SlideShare a Scribd company logo
Summer Training on
RESIDENTIAL BUILDINGs
FROM D.D.A
AKASH GARG
ROLL NO.- 1506800008
M.I.E.T, MEERUT
4th Year
1
2
Starting Date of Training:
06/06/2018
End Date of Training:
04/07/2018
PROJECT :- C/o 1568DUs /Cat-II(312,2BHK)+ 288(1BHK)
and 968 EWS Multistoried Composite Houses
including internal development and
electrification in pocket 5, sector 14 Dwarka
phase –II.
Agency:- M/s B G Shirke Construction
Technology Private Limited.
Estimate Cost:- Rs 233.83 crores
Tender cost:- Rs 249.12 crores
Time Allowed:- 42 Months
Date of Start:- 18/08/2017
Date of Completion:- 17/02/2021
Specification to followed:- CPWD Specification 2009 with up to
date correction slips issued.
3
Area of Plot:- 41526 Sqm
Total Plinth Area:- 83023.03 Sqm
Total built-up Area:- 151995 Sqm
Proposed Floor Area
(CAT-II HOUSING):- 51564.06 Sqm
Proposed Floor Area of EWS:- 30140.24 Sqm
Proposed Shops and park Facility- 1318.73 Sqm
1. Shop- 36 NOS
2. Recreational Room- 1 No.
3. Community Room- 1 No.
4. Senior Citizen Room- 1 No.
4
MODEL OF BUILDINGS
5
 Precast concrete is a construction product produced by casting
concrete in a reusable mold or "form" which is then cured in a
controlled environment, transported to the construction site and
lifted into place ("tilt up").
6
 Concrete elements, cast and cured in a manufacturing plant,
then transported to the construction site. • Plant casting allows
increased efficiency and higher quality control. • Durable,
permanent steel forms are reused many times, reducing
formwork costs compared to sitecast concrete. • Use of Type III,
high early strength cement and steam curing allow concrete
members to be cast and cured in as little as 24 hours. •
Controlled casting conditions and high quality forms allow for
greater control of surface finishes.
Very rapid speed of erection
Good quality control
Entire building can be precast-walls,
floors,beams,etc.
Rapid construction on site
High quality because of the controlled
conditions in the factory
Prestressing is easily done which can reduce
the size and number of the structural members.
7
 MANUFACTURING UNIT(MU)- It is the place where all the
elements of the buildings are Precasted under a control
environment.(these elements includes-
BEAMS,COLUMNS,SLABS,RETAINING WALLS etc.)
 CONSTRUCTION SITE- Place where the flats were under
construction. The elemnts manufactured in MU get transported and
assembled at the construction site as per the drawings.
 BATCHING PLANT AND QUALITY ASSUARANCE
LAB- In the batching plant, concrete is produced and the
material is tested in the quality assurance lab to assure that the
material is suitable for use or not.
8
MANUFACTURING UNIT
9
CASTING OF SLABS- Slabs moulds(frame) are prepared as per the
specification(drawings), reinforcement is placed and then concrete is
poured into the frame and is allowed to attain its compressive strength for
the duration of 28 days.
TRANSPORTATION OF SLABS- Precasted slabs are then loaded on the
conveyor through crane(capacity-15 tonne) and is transported to the site.
10DDA SUMMER
INTERSHIPVID-
20180709-WA0046.mp4
PRECASTING AT LOW TEMPERATURE
11
 It is that time of the year when cold weather plays an immense role
in the procedures, requirements and practices that encompass
precast concrete production. For manufacturers in the warmer
climates, cold-weather concreting is not so much of a concern, but it
is better to be prepared for extreme climatic conditions.
SPOT WELDING
12
 Resistance spot welding
(RSW) is a process in which
contacting metal surface
points are joined by the heat
obtained from resistance to
electric current.
 Work-pieces are held together under
pressure exerted by electrodes.
Typically the sheets are in the 0.5 to 3
mm (0.020 to 0.118 in) thickness
range. The process uses two shaped
copper alloy electrodes to concentrate
welding current into a small "spot" and
to simultaneously clamp the sheets
together.
A corrosion inhibitor is a chemical
compound that, when added to a liquid or gas,
decreases the corrosion rate of a material,
typically a metal or an alloy. The effectiveness of
a corrosion inhibitor depends on fluid
composition, quantity of water, and flow
regime. A common mechanism for inhibiting
corrosion involves formation of a coating, often
a passivation layer, which prevents access of the
corrosive substance to the metal. Permanent
