a drain hole is also construct in
the crash barrier.
20
21
CANTILEVER PIER ARM
A pier is consist 2 pier arms at Concourse level.
M -55 grade concrete is used.
The size of one arm is 10230 mm from center of the pier.
The depth of pier arm at near to the pier is 2250 mm and at
end point is 1650 mm.
22
CANTILEVER PIER ARM
23
10230 mm
1650 mm
PRECAST GIRDER
They are precast at casting yard or on site.
The girders are placed on the corbel.
The sizes of girders are 350 mm X 1200 mm.
 Grade of concrete is M-50.
24
PRECAST GIRDER
25
PRECAST SLAB
The dimensions of precast slab are 165 mm X 1000 mm.
The concrete grade is M-35.
The slabs and girders are jointed each other by arc welded
connection.
26
LAUNCHING OF PRECAST
GIRDER
HYDRA DEMAG HC-400” is used to launching or
Erect the Precast Slabs and Precast Girders on
Pier Arms.
Firstly Hydra must be stand on hydraulic jack.
 The capacity of this crane is about 150KN.
The Capacity of Hydra is Depend on its Boom
Length.
27
HYDRA DEMAG HC-400
28
PROBLEM AT SITE
Allowing free flow of vehicular traffic on the already
congested along with chosen alignment.
Paucity availability of Land.
Existence of charted and uncharted utilities.
Problems to pedestrian.
Problems to existing residents.
 Environmental Impact including noise and vibration etc. 29
SAFETY
Safety is very important thing for any kind of
construction.
 The safety is for workers as well as for public also.
 The safety belts, helmets and Safety shoe is used,
without these things, the entry to the site is
prohibited.
30
SAFETY HELMETS & SHOES
31
DMRC
ENGINEER
ELECTRICIAN
SAFETY LABOUR
SHOES BELTS
CONCLUSION
Such types of construction actually is very
difficult.reduce the traffic volume, travelling time .
Summer Training is a golden opportunity for
learning and self development and really
experiencing the real scenario of the company
environment. It helped me to increase my
technical skills. It is also helped me to be with
latest and new technologies.
32
Jaipur
Metro
33

More Related Content

What's hot

Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Nandan Shandilya
 
Metro rail in india
Metro rail in indiaMetro rail in india
Metro rail in indiaSourav Paul
 
Hyderabad metro rail – for a better livable city
Hyderabad metro rail – for a better livable cityHyderabad metro rail – for a better livable city
Hyderabad metro rail – for a better livable cityPramod Kumar
 
Bandra worli sea link case study
Bandra worli sea link  case studyBandra worli sea link  case study
Bandra worli sea link case studyAKSHAY CHATURVEDI
 
Hill road construction
Hill road constructionHill road construction
Hill road constructionGeet KH
 
Metro elevated structures AR.pdf
Metro elevated structures AR.pdfMetro elevated structures AR.pdf
Metro elevated structures AR.pdfAshutoshRankawat
 
Mumbai metro project Phase I
Mumbai metro project Phase IMumbai metro project Phase I
Mumbai metro project Phase IKaran Shah
 
Metro and monorail infrastructure development in india
Metro and monorail infrastructure development in indiaMetro and monorail infrastructure development in india
Metro and monorail infrastructure development in indiaBhavya Jaiswal
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
 
Metro Rail in India ppt
Metro Rail in India pptMetro Rail in India ppt
Metro Rail in India pptNikita James
 

What's hot (20)

Metro ppt - copy
Metro ppt - copyMetro ppt - copy
Metro ppt - copy
 
Metro Work
Metro WorkMetro Work
Metro Work
 
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
 
Flyover construction
Flyover constructionFlyover construction
Flyover construction
 
Bangalore Metro Project
Bangalore Metro ProjectBangalore Metro Project
Bangalore Metro Project
 
Metro rail in india
Metro rail in indiaMetro rail in india
Metro rail in india
 
Hyderabad Metro Rail Project
Hyderabad Metro Rail ProjectHyderabad Metro Rail Project
Hyderabad Metro Rail Project
 
Hyderabad metro rail – for a better livable city
Hyderabad metro rail – for a better livable cityHyderabad metro rail – for a better livable city
Hyderabad metro rail – for a better livable city
 
Metro Project
Metro ProjectMetro Project
Metro Project
 
Bandra worli sea link case study
Bandra worli sea link  case studyBandra worli sea link  case study
Bandra worli sea link case study
 
Casting yard
Casting yardCasting yard
Casting yard
 
Box culverts
Box culvertsBox culverts
Box culverts
 
Viaduct
Viaduct Viaduct
Viaduct
 
Hill road construction
Hill road constructionHill road construction
Hill road construction
 
