SlideShare a Scribd company logo
CONTENTSCONTENTS 11 PROJECT LOCATIONPROJECT LOCATIONCONTENTSCONTENTS 11 PROJECT LOCATIONPROJECT LOCATION
22 EXISTING CONDITIONEXISTING CONDITION
33 CONSTRUCTION EXECUTION PLANCONSTRUCTION EXECUTION PLAN
44 SAFETY PROTECTIONSAFETY PROTECTION
55 HSE MANAGEMENT PLANHSE MANAGEMENT PLAN55 HSE MANAGEMENT PLANHSE MANAGEMENT PLAN
PROJECT LOCATION
CONSTRUCTION EXECUTION PLAN
Legend :
1. Puri Casablanca
2. Park Lane Hotel
3. Wisma Staco
Jl. Dr. Saharjo
KOTA
KASABLANKA 3
65
1
3
4
2
3. Wisma Staco
4. Kota Kasablanka 1 & 2
5. Apartment Casablanca
6. Casablanca Mansion
Jl. KH. Abdullah
Syafei
Jl. Casablanca Raya
Jl. Prof. Dr. Soepomo
3
2MEGA KUNINGAN
DETAIL PROJECT LOCATION
CONSTRUCTION EXECUTION PLAN
4
2B
C
PROJECT NAME:
KOTA KASABLANKA 3
CLIENT : PT ELITE PRIMA HUTAMA
PROJECT LOCATION:
PROJECT LOCATION
1
3
2
A
B
C
PROJECT LOCATION:
JL. KASABLANKA KAV. 88 MENTENG DALAM,
TEBET, JAKARTA SELATAN
STORIES :
5 BASEMENT
2 PODIUM
3 TOWER ( 2 TOWER APARTMENT, 42 FLOORS
1 TOWER OFFICE, 41 FLOORS)
SITE AREA : ± 27.011 m²
GROSS FLOOR AREA : ± 336,596 m²
Legend :
A. TOWER 1 (APARTMENT)
B. TOWER 3 (APARTMENT)B. TOWER 3 (APARTMENT)
C. TOWER 2 (OFFICE)
1. SITE OFFICE MAINCONT & SUBCONT
2. STOCK YARD
3. BATCHING PLAN
4. LABOUR BARRACK
EXISTING CONDITION
CONSTRUCTION EXECUTION PLAN
27 MARCH 2015
A
B C
D D
A B C
D
A B C
EXISTING CONDITION
CONSTRUCTION EXECUTION PLAN
27 MARCH 2015
A D
DA
A B
B
C
D
C
D
A B C
EXISTING CONDITION
CONSTRUCTION EXECUTION PLAN
27 MARCH 2015
AB
C
D
D
A B C
D
A B C
EXISTING CONDITION
CONSTRUCTION EXECUTION PLAN
27 MARCH 2015
A
B
D
D
A
A B
C
C
D
A B C
03 CONSTRUCTION EXECUTION PLAN
I Site Organization Chart
II Site Plan
III Heavy Equipment PlanIII Heavy Equipment Plan
Construction Method
1. Milestone Schedule
2. Zoning Plan
3. Structural Work Method
4. QA / QC Plan
SITE ORGANIZATION
I
Project Manager
LOTTE
Administration Mgr
LOTTE LOTTE
MEP Senior
ManagerKOR
Construct.
CoordinatorLOTTE
Engineering
Manager
Senior. Const.
Manager1
Chief
SupervisorKOR
Quantity Surveyor Scheduler Drafer
Cost Controller
1
5
2
BBS
Typist / Secretary
Supervisor (Con'c)
4 4
Tower 3 Manager
1
Tower 1 Manager Tower 2 Manager
Typist /
Secretary
Chief Drafter
8
Senior OS
1 1 1
5 1 4 2
Basement Manager
1
Supervisor (Rebar)
2
Safety Officer QA/QC Manager
1 1
Supervisor
2 2 1 1
Supervisor (Con'c) Supervisor (Con'c) Supervisor (Con'c)
Typist /
Secretary
1
Material Asist.Supervisor (Form)Supervisor (Form)
2
Supervisor (Form)
2
Supervisor (Form)
1
22
1
Mech Supervisor Elect Supervisor General Affairs
1
2 2 1
Mech Engineer Elect Engineer Accountant
Typist / Secretary
Elect Manager Security Manager
1 LOTTE KOR 1 1 1
QS Manager Contract Manager Design Manager Mech Manager
2
Supervisor
Supervisor (Rebar) Supervisor (Rebar) Supervisor (Rebar)
1 1 1
2
Surveyor
4
1 1 11
Arch. Chief
Supervisor
Arch. Chief
Supervisor
Arch. Chief
Supervisor
Arch. Chief
Supervisor
Supervisor (Arch.)
12
Typist /
Secretary1
4 4
Supervisor (Arch.)
3
Supervisor (Arch.) Supervisor (Arch.)
sub-total 5 3 112 120
Total 8 112 120
품질 QA/QC 7 7
안전 Safety 9 9
기전 MEP 1 15 16
관리 ADM. 1 5 6
공무 ENG. 2 1 17 20
공사 CON. 1 1 59 61
Description
Korean Local
합계
LOTTE JO Totalindo & JO
소장 PM 1 1
SITE PLAN
CONSTRUCTION EXECUTION PLAN
Access road
REBAR FABRICATION
AND
REBAR STOCK PROTECTION ROAD WAY
Conc’
pump
SUBCO
NT SIT
E OFFIC
E
(300m2
EXISTING
BUILDING
BATCHING
PLANT
CONTRACTOR
SITE OFFICE
STOCK
AREA
CANTEEN
600 m2
LABOUR CAMP 1
1500 m2
BT.SLAB B5
Elv.-3.3m
BOTTOM RAFT
Elv.-5.9
Elv.-5.9
Elv.-5.9
REBAR FABRICATION
AND
REBAR STOCK
Elv.-3.3
Elv.-3.3
Conc’
pump
Conc’
pump
Conc’
pump
Existing
(300m2
)
BUILDING
SITE OFFICE
TEMPORARY FENCE
BASEMENT LINE
TEMPORARY ACCESS ROAD
LABOUR CAMP
CONTRACTOR SITE OFFICE
STOCK AREA
CONCRETE BATCHING PLANT
CANTEEN
SITE PLAN
CONSTRUCTION EXECUTION PLAN
Access road
F/W FABRICATION
REBAR FABRICATION
PROTECTION ROAD WAY
Conc’
pump
SUBCO
NT SIT
E OFFIC
E
(300m2EXISTING
BATCHING
PLANT
CONTRACTOR
SITE OFFICE
STOCK
AREA
CANTEEN
600 m2
LABOUR CAMP 1
1500 m2
GF
GF
TYP. FLOOR
TYP. FLOOR
TYP. FLOOR
B4
B4
GF
Conc’
pump
Conc’
pump
Existing
(300m2
)
EXISTING
BUILDING
SITE OFFICE
TEMPORARY FENCE
BASEMENT LINE
TEMPORARY ACCESS ROAD
LABOUR CAMP
CONTRACTOR SITE OFFICE
STOCK AREA
CONCRETE BATCHING PLANT
CANTEEN
REBAR FABRICATION
REBAR
FABRICATION
AND
REBAR STOCK
CONSTRUCTION EXECUTION PLAN
III
TC #3
R =50M
TC #5
R =50M
Expected Max. Lifting Weight
DESCRIPTION Lifting Item Weight
FORM-WORK
Wall 2.0 Ton
Column 1.5 Ton
TC #1
R =45M
TC #2
R =50M
TC #4
R =50M
R =50M
TC #6
R =50M
TOWER CRANE SPECIFICATION
TC NAME T/C #1 T/C #2~6
TYPE HAMMER HEAD, STATIC HAMMER HEAD, STATIC
(TIP LOAD) 45M – 3.5 Ton 50M – 3.15 Ton
PERIODE 25 MONTH 26 MONTH
Column 1.5 Ton
REBAR
Bundle Rebar 2.0 Ton
Prefab Rebar 2.5 Ton
FACAD
Panel 1 1.8 Ton
Panel 2 1.5 Ton
PC Panel 2 Ton
CONC’ CPB 5.0 Ton
ELECTRICAL &
MACHINERY
Elec. Panel 2.0 Ton
ELEV 2.5 Ton
CONSTRUCTION EXECUTION PLAN
III
30m
30m
30m
30m
160m
200m
30m
30m
30m
III
CONSTRUCTION EXECUTION PLAN
MH#3
MH#4 MH#5
MH#6
TOWER 3
TC3
TC5
MH#1
Note :
MH = Material Hoist
TOWER 1
MH#2
MH#3
MH#7
TOWER 2
TC1
TC2 TC4
TC6
MH#1
Description Specification Remark
Equipment Type Twin Medium Type
Equipment Name ALIMAK SC 65/32
Cage Size 1.5W*3.2L*2.5H
Load Capacity 2 TON
Speed 60 M/MIN
III
CONSTRUCTION EXECUTION PLAN
8M
CPB#3
CPB maximum distance from unapplied area
: Approximately 8M
CPB#2
CPB#3
CPB#4
Concrete Placing Boom Specification
