SlideShare a Scribd company logo
1 of 6
Download to read offline
The International Journal Of Engineering And Science (IJES)
|| Volume || 5 || Issue || 5 || Pages || PP -131-136 || 2016 ||
ISSN (e): 2319 – 1813 ISSN (p): 2319 – 1805
www.theijes.com The IJES Page 131
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Priya Deshpande1
, Harihar S. Lunge2
1
Institute of Industrial and Computer management and Research, Nigdi , Pune.(M.S.)
2
Shri Shivaji Science college, Amaravati , (M.S.)
--------------------------------------------------------ABSTRACT-----------------------------------------------------------
Earned Value analysis (EVA) is the most efficient tool used for transitional review of project execution .It is
helpful to project managers and management team to value the progress of project work throughout the project
life cycle. The Earned Schedule (ES) is used to approximate the time or duration of project/ s for appropriate
evaluation of project execution. ES also help to forecast the time required to complete the project. When
combined with schedule analysis, ES can enhance the project. EVA provides the controlling tool for better
decision making in project management. The paper discuss about the probability distribution of Cost
performance Index (CPI) and Schedule performance Index (SPI). Best fitted distribution will help for
forecasting project duration effectively. This helps the Project Manager to prevent the over budgeted cost in
future. So an attempt is made to find the alternative distribution of CPI and SPI for better decision making. If the
project schedule performance shows poor results then manager need to take the corrective action with the help
of this tool. Weibull, Gamma and Exponentiated Exponential Distribution functions are used to study the effect
of SPI on CPI. For making better decision in project scheduling, Project managers can review the parameters
using EVM tool. The tool is useful in all types of civil engineering and software engineering projects.
Keywords: Earned Value Analysis(EVA), Earned Value Management(EVM), Cost Performance Index(CPI),
Scheduled Performance Index(SPI) , Probability distribution.
-------------------------------------------------------------------------------------------------------------------------------------
Date of Submission: 06 May 2016 Date of Accepted: 25 May 2016
--------------------------------------------------------------------------------------------------------------------------------------
I. INTRODUCTION
In project management, it is very important to keep the completion deadlines and project cost in control .Each
project should be completed in scheduled time and in budgeted cost and as per customer‟s dynamic expectation,
is a big task. Guiding the project team in appropriate direction with proper risk assessment associated with
project activities is not a very easy task. If the project manager is capable of executing the project plan as per
schedule with minimum variation, then it will certainly shows better performance as the project progresses.
If some problem arises during project execution, then some reserved sources are used to compensate that impact
on project. EVA minimizes the use of reserves by anticipating and estimating the performance of activities
during the execution of project. The effective use of EVA and ES will create good opportunities to complete the
project within time and cost.
In EVM, Earned value analysis (EVA) is used for measuring project progress in an effective way. EVA has the
capability to measurements of scope, schedule, and cost collectively. Earned value is the cumulative value of
work completed at that point of time. Planned value is the budgeted cost for accomplishing that activity. Actual
cost is the cumulative money spent to accomplish that activity at given point of time. The Earned Value
Management (EVM) indicators are Schedule Variance (SV) is used to compute the cost difference, i.e.SV=
Earned Value –Planned Value, while the Cost Variance (CV) = Earned Value – Actual Cost. The Cost and
Schedule Performance Indexes, CPI and SPI, respectively, are ratios. SPI is computed from the ratio, EV/PV,
while CPI equals EV/AC.
The cost indicators behave differently from those for schedule. The cost indicators appear to establish a trend
with some variation. Similarly, the schedule indicators initially appear to establish a trend, The study of Cost
Performance Index (CPI), Schedule Performance Index (SPI), will be studied to develop the new regression
model to forecast the project cost.
This paper discusses about effectiveness of Earned Value Management and Earned Schedule for better results
and proper decision making in Project and risk management. By knowing the over exact function form of CPI
and SPI, Project manager can work better on cost and time so as to reduce delay time. Project manager can
prepare alternative contingency plan to reduce risk and avoid the delay in project completion in minimal over
budget cast.
