SlideShare a Scribd company logo
Precast Segmental Lining Design W.K. Kong (2007)
Overview  ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Concept of Shield Tunnel Design ,[object Object],[object Object],[object Object],[object Object],[object Object]
Design Standard and Specification ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Segmental Lining Design – Lining Geometry ,[object Object],Tunnel advance Leading edge Trailing edge Circumferential joint Radial joint Key block
Segmental Lining Design – Lining Geometry ,[object Object],Universal Taper Ring Left Hand Taper Ring Left Hand Taper Ring
Segmental Lining Design – Lining Geometry ,[object Object],Bolt hole Segment plate arrangement and number of bolts are critical for: a) Alignment control b) Practical handling ring build R – Rectangular T – Trapezoidal K – Key block R R R T T K
Segmental Lining Design – Lining Geometry ,[object Object]
Segmental Lining Design – Lining Geometry ,[object Object],[object Object],[object Object],[object Object],[object Object]
Segmental Lining Design – Lining Geometry Key block design Principle issues: a) Limiting obliqueness of angle (as surface becomes twisted) b) Ensuring can be inserted by TBM segment erector
Segmental Lining Design – Lining Geometry Key block design Principle issues: a) Limiting obliqueness of angle (as surface becomes twisted) b) Ensuring can be inserted by TBM segment erector
Segmental Lining Design – Lining Geometry
Segmental Lining Design – Calculation of Internal Forces ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Segmental Lining Design – Calculation of Internal Forces ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Ultimate Limit State: Check against failure Max. Bending moment/min. thrust couple
Segmental Lining Design – Calculation of Internal Forces ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Serviceability Limit State: Check against cracking Max. Bending moment/min. thrust couple
Segmental Lining Design – Calculation of Internal Forces ,[object Object],[object Object],[object Object],[object Object],Example: 6m diameter tunnel 20m deep Lining = 250mm segmental Stiff Clay – E = 100MPa Ko = 0.8
Segmental Lining Design – Calculation of Internal Forces ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Segmental Lining Design – Calculation of Internal Forces ,[object Object],Curtis/Muir Wood (1976) Method Elastic continuum analysis for cases in soil or rock Worst Case
Segmental Lining Design – Calculation of Internal Forces ,[object Object],Assessed using methods of Morgan (1961) to derive bending moment due to distortion coupled with minimum thrust value: a)  deflection checking at maximum allowable deflection of 1% internal diameter; b)  future development load case: distortion of 25mm. For assumed jointed and un-jointed lining, where Moment of Inertia derived from Muir Wood (1975).
Segmental Lining Design – Calculation of Internal Forces Effects of Poor Ring Build
Segmental Lining Design – Calculation of Internal Forces Effects of Poor Ring Build
Segmental Lining Design – Calculation of Internal Forces Effects of Poor Ring Build
Segmental Lining Design – Calculation of Internal Forces Grouting loads (annulus and secondary grouting): Assessment: a)  Determine   grout  for Annulus Primary and Secondary Grouting; b)  Check using Muir-Wood (1976) – Stage 1 will give Big Thrust, Zero Moment,  Stage 2 will give Small Thrust, Large Moment
Segmental Lining Design – Calculation of Internal Forces ,[object Object],[object Object],[object Object],Analysis of effects of eccentric ram loads TBM propulsion jacking loads:
Segmental Lining Design – Calculation of Internal Forces TBM propulsion jacking loads:  Assessed using Guyon (1972)
Segmental Lining Design – Calculation of Internal Forces Seismic Design  – Use method of Wang (1991) Assess impact of: a) Axial deformation along tunnel b) Curvature deformation along tunnel c) Ovaling of tunnel profile Normally, no special joints are required, more reinforcement may be needed.
Segmental Lining Design – Calculation of Internal Forces ,[object Object],Handling and stacking loads Normally, check reinforcement capacity derived for other reasons, against stacking loads
Segmental Lining Design – Calculation of Internal Forces ,[object Object],Handling and stacking loads Normally, check reinforcement capacity derived for other reasons, against handling loads
