SlideShare a Scribd company logo
ELECTRICAL POWER
GENERATION
Load curve and Important terms
By D. N. Thakkar
RCTI, Ahmedabad
Connected load
• The sum of continuous ratings of all the
electrical equipments connected to the supply
system is called the connected load
Demand Factor.
• The word “demand” itself says the meaning of
Demand Factor. Demand Factor = Maximum
demand / Total connected load
• For example, an over sized motor 20 Kw drives a
constant 15 Kw load whenever it is ON. The
motor demand factor is then 15/20 =0.75= 75 %.
• Demand Factor is express as a percentage (%) or
in a ratio
• Demand factor is always < =1.
• The lower the demand factor, the less system
capacity required to serve the connected load.
Load factor
• Load Factor = Actual Load / Full Load
• OR
• Load Factor = Area under the curve / Area of
the rectangle
• OR
• Load Factor = Units generated / (Maximum
demand x hours)
Load factor
• It is the ratio of actual kilowatt-Hours used in
a given period, divided by the total possible
kilowatt -hours that could have been used in
the same period at the peak KW level.
• Load Factor = ( energy (kWh per month) ) /
( peak demand (kW) x hours/month )
• The Load factor is always <=1.
Load factor
• Higher the load factor is GOOD and it will more
Output of Plan, lesser the cost per unit which
means an electricity generator can sell more
electricity at a higher spark spread, Fixed costs
are spread over more kWh of output. A power
plant may be highly efficient at High load factors.
• Low load factor is a BED. A low load factor will
use electricity inefficiently relative to what we
could be if we were controlling our peak demand.
A power plant may be less efficient at low load
factors.
Connected load factor
Connected load factor = Average load /
connected load
= (Average demand / Maximum demand) x
(Maximum demand / connected load)
= Load factor x Demand factor
Diversity factor
• Diversity Factor = Sum of Individual
Maximum Demands / Maximum Demand of
the System.
• The diversity factor is always >= 1.
Coincidence factor
• The reciprocal of diversity factor is
coincidence factor
• Coincidence factor = Maximum demand /
Sum of individual maximum demands
• The Coincidence Factor is always <=1.
Load diversity
• Load diversity is the difference of sum of
individual maximum demands of two or more
consumers and their combined maximum
demand
Loss factor
Loss factor = Average power loss / Power loss at
peak load
Plant capacity factor
Plant capacity factor = Average demand /
Installed plant capacity
OR
Plant capacity factor = Units generated in a year
/ Installed plant capacity x 8760
Utilization factor
Utilization factor = Maximum demand / Plant
capacity
Plant use factor
Plant use factor = Units generated / ∑kWh
= Units generated / kW1h1+kW2h2+….
Load curve
Load curve is the variation
of load with time on a
Power Station. As the load
on a Power Station never
remain constant rather it
varies time to time, these
variations in load is plotted
on half hourly or hourly
basis for the whole day. The
curve thus obtained is
known as Daily Load Curve.
Importance of Load Curve
• From the daily load curve we can have insight of load at different time for a
day.
• The area under the daily load curve gives the total units of electric energy
generated.
• Units Generated / day = Area under the daily Load Curve in kW
• The peak point on the daily load curve gives the highest demand on the
Power Station for that day.
• The average load per day on the Power Station can be calculated using the
daily load curve.
• Average load = Area under the daily Load Curve (kWh)/ 24 hrs.
• Load curve helps in deciding the size and number of Generating Units.
• Load Factor = Avg. Load / maximum Load = Avg. Load x24 / 24xmaximum
Load
• = Area under daily Load Curve/Area of Rectangle having Daily
Load Curve
• Load curve helps in the preparing the operation schedule of the generating
units.
Load Duration Curve
• Load Duration Curve is the plot of Load versus
time duration for which that load was
persisting.
Base load & Peak load
• Base load is the minimum level of electricity
demand required over a period of 24 hours. It
is needed to provide power to components
that keep running at all times (also referred as
continuous load). Peak load is the time of
high demand.
Base load & Peak load
Base load & Peak load
Characteristics of Base load station
• Operating throughout the year
• Load factor is high
• Efficiency is high
• Cost of unit generation is less
• Capital cost is high
• Capacity is high
• Difficult to start and stop
TPS in Gujarat

More Related Content

What's hot

Single line diagram
Single line diagramSingle line diagram
Single line diagram
Md. Rimon Mia
 
Active, reactive and apparent power
Active, reactive and apparent powerActive, reactive and apparent power
Active, reactive and apparent power
Sourabh sharma
 