treatments such as chrome platingare not
generally considered inhibitors, however.
Instead corrosion inhibitors are additives to the
fluids that surround the metal or related object.
Concentration used: 600ml per kg of
cement.
13
 RAFT FOUNDATION
 FOOTING
 PLINTH
 BASEMENT
 P.C.C(150mm)
 Retaining Wall
 Ramp
 surveying
14
Project plan-
15
RETAINING WALL
16
A retaining wall is a structure designed and constructed to
resist the lateral pressure of soil, when there is a desired
change in ground elevation that exceeds the angle of repose of
the soil.
RAFT FOOTING DDA SUMMER INTERSHIPVID_20180626_111925.3gp
17
Raft foundations (sometimes known as Mat Foundations) are a
large concrete slab which can support a number of columns and walls.
The slab is spread out under the entire building or at least a large part
of it which lowers the contact pressure compared to the traditionally
used strip or trench footings.
P.C.C(PLAINCEMENT CONCRETE)DDA SUMMER
INTERSHIPVID_20180614_120708.3gp
18
Plain cement concrete (PCC) is used to provide rigid impervious bed
to RCC in foundation where the earth is soft and yielding. PCC can be used
over brick flat soling or without brick flat soling.
THICKNESS OF P.C.C- 150mm
PLACING AND COMPACTION OF PCC:
 Make sure brick soling/sand bed level for PCC is ok.
 Make form work for PCC with wooden plank as per specified dimenSions.
 Clean dust or foreign or loose earth from concreting area.
 Spread polythene over the bed of PCC.
 Make level pillars of fresh concrete in the area at suitable intervals but not
more than 2m c/c both ways.
 Place the concrete gently (don’t through) from one side. Use the mixed
concrete within 45 minutes after the water is added.
 Use wooden rammer for compaction and finishing of PCC.
 Make the surface of PCC roughen for joining future work before the
concrete become harden.
FOOTING
19
The isolated footing is one of the most popular and simplest types of
foundation used worldwide. An isolated footing is used to support a single
column. Isolated footings are independent footings which are provided for
each column. This type of footing is used when. Columns are not closely
spaced.
ASSEMBLING OF SLAB AT THE SITE
20
SCREEDING
21
A floor screed is usually a cementitious material made from a 1:3 or 1:4.5
ratio of cement to sharp sand. It may be applied onto either a solid in-situ
concrete ground floor slab or onto a precast concrete floor unit. There are
many proprietary screeds on the market and information about these can be
obtained from the manufacturer.
PLACING OF COLUMN
22
PROBLEM:- if the drawing get revised for the new position of
column and the raft get casted, then the column reinforcement coming
out of raft is curtained and isolated foundation is perpared for the
column at the new position above the raft specified by the revised
drawing.
23
BATCHING PLANT
24
A concrete plant, also known as a batch plant or batching plant or a
concrete batching plant, is equipment that combines various ingredients
to form concrete. Some of these inputs include water,
air, admixtures, sand, aggregate (rocks, gravel, etc.), fly ash, silica fume, slag,
and cement.
25DDA SUMMER INTERSHIPVID-
20180709-WA0047.mp4
DDA SUMMER
INTERSHIPVID_20180618_115046.3gp
•Describe the quality program and organization to be implemented
so that the project is constructed in accordance with the contract
requirements and industry standards.
•Describe guidelines for inspection and documentation of
construction activities.
•Provide reasonable assurance that the completed work will meet
or exceed the requirements of the construction drawings and
specifications.
26
Need For Quality Control And Assurance In
Construction:
•Concern for project managers.
•Even minor defects in constructed facilities can cause heavy loss.
•Quality control during construction consists largely of insuring conformance
to these original design and planning decisions.
Other miscellaneous work
27
DDA SUMMER INTERSHIPVI
20180709-WA0045.mp4
28
29
30
 Learned to read structural and architectural
drawings.
 Gained basic knowledge in the field of
construction.
 Learned basic work of R.C.C structure at the
site.
 Manufacturing of structural precast component
like beams, column, slabs etc.
 Learned wise use of available resources.
 Learned an importance of proper
communication between office and work site.
31

