SlideShare a Scribd company logo
Course: MBA
Subject: Production & Operation
Management
Unit: 1.4
Process design, analysis and selection
• Process Analysis
• Process Flowcharting
• Types of Processes
• Process Performance Metrics
• Manufacturing Processes
• Service Processes
OBJECTIVES
Process Management
• Processes relate to work that is ongoing and
repetitive
• Process management concepts and methods
can be applied to improve manufacturing,
service, and business processes
• Effort is placed trying to reduce cost, increase
throughput, and improve quality
Process Analysis Terms
• Process: Is any part of an organization that
takes inputs and transforms them into
outputs
• Cycle Time: Is the average successive time
between completions of successive units
• Utilization: Is the ratio of the time that a
resource is actually activated relative to the
time that it is available for use
Process Flowcharting
Defined
• Process flowcharting is the use of a diagram to
present the major elements of a process
• The basic elements can include tasks or
operations, flows of materials or customers,
decision points, and storage areas or queues
• It is an ideal methodology by which to begin
analyzing a process
Tasks or operations
Examples: Giving an
admission ticket to a
customer, installing a
engine in a car, etc.
Examples: Giving an
admission ticket to a
customer, installing a
engine in a car, etc.
Decision Points
Examples: How much
change should be
given to a customer,
which wrench should
be used, etc.
Examples: How much
change should be
given to a customer,
which wrench should
be used, etc.
Purpose and Examples
Flowchart Symbols
Examples: Sheds,
lines of people waiting
for a service, etc.
Examples: Sheds,
lines of people waiting
for a service, etc.
Examples: Customers
moving to a seat,
mechanic getting a
tool, etc.
Examples: Customers
moving to a seat,
mechanic getting a
tool, etc.
Storage areas or
queues
Flows of
materials or
customers
Purpose and Examples
Flowchart Symbols
Types of Processes
Single-stage Process
Stage 1
Stage 1 Stage 2 Stage 3
Multi-stage Process
Types of Processes (Continued)
A buffer refers to a storage area between
stages where the output of a stage is
placed prior to being used in a
downstream stage
Stage 1 Stage 2
Buffer
Multi-stage Process with Buffer
Other Process Terminology
• Blocking
– Occurs when the activities in a stage must stop because
there is no place to deposit the item just completed
– If there is no room for an employee to place a unit of work
down, the employee will hold on to it not able to continue
working on the next unit
• Starving
– Occurs when the activities in a stage must stop because
there is no work
– If an employee is waiting at a work station and no work is
coming to the employee to process, the employee will
remain idle until the next unit of work comes
Other Process Terminology (Continued)
• Bottleneck
– Occurs when the limited capacity of a process
causes work to pile up or become unevenly
distributed in the flow of a process
– If an employee works too slow in a multi-stage
process, work will begin to pile up in front of that
employee. In this is case the employee represents
the limited capacity causing the bottleneck.
• Pacing
– Refers to the fixed timing of the movement of
items through the process
Other Types of Processes
• Make-to-order
– Only activated in response to an actual order
– Both work-in-process and finished goods inventory
kept to a minimum
• Make-to-stock
– Process activated to meet expected or forecast
demand
– Customer orders are served from target stocking
level
Process Performance Metrics
Capacity: maximum output of a
process or resource measured in
units/time: a rate
Operation time = Setup time + Run
time
Setup time: the length of time
required to changeover from one
product to another (assumes
products are produced in batches)
Throughput time = Average time for
a unit to move through the system
Process Performance Metrics (Continued)
• Cycle time = Average time between
completion of units
• Throughput rate = 1___
Cycle time
• Utilization of an operation =
Demand/Capacity
Cycle Time Example
Suppose you had to produce 600 units in 80 hours to
meet the demand requirements of a product. What is
the cycle time to meet this demand requirement?
Suppose you had to produce 600 units in 80 hours to
meet the demand requirements of a product. What is
the cycle time to meet this demand requirement?
Answer: There are 4,800 minutes (60
minutes/hour x 80 hours) in 80 hours. So the
average time between completions would have
to be: Cycle time = 4,800/600 units = 8 minutes.
Answer: There are 4,800 minutes (60
minutes/hour x 80 hours) in 80 hours. So the
average time between completions would have
to be: Cycle time = 4,800/600 units = 8 minutes.
Bread-Making Questions
• What is the bottleneck when one
bread-making line is used? What is the
capacity of the process? What is the
utilization of packaging? What is the
throughput time?
• What happens to capacity and
utilization when two bread-making
lines are used? What is the bottleneck?
Process Throughput Time Reduction
• Perform activities in parallel
• Change the sequence of activities
• Reduce interruptions
Basic work flow structures
Project layout – fixed position; construction,
movie lots
Workcenter (job shop) – similar equipment
grouped together; machine shop
Manufacturing cell – similar set of processes for a
limited range of products
Assembly Line – discrete parts move through
workstations; toys, appliances, cars
Continuous process – flow vs discrete, flows a set
sequence of steps; oil, rubber, chemicals
Process types
• Continuous
• Assembly Line
• Job Shop
• Cell
• Project
Continuous Process
• Highly standardized products in large volumes
• Often these products have become commodities
• Typically these processes operate 24 hours/day
seven days/week
• Objective is to spread fixed cost over as large a
volume as possible
Continuous Process continued
• Starting and stopping a continuous process
can be prohibitively expensive
• Highly automated and specialized
equipment used
• Layout follows the processing stages
• Output rate controlled through equipment
capacity and flow mixture rates
Continuous Process continued
• Low labor
requirements
• Often one primary
input
• Initial setup of
equipment and
procedures very
complex
24
Assembly Line
• Similar to continuous process except
discrete product is produced
• Heavily automated special purpose
equipment
• High volume - low variety
• Both services and products can use flow
shop form of processing
A Generalized Assembly Line
Operation
Advantages of the Assembly Line
• Low unit cost
– specialized high volume equipment
– bulk purchasing
– lower labor rates
– low in-process inventories
– simplified managerial control
Disadvantages of Assembly Line
• Variety of output difficult to obtain
• Difficult to change rate of output
• Minor design changes may require
substantial changes to the equipment
• Worker boredom and absenteeism
• Work not very challenging
• Vulnerable to equipment breakdowns
Disadvantages of Assembly Line
continued
• Line balanced to slowest element
• Large support staff required
• Planning, design, and installation very
complex task
• Difficult to dispose of or modify special
purpose equipment
Assembly Line Layout
• Objective is to assign tasks to groups
• The work assigned to each group should
take about the same amount of time to
complete
• Final assembly operations with more labor
input often subdivided easier
• Paced versus unpaced lines
Job Shop
• High variety - low volume
• Equipment and staff grouped based on
function
• Each output processed differently
A Generalized Job Shop Operation
32
Advantages of the Job Shop
• Flexibility to respond to individual demands
• Less expensive general purpose equipment
used
• Maintenance and installation of general
purpose equipment easier
• General purpose equipment easier to
modify and therefore less susceptible to
becoming obsolete
Advantages of the Job Shop continued
• Dangerous activities can be segregated
from other operations
• Higher skilled work leading to pride of
workmanship
• Experience and expertise concentrated
• Pace of work not dictated by moving line
• Less vulnerable to equipment breakdowns
Disadvantages of the Job Shop
• General purpose equipment is slower
• Higher direct labor cost
• High WIP inventories
• High material handling costs
• Management control very difficult
The Cell Form
• Combines flexibility of job shop with low
costs and short response times of flow
shop
• Based on group technology
• First identify part families
• Then form machine cells to produce part
families
Conversion of a Job Shop Layout to a
Cellular Layout
37
Organization of Miscellaneous Parts
into Families
38
Advantages of Cellular Production
• Reduced machine setup times
– increased capacity
– economical to produce in smaller batch sizes
– smaller batch sizes result in less WIP
– less WIP leads to shorter lead times
– shorter lead times increase forecast accuracy
and provide a competitive advantage
• Parts produced in one cell
Advantages of Cellular Production
continued
• Capitalize on benefits of using worker
teams
