SlideShare a Scribd company logo
• Terminology used in estimating and costing
Estimating, Costing and Valuation
Prepared by:
Janak Mehta
Assistant Professor
Civil Engineering Department
Diwaliba Polytechnic, Mahuva.
Contents
• Taking off in quantity surveying
• Provisional sums
• Prime cost
• Provisional quantities
• Spot items
• Day work
• Contingencies
• Work charged establishment charges
• Water charges
• Overhead charges
Taking off in quantity surveying
• This is the process of finding out the quantities for various items of works
involved in a project by taking off various dimensions from the plan,
sections of the drawings and tabulating in a measurement seat.
• The measurement sheet contains following columns like description,
number, length, breadth, thickness/height and quantity.
Provisional sums
• While preparing the estimate some amount is provided in it for items
whose details regarding cost or specifications are unknown during the
preparation. for such items, a reasonable amount is provided in the estimate
and in the bill of quantities, known as provisional sum.
• For example the cost and specifications for a lift may be unknown during
estimation for the building. Such amounts are known as provisional sum.
However the payments for these provisional items are done as per actual
rate.
Prime cost
• Prime cost is the purchase cost of articles at a shop. Prime cost is generally
referred to the supply of a particular article and not for carrying out a work.
The prime cost includes the Estimation and Professional Practices cost for
carriage but excludes the cost of fixing or fitting.
• For example: the door and window fittings are purchased from the shop at
a cost of Rs 1000.00. The transportation cost is Rs.50.00 and the cost for
fixing and fitting is Rs.100.00. Then the prime costs of the fittings are Rs.
1050.00.
Provisional quantities
• During preparation of an estimate if it is apprehended that additional
quantities against some items may be required due to variation of site
conditions, then those quantities are estimated separately from the
dimensions of the drawing and kept separately in the estimate under a
heading Provisional Quantities.
Spot items
• There are certain items for which it is not possible for the estimator to fix
an amount without seeing and studying them in detail. Such items are
known as spot items.
• The estimate of such items can be prepared only after inspection and taking
detailed measurements at site.
• Examples
▫ Demolishing existing structures
▫ Constructing openings in the existing wall
▫ Clearing the site
▫ Connecting an old building to a new building, etc.
• The estimator should give detail and precise description of the spot items
so that the contractor can put up a more accurate price for such items.
Day work
• During execution of a project there may be certain type of works, for which
the actual quantities of labour required is difficult to measure.
• For example fine architectural works, and drawings in the wall. The
payments towards such items are made on the basis of actual number of
days or actual quantity of materials required. Such works are known as day
works.
• The day work is adopted for certain complicated items of work which can
not be measured as a design in the plaster work, front architectural finish of
a building, work under water, ornamental door etc. are valued and paid by
day work.
• If a considerable amount of day work is involved, it is a general practice to
include a schedule of materials and labours in the tender form.
• It should be clear mentioned in the specification that the day work prices
quoted by the contractor should include the following:
▫ Cost of transport of material at site
▫ Contractor’s supervision
▫ Contractor’s profit
▫ Contractor’s overhead charges
▫ Use of contractor’s equipment
• The day work should not be commenced till the necessary sanction has
been obtained form the engineer appointed by the owner. The contractor
should start the work after giving necessary notice to the engineer so that a
close match can be maintained on the work.
Contingencies
• There are certain expenses which are incidental in nature and it is not
possible to predict them with reasonable accuracy. To cater all such
expenses an additional amount of 3% to 5% of estimated cost is provided
in the total estimate.
• For example, suppose there is an item in an estimate for cement plastering
1:4 with neat cement finish, but during execution, it is desired to provide
nosing at the end of steps, as there is no allocation of funds for this small
work, the cost of such work may be met up from the contingency fund. But
in case an expenditure is necessary due to change of design fund,
supplementary or revised estimates are submitted for its sanction before
taking up the work.
• If there is any saving against the amount provided under contingencies, this
amount may be utilized with the sanction of the component authority, to
meet the expenses of extra items of work.
• The provision for contingencies may not be diverted to any new work or
repair which is not provided in the estimate and of which cost exceeds
Rs.2000/- without the sanction of superintending engineer.
Work charged establishment charges
• During the construction of a project considerable number of skilled
supervisors, work assistance, watch men etc., are employed on temporary
basis. The salaries of these persons are drawn from the L.S. amount allotted
towards the work charged establishment.
• For such work charged establishment an amount of 2 to 2.5% (accordingly
to the practice of P.W.D) of the estimated cost of works is provided in the
estimate.
• Generally work charged persons are employed on monthly basis or
temporary basis according to the progress of the work. Their services last
for the sanctioned period but may be continued on fresh sanction. Their
services are terminable by one month’s notice for one year continuous
service. But for less than one year service 14 days notice is required to
terminate their services.
Water charges
• For drinking purpose of the workers and for the work, arrangement of
water either by sinking tube-well or by taking temporary water connection
from the corporation or municipality becomes necessary.
• In order to meet up the expenses an amount of 1 % 1.5% of the total cost of
material and labour has been provided in the analysis of rate.
Overhead charges
• Overhead charges include general office expenses, rents, taxes, salaries of
office staff, and other costs which are indirect expenses and not productive
expenses on the job.
• General overheads:
▫ Establishment (office staff)
▫ Stationary, printing
▫ Postage
▫ Travelling expenses
▫ Telephone
▫ Rent
▫ Taxes
▫ Electrical bills, etc.
• Job overheads:
▫ Salary of engineers, supervisors
▫ Handling of material
▫ Repair, carriage and depreciation of tools and plants (T&P)
▫ Amenities of labour
▫ Workmen’s compensation , insurance, etc
▫ Interest on investment
▫ Lighting at site
▫ Public relations
▫ Theft, etc.