More Related Content

What's hot

prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated Structures
Boopathi Raja
 
Technical textiles in Central Public Works Department
Technical textiles in Central Public Works DepartmentTechnical textiles in Central Public Works Department
Technical textiles in Central Public Works Department
Dr K M SONI
 
Bc open pre fabricated construction system
Bc open pre fabricated construction systemBc open pre fabricated construction system
Bc open pre fabricated construction system
Anuj Singhal
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
ashleyyeap
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
ABIRAMI G
 
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...
Shabaz Khan
 
Speedy construction
Speedy constructionSpeedy construction
Speedy construction
somitra bhardwaj
 
Company introduction
Company introduction Company introduction
Company introduction
Broad Homes Intl.
 
PEB construction-Mukesh Bhavsar
PEB construction-Mukesh BhavsarPEB construction-Mukesh Bhavsar
PEB construction-Mukesh Bhavsar
Mukesh Bhavsar
 
Prefabricated Structure and its installation process
Prefabricated Structure and its installation processPrefabricated Structure and its installation process
Prefabricated Structure and its installation process
Udayram Patil
 
Precast concrete structures
Precast concrete structuresPrecast concrete structures
Precast concrete structures
gayathrysatheesan1
 
Precast Construction technology
Precast Construction technologyPrecast Construction technology
Precast Construction technology
GedalaJairam
 
Presentation of precast concrete
Presentation of precast concretePresentation of precast concrete
Presentation of precast concrete
Ashik Ásh
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWJaspreet singh
 
ALL ABOUT PRECAST
ALL ABOUT PRECASTALL ABOUT PRECAST
ALL ABOUT PRECAST
jagrutib22
 
1.6 _Important element required to complete a building
1.6  _Important element required to complete a building1.6  _Important element required to complete a building
1.6 _Important element required to complete a buildingTeow Beng Hur
 
Aasra Martech Pvt. Ltd., New Delhi, Prefab Building Systems
Aasra Martech Pvt. Ltd., New Delhi, Prefab Building SystemsAasra Martech Pvt. Ltd., New Delhi, Prefab Building Systems
Aasra Martech Pvt. Ltd., New Delhi, Prefab Building Systems
IndiaMART InterMESH Limited
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
Prashant Borge
 
Mass Concrete, RMC, Plum Concrete
Mass Concrete, RMC, Plum ConcreteMass Concrete, RMC, Plum Concrete
Mass Concrete, RMC, Plum Concrete
Jay1997Singhania
 
Morocco Mall Post Tensioned Concrete Case Study
Morocco Mall Post Tensioned Concrete Case StudyMorocco Mall Post Tensioned Concrete Case Study
Morocco Mall Post Tensioned Concrete Case Study
CCL Concrete
 

What's hot (20)

prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated Structures
 
Technical textiles in Central Public Works Department
Technical textiles in Central Public Works DepartmentTechnical textiles in Central Public Works Department
Technical textiles in Central Public Works Department
 
Bc open pre fabricated construction system
Bc open pre fabricated construction systemBc open pre fabricated construction system
Bc open pre fabricated construction system
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
 
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...
 
Speedy construction
Speedy constructionSpeedy construction
Speedy construction
 
Company introduction
Company introduction Company introduction
Company introduction
 
PEB construction-Mukesh Bhavsar
PEB construction-Mukesh BhavsarPEB construction-Mukesh Bhavsar
PEB construction-Mukesh Bhavsar
 
Prefabricated Structure and its installation process
Prefabricated Structure and its installation processPrefabricated Structure and its installation process
Prefabricated Structure and its installation process
 
Precast concrete structures
Precast concrete structuresPrecast concrete structures
Precast concrete structures
 
Precast Construction technology
Precast Construction technologyPrecast Construction technology
Precast Construction technology
 
Presentation of precast concrete
Presentation of precast concretePresentation of precast concrete
Presentation of precast concrete
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
 
