Surveys for Highwaywww.skpatil.com 2
■ Before a highway alignment is finalised in highway project,
the engineering survey are to be carried out.
1) Map study
2) Reconnaissance survey
3) Preliminary survey
4) Final location and detailed surveys
1. Map Studywww.skpatil.com 3
■ From the map alternative routes can be suggested in the office, if
the topographic map of that area is available.
■ The probable alignment can be located on the map from the
fallowing details available on the map.
– Avoiding valleys, ponds or lake
– Avoiding bend of river
– If road has to cross a row of hills, possibility of crossing
through mountain pass.
■ Map study gives a rough guidance of the routes to be further
surveyed in the field
2. Reconnaissance Surveywww.skpatil.com 4
■ To confirm features indicated on map.
■ To examine the general character of the area in field for deciding the most feasible
routes for detailed studies.
■ A survey party may inspect along the proposed alternative routes of the map in the field
with very simple instrument like abney level, tangent clinometer, barometer etc. to
collect additional details.
■ Details to be collected from alternative routes from this survey are,
– Valleys, ponds, lakes, marshy land, hill, permanent structure and other
obstruction.
– Value of gradient, length of gradient and radius of curve.
– Number and type of cross drainage structures.
– High Flood Level(HFL)
– Soil Characteristics.
– Geological features.
– source of construction materials-stone quarries, water sources.
■ Prepare a report on merits and demerits of different alternative routes.
■ As a result a few alternate alignments may be chosen for further study based on
practical considerations observed at the site.
3. Preliminary surveywww.skpatil.com 5
■ Objectives
– To survey the various alternative alignments proposed after
the reconnaissance and to collect all the necessary physical
information and detail of topography, drainage and soil.
– To compare the different proposals in view of the
requirements of the good alignment.
– To estimate quantity of earthwork materials and other
construction aspect and to workout the cost of the alternate
proposals.
3. Preliminary surveywww.skpatil.com 6
■ Methods
– Conventional approach-survey party carries out surveys
using the required field equipment, taking measurement,
collecting topographical and other data and carrying out
soil survey.
■ Longitudinal and cross sectional profile.
– PlainTerrain`:100–200m
– RollingTerrain:50m
– HillyTerrain:30m
■ Other studies
– Drainage, Hydrological survey, soil survey, Traffic and Material
survey.
– Modern Rapid Approach
■ Aerial Photogrammetry, High Res. Satellite Images, Drones
4. Final location and detailed surveywww.skpatil.com 7
■ The alignment finalised at the design office after the
preliminary survey is to be first located on the field by
establishing the centre line.
■ Location survey:
– Transferring the alignment on to ground.
– This is done by transit theodolite.
– Major and minor control points are established on the
ground and centre pegs are driven, checking the
geometric design requirements.
– Centre line stacks are driven at suitable intervals, say
50m interval in plane and rolling terrains and 20m in
hilly terrain
4. Final location and detailed surveywww.skpatil.com 8
■ Detailed Survey
– Temporary benchmarks are fixed at intervals of about
250m and at all drainage and underpass structure.
– Earthwork calculations and drainage details are to be
workout from the level books.
– Cross-sectional levels are taken at intervals of 50-100m in
Plane terrain, 50-75m in Rolling terrain,50m in built-up
area, 20m in Hilly terrain.
– Detail soil survey is to be carried out.
– CBR value of the soils along the alignment may be
determined for design of pavement.
– The data during detailed survey should be elaborate and
complete for preparing detailed plans, design and
estimates of project.
Drawing and Reportwww.skpatil.com 9
■ Key map
■ Index map
■ Preliminary survey plans
■ Detailed plan and longitudinal section
■ Detailed cross section
■ Land acquisition plans
■ Drawings of cross drainage and other retaining structures
■ Drawings of road intersections
■ Land plans showing quarries etc.
■ All these information is compiled into DPR.
DPR - Detailed Project Reportwww.skpatil.com 10
1. Executive Summary
2. Background
3. General Details
4. Socio-Economic Profile
5. Demographic Profile
6. Traffic surveys & forecast
7. Engineering surveys &
investigation
8. Design standards and
specifications
9. Pavement design details
10.Drainage studies, C/D works
design
11.Environmental considerations
with resettlements plan
12.Material, Equipment and
human resources
13.Analysis & Design
14.Rate analysis & Estimate
15.Construction schedule
16.Traffic management during
construction
17.Conclusion
Highway Planning and Development
■ Road Classification based on diff criteria
■ Criteria
– Material
– Location & Function
– Traffic Volume
– Economy
– Rigidity
– Topography
– Traffic Type
– Special Roads
www.skpatil.com 11
Life's biggest challenge is deciding
what's important ... then
disregarding the rest - Anonymous
I can be reached at
www.skpatil.com
www.skpatil.com 12