CPB Name CPB #1~4
Type Potential HG 28 H
Radius ± 28 Meter
High ± 22.9 Meter
CPB#1
Note :
CPB = Concrete Placing Boom
CONSTRUCTION METHOD
1
CONSTRUCTION METHOD
2
Footprint tower is
the priority area
Basement Line
Note:
ZONNING SUBSTRUCTUREZONNING SUBSTRUCTURE
Zone 1
8,115m2
Zone 3
5,742m2
Tower 1
Tower 3
Tower 2
Zone 2
3,758m2
Footprint tower is
the priority area
Note:
♦ Zoning area of sub-structure
work is divided into 3 zones:
Zone 1 : Area Tower 1, 8115 m²
Zone 2 : Area Tower 3, 3758 m²
Zone 3 : Area Tower 2, 5742 m²
Footprint tower is
the priority area
the priority area
2
CONSTRUCTION METHOD
Note:
♦ Zoning area of super-
structure work is divided
into several zones
Area Tower 1 : 2100 m²
Zone 1, 325 m²Zone 1, 325 m²
Zone 2, 256 m²
Zone 3, 469 m²
Zone 1’, 325 m²
Zone 2’, 256 m²
Zone 3’, 469 m²
Area Tower 2 : 2294 m²
Zone 1, 453 m²
Zone 2, 465 m²
Zone 3, 448 m²
Zone 4, 421 m²
3’3’ 2’2’ 1’1’
11 22 4433
11 22
44 33
55
ZONNING SUPER STRUCTUREZONNING SUPER STRUCTURE
TOWER 3TOWER 3TOWER 3TOWER 3
TOWER 2TOWER 2TOWER 2TOWER 2
Zone 4, 421 m²
Zone 5, 505 m²
Area Tower 3 : 1337 m²
Zone 1, 322 m²
Zone 2, 353 m²
Zone 3, 340 m²
Zone 4, 322 m²
33 22 11
TOWER 1TOWER 1TOWER 1TOWER 1
3
CONSTRUCTION METHOD
Access road ZONE ACTIVITIES
TOWER 1
- Detail Excavation for raft,
cutting bore pile,
Conc’ Foundation TC1
Existing
SUBCO
NT SIT
E OFFI
CE
(300m2
)
EXISTING
BUILDING
Conc’ Foundation TC1
TOWER 3 - Bulk Excavation (by Owner)
TOWER 2 - Bulk Excavation (by Owner)TC1
Tower 1 Tower 3 Tower 2
3
CONSTRUCTION METHOD
Access road ZONE ACTIVITIES
TOWER 1
- Excavation for raft, cutting bore pile,
Install TC1 & TC2, Conc’ Lift Pit, Install
rebar for raft foundation
Existing
SUBCO
NT SIT
E OFFI
CE
(300m2
)
EXISTING
BUILDING
rebar for raft foundation
TOWER 3 - Bulk Excavation (by Owner)
TOWER 2 - Bulk Excavation (by Owner)TC1
TC2
LIFT
PIT
LIFT
PIT
Tower 1 Tower 3 Tower 2
LIFT
PIT
3
CONSTRUCTION METHOD
Access road ZONE ACTIVITIES
TOWER 1
- Excavation for raft foundation
completed, Install rebar for raft
foundation continued
Existing
SUBCO
NT SIT
E OFFI
CE
(300m2
)
EXISTING
BUILDING
foundation continued
TOWER 3 - Excavation (by Owner)
TOWER 2 - BExcavation (by Owner)TC1
TC2
TC1
Tower 1 Tower 3 Tower 2
RAFT
FOUNDATION
3
CONSTRUCTION METHOD
Access road ZONE ACTIVITIES
TOWER 1
- Raft Foundation completed,
B5 columns in progress,
GWT in progress
Existing
SUBCO
NT SIT
E OFFI
CE
(300m2
)
EXISTING
BUILDING
Podium
Outer Tower 1
- Excavation and cutting bored pile,
B5 slab in progress
Podium
Tower 1 –2
- Excavation and cutting bored pile,
B5 slab in progress
TOWER 3 - Start Excavation for raft foundation
TOWER 2 - Bulk Excavation (by Owner)
TC1
TC2
B5
Tower 1 Tower 3 Tower 2
3
CONSTRUCTION METHOD
Access road ZONE ACTIVITIES
TOWER 1
- B4 slab in progress, GWT in B5
completed, B4 column in progressB5
TC3
Existing
SUBCO
NT SIT
E OFFI
CE
(300m2
)
EXISTING
BUILDING
Podium
Outer Tower 1
- B5 slab completed
Podium
Tower 1 –2
- B5 slab completed
TOWER 3
- Excavation for raft and cutting bored
pile, install TC 3 & TC 4,
Install rebar for lift pit and raft
foundation
TOWER 2 - Bulk Excavation (by Owner)
B5 TC1
TC2
B5
B4
TC4
Tower 1 Tower 3 Tower 2
B4 RAFT
FOUNDATION
3
CONSTRUCTION METHOD
Access road ZONE ACTIVITIES
TOWER 1
- B4 slab completed,
B3 slab & column in progress,B5
TC3
TC5
Existing
SUBCO
NT SIT
E OFFI
CE
(300m2
)
EXISTING
BUILDING
TOWER 3
- Lift pit completed,
Install rebar for raft foundation
TOWER 2
- Excavation for raft & cutting bored
pile, install TC 5 and TC 6B5 TC1
TC2
B5
B3
TC4
B4 TC6
Tower 1 Tower 3 Tower 2
RAFT
FOUNDATION
B3
3
CONSTRUCTION METHOD
Access road ZONE ACTIVITIES
TOWER 1
- B3 slab completed,
B2 slab & column in progress,B5
TC3
B5 STP
TC5
Existing
SUBCO
NT SIT
E OFFI
CE
(300m2
)
EXISTING
BUILDING
TOWER 3
- Raft foundation completed,
STP in progress, B5 column in progress,
Podium
Outer Tower 3
- Excavation for pile cap & cutting bored
pile, B5 Slab in progress
TOWER 2
- Conc’ lift pit, install rebar for raft
foundation in progress.
B5 TC1
TC2
B5
B2
TC4
B3 TC6
B2
B5
Tower 1 Tower 3 Tower 2
B2
RAFT
FOUNDATION
B5B5
3
CONSTRUCTION METHOD
Access road ZONE ACTIVITIES
TOWER 1
- B1 slab completed,
GF slab in progress,B5
TC5
B5
B4
TC3 B5
Existing
SUBCO
NT SIT
E OFFI
CE
(300m2
)
EXISTING
BUILDING
Podium
Outer Tower 1
- B4 and B3 slab in progress
TOWER 3 - B4 slab completed,
Podium
Outer Tower 3
- B5 slab completed
TOWER 2 - Raft foundation completed
B4 TC1
TC2
B3
B2
B1 TC6
GF
B5
B4
RAFT
FOUNDATION
TC4B5
Tower 1 Tower 3 Tower 2
GF
B4
B1
B4
B5
RAFT
FOUNDATION
3
CONSTRUCTION METHOD
Access road
B5
TC3 B5
B5
B4
L2GF
TC5
B4B5
ZONE ACTIVITIES
TOWER 1
- Level 9 slab completed,
Level 10 & 11 slab in progress,
Existing
SUBCO
NT SIT
E OFFI
CE
(300m2
)
EXISTING
BUILDING
GF TC1
GF
GF
TC2
B5
L11
L9
L10
L2
B4
GF
TC6
B4
TC4
B3
B5
B5
B5
Podium
Outer Tower 1
- GF slab completed
Podium
Tower 1 -3
- B4 slab in progress,
TOWER 3
- GF slab completed,
Level 2 slab in progress
Podium
Outer Tower 3
- B4 slab in progress
TOWER 2
- B4 slab completed,
B3 slab in progress
Podium
Tower 1
Tower 3 Tower 2
GF
Level 2
Podium
Outer Tower 3
- B5 slab complete
B3
Level 11
Level 10
B5 B5
3
CONSTRUCTION METHOD
ZONE ACTIVITIES
TOWER 1
- Roof slab completed,
Lift Motor Room Completed,
TC3
TC2
L2
TC5
TC4
GF GF
GFL26
Access road
L25
L39
L38
L37
TOWER 3
- Level 37 slab completed,
Level 38 & 39 slab in progress
TOWER 2
- Level 25 slab completed,
Level 26 & 27 slab in progress
