The document provides details about the construction of the underground Vasant Vihar Metro Station in Delhi. Key points include:
- The station is being constructed using the bottom-up method due to the hard rock strata. This involves excavation, constructing the base slab and then working upwards.
- Concrete grades M40 and M50 are being used for the slabs and columns respectively. Waterproofing involves priming with Master Seal M2525 and applying the waterproofing layer of Master Seal M800.
- Other aspects covered are borehole data analysis, structure layout, concreting operations, machinery used, and repair works. Precise construction methods are highlighted.
Industrial Training report Civil Engineering.JAPJEETSINGH13
Industrial training report for civil engineering major training final year. All rights to the images, blueprints and content is reserved.
Only available for educational purposes.
Industrial Training report Civil Engineering.JAPJEETSINGH13
Industrial training report for civil engineering major training final year. All rights to the images, blueprints and content is reserved.
Only available for educational purposes.
Summer Internship Presentation of Building Self-employed
This presentation includes various types of information which are precisely done at the time of internship. This includes Short detail of company, project, process, difficulties faced and some simple formulae to calculate the Quantity and estimation of materials used.
Industrial Summer Training Report at Construction Site of CPWD Alok Mishra
Construction of Police Station Khajuri Khas, Near Sonia Vihar, Delhi (SH: C/o Police Station Building, Electric sub Station & External Development Work i.e. Internal Electrical Installations)
Construction sequence for metro Project (Elevated and Underground) and Time c...Akhilesh Shukla
Construction sequence for metro Project (Elevated and Underground) and Time cycle of the metro construction activity . For more details u can contact me on my mail id -shuklaakhilesh08@gmail.com
Summer Internship Presentation of Building Self-employed
This presentation includes various types of information which are precisely done at the time of internship. This includes Short detail of company, project, process, difficulties faced and some simple formulae to calculate the Quantity and estimation of materials used.
Industrial Summer Training Report at Construction Site of CPWD Alok Mishra
Construction of Police Station Khajuri Khas, Near Sonia Vihar, Delhi (SH: C/o Police Station Building, Electric sub Station & External Development Work i.e. Internal Electrical Installations)
Construction sequence for metro Project (Elevated and Underground) and Time c...Akhilesh Shukla
Construction sequence for metro Project (Elevated and Underground) and Time cycle of the metro construction activity . For more details u can contact me on my mail id -shuklaakhilesh08@gmail.com
Shortcreting has proved to be the best method for construction of curved surfaces. Domes are now much easier to construct with the advent of shotcrete technology. Tunnel linings are also becoming easy with this technology. Not only are these but there a wide range of applications where this technology has been a leading one. This technical paper includes the concept of shotcrete and how it differs from conventional concrete. It also enumerates the different types of process involved in shotcreting i.e. dry mix process and wet mix process. Advantages of shotcrete and its applications in various fields like tunneling, canals, buildings etc. are specified in detail. This paper presents an overview of shotcreting technology along with its applications.
DEFINITION OF SHOTCRETE:-
Shotcrete is a mortar or high performance concrete conveyed through a hose and pneumatically projected at high velocity onto a backing surface. It is the force of this spraying action that leads to compaction of the concrete or mortar which then forms layers of concrete to the required thickness. Shotcreting has been an acceptable way of placing cementitious material in a variety of applications.
Usually patented polypropylene fibers are included in the shotcrete which increases the cohesive nature of the shotcrete through mechanically binding the cementitious materials together. This mechanism reduces the rebound waste that occurs through the shotcreting process and these fibers also resist plastic shrinkage and cracking through their ability to enhance the early stage tensile strength of concrete.
Shotcrete also gives better surface finishes and reduces surface tearing on non- linear sections. Cementitious material containing the poly propylene fibers resist cycles of freezing and thawing and also reduces the chances of water and chemical penetrations.
The main outcome of this project is the construction sequence of HMR which primarily starts with excavation, erection of piers, launching girder process and assembling of segments. This project clearly gives a brief knowledge on how the post tensioning and pre stressing works are held at off site and onsite. This project enlightens about the safety requirements and measures taken during the pre-casting works and at on site works.
