The document discusses the design of precast segmental tunnel linings used for shield tunneling. It covers key aspects of segmental lining design including geometry, calculation of internal forces, reinforcement design, segment manufacture, waterproofing, and types of tunnel boring machines (TBMs) used for shield tunnel excavation.
tunnel lining may be permanent or temporary based upon their use and requirement. design of lining is done in two parts one is temporary or initial lining design and other is permanent design of the lining. empirical and theoretical methods are major design methods.
Diaphragm wall: Construction and DesignUmer Farooq
Diaphragm walls are concrete or reinforced concrete walls constructed in slurry-supported, open trenches below existing ground.
Concrete is placed using the Tremie installation method or by installing pre-cast concrete panels (known as a pre-cast diaphragm wall). Diaphragm walls can be constructed to depths of 150 meters and to widths of 0.5 to 1.50 meters.
tunnel lining may be permanent or temporary based upon their use and requirement. design of lining is done in two parts one is temporary or initial lining design and other is permanent design of the lining. empirical and theoretical methods are major design methods.
Diaphragm wall: Construction and DesignUmer Farooq
Diaphragm walls are concrete or reinforced concrete walls constructed in slurry-supported, open trenches below existing ground.
Concrete is placed using the Tremie installation method or by installing pre-cast concrete panels (known as a pre-cast diaphragm wall). Diaphragm walls can be constructed to depths of 150 meters and to widths of 0.5 to 1.50 meters.
Dense Bituminous Macadam (DBM) is a binder course used for roads with more number of heavy commercial vehicles and a close-graded premix material having a voids content of 5-10 per cent.
Class notes of Geotechnical Engineering course I used to teach at UET Lahore. Feel free to download the slide show.
Anyone looking to modify these files and use them for their own teaching purposes can contact me directly to get hold of editable version.
Necessity/advantage of a tunnel, Classification of Tunnels,
Size and shape of a tunnel, Alignment of a Tunnel, Portals and Shafts,
Methods of Tunneling in Hard Rock and Soft ground, Mucking, Lighting
and Ventilation in tunnel, Dust control, Drainage of tunnels, Safety in
tunnel construction.
Dense Bituminous Macadam (DBM) is a binder course used for roads with more number of heavy commercial vehicles and a close-graded premix material having a voids content of 5-10 per cent.
Class notes of Geotechnical Engineering course I used to teach at UET Lahore. Feel free to download the slide show.
Anyone looking to modify these files and use them for their own teaching purposes can contact me directly to get hold of editable version.
Necessity/advantage of a tunnel, Classification of Tunnels,
Size and shape of a tunnel, Alignment of a Tunnel, Portals and Shafts,
Methods of Tunneling in Hard Rock and Soft ground, Mucking, Lighting
and Ventilation in tunnel, Dust control, Drainage of tunnels, Safety in
tunnel construction.
Closing Lecture: World Tunnel Congress 2014, Iguassu Falls, Brazil
Quo Vadis Tunnel Engineering?Predicting the Unpredictable
by Z T Richard Bieniawski v. Preinl
The Austrian Standards Institute published ÖNORM B 2203-1 “Underground Works – Works contract, Part 1: Cyclic driving (conventional tunnelling)” in 2001.
This Austrian Standard includes particular directives for tendering procedures, preparation of the bid and terms of contract for the execution of conventional tunnelling called “New Austrian Tunnelling Method (NATM)”.
In addition to the Standard the Austrian Society for Geomechanics in 2011 published the document “The Austrian Practice of NATM Tunnelling Contracts” which describes the application of the Standard in detail with respect to the NATM. The main chapters of the document are
Tendering and Costing as well as Construction and Payment with information in detail about
time-dependent costs,
tunnelling interruptions
, tunnel classes
, difficulties due to water ingress
, over-excavation, excess concrete
, selection of supporting measures and classifying tunnelling
. Examples describing the method are presented in an annex
. The Austrian Society for Geomechanics recommends the download of this document in addition to the Austrian Standard ÖNORM B 2203-1:2001. The document “The Austrian Practice of NATM Tunnelling Contracts” with its annex is free of charge. Learn more: http://www.as-institute.at/en/standards/downloads.html
Join Ron Prychitko & Lorne Mielty for an overview of various Bridge-Plate, Multi-Plate and Tunnel Liner Plate applications. Through the presentation of various case studies they will cover product selection criteria for corrugated steel plate structures and best practices including assembly and installation.