Tripping and control of impulse generators
Tripping and control of impulse generatorsTripping and control of impulse generators
Tripping and control of impulse generators
Fariza Zahari
 
Transient in Power system
Transient in Power systemTransient in Power system
Transient in Power system
Preet_patel
 
Transformer protection
Transformer protectionTransformer protection
Transformer protection
jawaharramaya
 
Power factor
Power factorPower factor
Power factor
NAVEEN KOREDDI
 
Distribution System
Distribution SystemDistribution System
Distribution System
Kupusaami Anbumani
 
DISTRIBUTED GENERATION TECHNOLOGIES
DISTRIBUTED GENERATION TECHNOLOGIESDISTRIBUTED GENERATION TECHNOLOGIES
DISTRIBUTED GENERATION TECHNOLOGIES
Editor IJMTER
 
economics of power generation
economics of power generationeconomics of power generation
economics of power generation
jagniyant
 
Voltage and Frequency Control of the Grid
Voltage and Frequency Control of the GridVoltage and Frequency Control of the Grid
Voltage and Frequency Control of the Grid
Leonardo ENERGY
 
Electric traction ppt
Electric traction pptElectric traction ppt
Electric traction ppt
ragulkncet
 
Demand side management
Demand side managementDemand side management
Demand side management
Shivraj Nalawade
 
Types Of Substations
Types Of SubstationsTypes Of Substations
Types Of Substations
sapna186
 
Power systems voltage and power control
Power systems voltage and power controlPower systems voltage and power control
Power systems voltage and power control
Caner Göksel Sonuzun
 
Planning and modern trends in hvdc
Planning and modern trends in hvdcPlanning and modern trends in hvdc
Planning and modern trends in hvdc
jawaharramaya
 
Distribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationDistribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss Calculation
Ameen San
 
Introduction
IntroductionIntroduction
Introduction
jawaharramaya
 
Alternator protection
Alternator protectionAlternator protection
Alternator protection
jawaharramaya
 
Power factor improvement
Power factor improvement Power factor improvement
Power factor improvement
Saiful Islam Rukon
 
Skin effect, proximity effect, ferranti effect, corona discharge
Skin effect, proximity effect, ferranti effect, corona dischargeSkin effect, proximity effect, ferranti effect, corona discharge
Skin effect, proximity effect, ferranti effect, corona discharge
RoungpaSukhe
 

What's hot (20)

Single line diagram
Single line diagramSingle line diagram
Single line diagram
 
Active, reactive and apparent power
Active, reactive and apparent powerActive, reactive and apparent power
Active, reactive and apparent power
 
Tripping and control of impulse generators
Tripping and control of impulse generatorsTripping and control of impulse generators
Tripping and control of impulse generators
 
Transient in Power system
Transient in Power systemTransient in Power system
Transient in Power system
 
Transformer protection
Transformer protectionTransformer protection
Transformer protection
 
Power factor
Power factorPower factor
Power factor
 
Distribution System
Distribution SystemDistribution System
Distribution System
 
DISTRIBUTED GENERATION TECHNOLOGIES
DISTRIBUTED GENERATION TECHNOLOGIESDISTRIBUTED GENERATION TECHNOLOGIES
DISTRIBUTED GENERATION TECHNOLOGIES
 
economics of power generation
economics of power generationeconomics of power generation
economics of power generation
 
Voltage and Frequency Control of the Grid
Voltage and Frequency Control of the GridVoltage and Frequency Control of the Grid
Voltage and Frequency Control of the Grid
 
Electric traction ppt
Electric traction pptElectric traction ppt
Electric traction ppt
 
Demand side management
Demand side managementDemand side management
Demand side management
 
Types Of Substations
Types Of SubstationsTypes Of Substations
Types Of Substations
 
Power systems voltage and power control
Power systems voltage and power controlPower systems voltage and power control
Power systems voltage and power control
 
Planning and modern trends in hvdc
Planning and modern trends in hvdcPlanning and modern trends in hvdc
Planning and modern trends in hvdc
 
Distribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationDistribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss Calculation
 
Introduction
IntroductionIntroduction
Introduction
 
Alternator protection
Alternator protectionAlternator protection
Alternator protection
 
Power factor improvement
Power factor improvement Power factor improvement
Power factor improvement
 
Skin effect, proximity effect, ferranti effect, corona discharge
Skin effect, proximity effect, ferranti effect, corona dischargeSkin effect, proximity effect, ferranti effect, corona discharge
Skin effect, proximity effect, ferranti effect, corona discharge
 

