SlideShare a Scribd company logo
SUBMITTED BY-RAVI 
GUPTA 
B.TECH(CIVIL ENGG.) 
ROLL NO.- 111000125
PUBLIC WORKS DEPARTMENT-AN 
OVERVIEW 
 Public Works Department (PWD), under the Ministry of Public Works 
department, is the pioneer in construction arena of Uttar Pradesh. 
 It plays a pivotal role in the implementation of government 
construction projects 
 To accelerate the construction of bridges in the state, Uttar Pradesh 
State Bridge Corporation was founded in 1973. 
 In year 2004-05, Uttar Pradesh state highways authority was 
established to overcome with problem of pavements in state.
INTRODUCTION 
 Development of a country depends on the connectivity of various 
places with adequate road network. 
 Roads constitute the most important mode of communication in 
areas where railways have not developed much. 
 India has one of the largest road networks in the world (over 3 million 
km at present).For the purpose of management and administration, 
roads in India are divided into the following five categories: 
• National Highways (NH) 
• State Highways (SH) 
• Major District Roads (MDR) 
• Other District Roads (ODR) 
• Village Roads (VR)
Fig. Showing status of Road Network 
In India 
Position of India In World Road 
Network
WHAT IS ROAD AND PAVEMENT 
?  Road is an open, generally public way for the passage of 
vehicles, people, and animals. 
 Pavement is finished with a hard smooth surface. It helped 
make them durable and able to withstand traffic and the 
environment. They have a life span of between 20 – 30 years. 
FUNCTIONS 
One of the primary functions of pavement is load distribution. It 
can be characterized by the tire loads, tire configurations, 
repetition of loads, and distribution of traffic across the 
pavement, and vehicle speed
TYPES OF PAVEMENTS 
There are various types of pavements depending upon the materials used; a briefs 
description of all types is given here- 
FLEXIBLE PAVEMENT 
Bitumen has been widely used in the construction of flexible pavements for a long time. 
This is the most convenient and simple type of construction. The cost of construction of 
single lane bituminous pavement varies from 20 to 30 lakhs per km in plain area. 
Flexible pavement have- 
 Have low flexural strength 
 Load is transferred by grain to grain contact 
 Have low completion cost but repairing cost is high 
 Have low life span (High Maintenance Cost)
RIGID PAVEMENT 
Rigid pavements, though costly in initial investment, are cheap in long run 
because of low maintenance costs, The cost of construction of single lane rigid 
pavement varies from 35 to 50 lakhs per km in plain area, 
Rigid pavement have- 
Deformation in the sub grade is not transferred to subsequent layers 
Design is based on flexural strength or slab action 
Have high flexural strength 
No such phenomenon of grain to grain load transfer exists 
Have low repairing cost but completion cost is high 
Life span is more as compare to flexible (Low Maintenance Cost)
Difference b/w Flexible and 
Rigid 
Pavement in terms of load 
distribution In different 
layers 
Different layers in Flexible and 
Rigid Pavement
Basic Components of a Concrete 
Longitudinal joint 
Transverse joint 
Surface Texture 
Subgrade 
Base 
Surface smoothness Thickness Design 
Concrete materials 
Dowel bars 
Tiebars 
Pavement
Types of Rigid Pavements 
 Jointed Plain Concrete Pavement (JPCP) 
– does not use any reinforcing steel 
 Jointed Reinforced Concrete Pavement (JRCP) 
– Reinforcing steel placed at mid height and discontinued at the 
joints. 
 Continuously Reinforced Concrete Pavement (CRCP) 
– This method is very costly and generally not used in India. 
 Pre-stressed Concrete Pavement (PCP) 
– Comprises new and innovative construction methods 
– Precast pavement components are fabricated and installed on a 
prepared foundation (existing pavement or re-graded foundation).
MINERALS USED 
Cement 
 Ordinary Portland cement (OPC) 
Ordinary Portland cement and High Strength Ordinary Portland Cement are 
most widely used for concrete pavements. 
 Rapid hardening Portland cement 
In general, this cement would be used only where time is a critical factor 
and the road is required to be opened to traffic at an earlier date than 
would be possible if Ordinary Portland Cement or High Strength Ordinary 
Portland Cement is used.
Mineral used( cont.) 
Aggregates 
• There are two types of Aggregates are used during construction of road i.e. 
Fine and Coarse Aggregate depending on requirements. 
• Maximum size of aggregate should not exceed 1/4th of the pavement slab 
thickness. 
Water 