Segmental Lining Design – Calculation of Internal Forces Reinforcement Design:
Segmental Lining Design – Calculation of Internal Forces Reinforcement Design Design of reinforcing quantity and layout needs to accommodate: a) Design loading; b) Distribution to limit crack widths and cover for durability; c) Limit damage (accidental or under loading) around bolt pockets, lifting socket, segment corners, etc).
Segmental Lining Design – Calculation of Internal Forces Reinforcement Design:
Segmental Lining Design – Calculation of Internal Forces ,[object Object],Reinforcement Design – Circumferential bars:
Bolt Design Design principles: Bolts are intended to: a) Aid ring build quality b) Compress gaskets c) Provide safety prior to annulus grout hardening Bolts can be curved or straight (steel or plastics).  Bolts and washer assemblies do not need waterproofing
Segment Manufacture Documentation required: a) Segment design drawings; b) Segment mould shop drawings; c) Specification on casting, concrete mix, steel fixing, etc. d) Tolerances for mould, steel fixing, etc.
Waterproofing Design Main waterproofing elements: a)  Gaskets on all joints with hydrophilic inserts in gaskets b)  Use of hydrophilic strips c)  Provision of caulking groove Soil side Drive direction
Waterproofing Design Gasket design:  Need to check against poor ring build and bolt capacity
TBM Introduction Type of TBM ( (According AFTES Association)  Ground support Main TBM Types  None  Beam TBM Road Header  With Shied Support only Open Shield Machine  With Shield and Front support Earth pressure balance Machine Slurry Machine Compressed air shield
TBM with no shield and frontal support Main Beam and Reamer Beam Machine Road Header
TBM with open shield  Double Shield TBM Single Shield TBM
Closed Shield TBM – Slurry Machine Confinement is achieved by pressurizing boring fluid inside the cutterhead chamber
Slurry Machine/ AIR BUBBLE TECHNOLOGY  ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],1 2 3 4 5 6 7 8
Slurry Machine /  AIR BUBBLE TECHNOLOGY  ,[object Object],[object Object],[object Object],[object Object],[object Object],3 1 4 5 2
Closed Shield TBM – EPBM  Shield Tail skin Mucking and support functions trailing Ring building and annulus grouting Propulsion / steerage Excavation Active pre-cast concrete tunnel lining support
Mix Shield Machine ,[object Object]
TBM OPERATION – Erecting for launch Launching shaft prepared Lower part of shield, bulkhead and drive rams Installing main drive
TBM OPERATION – Erecting for launch Upper shield and drive rams Lower part of tail-skin Ring erector installed   Cutter-head installed
TBM OPERATION – Erecting Al Bugeisha for launch Completed shield and tail-skin  Prepared launching eye with seals
TBM OPERATION – Segmental tunnel lining Stack of 3 test rings  Ring placed in TBM tail skin Ground is not exposed  Segment casting  Soil  Annulus grout  Key block
PORE WATER PRESSURE IN SCREW Soil conditioning improves hydraulic gradient in screw TBM OPERATION – Application of EPB face pressure h o h 1 Ratio of h 1 /h o  is linearly proportional to achievable effective face pressure h 2 Second screw is a risk mitigation measure   Soil conditioning = higher effective face pressure
TBM OPERATION – Alignment control Use of ring taper on curves  ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
TBM OPERATION – Measures to limit settlement risk AVOIDANCE OF OVER-EXCAVATION: If results indicate over-excavation: ,[object Object],[object Object],Cut soil: Volume = 109m 3 /ring Mass = approx. 212T/ring Spoil from advance: Volume =F.109m 3 /ring Mass = f.212T/ring Muck volume compared to theoretical volume, by means of: ,[object Object],[object Object],Volume m 3 /m Advance (m)
TBM Selection ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
TBM Selection – Face stability   Yoshikowa  et al  (1980) Requires measures to maintain slurry pressure Slurry TBM requires heavy de-siltation facilities Slurry requires secondary separation treatment  High risk of blockages particularly when N>15 APPLICABILITY OF SLURRY TBM FOR COMPARISON
TBM Selection  Geological Profiles
TBM Selection  ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
TBM Selection ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
TBM Selection  ,[object Object],[object Object],[object Object],[object Object],[object Object]
TBM Selection  ,[object Object],[object Object],[object Object],[object Object],[object Object]