Similar to Load factor and demand factor

Lecture 7 load duration curves
Lecture 7 load duration curvesLecture 7 load duration curves
Lecture 7 load duration curves
Swapnil Gadgune
 
Lecture 8 load duration curves
Lecture 8 load duration curvesLecture 8 load duration curves
Lecture 8 load duration curves
Swapnil Gadgune
 
Economic Aspects.docx
Economic Aspects.docxEconomic Aspects.docx
Economic Aspects.docx
ArpitaBanik8
 
Power station
Power stationPower station
Power station
Sirat Mahmood
 
Unit-5.pptx
Unit-5.pptxUnit-5.pptx
Unit-5.pptx
ssuserd0df33
 
Economics of power plant
Economics of power plantEconomics of power plant
Economics of power plant
Dr. Rohit Singh Lather, Ph.D.
 
Economics of Power Generation
Economics of Power GenerationEconomics of Power Generation
Economics of Power Generation
Niraj Solanki
 
Economics of power generation
Economics of power generationEconomics of power generation
Economics of power generation
Maharishi Tiwari
 
diversity
diversitydiversity
diversity
Syed Ahamed
 
Shreelakshmi(power).pptx
Shreelakshmi(power).pptxShreelakshmi(power).pptx
Shreelakshmi(power).pptx
surbhi agarwal
 
Energy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsEnergy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plants
Balamurugan Subburaj
 
Tarrif and load curves
Tarrif and load curvesTarrif and load curves
Tarrif and load curves
GPERI
 
Load on Power Station from power sytem engineering
Load on Power Station from power sytem engineeringLoad on Power Station from power sytem engineering
Load on Power Station from power sytem engineering
DIGESHSHAH9
 
Power system -Economic Aspect of Electric power Genration
Power system -Economic Aspect of Electric power Genration Power system -Economic Aspect of Electric power Genration
Power system -Economic Aspect of Electric power Genration
Prof.Nagnath Khandekar
 
PRAYAS.pptx
PRAYAS.pptxPRAYAS.pptx
PRAYAS.pptx
KhushbooMadaan8
 
SodaPDF-converted-Copy of PSOC-unit1.ppt
SodaPDF-converted-Copy of PSOC-unit1.pptSodaPDF-converted-Copy of PSOC-unit1.ppt
SodaPDF-converted-Copy of PSOC-unit1.ppt
swathisriranjani1
 
Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1
NBoss
 
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxLecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
FelcherLayugan
 
Copy of PSOC-unit1.pdf
Copy of PSOC-unit1.pdfCopy of PSOC-unit1.pdf
Copy of PSOC-unit1.pdf
ShubhamVerma961456
 
12201619008_PEG_GouravSingh.pdf
12201619008_PEG_GouravSingh.pdf12201619008_PEG_GouravSingh.pdf
12201619008_PEG_GouravSingh.pdf
NiladreePaul1
 

Similar to Load factor and demand factor (20)

Lecture 7 load duration curves
Lecture 7 load duration curvesLecture 7 load duration curves
Lecture 7 load duration curves
 
Lecture 8 load duration curves
Lecture 8 load duration curvesLecture 8 load duration curves
Lecture 8 load duration curves
 
Economic Aspects.docx
Economic Aspects.docxEconomic Aspects.docx
Economic Aspects.docx
 
Power station
Power stationPower station
Power station
 
Unit-5.pptx
Unit-5.pptxUnit-5.pptx
Unit-5.pptx
 
Economics of power plant
Economics of power plantEconomics of power plant
Economics of power plant
 
Economics of Power Generation
Economics of Power GenerationEconomics of Power Generation
Economics of Power Generation
 
Economics of power generation
Economics of power generationEconomics of power generation
Economics of power generation
 
diversity
diversitydiversity
diversity
 
Shreelakshmi(power).pptx
Shreelakshmi(power).pptxShreelakshmi(power).pptx
Shreelakshmi(power).pptx
 
Energy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsEnergy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plants
 
Tarrif and load curves
Tarrif and load curvesTarrif and load curves
Tarrif and load curves
 
Load on Power Station from power sytem engineering
Load on Power Station from power sytem engineeringLoad on Power Station from power sytem engineering
Load on Power Station from power sytem engineering
 
Power system -Economic Aspect of Electric power Genration
Power system -Economic Aspect of Electric power Genration Power system -Economic Aspect of Electric power Genration
Power system -Economic Aspect of Electric power Genration
 