• Water used in mixing or curing of concrete shall be clean and free from 
injurious amounts of oil, salt, acid, vegetable matter or other substances 
harmful to the finished concrete. 
• Potable waters are generally considered satisfactory for mixing or curing.
Equipments used 
A list of tools, equipment and appliances required for the different phases of 
concrete road construction is given below 
 Three wheeled or vibratory roller for compaction purpose 
 Shovels, spades and Sieving screens 
 Concrete mixer for mixing of concrete 
 Formwork and iron stakes 
 Watering devices - Water Lorries, water carriers or watering cans 
 Wooden hand tampers for concrete compaction 
 Cycle pump/pneumatic air blower for cleaning of joint 
 Mild steel sections and blocks for making joint grooves for finishing purpose
Site Preparation 
Before construction begins, the construction site must be carefully prepared, This 
includes preparing the grade or road base, sub grade and sub base- 
 First the site is graded to cut high points and fill low areas to the desired roadway 
profile elevations. 
 Generally, cut material can be used as embankment fill. 
 A course of material is placed on the sub grade to provide drainage and stability. 
 A course of fairly rigid material, sometimes cement- or asphalt-treated, that is 
placed on the sub base to provide a stable platform for the concrete pavement slab.
Construction Process 
After site preparation, Construction process consists of various steps, which are 
described below- 
FORM WORK 
Wooden sheets, battens, plywood, fibre hard board, steel plates, angles, rope etc are 
generally use for form work. 
 before using form work, it should free from all type material like as dust ,cement. 
 To placing the concrete in appropriate depth used 2.5-5cm thick and 3mtr long wooden 
sheeting 
 The depth of wooden block must be same as level of slab thick. 
 After 24hrs, form work displaced next length 
of road.
Watering of base 
If the base of the road is dry or construction is taken place during summer seasons 
Then watering is done using the sprinkling process, after this concrete should be 
Placed. 
Construction of Joints 
• There are three basic joint types used in concrete pavement: contraction, 
construction and isolation. 
• Except for some isolation joints, all joints provide a means to mechanically connect 
slabs. The connection helps to spread a load applied on one slab onto slabs along its 
perimeter. 
• Where it is necessary to provide transverse and Longitudinal joints; there wedge of 
woods, metals fix on level of concrete. 
• After setting of concrete it should be pull out.
EFFECT OF DOWEL BARS ON CONCRETE PAVEMENT 
Fig.-1 Fig.-2 
MATERIAL MIXING AND PLACING OF CONCRETE 
Mixer is equipment that mix the concrete using distinct amount of cement , concrete, 
sand and water. There are two type of mixer generally used during construction, 
Batch mixer- used for small road construction 
Continuous mixer- used for large construction . 
 If distance is more from site , mix concrete transported at site within setting time.
PLACING OF CONCRETE 
Two methods generally used in placing of concrete- 
1- Alternate bay method- 
Placed the concrete on both side of road alternatively like as1,3,5… part at one side 
and 2,4,6… part other side, This method have slow process due to road traffic 
problems. 
2- Continuous bay method- 
Construct one side of road regularly, and after construction of some part of first side 
than construct other side, this method have fast process without no obstruction of 
traffic
COMPACTION OF CONCRETE 
Purpose of compaction is that to pull out air from void and make concrete harden. 
Compaction done by- 
1.Mechanically surface vibrator 
2. Manually hand tempers 
 After this, Floating, Belting, Screeding or strike off, Bull floating and Brooming is 
done as per requirement for the finishing purpose of concrete pavement to smoothen 
the top surface. 
CURING 
After completion of the finishing operations, the surface of the pavement shall be 
entirely covered with wet hessian cloth, burlap or jute mats 
Curing is the process of increasing the hydration of cement, after setting the concrete 
curing process done till 14-28days.
OPENING OF THE TRAFFIC 
Generally after a month, road should be open to traffic, but If we used rapid 
hardening cement it take 7 days to open traffic. 
Advantages of Concrete Road 
• Durability and maintenance free life 
• Vehicles consume less fuel 
• Resistant to automobile fuel spillage and extreme weather 
• Greener process 
• Saving of natural resources 
• Eco friendly process
CONSTRUCTION OF CEMENT CONCRETE ROAD

