Finance management in construction
site- Case study
RV College of
Engineering
Go, change the world
By:
SHAHID BASHIR MALIK
USN: 1RV19CV410
The scope of this paper is to discuss the financial
management of a construction project. This paper attempts
to approach this subject in a logical and systematic way. It
communicates the importance of financial analysis and
planning along with cash planning.
RV College of
Engineering
ABSTRACT
Go, change the world
• The construction activity includes gathering and assembling materials
which are produced by a group of suppliers, working in a diversity of
technologies and discipline, to create a ―built environment‖. These
activities consist of construction, manufacture, regulation, design,
maintenance and decommissioning of various structures and buildings.
• The company’s financial resources include cash and assets of the firm and
this is deriving from the term financial management. Decisions that are
made on the basis of financial management affect a company’s financial
future and therefore the decision made by the personnel is very important
regarding the company’s benefits and industries image in future.
RV College of
Engineering
INTRODUCTION
Go, change the world
Financial management of your small business encompasses more than keeping an
accurate set of books and balancing your business checking account
Some of the authoritative definitions are given below:
1. ―Financial Management is concerned with the efficient use of an important
economic resource, namely, Capital Funds‖ —Solomon
2. ―Financial Management is concerned with the managerial decisions that result in
the acquisition and financing of short-term and long-term credits for the firm‖ —
Phillioppatus
3. ―Business finance is that business activity which is concerned with the
conservation and acquisition of capital funds in meeting financial needs and overall
objectives of a business enterprise‖ —Wheeler
RV College of
Engineering
SIGNIFICANCE
Go, change the world
. Description of Site
The study area is located in OU Hyderabad, TS. It is a G+4 building consisting of 250rooms which
accommodates 500 people. The project started in dec2017 and is expected to be finished by jun2019.The
present status of the project: external and internal brick work competed. Terrace parapet wall construction in
process. Inside and outside plastering work, plumbing work, tile work, paint work, electrical work, carpentry
work, and flooring are pending
DESCRIPTION OF WORK
methodology adopted/ involved in this research work is comparison of the two processes of sequential steps,
as per objectives set for his study, and that runs parallel throughout the research until the analysis and
comparison of the project outcomes of both the processes are done to conclude on the research work as
shown detail in the flowchart and it was shown in Figure I.
RV College of
Engineering
CASE STUDY
Go, change the world
RV College of
Engineering
Selection of A Live Project to Track the Project Parameters Like Project Scheduling and Cost
Go, change the world
S.NoTitle Details
1 Project cost 21Crores
2 Total area of the project 10942.30 Sq.mt
3 Ground floor area 2506.82 Sq.mts
4 First floor area 1903.84Sq.mts
5 Second floor area 2256.00 Sq.mts
6 Third floor area 2256.00 Sq.mts
7 Fourth floor area 2019.64 Sq.mts
8 Ground floor 43rooms – 86persons
9 First floor 49rooms – 98persons
10 Second floor 52rooms – 104persons
11 Third floor 52rooms – 104persons
12 Fourth floor 54rooms – 108persons
A 500 bedded hostel building of
Osmania university of Hyderabad
is selected and this project
consists of G+4 floors. Table I
explains the detail of the project.
Primavera description
Project management using primavera (p6) software to plan, monitor,
schedule, and update the progress of the project can be done effectively in
terms of cost and time.
Steps involved in implementing the project in primavera
Enterprise project structure (EPS): EPS is a hierarchical arrangement of
projects in an organization. The EPS is available to all existing and future
projects in the Enterprise.
Organizational breakdown structure (OBS): After Creating EPS the main
step involved in the software is to create OBS which shows that the persons
responsible for the project in the enterprise
RV College of
Engineering
PRIMAVERA
Go, change the world
Interlinking: link both enterprise project structure (EPS)
and organizational breakdown structure(OBS).
Create a project: After linking the EPS and the OBS the
project has been created. A project is a collection of both
activities and tasks that all together result in the creation
of the structure or product.
RV College of
Engineering
CONTD>:
Go, change the world
Listing of project activities: after creating
the work break down structure, we have to
define the activities i.e. to break down the
components into sub components. It is known
that each activity has its own duration, start
and finish dates and logical relationship which