More Related Content

What's hot

estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methodsgayu pandian
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimationDhavalMithaiwala
 
Prefabrication in construction
Prefabrication in constructionPrefabrication in construction
Prefabrication in constructionShailja km
 
Working Drawing Building Layout Architectural
Working Drawing Building Layout ArchitecturalWorking Drawing Building Layout Architectural
Working Drawing Building Layout ArchitecturalRAMPRASAD KUMAWAT
 
modular coordination
modular coordinationmodular coordination
modular coordinationShailja km
 
Roof structures and Types of roofs
Roof structures and Types of roofsRoof structures and Types of roofs
Roof structures and Types of roofsAbhishek kumar
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing Vijay325
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONAr Naveen Naveen
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line methodmalang1214
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete constructionJenilPatel22
 

What's hot (20)

Superstructure construction
Superstructure constructionSuperstructure construction
Superstructure construction
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
Prefabrication in construction
Prefabrication in constructionPrefabrication in construction
Prefabrication in construction
 
Working Drawing Building Layout Architectural
Working Drawing Building Layout ArchitecturalWorking Drawing Building Layout Architectural
Working Drawing Building Layout Architectural
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 
modular coordination
modular coordinationmodular coordination
modular coordination
 
Roof structures and Types of roofs
Roof structures and Types of roofsRoof structures and Types of roofs
Roof structures and Types of roofs
 
Formwork
FormworkFormwork
Formwork
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
 
Earthwork
EarthworkEarthwork
Earthwork
 
Estimation
EstimationEstimation
Estimation
 
Foundation types
Foundation typesFoundation types
Foundation types
 

Similar to Terminology used in estimating and costing

Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsmeghajain275
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfsuchitamantry2002
 
EEEC pdf.pdf
EEEC pdf.pdfEEEC pdf.pdf
EEEC pdf.pdfBSuresh26
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costingPrasad Manerikar
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial buildinglckr117
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Padmasinh Patil
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costingAyushHajare
 
Charging of Engineering Services.pptx
Charging of Engineering Services.pptxCharging of Engineering Services.pptx
Charging of Engineering Services.pptxLovelynCosicol
 
Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Padmasinh Patil
 
How to Navigate the Commissioning Process From Planning to Post-Constructi...
How to Navigate the Commissioning Process    From Planning to Post-Constructi...How to Navigate the Commissioning Process    From Planning to Post-Constructi...
How to Navigate the Commissioning Process From Planning to Post-Constructi...Olivia Wilson
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdfDeepak37004
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 
2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptxRaniVishwakarma15
 
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxCCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxMariaNambahu
 
9-180307064518 (1).pptx
9-180307064518 (1).pptx9-180307064518 (1).pptx
9-180307064518 (1).pptxRenvic
 

Similar to Terminology used in estimating and costing (20)

Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic terms
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdf
 
EEEC pdf.pdf
EEEC pdf.pdfEEEC pdf.pdf
EEEC pdf.pdf
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costing
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
 
Charging of Engineering Services.pptx
Charging of Engineering Services.pptxCharging of Engineering Services.pptx
Charging of Engineering Services.pptx
 
Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6
 
How to Navigate the Commissioning Process From Planning to Post-Constructi...
How to Navigate the Commissioning Process    From Planning to Post-Constructi...How to Navigate the Commissioning Process    From Planning to Post-Constructi...
How to Navigate the Commissioning Process From Planning to Post-Constructi...
 