• Minimal cost to move from job shop to
cellular production (e.g. EHC)
• Can move from cellular production to
“mini-plants”
Disadvantages of Cellular Production
• Volumes too low to justify highly efficient
high volume equipment
• Vulnerable to equipment breakdowns
• Balancing work across cells
• Does not offer the same high degree of
customization as the job shop
Cellular Layout
• Teams of workers and equipment to
produce families of outputs
• Workers cross-trained
• Nominal cells versus physical cells.
• Remainder cell
• Cell formation methods
– production flow analysis
Project Operations
• Large scale
• Finite duration
• Nonrepetitive
• Multiple
interdependent
activities
• Offers extremely
short reaction times
Product-Process Matrix
Selection of Transformation System by
Stage of Life Cycle
Break-Even Analysis
• A standard approach to choosing among
alternative processes or equipment
• Model seeks to determine the point in units
produced (and sold) where we will start
making profit on the process or equipment
• Model seeks to determine the point in units
produced (and sold) where total revenue and
total cost are equal
Break-Even Analysis (Continued)
This formula can be used to find any of its
components algebraically if the other
parameters are known
Break-even Demand=Break-even Demand=
Purchase cost of process or equipment
Price per unit - Cost per unit
or
Total fixed costs of process or equipment
Unit price to customer - Variable costs per unit
Purchase cost of process or equipment
Price per unit - Cost per unit
or
Total fixed costs of process or equipment
Unit price to customer - Variable costs per unit
Break-Even Analysis (Continued)
Example: Suppose you want to purchase a new
computer that will cost $5,000. It will be used to
process written orders from customers who will
pay $25 each for the service. The cost of labor,
electricity and the form used to place the order is
$5 per customer. How many customers will we
need to serve to permit the total revenue to
break-even with our costs?
Break-even Demand:
= Total fixed costs of process or equip.
Unit price to customer – Variable costs
=5,000/(25-5)
=250 customers
Example: Suppose you want to purchase a new
computer that will cost $5,000. It will be used to
process written orders from customers who will
pay $25 each for the service. The cost of labor,
electricity and the form used to place the order is
$5 per customer. How many customers will we
need to serve to permit the total revenue to
break-even with our costs?
Break-even Demand:
= Total fixed costs of process or equip.
Unit price to customer – Variable costs
=5,000/(25-5)
=250 customers
Manufacturing Process Flow Design
• A process flow design can be defined as a
mapping of the specific processes that raw
materials, parts, and subassemblies follow as
they move through a plant
• The most common tools to conduct a process
flow design include assembly drawings,
assembly charts, and operation and route
sheets
Example: Assembly Chart (Gozinto) – Plug Assembly
A-2SA-2
4
5
6
7
Lockring
Spacer, detent spring
Rivets (2)
Spring-detent
A-5
Component/Assy Operation
Inspection
From Exhibit 7.4From Exhibit 7.4
Service Businesses
• Facilities-based services: Where the
customer must go to the service facility
• Field-based services: Where the
production and consumption of the
service takes place in the customer’s
A service business is the management of
organizations whose primary business
requires interaction with the customer to
produce the service
The Customer Centered View
The
Customer
The Service
Strategy
The
People
The
Systems
A philosophical view that
suggests the organization
exists to serve the
customer, and the
systems and the
employees exist to
facilitate the process of
service.
A philosophical view that
suggests the organization
exists to serve the
customer, and the
systems and the
employees exist to
facilitate the process of
service.
Service-System Design Matrix
Mail contact
Face-to-face
loose specs
Face-to-face
tight specs
Phone
Contact
Face-to-face
total
customization
Buffered
core (none)
Permeable
system (some)
Reactive
system (much)
High
LowHigh
Low
Degree of customer/server contact
Internet &
on-site
technology
Sales
Opportunity
Production
Efficiency
Characteristics of Workers, Operations, and Innovations Relative to the
Degree of Customer/Service Contact
Example of Service Blueprinting
Brush
shoes
Apply
polish
Fail
point
Buff
Collect
payment
Clean
shoes Materials
(e.g., polish, cloth)
Select and
purchase
supplies
Standard
execution time
2 minutes
Total acceptable
execution time
5 minutes
30
secs
30
secs
45
secs
15
secs
Wrong
color wax
Seen by
customer 45
secs
Line of
visibility
Not seen by
customer but
necessary to
performance
Service Fail-safing
Poka-Yokes (A Proactive Approach)
• Keeping a
mistake from
becoming a
service defect
• How can we fail-
safe the three
Ts?
Task
TangiblesTreatment
Three Contrasting Service Designs
The production line approach (ex.
McDonald’s)
The self-service approach (ex. automatic
teller machines)
The personal attention approach (ex. Ritz-
Carlton Hotel Company)
Managing Customer Introduced Variation
•Arrival variability
•Request variability
•Capability variability
•Effort variability
•Subjective preference variability
Accommodation Strategies
• Classic accommodation – extra employees
or additional employee skills
• Low cost accommodation – use low cost
labor, outsource, self-service
• Classic reduction – more self-service,
reservations, adjust expectations
• Uncompromised reduction – develop
procedures for good service, minimizing
variation impact
Characteristics of a Well-Designed Service System
1. Each element of the service system is
consistent with the operating focus
of the firm
2. It is user-friendly
3. It is robust
4. It is structured so that consistent
performance by its people and
systems is easily maintained
Characteristics of a Well-Designed Service System (Continued)
5. It provides effective links between the back
office and the front office so that nothing
falls between the cracks
6. It manages the evidence of service quality in
such a way that customers see the value of
the service provided
7. It is cost-effective
Service Guarantees as Design Drivers
• Recent research suggests:
– Any guarantee is better than no guarantee
– Involve the customer as well as employees in the
design
– Avoid complexity or legalistic language
– Do not quibble or wriggle when a customer
invokes a guarantee
– Make it clear that you are happy for customers to
invoke the guarantee
Business Process Design
(Reengineering)
Division of Labor Concept
• Work broken down into its simplest most
basic tasks
– Performing same task facilitates attaining
greater skill
– No time lost switching to another task
– Workers well positioned to improve tools
and techniques
Division of Labor Concept continued
• Division of labor concept not challenged
until recently despite dramatic changes
in technology
• Quality, innovation, service, and value
more important than cost, growth, and
control
Process
• Set of activities that taken together
produce a result of value to the customer
• Organizing on basis of processes
– Eliminate delays and errors when work is
handed off
– Capture information once and at source
– When people closest to process perform
work, there is little need for management
overhead
Business Process Design (BPD)
The fundamental rethinking and radical
redesign of business processes to bring
about dramatic improvements in
performance
Hammer, M. and Stanton, S. The Reengineering Revolution, Harper
Business, 1995.
Radical
• Profoundly change the way work
performed
• Not concerned with making superficial
changes
• Get to root
• Get rid of old
• Reinventing, not improving
Redesign
• BPD is about designing how work is done
• Smart, capable, well trained, highly
motivated employees mean little if the
way work is performed is poorly designed
Process
• All organizations perform processes
• Customers not interested in individual
activities but rather overall results
• Few of them are organized on the basis of
processes
• Thus, processes tend to go unmanaged
• Team approach one way this addressed
Dramatic
• Quantum leaps in performance, not
marginal or incremental improvements
• Breakthroughs in performance
IBM Credit Example
72
IBM Credit Example continued
• Order logged by 1 of 14 people in
conference room
• Carted upstairs to credit department
• Information entered into computer to
check borrower’s creditworthiness
• Results written on piece of paper
IBM Credit Example continued
• Business practices department modified
standard loan covenant in response to
customer requests
• Used its own computer system
• Pricer keyed data into PC to determine
appropriate interest rate
• Administrator converted to quote letter
and Fedexed to field sales rep.
IBM Credit Example continued
• Average time to process a request was 6
days
• Could take as long as 2 weeks
• Actual processing time 90 minutes
• Deal Structurer
– Turnaround time 4 hours
– Number of deals processed increased 100 times
with small reduction in head count
Reference
• www.csun.edu
• www.crfproject-eu.org
• erp.acuvisions.com/ERP01.