ALL ABOUT PRECAST
ALL ABOUT PRECASTALL ABOUT PRECAST
ALL ABOUT PRECAST
 
1.6 _Important element required to complete a building
1.6  _Important element required to complete a building1.6  _Important element required to complete a building
1.6 _Important element required to complete a building
 
Aasra Martech Pvt. Ltd., New Delhi, Prefab Building Systems
Aasra Martech Pvt. Ltd., New Delhi, Prefab Building SystemsAasra Martech Pvt. Ltd., New Delhi, Prefab Building Systems
Aasra Martech Pvt. Ltd., New Delhi, Prefab Building Systems
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 
Mass Concrete, RMC, Plum Concrete
Mass Concrete, RMC, Plum ConcreteMass Concrete, RMC, Plum Concrete
Mass Concrete, RMC, Plum Concrete
 
Morocco Mall Post Tensioned Concrete Case Study
Morocco Mall Post Tensioned Concrete Case StudyMorocco Mall Post Tensioned Concrete Case Study
Morocco Mall Post Tensioned Concrete Case Study
 

Similar to Dda training presentation

Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New Delhi
Jaspreet singh
 
6 pavement quality concrete
6 pavement quality concrete6 pavement quality concrete
6 pavement quality concrete
thamand7
 
14325 connels house drafting (1)
14325 connels house drafting (1)14325 connels house drafting (1)
14325 connels house drafting (1)Yousef Riad
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02Minh Bui Si
 
Acm assignment
Acm assignmentAcm assignment
Acm assignment
Aaqib Iqbal
 
uv_bpm.pdf
uv_bpm.pdfuv_bpm.pdf
uv_bpm.pdf
osamaanter1
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examples
SayedaAmrin
 
IRJET- Strengthening of New Building
IRJET- Strengthening of New BuildingIRJET- Strengthening of New Building
IRJET- Strengthening of New Building
IRJET Journal
 
New materials and technologies used in some buildings in Mumbai
New materials and technologies used in some buildings in MumbaiNew materials and technologies used in some buildings in Mumbai
New materials and technologies used in some buildings in Mumbai
Dr K M SONI
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technology
Abhishek Paul
 
JEEVA.pptx
JEEVA.pptxJEEVA.pptx
JEEVA.pptx
SachinHM14
 
B tech individual report
B tech individual reportB tech individual report
B tech individual reportong93
 
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
Firdaurs Abdullah
 
Distress of concrete structures & their repair techniques
Distress of concrete structures & their repair techniquesDistress of concrete structures & their repair techniques
Distress of concrete structures & their repair techniquesZaid Ansari
 
Metroppt
MetropptMetroppt
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
JaiminTandel1
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
Raghavendra Raghu
 
Summer training report
Summer training reportSummer training report
Summer training report
aki8872233
 

Similar to Dda training presentation (20)

Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New Delhi
 
6 pavement quality concrete
6 pavement quality concrete6 pavement quality concrete
6 pavement quality concrete
 
14325 connels house drafting (1)
14325 connels house drafting (1)14325 connels house drafting (1)
14325 connels house drafting (1)
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
 
Acm assignment
Acm assignmentAcm assignment
Acm assignment
 
uv_bpm.pdf
uv_bpm.pdfuv_bpm.pdf
uv_bpm.pdf
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examples
 
IRJET- Strengthening of New Building
IRJET- Strengthening of New BuildingIRJET- Strengthening of New Building
IRJET- Strengthening of New Building
 
New materials and technologies used in some buildings in Mumbai
New materials and technologies used in some buildings in MumbaiNew materials and technologies used in some buildings in Mumbai
New materials and technologies used in some buildings in Mumbai
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technology
 
JEEVA.pptx
JEEVA.pptxJEEVA.pptx
JEEVA.pptx
 
B tech individual report
B tech individual reportB tech individual report
B tech individual report
 
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
 
Distress of concrete structures & their repair techniques
Distress of concrete structures & their repair techniquesDistress of concrete structures & their repair techniques
Distress of concrete structures & their repair techniques
 
Metroppt
MetropptMetroppt
Metroppt
 
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
 
Site report 1
Site report 1Site report 1
Site report 1
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Ayush
AyushAyush
Ayush
 

Recently uploaded

NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 

Recently uploaded (20)

NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 

Dda training presentation

  • 1. Summer Training on RESIDENTIAL BUILDINGs FROM D.D.A AKASH GARG ROLL NO.- 1506800008 M.I.E.T, MEERUT 4th Year 1
  • 2. 2 Starting Date of Training: 06/06/2018 End Date of Training: 04/07/2018
  • 3. PROJECT :- C/o 1568DUs /Cat-II(312,2BHK)+ 288(1BHK) and 968 EWS Multistoried Composite Houses including internal development and electrification in pocket 5, sector 14 Dwarka phase –II. Agency:- M/s B G Shirke Construction Technology Private Limited. Estimate Cost:- Rs 233.83 crores Tender cost:- Rs 249.12 crores Time Allowed:- 42 Months Date of Start:- 18/08/2017 Date of Completion:- 17/02/2021 Specification to followed:- CPWD Specification 2009 with up to date correction slips issued. 3
  • 4. Area of Plot:- 41526 Sqm Total Plinth Area:- 83023.03 Sqm Total built-up Area:- 151995 Sqm Proposed Floor Area (CAT-II HOUSING):- 51564.06 Sqm Proposed Floor Area of EWS:- 30140.24 Sqm Proposed Shops and park Facility- 1318.73 Sqm 1. Shop- 36 NOS 2. Recreational Room- 1 No. 3. Community Room- 1 No. 4. Senior Citizen Room- 1 No. 4
  • 6.  Precast concrete is a construction product produced by casting concrete in a reusable mold or "form" which is then cured in a controlled environment, transported to the construction site and lifted into place ("tilt up"). 6  Concrete elements, cast and cured in a manufacturing plant, then transported to the construction site. • Plant casting allows increased efficiency and higher quality control. • Durable, permanent steel forms are reused many times, reducing formwork costs compared to sitecast concrete. • Use of Type III, high early strength cement and steam curing allow concrete members to be cast and cured in as little as 24 hours. • Controlled casting conditions and high quality forms allow for greater control of surface finishes.
  • 7. Very rapid speed of erection Good quality control Entire building can be precast-walls, floors,beams,etc. Rapid construction on site High quality because of the controlled conditions in the factory Prestressing is easily done which can reduce the size and number of the structural members. 7
  • 8.  MANUFACTURING UNIT(MU)- It is the place where all the elements of the buildings are Precasted under a control environment.(these elements includes- BEAMS,COLUMNS,SLABS,RETAINING WALLS etc.)  CONSTRUCTION SITE- Place where the flats were under construction. The elemnts manufactured in MU get transported and assembled at the construction site as per the drawings.  BATCHING PLANT AND QUALITY ASSUARANCE LAB- In the batching plant, concrete is produced and the material is tested in the quality assurance lab to assure that the material is suitable for use or not. 8
  • 10. CASTING OF SLABS- Slabs moulds(frame) are prepared as per the specification(drawings), reinforcement is placed and then concrete is poured into the frame and is allowed to attain its compressive strength for the duration of 28 days. TRANSPORTATION OF SLABS- Precasted slabs are then loaded on the conveyor through crane(capacity-15 tonne) and is transported to the site. 10DDA SUMMER INTERSHIPVID- 20180709-WA0046.mp4
  • 11. PRECASTING AT LOW TEMPERATURE 11  It is that time of the year when cold weather plays an immense role in the procedures, requirements and practices that encompass precast concrete production. For manufacturers in the warmer climates, cold-weather concreting is not so much of a concern, but it is better to be prepared for extreme climatic conditions.
  • 12. SPOT WELDING 12  Resistance spot welding (RSW) is a process in which contacting metal surface points are joined by the heat obtained from resistance to electric current.  Work-pieces are held together under pressure exerted by electrodes. Typically the sheets are in the 0.5 to 3 mm (0.020 to 0.118 in) thickness range. The process uses two shaped copper alloy electrodes to concentrate welding current into a small "spot" and to simultaneously clamp the sheets together.
  • 13. A corrosion inhibitor is a chemical compound that, when added to a liquid or gas, decreases the corrosion rate of a material, typically a metal or an alloy. The effectiveness of a corrosion inhibitor depends on fluid composition, quantity of water, and flow regime. A common mechanism for inhibiting corrosion involves formation of a coating, often a passivation layer, which prevents access of the corrosive substance to the metal. Permanent treatments such as chrome platingare not generally considered inhibitors, however. Instead corrosion inhibitors are additives to the fluids that surround the metal or related object. Concentration used: 600ml per kg of cement. 13