Podium All - GF slab complete
Tower 1
Tower 3 Tower 2
ROOF
Existing
SUB
CON
T SI
TE O
FFIC
E
(300
m2)
EXISTING
BUILDING
GF TC1
GF
TC6
TC4
L27
LMRLMR
Level 39
Level 38
ROOF
ROOF
GF
Level 37
Level 38
Level 27
Level 26
GF GF
3
CONSTRUCTION METHOD
ZONE ACTIVITIES
TOWER 1 - Finishing work in progress
TC3
TC2
L2
TC5
GF
GFL37
Access road
L36
ROOF
TC4
L2
L2
TOWER 3
- Roof slab completed,
Lift Motor Room Completed
TOWER 2
- Level 36 slab completed,
Level 37& 38 slab in progress
Podium - L2 slab completed
Tower 1 Tower 3 Tower 2
ROOF
Existing
SUB
CON
T SI
TE O
FFIC
E
(300
m2)
EXISTING
BUILDING
GF
GF
TC6
L38
LMRLMR
Level 38Level 37
ROOF
ROOF
TC1
TC4L2
L2
ROOF
LMRLMR
L2 L2
GF
FINISHING
WORK
3
CONSTRUCTION METHOD
ZONE ACTIVITIES
TOWER 1 - Finishing work in progress
TC3
L2
TC6
TC5
GF
GF
Access road
ROOF
ROOF
TC4
L3
L3 ROOF
TOWER 3 - Finishing work in progress
TOWER 2
- Roof slab completed,
Lift Motor Room Completed
Podium - L3 slab completed
Tower 1 Tower 3
ROOF
LMRLMR
ROOF
ROOF
LMRLMR
Existing
SUB
CON
T SI
TE O
FFIC
E
(300
m2)
EXISTING
BUILDING
GF
GF
TC6
ROOF
ROOF
L3
LMR LMR
Tower 2
L3 L3
GF
FINISHING
WORK
FINISHING
WORK
CONSTRUCTION METHOD
3
Thermocouple
posisition
Thermocouple Plan
Existing
SUBCO
NT SIT
E OFFI
CE
(300m2
)
EXISTING
BUILDING
Bottom Slab B5
Elv.-3.3m
Detail of thermocouple installation
Note:
• Concrete volume±7500m³
• Supportive equipments :
• Conc. Pump : 7unit (1 stand-by)
• Vibrator : 25 unit (5 stand-by)
• Tent for protecting area that should be poured concrete
• Thermocouple for thermal monitoring
• After all preparation completed, pouring concrete use concrete pump ± 25m³/hr capacity.
Casting raft foundation can be completed within ± 60 hours
Thermal monitoring
3
Excavation for raft foundation Cuti bored pile Spray anti termite (optional if necessary)
CONSTRUCTION METHOD
Lean concreteFormworkRebar work
Bottom layer Support rebar
Upper layerStarter rebar
3
ME installation Thermocouple installation Starter bar inspection
CONSTRUCTION METHOD
Cold-joint installationProtective Tent installation
3
Concrete finishingConcrete
acceptance scheme
Casting Process
CONSTRUCTION METHOD
Concrete truck
access
Area for concrete
truck
Concrete curing
Always provide 1
unit Concrete pump
stand-by
Concrete sample
Styrofoam installation
3
CONSTRUCTION METHOD
1 2 3
4 5
3
CONSTRUCTION METHOD
6 87
9 10
3
CONSTRUCTION METHOD
ZONE 1’
9 TABLES
ZONE 1
9 TABLES
Slab conc’:
Zone 1 = ± 110.5 m³
Zone 2 = ± 84.5 m³
Zone 3 = ± 155 m³
ZONE 2’
7 TABLES
ZONE 2
7 TABLES
Zone 3 = ± 155 m³
Zone 1’ = ± 110.5 m³
Zone 2’= ± 84.5 m³
Zone 3’= ± 155 m³
ZONE 3’
12 TABLES
ZONE 3
12 TABLES
CONVENSIONAL CONVENSIONAL
3
CONSTRUCTION METHOD
Typical Elevation Table Tower 1
Typical Section Table Tower 1
3
CONSTRUCTION METHOD
ZONE 1
9 TABLES
ZONE 2
7 TABLES
ZONE 4
9 TABLES
ZONE 3
7 TABLES
Slab conc’:
Zone 1 = ± 106 m³
Zone 2 = ± 117 m³
Zone 3 = ± 112 m³
Zone 4 = ± 106 m³
3
CONSTRUCTION METHOD
Typical Elevation Table Tower 3
Typical Section Table Tower 3
3
CONSTRUCTION METHOD
Slab conc’:
Zone 1 = ± 150 m³
Zone 2 = ± 153.5 m³
Zone 3 = ± 147.8 m³
Zone 4 = ± 138.93 m³Zone 4 = ± 138.93 m³
ZONE 2
7 TABLES
ZONE 1
7 TABLES
CONVENSIONAL
ZONE 3
7 TABLES
ZONE 4
8 TABLES
3
CONSTRUCTION METHOD
Typical Elevation Table Tower 2
Typical Section Table Tower 2
3
CONSTRUCTION METHOD
1st Set 2nd Set 3rd Set 1st Set
3
Note:
Concrete mold for column and shearwall are using
Aluma Beam, Steel waler and plywood 18mm double film
CONSTRUCTION METHOD
Typical Shear wall
Shear wall type
SW40A & SW35A
03
Note:
CONSTRUCTION METHOD
Note:
This the illustrations when the Table
Form Flying next to the upper floors,
very easy and fast
03
CONSTRUCTION METHOD
Note:
Aluma Table Form is often calledAluma Table Form is often called
Flying Table because when the table
stripped out to next floor is lifted by
tower crane, making it very fast
for the cycle time floor to the next floor
QA / QC PLAN
4
Shop Drawing &Shop Drawing &
Material SubmissionMaterial Submission
Method of Construction (Trade)Method of Construction (Trade)
Method Briefing &Method Briefing &
Training to WorkersTraining to Workers
Method Briefing &Method Briefing &
Training to WorkersTraining to Workers
Trade DemonstrationTrade Demonstration
(Mock Up)(Mock Up)
Trade DemonstrationTrade Demonstration
(Mock Up)(Mock Up) DefineDefine Holding PointHolding Point
Inspection & Test PlanInspection & Test Plan
Step by Step InspectionStep by Step Inspection
Execution of WorkExecution of Work
Quality WorkQuality Work
SetSet--upup Quality StandardQuality Standard
Consultant + Main-con + Subcon
04 SAFETY PROTECTION
01 Building Protection
Building Protection
01
SAFETY
DECK
SAFETY
DECK
SAFETY DECK
SAFETY
VOID
SAFETY DECK
PERMANENT
Building Protection
01
SAFETY
NET
SAFETY
NET
SAFETY
NET
Building Protection
01
Safety Rail
Building Protection
01
COUPLER
TIANG RAILINGHANDRAIL
INSTALLATION
MID HANDRAIL
BESI BEHEL D12
BASEPLATE
POLYNET
TIANG RAILING
POLYNET
safety wing net/
Safety deck
safety wing net/
Safety deck
CORNER
BESI BEHEL D12
Perimeter Safety Net / Safety Railing
Building Protection
01
Building Protection
01
HANDRAIL
MID HANDRAIL
OPENING 100 ~ 600 mm
OPENING > 2 M / VOID AREA
KAWAT AYAM + SAFETY NET
BESI BEHEL D12
OPENING 650~ 2000 mm
Building Protection
01
SAFETY NET DI LIFT SAFETY VOID
05 HSE MANAGEMENT
PLAN
01 Certificate
02 Safety Plan
EHS MANAGEMENT PLAN
01
EHS MANAGEMENT PLAN
02
EHS MANAGEMENT PLAN
02
EHS MANAGEMENT PLAN
02
Thank youThank you

