SlideShare a Scribd company logo
Latest Trends In Operations
       Management

    Just In Time
                Sannik
                Seemoli Ganatra
                Shashank
                Saptha
                Anju Maria John
                Mahale Akshay Uday
WHAT IS JUST IN TIME ????

•   Producing the quantity if goods that is needed, no more, no less


•   Producing them on the date and at the time required, not before,
    not after.


•   Suppliers deliver the exact quantity demanded, at scheduled time
    and date


•   Just in time is a ‘pull’ system of production.


•   Demand-pull enables a firm to produce only what is required, in
    the correct quantity and at the correct time.
•   This requires a carefully planned scheduling and flow of
    resources through the production process.


•   Modern manufacturing firms use sophisticated production
    scheduling software to plan production for each period of time,.


•   Information is exchanged with suppliers and customers through
    EDI (Electronic Data Interchange) to help ensure that every
    detail is correct.


•   For example, a car manufacturing plant might receive exactly
    the right number and type of tyres for one day’s production
•   A lean system works best if the daily load on individual
    workstations is relatively uniform


    Uniform loads can be achieved by assembling the same type
    and number of units each day, thus creating a uniform daily
    demand at all workstations


    Workers should be trained to operate several machines,
    to perform maintenance tasks, and to perform quality
    inspections


    Use effective machines but the key is to use machine and
    worker idle time to maintain equipment and prevent break
    downs
TRADITIONAL SYSTEMS COMPARED
            WITH JIT
PRIORITIES


•   Traditionally
     • Accept all customer orders
     • Provide a large number of options from which customers
       may order




•   JIT
     • low cost/high quality within limited market
ENGINEERING



•   Traditional
     • design custom outputs




•   JIT
     • design standard outputs
     • incremental improvements
     • design for manufacturability (DFM)
CAPACITY

•   Traditional
     • excess capacity designed into system just-in-case problem
       arises
     • highly utilized
     • inflexible


•   JIT
     • minimize waste of having extra capacity
     • flexible capacity
     • moderately utilized
TRANSFORMATION SYSTEM

•   Traditional-
     • long lead times are often thought to allow more time to
       make decisions and get work performed .
•   JIT
     • short lead times mean easier, more accurate forecasting and
       planning.
     • If lead times are reduced, there is less time for things go awry, to
       get lost, or to be changed
     • “Don’t let the parts touch the floor” (the parts have to be kept
       on the machines and thus be worked on until completed)
     •    Smaller batches result in shorter lead times and less inventory, at the
          same time. With smaller batches, engineering changes get to the
          customer sooner, problems with quality are corrected more quickly,
          rework is reduced, there is less obsolete inventory, and new
          products get to market more promptly .
LAYOUT

•   Traditional
     • job shop approach of using widely spread-out equipment
       with space for stockrooms, tool cribs, and work-in-process
       inventories between the equipment
     • To handle and move all this inventory, automated or semi
       automated materials handling equipment
       (conveyors, forklifts) is required, which takes even more
       space.
•   JIT
     • Equipment is moved as close together as possible so that
       parts can be actually handed from one worker or machine
       to the next.
     • Use of cells, and flow lines dictates small lots of parts with
       minimal work-in-process and material-moving equipment.
INVENTORIES



•   Traditional
     • used to buffer operations
     • large WIP buffers


•   JIT
     • inventory is seen as an evil
     • small WIP buffers
WORKFORCE

•   Traditional
     • competitive attitude between workers and managers
     • status symbols and privileges
     • much of the employees’ time is wasted looking for parts,
       moving materials, setting up machines, getting instructions,
       and so on. When actually working, they tend to work fast.
•   JIT
     • broadly skilled flexible workers who can uncover and solve
       problems
     • work teams
     • cooperative attitudes
ADVANTAGES

•   Just-in-time manufacturing keeps stock holding costs to a bare minimum.


•   The release of storage space results in better utilization of space and thereby
    bears a favorable impact on the rent paid


•   Just-in-time manufacturing eliminates waste, as out-of-date or expired
    products; do not enter into this equation at all.


•   As under this technique, only essential stocks are obtained, less working
    capital is required, to finance procurement.


•   Here, a minimum re-order level is set, and only once that mark is reached
    fresh stocks are ordered, making this a boon to inventory management too.