More Related Content

What's hot

Types of pavements
Types of pavementsTypes of pavements
Types of pavements
Aglaia Connect
 
Unit 1
Unit 1Unit 1
Highway drainage
Highway drainageHighway drainage
Highway drainage
Aglaia Connect
 
Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavements
pradip dangar
 
Soil stabilisation (1)
Soil stabilisation (1)Soil stabilisation (1)
Soil stabilisation (1)
Safiullah Khan
 
Cross section of road
Cross section of roadCross section of road
Cross section of road
Ghanashyam Prajapati
 
Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineering
KHUSHBU SHAH
 
Benkelman beam deflection studies
Benkelman beam deflection studiesBenkelman beam deflection studies
Benkelman beam deflection studies
vikasravekar
 
GEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAYGEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAY
reemajadwani
 
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICEHIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
Fresher Thinking
 
Embankment
EmbankmentEmbankment
Embankment
civilguna
 
Overtaking sight distance
Overtaking sight distanceOvertaking sight distance
Overtaking sight distance
Aglaia Connect
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
GARRE RAVI KUMAR
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
mohit kumar panchal
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentation
Pawan Kumar
 
Highway planning and alignment
Highway planning and alignmentHighway planning and alignment
Introduction to highway engineering
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineering
Aavani Thampi
 
GROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODSGROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODS
ramgsvhce
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
pradip dangar
 
8. Road Construction Technology.pdf
8. Road Construction Technology.pdf8. Road Construction Technology.pdf
8. Road Construction Technology.pdf
Er. Bam Bhandari
 

What's hot (20)

Types of pavements
Types of pavementsTypes of pavements
Types of pavements
 
Unit 1
Unit 1Unit 1
Unit 1
 
Highway drainage
Highway drainageHighway drainage
Highway drainage
 
Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavements
 
Soil stabilisation (1)
Soil stabilisation (1)Soil stabilisation (1)
Soil stabilisation (1)
 
Cross section of road
Cross section of roadCross section of road
Cross section of road
 
Transportation engineering
Transportation engineeringTransportation engineering
Transportation engineering
 
Benkelman beam deflection studies
Benkelman beam deflection studiesBenkelman beam deflection studies
Benkelman beam deflection studies
 
GEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAYGEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAY
 
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICEHIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
 
Embankment
EmbankmentEmbankment
Embankment
 
Overtaking sight distance
Overtaking sight distanceOvertaking sight distance
Overtaking sight distance
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentation
 
Highway planning and alignment
Highway planning and alignmentHighway planning and alignment
Highway planning and alignment
 
Introduction to highway engineering
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineering
 
GROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODSGROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODS
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
8. Road Construction Technology.pdf
8. Road Construction Technology.pdf8. Road Construction Technology.pdf
8. Road Construction Technology.pdf
 

Similar to L4 engineering surveys for highways 1.3

2 - Route Surveys and Location.pptx
2 - Route Surveys and Location.pptx2 - Route Surveys and Location.pptx
2 - Route Surveys and Location.pptx
natan82253
 
Unit 1:- HIGHWAY DEVELOPMENT AND PLANNING
Unit 1:- HIGHWAY DEVELOPMENT AND PLANNINGUnit 1:- HIGHWAY DEVELOPMENT AND PLANNING
Unit 1:- HIGHWAY DEVELOPMENT AND PLANNING
RNRANGANATH
 