helps in scheduling the project. And all the
stages of activities consist of 485 activities
RV College of
Engineering
CONTD…..:
Go, change the world
Assigning relationships among activities
After entering all the task, the next step is to assign the relationships.
Assigning logical links is nothing but assigning interdependency of
each activity.
Predecessor: The preceding activity for a specific activity is called
Predecessor.
Successor: The succeeding activity for a specific activity is called
Successor.
RV College of
Engineering
CONTD….:
Go, change the world
There are four types of relationships available. They are as follows:
Finish to start (FS): It is a default relationship followed in primavera;
here the activity starts the completion of the previous activity.
Start to start (SS): It indicates that the current activity and its
predecessor will start on the same date.
Finish to finish (FF):It indicates that the current activity and its
predecessor will finish on the same date.
Start to finish (SF): It indicates that the current activity and its
predecessor activity start date will be same.
RV College of
Engineering
Go, change the world
Project scheduling: It is the main step to analyses the
project is to schedule the overall project. If any changes
are made in project during the execution, primavera
software enables us to reschedule the project for cost
and other parameters and project scheduling is used to
know the total duration and cost of the project from the
assigned baseline
RV College of
Engineering
Go, change the world
Fixing the Base Line & Updating the project:
After completing the above steps it is necessary to
make a base line of the project and it refers to the
copy of the original schedule, while updating the
project it allows you to display where the project is
diverting from the original schedule.
RV College of
Engineering
Go, change the world
Tracking the project progress: It is the important step in the primavera. It
helps to track the project against the original schedule by EVA (Earned Value
Analysis). It is one of the most popular and standard method of measuring
the project progress at any given time and also used to analyses variances of
the actual cost of the project from the baseline cost during the progress of the
project. EVA requires three parameters namely
1. Planned value (PV):It is referred to the budgeted cost for the work
schedule for the project.
2. Earned value (EV):It is referred to the budgeted cost for the work
schedule for the evaluation of the progress of the project in terms of schedule
and cost.
3. Actual cost (AC): It is referred to the actual amount spent on the work
performed.
RV College of
Engineering
Go, change the world
RESULTS AND DISCUSSION
The earned value management is a program evaluation approach
which is evaluated and tracks the project in an effective manner. The
project is tracked in one time i.e. from March 31-03-2018 to 26-12-
2018 in all that we obtained Plan Value (PV), Earn Value (EV) & Actual
Cost (AC) from these 3 basic specifications the Earned Value
Performance measurement indices obtained. The Earned Value
Performance index shows the performance of a project. Figure VII
shows the cost analysis of project
RV College of
Engineering
Go, change the world
As on tracking 255 days are remaining to complete the activities, the
schedule performing 100% (SPI (1)) as planned value under 1 show
the project is running from planned schedule value. And cost
performing 88% (CPI 0.88) as budgeted cost, it shows the project cost
is overrunning.67.19% of the project is completed up to December 26
2018. To complete the project in time the schedule has to perform 1-
2% of speed than the planned schedule. Figure 8 shows the cost
performance index and schedule performance index graph
RV College of
Engineering
CONTD…..
Go, change the world
CONCLUSIONS
Financial and work management of any project decided its successfulness. The present study
aimed to know difference between the manmade and primavera software, in estimation of
scheduling of financial and work management of a project with the aid e.g. literature references
and the unique methodology in monitoring and control with the help of primavera software. The
estimated project completion time for G+4 building, Osmania University, Hyderabadis formed
560 days by the contractor, which is approximately equal to 18months, but the same project,
precise planning, controlling implementation and monitoring of every activity using primavera
tool, the expected time of the project completion is estimated to be 486 days only. The
planning of various activities throughout the project run would be optimum, then financial and
work management can be done properly. The primavera software P6 is a perfect and efficient
tool for the project management and for the purpose of monitoring and controlling of the
various construction projects.
RV College of
Engineering
Go, change the world
RV College of
Engineering
Go, change the world