Metro Rail and the City
Metro Rail and the CityMetro Rail and the City
Metro Rail and the City
 
Metro elevated structures AR.pdf
Metro elevated structures AR.pdfMetro elevated structures AR.pdf
Metro elevated structures AR.pdf
 
Mumbai metro project Phase I
Mumbai metro project Phase IMumbai metro project Phase I
Mumbai metro project Phase I
 
Metro and monorail infrastructure development in india
Metro and monorail infrastructure development in indiaMetro and monorail infrastructure development in india
Metro and monorail infrastructure development in india
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
Metro Rail in India ppt
Metro Rail in India pptMetro Rail in India ppt
Metro Rail in India ppt
 

Viewers also liked

Bangalore metro rail project
Bangalore metro rail projectBangalore metro rail project
Bangalore metro rail projectSaravanan rulez
 
Metro And Bangalore
Metro And BangaloreMetro And Bangalore
Metro And BangaloreDasarathi GV
 
Mumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metroMumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metrosatish choudhari
 
Saudi Railway Company Presentation - Railways Projects 2014
Saudi Railway Company Presentation - Railways Projects 2014Saudi Railway Company Presentation - Railways Projects 2014
Saudi Railway Company Presentation - Railways Projects 2014Ibrahim Al-Hudhaif
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniquesEsri India
 
Delhi metro presentation(SCHOOL/COLLEGE)
Delhi metro presentation(SCHOOL/COLLEGE)Delhi metro presentation(SCHOOL/COLLEGE)
Delhi metro presentation(SCHOOL/COLLEGE)Aashna Sharma
 
Summer training DMRC ppt
Summer training DMRC pptSummer training DMRC ppt
Summer training DMRC pptVimal Maurya
 
Jaipur metro rail project
Jaipur metro rail projectJaipur metro rail project
Jaipur metro rail projectDocumentStory
 
Groundwater improvement techniques
Groundwater improvement techniques Groundwater improvement techniques
Groundwater improvement techniques my-will
 
PILE FOUNDATION-INDIA
PILE FOUNDATION-INDIAPILE FOUNDATION-INDIA
PILE FOUNDATION-INDIAaditya singh
 
What is Ground Improvement Techniques?
What is Ground Improvement Techniques?What is Ground Improvement Techniques?
What is Ground Improvement Techniques?roks99
 

Viewers also liked (16)

Bangalore metro rail project
Bangalore metro rail projectBangalore metro rail project
Bangalore metro rail project
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
 
lucknow metro ppt
lucknow metro pptlucknow metro ppt
lucknow metro ppt
 
Metro And Bangalore
Metro And BangaloreMetro And Bangalore
Metro And Bangalore
 
Mumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metroMumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metro
 
Saudi Railway Company Presentation - Railways Projects 2014
Saudi Railway Company Presentation - Railways Projects 2014Saudi Railway Company Presentation - Railways Projects 2014
Saudi Railway Company Presentation - Railways Projects 2014
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
Delhi metro presentation(SCHOOL/COLLEGE)
Delhi metro presentation(SCHOOL/COLLEGE)Delhi metro presentation(SCHOOL/COLLEGE)
Delhi metro presentation(SCHOOL/COLLEGE)
 
Pile load test
Pile load testPile load test
Pile load test
 
Summer training DMRC ppt
Summer training DMRC pptSummer training DMRC ppt
Summer training DMRC ppt
 
Reinfocing details of column
Reinfocing details of columnReinfocing details of column
Reinfocing details of column
 
Jaipur metro rail project
Jaipur metro rail projectJaipur metro rail project
Jaipur metro rail project
 
Groundwater improvement techniques
Groundwater improvement techniques Groundwater improvement techniques
Groundwater improvement techniques
 
PILE FOUNDATION-INDIA
PILE FOUNDATION-INDIAPILE FOUNDATION-INDIA
PILE FOUNDATION-INDIA
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
What is Ground Improvement Techniques?
What is Ground Improvement Techniques?What is Ground Improvement Techniques?
What is Ground Improvement Techniques?
 

Similar to Metro Construction

lmrc presentation
lmrc presentationlmrc presentation
lmrc presentationATUL SHUKLA
 
DESIGN OF POST TENSIONED DECK SLAB FOR FLYOVER
DESIGN OF POST TENSIONED DECK SLAB FOR FLYOVERDESIGN OF POST TENSIONED DECK SLAB FOR FLYOVER
DESIGN OF POST TENSIONED DECK SLAB FOR FLYOVERManiKandan1175
 
Design of flyover elements
Design of flyover elementsDesign of flyover elements
Design of flyover elementssubbu lakshmi
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMIshant Gautam.
 