Lining is an integral part of Tunneling. Once the Shotcrete line ,i.e the B-line,is laid, the Kerb/Kicker or Say Beam is executed. Next Comes the Geotextile/Waterproofing Membrane. After that, C-line is laid which is referred to as inner lining.
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
Hello Friends Myself SHUBHAM RANA . I am pursuing B.Tech in Civil Engineering from IIT ROORKEE. This is the glimpse of my work and basic aspects which I learned while doing my Internship in Larsen and Toubro Heavy Civil Infra IC. Thank You :)
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
The said technical paper was presented by Rajesh Prasad in IC TRAM 2018 (International Conference- Technological Advancement in Railways and Metro Projects at Manekshaw Centre New Delhi on 04.10.2018
The presentation helps in understanding the influence of JICA (Financing authority) on the tender guidelines on DMRC. The presentation further provides a basic understanding of the Tender structure of DRMC
The project provides an insight on pavement Management Systems.PMS helps in making informed decisions enabling the maintenance of the network in a serviceable and safe condition at a minimum cost to both the agency and the road users. To adequately meet this requirement, well-documented information is essential to make defensible decisions on the basis of sound principles of engineering and management
Transforming Brand Perception and Boosting Profitabilityaaryangarg12
In today's digital era, the dynamics of brand perception, consumer behavior, and profitability have been profoundly reshaped by the synergy of branding, social media, and website design. This research paper investigates the transformative power of these elements in influencing how individuals perceive brands and products and how this transformation can be harnessed to drive sales and profitability for businesses.
Through an exploration of brand psychology and consumer behavior, this study sheds light on the intricate ways in which effective branding strategies, strategic social media engagement, and user-centric website design contribute to altering consumers' perceptions. We delve into the principles that underlie successful brand transformations, examining how visual identity, messaging, and storytelling can captivate and resonate with target audiences.
Methodologically, this research employs a comprehensive approach, combining qualitative and quantitative analyses. Real-world case studies illustrate the impact of branding, social media campaigns, and website redesigns on consumer perception, sales figures, and profitability. We assess the various metrics, including brand awareness, customer engagement, conversion rates, and revenue growth, to measure the effectiveness of these strategies.
The results underscore the pivotal role of cohesive branding, social media influence, and website usability in shaping positive brand perceptions, influencing consumer decisions, and ultimately bolstering sales and profitability. This paper provides actionable insights and strategic recommendations for businesses seeking to leverage branding, social media, and website design as potent tools to enhance their market position and financial success.
Connect Conference 2022: Passive House - Economic and Environmental Solution...TE Studio
Passive House: The Economic and Environmental Solution for Sustainable Real Estate. Lecture by Tim Eian of TE Studio Passive House Design in November 2022 in Minneapolis.
- The Built Environment
- Let's imagine the perfect building
- The Passive House standard
- Why Passive House targets
- Clean Energy Plans?!
- How does Passive House compare and fit in?
- The business case for Passive House real estate
- Tools to quantify the value of Passive House
- What can I do?
- Resources
Book Formatting: Quality Control Checks for DesignersConfidence Ago
This presentation was made to help designers who work in publishing houses or format books for printing ensure quality.
Quality control is vital to every industry. This is why every department in a company need create a method they use in ensuring quality. This, perhaps, will not only improve the quality of products and bring errors to the barest minimum, but take it to a near perfect finish.
It is beyond a moot point that a good book will somewhat be judged by its cover, but the content of the book remains king. No matter how beautiful the cover, if the quality of writing or presentation is off, that will be a reason for readers not to come back to the book or recommend it.
So, this presentation points designers to some important things that may be missed by an editor that they could eventually discover and call the attention of the editor.
Fonts play a crucial role in both User Interface (UI) and User Experience (UX) design. They affect readability, accessibility, aesthetics, and overall user perception.
Can AI do good? at 'offtheCanvas' India HCI preludeAlan Dix
Invited talk at 'offtheCanvas' IndiaHCI prelude, 29th June 2024.
https://www.alandix.com/academic/talks/offtheCanvas-IndiaHCI2024/
The world is being changed fundamentally by AI and we are constantly faced with newspaper headlines about its harmful effects. However, there is also the potential to both ameliorate theses harms and use the new abilities of AI to transform society for the good. Can you make the difference?