More Related Content

What's hot

Construction Of Multistoreyed Building
Construction Of Multistoreyed BuildingConstruction Of Multistoreyed Building
Construction Of Multistoreyed Building
Sahla Fathima
 
Building Construction II Report
Building Construction II ReportBuilding Construction II Report
Building Construction II Report
Bolin Loong
 
Industrial training report of construction of the residential building
Industrial training report of construction of the residential buildingIndustrial training report of construction of the residential building
Industrial training report of construction of the residential building
suraj jha
 
presentation on petronas twin tower
 presentation on petronas twin tower presentation on petronas twin tower
presentation on petronas twin tower
Kaish Pasha
 
Summer training report
Summer training reportSummer training report
Summer training report
Raj Vaibhav Singh
 
Petronas twin towers malaysia
Petronas twin towers malaysiaPetronas twin towers malaysia
Petronas twin towers malaysia
humayoun shah
 
Skyscrapers- Petronas Towers
Skyscrapers- Petronas TowersSkyscrapers- Petronas Towers
Skyscrapers- Petronas Towers
Ranju Ravindran
 
The petronas twin towers
The petronas twin towersThe petronas twin towers
The petronas twin towers
aman shukla
 
Internship report
Internship reportInternship report
Internship report
Abdullah Jawaid
 
Major Project ppt
Major Project ppt Major Project ppt
Major Project ppt
Narayan Gupta
 
petronas twin tower
petronas twin towerpetronas twin tower
petronas twin tower
Hãrsh Båçhhäv HB
 
Burj khalifa
Burj khalifaBurj khalifa
Selecting one single type of building and covering
Selecting one single type of building and coveringSelecting one single type of building and covering
Selecting one single type of building and covering
HREAT
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
David H Moloney
 
Petronas tower - Malaysia (Theory of Structures)
Petronas tower - Malaysia  (Theory of Structures)Petronas tower - Malaysia  (Theory of Structures)
Petronas tower - Malaysia (Theory of Structures)
RADHIKASARDA8
 
Building Construction 1 : Experience construction; a building construction re...
Building Construction 1 : Experience construction; a building construction re...Building Construction 1 : Experience construction; a building construction re...
Building Construction 1 : Experience construction; a building construction re...
aarenneoone
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
Constructionmethodologyandprojectmanagementreport
Divyesh Mungara
 
Petronas tower
Petronas towerPetronas tower
Petronas tower
Mohammad Alamin
 
Petronas twin towers, taipei 101, burj al-arab
Petronas twin towers, taipei 101, burj al-arabPetronas twin towers, taipei 101, burj al-arab
Petronas twin towers, taipei 101, burj al-arab
Rajat Nainwal
 
Site visit report
Site visit reportSite visit report
Site visit report
Doreen Yeo
 

What's hot (20)

Construction Of Multistoreyed Building
Construction Of Multistoreyed BuildingConstruction Of Multistoreyed Building
Construction Of Multistoreyed Building
 
Building Construction II Report
Building Construction II ReportBuilding Construction II Report
Building Construction II Report
 
Industrial training report of construction of the residential building
Industrial training report of construction of the residential buildingIndustrial training report of construction of the residential building
Industrial training report of construction of the residential building
 
presentation on petronas twin tower
 presentation on petronas twin tower presentation on petronas twin tower
presentation on petronas twin tower
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Petronas twin towers malaysia
Petronas twin towers malaysiaPetronas twin towers malaysia
Petronas twin towers malaysia
 
Skyscrapers- Petronas Towers
Skyscrapers- Petronas TowersSkyscrapers- Petronas Towers
Skyscrapers- Petronas Towers
 
The petronas twin towers
The petronas twin towersThe petronas twin towers
The petronas twin towers
 
Internship report
Internship reportInternship report
Internship report
 
Major Project ppt
Major Project ppt Major Project ppt
Major Project ppt
 
petronas twin tower
petronas twin towerpetronas twin tower
petronas twin tower
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
Selecting one single type of building and covering
Selecting one single type of building and coveringSelecting one single type of building and covering
Selecting one single type of building and covering
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
 
Petronas tower - Malaysia (Theory of Structures)
Petronas tower - Malaysia  (Theory of Structures)Petronas tower - Malaysia  (Theory of Structures)
Petronas tower - Malaysia (Theory of Structures)
 
Building Construction 1 : Experience construction; a building construction re...
Building Construction 1 : Experience construction; a building construction re...Building Construction 1 : Experience construction; a building construction re...
Building Construction 1 : Experience construction; a building construction re...
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
Constructionmethodologyandprojectmanagementreport
 
Petronas tower
Petronas towerPetronas tower
Petronas tower
 
Petronas twin towers, taipei 101, burj al-arab
Petronas twin towers, taipei 101, burj al-arabPetronas twin towers, taipei 101, burj al-arab
Petronas twin towers, taipei 101, burj al-arab
 
Site visit report
Site visit reportSite visit report
Site visit report
 

Viewers also liked

high rise building (BURJ KHALIFA)
high rise building (BURJ KHALIFA)high rise building (BURJ KHALIFA)
high rise building (BURJ KHALIFA)
suraj kumar
 
Heat of Hydration in Mass Concrete
Heat of Hydration in Mass ConcreteHeat of Hydration in Mass Concrete
Heat of Hydration in Mass Concrete
Khaldoon Slaiai
 
Petronas Twin Towers
Petronas Twin TowersPetronas Twin Towers
Petronas Twin Towers
matsrock
 
Construction Project Management.
Construction Project Management.Construction Project Management.
Construction Project Management.
Yousef Abujubba
 
Foundation Deisgn of Burj Khalifa
Foundation Deisgn of Burj KhalifaFoundation Deisgn of Burj Khalifa
Foundation Deisgn of Burj Khalifa
astoria104
 
Top down construction
Top down constructionTop down construction
Top down construction
Amulya Kansal
 
Design, Structure, Construction and Analysis of Burj Al Arab, Dubai
Design, Structure, Construction and Analysis of Burj Al Arab, DubaiDesign, Structure, Construction and Analysis of Burj Al Arab, Dubai
Design, Structure, Construction and Analysis of Burj Al Arab, Dubai
Ar. Md Shahroz Alam
 
Burj khalifa-mode of construction
Burj khalifa-mode of constructionBurj khalifa-mode of construction
Burj khalifa-mode of construction
Joji Mathew
 
Petronas twin tower
Petronas twin towerPetronas twin tower
Petronas twin tower
Somya Gupta
 
High rise structure
High rise structureHigh rise structure
High rise structure
Anuj Singhal
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
Safa Aboelssaad
 
klcc
klccklcc

Viewers also liked (12)

high rise building (BURJ KHALIFA)
high rise building (BURJ KHALIFA)high rise building (BURJ KHALIFA)
high rise building (BURJ KHALIFA)
 
Heat of Hydration in Mass Concrete
Heat of Hydration in Mass ConcreteHeat of Hydration in Mass Concrete
Heat of Hydration in Mass Concrete
 
Petronas Twin Towers
Petronas Twin TowersPetronas Twin Towers
Petronas Twin Towers
 
Construction Project Management.
Construction Project Management.Construction Project Management.
Construction Project Management.
 