•   Due to the afore-mentioned low level of stocks held, the organizations return
    on investment (referred to as ROI, in management parlance) would
    generally be high.
•   As just-in-time production works on a demand-pull basis, all goods made
    would be sold, and thus it incorporates changes in demand with surprising
    ease.


•   This makes it especially appealing today, where the market demand is
    volatile and somewhat unpredictable.


•   High quality products and greater efficiency can be derived from following
    a just-in-time production system.


•   Close relationships are fostered along the production chain under a just-in-
    time manufacturing system.


•   Constant communication with the customer results in high customer
    satisfaction.


•   Over production is eliminated, when just-in-time manufacturing is adopted.
DISADVANTAGES

•   Just-in-time manufacturing provides zero tolerance for mistakes, as it makes
    re-working very difficult in practice, as inventory is kept to a bare minimum.


•   There is a high reliance on suppliers, whose performance is generally outside
    the purview of the manufacturer.


•   Due to there being no buffers for delays, production downtime and line
    idling can occur, which would bear a detrimental effect on finances and on
    the equilibrium of the production process.


•   The organization would not be able to meet an unexpected increase in
    orders, due to the fact that there are no excess finish goods.


•   Transaction costs would be relatively high, as frequent transactions would be
    made.
•   Just-in-time manufacturing may have certain detrimental effects on the
    environment, due to the frequent deliveries that would result in increased
    use of transportation which in turn would consume more fossil fuels.
PRECAUTIONS
•   Management buy-in and support at all levels of the organization
    are required, if a just-in-time manufacturing system is to be
    successfully adopted.


•   Adequate resources should be allocated, so as to obtain
    technologically advanced software.


•   Building a close, trusting relationship with reputed and time-tested
    suppliers will minimize unexpected delays in the receipt of inventory.


•   Just-in-time manufacturing cannot be adopted overnight. It requires
    commitment in terms of time and adjustments to corporate culture
    would be required, as it is starkly different to traditional production
    processes.
•   Lot sizes need to be minimized.


•   Work station capacity should be balanced whenever possible.


•   Preventive maintenance should be carried out, so as to
    minimize machine breakdowns.


•   Set up times should be reduced wherever possible.


•   Quality enhancement programs should be adopted, so that
    total quality control practices can be adopted.
•   Reduction in lead times and frequent deliveries should be
    incorporated.


•   Motion waste should be minimized, so the incorporation of
    conveyor belts might prove to be a good idea when
    implementing a just-in-time manufacturing system.


•   The design flow process needs to be redesigned and layouts
    need to be re-formatted, so as to incorporate just-in-time
    manufacturing.
KANBAN

•   Kanban is a card that represents a unit of work


•   Flow work in single units or small batches


•   Pace the work by limiting WIP


•   Use signaling to trigger pull


•   New work can start only when a space is available
•   A space becomes available when previous work is complete


•   Level of mix and quantity to spread risk and optimize portfolio


•   In ‘push’ system of production start date and finish date is
    planned up front


•   But we don’t know what we need to build and how long it will
    take to build
•   WorkCentre B uses parts
    produced by WorkCentre A


•   How can we control the
    flow so that B always has
    parts and A doesn’t
    overproduce ??
Signal To Produce

•   When a container is
    opened by WorkCentre B,
    its kanban card is sent back
    to WorkCentre A


•   This is a signal to
    WorkCentre A to produce
    another box of parts
Signal To Pull

•   Empty box sent back.
    Signal to pull another full
    box to WorkCentre B
REFERENCES

•   http://en.wikipedia.org/wiki/Just_in_time_(business)
•   http://www.investopedia.com/terms/j/jit.asp
•   http://www.toyota-
    global.com/company/vision_philosophy/toyota_production_syst
    em/just-in-time.html
•   http://www.tutebox.com/3309/business/management/introduct
    ion-to-jit-just-in-time-concept/
•   http://www.ijest.info/docs/IJEST10-02-01-06.pdf
•   http://www.articlesbase.com/business-ideas-articles/the-
    concept-of-just-in-time-management-1879039.html
•   http://www.cir-q-tech.net/Lean-Manufacturing/just-in-time-
    Kaizen