More Related Content

What's hot

Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavements
pradip dangar
 
highway development in india
highway development in indiahighway development in india
highway development in india
Prathi Baa
 
Highway planning
Highway planningHighway planning
Highway planning
AKANSHA GURELE
 
BITUMINOUS ROAD PPT
BITUMINOUS ROAD PPTBITUMINOUS ROAD PPT
BITUMINOUS ROAD PPT
shubham paliwal
 
Construction of flexible pavement
Construction of flexible pavementConstruction of flexible pavement
Construction of flexible pavement
UTU Dehradun
 
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESHPRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
Imrul Quesh
 
Pavement ppt
Pavement pptPavement ppt
Pavement ppt
Harsha Singh
 
CONSTRUCTION OF ROADS
CONSTRUCTION OF ROADSCONSTRUCTION OF ROADS
CONSTRUCTION OF ROADS
reemajadwani
 
Internship report on rcc road
Internship report on rcc roadInternship report on rcc road
Internship report on rcc road
deepak athwal
 
Highway Materials Unit-III
Highway Materials  Unit-IIIHighway Materials  Unit-III
Highway Materials Unit-III
GAURAV. H .TANDON
 
ppt on pavement design
ppt on pavement designppt on pavement design
ppt on pavement design
Rohit Ranjan
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
pjainrahul
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road construction
Anitha Jacob
 
Highway drainage
Highway drainageHighway drainage
Highway drainage
Aglaia Connect
 
PQC concrete road
PQC concrete roadPQC concrete road
PQC concrete road
pramodchavan32
 
Well foundation
Well foundationWell foundation
Bituminous Road
 Bituminous Road Bituminous Road
Bituminous Road
shubham paliwal
 
Importance of highway maintenance
Importance of highway maintenanceImportance of highway maintenance
Importance of highway maintenance
Dharmesh Vadher
 
1 st 20 year road plan
1 st 20 year road plan1 st 20 year road plan
1 st 20 year road plan
12cl0viren
 
SUMMER TRAINING FROM PWD
SUMMER TRAINING FROM PWDSUMMER TRAINING FROM PWD
SUMMER TRAINING FROM PWD
Ratnesh Kushwaha
 

What's hot (20)

Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavements
 
highway development in india
highway development in indiahighway development in india
highway development in india
 
Highway planning
Highway planningHighway planning
Highway planning
 
BITUMINOUS ROAD PPT
BITUMINOUS ROAD PPTBITUMINOUS ROAD PPT
BITUMINOUS ROAD PPT
 
Construction of flexible pavement
Construction of flexible pavementConstruction of flexible pavement
Construction of flexible pavement
 
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESHPRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
 
Pavement ppt
Pavement pptPavement ppt
Pavement ppt
 
CONSTRUCTION OF ROADS
CONSTRUCTION OF ROADSCONSTRUCTION OF ROADS
CONSTRUCTION OF ROADS
 
Internship report on rcc road
Internship report on rcc roadInternship report on rcc road
Internship report on rcc road
 
Highway Materials Unit-III
Highway Materials  Unit-IIIHighway Materials  Unit-III
Highway Materials Unit-III
 
ppt on pavement design
ppt on pavement designppt on pavement design
ppt on pavement design
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road construction
 