Foundation Deisgn of Burj Khalifa
Foundation Deisgn of Burj KhalifaFoundation Deisgn of Burj Khalifa
Foundation Deisgn of Burj Khalifa
 
Top down construction
Top down constructionTop down construction
Top down construction
 
Design, Structure, Construction and Analysis of Burj Al Arab, Dubai
Design, Structure, Construction and Analysis of Burj Al Arab, DubaiDesign, Structure, Construction and Analysis of Burj Al Arab, Dubai
Design, Structure, Construction and Analysis of Burj Al Arab, Dubai
 
Burj khalifa-mode of construction
Burj khalifa-mode of constructionBurj khalifa-mode of construction
Burj khalifa-mode of construction
 
Petronas twin tower
Petronas twin towerPetronas twin tower
Petronas twin tower
 
High rise structure
High rise structureHigh rise structure
High rise structure
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
klcc
klccklcc
klcc
 

Similar to Method Statement Kota Kasablanka 3

Report
ReportReport
Benjamin colbrandt | C-Power offshore windmolenpark
Benjamin colbrandt  | C-Power offshore windmolenparkBenjamin colbrandt  | C-Power offshore windmolenpark
Benjamin colbrandt | C-Power offshore windmolenpark
Greenbridge nv
 
Prima Vera Final Project PPT.pptx
Prima Vera Final Project PPT.pptxPrima Vera Final Project PPT.pptx
Prima Vera Final Project PPT.pptx
Ziyad Zaidi
 
Presentation - 1240 Villas
Presentation - 1240 VillasPresentation - 1240 Villas
Presentation - 1240 Villas
Issam M. Faqir
 
Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)
Hamza Waheed
 
ICI FINAL REPORT PDF
ICI FINAL REPORT PDFICI FINAL REPORT PDF
ICI FINAL REPORT PDF
Clement Seong
 
Aurora heights first homes final
Aurora heights first homes finalAurora heights first homes final
Aurora heights first homes final
Reggie Refugio
 
Aurora heights first homes final
Aurora heights first homes finalAurora heights first homes final
Aurora heights first homes final
Reggie Refugio
 
Building Structure Project 2
Building Structure Project 2Building Structure Project 2
Building Structure Project 2
Gertrude Lee
 
DCES_Classroom_Building_100_CDs.pdf
DCES_Classroom_Building_100_CDs.pdfDCES_Classroom_Building_100_CDs.pdf
DCES_Classroom_Building_100_CDs.pdf
RoshelleStahl1
 
Building Structure - Structural Analysis of a bungalow
Building Structure - Structural Analysis of a bungalowBuilding Structure - Structural Analysis of a bungalow
Building Structure - Structural Analysis of a bungalow
Lovie Tey
 
Mega kuningan office tower for investor
Mega kuningan office tower for investorMega kuningan office tower for investor
Mega kuningan office tower for investor
Aditya Tumbuan
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
kiransuresh7
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
kiransuresh7
 
Analysis and design of building
Analysis and design of buildingAnalysis and design of building
Analysis and design of building
Krishnagnr
 
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
ssuser2ec079
 
Drawing set for building complex - Three building and swimming poll
Drawing set for building complex - Three building and swimming pollDrawing set for building complex - Three building and swimming poll
Drawing set for building complex - Three building and swimming poll
AripSuhariyanto1
 
ROYAL PALM GARDENS - C-5/C-6 near THE GLOBAL, CITY, TAGUIG CITY
ROYAL PALM GARDENS - C-5/C-6 near THE GLOBAL, CITY, TAGUIG CITYROYAL PALM GARDENS - C-5/C-6 near THE GLOBAL, CITY, TAGUIG CITY
ROYAL PALM GARDENS - C-5/C-6 near THE GLOBAL, CITY, TAGUIG CITY
jaylselga
 
Royal Palm Residences
Royal Palm ResidencesRoyal Palm Residences
Royal Palm Residences
roy69710
 
Royal Palm Residences
Royal Palm ResidencesRoyal Palm Residences
Royal Palm Residences
rchrealty
 

Similar to Method Statement Kota Kasablanka 3 (20)

Report
ReportReport
Report
 
Benjamin colbrandt | C-Power offshore windmolenpark
Benjamin colbrandt  | C-Power offshore windmolenparkBenjamin colbrandt  | C-Power offshore windmolenpark
Benjamin colbrandt | C-Power offshore windmolenpark
 
Prima Vera Final Project PPT.pptx
Prima Vera Final Project PPT.pptxPrima Vera Final Project PPT.pptx
Prima Vera Final Project PPT.pptx
 
Presentation - 1240 Villas
Presentation - 1240 VillasPresentation - 1240 Villas
Presentation - 1240 Villas
 
Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)
 
ICI FINAL REPORT PDF
ICI FINAL REPORT PDFICI FINAL REPORT PDF
ICI FINAL REPORT PDF
 
Aurora heights first homes final
Aurora heights first homes finalAurora heights first homes final
Aurora heights first homes final
 
Aurora heights first homes final
Aurora heights first homes finalAurora heights first homes final
Aurora heights first homes final
 
Building Structure Project 2
Building Structure Project 2Building Structure Project 2
Building Structure Project 2
 
DCES_Classroom_Building_100_CDs.pdf
DCES_Classroom_Building_100_CDs.pdfDCES_Classroom_Building_100_CDs.pdf
DCES_Classroom_Building_100_CDs.pdf
 
Building Structure - Structural Analysis of a bungalow
Building Structure - Structural Analysis of a bungalowBuilding Structure - Structural Analysis of a bungalow
Building Structure - Structural Analysis of a bungalow
 
Mega kuningan office tower for investor
Mega kuningan office tower for investorMega kuningan office tower for investor
Mega kuningan office tower for investor
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Analysis and design of building
Analysis and design of buildingAnalysis and design of building
Analysis and design of building
 
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
 
Drawing set for building complex - Three building and swimming poll
Drawing set for building complex - Three building and swimming pollDrawing set for building complex - Three building and swimming poll
Drawing set for building complex - Three building and swimming poll
 
ROYAL PALM GARDENS - C-5/C-6 near THE GLOBAL, CITY, TAGUIG CITY
ROYAL PALM GARDENS - C-5/C-6 near THE GLOBAL, CITY, TAGUIG CITYROYAL PALM GARDENS - C-5/C-6 near THE GLOBAL, CITY, TAGUIG CITY
ROYAL PALM GARDENS - C-5/C-6 near THE GLOBAL, CITY, TAGUIG CITY
 
Royal Palm Residences
Royal Palm ResidencesRoyal Palm Residences
Royal Palm Residences
 
Royal Palm Residences
Royal Palm ResidencesRoyal Palm Residences
Royal Palm Residences
 