More Related Content

What's hot

Just In Time and Lean Operation Chapter Presentation
Just In Time and Lean Operation Chapter PresentationJust In Time and Lean Operation Chapter Presentation
Just In Time and Lean Operation Chapter Presentation
SINGHZEE
 
Slide Show Week #9 Chapter 11 Jit
Slide Show Week #9 Chapter 11 JitSlide Show Week #9 Chapter 11 Jit
Slide Show Week #9 Chapter 11 Jitsree19881988
 
Just In Time Production (JIT)
Just In Time Production (JIT)Just In Time Production (JIT)
Just In Time Production (JIT)
Arunnima B S
 
Just In Time (jit) inventory management
Just In Time (jit) inventory managementJust In Time (jit) inventory management
Just In Time (jit) inventory management
iWriteEssays
 
JIT and lean operations
JIT and lean operationsJIT and lean operations
JIT and lean operations
RajThakuri
 
Jit
JitJit
Just-In-Time
Just-In-TimeJust-In-Time
Just-In-Time
Raj Shravanthi
 
Just in time technology (JIT)
Just in time technology (JIT)Just in time technology (JIT)
Just in time technology (JIT)
Akash Dutta
 
Just in time manufacturing ppt
Just in time manufacturing pptJust in time manufacturing ppt
Just in time manufacturing ppt
Swati Luthra
 
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh AroraIntroduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
ADD VALUE CONSULTING Inc
 
Just in Time and Lean Manufacturing
Just in Time and Lean ManufacturingJust in Time and Lean Manufacturing
Just in Time and Lean Manufacturing
shahroze11
 
Just In Time and Lean Management
Just In Time and Lean ManagementJust In Time and Lean Management
Just In Time and Lean ManagementRuhi Beri
 
just in time
just in timejust in time
just in time manufacturing
just in time manufacturingjust in time manufacturing
just in time manufacturing
ALIGARH MUSLIM UNIVERSITY
 
Jit (us), kanban, lean
Jit (us), kanban, leanJit (us), kanban, lean
Jit (us), kanban, leanNishit Patel
 
Just in time
Just in timeJust in time
Just in time
Navdeep Asteya
 
Lean Management and Kanban System
Lean Management and Kanban SystemLean Management and Kanban System
Lean Management and Kanban System
Gaurav Singh
 

What's hot (20)

Just In Time and Lean Operation Chapter Presentation
Just In Time and Lean Operation Chapter PresentationJust In Time and Lean Operation Chapter Presentation
Just In Time and Lean Operation Chapter Presentation
 
Slide Show Week #9 Chapter 11 Jit
Slide Show Week #9 Chapter 11 JitSlide Show Week #9 Chapter 11 Jit
Slide Show Week #9 Chapter 11 Jit
 
Just In Time Production (JIT)
Just In Time Production (JIT)Just In Time Production (JIT)
Just In Time Production (JIT)
 
Jit systems
Jit systemsJit systems
Jit systems
 
Just In Time (jit) inventory management
Just In Time (jit) inventory managementJust In Time (jit) inventory management
Just In Time (jit) inventory management
 
JIT and lean operations
JIT and lean operationsJIT and lean operations
JIT and lean operations
 
Jit
JitJit
Jit
 
Just-In-Time
Just-In-TimeJust-In-Time
Just-In-Time
 
Just in time technology (JIT)
Just in time technology (JIT)Just in time technology (JIT)
Just in time technology (JIT)
 
Just in time
Just in timeJust in time
Just in time
 
Just in time manufacturing ppt
Just in time manufacturing pptJust in time manufacturing ppt
Just in time manufacturing ppt
 
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh AroraIntroduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
Introduction of Flow Management in Manufacturing - ADDVALUE - Nilesh Arora
 
Just in Time and Lean Manufacturing
Just in Time and Lean ManufacturingJust in Time and Lean Manufacturing
Just in Time and Lean Manufacturing
 
Just In Time and Lean Management
Just In Time and Lean ManagementJust In Time and Lean Management
Just In Time and Lean Management
 
just in time
just in timejust in time
just in time
 
just in time manufacturing
just in time manufacturingjust in time manufacturing
just in time manufacturing
 
Jit (us), kanban, lean
Jit (us), kanban, leanJit (us), kanban, lean
Jit (us), kanban, lean
 