Study of Probability Distributions of CPI and SPI in Earned Value Analysis….
www.theijes.com The IJES Page 132
1.2.1 Problem statement: How to control the risk, delay in time and cost of the project using Earned Value
Management and Earned Scheduled?
1.2.2 Research objective: The main objective of this paper is to study the best suited distribution for CPI and
SPI to reduce risk, to study delay time in completion and to estimate the minimum budgeted cost.
H0: The assumed distribution of the data set is same as the observed one.
H1: The assumed distribution of the data set is not same as the observed one
II. LITERATURE REVIEW
(ES) is an extension to Earned Value Management (EVM) providing the capability of schedule analysis. ES was
introduced in 2003 by Lipke in article “Schedule Is Different” 6
. “Connecting Earned Value to the Schedule,” 6
“ES can be used for much more. It facilitates the ability to identify constraints, impediments, and the possibility
of rework at the task level. This information is very useful for management purposes, but it does not provide
performance indicators below the project level. ES can be applied to sub-levels of the project. Using this
capability, the project manager can analyze schedule performance at virtually any level desired – control
accounts, work packages, and critical path activities.”6
Earned Value Management is a system which integrate the scope, cost and time management of project by using
the resource –loaded project schedule and facilitate the systematic measurement of various factors involved in
it.11
EVM is endorsed by the Project management Institute 10
and is implemented by public and private
organization for project progress evaluation .The main benefit of EVM is that it is applicable to all types and
sizes of projects. Furthermore, the method is being used in research, instructed in several universities, and is
included in recent project management texts and the newer EVM analysis tools. Presently an appendix
describing ES is being prepared for inclusion in the PMIPractice Standard for Earned Value Management 9
.
III. TERMINOLOGY AND METHODS
3.1 Project Management
There are many tools to measure the project progress and evaluate the performance of the project. But EVA and
ES gives the efficient way of measuring the performance using cost performance index , schedule performance
index, ,earned scheduled and the various indices associated with it. During project execution if CPI = 1, it
indicates that the project is as per scheduled and completed at planned or budgeted cost. If SPI = 1 then it
indicates that the project is on schedule and it will be completed in estimated time. Now the project manager is
capable of estimating the delay time and over budgeted cost and can use the reserved resources to complete the
project in forecasted time and with minimal use of reserved resources.
3.1.1 Elements of Earned Value Management
There are 3 major elements of project management: scope, cost and time management. In EVM the review is
taken after specific interval of time and continuous monitoring is required to find the actual expenses and actual
amount of work completed. The periodic comparison is done between actual expenses and planned or budgeted
cost of that work done and ii) actual amount of work done and scheduled amount of work to be done in that
period. In this regard, two performance indices SPI and CPI are measured in terms of four indicators using three
functions.
3.1.2 Three functions of EVM:
1) Planned value,(PV) 2) Earned value (EV) and 3) Actual cost (AC)
Four factors and indicators used to in Earned value Analysis: -
1) Cost variance (CV) = EV – AC
2) Cost Performance Index (CPI) = EV /AC
3) Schedule Variance (SV) = EV – PV
4) Schedule Performance Index (SPI) = EV/ PV
Earned Value Management (EVM) has been applied to various projects from several years. It has proven to be
a successful tool to project planning, tracking, and decision-making. And, the Reporting methods of EVM are
proved a very good tool for communicating with management ,customers and stakeholders. From many years,
in the Software Development Industry ,the EVM is applied to study the project performance . Statistical
techniques are used to predict project outcomes, and past data is used for new project planning. To confidently
apply EVM data for outcome prediction and project planning, data must be recorded in correct and accurate
manner. It is identified that the schedule indicators of EVM fall short to provide correct and good information.
To overcome this deficiency, the Software Development Industry has been applying the concept and methods of
“Earned Schedule”.