Method Statement Kota Kasablanka 3

  • 1.
  • 2. CONTENTSCONTENTS 11 PROJECT LOCATIONPROJECT LOCATIONCONTENTSCONTENTS 11 PROJECT LOCATIONPROJECT LOCATION 22 EXISTING CONDITIONEXISTING CONDITION 33 CONSTRUCTION EXECUTION PLANCONSTRUCTION EXECUTION PLAN 44 SAFETY PROTECTIONSAFETY PROTECTION 55 HSE MANAGEMENT PLANHSE MANAGEMENT PLAN55 HSE MANAGEMENT PLANHSE MANAGEMENT PLAN
  • 3. PROJECT LOCATION CONSTRUCTION EXECUTION PLAN Legend : 1. Puri Casablanca 2. Park Lane Hotel 3. Wisma Staco Jl. Dr. Saharjo KOTA KASABLANKA 3 65 1 3 4 2 3. Wisma Staco 4. Kota Kasablanka 1 & 2 5. Apartment Casablanca 6. Casablanca Mansion Jl. KH. Abdullah Syafei Jl. Casablanca Raya Jl. Prof. Dr. Soepomo 3 2MEGA KUNINGAN
  • 4. DETAIL PROJECT LOCATION CONSTRUCTION EXECUTION PLAN 4 2B C PROJECT NAME: KOTA KASABLANKA 3 CLIENT : PT ELITE PRIMA HUTAMA PROJECT LOCATION: PROJECT LOCATION 1 3 2 A B C PROJECT LOCATION: JL. KASABLANKA KAV. 88 MENTENG DALAM, TEBET, JAKARTA SELATAN STORIES : 5 BASEMENT 2 PODIUM 3 TOWER ( 2 TOWER APARTMENT, 42 FLOORS 1 TOWER OFFICE, 41 FLOORS) SITE AREA : ± 27.011 m² GROSS FLOOR AREA : ± 336,596 m² Legend : A. TOWER 1 (APARTMENT) B. TOWER 3 (APARTMENT)B. TOWER 3 (APARTMENT) C. TOWER 2 (OFFICE) 1. SITE OFFICE MAINCONT & SUBCONT 2. STOCK YARD 3. BATCHING PLAN 4. LABOUR BARRACK
  • 5. EXISTING CONDITION CONSTRUCTION EXECUTION PLAN 27 MARCH 2015 A B C D D A B C D A B C
  • 6. EXISTING CONDITION CONSTRUCTION EXECUTION PLAN 27 MARCH 2015 A D DA A B B C D C D A B C
  • 7. EXISTING CONDITION CONSTRUCTION EXECUTION PLAN 27 MARCH 2015 AB C D D A B C D A B C
  • 8. EXISTING CONDITION CONSTRUCTION EXECUTION PLAN 27 MARCH 2015 A B D D A A B C C D A B C
  • 9. 03 CONSTRUCTION EXECUTION PLAN I Site Organization Chart II Site Plan III Heavy Equipment PlanIII Heavy Equipment Plan Construction Method 1. Milestone Schedule 2. Zoning Plan 3. Structural Work Method 4. QA / QC Plan
  • 10. SITE ORGANIZATION I Project Manager LOTTE Administration Mgr LOTTE LOTTE MEP Senior ManagerKOR Construct. CoordinatorLOTTE Engineering Manager Senior. Const. Manager1 Chief SupervisorKOR Quantity Surveyor Scheduler Drafer Cost Controller 1 5 2 BBS Typist / Secretary Supervisor (Con'c) 4 4 Tower 3 Manager 1 Tower 1 Manager Tower 2 Manager Typist / Secretary Chief Drafter 8 Senior OS 1 1 1 5 1 4 2 Basement Manager 1 Supervisor (Rebar) 2 Safety Officer QA/QC Manager 1 1 Supervisor 2 2 1 1 Supervisor (Con'c) Supervisor (Con'c) Supervisor (Con'c) Typist / Secretary 1 Material Asist.Supervisor (Form)Supervisor (Form) 2 Supervisor (Form) 2 Supervisor (Form) 1 22 1 Mech Supervisor Elect Supervisor General Affairs 1 2 2 1 Mech Engineer Elect Engineer Accountant Typist / Secretary Elect Manager Security Manager 1 LOTTE KOR 1 1 1 QS Manager Contract Manager Design Manager Mech Manager 2 Supervisor Supervisor (Rebar) Supervisor (Rebar) Supervisor (Rebar) 1 1 1 2 Surveyor 4 1 1 11 Arch. Chief Supervisor Arch. Chief Supervisor Arch. Chief Supervisor Arch. Chief Supervisor Supervisor (Arch.) 12 Typist / Secretary1 4 4 Supervisor (Arch.) 3 Supervisor (Arch.) Supervisor (Arch.) sub-total 5 3 112 120 Total 8 112 120 품질 QA/QC 7 7 안전 Safety 9 9 기전 MEP 1 15 16 관리 ADM. 1 5 6 공무 ENG. 2 1 17 20 공사 CON. 1 1 59 61 Description Korean Local 합계 LOTTE JO Totalindo & JO 소장 PM 1 1
  • 11. SITE PLAN CONSTRUCTION EXECUTION PLAN Access road REBAR FABRICATION AND REBAR STOCK PROTECTION ROAD WAY Conc’ pump SUBCO NT SIT E OFFIC E (300m2 EXISTING BUILDING BATCHING PLANT CONTRACTOR SITE OFFICE STOCK AREA CANTEEN 600 m2 LABOUR CAMP 1 1500 m2 BT.SLAB B5 Elv.-3.3m BOTTOM RAFT Elv.-5.9 Elv.-5.9 Elv.-5.9 REBAR FABRICATION AND REBAR STOCK Elv.-3.3 Elv.-3.3 Conc’ pump Conc’ pump Conc’ pump Existing (300m2 ) BUILDING SITE OFFICE TEMPORARY FENCE BASEMENT LINE TEMPORARY ACCESS ROAD LABOUR CAMP CONTRACTOR SITE OFFICE STOCK AREA CONCRETE BATCHING PLANT CANTEEN
  • 12. SITE PLAN CONSTRUCTION EXECUTION PLAN Access road F/W FABRICATION REBAR FABRICATION PROTECTION ROAD WAY Conc’ pump SUBCO NT SIT E OFFIC E (300m2EXISTING BATCHING PLANT CONTRACTOR SITE OFFICE STOCK AREA CANTEEN 600 m2 LABOUR CAMP 1 1500 m2 GF GF TYP. FLOOR TYP. FLOOR TYP. FLOOR B4 B4 GF Conc’ pump Conc’ pump Existing (300m2 ) EXISTING BUILDING SITE OFFICE TEMPORARY FENCE BASEMENT LINE TEMPORARY ACCESS ROAD LABOUR CAMP CONTRACTOR SITE OFFICE STOCK AREA CONCRETE BATCHING PLANT CANTEEN REBAR FABRICATION REBAR FABRICATION AND REBAR STOCK
  • 13. CONSTRUCTION EXECUTION PLAN III TC #3 R =50M TC #5 R =50M Expected Max. Lifting Weight DESCRIPTION Lifting Item Weight FORM-WORK Wall 2.0 Ton Column 1.5 Ton TC #1 R =45M TC #2 R =50M TC #4 R =50M R =50M TC #6 R =50M TOWER CRANE SPECIFICATION TC NAME T/C #1 T/C #2~6 TYPE HAMMER HEAD, STATIC HAMMER HEAD, STATIC (TIP LOAD) 45M – 3.5 Ton 50M – 3.15 Ton PERIODE 25 MONTH 26 MONTH Column 1.5 Ton REBAR Bundle Rebar 2.0 Ton Prefab Rebar 2.5 Ton FACAD Panel 1 1.8 Ton Panel 2 1.5 Ton PC Panel 2 Ton CONC’ CPB 5.0 Ton ELECTRICAL & MACHINERY Elec. Panel 2.0 Ton ELEV 2.5 Ton
  • 15. III CONSTRUCTION EXECUTION PLAN MH#3 MH#4 MH#5 MH#6 TOWER 3 TC3 TC5 MH#1 Note : MH = Material Hoist TOWER 1 MH#2 MH#3 MH#7 TOWER 2 TC1 TC2 TC4 TC6 MH#1 Description Specification Remark Equipment Type Twin Medium Type Equipment Name ALIMAK SC 65/32 Cage Size 1.5W*3.2L*2.5H Load Capacity 2 TON Speed 60 M/MIN