Just in time
Just in timeJust in time
Just in time
 
Lean Management and Kanban System
Lean Management and Kanban SystemLean Management and Kanban System
Lean Management and Kanban System
 
Lean Production
Lean ProductionLean Production
Lean Production
 

Viewers also liked

End User Computing (EUC)
End User Computing (EUC)End User Computing (EUC)
End User Computing (EUC)
Jashisha Gupta
 
Six Sigma - A Presentation by Akshay Anand
Six Sigma - A Presentation by Akshay AnandSix Sigma - A Presentation by Akshay Anand
Six Sigma - A Presentation by Akshay Anand
Akshay Anand
 
End User Computing
End User ComputingEnd User Computing
End User Computing
Mudit Dhebar
 
MRP
MRPMRP
Six sigma and mumbai dabbawala
Six sigma and mumbai dabbawalaSix sigma and mumbai dabbawala
Six sigma and mumbai dabbawalaSandeep Mane
 
Material requirement planning presentation
Material requirement planning presentationMaterial requirement planning presentation
Material requirement planning presentationjhanakshah
 
4. materials requirement planning
4. materials requirement planning4. materials requirement planning
4. materials requirement planningkunal.kakkad
 
Management Information System (MIS)
Management Information System (MIS)Management Information System (MIS)
Management Information System (MIS)
Navneet Jingar
 
Management information system
Management information systemManagement information system
Management information system
Sikander Saini
 

Viewers also liked (13)

Six Sigma
Six SigmaSix Sigma
Six Sigma
 
End User Computing (EUC)
End User Computing (EUC)End User Computing (EUC)
End User Computing (EUC)
 
Six Sigma - A Presentation by Akshay Anand
Six Sigma - A Presentation by Akshay AnandSix Sigma - A Presentation by Akshay Anand
Six Sigma - A Presentation by Akshay Anand
 
Mrp 1
Mrp 1Mrp 1
Mrp 1
 
End User Computing
End User ComputingEnd User Computing
End User Computing
 
MRP
MRPMRP
MRP
 
Contemporary Management
Contemporary ManagementContemporary Management
Contemporary Management
 
Tqm and six sigma
Tqm and six sigmaTqm and six sigma
Tqm and six sigma
 
Six sigma and mumbai dabbawala
Six sigma and mumbai dabbawalaSix sigma and mumbai dabbawala
Six sigma and mumbai dabbawala
 
Material requirement planning presentation
Material requirement planning presentationMaterial requirement planning presentation
Material requirement planning presentation
 
4. materials requirement planning
4. materials requirement planning4. materials requirement planning
4. materials requirement planning
 
Management Information System (MIS)
Management Information System (MIS)Management Information System (MIS)
Management Information System (MIS)
 
Management information system
Management information systemManagement information system
Management information system
 

Similar to Just in time

EngManagement-Lecture 9.pptx
EngManagement-Lecture 9.pptxEngManagement-Lecture 9.pptx
EngManagement-Lecture 9.pptx
shayanzafar2
 
Just in time
Just in timeJust in time
Just in time
Avish Shah
 
Chapter 1 pom
Chapter 1 pomChapter 1 pom
Chapter 1 pom
Shalini Krishna
 
Operation management
Operation managementOperation management
Operation managementMamta Karanji
 
Dr. rajesha. pom 1st module-buc
Dr. rajesha. pom 1st module-bucDr. rajesha. pom 1st module-buc
Dr. rajesha. pom 1st module-buc
Dr. Rajesha Shivaramegowda
 
lean manufacturing.ppt cost profit accounts
lean manufacturing.ppt cost profit accountslean manufacturing.ppt cost profit accounts
lean manufacturing.ppt cost profit accounts
SabaKhalid48
 
Types of layout
Types of layoutTypes of layout
Types of layout
Ebenezer Raja
 
1ST MODULE PRODUCTION MANAGEMENT AND OPERATION RESEARCH
1ST MODULE PRODUCTION MANAGEMENT AND OPERATION RESEARCH1ST MODULE PRODUCTION MANAGEMENT AND OPERATION RESEARCH
1ST MODULE PRODUCTION MANAGEMENT AND OPERATION RESEARCH
Dr. Rajesha Shivaramegowda
 
Facility Layout,PPT.pptx
Facility Layout,PPT.pptxFacility Layout,PPT.pptx
Facility Layout,PPT.pptx
SakhawatHossainRony
 