Highway drainage
Highway drainageHighway drainage
Highway drainage
 
PQC concrete road
PQC concrete roadPQC concrete road
PQC concrete road
 
Well foundation
Well foundationWell foundation
Well foundation
 
Bituminous Road
 Bituminous Road Bituminous Road
Bituminous Road
 
Importance of highway maintenance
Importance of highway maintenanceImportance of highway maintenance
Importance of highway maintenance
 
1 st 20 year road plan
1 st 20 year road plan1 st 20 year road plan
1 st 20 year road plan
 
SUMMER TRAINING FROM PWD
SUMMER TRAINING FROM PWDSUMMER TRAINING FROM PWD
SUMMER TRAINING FROM PWD
 

Viewers also liked

cement road construction in the rural areas
cement road construction in the rural areas cement road construction in the rural areas
cement road construction in the rural areas
Anshul Shakya
 
Design and construction of concrete roads
Design and construction of concrete roadsDesign and construction of concrete roads
Design and construction of concrete roadsOlukayode Alao
 
Mukesh ppt cc road
Mukesh ppt cc roadMukesh ppt cc road
Mukesh ppt cc road
HJ Sims
 
Rigid Pavement Design Part II
Rigid Pavement Design Part IIRigid Pavement Design Part II
Rigid Pavement Design Part II
Sachin Kulkarni
 
Exercise Physiology
Exercise PhysiologyExercise Physiology
Exercise Physiology
Wbuhs
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of building
ARUN KUMAR
 
Road Construction
Road ConstructionRoad Construction
Road Construction
Danish Mohd
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-Presented
SlideShare
 

Viewers also liked (8)

cement road construction in the rural areas
cement road construction in the rural areas cement road construction in the rural areas
cement road construction in the rural areas
 
Design and construction of concrete roads
Design and construction of concrete roadsDesign and construction of concrete roads
Design and construction of concrete roads
 
Mukesh ppt cc road
Mukesh ppt cc roadMukesh ppt cc road
Mukesh ppt cc road
 
Rigid Pavement Design Part II
Rigid Pavement Design Part IIRigid Pavement Design Part II
Rigid Pavement Design Part II
 
Exercise Physiology
Exercise PhysiologyExercise Physiology
Exercise Physiology
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of building
 
Road Construction
Road ConstructionRoad Construction
Road Construction
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-Presented
 

Similar to CONSTRUCTION OF CEMENT CONCRETE ROAD

Aryan k tranning file road ppt 07
Aryan k tranning file road ppt 07Aryan k tranning file road ppt 07
Aryan k tranning file road ppt 07
aryan kumar
 
Construction of Road
Construction of RoadConstruction of Road
Construction of Road
Aman Shakya
 
Highway report
Highway reportHighway report
Highway report
Priyank Lakhani
 
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
Anil Gupta
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
DanielWisman1
 
Anshuman.pptx
Anshuman.pptxAnshuman.pptx
Anshuman.pptx
Devanshumangal1
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
chiranjeevulu chinthala
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
JaySinghchib1
 
Road construction ppt for college rajkiya presentation
Road construction ppt for college rajkiya presentationRoad construction ppt for college rajkiya presentation
Road construction ppt for college rajkiya presentation
mahesh515545
 
Highway construction and equipments
Highway construction and equipmentsHighway construction and equipments
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
pjainrahul
 
PRESENTATION ON RIGID PAVEMExNT.pptx for
PRESENTATION ON RIGID PAVEMExNT.pptx forPRESENTATION ON RIGID PAVEMExNT.pptx for
PRESENTATION ON RIGID PAVEMExNT.pptx for
Vishalshukla347388
 
Gangaram yadav ppt road con....
Gangaram yadav ppt road con....Gangaram yadav ppt road con....
Gangaram yadav ppt road con....
RaazYadav6
 
Industrial training abhi edited.pdf
Industrial training abhi edited.pdfIndustrial training abhi edited.pdf
Industrial training abhi edited.pdf
Abhi858562
 
highway materials and desihn.pptx
highway materials and desihn.pptxhighway materials and desihn.pptx
highway materials and desihn.pptx
SekharJ4
 