  • 16. III CONSTRUCTION EXECUTION PLAN 8M CPB#3 CPB maximum distance from unapplied area : Approximately 8M CPB#2 CPB#3 CPB#4 Concrete Placing Boom Specification CPB Name CPB #1~4 Type Potential HG 28 H Radius ± 28 Meter High ± 22.9 Meter CPB#1 Note : CPB = Concrete Placing Boom
  • 18. CONSTRUCTION METHOD 2 Footprint tower is the priority area Basement Line Note: ZONNING SUBSTRUCTUREZONNING SUBSTRUCTURE Zone 1 8,115m2 Zone 3 5,742m2 Tower 1 Tower 3 Tower 2 Zone 2 3,758m2 Footprint tower is the priority area Note: ♦ Zoning area of sub-structure work is divided into 3 zones: Zone 1 : Area Tower 1, 8115 m² Zone 2 : Area Tower 3, 3758 m² Zone 3 : Area Tower 2, 5742 m² Footprint tower is the priority area the priority area
  • 19. 2 CONSTRUCTION METHOD Note: ♦ Zoning area of super- structure work is divided into several zones Area Tower 1 : 2100 m² Zone 1, 325 m²Zone 1, 325 m² Zone 2, 256 m² Zone 3, 469 m² Zone 1’, 325 m² Zone 2’, 256 m² Zone 3’, 469 m² Area Tower 2 : 2294 m² Zone 1, 453 m² Zone 2, 465 m² Zone 3, 448 m² Zone 4, 421 m² 3’3’ 2’2’ 1’1’ 11 22 4433 11 22 44 33 55 ZONNING SUPER STRUCTUREZONNING SUPER STRUCTURE TOWER 3TOWER 3TOWER 3TOWER 3 TOWER 2TOWER 2TOWER 2TOWER 2 Zone 4, 421 m² Zone 5, 505 m² Area Tower 3 : 1337 m² Zone 1, 322 m² Zone 2, 353 m² Zone 3, 340 m² Zone 4, 322 m² 33 22 11 TOWER 1TOWER 1TOWER 1TOWER 1
  • 20. 3 CONSTRUCTION METHOD Access road ZONE ACTIVITIES TOWER 1 - Detail Excavation for raft, cutting bore pile, Conc’ Foundation TC1 Existing SUBCO NT SIT E OFFI CE (300m2 ) EXISTING BUILDING Conc’ Foundation TC1 TOWER 3 - Bulk Excavation (by Owner) TOWER 2 - Bulk Excavation (by Owner)TC1 Tower 1 Tower 3 Tower 2
  • 21. 3 CONSTRUCTION METHOD Access road ZONE ACTIVITIES TOWER 1 - Excavation for raft, cutting bore pile, Install TC1 & TC2, Conc’ Lift Pit, Install rebar for raft foundation Existing SUBCO NT SIT E OFFI CE (300m2 ) EXISTING BUILDING rebar for raft foundation TOWER 3 - Bulk Excavation (by Owner) TOWER 2 - Bulk Excavation (by Owner)TC1 TC2 LIFT PIT LIFT PIT Tower 1 Tower 3 Tower 2 LIFT PIT
  • 22. 3 CONSTRUCTION METHOD Access road ZONE ACTIVITIES TOWER 1 - Excavation for raft foundation completed, Install rebar for raft foundation continued Existing SUBCO NT SIT E OFFI CE (300m2 ) EXISTING BUILDING foundation continued TOWER 3 - Excavation (by Owner) TOWER 2 - BExcavation (by Owner)TC1 TC2 TC1 Tower 1 Tower 3 Tower 2 RAFT FOUNDATION
  • 23. 3 CONSTRUCTION METHOD Access road ZONE ACTIVITIES TOWER 1 - Raft Foundation completed, B5 columns in progress, GWT in progress Existing SUBCO NT SIT E OFFI CE (300m2 ) EXISTING BUILDING Podium Outer Tower 1 - Excavation and cutting bored pile, B5 slab in progress Podium Tower 1 –2 - Excavation and cutting bored pile, B5 slab in progress TOWER 3 - Start Excavation for raft foundation TOWER 2 - Bulk Excavation (by Owner) TC1 TC2 B5 Tower 1 Tower 3 Tower 2
  • 24. 3 CONSTRUCTION METHOD Access road ZONE ACTIVITIES TOWER 1 - B4 slab in progress, GWT in B5 completed, B4 column in progressB5 TC3 Existing SUBCO NT SIT E OFFI CE (300m2 ) EXISTING BUILDING Podium Outer Tower 1 - B5 slab completed Podium Tower 1 –2 - B5 slab completed TOWER 3 - Excavation for raft and cutting bored pile, install TC 3 & TC 4, Install rebar for lift pit and raft foundation TOWER 2 - Bulk Excavation (by Owner) B5 TC1 TC2 B5 B4 TC4 Tower 1 Tower 3 Tower 2 B4 RAFT FOUNDATION
  • 25. 3 CONSTRUCTION METHOD Access road ZONE ACTIVITIES TOWER 1 - B4 slab completed, B3 slab & column in progress,B5 TC3 TC5 Existing SUBCO NT SIT E OFFI CE (300m2 ) EXISTING BUILDING TOWER 3 - Lift pit completed, Install rebar for raft foundation TOWER 2 - Excavation for raft & cutting bored pile, install TC 5 and TC 6B5 TC1 TC2 B5 B3 TC4 B4 TC6 Tower 1 Tower 3 Tower 2 RAFT FOUNDATION B3
  • 26. 3 CONSTRUCTION METHOD Access road ZONE ACTIVITIES TOWER 1 - B3 slab completed, B2 slab & column in progress,B5 TC3 B5 STP TC5 Existing SUBCO NT SIT E OFFI CE (300m2 ) EXISTING BUILDING TOWER 3 - Raft foundation completed, STP in progress, B5 column in progress, Podium Outer Tower 3 - Excavation for pile cap & cutting bored pile, B5 Slab in progress TOWER 2 - Conc’ lift pit, install rebar for raft foundation in progress. B5 TC1 TC2 B5 B2 TC4 B3 TC6 B2 B5 Tower 1 Tower 3 Tower 2 B2 RAFT FOUNDATION B5B5
  • 27. 3 CONSTRUCTION METHOD Access road ZONE ACTIVITIES TOWER 1 - B1 slab completed, GF slab in progress,B5 TC5 B5 B4 TC3 B5 Existing SUBCO NT SIT E OFFI CE (300m2 ) EXISTING BUILDING Podium Outer Tower 1 - B4 and B3 slab in progress TOWER 3 - B4 slab completed, Podium Outer Tower 3 - B5 slab completed TOWER 2 - Raft foundation completed B4 TC1 TC2 B3 B2 B1 TC6 GF B5 B4 RAFT FOUNDATION TC4B5 Tower 1 Tower 3 Tower 2 GF B4 B1 B4 B5 RAFT FOUNDATION
  • 28. 3 CONSTRUCTION METHOD Access road B5 TC3 B5 B5 B4 L2GF TC5 B4B5 ZONE ACTIVITIES TOWER 1 - Level 9 slab completed, Level 10 & 11 slab in progress, Existing SUBCO NT SIT E OFFI CE (300m2 ) EXISTING BUILDING GF TC1 GF GF TC2 B5 L11 L9 L10 L2 B4 GF TC6 B4 TC4 B3 B5 B5 B5 Podium Outer Tower 1 - GF slab completed Podium Tower 1 -3 - B4 slab in progress, TOWER 3 - GF slab completed, Level 2 slab in progress Podium Outer Tower 3 - B4 slab in progress TOWER 2 - B4 slab completed, B3 slab in progress Podium Tower 1 Tower 3 Tower 2 GF Level 2 Podium Outer Tower 3 - B5 slab complete B3 Level 11 Level 10 B5 B5