Highway presentation
Highway presentationHighway presentation
Highway presentation
Gaurav Baviskar
 
Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)
Saksham Bhutani
 
Location survey for the Rural and urban areas
Location survey for the Rural and urban areasLocation survey for the Rural and urban areas
Location survey for the Rural and urban areas
Rana Ibrahim
 
Introduction to surveying
Introduction to surveyingIntroduction to surveying
Introduction to surveying
Mir Zafarullah
 
Surveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringSurveys & alignment of Railway Engineering
Surveys & alignment of Railway Engineering
Latif Hyder Wadho
 
Lecture 7
Lecture 7Lecture 7
Geological investigations for highways
Geological investigations for highwaysGeological investigations for highways
Geological investigations for highways
Prof. A.Balasubramanian
 
Terrain Evaluation with Landuse Planning
Terrain Evaluation with Landuse PlanningTerrain Evaluation with Landuse Planning
Terrain Evaluation with Landuse Planning
pankaj kumar
 
presentation on Proposal for road survey & construction
presentation on Proposal for road survey & constructionpresentation on Proposal for road survey & construction
presentation on Proposal for road survey & construction
Dipendra Bhattarai
 
Dam engineering i 3
Dam engineering i 3Dam engineering i 3
Dam engineering i 3
FeteneBefekadu
 
civil engineers project work .docx
civil engineers project work .docxcivil engineers project work .docx
civil engineers project work .docx
Vijay Kumar
 
Highway Projects
Highway Projects Highway Projects
Highway Projects
RAMPRASAD KUMAWAT
 
Unit 5
Unit 5Unit 5
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
Subhendu Samui
 
PROJECT-REPORT-SUBHENDU
PROJECT-REPORT-SUBHENDUPROJECT-REPORT-SUBHENDU
PROJECT-REPORT-SUBHENDUSubhendu Samui
 
Module 1 Highway Engg (1).pdf
Module 1 Highway Engg (1).pdfModule 1 Highway Engg (1).pdf
Module 1 Highway Engg (1).pdf
DhananjayM13
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to road
KHUSHBU SHAH
 
Alignment Survey | Track Alignment | Civil TechMate
Alignment Survey | Track Alignment | Civil TechMateAlignment Survey | Track Alignment | Civil TechMate
Alignment Survey | Track Alignment | Civil TechMate
Civil TechMate
 

Similar to L4 engineering surveys for highways 1.3 (20)

2 - Route Surveys and Location.pptx
2 - Route Surveys and Location.pptx2 - Route Surveys and Location.pptx
2 - Route Surveys and Location.pptx
 
Unit 1:- HIGHWAY DEVELOPMENT AND PLANNING
Unit 1:- HIGHWAY DEVELOPMENT AND PLANNINGUnit 1:- HIGHWAY DEVELOPMENT AND PLANNING
Unit 1:- HIGHWAY DEVELOPMENT AND PLANNING
 
Highway presentation
Highway presentationHighway presentation
Highway presentation
 
Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)
 
Location survey for the Rural and urban areas
Location survey for the Rural and urban areasLocation survey for the Rural and urban areas
Location survey for the Rural and urban areas
 
Introduction to surveying
Introduction to surveyingIntroduction to surveying
Introduction to surveying
 
Surveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringSurveys & alignment of Railway Engineering
Surveys & alignment of Railway Engineering
 
Lecture 7
Lecture 7Lecture 7
Lecture 7
 
Geological investigations for highways
Geological investigations for highwaysGeological investigations for highways
Geological investigations for highways
 
Terrain Evaluation with Landuse Planning
Terrain Evaluation with Landuse PlanningTerrain Evaluation with Landuse Planning
Terrain Evaluation with Landuse Planning
 
presentation on Proposal for road survey & construction
presentation on Proposal for road survey & constructionpresentation on Proposal for road survey & construction
presentation on Proposal for road survey & construction
 
Dam engineering i 3
Dam engineering i 3Dam engineering i 3
Dam engineering i 3
 
civil engineers project work .docx
civil engineers project work .docxcivil engineers project work .docx
civil engineers project work .docx
 