Case study examples will include bridges, culverts, wildlife passes, mine portals, pedestrian tunnels and more.
What You’ll Learn:
-Learn about unique applications that solve demanding -problems
-Advantages of soil/steel structures
-Construction process for structures
-Available product, application and design resources
-General Canadian Codes and Standards will be referenced
Who Should Attend
-Bridge / Structural Engineers
-Municipal & Transportation Engineers
-Municipal, Provincial and Federal Infrastructure personnel
-Developers
-Earthworks & Highways Contractors
-Mining Engineers & Contractors
-Road Superintendents
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Mohit Shukla
This paper has been selected for oral presentation as well as inclusion in the conference proceedings of the ICCCGE 2016 : 18th International Conference on Civil,Construction and Geological Engineering held in Toronto, Canada during June,
13-14, 2016. This paper was also able to find a position in the international conference of Dams and Hydropower held at Laos in May 2016.
A presentation of a precast segmental casting yard setup showing the required sequential steps. At the time, I worked for Parsons Brinckerhoff as Lead Construction Engineer.
oin Heba Ahmed and Drew Willms for Soil Steel Structures & End Treatments – Design Basics. The presenters will begin with an overview of the benefits of buried plate structures and will then go over design basics, coating options, shapes and custom fittings. They will finish up with reviewing the necessity of, and best practices in, end-treatment selection.
Various soil steel structures will be highlighted including Bridge-Plate, Multi-Plate, Bin-Wall and Sheeting as well as different wall materials used as end treatments.
Who Should Attend
Bridge / Structural Engineers
Road & Transportation Engineers
Road Superintendents
Provincial Departments of Transport
Earthworks & Highways Contractors
Mining Contractors
Mining Engineers
Municipal Engineers
Forestry Contractors
What You'll Learn
Benefits and applications of buried plate structures
Design considerations
Choosing the right coating for the project application
End treatment options and selection criteria
Review of case studies and applications across Canada
Economic Concrete Frame Elements to Eurocode 2Yusuf Yıldız
Eurocode 2'ye göre betonarme çerçeve elemanlarının ekonomik tasarımlarını ele alan dokümanın içerisinde yerinde dökülen, prekast, kompozit, ardgerme kolonlar, kirişler, döşemeler, perdeler ve merdivenlerin tasarımlarına dair bilgiler yer almakta.
10. Segmental Lining Design – Lining Geometry Key block design Principle issues: a) Limiting obliqueness of angle (as surface becomes twisted) b) Ensuring can be inserted by TBM segment erector
11. Segmental Lining Design – Lining Geometry Key block design Principle issues: a) Limiting obliqueness of angle (as surface becomes twisted) b) Ensuring can be inserted by TBM segment erector
23. Segmental Lining Design – Calculation of Internal Forces Grouting loads (annulus and secondary grouting): Assessment: a) Determine grout for Annulus Primary and Secondary Grouting; b) Check using Muir-Wood (1976) – Stage 1 will give Big Thrust, Zero Moment, Stage 2 will give Small Thrust, Large Moment
24.
25. Segmental Lining Design – Calculation of Internal Forces TBM propulsion jacking loads: Assessed using Guyon (1972)
26. Segmental Lining Design – Calculation of Internal Forces Seismic Design – Use method of Wang (1991) Assess impact of: a) Axial deformation along tunnel b) Curvature deformation along tunnel c) Ovaling of tunnel profile Normally, no special joints are required, more reinforcement may be needed.
30. Segmental Lining Design – Calculation of Internal Forces Reinforcement Design Design of reinforcing quantity and layout needs to accommodate: a) Design loading; b) Distribution to limit crack widths and cover for durability; c) Limit damage (accidental or under loading) around bolt pockets, lifting socket, segment corners, etc).