Jit and lean operations
Jit and lean operationsJit and lean operations
Jit and lean operationsSumit Malhotra
 
Lean - PPT (Lean manufacturing and six sigma)
Lean - PPT (Lean manufacturing and six sigma)Lean - PPT (Lean manufacturing and six sigma)
Lean - PPT (Lean manufacturing and six sigma)
Blankdevil
 
Mba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection aMba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection a
Rai University
 
JIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
JIT & Lean Manufacturing - ADDVALUE - Nilesh AroraJIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
JIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
ADD VALUE CONSULTING Inc
 
Production planning and control - PPC
Production planning and control - PPCProduction planning and control - PPC
Production planning and control - PPC
The Learning Hub
 
Presentation on Just in Time
Presentation on Just in TimePresentation on Just in Time
Presentation on Just in Time
Musfiqur Rahman
 
Just in time
Just in timeJust in time
Just in timeyashpalsg
 
Production management
Production managementProduction management
Production management
shreenibasa maharana
 
Lean DL Arsene
Lean DL ArseneLean DL Arsene
Lean DL ArseneLuciArsene
 
BBA UNIT -1 INTRODUCTION ABOUT PRODUCTION.ppt
BBA UNIT -1 INTRODUCTION ABOUT PRODUCTION.pptBBA UNIT -1 INTRODUCTION ABOUT PRODUCTION.ppt
BBA UNIT -1 INTRODUCTION ABOUT PRODUCTION.ppt
Chandramouli Seetharaman
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.ppt
SandipanMaji3
 

Similar to Just in time (20)

EngManagement-Lecture 9.pptx
EngManagement-Lecture 9.pptxEngManagement-Lecture 9.pptx
EngManagement-Lecture 9.pptx
 
Just in time
Just in timeJust in time
Just in time
 
Chapter 1 pom
Chapter 1 pomChapter 1 pom
Chapter 1 pom
 
Operation management
Operation managementOperation management
Operation management
 
Dr. rajesha. pom 1st module-buc
Dr. rajesha. pom 1st module-bucDr. rajesha. pom 1st module-buc
Dr. rajesha. pom 1st module-buc
 
lean manufacturing.ppt cost profit accounts
lean manufacturing.ppt cost profit accountslean manufacturing.ppt cost profit accounts
lean manufacturing.ppt cost profit accounts
 
Types of layout
Types of layoutTypes of layout
Types of layout
 
1ST MODULE PRODUCTION MANAGEMENT AND OPERATION RESEARCH
1ST MODULE PRODUCTION MANAGEMENT AND OPERATION RESEARCH1ST MODULE PRODUCTION MANAGEMENT AND OPERATION RESEARCH
1ST MODULE PRODUCTION MANAGEMENT AND OPERATION RESEARCH
 
Facility Layout,PPT.pptx
Facility Layout,PPT.pptxFacility Layout,PPT.pptx
Facility Layout,PPT.pptx
 
Jit and lean operations
Jit and lean operationsJit and lean operations
Jit and lean operations
 
Lean - PPT (Lean manufacturing and six sigma)
Lean - PPT (Lean manufacturing and six sigma)Lean - PPT (Lean manufacturing and six sigma)
Lean - PPT (Lean manufacturing and six sigma)
 
Mba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection aMba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection a
 
JIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
JIT & Lean Manufacturing - ADDVALUE - Nilesh AroraJIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
JIT & Lean Manufacturing - ADDVALUE - Nilesh Arora
 
Production planning and control - PPC
Production planning and control - PPCProduction planning and control - PPC
Production planning and control - PPC
 
Presentation on Just in Time
Presentation on Just in TimePresentation on Just in Time
Presentation on Just in Time
 
Just in time
Just in timeJust in time
Just in time
 
Production management
Production managementProduction management
Production management
 
Lean DL Arsene
Lean DL ArseneLean DL Arsene
Lean DL Arsene
 
BBA UNIT -1 INTRODUCTION ABOUT PRODUCTION.ppt
BBA UNIT -1 INTRODUCTION ABOUT PRODUCTION.pptBBA UNIT -1 INTRODUCTION ABOUT PRODUCTION.ppt
BBA UNIT -1 INTRODUCTION ABOUT PRODUCTION.ppt
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.ppt
 