More Related Content

What's hot

Process selection
Process selectionProcess selection
Process selection
olenyxa
 
Job Design and Work Measurement
Job Design and Work Measurement Job Design and Work Measurement
Job Design and Work Measurement
Joshua Miranda
 
Types of layout
Types of layoutTypes of layout
Types of layout
Ebenezer Raja
 
Product and service design
Product and service designProduct and service design
Product and service design
SurabhiMukherjee3
 
Production Planning and Control
Production Planning and ControlProduction Planning and Control
Production Planning and Control
learnito
 
Operation management-notes
Operation management-notesOperation management-notes
Operation management-notesismatullahzazai
 
Product and service design
Product and service designProduct and service design
Product and service designGrace Falcis
 
Inventory models
Inventory modelsInventory models
Inventory models
MOHD BILAL NAIM SHAIKH
 
job shop production system in productions and operations system
job shop production system in productions and operations systemjob shop production system in productions and operations system
job shop production system in productions and operations system
ar9530
 
Operation Process
Operation ProcessOperation Process
Operation Process
Dr. Prashant Kalaskar
 
Process design layout
Process design layoutProcess design layout
Process design layout
AL Kindi
 
Inventory models with two supply models
Inventory models with two supply modelsInventory models with two supply models
Inventory models with two supply models
MOHAMMED ASIF
 
02 elements of production systems
02 elements of production systems02 elements of production systems
02 elements of production systems
Arif Rahman
 
Production Planning and Control (Operations Management)
Production Planning and Control (Operations Management)Production Planning and Control (Operations Management)
Production Planning and Control (Operations Management)
Manu Alias
 
Introduction to Operations and Supply Chain Management
Introduction to Operations and Supply Chain ManagementIntroduction to Operations and Supply Chain Management
Introduction to Operations and Supply Chain Management
Dr. Prashant Kalaskar
 
Production management
Production managementProduction management
Production management
Ms. Shery Asthana
 
plant layout ( Operation Research )
plant layout ( Operation Research ) plant layout ( Operation Research )
plant layout ( Operation Research )
Arpit gupta
 
Just In Time (JIT)
Just In Time (JIT)Just In Time (JIT)
Just In Time (JIT)
Manoj Subedi
 

What's hot (20)

Process selection
Process selectionProcess selection
Process selection
 
Job Design and Work Measurement
Job Design and Work Measurement Job Design and Work Measurement
Job Design and Work Measurement
 
Types of layout
Types of layoutTypes of layout
Types of layout
 
Plant layout
Plant layoutPlant layout
Plant layout
 
Product and service design
Product and service designProduct and service design
Product and service design
 