More Related Content

What's hot

report for tunnelling by tunnel boring machine
report for tunnelling by tunnel boring machinereport for tunnelling by tunnel boring machine
report for tunnelling by tunnel boring machine
VISHAL KUMAR SINGH
 
Geotechnical investigation
Geotechnical investigationGeotechnical investigation
Geotechnical investigation
Abdul Mutakaber Tareen
 
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Make Mannan
 
Dense Bituminous macadam
Dense Bituminous macadamDense Bituminous macadam
Dense Bituminous macadam
pradip dangar
 
Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]
Muhammad Irfan
 
Soil investigation
Soil investigationSoil investigation
Soil investigation
Simarpreet Singh
 
Pile load test
Pile load testPile load test
Pile load test
Naman Kantesaria
 
Ground improvement techniques compaction vibration
Ground improvement techniques  compaction vibrationGround improvement techniques  compaction vibration
Ground improvement techniques compaction vibration
Anjana R Menon
 
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Make Mannan
 
Grouting Methods
Grouting Methods Grouting Methods
Grouting Methods
Rushikesh Kolhe
 
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONSPILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
Shivananda Roy
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
VATSAL PATEL
 
Interface treatment
Interface treatmentInterface treatment
Interface treatment
pradip dangar
 
Shield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and LessonsShield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and Lessonscoen_van_der_vliet
 
Lining of tunnel
Lining of tunnelLining of tunnel
Lining of tunnel
Giri Guru
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
jagadish chintu
 
case study on terzaghi’s theory
case study on terzaghi’s theorycase study on terzaghi’s theory
case study on terzaghi’s theory
Abhishek Mangukiya
 
Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)
Mayur Rahangdale
 

What's hot (20)

Tbm
TbmTbm
Tbm
 
report for tunnelling by tunnel boring machine
report for tunnelling by tunnel boring machinereport for tunnelling by tunnel boring machine
report for tunnelling by tunnel boring machine
 
Geotechnical investigation
Geotechnical investigationGeotechnical investigation
Geotechnical investigation
 
NATM-Time cycle presentation (2)
NATM-Time cycle presentation (2)NATM-Time cycle presentation (2)
NATM-Time cycle presentation (2)
 
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
 
Dense Bituminous macadam
Dense Bituminous macadamDense Bituminous macadam
Dense Bituminous macadam
 
Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]
 
Soil investigation
Soil investigationSoil investigation
Soil investigation
 
Pile load test
Pile load testPile load test
Pile load test
 
Ground improvement techniques compaction vibration
Ground improvement techniques  compaction vibrationGround improvement techniques  compaction vibration
Ground improvement techniques compaction vibration
 
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
 
Grouting Methods
Grouting Methods Grouting Methods
Grouting Methods
 
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONSPILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
 
Interface treatment
Interface treatmentInterface treatment
Interface treatment
 
Shield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and LessonsShield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and Lessons
 
Lining of tunnel
Lining of tunnelLining of tunnel
Lining of tunnel
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
case study on terzaghi’s theory
case study on terzaghi’s theorycase study on terzaghi’s theory
case study on terzaghi’s theory
 
Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)
 

Viewers also liked

Tunneling
Tunneling Tunneling
Tunneling
ila vamsi krishna
 
World Tunnel Conference 2014
World Tunnel Conference 2014World Tunnel Conference 2014
World Tunnel Conference 2014
richardbieniawski
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
Durgesh Kumar Yadav
 
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Hamed Zarei
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
Top down construction
Top down constructionTop down construction
Top down construction
Amulya Kansal
 
New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)
Austrian Standards
 
Directional Drilling
Directional DrillingDirectional Drilling
Directional Drilling
Narendra Kumar Dewangan
 
Tunneling Construction - NATM
Tunneling Construction - NATMTunneling Construction - NATM
Tunneling Construction - NATM
luisaam
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
1971995
 
Dam PPT
Dam PPTDam PPT
Guidelines
GuidelinesGuidelines
Guidelines
Šumadin Šumić
 
Tunnel engg.2
Tunnel engg.2Tunnel engg.2
Tunnel engg.2
SHUBHAM DABHADE
 
Corrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel SolutionsCorrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel Solutions
Communications Branding
 
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Mohit Shukla
 
Precast segmental concrete bridges a
Precast segmental concrete bridges aPrecast segmental concrete bridges a
Precast segmental concrete bridges a
Palmer Consulting Services, LLC
 
My publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazineMy publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazineFilipe Mello
 
Bridge
BridgeBridge

Viewers also liked (20)

Bridge 91 Design
Bridge 91 DesignBridge 91 Design
Bridge 91 Design
 
Tunneling
Tunneling Tunneling
Tunneling
 
World Tunnel Conference 2014
World Tunnel Conference 2014World Tunnel Conference 2014
World Tunnel Conference 2014
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Top down construction
Top down constructionTop down construction
Top down construction
 
New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)
 
Directional Drilling
Directional DrillingDirectional Drilling
Directional Drilling
 