Hello everyone! I am thrilled to present my latest portfolio on LinkedIn, marking the culmination of my architectural journey thus far. Over the span of five years, I've been fortunate to acquire a wealth of knowledge under the guidance of esteemed professors and industry mentors. From rigorous academic pursuits to practical engagements, each experience has contributed to my growth and refinement as an architecture student. This portfolio not only showcases my projects but also underscores my attention to detail and to innovative architecture as a profession.
PDF SubmissionDigital Marketing Institute in NoidaPoojaSaini954651
https://www.safalta.com/online-digital-marketing/advance-digital-marketing-training-in-noidaTop Digital Marketing Institute in Noida: Boost Your Career Fast
[3:29 am, 30/05/2024] +91 83818 43552: Safalta Digital Marketing Institute in Noida also provides advanced classes for individuals seeking to develop their expertise and skills in this field. These classes, led by industry experts with vast experience, focus on specific aspects of digital marketing such as advanced SEO strategies, sophisticated content creation techniques, and data-driven analytics.
Visual Style and Aesthetics: Basics of Visual Design
Visual Design for Enterprise Applications
Range of Visual Styles.
Mobile Interfaces:
Challenges and Opportunities of Mobile Design
Approach to Mobile Design
Patterns
Maximize Your Content with Beautiful Assets : Content & Asset for Landing Page pmgdscunsri
Figma is a cloud-based design tool widely used by designers for prototyping, UI/UX design, and real-time collaboration. With features such as precision pen tools, grid system, and reusable components, Figma makes it easy for teams to work together on design projects. Its flexibility and accessibility make Figma a top choice in the digital age.
Maximize Your Content with Beautiful Assets : Content & Asset for Landing Page
DMRC (METRO TRAINING REPORT)
1. A detailed presentation on the
construction of underground Metro
Station
Sukhdarshan
Under the guidance of
Mr Tanuj Chopra
L&T SUCG JV DELHI
DMRC CC-27 PROJECT
2. CONTENT
Introduction to Project CC-27
Tendering For the Project
Bore Hole Results
Vasant Vihar structure lay out
Bottom-Up Construction
Excavation/Soil stabilization
Concreting Operation& Repair
Waterproofing of Structure
3. Project Name-Design and construction of tunnel & underground metro stations from Janakpuri
West to Botanical Garden(CC-27)
Key Details
COST OF PROJECT(App) INR 1435 CRORES
COMPLETION PERIOD(Expected) 42 MONTHS
TENDER SECURITY AMOUNT INR 14.35 CRORES
TENDERING AGENCY DMRC
TENDER GIVEN TO L&T-SUCG-JV
Quoted Price & Final Price 1265 CRORES
5. Tendering For the Project
Tender document is further divided into volumes that define the scope
and procedure for various activities related to project. The CC-27 Tender
Document was further divided into 9 volumes
Volume 1- Instructions for tenderer and form of tender.
Volume 2-General conditions and special conditions for contract
Volume 3-Emplyers Requirement about Functional, Design &
construction.
Volume 4-Outline Design Specifications
Volume 5-Outline Construction Specifications
Volume 6-Tender Drawings
Volume 7-Bill of Quantities
Volume 8-Vonditions on Safety, Health & Environment
Volume 9-Reference Document(Geotechnical report)
6. Eligibility Criteria for bidding
Work Experience
Financial Standings
a) Liquidity
b) Profitability
c) Net Worth
d) Annual Turnover
Bid Capacity Criteria
Minimum Key staff Requirement
7. AWARDING OF TENDER
• The most basic criteria for awarding the tender is as follows but not
limited to it
“The employer awards the contract to the tenderer whose tender has
been determined to be substantially responsive and compliant to the
requirements contained in the tender document & who has offered the
lowest evaluated tender price”
9. Bore Hole Data
-Before starting construction Geotechnical data was collected from various
locations along the proposed route to know about soil characteristics.
-Bore Holes were made along the proposed route up to a depth of 30m below
the existing ground level.