PRAYAS.pptx
PRAYAS.pptxPRAYAS.pptx
PRAYAS.pptx
 
SodaPDF-converted-Copy of PSOC-unit1.ppt
SodaPDF-converted-Copy of PSOC-unit1.pptSodaPDF-converted-Copy of PSOC-unit1.ppt
SodaPDF-converted-Copy of PSOC-unit1.ppt
 
Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1
 
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxLecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
 
Copy of PSOC-unit1.pdf
Copy of PSOC-unit1.pdfCopy of PSOC-unit1.pdf
Copy of PSOC-unit1.pdf
 
12201619008_PEG_GouravSingh.pdf
12201619008_PEG_GouravSingh.pdf12201619008_PEG_GouravSingh.pdf
12201619008_PEG_GouravSingh.pdf
 

More from dhirajthakkar1

Wind power plant 1
Wind power plant 1Wind power plant 1
Wind power plant 1
dhirajthakkar1
 
Wind power plant 2
Wind power plant 2Wind power plant 2
Wind power plant 2
dhirajthakkar1
 
Chapter 5 Wind Power
Chapter 5 Wind PowerChapter 5 Wind Power
Chapter 5 Wind Power
dhirajthakkar1
 
Aerodynamic principle in wind turbine
Aerodynamic principle in wind turbineAerodynamic principle in wind turbine
Aerodynamic principle in wind turbine
dhirajthakkar1
 
Chapter 6 otec
Chapter 6 otecChapter 6 otec
Chapter 6 otec
dhirajthakkar1
 
Chapter 6 gtec
Chapter 6 gtecChapter 6 gtec
Chapter 6 gtec
dhirajthakkar1
 
Chapter 6 otpp
Chapter 6 otppChapter 6 otpp
Chapter 6 otpp
dhirajthakkar1
 
Chapter 6 biomass
Chapter 6 biomassChapter 6 biomass
Chapter 6 biomass
dhirajthakkar1
 
Chapter 6 gpp
Chapter 6 gppChapter 6 gpp
Chapter 6 gpp
dhirajthakkar1
 
Chap 5 wind power station
Chap 5 wind power stationChap 5 wind power station
Chap 5 wind power station
dhirajthakkar1
 
Chapter 6 dpp
Chapter 6 dppChapter 6 dpp
Chapter 6 dpp
dhirajthakkar1
 
Hydro power station
Hydro power stationHydro power station
Hydro power station
dhirajthakkar1
 
Examples on load curve
Examples on load curveExamples on load curve
Examples on load curve
dhirajthakkar1
 
Ohm's law
Ohm's lawOhm's law
Ohm's law
dhirajthakkar1
 
Epg chap 1 continue
Epg chap 1 continueEpg chap 1 continue
Epg chap 1 continue
dhirajthakkar1
 
Epg chap 1
Epg chap 1Epg chap 1
Epg chap 1
dhirajthakkar1
 

More from dhirajthakkar1 (16)

Wind power plant 1
Wind power plant 1Wind power plant 1
Wind power plant 1
 
Wind power plant 2
Wind power plant 2Wind power plant 2
Wind power plant 2
 
Chapter 5 Wind Power
Chapter 5 Wind PowerChapter 5 Wind Power
Chapter 5 Wind Power
 
Aerodynamic principle in wind turbine
Aerodynamic principle in wind turbineAerodynamic principle in wind turbine
Aerodynamic principle in wind turbine
 
Chapter 6 otec
Chapter 6 otecChapter 6 otec
Chapter 6 otec
 
Chapter 6 gtec
Chapter 6 gtecChapter 6 gtec
Chapter 6 gtec
 
Chapter 6 otpp
Chapter 6 otppChapter 6 otpp
Chapter 6 otpp
 
Chapter 6 biomass
Chapter 6 biomassChapter 6 biomass
Chapter 6 biomass
 
Chapter 6 gpp
Chapter 6 gppChapter 6 gpp
Chapter 6 gpp
 
Chap 5 wind power station
Chap 5 wind power stationChap 5 wind power station
Chap 5 wind power station
 
Chapter 6 dpp
Chapter 6 dppChapter 6 dpp
Chapter 6 dpp
 
Hydro power station
Hydro power stationHydro power station
Hydro power station
 
Examples on load curve
Examples on load curveExamples on load curve
Examples on load curve
 