More Related Content

What's hot

INTRO TO FUNDAMENTALS OF MANAGEMENT
INTRO TO FUNDAMENTALS OF MANAGEMENTINTRO TO FUNDAMENTALS OF MANAGEMENT
INTRO TO FUNDAMENTALS OF MANAGEMENTshaziaw
 
Project Management:Life Cycle & Phases.
Project Management:Life Cycle & Phases.Project Management:Life Cycle & Phases.
Project Management:Life Cycle & Phases.Ashutosh Mishra
 
Construction financial-management
Construction financial-managementConstruction financial-management
Construction financial-managementAnnisa Wisdayati
 
Project management in construction
Project management in constructionProject management in construction
Project management in constructionNAVNEET KUMAR JHA
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In ConstructionAB MAKASANA
 
Construction management
Construction managementConstruction management
Construction managementUsama Khalid
 
Job layout per
Job layout perJob layout per
Job layout perraj balar
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimatinghatim ahmed
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Construction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfConstruction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfMeleseMengistu
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost controlGuhan M
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?maria_singh
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineeringrathodjaydeep2
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction CostingManish Kandpal
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 

What's hot (20)

INTRO TO FUNDAMENTALS OF MANAGEMENT
INTRO TO FUNDAMENTALS OF MANAGEMENTINTRO TO FUNDAMENTALS OF MANAGEMENT
INTRO TO FUNDAMENTALS OF MANAGEMENT
 
Project Management:Life Cycle & Phases.
Project Management:Life Cycle & Phases.Project Management:Life Cycle & Phases.
Project Management:Life Cycle & Phases.
 
Construction financial-management
Construction financial-managementConstruction financial-management
Construction financial-management
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Tender
TenderTender
Tender
 
Construction management
Construction managementConstruction management
Construction management
 
Job layout per
Job layout perJob layout per
Job layout per
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Construction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfConstruction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdf
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction Costing
 
crashing of project
crashing of project crashing of project
crashing of project
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 

Similar to Finance management in construction site

Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...IRJET Journal
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET Journal
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementIRJET Journal
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docxpauline234567
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&tNishant Pandey
 
Tracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraTracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraIRJET Journal
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...IRJET Journal
 
Primavera6.0
Primavera6.0Primavera6.0
Primavera6.0niict
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Mohammad Lemar ZALMAİ
 
Project summary report 1 3 proj
Project summary report  1     3 projProject summary report  1     3 proj
Project summary report 1 3 projDIPESH30
 
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docx
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docxRunning Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docx
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docxtodd581
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSIAEME Publication
 
L03 integration management
L03 integration managementL03 integration management
L03 integration managementAsa Chan
 
76 s201905
76 s20190576 s201905
76 s201905IJRAT
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedWaqar Ahmed
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...IRJET Journal
 
76 s201903
76 s20190376 s201903
76 s201903IJRAT
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Mohammad Lemar ZALMAİ
 

Similar to Finance management in construction site (20)

Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docx
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&t
 
Tracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraTracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using Primavera
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
 
Primavera6.0
Primavera6.0Primavera6.0
Primavera6.0
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
 
Project summary report 1 3 proj
Project summary report  1     3 projProject summary report  1     3 proj
Project summary report 1 3 proj
 
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docx
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docxRunning Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docx
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docx
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
 
L03 integration management
L03 integration managementL03 integration management
L03 integration management
 
76 s201905
76 s20190576 s201905
76 s201905
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
 
Ch04
Ch04Ch04
Ch04
 
76 s201903
76 s20190376 s201903
76 s201903
 
I012335763
I012335763I012335763
I012335763
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
 

More from SHAHIDBASHIRMALIK

INDUSTRIAL DESIGN AND ITS PIRACY
INDUSTRIAL DESIGN AND ITS PIRACYINDUSTRIAL DESIGN AND ITS PIRACY
INDUSTRIAL DESIGN AND ITS PIRACYSHAHIDBASHIRMALIK
 
Determination of acidity of water
Determination of acidity of waterDetermination of acidity of water
Determination of acidity of waterSHAHIDBASHIRMALIK
 
partial replacement of aggregates by recycled concrete
 partial replacement of aggregates by recycled concrete partial replacement of aggregates by recycled concrete
partial replacement of aggregates by recycled concreteSHAHIDBASHIRMALIK
 
Huge water wasted while cleaning our vehicles everyday
Huge water wasted while cleaning our vehicles everydayHuge water wasted while cleaning our vehicles everyday
Huge water wasted while cleaning our vehicles everydaySHAHIDBASHIRMALIK
 
Cpm network analysis and problems
Cpm network analysis and problemsCpm network analysis and problems
Cpm network analysis and problemsSHAHIDBASHIRMALIK
 
SPACE TECHNOLOGY & APPLICATION
SPACE TECHNOLOGY & APPLICATIONSPACE TECHNOLOGY & APPLICATION
SPACE TECHNOLOGY & APPLICATIONSHAHIDBASHIRMALIK
 

More from SHAHIDBASHIRMALIK (9)

INDUSTRIAL DESIGN AND ITS PIRACY
INDUSTRIAL DESIGN AND ITS PIRACYINDUSTRIAL DESIGN AND ITS PIRACY
INDUSTRIAL DESIGN AND ITS PIRACY
 