Next Image shows the Soil Strata available at various sections of the project.
11. Based on the samples obtained from the bore holes following tests were conducted
on the samples-
Following tests were then performed on the collected samples-
• Sieve analysis.
• Hydrometer testing
• Moisture content
• Specific gravity
• Dry Density
• Atterbergs limit
• Triaxial shear test(uu, cu, cd)
• Consolidation test
• Direct Shear Test
• Chemical analysis of both soil and water samples
12. The collected rock core samples(VASANT VIHAR SITE) were taken and the following tests
were conducted on them-
• Density test
• Water absorption& porosity
• Hardness
• Ucs
• Point load index
• Vasant Vihar-Hard Rock strata (Bottom-Up construction approach)
• Hauz Khas - Soft Soil strata(Top-Bottom construction approach)
13. Vasant Vihar Station
TOP VIEW – VASANT VIHAR
METHOD OF CONSTRUCTION- BOTTOM UP CONSTRUCTION
EAST SIDE
WEST SIDE
14. VASANT VIHAR PLAN
1
2
3
4
D
S.NO DESCRIPTION UNIT SCOPE
1 STATION LENGTH M 265
2 WIDTH(BOX) M 21.57
3 Launching Shafts Num 2
4 Entery/Exit Num 4
East Side
West Side
16. BLOCK WORK INFRONT OF RETAINING WALL Dimension of Block– 400*200*200
Mortar-Cement sand mortar with ratio 1:4
Block Strength- 7.5 N/mm2
MIX –M15
Thickness of the bond-10mm
Joint Type-Basic English Bond(1 block thick)
CONCOURSE SLAB
ROOF SLAB
BLOCK WORK IN FRONT
OF RETAINING WALL
RETAINING WALL
INITIAL LAYER OF BLOCK WORK
17. BLOCK WORK FOR ROOMS
ARCHITECTURAL ROOM PLAN(CONCOURSE SLAB)
EXAMPLE
U23-SAFETY ROOM
U64-ELECTRICAL APPLIANCE REPAIR
U26-WAITING ROOM
18. UPE(UNDER PLATFORM EXHAUST)
BASE SLAB
UPE CUTOUT
PLATFORM SLAB
UNDER PLATFROM
EXHAUST
(UNDER PLATFROM EXHAUST ) are basically cut outs provided below the platform slab
21. FRESH AIR DUCTS
Ventilation systems provided below the roof slab for a constant supply
of fresh air.
ROOF SLAB
22. SCUPPER DRAIN(BEHIND BLOCK WORK) Water proofing material (Brush Bond Rfx)
Scupper Drain Behind Block Work
DIMENSION- .37m X .3m
PCC M15
Brush bond Rfx Coating for waterproofing of
thickness 1mm
25. Factors that determine the construction approach are
• Soil Profile- As suggested by the geotechnical investigation.
• Site Location-Weather the site is located in an isolated environment or urban dwellings.
• Cost Incurred -Depends
• Surrounding Environment-Weather the Surrounding environment consists of existing
structures and road networks.
• Time Constrain-The total time available for completion of project.
• Availability of Material-The availability of material for filling and construction Activities
to be carried out
28. Bottom Up construction Method(VASANT VIHAR)
Bottom up construction
involves
Excavation & Soil
Stabilization
Construction of Base slab,
Concourse slab & Roof slab
Construction of Columns and
Retaining wall.
Waterproofing of structure
Filling Operations
29. Excavation
• Excavation on site was carried out according to IS 3764:1992.
• Excavation can be done in many ways depending on the soil profile in our
case it was done using Breakers and Excavators.
• Excavation Volume= 18*265*26=124020 cum(Lump sum)
30. Machinery used in excavation
EXCAVATORS
Hydraulic 220 Excavator
Hydraulic 210 Excavator
Hydraulic 215 Excavator
BREAKERS
Hydraulic 340 Breaker
Hydraulic 210 Breaker
HEAD ATTACHMENT FOR
BREAKER
32. Shot creting
Shot Creting is done according to IS 9012:1978(reaffirmed 2002)
Mix- 1:3 To 1:5 is used depending upon surface . W/c is kept at .30-.35
Plasticizer -6% wt of cement( Glenium sky 777)
Operating temp- 5deg to 30deg Celsius
Mesh Dia- 4mm
Mesh overlap length- 300mm
Min area for applying-300mm*300mm
33. Procedure For shotcreting 1)Clean the surface off the loose material
and then clean with air compressor.