Ohm's law
Ohm's lawOhm's law
Ohm's law
 
Epg chap 1 continue
Epg chap 1 continueEpg chap 1 continue
Epg chap 1 continue
 
Epg chap 1
Epg chap 1Epg chap 1
Epg chap 1
 

Recently uploaded

Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
PuktoonEngr
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 

Recently uploaded (20)

Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 

Load factor and demand factor

  • 1. ELECTRICAL POWER GENERATION Load curve and Important terms By D. N. Thakkar RCTI, Ahmedabad
  • 2. Connected load • The sum of continuous ratings of all the electrical equipments connected to the supply system is called the connected load
  • 3. Demand Factor. • The word “demand” itself says the meaning of Demand Factor. Demand Factor = Maximum demand / Total connected load • For example, an over sized motor 20 Kw drives a constant 15 Kw load whenever it is ON. The motor demand factor is then 15/20 =0.75= 75 %. • Demand Factor is express as a percentage (%) or in a ratio • Demand factor is always < =1. • The lower the demand factor, the less system capacity required to serve the connected load.
  • 4. Load factor • Load Factor = Actual Load / Full Load • OR • Load Factor = Area under the curve / Area of the rectangle • OR • Load Factor = Units generated / (Maximum demand x hours)
  • 5. Load factor • It is the ratio of actual kilowatt-Hours used in a given period, divided by the total possible kilowatt -hours that could have been used in the same period at the peak KW level. • Load Factor = ( energy (kWh per month) ) / ( peak demand (kW) x hours/month ) • The Load factor is always <=1.
  • 6. Load factor • Higher the load factor is GOOD and it will more Output of Plan, lesser the cost per unit which means an electricity generator can sell more electricity at a higher spark spread, Fixed costs are spread over more kWh of output. A power plant may be highly efficient at High load factors. • Low load factor is a BED. A low load factor will use electricity inefficiently relative to what we could be if we were controlling our peak demand. A power plant may be less efficient at low load factors.
  • 7. Connected load factor Connected load factor = Average load / connected load = (Average demand / Maximum demand) x (Maximum demand / connected load) = Load factor x Demand factor
  • 8. Diversity factor • Diversity Factor = Sum of Individual Maximum Demands / Maximum Demand of the System. • The diversity factor is always >= 1.
  • 9. Coincidence factor • The reciprocal of diversity factor is coincidence factor • Coincidence factor = Maximum demand / Sum of individual maximum demands • The Coincidence Factor is always <=1.
  • 10. Load diversity • Load diversity is the difference of sum of individual maximum demands of two or more consumers and their combined maximum demand
  • 11. Loss factor Loss factor = Average power loss / Power loss at peak load
  • 12. Plant capacity factor Plant capacity factor = Average demand / Installed plant capacity OR Plant capacity factor = Units generated in a year / Installed plant capacity x 8760
  • 13. Utilization factor Utilization factor = Maximum demand / Plant capacity
  • 14. Plant use factor Plant use factor = Units generated / ∑kWh = Units generated / kW1h1+kW2h2+….
  • 15. Load curve Load curve is the variation of load with time on a Power Station. As the load on a Power Station never remain constant rather it varies time to time, these variations in load is plotted on half hourly or hourly basis for the whole day. The curve thus obtained is known as Daily Load Curve.
  • 16. Importance of Load Curve • From the daily load curve we can have insight of load at different time for a day. • The area under the daily load curve gives the total units of electric energy generated. • Units Generated / day = Area under the daily Load Curve in kW • The peak point on the daily load curve gives the highest demand on the Power Station for that day. • The average load per day on the Power Station can be calculated using the daily load curve. • Average load = Area under the daily Load Curve (kWh)/ 24 hrs. • Load curve helps in deciding the size and number of Generating Units. • Load Factor = Avg. Load / maximum Load = Avg. Load x24 / 24xmaximum Load • = Area under daily Load Curve/Area of Rectangle having Daily Load Curve • Load curve helps in the preparing the operation schedule of the generating units.
  • 17. Load Duration Curve • Load Duration Curve is the plot of Load versus time duration for which that load was persisting.
  • 18. Base load & Peak load • Base load is the minimum level of electricity demand required over a period of 24 hours. It is needed to provide power to components that keep running at all times (also referred as continuous load). Peak load is the time of high demand.
  • 19. Base load & Peak load
  • 20. Base load & Peak load
  • 21. Characteristics of Base load station • Operating throughout the year • Load factor is high • Efficiency is high • Cost of unit generation is less • Capital cost is high • Capacity is high • Difficult to start and stop