337276998-project-report-on-pavement-design.pptx
337276998-project-report-on-pavement-design.pptx337276998-project-report-on-pavement-design.pptx
337276998-project-report-on-pavement-design.pptx
sakibhussain036
 
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESProject:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Malay Talaviya
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
pradip dangar
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 

Similar to CONSTRUCTION OF CEMENT CONCRETE ROAD (20)

Aryan k tranning file road ppt 07
Aryan k tranning file road ppt 07Aryan k tranning file road ppt 07
Aryan k tranning file road ppt 07
 
Construction of Road
Construction of RoadConstruction of Road
Construction of Road
 
Highway report
Highway reportHighway report
Highway report
 
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
 
Anshuman.pptx
Anshuman.pptxAnshuman.pptx
Anshuman.pptx
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Road construction ppt for college rajkiya presentation
Road construction ppt for college rajkiya presentationRoad construction ppt for college rajkiya presentation
Road construction ppt for college rajkiya presentation
 
Highway construction and equipments
Highway construction and equipmentsHighway construction and equipments
Highway construction and equipments
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
PRESENTATION ON RIGID PAVEMExNT.pptx for
PRESENTATION ON RIGID PAVEMExNT.pptx forPRESENTATION ON RIGID PAVEMExNT.pptx for
PRESENTATION ON RIGID PAVEMExNT.pptx for
 
Gangaram yadav ppt road con....
Gangaram yadav ppt road con....Gangaram yadav ppt road con....
Gangaram yadav ppt road con....
 
Industrial training abhi edited.pdf
Industrial training abhi edited.pdfIndustrial training abhi edited.pdf
Industrial training abhi edited.pdf
 
highway materials and desihn.pptx
highway materials and desihn.pptxhighway materials and desihn.pptx
highway materials and desihn.pptx
 
337276998-project-report-on-pavement-design.pptx
337276998-project-report-on-pavement-design.pptx337276998-project-report-on-pavement-design.pptx
337276998-project-report-on-pavement-design.pptx
 
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESProject:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 

More from GLA University

DELHI-AGRA ROAD PROJECT
DELHI-AGRA ROAD PROJECTDELHI-AGRA ROAD PROJECT
DELHI-AGRA ROAD PROJECT
GLA University
 
SEWAGE TREATMENT PLANT,LUCKNOW
SEWAGE TREATMENT PLANT,LUCKNOWSEWAGE TREATMENT PLANT,LUCKNOW
SEWAGE TREATMENT PLANT,LUCKNOW
GLA University
 
ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE & NON DESTRUCTIVE TE...
ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE &  NON DESTRUCTIVE TE...ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE &  NON DESTRUCTIVE TE...
ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE & NON DESTRUCTIVE TE...
GLA University
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTION
GLA University
 
ROMDAS
ROMDASROMDAS
self compacting concrete
self compacting concreteself compacting concrete
self compacting concrete
GLA University
 

More from GLA University (7)

DELHI-AGRA ROAD PROJECT
DELHI-AGRA ROAD PROJECTDELHI-AGRA ROAD PROJECT
DELHI-AGRA ROAD PROJECT
 
SEWAGE TREATMENT PLANT,LUCKNOW
SEWAGE TREATMENT PLANT,LUCKNOWSEWAGE TREATMENT PLANT,LUCKNOW
SEWAGE TREATMENT PLANT,LUCKNOW
 
ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE & NON DESTRUCTIVE TE...
ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE &  NON DESTRUCTIVE TE...ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE &  NON DESTRUCTIVE TE...
ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE & NON DESTRUCTIVE TE...
 