  • 29. 3 CONSTRUCTION METHOD ZONE ACTIVITIES TOWER 1 - Roof slab completed, Lift Motor Room Completed, TC3 TC2 L2 TC5 TC4 GF GF GFL26 Access road L25 L39 L38 L37 TOWER 3 - Level 37 slab completed, Level 38 & 39 slab in progress TOWER 2 - Level 25 slab completed, Level 26 & 27 slab in progress Podium All - GF slab complete Tower 1 Tower 3 Tower 2 ROOF Existing SUB CON T SI TE O FFIC E (300 m2) EXISTING BUILDING GF TC1 GF TC6 TC4 L27 LMRLMR Level 39 Level 38 ROOF ROOF GF Level 37 Level 38 Level 27 Level 26 GF GF
  • 30. 3 CONSTRUCTION METHOD ZONE ACTIVITIES TOWER 1 - Finishing work in progress TC3 TC2 L2 TC5 GF GFL37 Access road L36 ROOF TC4 L2 L2 TOWER 3 - Roof slab completed, Lift Motor Room Completed TOWER 2 - Level 36 slab completed, Level 37& 38 slab in progress Podium - L2 slab completed Tower 1 Tower 3 Tower 2 ROOF Existing SUB CON T SI TE O FFIC E (300 m2) EXISTING BUILDING GF GF TC6 L38 LMRLMR Level 38Level 37 ROOF ROOF TC1 TC4L2 L2 ROOF LMRLMR L2 L2 GF FINISHING WORK
  • 31. 3 CONSTRUCTION METHOD ZONE ACTIVITIES TOWER 1 - Finishing work in progress TC3 L2 TC6 TC5 GF GF Access road ROOF ROOF TC4 L3 L3 ROOF TOWER 3 - Finishing work in progress TOWER 2 - Roof slab completed, Lift Motor Room Completed Podium - L3 slab completed Tower 1 Tower 3 ROOF LMRLMR ROOF ROOF LMRLMR Existing SUB CON T SI TE O FFIC E (300 m2) EXISTING BUILDING GF GF TC6 ROOF ROOF L3 LMR LMR Tower 2 L3 L3 GF FINISHING WORK FINISHING WORK
  • 32. CONSTRUCTION METHOD 3 Thermocouple posisition Thermocouple Plan Existing SUBCO NT SIT E OFFI CE (300m2 ) EXISTING BUILDING Bottom Slab B5 Elv.-3.3m Detail of thermocouple installation Note: • Concrete volume±7500m³ • Supportive equipments : • Conc. Pump : 7unit (1 stand-by) • Vibrator : 25 unit (5 stand-by) • Tent for protecting area that should be poured concrete • Thermocouple for thermal monitoring • After all preparation completed, pouring concrete use concrete pump ± 25m³/hr capacity. Casting raft foundation can be completed within ± 60 hours Thermal monitoring
  • 33. 3 Excavation for raft foundation Cuti bored pile Spray anti termite (optional if necessary) CONSTRUCTION METHOD Lean concreteFormworkRebar work Bottom layer Support rebar Upper layerStarter rebar
  • 34. 3 ME installation Thermocouple installation Starter bar inspection CONSTRUCTION METHOD Cold-joint installationProtective Tent installation
  • 35. 3 Concrete finishingConcrete acceptance scheme Casting Process CONSTRUCTION METHOD Concrete truck access Area for concrete truck Concrete curing Always provide 1 unit Concrete pump stand-by Concrete sample Styrofoam installation
  • 38. 3 CONSTRUCTION METHOD ZONE 1’ 9 TABLES ZONE 1 9 TABLES Slab conc’: Zone 1 = ± 110.5 m³ Zone 2 = ± 84.5 m³ Zone 3 = ± 155 m³ ZONE 2’ 7 TABLES ZONE 2 7 TABLES Zone 3 = ± 155 m³ Zone 1’ = ± 110.5 m³ Zone 2’= ± 84.5 m³ Zone 3’= ± 155 m³ ZONE 3’ 12 TABLES ZONE 3 12 TABLES CONVENSIONAL CONVENSIONAL
  • 39. 3 CONSTRUCTION METHOD Typical Elevation Table Tower 1 Typical Section Table Tower 1
  • 40. 3 CONSTRUCTION METHOD ZONE 1 9 TABLES ZONE 2 7 TABLES ZONE 4 9 TABLES ZONE 3 7 TABLES Slab conc’: Zone 1 = ± 106 m³ Zone 2 = ± 117 m³ Zone 3 = ± 112 m³ Zone 4 = ± 106 m³
  • 41. 3 CONSTRUCTION METHOD Typical Elevation Table Tower 3 Typical Section Table Tower 3
  • 42. 3 CONSTRUCTION METHOD Slab conc’: Zone 1 = ± 150 m³ Zone 2 = ± 153.5 m³ Zone 3 = ± 147.8 m³ Zone 4 = ± 138.93 m³Zone 4 = ± 138.93 m³ ZONE 2 7 TABLES ZONE 1 7 TABLES CONVENSIONAL ZONE 3 7 TABLES ZONE 4 8 TABLES
  • 43. 3 CONSTRUCTION METHOD Typical Elevation Table Tower 2 Typical Section Table Tower 2
  • 44. 3 CONSTRUCTION METHOD 1st Set 2nd Set 3rd Set 1st Set
  • 45. 3 Note: Concrete mold for column and shearwall are using Aluma Beam, Steel waler and plywood 18mm double film CONSTRUCTION METHOD Typical Shear wall Shear wall type SW40A & SW35A
  • 46. 03 Note: CONSTRUCTION METHOD Note: This the illustrations when the Table Form Flying next to the upper floors, very easy and fast
  • 47. 03 CONSTRUCTION METHOD Note: Aluma Table Form is often calledAluma Table Form is often called Flying Table because when the table stripped out to next floor is lifted by tower crane, making it very fast for the cycle time floor to the next floor
  • 48. QA / QC PLAN 4 Shop Drawing &Shop Drawing & Material SubmissionMaterial Submission Method of Construction (Trade)Method of Construction (Trade) Method Briefing &Method Briefing & Training to WorkersTraining to Workers Method Briefing &Method Briefing & Training to WorkersTraining to Workers Trade DemonstrationTrade Demonstration (Mock Up)(Mock Up) Trade DemonstrationTrade Demonstration (Mock Up)(Mock Up) DefineDefine Holding PointHolding Point Inspection & Test PlanInspection & Test Plan Step by Step InspectionStep by Step Inspection Execution of WorkExecution of Work Quality WorkQuality Work SetSet--upup Quality StandardQuality Standard Consultant + Main-con + Subcon
  • 49. 04 SAFETY PROTECTION 01 Building Protection
  • 53. Building Protection 01 COUPLER TIANG RAILINGHANDRAIL INSTALLATION MID HANDRAIL BESI BEHEL D12 BASEPLATE POLYNET TIANG RAILING POLYNET safety wing net/ Safety deck safety wing net/ Safety deck CORNER BESI BEHEL D12 Perimeter Safety Net / Safety Railing
  • 55. Building Protection 01 HANDRAIL MID HANDRAIL OPENING 100 ~ 600 mm OPENING > 2 M / VOID AREA KAWAT AYAM + SAFETY NET BESI BEHEL D12 OPENING 650~ 2000 mm
  • 56. Building Protection 01 SAFETY NET DI LIFT SAFETY VOID
  • 57. 05 HSE MANAGEMENT PLAN 01 Certificate 02 Safety Plan