Study of Probability Distributions of CPI and SPI in Earned Value Analysis….
www.theijes.com The IJES Page 133
3.2 Earned Value Analysis
(EVA): Earned Value Analysis is computed by taking product os budgeted cost per activity and completion
percentage and sum all activities in the project. Basic elements required for Earned Value Analysis are :Budget
At Completion (BAC).
Total budgeted cost of project.
Planned value (PV): Earlier it is also called as Budgeted Cost of Work Scheduled (BCWS).
Budgeted cost of work performed (BCWP): Budgeted cost of work that is completed in given point of time in
project.
Actual cost (AC) or Actual Cost of Work Performed (ACWP).
3.3 ES: Earned Schedule
ES method is largely measured to be a important advancement to the practice of EVM. Canada, India, Japan and
other countries, as ES is being used majorly in all industries where EVM is applied for all sizes of projects.
The measure of ES has provided schedule analysis and forecasting capacity to those using EVM. ES facilitates a
simple calculation for the forecasting of project duration and completion dates. In addition, it has been shown
that the forecasting is improved through the application of statistical methods 16
. “Earned Schedule is a fairly
new method for analyzing schedule performance; it is a derived application of Earned Value Management
(EVM) data. Created three years ago, the method has propagated to several countries and been used for various
types of work spanning a large and varied range of project sizes.
3.4 Forecasts
“A significant advantage from applying ES is that the method provides the capability to forecast the project
duration and the expected completion date. Other methods exist; however, through studies it has been shown
that ES is the most reliable forecasting method using EVM data.” 15
3.4.1 Elements of Earned Schedule Management
Various parameters used in Earned Value Management and Earned Schedule:
Actual Time (AT): This is the duration from the beginning of the project to status date.
Schedule at Completion (SAC): This is the original planned completion duration of the project.
Earned Schedule (ES): This is the duration from the beginning of the project to the date on which PV should
have been equal to the current value of EV.
ES = % Complete x SAC
Time Variance (TV): The Time variance is a measure of schedule performance in time units rather than cost
units.
TV = ES – AT
If TV value is negative the project is behind schedule, and if it is positive it is ahead of schedule.
Planned Value (PV) is the estimated value of the work planned to be done.
Earned Value (EV) is the estimated value of the work actually accomplished.
Actual Cost (AC) is the actual cost incurred for the work accomplished.
Cost Variance CV = EV - AC If it is negative then project is going to be over Budget.
Cost Performance Index (CPI) = EV / AC
Critical Ratio (CR) = CPI * SPI Overall Performance of the Project.
IV. PROBABILITY DISTRIBUTIONS
The basic need of knowing the exact form of distribution followed by CPI and SPI is to understand the nature of
these parameters. With the help of accurate function form of CPI and SPI, forecasting models can be developed
based on these distributions to reduce delay time and ultimately project cost.
Alternative distribution function forms will be available for predictive analysis which will enhance the
application domain area of the predictive models based on these distribution in Project management.
Diversity in projects causes the limitation for application of specific distribution in forecasting or predictive
models of project management.
To overcome this limitation, the paper discusses the set of various distributions which will be available to
develop the models for different types of projects.
Following distributions are used in project forecasting models:
4.1 Gamma-Type Density Function:
The Gamma-Type Density Function is having both a shape and a scale parameter. In Gamma distribution the
shape and scale parameters equal to 1, this results in the exponential density function.
The p.d.f. of Gamma distribution is:
f (x, α, α) = ( αα
/αα) xα– 1
e- αx
; α, α, x >0
Study of Probability Distributions of CPI and SPI in Earned Value Analysis….
www.theijes.com The IJES Page 134
Applications: It is used for the variables which are one sided bounded at one side ; for example x greater than
or equal to zero. The gamma density gives distribution of time required for exactly k independent events to
occur, assuming events take place at a constant rate. It is used frequently in queuing theory, reliability, and other
industrial applications. The parameters of Gamma distribution describes the scale and shape of the distribution.
The distribution shows great flexibility for analysis for positive real data.
Comments: Erlangian, Exponential, and Chi-square distributions are special cases. The negative binomial is an
similar to gamma distribution with discrete random variable.