Highway Projects
Highway Projects Highway Projects
Highway Projects
 
Unit 5
Unit 5Unit 5
Unit 5
 
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
 
PROJECT-REPORT-SUBHENDU
PROJECT-REPORT-SUBHENDUPROJECT-REPORT-SUBHENDU
PROJECT-REPORT-SUBHENDU
 
Module 1 Highway Engg (1).pdf
Module 1 Highway Engg (1).pdfModule 1 Highway Engg (1).pdf
Module 1 Highway Engg (1).pdf
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to road
 
Alignment Survey | Track Alignment | Civil TechMate
Alignment Survey | Track Alignment | Civil TechMateAlignment Survey | Track Alignment | Civil TechMate
Alignment Survey | Track Alignment | Civil TechMate
 

More from Sachin PatiL

C 1 highway development in india
C 1 highway development in indiaC 1 highway development in india
C 1 highway development in india
Sachin PatiL
 
L2 Highway planning and development Unit 1.1
L2 Highway planning and development Unit 1.1  L2 Highway planning and development Unit 1.1
L2 Highway planning and development Unit 1.1
Sachin PatiL
 
Job Opportunities as Transportation Engineer
Job Opportunities as  Transportation EngineerJob Opportunities as  Transportation Engineer
Job Opportunities as Transportation Engineer
Sachin PatiL
 
Traffic survey student activity janata bazar kolhapur
Traffic survey student activity janata bazar kolhapurTraffic survey student activity janata bazar kolhapur
Traffic survey student activity janata bazar kolhapur
Sachin PatiL
 
Traffic survey student activity dabhil naka
Traffic survey student activity dabhil nakaTraffic survey student activity dabhil naka
Traffic survey student activity dabhil naka
Sachin PatiL
 
Traffic survey student activity chiplun
Traffic survey student activity chiplunTraffic survey student activity chiplun
Traffic survey student activity chiplun
Sachin PatiL
 
Traffic survey student activity bharane naka
Traffic survey student activity bharane nakaTraffic survey student activity bharane naka
Traffic survey student activity bharane naka
Sachin PatiL
 
CiviLions GIT civil newsletter vol 1 issue-2
CiviLions GIT civil newsletter vol 1 issue-2CiviLions GIT civil newsletter vol 1 issue-2
CiviLions GIT civil newsletter vol 1 issue-2
Sachin PatiL
 
Amgoi news vol 1 issue 1
Amgoi news vol 1 issue 1Amgoi news vol 1 issue 1
Amgoi news vol 1 issue 1
Sachin PatiL
 
3.3 land acquisition act
3.3 land acquisition act3.3 land acquisition act
3.3 land acquisition act
Sachin PatiL
 
3.2 Maharashtra regional town planning act
3.2 Maharashtra regional town planning act3.2 Maharashtra regional town planning act
3.2 Maharashtra regional town planning act
Sachin PatiL
 
3.1.2 development control rules tdr
3.1.2 development control rules tdr3.1.2 development control rules tdr
3.1.2 development control rules tdr
Sachin PatiL
 
3.1.1 development control rules case study
3.1.1 development control rules case study3.1.1 development control rules case study
3.1.1 development control rules case study
Sachin PatiL
 
3.1 development control rules
3.1 development control rules3.1 development control rules
3.1 development control rules
Sachin PatiL
 
3.6 urban renewal
3.6 urban renewal3.6 urban renewal
3.6 urban renewal
Sachin PatiL
 
3.5.1 master plan
3.5.1 master plan3.5.1 master plan
3.5.1 master plan
Sachin PatiL
 
3.5 structure, dpp subject plan
3.5 structure, dpp subject plan3.5 structure, dpp subject plan
3.5 structure, dpp subject plan
Sachin PatiL
 
3.4 village planning
3.4 village planning3.4 village planning
3.4 village planning
Sachin PatiL
 
2.6.2 slum case study mumbai sparc
2.6.2 slum case study mumbai sparc2.6.2 slum case study mumbai sparc
2.6.2 slum case study mumbai sparc
Sachin PatiL
 