Determination of acidity of water
Determination of acidity of waterDetermination of acidity of water
Determination of acidity of water
 
partial replacement of aggregates by recycled concrete
 partial replacement of aggregates by recycled concrete partial replacement of aggregates by recycled concrete
partial replacement of aggregates by recycled concrete
 
Huge water wasted while cleaning our vehicles everyday
Huge water wasted while cleaning our vehicles everydayHuge water wasted while cleaning our vehicles everyday
Huge water wasted while cleaning our vehicles everyday
 
GPS
GPSGPS
GPS
 
Cpm network analysis and problems
Cpm network analysis and problemsCpm network analysis and problems
Cpm network analysis and problems
 
Internship PMGSY Anantnag
Internship PMGSY AnantnagInternship PMGSY Anantnag
Internship PMGSY Anantnag
 
SPACE TECHNOLOGY & APPLICATION
SPACE TECHNOLOGY & APPLICATIONSPACE TECHNOLOGY & APPLICATION
SPACE TECHNOLOGY & APPLICATION
 
SPECIAL STATUS FOR J&K
SPECIAL STATUS FOR J&KSPECIAL STATUS FOR J&K
SPECIAL STATUS FOR J&K
 

Recently uploaded

Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 

Recently uploaded (20)

Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 

Finance management in construction site

  • 1. Finance management in construction site- Case study RV College of Engineering Go, change the world By: SHAHID BASHIR MALIK USN: 1RV19CV410
  • 2. The scope of this paper is to discuss the financial management of a construction project. This paper attempts to approach this subject in a logical and systematic way. It communicates the importance of financial analysis and planning along with cash planning. RV College of Engineering ABSTRACT Go, change the world
  • 3. • The construction activity includes gathering and assembling materials which are produced by a group of suppliers, working in a diversity of technologies and discipline, to create a ―built environment‖. These activities consist of construction, manufacture, regulation, design, maintenance and decommissioning of various structures and buildings. • The company’s financial resources include cash and assets of the firm and this is deriving from the term financial management. Decisions that are made on the basis of financial management affect a company’s financial future and therefore the decision made by the personnel is very important regarding the company’s benefits and industries image in future. RV College of Engineering INTRODUCTION Go, change the world
  • 4. Financial management of your small business encompasses more than keeping an accurate set of books and balancing your business checking account Some of the authoritative definitions are given below: 1. ―Financial Management is concerned with the efficient use of an important economic resource, namely, Capital Funds‖ —Solomon 2. ―Financial Management is concerned with the managerial decisions that result in the acquisition and financing of short-term and long-term credits for the firm‖ — Phillioppatus 3. ―Business finance is that business activity which is concerned with the conservation and acquisition of capital funds in meeting financial needs and overall objectives of a business enterprise‖ —Wheeler RV College of Engineering SIGNIFICANCE Go, change the world
  • 5. . Description of Site The study area is located in OU Hyderabad, TS. It is a G+4 building consisting of 250rooms which accommodates 500 people. The project started in dec2017 and is expected to be finished by jun2019.The present status of the project: external and internal brick work competed. Terrace parapet wall construction in process. Inside and outside plastering work, plumbing work, tile work, paint work, electrical work, carpentry work, and flooring are pending DESCRIPTION OF WORK methodology adopted/ involved in this research work is comparison of the two processes of sequential steps, as per objectives set for his study, and that runs parallel throughout the research until the analysis and comparison of the project outcomes of both the processes are done to conclude on the research work as shown detail in the flowchart and it was shown in Figure I. RV College of Engineering CASE STUDY Go, change the world
  • 6. RV College of Engineering Selection of A Live Project to Track the Project Parameters Like Project Scheduling and Cost Go, change the world S.NoTitle Details 1 Project cost 21Crores 2 Total area of the project 10942.30 Sq.mt 3 Ground floor area 2506.82 Sq.mts 4 First floor area 1903.84Sq.mts 5 Second floor area 2256.00 Sq.mts 6 Third floor area 2256.00 Sq.mts 7 Fourth floor area 2019.64 Sq.mts 8 Ground floor 43rooms – 86persons 9 First floor 49rooms – 98persons 10 Second floor 52rooms – 104persons 11 Third floor 52rooms – 104persons 12 Fourth floor 54rooms – 108persons A 500 bedded hostel building of Osmania university of Hyderabad is selected and this project consists of G+4 floors. Table I explains the detail of the project.
  • 7. Primavera description Project management using primavera (p6) software to plan, monitor, schedule, and update the progress of the project can be done effectively in terms of cost and time. Steps involved in implementing the project in primavera Enterprise project structure (EPS): EPS is a hierarchical arrangement of projects in an organization. The EPS is available to all existing and future projects in the Enterprise. Organizational breakdown structure (OBS): After Creating EPS the main step involved in the software is to create OBS which shows that the persons responsible for the project in the enterprise RV College of Engineering PRIMAVERA Go, change the world