Recently uploaded

Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
HARSHITHV26
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
Naaraayani Minerals Pvt.Ltd
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
SynapseIndia
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
Sam H
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Jos Voskuil
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
my Pandit
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
dylandmeas
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
awaisafdar
 
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop.com LTD
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
PaulBryant58
 
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
Kumar Satyam
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 
Lookback Analysis
Lookback AnalysisLookback Analysis
Lookback Analysis
Safe PaaS
 
chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
AUDIJEAngelo
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
YourLegal Accounting
 

Recently uploaded (20)

Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
 
PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024PriyoShop Celebration Pohela Falgun Mar 20, 2024
PriyoShop Celebration Pohela Falgun Mar 20, 2024
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
 
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 
Lookback Analysis
Lookback AnalysisLookback Analysis
Lookback Analysis
 
chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
 

Just in time

  • 1. Latest Trends In Operations Management Just In Time Sannik Seemoli Ganatra Shashank Saptha Anju Maria John Mahale Akshay Uday
  • 2. WHAT IS JUST IN TIME ???? • Producing the quantity if goods that is needed, no more, no less • Producing them on the date and at the time required, not before, not after. • Suppliers deliver the exact quantity demanded, at scheduled time and date • Just in time is a ‘pull’ system of production. • Demand-pull enables a firm to produce only what is required, in the correct quantity and at the correct time.
  • 3. This requires a carefully planned scheduling and flow of resources through the production process. • Modern manufacturing firms use sophisticated production scheduling software to plan production for each period of time,. • Information is exchanged with suppliers and customers through EDI (Electronic Data Interchange) to help ensure that every detail is correct. • For example, a car manufacturing plant might receive exactly the right number and type of tyres for one day’s production
  • 4. A lean system works best if the daily load on individual workstations is relatively uniform Uniform loads can be achieved by assembling the same type and number of units each day, thus creating a uniform daily demand at all workstations Workers should be trained to operate several machines, to perform maintenance tasks, and to perform quality inspections Use effective machines but the key is to use machine and worker idle time to maintain equipment and prevent break downs
  • 6. PRIORITIES • Traditionally • Accept all customer orders • Provide a large number of options from which customers may order • JIT • low cost/high quality within limited market
  • 7. ENGINEERING • Traditional • design custom outputs • JIT • design standard outputs • incremental improvements • design for manufacturability (DFM)
  • 8. CAPACITY • Traditional • excess capacity designed into system just-in-case problem arises • highly utilized • inflexible • JIT • minimize waste of having extra capacity • flexible capacity • moderately utilized
  • 9. TRANSFORMATION SYSTEM • Traditional- • long lead times are often thought to allow more time to make decisions and get work performed . • JIT • short lead times mean easier, more accurate forecasting and planning. • If lead times are reduced, there is less time for things go awry, to get lost, or to be changed • “Don’t let the parts touch the floor” (the parts have to be kept on the machines and thus be worked on until completed) • Smaller batches result in shorter lead times and less inventory, at the same time. With smaller batches, engineering changes get to the customer sooner, problems with quality are corrected more quickly, rework is reduced, there is less obsolete inventory, and new products get to market more promptly .
  • 10. LAYOUT • Traditional • job shop approach of using widely spread-out equipment with space for stockrooms, tool cribs, and work-in-process inventories between the equipment • To handle and move all this inventory, automated or semi automated materials handling equipment (conveyors, forklifts) is required, which takes even more space. • JIT • Equipment is moved as close together as possible so that parts can be actually handed from one worker or machine to the next. • Use of cells, and flow lines dictates small lots of parts with minimal work-in-process and material-moving equipment.
  • 11. INVENTORIES • Traditional • used to buffer operations • large WIP buffers • JIT • inventory is seen as an evil • small WIP buffers
  • 12. WORKFORCE • Traditional • competitive attitude between workers and managers • status symbols and privileges • much of the employees’ time is wasted looking for parts, moving materials, setting up machines, getting instructions, and so on. When actually working, they tend to work fast. • JIT • broadly skilled flexible workers who can uncover and solve problems • work teams • cooperative attitudes