Dishant ppt
Dishant pptDishant ppt
Dishant ppt
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTION
 
ROMDAS
ROMDASROMDAS
ROMDAS
 
self compacting concrete
self compacting concreteself compacting concrete
self compacting concrete
 

Recently uploaded

COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 

Recently uploaded (20)

COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 

CONSTRUCTION OF CEMENT CONCRETE ROAD

  • 1. SUBMITTED BY-RAVI GUPTA B.TECH(CIVIL ENGG.) ROLL NO.- 111000125
  • 2. PUBLIC WORKS DEPARTMENT-AN OVERVIEW  Public Works Department (PWD), under the Ministry of Public Works department, is the pioneer in construction arena of Uttar Pradesh.  It plays a pivotal role in the implementation of government construction projects  To accelerate the construction of bridges in the state, Uttar Pradesh State Bridge Corporation was founded in 1973.  In year 2004-05, Uttar Pradesh state highways authority was established to overcome with problem of pavements in state.
  • 3. INTRODUCTION  Development of a country depends on the connectivity of various places with adequate road network.  Roads constitute the most important mode of communication in areas where railways have not developed much.  India has one of the largest road networks in the world (over 3 million km at present).For the purpose of management and administration, roads in India are divided into the following five categories: • National Highways (NH) • State Highways (SH) • Major District Roads (MDR) • Other District Roads (ODR) • Village Roads (VR)
  • 4. Fig. Showing status of Road Network In India Position of India In World Road Network
  • 5. WHAT IS ROAD AND PAVEMENT ?  Road is an open, generally public way for the passage of vehicles, people, and animals.  Pavement is finished with a hard smooth surface. It helped make them durable and able to withstand traffic and the environment. They have a life span of between 20 – 30 years. FUNCTIONS One of the primary functions of pavement is load distribution. It can be characterized by the tire loads, tire configurations, repetition of loads, and distribution of traffic across the pavement, and vehicle speed
  • 6. TYPES OF PAVEMENTS There are various types of pavements depending upon the materials used; a briefs description of all types is given here- FLEXIBLE PAVEMENT Bitumen has been widely used in the construction of flexible pavements for a long time. This is the most convenient and simple type of construction. The cost of construction of single lane bituminous pavement varies from 20 to 30 lakhs per km in plain area. Flexible pavement have-  Have low flexural strength  Load is transferred by grain to grain contact  Have low completion cost but repairing cost is high  Have low life span (High Maintenance Cost)
  • 7. RIGID PAVEMENT Rigid pavements, though costly in initial investment, are cheap in long run because of low maintenance costs, The cost of construction of single lane rigid pavement varies from 35 to 50 lakhs per km in plain area, Rigid pavement have- Deformation in the sub grade is not transferred to subsequent layers Design is based on flexural strength or slab action Have high flexural strength No such phenomenon of grain to grain load transfer exists Have low repairing cost but completion cost is high Life span is more as compare to flexible (Low Maintenance Cost)
  • 8. Difference b/w Flexible and Rigid Pavement in terms of load distribution In different layers Different layers in Flexible and Rigid Pavement
  • 9. Basic Components of a Concrete Longitudinal joint Transverse joint Surface Texture Subgrade Base Surface smoothness Thickness Design Concrete materials Dowel bars Tiebars Pavement
  • 10. Types of Rigid Pavements  Jointed Plain Concrete Pavement (JPCP) – does not use any reinforcing steel  Jointed Reinforced Concrete Pavement (JRCP) – Reinforcing steel placed at mid height and discontinued at the joints.  Continuously Reinforced Concrete Pavement (CRCP) – This method is very costly and generally not used in India.  Pre-stressed Concrete Pavement (PCP) – Comprises new and innovative construction methods – Precast pavement components are fabricated and installed on a prepared foundation (existing pavement or re-graded foundation).
  • 11. MINERALS USED Cement  Ordinary Portland cement (OPC) Ordinary Portland cement and High Strength Ordinary Portland Cement are most widely used for concrete pavements.  Rapid hardening Portland cement In general, this cement would be used only where time is a critical factor and the road is required to be opened to traffic at an earlier date than would be possible if Ordinary Portland Cement or High Strength Ordinary Portland Cement is used.