CPM 1 .pdf
CPM 1 .pdfCPM 1 .pdf
CPM 1 .pdf
 
Ppt chapter1
Ppt chapter1Ppt chapter1
Ppt chapter1
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdf
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
 
Pmc hitesh
Pmc hiteshPmc hitesh
Pmc hitesh
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx
 
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxCCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
 
9-180307064518 (1).pptx
9-180307064518 (1).pptx9-180307064518 (1).pptx
9-180307064518 (1).pptx
 
Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
 

Recently uploaded

Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringC Sai Kiran
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringC Sai Kiran
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfPipe Restoration Solutions
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdfKamal Acharya
 
retail automation billing system ppt.pptx
retail automation billing system ppt.pptxretail automation billing system ppt.pptx
retail automation billing system ppt.pptxfaamieahmd
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxMd. Shahidul Islam Prodhan
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGKOUSTAV SARKAR
 
Explosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdfExplosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdf884710SadaqatAli
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...Amil baba
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientistgettygaming1
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdfKamal Acharya
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edgePaco Orozco
 
Introduction to Casting Processes in Manufacturing
Introduction to Casting Processes in ManufacturingIntroduction to Casting Processes in Manufacturing
Introduction to Casting Processes in Manufacturingssuser0811ec
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfKamal Acharya
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfKamal Acharya
 
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringKIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringDr. Radhey Shyam
 
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data StreamKIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data StreamDr. Radhey Shyam
 
shape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxshape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxVishalDeshpande27
 
Furniture showroom management system project.pdf
Furniture showroom management system project.pdfFurniture showroom management system project.pdf
Furniture showroom management system project.pdfKamal Acharya
 

Recently uploaded (20)

Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
retail automation billing system ppt.pptx
retail automation billing system ppt.pptxretail automation billing system ppt.pptx
retail automation billing system ppt.pptx
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
 
Explosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdfExplosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdf
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
Introduction to Casting Processes in Manufacturing
Introduction to Casting Processes in ManufacturingIntroduction to Casting Processes in Manufacturing
Introduction to Casting Processes in Manufacturing
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringKIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
 
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data StreamKIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
 
shape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxshape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptx
 
Furniture showroom management system project.pdf
Furniture showroom management system project.pdfFurniture showroom management system project.pdf
Furniture showroom management system project.pdf
 