  • 13.
  • 14.
  • 15. ADVANTAGES • Just-in-time manufacturing keeps stock holding costs to a bare minimum. • The release of storage space results in better utilization of space and thereby bears a favorable impact on the rent paid • Just-in-time manufacturing eliminates waste, as out-of-date or expired products; do not enter into this equation at all. • As under this technique, only essential stocks are obtained, less working capital is required, to finance procurement. • Here, a minimum re-order level is set, and only once that mark is reached fresh stocks are ordered, making this a boon to inventory management too. • Due to the afore-mentioned low level of stocks held, the organizations return on investment (referred to as ROI, in management parlance) would generally be high.
  • 16. As just-in-time production works on a demand-pull basis, all goods made would be sold, and thus it incorporates changes in demand with surprising ease. • This makes it especially appealing today, where the market demand is volatile and somewhat unpredictable. • High quality products and greater efficiency can be derived from following a just-in-time production system. • Close relationships are fostered along the production chain under a just-in- time manufacturing system. • Constant communication with the customer results in high customer satisfaction. • Over production is eliminated, when just-in-time manufacturing is adopted.
  • 17. DISADVANTAGES • Just-in-time manufacturing provides zero tolerance for mistakes, as it makes re-working very difficult in practice, as inventory is kept to a bare minimum. • There is a high reliance on suppliers, whose performance is generally outside the purview of the manufacturer. • Due to there being no buffers for delays, production downtime and line idling can occur, which would bear a detrimental effect on finances and on the equilibrium of the production process. • The organization would not be able to meet an unexpected increase in orders, due to the fact that there are no excess finish goods. • Transaction costs would be relatively high, as frequent transactions would be made. • Just-in-time manufacturing may have certain detrimental effects on the environment, due to the frequent deliveries that would result in increased use of transportation which in turn would consume more fossil fuels.
  • 18. PRECAUTIONS • Management buy-in and support at all levels of the organization are required, if a just-in-time manufacturing system is to be successfully adopted. • Adequate resources should be allocated, so as to obtain technologically advanced software. • Building a close, trusting relationship with reputed and time-tested suppliers will minimize unexpected delays in the receipt of inventory. • Just-in-time manufacturing cannot be adopted overnight. It requires commitment in terms of time and adjustments to corporate culture would be required, as it is starkly different to traditional production processes.
  • 19. Lot sizes need to be minimized. • Work station capacity should be balanced whenever possible. • Preventive maintenance should be carried out, so as to minimize machine breakdowns. • Set up times should be reduced wherever possible. • Quality enhancement programs should be adopted, so that total quality control practices can be adopted.
  • 20. Reduction in lead times and frequent deliveries should be incorporated. • Motion waste should be minimized, so the incorporation of conveyor belts might prove to be a good idea when implementing a just-in-time manufacturing system. • The design flow process needs to be redesigned and layouts need to be re-formatted, so as to incorporate just-in-time manufacturing.
  • 21. KANBAN • Kanban is a card that represents a unit of work • Flow work in single units or small batches • Pace the work by limiting WIP • Use signaling to trigger pull • New work can start only when a space is available
  • 22. A space becomes available when previous work is complete • Level of mix and quantity to spread risk and optimize portfolio • In ‘push’ system of production start date and finish date is planned up front • But we don’t know what we need to build and how long it will take to build
  • 23.
  • 24.
  • 25.
  • 26.
  • 27. WorkCentre B uses parts produced by WorkCentre A • How can we control the flow so that B always has parts and A doesn’t overproduce ??
  • 28. Signal To Produce • When a container is opened by WorkCentre B, its kanban card is sent back to WorkCentre A • This is a signal to WorkCentre A to produce another box of parts
  • 29. Signal To Pull • Empty box sent back. Signal to pull another full box to WorkCentre B
  • 30. REFERENCES • http://en.wikipedia.org/wiki/Just_in_time_(business) • http://www.investopedia.com/terms/j/jit.asp • http://www.toyota- global.com/company/vision_philosophy/toyota_production_syst em/just-in-time.html • http://www.tutebox.com/3309/business/management/introduct ion-to-jit-just-in-time-concept/ • http://www.ijest.info/docs/IJEST10-02-01-06.pdf • http://www.articlesbase.com/business-ideas-articles/the- concept-of-just-in-time-management-1879039.html • http://www.cir-q-tech.net/Lean-Manufacturing/just-in-time- Kaizen