2) Apply a layer of shortcrete to the surface
and wait for it to cure.
3) Apply the wire mesh on the surface and
bind it to the surface using reinforcements.
4) Now apply the second layer of the
shortcrete on the surface . Keep the nozzle
perpendicular at a distance of 1 to 1.4 m
away form surface.
Mechanism for Dry- Mix shot creting
34. Construction of slabs
Base Slabs
-M40 Grade Concrete was used
-Reinforcement conforming to FE500D shall be used on site.
-Water Stops –PVC water stop will be used to arrest the water leakage (at construction joints)
-Binding wire used for binding reinforcement has a core dia of 1.25mm
-Formwork ply 12mm thick coated with Formwork oil for easy removal of formwork
-Cover blocks should be used depending on clearance that needs to be provided to the reinforcement(50mm Base slab)
-Vibrator of 60mm Dia 4nos.
35. Mix Design of concrete M 40
MATERIAL QUANTIY(KG) TYPE
CEMENT 380 ULTRA TECH(OPC 53 GRADE)
FLYASH 80 Ashtech:IS3812(NTPC BADARPUR)
AGGREGATE(10mm) 481 Kotpulti
AGGREGATE(20mm) 666 Kotpulti
RIVER SAND 677 Yamuna Nagar
W/C RATIO .35
ADMIXTURE @ .85% 3.91 Glenium 147,Suretec(BASF)
W/P CAMPOunds@1% 4.6 MasterPel 760(BASF)
WATER 161 R.O Water at Batching Plant
Following admixture were used
Masterglenium 147 provides
Extended workability
Providing the ultimate high strength, especially ready.
Application
Add to the mixture 80% -90% of the calculated water for
the concrete mix and then, with the remaining water
masterglenium 147 must be added to the mixture,
Water Proofing Campound used-
Masterpel 760
Provides resistance to water penetration either under
hydrostatic pressure or capillary absorption.
Imparts integral water tightness to structures.
Application
MasterPel 760 is a ready-to-use powder which is
dispensed into the concrete together with the cement.
M-40 has been used for 3 slabs and retaining walls
37. • After the final set has taken place wet hessian cloth shall be placed and covered by polythene sheet. The
hessian cloth shall be kept permanently damp
• After 24Hours hessian cloth and the polythene sheet shall be removed and the area would be ponded with
water .
• For vertical curing the hessian cloth along with polythene sheet shall secure the surface for at leasdays
before next vertical pouring begins. The hessian cloth should be damp all the time.
40. Roof Slab
Sealing Of construction Joints on roof slab
Cut Outs of the roof Slab( Sattelite view
Design Mix M-40
Thickness-1.8m
Roof level
41. Machinery used for Concreting
Volume-6cum but loaded up to 5-5.5cum.
Rotations –Depend upon distance and Mix
BOOM PLACER
Concrete Bucket Vol 1-1.2cum
CONCRETING THROUGH PIPES
42. Mix Design M-50
MATERIAL QUANTIY(KG) TYPE
CEMENT 410 ULTRA TECH(OPC 53 GRADE)
MICRO SILICA 22 TAM CEM
AGGREGATE(10mm) 457 Kotpulti
AGGREGATE(20mm) 686 Kotpulti
RIVER SAND 765 Yamuna Nagar
W/C RATIO .37
ADMIXTURE @
.85%
2.16 Glenium sky 777
WATER 151 R.O Water at Batching Plant
M 50 was used for concreting of columns
MasterGlenium SKY 8777 -is the super plasticizer based on
second generation polycarboxylic ether polymers,
developed using nano-technology. The product has been
primarily developed for applications in high performance
ready-mix concrete to facilitate
Capability of delivering high quality concrete at any
time to the job site in place.Production of concrete with
low w/c ratio that meets international guidelines for
consistency classes (EN 206-1) without loss of
workability.