33. Bolt Design Design principles: Bolts are intended to: a) Aid ring build quality b) Compress gaskets c) Provide safety prior to annulus grout hardening Bolts can be curved or straight (steel or plastics). Bolts and washer assemblies do not need waterproofing
34. Segment Manufacture Documentation required: a) Segment design drawings; b) Segment mould shop drawings; c) Specification on casting, concrete mix, steel fixing, etc. d) Tolerances for mould, steel fixing, etc.
35. Waterproofing Design Main waterproofing elements: a) Gaskets on all joints with hydrophilic inserts in gaskets b) Use of hydrophilic strips c) Provision of caulking groove Soil side Drive direction
37. TBM Introduction Type of TBM ( (According AFTES Association) Ground support Main TBM Types None Beam TBM Road Header With Shied Support only Open Shield Machine With Shield and Front support Earth pressure balance Machine Slurry Machine Compressed air shield
38. TBM with no shield and frontal support Main Beam and Reamer Beam Machine Road Header
39. TBM with open shield Double Shield TBM Single Shield TBM
40. Closed Shield TBM – Slurry Machine Confinement is achieved by pressurizing boring fluid inside the cutterhead chamber
41.
42.
43. Closed Shield TBM – EPBM Shield Tail skin Mucking and support functions trailing Ring building and annulus grouting Propulsion / steerage Excavation Active pre-cast concrete tunnel lining support
44.
45. TBM OPERATION – Erecting for launch Launching shaft prepared Lower part of shield, bulkhead and drive rams Installing main drive
46. TBM OPERATION – Erecting for launch Upper shield and drive rams Lower part of tail-skin Ring erector installed Cutter-head installed
47. TBM OPERATION – Erecting Al Bugeisha for launch Completed shield and tail-skin Prepared launching eye with seals
48. TBM OPERATION – Segmental tunnel lining Stack of 3 test rings Ring placed in TBM tail skin Ground is not exposed Segment casting Soil Annulus grout Key block
49. PORE WATER PRESSURE IN SCREW Soil conditioning improves hydraulic gradient in screw TBM OPERATION – Application of EPB face pressure h o h 1 Ratio of h 1 /h o is linearly proportional to achievable effective face pressure h 2 Second screw is a risk mitigation measure Soil conditioning = higher effective face pressure
50.
51.
52.
53. TBM Selection – Face stability Yoshikowa et al (1980) Requires measures to maintain slurry pressure Slurry TBM requires heavy de-siltation facilities Slurry requires secondary separation treatment High risk of blockages particularly when N>15 APPLICABILITY OF SLURRY TBM FOR COMPARISON
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
NOTES: This slide illustrates the main portions of the EPB TBM and activities that are undertaken. Key feature is ring building within the protection of the tail-skin.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
NOTES: No added comment
NOTES: No added comment
NOTES: This slide illustrates the launching seal that pressures onto the shield skin, permitting early pressurising of the cutterhead with grout/backfill or other materials.
NOTES: This slide illustrates how the permanent, one-pass placement, segmental lining is placed within the protection of the tail-skin and continuous annulus grouting maintains bedding of the ring and limits ground movements.
NOTES: This slide illustrates the mechanism of the screw in applying face pressure and the importance of pore water pressure control.
NOTES: This slide illustrates steering mechanisms and survey control measures to limit risk of mis-alignment.
NOTES: This slide illustrates the importance of monitoring actual spoil quantity compared to assumed quantities to limit risk of over-excavation and subsequent settlement/subsidence risk.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.
The first part of the presentation will describe the Earth Pressure Balance TBM used for excavating the Tsing Tsuen Tunnels. Initially I will give a brief introduction to the West Rail Project which will serve as an introduction for both parts of my presentation. I’m aware many of you will be very familiar with this project so I will try to keep this brief. Then I will focus on the Tsing Tsuen Tunnels and will describe the: Site conditions; TBM used; Segmental Linings Installed; TBM Performance; Tunnelling Challenges Tunnellling Success I will close this first presentation by drawing some conclusions.