2.6.1 slum case study mumbai
2.6.1 slum case study mumbai2.6.1 slum case study mumbai
2.6.1 slum case study mumbai
Sachin PatiL
 

More from Sachin PatiL (20)

C 1 highway development in india
C 1 highway development in indiaC 1 highway development in india
C 1 highway development in india
 
L2 Highway planning and development Unit 1.1
L2 Highway planning and development Unit 1.1  L2 Highway planning and development Unit 1.1
L2 Highway planning and development Unit 1.1
 
Job Opportunities as Transportation Engineer
Job Opportunities as  Transportation EngineerJob Opportunities as  Transportation Engineer
Job Opportunities as Transportation Engineer
 
Traffic survey student activity janata bazar kolhapur
Traffic survey student activity janata bazar kolhapurTraffic survey student activity janata bazar kolhapur
Traffic survey student activity janata bazar kolhapur
 
Traffic survey student activity dabhil naka
Traffic survey student activity dabhil nakaTraffic survey student activity dabhil naka
Traffic survey student activity dabhil naka
 
Traffic survey student activity chiplun
Traffic survey student activity chiplunTraffic survey student activity chiplun
Traffic survey student activity chiplun
 
Traffic survey student activity bharane naka
Traffic survey student activity bharane nakaTraffic survey student activity bharane naka
Traffic survey student activity bharane naka
 
CiviLions GIT civil newsletter vol 1 issue-2
CiviLions GIT civil newsletter vol 1 issue-2CiviLions GIT civil newsletter vol 1 issue-2
CiviLions GIT civil newsletter vol 1 issue-2
 
Amgoi news vol 1 issue 1
Amgoi news vol 1 issue 1Amgoi news vol 1 issue 1
Amgoi news vol 1 issue 1
 
3.3 land acquisition act
3.3 land acquisition act3.3 land acquisition act
3.3 land acquisition act
 
3.2 Maharashtra regional town planning act
3.2 Maharashtra regional town planning act3.2 Maharashtra regional town planning act
3.2 Maharashtra regional town planning act
 
3.1.2 development control rules tdr
3.1.2 development control rules tdr3.1.2 development control rules tdr
3.1.2 development control rules tdr
 
3.1.1 development control rules case study
3.1.1 development control rules case study3.1.1 development control rules case study
3.1.1 development control rules case study
 
3.1 development control rules
3.1 development control rules3.1 development control rules
3.1 development control rules
 
3.6 urban renewal
3.6 urban renewal3.6 urban renewal
3.6 urban renewal
 
3.5.1 master plan
3.5.1 master plan3.5.1 master plan
3.5.1 master plan
 
3.5 structure, dpp subject plan
3.5 structure, dpp subject plan3.5 structure, dpp subject plan
3.5 structure, dpp subject plan
 
3.4 village planning
3.4 village planning3.4 village planning
3.4 village planning
 
2.6.2 slum case study mumbai sparc
2.6.2 slum case study mumbai sparc2.6.2 slum case study mumbai sparc
2.6.2 slum case study mumbai sparc
 
2.6.1 slum case study mumbai
2.6.1 slum case study mumbai2.6.1 slum case study mumbai
2.6.1 slum case study mumbai
 

Recently uploaded

Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 

Recently uploaded (20)

Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 

L4 engineering surveys for highways 1.3

  • 1. Transportation Engineering Module 1 Highway Planning and Development “Engineering Surveys for Highways” www.skpatil.com Dr. S.K. Patil HOD Civil, Gharda Institute of Technology, Lavel
  • 2. Surveys for Highwaywww.skpatil.com 2 ■ Before a highway alignment is finalised in highway project, the engineering survey are to be carried out. 1) Map study 2) Reconnaissance survey 3) Preliminary survey 4) Final location and detailed surveys
  • 3. 1. Map Studywww.skpatil.com 3 ■ From the map alternative routes can be suggested in the office, if the topographic map of that area is available. ■ The probable alignment can be located on the map from the fallowing details available on the map. – Avoiding valleys, ponds or lake – Avoiding bend of river – If road has to cross a row of hills, possibility of crossing through mountain pass. ■ Map study gives a rough guidance of the routes to be further surveyed in the field
  • 4. 2. Reconnaissance Surveywww.skpatil.com 4 ■ To confirm features indicated on map. ■ To examine the general character of the area in field for deciding the most feasible routes for detailed studies. ■ A survey party may inspect along the proposed alternative routes of the map in the field with very simple instrument like abney level, tangent clinometer, barometer etc. to collect additional details. ■ Details to be collected from alternative routes from this survey are, – Valleys, ponds, lakes, marshy land, hill, permanent structure and other obstruction. – Value of gradient, length of gradient and radius of curve. – Number and type of cross drainage structures. – High Flood Level(HFL) – Soil Characteristics. – Geological features. – source of construction materials-stone quarries, water sources. ■ Prepare a report on merits and demerits of different alternative routes. ■ As a result a few alternate alignments may be chosen for further study based on practical considerations observed at the site.
  • 5. 3. Preliminary surveywww.skpatil.com 5 ■ Objectives – To survey the various alternative alignments proposed after the reconnaissance and to collect all the necessary physical information and detail of topography, drainage and soil. – To compare the different proposals in view of the requirements of the good alignment. – To estimate quantity of earthwork materials and other construction aspect and to workout the cost of the alternate proposals.
  • 6. 3. Preliminary surveywww.skpatil.com 6 ■ Methods – Conventional approach-survey party carries out surveys using the required field equipment, taking measurement, collecting topographical and other data and carrying out soil survey. ■ Longitudinal and cross sectional profile. – PlainTerrain`:100–200m – RollingTerrain:50m – HillyTerrain:30m ■ Other studies – Drainage, Hydrological survey, soil survey, Traffic and Material survey. – Modern Rapid Approach ■ Aerial Photogrammetry, High Res. Satellite Images, Drones
  • 7. 4. Final location and detailed surveywww.skpatil.com 7 ■ The alignment finalised at the design office after the preliminary survey is to be first located on the field by establishing the centre line. ■ Location survey: – Transferring the alignment on to ground. – This is done by transit theodolite. – Major and minor control points are established on the ground and centre pegs are driven, checking the geometric design requirements. – Centre line stacks are driven at suitable intervals, say 50m interval in plane and rolling terrains and 20m in hilly terrain
  • 8. 4. Final location and detailed surveywww.skpatil.com 8 ■ Detailed Survey – Temporary benchmarks are fixed at intervals of about 250m and at all drainage and underpass structure. – Earthwork calculations and drainage details are to be workout from the level books. – Cross-sectional levels are taken at intervals of 50-100m in Plane terrain, 50-75m in Rolling terrain,50m in built-up area, 20m in Hilly terrain. – Detail soil survey is to be carried out. – CBR value of the soils along the alignment may be determined for design of pavement. – The data during detailed survey should be elaborate and complete for preparing detailed plans, design and estimates of project.
  • 9. Drawing and Reportwww.skpatil.com 9 ■ Key map ■ Index map ■ Preliminary survey plans ■ Detailed plan and longitudinal section ■ Detailed cross section ■ Land acquisition plans ■ Drawings of cross drainage and other retaining structures ■ Drawings of road intersections ■ Land plans showing quarries etc. ■ All these information is compiled into DPR.
  • 10. DPR - Detailed Project Reportwww.skpatil.com 10 1. Executive Summary 2. Background 3. General Details 4. Socio-Economic Profile 5. Demographic Profile 6. Traffic surveys & forecast 7. Engineering surveys & investigation 8. Design standards and specifications 9. Pavement design details 10.Drainage studies, C/D works design 11.Environmental considerations with resettlements plan 12.Material, Equipment and human resources 13.Analysis & Design 14.Rate analysis & Estimate 15.Construction schedule 16.Traffic management during construction 17.Conclusion
  • 11. Highway Planning and Development ■ Road Classification based on diff criteria ■ Criteria – Material – Location & Function – Traffic Volume – Economy – Rigidity – Topography – Traffic Type – Special Roads www.skpatil.com 11