TAM CEM
TamCem Micro Silica is composed of silicon dioxide
(5i02).Collected from silicon metal and ferrosilicon.
TamCem Micro Silica will react with the Calcium Hydroxide
from the cement, which will form more of the Calcium
Silicate hydrate, increasing the strength of the concrete.
43. Concrete Repairing
BULGED CONCRETE
Bulged Concrete – Bulging in concrete takes place due to displacement of formwork.
Surface preparation: The bulged area on concrete surface shall be hacked with chisel to
required line, level. All dirt, dust shall be cleaned with brush and water.
Repairing: Hacked area will be patched up with cement: sand mortar of proportion 1:4.
On the completion of patch up work, the exposed area shall be thoroughly cured.
Grout Loss Exposed aggregate surface created by exit of cement slurry/grout mortar from
the gaps of formwork due to excessive vibration, unsealed joint of formwork
during pouring of concrete.
Repair
-The concrete surface is cleaned and free from dust/oil/grease etc by using
broom or wire mesh by scrubbing vigorously.
-After removal of loose particles surface is washed with water.
-Patch-up is done at cleaned surface with non-shrink Grout conbextra GP2
44. It is due segregation of aggregates and mortar into the concrete.
Honeycomb creates in structures due to mainly improper
compaction in terms of excessive/insufficient vibration at the
time of placing.
Minor Honey Combing
Major Honeycombing
Repairing Involves-
The loose aggregate that are exposed shall be removed by
gently tapping on it. After removal of all loose aggregate,
dust, dirt etc. by wire/Soft brush then surface will be
cleaned with Water. Patchup is done by using conbextra
GP2/Rendroc which is mixed with cement and then the
paste is applied.
45. Waterproofing of Structure
Chemicals used for Waterproofing
-For Priming Purpose
Master Seal M2525(Provided In two component A & B)
-Waterproofing Layer
Master Seal M800(Provided In two component A & B)
Master Seal M2525-Master Emaco 2525 is a solvent free, high-performance, versatile epoxy binder that can be used to
produce a range of epoxy resin based mortars.
Used For-
Structural bonding of new to old concrete
Production of epoxy resin mortars to grout bolt holes
Steel bonding
46. Master Seal M800
A highly elastic, solvent free, ultra-fast curing, spray applied polyurethane coating and it is used in
waterproofing applications. Master Seal M800 is a solvent free, two component substance. It is a
highly reactive two component mixture used for waterproofing in tunneling and cut & cover stations
Uses-
Waterproofing compound with a setting time of 2-3seconds
Step wise Process for Waterproofing.
-SURFACE CONDITIONS
The RCC surface shall be dry before waterproofing.
Any ingress for water seepage shall be identified and treated.
Construction Joint shall be filled with high performance water stop grout of crystalline growth.
Step 1 Surface Preparation & Filling of
any voids by Epoxy and Cement
47. -MIXING
• Application of Primer Involves mixing of component A and B and application on
the surface as shown MIXING OF A & B
-Thin coat of mixed primer (RESIN + HARDNER) on the surface shall be
mechanically & uniformly applied, ensuring continuous film soon after surface
preparation is complete.
-Moisture content in the substrate shall be less than 5 %.
-The drying period of primer depends on the ambient temperature and relative
humidity.
48. Checking moisture before application of
primer.
BASF AGGREGATES
BASF AGGREGATES are sprinkled over the primer layer immediately after application of
the primer. Aggregates help in roughening the surface of primer for proper bonding
between the primer layer and the waterproofing membrane layer.
49. Application of the water proofing
Layer with 2 component gun
Special 2 Component
gun used for applying
waterproofing
campound
-MasterSeal M800 is available with the Part A coloured white
and the Part B colored black.
-This results in a uniform grey colour of the sprayed material
thus giving the sprayer a visual control of the quality of the
mixing, and machine faults become immediately obvious. If
the membrane colour changes, stop spraying and check
machine .
-MasterSeal M800 is normally applied at 1.5–2.0kg/SQM this
corresponds to a thickness of 1.5–2.0mm.
Ponding test