Production Planning and Control
Production Planning and ControlProduction Planning and Control
Production Planning and Control
 
Operation management-notes
Operation management-notesOperation management-notes
Operation management-notes
 
Product and service design
Product and service designProduct and service design
Product and service design
 
Inventory models
Inventory modelsInventory models
Inventory models
 
job shop production system in productions and operations system
job shop production system in productions and operations systemjob shop production system in productions and operations system
job shop production system in productions and operations system
 
Operation Process
Operation ProcessOperation Process
Operation Process
 
Process design layout
Process design layoutProcess design layout
Process design layout
 
Inventory models with two supply models
Inventory models with two supply modelsInventory models with two supply models
Inventory models with two supply models
 
02 elements of production systems
02 elements of production systems02 elements of production systems
02 elements of production systems
 
Production Planning and Control (Operations Management)
Production Planning and Control (Operations Management)Production Planning and Control (Operations Management)
Production Planning and Control (Operations Management)
 
Introduction to Operations and Supply Chain Management
Introduction to Operations and Supply Chain ManagementIntroduction to Operations and Supply Chain Management
Introduction to Operations and Supply Chain Management
 
JUST IN TIME
JUST IN TIMEJUST IN TIME
JUST IN TIME
 
Production management
Production managementProduction management
Production management
 
plant layout ( Operation Research )
plant layout ( Operation Research ) plant layout ( Operation Research )
plant layout ( Operation Research )
 
Just In Time (JIT)
Just In Time (JIT)Just In Time (JIT)
Just In Time (JIT)
 

Similar to Mba ii pmom_unit-1.4 process design, analysis & selection a

Facility Layout,PPT.pptx
Facility Layout,PPT.pptxFacility Layout,PPT.pptx
Facility Layout,PPT.pptx
SakhawatHossainRony
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.ppt
SandipanMaji3
 
Typesofproductionprocesses 130108024851-phpapp01 (2)
Typesofproductionprocesses 130108024851-phpapp01 (2)Typesofproductionprocesses 130108024851-phpapp01 (2)
Typesofproductionprocesses 130108024851-phpapp01 (2)
Pravin David
 
Process Selection & Facility Layout.ppt
Process Selection & Facility Layout.pptProcess Selection & Facility Layout.ppt
Process Selection & Facility Layout.ppt
Renu Lamba
 
Production management
Production managementProduction management
Production management
shreenibasa maharana
 
JIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
JIT & Lean Manufacturing - ADDVALUE - Nilesh AroraJIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
JIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
ADD VALUE CONSULTING Inc
 
ie450pp4.ppt
ie450pp4.pptie450pp4.ppt
ie450pp4.ppt
GauthamS49
 
OPERATIONS MANAGEMENT- Full Slides.pptx
OPERATIONS MANAGEMENT- Full Slides.pptxOPERATIONS MANAGEMENT- Full Slides.pptx
OPERATIONS MANAGEMENT- Full Slides.pptx
ThusharaVinay
 
Process Planning & Cost Estimation - Cellular Manufacturing
Process Planning & Cost Estimation - Cellular ManufacturingProcess Planning & Cost Estimation - Cellular Manufacturing
Process Planning & Cost Estimation - Cellular Manufacturing
DrGopiKrishnanPonnus
 
Manufacturing systems
Manufacturing systems Manufacturing systems
Manufacturing systems
Sumit Bhattacharya
 
Meenakshi mam Types of plant layout video.ppt
Meenakshi mam Types of plant layout video.pptMeenakshi mam Types of plant layout video.ppt
Meenakshi mam Types of plant layout video.ppt
tommychauhan
 
Chapter 1 pom
Chapter 1 pomChapter 1 pom
Chapter 1 pom
Shalini Krishna
 
JIT and lean operations
JIT and lean operationsJIT and lean operations
JIT and lean operations
RajThakuri
 
IEM UNIT 4 PLANT LOCATION.ppt
IEM UNIT 4 PLANT LOCATION.pptIEM UNIT 4 PLANT LOCATION.ppt
IEM UNIT 4 PLANT LOCATION.ppt
Raja Manyam
 
Unit iii operations management
Unit iii operations managementUnit iii operations management
Unit iii operations management
Management
 
lean manufacturing.ppt cost profit accounts
lean manufacturing.ppt cost profit accountslean manufacturing.ppt cost profit accounts
lean manufacturing.ppt cost profit accounts
SabaKhalid48
 
Dr. rajesha. pom 1st module-buc
Dr. rajesha. pom 1st module-bucDr. rajesha. pom 1st module-buc
Dr. rajesha. pom 1st module-buc
Dr. Rajesha Shivaramegowda
 
1ST MODULE PRODUCTION MANAGEMENT AND OPERATION RESEARCH
1ST MODULE PRODUCTION MANAGEMENT AND OPERATION RESEARCH1ST MODULE PRODUCTION MANAGEMENT AND OPERATION RESEARCH
1ST MODULE PRODUCTION MANAGEMENT AND OPERATION RESEARCH
Dr. Rajesha Shivaramegowda
 

Similar to Mba ii pmom_unit-1.4 process design, analysis & selection a (20)

Facility Layout,PPT.pptx
Facility Layout,PPT.pptxFacility Layout,PPT.pptx
Facility Layout,PPT.pptx
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.ppt
 
Typesofproductionprocesses 130108024851-phpapp01 (2)
Typesofproductionprocesses 130108024851-phpapp01 (2)Typesofproductionprocesses 130108024851-phpapp01 (2)
Typesofproductionprocesses 130108024851-phpapp01 (2)
 
Om plant_layout
Om   plant_layoutOm   plant_layout
Om plant_layout
 
Process Selection & Facility Layout.ppt
Process Selection & Facility Layout.pptProcess Selection & Facility Layout.ppt
Process Selection & Facility Layout.ppt
 
Production management
Production managementProduction management
Production management
 
JIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
JIT & Lean Manufacturing - ADDVALUE - Nilesh AroraJIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
JIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
 
ie450pp4.ppt
ie450pp4.pptie450pp4.ppt
ie450pp4.ppt
 
OPERATIONS MANAGEMENT- Full Slides.pptx
OPERATIONS MANAGEMENT- Full Slides.pptxOPERATIONS MANAGEMENT- Full Slides.pptx
OPERATIONS MANAGEMENT- Full Slides.pptx
 