  • 14.  RAFT FOUNDATION  FOOTING  PLINTH  BASEMENT  P.C.C(150mm)  Retaining Wall  Ramp  surveying 14
  • 16. RETAINING WALL 16 A retaining wall is a structure designed and constructed to resist the lateral pressure of soil, when there is a desired change in ground elevation that exceeds the angle of repose of the soil.
  • 17. RAFT FOOTING DDA SUMMER INTERSHIPVID_20180626_111925.3gp 17 Raft foundations (sometimes known as Mat Foundations) are a large concrete slab which can support a number of columns and walls. The slab is spread out under the entire building or at least a large part of it which lowers the contact pressure compared to the traditionally used strip or trench footings.
  • 18. P.C.C(PLAINCEMENT CONCRETE)DDA SUMMER INTERSHIPVID_20180614_120708.3gp 18 Plain cement concrete (PCC) is used to provide rigid impervious bed to RCC in foundation where the earth is soft and yielding. PCC can be used over brick flat soling or without brick flat soling. THICKNESS OF P.C.C- 150mm PLACING AND COMPACTION OF PCC:  Make sure brick soling/sand bed level for PCC is ok.  Make form work for PCC with wooden plank as per specified dimenSions.  Clean dust or foreign or loose earth from concreting area.  Spread polythene over the bed of PCC.  Make level pillars of fresh concrete in the area at suitable intervals but not more than 2m c/c both ways.  Place the concrete gently (don’t through) from one side. Use the mixed concrete within 45 minutes after the water is added.  Use wooden rammer for compaction and finishing of PCC.  Make the surface of PCC roughen for joining future work before the concrete become harden.
  • 19. FOOTING 19 The isolated footing is one of the most popular and simplest types of foundation used worldwide. An isolated footing is used to support a single column. Isolated footings are independent footings which are provided for each column. This type of footing is used when. Columns are not closely spaced.
  • 20. ASSEMBLING OF SLAB AT THE SITE 20
  • 21. SCREEDING 21 A floor screed is usually a cementitious material made from a 1:3 or 1:4.5 ratio of cement to sharp sand. It may be applied onto either a solid in-situ concrete ground floor slab or onto a precast concrete floor unit. There are many proprietary screeds on the market and information about these can be obtained from the manufacturer.
  • 23. PROBLEM:- if the drawing get revised for the new position of column and the raft get casted, then the column reinforcement coming out of raft is curtained and isolated foundation is perpared for the column at the new position above the raft specified by the revised drawing. 23
  • 24. BATCHING PLANT 24 A concrete plant, also known as a batch plant or batching plant or a concrete batching plant, is equipment that combines various ingredients to form concrete. Some of these inputs include water, air, admixtures, sand, aggregate (rocks, gravel, etc.), fly ash, silica fume, slag, and cement.
  • 25. 25DDA SUMMER INTERSHIPVID- 20180709-WA0047.mp4 DDA SUMMER INTERSHIPVID_20180618_115046.3gp
  • 26. •Describe the quality program and organization to be implemented so that the project is constructed in accordance with the contract requirements and industry standards. •Describe guidelines for inspection and documentation of construction activities. •Provide reasonable assurance that the completed work will meet or exceed the requirements of the construction drawings and specifications. 26 Need For Quality Control And Assurance In Construction: •Concern for project managers. •Even minor defects in constructed facilities can cause heavy loss. •Quality control during construction consists largely of insuring conformance to these original design and planning decisions.
  • 27. Other miscellaneous work 27 DDA SUMMER INTERSHIPVI 20180709-WA0045.mp4
  • 28. 28
  • 29. 29
  • 30. 30
  • 31.  Learned to read structural and architectural drawings.  Gained basic knowledge in the field of construction.  Learned basic work of R.C.C structure at the site.  Manufacturing of structural precast component like beams, column, slabs etc.  Learned wise use of available resources.  Learned an importance of proper communication between office and work site. 31