Design of highway (Flexible pavement)
Design of highway (Flexible pavement)Design of highway (Flexible pavement)
Design of highway (Flexible pavement)Raz Gupta
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)vishal prakash
 
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...Bharat Badre
 
(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...
(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...
(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...Bharat Badre
 
Six week industrial training presentation BY GUPTA TARUN
Six week industrial training presentation BY GUPTA TARUNSix week industrial training presentation BY GUPTA TARUN
Six week industrial training presentation BY GUPTA TARUNTarun2222
 
Summer Internship Report.pptx
Summer Internship Report.pptxSummer Internship Report.pptx
Summer Internship Report.pptxDeepak37004
 
Job_reference_for_email
Job_reference_for_emailJob_reference_for_email
Job_reference_for_emailAngelo Scoppa
 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGJAPJEETSINGH13
 
Parametric Comparison of Rectangular and Trapezoidal Box Girder Bridge Deck S...
Parametric Comparison of Rectangular and Trapezoidal Box Girder Bridge Deck S...Parametric Comparison of Rectangular and Trapezoidal Box Girder Bridge Deck S...
Parametric Comparison of Rectangular and Trapezoidal Box Girder Bridge Deck S...IRJET Journal
 
Roads and its design factors pdf
Roads and its design factors pdfRoads and its design factors pdf
Roads and its design factors pdfSaqib Imran
 

Similar to Metro Construction (20)

Saurabhk601
Saurabhk601Saurabhk601
Saurabhk601
 
linkedin
linkedinlinkedin
linkedin
 
lmrc presentation
lmrc presentationlmrc presentation
lmrc presentation
 
DESIGN OF POST TENSIONED DECK SLAB FOR FLYOVER
DESIGN OF POST TENSIONED DECK SLAB FOR FLYOVERDESIGN OF POST TENSIONED DECK SLAB FOR FLYOVER
DESIGN OF POST TENSIONED DECK SLAB FOR FLYOVER
 
Design of flyover elements
Design of flyover elementsDesign of flyover elements
Design of flyover elements
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
 
Design of highway (Flexible pavement)
Design of highway (Flexible pavement)Design of highway (Flexible pavement)
Design of highway (Flexible pavement)
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
 
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
 
(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...
(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...
(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...
 
Metroppt
MetropptMetroppt
Metroppt
 
Major Project ppt
Major Project ppt Major Project ppt
Major Project ppt
 
Six week industrial training presentation BY GUPTA TARUN
Six week industrial training presentation BY GUPTA TARUNSix week industrial training presentation BY GUPTA TARUN
Six week industrial training presentation BY GUPTA TARUN
 
Ramesh kumar
Ramesh kumarRamesh kumar
Ramesh kumar
 
Summer Internship Report.pptx
Summer Internship Report.pptxSummer Internship Report.pptx
Summer Internship Report.pptx
 
4 Barrier Design 2008
4   Barrier Design 20084   Barrier Design 2008
4 Barrier Design 2008
 
Job_reference_for_email
Job_reference_for_emailJob_reference_for_email
Job_reference_for_email
 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERING
 
Parametric Comparison of Rectangular and Trapezoidal Box Girder Bridge Deck S...
Parametric Comparison of Rectangular and Trapezoidal Box Girder Bridge Deck S...Parametric Comparison of Rectangular and Trapezoidal Box Girder Bridge Deck S...
Parametric Comparison of Rectangular and Trapezoidal Box Girder Bridge Deck S...
 
Roads and its design factors pdf
Roads and its design factors pdfRoads and its design factors pdf
Roads and its design factors pdf
 

Recently uploaded

DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 

Recently uploaded (20)

DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 

Metro Construction

  • 2. 2
  • 3. JAIPUR METRO PHASE - I Corridor- I Corridor-II Sitapura to Ambabadi (North – South) Route Length (km.) Elevated 18.004 UnderGround 5.095 Total 23.099 Number of Stations Elevated 15 UnderGround 5 Total 20 Completion Cost (Rs. In crores) Without Taxes & Escalation 3481 With Taxes & Escalation 4624 Ridersh ip (PHPD T) 2014 11300 2021 18200 2031 27000 Mansarovar to Badi Chaupar (East - West) 9.439 2.628 12.067 8 3 11 2194 2907 10000 20200 34100 Total 21.03 7.88 28.91 21 8 29 5675 7531 21300 38400 61100 As per Revised DPRPHPDT- Peak Hour Peak Direction Trips 3
  • 4. INTRODUCTION PHASE I North-South(15.5 kilometers) East-West (13.5 kilometers) Totaling nearly 30 Kilometers, will be laid across the city at an estimated cost of Rs 8,000 crores., The East-West corridor will be from Ramganj to Mansarover,. A nine-km elevated track connecting Chandpole to Mansarover be the first to be completed The North-South corridor will connect Sanganer to Panipech 4
  • 5. NEED OF METRO SYSTEM Population growth rate of Jaipur is double the average growth rate of other cities. Significant reduction in environmental pollution. Development of Delhi-Mumbai Industrial Corridor, SEZ, International hub for Gem & Jewellery & increasing tourist inflow will put additional burden on transportation need. 5
  • 6. ADVANTAGE OF METRO SYSTEM Metro systems are superior to other modes because they provide higher carrying capacity, faster, smoother and safer travel, occupy less space, are non-polluting and energy-efficient. Causes no air pollution in the city. Causes lesser noise level. Reduces journey time by anything between 50% and 75% depending on road conditions. 6
  • 7. READY MIX CONCRETE Ready-mix concrete is a type of concrete is manufactured in a factory or batching plant. TRANSIT MIXTURE The cylindrical portion is continuously rotating. The rotation speed of cylindrical portion is 0-14 rpm. 7
  • 9. GRADE OF CONCRETE IN CONSTRUCTION Piles - M 35  Pile cap - M 35  Piers – M 50  All precast element for station- M 45 Crash Barrier - M-35  Cantilever piers arm- M 55 9
  • 11. CONSTRUCTION STEPS Pile Foundation Pile Cap Pier/Column  Pier Arm or Cross Arm Track Level 11
  • 13. PILE FOUNDATION STEP SETTING OUT DRIVING OF TEMPORARY CASING BORING REINFORCEMENT CAGE LOWERING FLUSHING OPERATION CONCRETING 13
  • 16. PILE CAP A pile cap is a thick Concrete mat that rests on concrete or timber piles that have been driven into soft or unstable ground to provide a suitable stable foundation. 16
  • 17. PIER Grade of Concrete M- 50 The Diameter of Pier is 2000 mm from Ground level to Concourse level and from Concourse level it is 1600 mm. 17
  • 19. CRASH BARRIER It is constructed around the pier to avoid the direct impact on the pier in case of accident. The thickness of crash barrier is225mm and consist 25mm cover. The height of crash barrier is 165mm.The grade of concrete use in crash barrier construction is M-35. 19
  • 20. DRAINAGE The drainage pipe is used for drain the rain water from track level. The diameter of drainage pipe is 200mm. For the drain of water a drain hole is also construct in the crash barrier. 20
  • 21. 21
  • 22. CANTILEVER PIER ARM A pier is consist 2 pier arms at Concourse level. M -55 grade concrete is used. The size of one arm is 10230 mm from center of the pier. The depth of pier arm at near to the pier is 2250 mm and at end point is 1650 mm. 22
  • 24. PRECAST GIRDER They are precast at casting yard or on site. The girders are placed on the corbel. The sizes of girders are 350 mm X 1200 mm.  Grade of concrete is M-50. 24
  • 26. PRECAST SLAB The dimensions of precast slab are 165 mm X 1000 mm. The concrete grade is M-35. The slabs and girders are jointed each other by arc welded connection. 26
  • 27. LAUNCHING OF PRECAST GIRDER HYDRA DEMAG HC-400” is used to launching or Erect the Precast Slabs and Precast Girders on Pier Arms. Firstly Hydra must be stand on hydraulic jack.  The capacity of this crane is about 150KN. The Capacity of Hydra is Depend on its Boom Length. 27
  • 29. PROBLEM AT SITE Allowing free flow of vehicular traffic on the already congested along with chosen alignment. Paucity availability of Land. Existence of charted and uncharted utilities. Problems to pedestrian. Problems to existing residents.  Environmental Impact including noise and vibration etc. 29
  • 30. SAFETY Safety is very important thing for any kind of construction.  The safety is for workers as well as for public also.  The safety belts, helmets and Safety shoe is used, without these things, the entry to the site is prohibited. 30
  • 31. SAFETY HELMETS & SHOES 31 DMRC ENGINEER ELECTRICIAN SAFETY LABOUR SHOES BELTS
  • 32. CONCLUSION Such types of construction actually is very difficult.reduce the traffic volume, travelling time . Summer Training is a golden opportunity for learning and self development and really experiencing the real scenario of the company environment. It helped me to increase my technical skills. It is also helped me to be with latest and new technologies. 32