Process Planning & Cost Estimation - Cellular Manufacturing
Process Planning & Cost Estimation - Cellular ManufacturingProcess Planning & Cost Estimation - Cellular Manufacturing
Process Planning & Cost Estimation - Cellular Manufacturing
 
Manufacturing systems
Manufacturing systems Manufacturing systems
Manufacturing systems
 
Meenakshi mam Types of plant layout video.ppt
Meenakshi mam Types of plant layout video.pptMeenakshi mam Types of plant layout video.ppt
Meenakshi mam Types of plant layout video.ppt
 
Chapter 1 pom
Chapter 1 pomChapter 1 pom
Chapter 1 pom
 
JIT and lean operations
JIT and lean operationsJIT and lean operations
JIT and lean operations
 
IEM UNIT 4 PLANT LOCATION.ppt
IEM UNIT 4 PLANT LOCATION.pptIEM UNIT 4 PLANT LOCATION.ppt
IEM UNIT 4 PLANT LOCATION.ppt
 
Unit iii operations management
Unit iii operations managementUnit iii operations management
Unit iii operations management
 
Just in time
Just in timeJust in time
Just in time
 
lean manufacturing.ppt cost profit accounts
lean manufacturing.ppt cost profit accountslean manufacturing.ppt cost profit accounts
lean manufacturing.ppt cost profit accounts
 
Dr. rajesha. pom 1st module-buc
Dr. rajesha. pom 1st module-bucDr. rajesha. pom 1st module-buc
Dr. rajesha. pom 1st module-buc
 
1ST MODULE PRODUCTION MANAGEMENT AND OPERATION RESEARCH
1ST MODULE PRODUCTION MANAGEMENT AND OPERATION RESEARCH1ST MODULE PRODUCTION MANAGEMENT AND OPERATION RESEARCH
1ST MODULE PRODUCTION MANAGEMENT AND OPERATION RESEARCH
 

More from Rai University

Brochure Rai University
Brochure Rai University Brochure Rai University
Brochure Rai University
Rai University
 
Mm unit 4point2
Mm unit 4point2Mm unit 4point2
Mm unit 4point2
Rai University
 
Mm unit 4point1
Mm unit 4point1Mm unit 4point1
Mm unit 4point1
Rai University
 
Mm unit 4point3
Mm unit 4point3Mm unit 4point3
Mm unit 4point3
Rai University
 
Mm unit 3point2
Mm unit 3point2Mm unit 3point2
Mm unit 3point2
Rai University
 
Mm unit 3point1
Mm unit 3point1Mm unit 3point1
Mm unit 3point1
Rai University
 
Mm unit 2point2
Mm unit 2point2Mm unit 2point2
Mm unit 2point2
Rai University
 
Mm unit 2 point 1
Mm unit 2 point 1Mm unit 2 point 1
Mm unit 2 point 1
Rai University
 
Mm unit 1point3
Mm unit 1point3Mm unit 1point3
Mm unit 1point3
Rai University
 
Mm unit 1point2
Mm unit 1point2Mm unit 1point2
Mm unit 1point2
Rai University
 
Mm unit 1point1
Mm unit 1point1Mm unit 1point1
Mm unit 1point1
Rai University
 
Bdft ii, tmt, unit-iii, dyeing & types of dyeing,
Bdft ii, tmt, unit-iii,  dyeing & types of dyeing,Bdft ii, tmt, unit-iii,  dyeing & types of dyeing,
Bdft ii, tmt, unit-iii, dyeing & types of dyeing,
Rai University
 
Bsc agri 2 pae u-4.4 publicrevenue-presentation-130208082149-phpapp02
Bsc agri  2 pae  u-4.4 publicrevenue-presentation-130208082149-phpapp02Bsc agri  2 pae  u-4.4 publicrevenue-presentation-130208082149-phpapp02
Bsc agri 2 pae u-4.4 publicrevenue-presentation-130208082149-phpapp02
Rai University
 
Bsc agri 2 pae u-4.3 public expenditure
Bsc agri  2 pae  u-4.3 public expenditureBsc agri  2 pae  u-4.3 public expenditure
Bsc agri 2 pae u-4.3 public expenditure
Rai University
 
Bsc agri 2 pae u-4.2 public finance
Bsc agri  2 pae  u-4.2 public financeBsc agri  2 pae  u-4.2 public finance
Bsc agri 2 pae u-4.2 public finance
Rai University
 
Bsc agri 2 pae u-4.1 introduction
Bsc agri  2 pae  u-4.1 introductionBsc agri  2 pae  u-4.1 introduction
Bsc agri 2 pae u-4.1 introduction
Rai University
 
Bsc agri 2 pae u-3.3 inflation
Bsc agri  2 pae  u-3.3  inflationBsc agri  2 pae  u-3.3  inflation
Bsc agri 2 pae u-3.3 inflation
Rai University
 
Bsc agri 2 pae u-3.2 introduction to macro economics
Bsc agri  2 pae  u-3.2 introduction to macro economicsBsc agri  2 pae  u-3.2 introduction to macro economics
Bsc agri 2 pae u-3.2 introduction to macro economics
Rai University
 
Bsc agri 2 pae u-3.1 marketstructure
Bsc agri  2 pae  u-3.1 marketstructureBsc agri  2 pae  u-3.1 marketstructure
Bsc agri 2 pae u-3.1 marketstructure
Rai University
 
Bsc agri 2 pae u-3 perfect-competition
Bsc agri  2 pae  u-3 perfect-competitionBsc agri  2 pae  u-3 perfect-competition
Bsc agri 2 pae u-3 perfect-competition
Rai University
 

More from Rai University (20)

Brochure Rai University
Brochure Rai University Brochure Rai University
Brochure Rai University
 