Terminology used in estimating and costing

  • 1. • Terminology used in estimating and costing Estimating, Costing and Valuation Prepared by: Janak Mehta Assistant Professor Civil Engineering Department Diwaliba Polytechnic, Mahuva.
  • 2. Contents • Taking off in quantity surveying • Provisional sums • Prime cost • Provisional quantities • Spot items • Day work • Contingencies • Work charged establishment charges • Water charges • Overhead charges
  • 3. Taking off in quantity surveying • This is the process of finding out the quantities for various items of works involved in a project by taking off various dimensions from the plan, sections of the drawings and tabulating in a measurement seat. • The measurement sheet contains following columns like description, number, length, breadth, thickness/height and quantity.
  • 4. Provisional sums • While preparing the estimate some amount is provided in it for items whose details regarding cost or specifications are unknown during the preparation. for such items, a reasonable amount is provided in the estimate and in the bill of quantities, known as provisional sum. • For example the cost and specifications for a lift may be unknown during estimation for the building. Such amounts are known as provisional sum. However the payments for these provisional items are done as per actual rate.
  • 5. Prime cost • Prime cost is the purchase cost of articles at a shop. Prime cost is generally referred to the supply of a particular article and not for carrying out a work. The prime cost includes the Estimation and Professional Practices cost for carriage but excludes the cost of fixing or fitting. • For example: the door and window fittings are purchased from the shop at a cost of Rs 1000.00. The transportation cost is Rs.50.00 and the cost for fixing and fitting is Rs.100.00. Then the prime costs of the fittings are Rs. 1050.00.
  • 6. Provisional quantities • During preparation of an estimate if it is apprehended that additional quantities against some items may be required due to variation of site conditions, then those quantities are estimated separately from the dimensions of the drawing and kept separately in the estimate under a heading Provisional Quantities.
  • 7. Spot items • There are certain items for which it is not possible for the estimator to fix an amount without seeing and studying them in detail. Such items are known as spot items. • The estimate of such items can be prepared only after inspection and taking detailed measurements at site. • Examples ▫ Demolishing existing structures ▫ Constructing openings in the existing wall ▫ Clearing the site ▫ Connecting an old building to a new building, etc. • The estimator should give detail and precise description of the spot items so that the contractor can put up a more accurate price for such items.
  • 8. Day work • During execution of a project there may be certain type of works, for which the actual quantities of labour required is difficult to measure. • For example fine architectural works, and drawings in the wall. The payments towards such items are made on the basis of actual number of days or actual quantity of materials required. Such works are known as day works. • The day work is adopted for certain complicated items of work which can not be measured as a design in the plaster work, front architectural finish of a building, work under water, ornamental door etc. are valued and paid by day work.
  • 9. • If a considerable amount of day work is involved, it is a general practice to include a schedule of materials and labours in the tender form. • It should be clear mentioned in the specification that the day work prices quoted by the contractor should include the following: ▫ Cost of transport of material at site ▫ Contractor’s supervision ▫ Contractor’s profit ▫ Contractor’s overhead charges ▫ Use of contractor’s equipment • The day work should not be commenced till the necessary sanction has been obtained form the engineer appointed by the owner. The contractor should start the work after giving necessary notice to the engineer so that a close match can be maintained on the work.
  • 10. Contingencies • There are certain expenses which are incidental in nature and it is not possible to predict them with reasonable accuracy. To cater all such expenses an additional amount of 3% to 5% of estimated cost is provided in the total estimate. • For example, suppose there is an item in an estimate for cement plastering 1:4 with neat cement finish, but during execution, it is desired to provide nosing at the end of steps, as there is no allocation of funds for this small work, the cost of such work may be met up from the contingency fund. But in case an expenditure is necessary due to change of design fund, supplementary or revised estimates are submitted for its sanction before taking up the work.
  • 11. • If there is any saving against the amount provided under contingencies, this amount may be utilized with the sanction of the component authority, to meet the expenses of extra items of work. • The provision for contingencies may not be diverted to any new work or repair which is not provided in the estimate and of which cost exceeds Rs.2000/- without the sanction of superintending engineer.
  • 12. Work charged establishment charges • During the construction of a project considerable number of skilled supervisors, work assistance, watch men etc., are employed on temporary basis. The salaries of these persons are drawn from the L.S. amount allotted towards the work charged establishment. • For such work charged establishment an amount of 2 to 2.5% (accordingly to the practice of P.W.D) of the estimated cost of works is provided in the estimate. • Generally work charged persons are employed on monthly basis or temporary basis according to the progress of the work. Their services last for the sanctioned period but may be continued on fresh sanction. Their services are terminable by one month’s notice for one year continuous service. But for less than one year service 14 days notice is required to terminate their services.
  • 13. Water charges • For drinking purpose of the workers and for the work, arrangement of water either by sinking tube-well or by taking temporary water connection from the corporation or municipality becomes necessary. • In order to meet up the expenses an amount of 1 % 1.5% of the total cost of material and labour has been provided in the analysis of rate.
  • 14. Overhead charges • Overhead charges include general office expenses, rents, taxes, salaries of office staff, and other costs which are indirect expenses and not productive expenses on the job. • General overheads: ▫ Establishment (office staff) ▫ Stationary, printing ▫ Postage ▫ Travelling expenses ▫ Telephone ▫ Rent ▫ Taxes ▫ Electrical bills, etc.
  • 15. • Job overheads: ▫ Salary of engineers, supervisors ▫ Handling of material ▫ Repair, carriage and depreciation of tools and plants (T&P) ▫ Amenities of labour ▫ Workmen’s compensation , insurance, etc ▫ Interest on investment ▫ Lighting at site ▫ Public relations ▫ Theft, etc.