  • 8. Interlinking: link both enterprise project structure (EPS) and organizational breakdown structure(OBS). Create a project: After linking the EPS and the OBS the project has been created. A project is a collection of both activities and tasks that all together result in the creation of the structure or product. RV College of Engineering CONTD>: Go, change the world
  • 9. Listing of project activities: after creating the work break down structure, we have to define the activities i.e. to break down the components into sub components. It is known that each activity has its own duration, start and finish dates and logical relationship which helps in scheduling the project. And all the stages of activities consist of 485 activities RV College of Engineering CONTD…..: Go, change the world
  • 10. Assigning relationships among activities After entering all the task, the next step is to assign the relationships. Assigning logical links is nothing but assigning interdependency of each activity. Predecessor: The preceding activity for a specific activity is called Predecessor. Successor: The succeeding activity for a specific activity is called Successor. RV College of Engineering CONTD….: Go, change the world
  • 11. There are four types of relationships available. They are as follows: Finish to start (FS): It is a default relationship followed in primavera; here the activity starts the completion of the previous activity. Start to start (SS): It indicates that the current activity and its predecessor will start on the same date. Finish to finish (FF):It indicates that the current activity and its predecessor will finish on the same date. Start to finish (SF): It indicates that the current activity and its predecessor activity start date will be same. RV College of Engineering Go, change the world
  • 12. Project scheduling: It is the main step to analyses the project is to schedule the overall project. If any changes are made in project during the execution, primavera software enables us to reschedule the project for cost and other parameters and project scheduling is used to know the total duration and cost of the project from the assigned baseline RV College of Engineering Go, change the world
  • 13. Fixing the Base Line & Updating the project: After completing the above steps it is necessary to make a base line of the project and it refers to the copy of the original schedule, while updating the project it allows you to display where the project is diverting from the original schedule. RV College of Engineering Go, change the world
  • 14. Tracking the project progress: It is the important step in the primavera. It helps to track the project against the original schedule by EVA (Earned Value Analysis). It is one of the most popular and standard method of measuring the project progress at any given time and also used to analyses variances of the actual cost of the project from the baseline cost during the progress of the project. EVA requires three parameters namely 1. Planned value (PV):It is referred to the budgeted cost for the work schedule for the project. 2. Earned value (EV):It is referred to the budgeted cost for the work schedule for the evaluation of the progress of the project in terms of schedule and cost. 3. Actual cost (AC): It is referred to the actual amount spent on the work performed. RV College of Engineering Go, change the world
  • 15. RESULTS AND DISCUSSION The earned value management is a program evaluation approach which is evaluated and tracks the project in an effective manner. The project is tracked in one time i.e. from March 31-03-2018 to 26-12- 2018 in all that we obtained Plan Value (PV), Earn Value (EV) & Actual Cost (AC) from these 3 basic specifications the Earned Value Performance measurement indices obtained. The Earned Value Performance index shows the performance of a project. Figure VII shows the cost analysis of project RV College of Engineering Go, change the world
  • 16. As on tracking 255 days are remaining to complete the activities, the schedule performing 100% (SPI (1)) as planned value under 1 show the project is running from planned schedule value. And cost performing 88% (CPI 0.88) as budgeted cost, it shows the project cost is overrunning.67.19% of the project is completed up to December 26 2018. To complete the project in time the schedule has to perform 1- 2% of speed than the planned schedule. Figure 8 shows the cost performance index and schedule performance index graph RV College of Engineering CONTD….. Go, change the world
  • 17. CONCLUSIONS Financial and work management of any project decided its successfulness. The present study aimed to know difference between the manmade and primavera software, in estimation of scheduling of financial and work management of a project with the aid e.g. literature references and the unique methodology in monitoring and control with the help of primavera software. The estimated project completion time for G+4 building, Osmania University, Hyderabadis formed 560 days by the contractor, which is approximately equal to 18months, but the same project, precise planning, controlling implementation and monitoring of every activity using primavera tool, the expected time of the project completion is estimated to be 486 days only. The planning of various activities throughout the project run would be optimum, then financial and work management can be done properly. The primavera software P6 is a perfect and efficient tool for the project management and for the purpose of monitoring and controlling of the various construction projects. RV College of Engineering Go, change the world
  • 18. RV College of Engineering Go, change the world