Mm unit 4point2
Mm unit 4point2Mm unit 4point2
Mm unit 4point2
 
Mm unit 4point1
Mm unit 4point1Mm unit 4point1
Mm unit 4point1
 
Mm unit 4point3
Mm unit 4point3Mm unit 4point3
Mm unit 4point3
 
Mm unit 3point2
Mm unit 3point2Mm unit 3point2
Mm unit 3point2
 
Mm unit 3point1
Mm unit 3point1Mm unit 3point1
Mm unit 3point1
 
Mm unit 2point2
Mm unit 2point2Mm unit 2point2
Mm unit 2point2
 
Mm unit 2 point 1
Mm unit 2 point 1Mm unit 2 point 1
Mm unit 2 point 1
 
Mm unit 1point3
Mm unit 1point3Mm unit 1point3
Mm unit 1point3
 
Mm unit 1point2
Mm unit 1point2Mm unit 1point2
Mm unit 1point2
 
Mm unit 1point1
Mm unit 1point1Mm unit 1point1
Mm unit 1point1
 
Bdft ii, tmt, unit-iii, dyeing & types of dyeing,
Bdft ii, tmt, unit-iii,  dyeing & types of dyeing,Bdft ii, tmt, unit-iii,  dyeing & types of dyeing,
Bdft ii, tmt, unit-iii, dyeing & types of dyeing,
 
Bsc agri 2 pae u-4.4 publicrevenue-presentation-130208082149-phpapp02
Bsc agri  2 pae  u-4.4 publicrevenue-presentation-130208082149-phpapp02Bsc agri  2 pae  u-4.4 publicrevenue-presentation-130208082149-phpapp02
Bsc agri 2 pae u-4.4 publicrevenue-presentation-130208082149-phpapp02
 
Bsc agri 2 pae u-4.3 public expenditure
Bsc agri  2 pae  u-4.3 public expenditureBsc agri  2 pae  u-4.3 public expenditure
Bsc agri 2 pae u-4.3 public expenditure
 
Bsc agri 2 pae u-4.2 public finance
Bsc agri  2 pae  u-4.2 public financeBsc agri  2 pae  u-4.2 public finance
Bsc agri 2 pae u-4.2 public finance
 
Bsc agri 2 pae u-4.1 introduction
Bsc agri  2 pae  u-4.1 introductionBsc agri  2 pae  u-4.1 introduction
Bsc agri 2 pae u-4.1 introduction
 
Bsc agri 2 pae u-3.3 inflation
Bsc agri  2 pae  u-3.3  inflationBsc agri  2 pae  u-3.3  inflation
Bsc agri 2 pae u-3.3 inflation
 
Bsc agri 2 pae u-3.2 introduction to macro economics
Bsc agri  2 pae  u-3.2 introduction to macro economicsBsc agri  2 pae  u-3.2 introduction to macro economics
Bsc agri 2 pae u-3.2 introduction to macro economics
 
Bsc agri 2 pae u-3.1 marketstructure
Bsc agri  2 pae  u-3.1 marketstructureBsc agri  2 pae  u-3.1 marketstructure
Bsc agri 2 pae u-3.1 marketstructure
 
Bsc agri 2 pae u-3 perfect-competition
Bsc agri  2 pae  u-3 perfect-competitionBsc agri  2 pae  u-3 perfect-competition
Bsc agri 2 pae u-3 perfect-competition
 

Recently uploaded

Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
Col Mukteshwar Prasad
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
Vivekanand Anglo Vedic Academy
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
AzmatAli747758
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
Excellence Foundation for South Sudan
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
Steve Thomason
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
Celine George
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
Jheel Barad
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 

Recently uploaded (20)

Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 

Mba ii pmom_unit-1.4 process design, analysis & selection a

  • 1. Course: MBA Subject: Production & Operation Management Unit: 1.4 Process design, analysis and selection
  • 2. • Process Analysis • Process Flowcharting • Types of Processes • Process Performance Metrics • Manufacturing Processes • Service Processes OBJECTIVES
  • 3. Process Management • Processes relate to work that is ongoing and repetitive • Process management concepts and methods can be applied to improve manufacturing, service, and business processes • Effort is placed trying to reduce cost, increase throughput, and improve quality
  • 4. Process Analysis Terms • Process: Is any part of an organization that takes inputs and transforms them into outputs • Cycle Time: Is the average successive time between completions of successive units • Utilization: Is the ratio of the time that a resource is actually activated relative to the time that it is available for use
  • 5. Process Flowcharting Defined • Process flowcharting is the use of a diagram to present the major elements of a process • The basic elements can include tasks or operations, flows of materials or customers, decision points, and storage areas or queues • It is an ideal methodology by which to begin analyzing a process
  • 6. Tasks or operations Examples: Giving an admission ticket to a customer, installing a engine in a car, etc. Examples: Giving an admission ticket to a customer, installing a engine in a car, etc. Decision Points Examples: How much change should be given to a customer, which wrench should be used, etc. Examples: How much change should be given to a customer, which wrench should be used, etc. Purpose and Examples Flowchart Symbols
  • 7. Examples: Sheds, lines of people waiting for a service, etc. Examples: Sheds, lines of people waiting for a service, etc. Examples: Customers moving to a seat, mechanic getting a tool, etc. Examples: Customers moving to a seat, mechanic getting a tool, etc. Storage areas or queues Flows of materials or customers Purpose and Examples Flowchart Symbols
  • 8. Types of Processes Single-stage Process Stage 1 Stage 1 Stage 2 Stage 3 Multi-stage Process
  • 9. Types of Processes (Continued) A buffer refers to a storage area between stages where the output of a stage is placed prior to being used in a downstream stage Stage 1 Stage 2 Buffer Multi-stage Process with Buffer
  • 10. Other Process Terminology • Blocking – Occurs when the activities in a stage must stop because there is no place to deposit the item just completed – If there is no room for an employee to place a unit of work down, the employee will hold on to it not able to continue working on the next unit • Starving – Occurs when the activities in a stage must stop because there is no work – If an employee is waiting at a work station and no work is coming to the employee to process, the employee will remain idle until the next unit of work comes
  • 11. Other Process Terminology (Continued) • Bottleneck – Occurs when the limited capacity of a process causes work to pile up or become unevenly distributed in the flow of a process – If an employee works too slow in a multi-stage process, work will begin to pile up in front of that employee. In this is case the employee represents the limited capacity causing the bottleneck. • Pacing – Refers to the fixed timing of the movement of items through the process
  • 12. Other Types of Processes • Make-to-order – Only activated in response to an actual order – Both work-in-process and finished goods inventory kept to a minimum • Make-to-stock – Process activated to meet expected or forecast demand – Customer orders are served from target stocking level
  • 13.
  • 14. Process Performance Metrics Capacity: maximum output of a process or resource measured in units/time: a rate Operation time = Setup time + Run time Setup time: the length of time required to changeover from one product to another (assumes products are produced in batches) Throughput time = Average time for a unit to move through the system
  • 15. Process Performance Metrics (Continued) • Cycle time = Average time between completion of units • Throughput rate = 1___ Cycle time • Utilization of an operation = Demand/Capacity
  • 16. Cycle Time Example Suppose you had to produce 600 units in 80 hours to meet the demand requirements of a product. What is the cycle time to meet this demand requirement? Suppose you had to produce 600 units in 80 hours to meet the demand requirements of a product. What is the cycle time to meet this demand requirement? Answer: There are 4,800 minutes (60 minutes/hour x 80 hours) in 80 hours. So the average time between completions would have to be: Cycle time = 4,800/600 units = 8 minutes. Answer: There are 4,800 minutes (60 minutes/hour x 80 hours) in 80 hours. So the average time between completions would have to be: Cycle time = 4,800/600 units = 8 minutes.
  • 17.
  • 18. Bread-Making Questions • What is the bottleneck when one bread-making line is used? What is the capacity of the process? What is the utilization of packaging? What is the throughput time? • What happens to capacity and utilization when two bread-making lines are used? What is the bottleneck?
  • 19. Process Throughput Time Reduction • Perform activities in parallel • Change the sequence of activities • Reduce interruptions
  • 20. Basic work flow structures Project layout – fixed position; construction, movie lots Workcenter (job shop) – similar equipment grouped together; machine shop Manufacturing cell – similar set of processes for a limited range of products Assembly Line – discrete parts move through workstations; toys, appliances, cars Continuous process – flow vs discrete, flows a set sequence of steps; oil, rubber, chemicals
  • 21. Process types • Continuous • Assembly Line • Job Shop • Cell • Project
  • 22. Continuous Process • Highly standardized products in large volumes • Often these products have become commodities • Typically these processes operate 24 hours/day seven days/week • Objective is to spread fixed cost over as large a volume as possible
  • 23. Continuous Process continued • Starting and stopping a continuous process can be prohibitively expensive • Highly automated and specialized equipment used • Layout follows the processing stages • Output rate controlled through equipment capacity and flow mixture rates
  • 24. Continuous Process continued • Low labor requirements • Often one primary input • Initial setup of equipment and procedures very complex 24
  • 25. Assembly Line • Similar to continuous process except discrete product is produced • Heavily automated special purpose equipment • High volume - low variety • Both services and products can use flow shop form of processing
  • 26. A Generalized Assembly Line Operation
  • 27. Advantages of the Assembly Line • Low unit cost – specialized high volume equipment – bulk purchasing – lower labor rates – low in-process inventories – simplified managerial control
  • 28. Disadvantages of Assembly Line • Variety of output difficult to obtain • Difficult to change rate of output • Minor design changes may require substantial changes to the equipment • Worker boredom and absenteeism • Work not very challenging • Vulnerable to equipment breakdowns
  • 29. Disadvantages of Assembly Line continued • Line balanced to slowest element • Large support staff required • Planning, design, and installation very complex task • Difficult to dispose of or modify special purpose equipment
  • 30. Assembly Line Layout • Objective is to assign tasks to groups • The work assigned to each group should take about the same amount of time to complete • Final assembly operations with more labor input often subdivided easier • Paced versus unpaced lines
  • 31. Job Shop • High variety - low volume • Equipment and staff grouped based on function • Each output processed differently
  • 32. A Generalized Job Shop Operation 32
  • 33. Advantages of the Job Shop • Flexibility to respond to individual demands • Less expensive general purpose equipment used • Maintenance and installation of general purpose equipment easier • General purpose equipment easier to modify and therefore less susceptible to becoming obsolete
  • 34. Advantages of the Job Shop continued • Dangerous activities can be segregated from other operations • Higher skilled work leading to pride of workmanship • Experience and expertise concentrated • Pace of work not dictated by moving line • Less vulnerable to equipment breakdowns
  • 35. Disadvantages of the Job Shop • General purpose equipment is slower • Higher direct labor cost • High WIP inventories • High material handling costs • Management control very difficult
  • 36. The Cell Form • Combines flexibility of job shop with low costs and short response times of flow shop • Based on group technology • First identify part families • Then form machine cells to produce part families
  • 37. Conversion of a Job Shop Layout to a Cellular Layout 37
  • 38. Organization of Miscellaneous Parts into Families 38
  • 39. Advantages of Cellular Production • Reduced machine setup times – increased capacity – economical to produce in smaller batch sizes – smaller batch sizes result in less WIP – less WIP leads to shorter lead times – shorter lead times increase forecast accuracy and provide a competitive advantage • Parts produced in one cell