Tunneling Construction - NATM
Tunneling Construction - NATMTunneling Construction - NATM
Tunneling Construction - NATM
 
Casting yard
Casting yardCasting yard
Casting yard
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
 
Dam PPT
Dam PPTDam PPT
Dam PPT
 
Guidelines
GuidelinesGuidelines
Guidelines
 
Tunnel engg.2
Tunnel engg.2Tunnel engg.2
Tunnel engg.2
 
Corrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel SolutionsCorrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel Solutions
 
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
 
Precast segmental concrete bridges a
Precast segmental concrete bridges aPrecast segmental concrete bridges a
Precast segmental concrete bridges a
 
My publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazineMy publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazine
 
Bridge
BridgeBridge
Bridge
 

Similar to Segmental Lining Design Presentation

Armtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End TreatmentsArmtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End Treatments
Communications Branding
 
DESIGN OF POST TENSIONED DECK SLAB FOR FLYOVER
DESIGN OF POST TENSIONED DECK SLAB FOR FLYOVERDESIGN OF POST TENSIONED DECK SLAB FOR FLYOVER
DESIGN OF POST TENSIONED DECK SLAB FOR FLYOVER
ManiKandan1175
 
Economic Concrete Frame Elements to Eurocode 2
Economic Concrete Frame Elements to Eurocode 2Economic Concrete Frame Elements to Eurocode 2
Economic Concrete Frame Elements to Eurocode 2
Yusuf Yıldız
 
10 steps pt_floor_design_si_international_version
10 steps pt_floor_design_si_international_version10 steps pt_floor_design_si_international_version
10 steps pt_floor_design_si_international_version
Nguyen Viet Tran
 
Hospital building project
Hospital building projectHospital building project
Hospital building project
sasi vijayalakshmi
 
Calculation note 29 11-2014
Calculation note 29 11-2014Calculation note 29 11-2014
Calculation note 29 11-2014
Khaled Eid
 
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Lovneesh Modi
 
36405231_seismic_design_steps_153.ppt
36405231_seismic_design_steps_153.ppt36405231_seismic_design_steps_153.ppt
36405231_seismic_design_steps_153.ppt
IrshadKhan97473
 
Seismic design steps
Seismic design stepsSeismic design steps
Seismic design steps
lalithkumar1451
 
SEISMIC DESIGN STEPS.ppt
SEISMIC DESIGN STEPS.pptSEISMIC DESIGN STEPS.ppt
SEISMIC DESIGN STEPS.ppt
AteeqRahman26
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
kiransuresh7
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
19R002-SDN-MJB-021-SUP-01.pdf
19R002-SDN-MJB-021-SUP-01.pdf19R002-SDN-MJB-021-SUP-01.pdf
19R002-SDN-MJB-021-SUP-01.pdf
Chandan Sharma
 
Design of earth-retaining structures - Lecture 6
Design of earth-retaining structures - Lecture 6Design of earth-retaining structures - Lecture 6
Design of earth-retaining structures - Lecture 6
Chris Bridges
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefitPerwez Ahmad
 
IRJET- Earthquake Resistance Column by using Helical Reinforcement
IRJET-  	  Earthquake Resistance Column by using Helical ReinforcementIRJET-  	  Earthquake Resistance Column by using Helical Reinforcement
IRJET- Earthquake Resistance Column by using Helical Reinforcement
IRJET Journal
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor Slab
IRJET Journal
 
Analysis and Design of Earthquake Resistant RC multi storied (G+3) Residentia...
Analysis and Design of Earthquake Resistant RC multi storied (G+3) Residentia...Analysis and Design of Earthquake Resistant RC multi storied (G+3) Residentia...
Analysis and Design of Earthquake Resistant RC multi storied (G+3) Residentia...
Kumar Aman
 

Similar to Segmental Lining Design Presentation (20)

Armtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End TreatmentsArmtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End Treatments
 
DESIGN OF POST TENSIONED DECK SLAB FOR FLYOVER
DESIGN OF POST TENSIONED DECK SLAB FOR FLYOVERDESIGN OF POST TENSIONED DECK SLAB FOR FLYOVER
DESIGN OF POST TENSIONED DECK SLAB FOR FLYOVER
 
Economic Concrete Frame Elements to Eurocode 2
Economic Concrete Frame Elements to Eurocode 2Economic Concrete Frame Elements to Eurocode 2
Economic Concrete Frame Elements to Eurocode 2
 