  • 12. Mineral used( cont.) Aggregates • There are two types of Aggregates are used during construction of road i.e. Fine and Coarse Aggregate depending on requirements. • Maximum size of aggregate should not exceed 1/4th of the pavement slab thickness. Water • Water used in mixing or curing of concrete shall be clean and free from injurious amounts of oil, salt, acid, vegetable matter or other substances harmful to the finished concrete. • Potable waters are generally considered satisfactory for mixing or curing.
  • 13. Equipments used A list of tools, equipment and appliances required for the different phases of concrete road construction is given below  Three wheeled or vibratory roller for compaction purpose  Shovels, spades and Sieving screens  Concrete mixer for mixing of concrete  Formwork and iron stakes  Watering devices - Water Lorries, water carriers or watering cans  Wooden hand tampers for concrete compaction  Cycle pump/pneumatic air blower for cleaning of joint  Mild steel sections and blocks for making joint grooves for finishing purpose
  • 14. Site Preparation Before construction begins, the construction site must be carefully prepared, This includes preparing the grade or road base, sub grade and sub base-  First the site is graded to cut high points and fill low areas to the desired roadway profile elevations.  Generally, cut material can be used as embankment fill.  A course of material is placed on the sub grade to provide drainage and stability.  A course of fairly rigid material, sometimes cement- or asphalt-treated, that is placed on the sub base to provide a stable platform for the concrete pavement slab.
  • 15. Construction Process After site preparation, Construction process consists of various steps, which are described below- FORM WORK Wooden sheets, battens, plywood, fibre hard board, steel plates, angles, rope etc are generally use for form work.  before using form work, it should free from all type material like as dust ,cement.  To placing the concrete in appropriate depth used 2.5-5cm thick and 3mtr long wooden sheeting  The depth of wooden block must be same as level of slab thick.  After 24hrs, form work displaced next length of road.
  • 16. Watering of base If the base of the road is dry or construction is taken place during summer seasons Then watering is done using the sprinkling process, after this concrete should be Placed. Construction of Joints • There are three basic joint types used in concrete pavement: contraction, construction and isolation. • Except for some isolation joints, all joints provide a means to mechanically connect slabs. The connection helps to spread a load applied on one slab onto slabs along its perimeter. • Where it is necessary to provide transverse and Longitudinal joints; there wedge of woods, metals fix on level of concrete. • After setting of concrete it should be pull out.
  • 17. EFFECT OF DOWEL BARS ON CONCRETE PAVEMENT Fig.-1 Fig.-2 MATERIAL MIXING AND PLACING OF CONCRETE Mixer is equipment that mix the concrete using distinct amount of cement , concrete, sand and water. There are two type of mixer generally used during construction, Batch mixer- used for small road construction Continuous mixer- used for large construction .  If distance is more from site , mix concrete transported at site within setting time.
  • 18. PLACING OF CONCRETE Two methods generally used in placing of concrete- 1- Alternate bay method- Placed the concrete on both side of road alternatively like as1,3,5… part at one side and 2,4,6… part other side, This method have slow process due to road traffic problems. 2- Continuous bay method- Construct one side of road regularly, and after construction of some part of first side than construct other side, this method have fast process without no obstruction of traffic
  • 19. COMPACTION OF CONCRETE Purpose of compaction is that to pull out air from void and make concrete harden. Compaction done by- 1.Mechanically surface vibrator 2. Manually hand tempers  After this, Floating, Belting, Screeding or strike off, Bull floating and Brooming is done as per requirement for the finishing purpose of concrete pavement to smoothen the top surface. CURING After completion of the finishing operations, the surface of the pavement shall be entirely covered with wet hessian cloth, burlap or jute mats Curing is the process of increasing the hydration of cement, after setting the concrete curing process done till 14-28days.
  • 20. OPENING OF THE TRAFFIC Generally after a month, road should be open to traffic, but If we used rapid hardening cement it take 7 days to open traffic. Advantages of Concrete Road • Durability and maintenance free life • Vehicles consume less fuel • Resistant to automobile fuel spillage and extreme weather • Greener process • Saving of natural resources • Eco friendly process