  • 40. Advantages of Cellular Production continued • Capitalize on benefits of using worker teams • Minimal cost to move from job shop to cellular production (e.g. EHC) • Can move from cellular production to “mini-plants”
  • 41. Disadvantages of Cellular Production • Volumes too low to justify highly efficient high volume equipment • Vulnerable to equipment breakdowns • Balancing work across cells • Does not offer the same high degree of customization as the job shop
  • 42. Cellular Layout • Teams of workers and equipment to produce families of outputs • Workers cross-trained • Nominal cells versus physical cells. • Remainder cell • Cell formation methods – production flow analysis
  • 43. Project Operations • Large scale • Finite duration • Nonrepetitive • Multiple interdependent activities • Offers extremely short reaction times
  • 45. Selection of Transformation System by Stage of Life Cycle
  • 46. Break-Even Analysis • A standard approach to choosing among alternative processes or equipment • Model seeks to determine the point in units produced (and sold) where we will start making profit on the process or equipment • Model seeks to determine the point in units produced (and sold) where total revenue and total cost are equal
  • 47. Break-Even Analysis (Continued) This formula can be used to find any of its components algebraically if the other parameters are known Break-even Demand=Break-even Demand= Purchase cost of process or equipment Price per unit - Cost per unit or Total fixed costs of process or equipment Unit price to customer - Variable costs per unit Purchase cost of process or equipment Price per unit - Cost per unit or Total fixed costs of process or equipment Unit price to customer - Variable costs per unit
  • 48. Break-Even Analysis (Continued) Example: Suppose you want to purchase a new computer that will cost $5,000. It will be used to process written orders from customers who will pay $25 each for the service. The cost of labor, electricity and the form used to place the order is $5 per customer. How many customers will we need to serve to permit the total revenue to break-even with our costs? Break-even Demand: = Total fixed costs of process or equip. Unit price to customer – Variable costs =5,000/(25-5) =250 customers Example: Suppose you want to purchase a new computer that will cost $5,000. It will be used to process written orders from customers who will pay $25 each for the service. The cost of labor, electricity and the form used to place the order is $5 per customer. How many customers will we need to serve to permit the total revenue to break-even with our costs? Break-even Demand: = Total fixed costs of process or equip. Unit price to customer – Variable costs =5,000/(25-5) =250 customers
  • 49. Manufacturing Process Flow Design • A process flow design can be defined as a mapping of the specific processes that raw materials, parts, and subassemblies follow as they move through a plant • The most common tools to conduct a process flow design include assembly drawings, assembly charts, and operation and route sheets
  • 50. Example: Assembly Chart (Gozinto) – Plug Assembly A-2SA-2 4 5 6 7 Lockring Spacer, detent spring Rivets (2) Spring-detent A-5 Component/Assy Operation Inspection From Exhibit 7.4From Exhibit 7.4
  • 51. Service Businesses • Facilities-based services: Where the customer must go to the service facility • Field-based services: Where the production and consumption of the service takes place in the customer’s A service business is the management of organizations whose primary business requires interaction with the customer to produce the service
  • 52. The Customer Centered View The Customer The Service Strategy The People The Systems A philosophical view that suggests the organization exists to serve the customer, and the systems and the employees exist to facilitate the process of service. A philosophical view that suggests the organization exists to serve the customer, and the systems and the employees exist to facilitate the process of service.
  • 53. Service-System Design Matrix Mail contact Face-to-face loose specs Face-to-face tight specs Phone Contact Face-to-face total customization Buffered core (none) Permeable system (some) Reactive system (much) High LowHigh Low Degree of customer/server contact Internet & on-site technology Sales Opportunity Production Efficiency
  • 54. Characteristics of Workers, Operations, and Innovations Relative to the Degree of Customer/Service Contact
  • 55. Example of Service Blueprinting Brush shoes Apply polish Fail point Buff Collect payment Clean shoes Materials (e.g., polish, cloth) Select and purchase supplies Standard execution time 2 minutes Total acceptable execution time 5 minutes 30 secs 30 secs 45 secs 15 secs Wrong color wax Seen by customer 45 secs Line of visibility Not seen by customer but necessary to performance
  • 56. Service Fail-safing Poka-Yokes (A Proactive Approach) • Keeping a mistake from becoming a service defect • How can we fail- safe the three Ts? Task TangiblesTreatment
  • 57. Three Contrasting Service Designs The production line approach (ex. McDonald’s) The self-service approach (ex. automatic teller machines) The personal attention approach (ex. Ritz- Carlton Hotel Company)
  • 58. Managing Customer Introduced Variation •Arrival variability •Request variability •Capability variability •Effort variability •Subjective preference variability
  • 59. Accommodation Strategies • Classic accommodation – extra employees or additional employee skills • Low cost accommodation – use low cost labor, outsource, self-service • Classic reduction – more self-service, reservations, adjust expectations • Uncompromised reduction – develop procedures for good service, minimizing variation impact
  • 60. Characteristics of a Well-Designed Service System 1. Each element of the service system is consistent with the operating focus of the firm 2. It is user-friendly 3. It is robust 4. It is structured so that consistent performance by its people and systems is easily maintained
  • 61. Characteristics of a Well-Designed Service System (Continued) 5. It provides effective links between the back office and the front office so that nothing falls between the cracks 6. It manages the evidence of service quality in such a way that customers see the value of the service provided 7. It is cost-effective
  • 62. Service Guarantees as Design Drivers • Recent research suggests: – Any guarantee is better than no guarantee – Involve the customer as well as employees in the design – Avoid complexity or legalistic language – Do not quibble or wriggle when a customer invokes a guarantee – Make it clear that you are happy for customers to invoke the guarantee
  • 64. Division of Labor Concept • Work broken down into its simplest most basic tasks – Performing same task facilitates attaining greater skill – No time lost switching to another task – Workers well positioned to improve tools and techniques
  • 65. Division of Labor Concept continued • Division of labor concept not challenged until recently despite dramatic changes in technology • Quality, innovation, service, and value more important than cost, growth, and control
  • 66. Process • Set of activities that taken together produce a result of value to the customer • Organizing on basis of processes – Eliminate delays and errors when work is handed off – Capture information once and at source – When people closest to process perform work, there is little need for management overhead
  • 67. Business Process Design (BPD) The fundamental rethinking and radical redesign of business processes to bring about dramatic improvements in performance Hammer, M. and Stanton, S. The Reengineering Revolution, Harper Business, 1995.
  • 68. Radical • Profoundly change the way work performed • Not concerned with making superficial changes • Get to root • Get rid of old • Reinventing, not improving
  • 69. Redesign • BPD is about designing how work is done • Smart, capable, well trained, highly motivated employees mean little if the way work is performed is poorly designed
  • 70. Process • All organizations perform processes • Customers not interested in individual activities but rather overall results • Few of them are organized on the basis of processes • Thus, processes tend to go unmanaged • Team approach one way this addressed
  • 71. Dramatic • Quantum leaps in performance, not marginal or incremental improvements • Breakthroughs in performance
  • 73. IBM Credit Example continued • Order logged by 1 of 14 people in conference room • Carted upstairs to credit department • Information entered into computer to check borrower’s creditworthiness • Results written on piece of paper
  • 74. IBM Credit Example continued • Business practices department modified standard loan covenant in response to customer requests • Used its own computer system • Pricer keyed data into PC to determine appropriate interest rate • Administrator converted to quote letter and Fedexed to field sales rep.
  • 75. IBM Credit Example continued • Average time to process a request was 6 days • Could take as long as 2 weeks • Actual processing time 90 minutes • Deal Structurer – Turnaround time 4 hours – Number of deals processed increased 100 times with small reduction in head count