Company profile
Company profileCompany profile
Company profile
 
10 steps pt_floor_design_si_international_version
10 steps pt_floor_design_si_international_version10 steps pt_floor_design_si_international_version
10 steps pt_floor_design_si_international_version
 
Hospital building project
Hospital building projectHospital building project
Hospital building project
 
Presentation
PresentationPresentation
Presentation
 
Calculation note 29 11-2014
Calculation note 29 11-2014Calculation note 29 11-2014
Calculation note 29 11-2014
 
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
 
36405231_seismic_design_steps_153.ppt
36405231_seismic_design_steps_153.ppt36405231_seismic_design_steps_153.ppt
36405231_seismic_design_steps_153.ppt
 
Seismic design steps
Seismic design stepsSeismic design steps
Seismic design steps
 
SEISMIC DESIGN STEPS.ppt
SEISMIC DESIGN STEPS.pptSEISMIC DESIGN STEPS.ppt
SEISMIC DESIGN STEPS.ppt
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
19R002-SDN-MJB-021-SUP-01.pdf
19R002-SDN-MJB-021-SUP-01.pdf19R002-SDN-MJB-021-SUP-01.pdf
19R002-SDN-MJB-021-SUP-01.pdf
 
Design of earth-retaining structures - Lecture 6
Design of earth-retaining structures - Lecture 6Design of earth-retaining structures - Lecture 6
Design of earth-retaining structures - Lecture 6
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefit
 
IRJET- Earthquake Resistance Column by using Helical Reinforcement
IRJET-  	  Earthquake Resistance Column by using Helical ReinforcementIRJET-  	  Earthquake Resistance Column by using Helical Reinforcement
IRJET- Earthquake Resistance Column by using Helical Reinforcement
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor Slab
 
Analysis and Design of Earthquake Resistant RC multi storied (G+3) Residentia...
Analysis and Design of Earthquake Resistant RC multi storied (G+3) Residentia...Analysis and Design of Earthquake Resistant RC multi storied (G+3) Residentia...
Analysis and Design of Earthquake Resistant RC multi storied (G+3) Residentia...
 

Segmental Lining Design Presentation

  • 1. Precast Segmental Lining Design W.K. Kong (2007)
  • 2.
  • 3.
  • 4.
  • 5.
  • 6.
  • 7.
  • 8.
  • 9.
  • 10. Segmental Lining Design – Lining Geometry Key block design Principle issues: a) Limiting obliqueness of angle (as surface becomes twisted) b) Ensuring can be inserted by TBM segment erector
  • 11. Segmental Lining Design – Lining Geometry Key block design Principle issues: a) Limiting obliqueness of angle (as surface becomes twisted) b) Ensuring can be inserted by TBM segment erector
  • 12. Segmental Lining Design – Lining Geometry
  • 13.
  • 14.
  • 15.
  • 16.
  • 17.
  • 18.
  • 19.
  • 20. Segmental Lining Design – Calculation of Internal Forces Effects of Poor Ring Build
  • 21. Segmental Lining Design – Calculation of Internal Forces Effects of Poor Ring Build
  • 22. Segmental Lining Design – Calculation of Internal Forces Effects of Poor Ring Build
  • 23. Segmental Lining Design – Calculation of Internal Forces Grouting loads (annulus and secondary grouting): Assessment: a) Determine  grout for Annulus Primary and Secondary Grouting; b) Check using Muir-Wood (1976) – Stage 1 will give Big Thrust, Zero Moment, Stage 2 will give Small Thrust, Large Moment
  • 24.
  • 25. Segmental Lining Design – Calculation of Internal Forces TBM propulsion jacking loads: Assessed using Guyon (1972)
  • 26. Segmental Lining Design – Calculation of Internal Forces Seismic Design – Use method of Wang (1991) Assess impact of: a) Axial deformation along tunnel b) Curvature deformation along tunnel c) Ovaling of tunnel profile Normally, no special joints are required, more reinforcement may be needed.
  • 27.
  • 28.
  • 29. Segmental Lining Design – Calculation of Internal Forces Reinforcement Design:
  • 30. Segmental Lining Design – Calculation of Internal Forces Reinforcement Design Design of reinforcing quantity and layout needs to accommodate: a) Design loading; b) Distribution to limit crack widths and cover for durability; c) Limit damage (accidental or under loading) around bolt pockets, lifting socket, segment corners, etc).
  • 31. Segmental Lining Design – Calculation of Internal Forces Reinforcement Design:
  • 32.
  • 33. Bolt Design Design principles: Bolts are intended to: a) Aid ring build quality b) Compress gaskets c) Provide safety prior to annulus grout hardening Bolts can be curved or straight (steel or plastics). Bolts and washer assemblies do not need waterproofing
  • 34. Segment Manufacture Documentation required: a) Segment design drawings; b) Segment mould shop drawings; c) Specification on casting, concrete mix, steel fixing, etc. d) Tolerances for mould, steel fixing, etc.
  • 35. Waterproofing Design Main waterproofing elements: a) Gaskets on all joints with hydrophilic inserts in gaskets b) Use of hydrophilic strips c) Provision of caulking groove Soil side Drive direction
  • 36. Waterproofing Design Gasket design: Need to check against poor ring build and bolt capacity
  • 37. TBM Introduction Type of TBM ( (According AFTES Association) Ground support Main TBM Types None Beam TBM Road Header With Shied Support only Open Shield Machine With Shield and Front support Earth pressure balance Machine Slurry Machine Compressed air shield
  • 38. TBM with no shield and frontal support Main Beam and Reamer Beam Machine Road Header
  • 39. TBM with open shield Double Shield TBM Single Shield TBM
  • 40. Closed Shield TBM – Slurry Machine Confinement is achieved by pressurizing boring fluid inside the cutterhead chamber
  • 41.
  • 42.
  • 43. Closed Shield TBM – EPBM Shield Tail skin Mucking and support functions trailing Ring building and annulus grouting Propulsion / steerage Excavation Active pre-cast concrete tunnel lining support
  • 44.
  • 45. TBM OPERATION – Erecting for launch Launching shaft prepared Lower part of shield, bulkhead and drive rams Installing main drive
  • 46. TBM OPERATION – Erecting for launch Upper shield and drive rams Lower part of tail-skin Ring erector installed Cutter-head installed
  • 47. TBM OPERATION – Erecting Al Bugeisha for launch Completed shield and tail-skin Prepared launching eye with seals
  • 48. TBM OPERATION – Segmental tunnel lining Stack of 3 test rings Ring placed in TBM tail skin Ground is not exposed Segment casting Soil Annulus grout Key block
  • 49. PORE WATER PRESSURE IN SCREW Soil conditioning improves hydraulic gradient in screw TBM OPERATION – Application of EPB face pressure h o h 1 Ratio of h 1 /h o is linearly proportional to achievable effective face pressure h 2 Second screw is a risk mitigation measure Soil conditioning = higher effective face pressure
  • 50.
  • 51.
  • 52.
  • 53. TBM Selection – Face stability   Yoshikowa et al (1980) Requires measures to maintain slurry pressure Slurry TBM requires heavy de-siltation facilities Slurry requires secondary separation treatment High risk of blockages particularly when N>15 APPLICABILITY OF SLURRY TBM FOR COMPARISON
  • 54. TBM Selection Geological Profiles
  • 55.
  • 56.
  • 57.
  • 58.

Editor's Notes

  1. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  2. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  3. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  4. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  5. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  6. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  7. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  8. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  9. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  10. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  11. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  12. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  13. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  14. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  15. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  16. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  17. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  18. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  19. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  20. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  21. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  22. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  23. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  24. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  25. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  26. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  27. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  28. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  29. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  30. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  31. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  32. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  33. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  34. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  35. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  36. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  37. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  38. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  39. NOTES: This slide illustrates the main portions of the EPB TBM and activities that are undertaken. Key feature is ring building within the protection of the tail-skin.
  40. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  41. NOTES: No added comment
  42. NOTES: No added comment
  43. NOTES: This slide illustrates the launching seal that pressures onto the shield skin, permitting early pressurising of the cutterhead with grout/backfill or other materials.
  44. NOTES: This slide illustrates how the permanent, one-pass placement, segmental lining is placed within the protection of the tail-skin and continuous annulus grouting maintains bedding of the ring and limits ground movements.
  45. NOTES: This slide illustrates the mechanism of the screw in applying face pressure and the importance of pore water pressure control.
  46. NOTES: This slide illustrates steering mechanisms and survey control measures to limit risk of mis-alignment.
  47. NOTES: This slide illustrates the importance of monitoring actual spoil quantity compared to assumed quantities to limit risk of over-excavation and subsequent settlement/subsidence risk.
  48. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  49. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  50. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  51. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  52. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
  53. The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.