Limitations of Gamma distribution: The distribution function or survival function cannot be expressed in a
closed form if shape parameter is not integer17
.
4.2 Exponentiated Exponential distribution:The Probability density function of exponentiated exponential is
defined by Gupta and Kunda (2001) with parameters α and λ as
f (x,α, α) =αα(1αeααx )α α.eααx 1 Where α, α, x > 0
Here α is the shape parameter and λ is the scale parameter. When α=1 it represent the exponential family.
Application: It gives distribution of time between independent events occurring at a constant rate.
Example: Distribution of time between arrival of jobs at a machine. It is useful in framing the strategy and
techniques in preventive maintenance.
4.3 Weibull distribution: Weibull distribution is more popular than Gamma distribution according to Gupta
and Kundu for analysis of lifetime data. 17
The p.d.f. of Weibull distribution is as follows:
f (x, α, α) = αα(x α)α-1
e(- αα)
; α, α, x >0
Application: Weibull distribution is generally useful for random variables which are left side bounded. To
determine the hazard rate of a system Weibull distribution is widely used.
The Weibull distribution is often used to model "time until failure." In this manner, it is applied in actuarial
science and in engineering work.
Example: Life distribution for some capacitors, ball bearings, relays, and similar variables..
Comments: Rayleigh and exponential distribution are special cases.
Advantage of Weibull distribution over Gamma distribution: Weibull distribution has an important property that
distribution function of Weibull distribution can be expressed in closed form for fractional and integer value
which does not hold true in Gamma distribution.
Due to this property, Weibull distribution is useful for any type of data.
Extreme value Distribution:
Application: Limiting model for the distribution of the maximum or minimum of N values selected from an
"exponential-type" distribution, such as the normal, gamma, or exponential.
Example: Distribution of breaking strength of some materials, capacitor breakdown voltage, gust velocities
encountered by airplanes, bacteria extinction times. These distributions are useful in Civil and Mechanical
engineering project management.
V. DATA SOURCES
The Secondary data 14
of eight projects is used.CPI and SPI of projects are computed from the data available
using SPSS version 20.The correlation between CPI and SPI is shown in the Table no.1
5.1 Data analysis for CPI and SPI in EVM and ES for performance measures
Data analysis is done using MS- Excel and SPSS Version 20 .Chi- square test is used to test the goodness of fit.
The chi-square test is used to test the validity of a distribution assumed for a random phenomenon. The test
evaluates the null hypotheses
H0: The data are governed by the assumed distribution against
H1
: The data are not drawn from the assumed distribution.
Comparison of Correlation and regression coefficient using Weibull , Gamma, and Exponential distribution.
Study of Probability Distributions of CPI and SPI in Earned Value Analysis….
www.theijes.com The IJES Page 135
Function Weibull Gamma Exponetial
CPI and SPI
Correlation
coefficient
0.4692 0.4692 0.4586
Regression
coefficient
0.4968 0.4968 0.4843
Table 1
Graph 1
The correlation is used to describe the existence of relationship between variables.
Pearson Correlation coefficients is used to evaluate the correlation between two variables is. It is denoted by „r‟
and it lies between -1 and 1.
If r = 1, then there is prefect positive correlation between variables under consideration.
Gamma distribution:
The table shows 2 and 3 the results of test of Goodness of fit using SPSS version 20.
Outcome of Chi- square Test of Goodness of Fit
Table 2
Test Statistics
EE_SPI weibull_SPI Gamma_SPI
Chi-Square .000a
.000a
.000a
Df 7 7 7
Asymp. Sig. 1.000 1.000 1.000
a. 8 cells (100.0%) have expected frequencies less than 5.
The minimum expected cell frequency is 1.0.
Table 3
Test Statistics
Weibull_CPI Gamma_CPI EE_CPI
Chi-Square .000a
.000a
.000a
Df 7 7 7
Asymp. Sig. 1.000 1.000 1.000
a. 8 cells (100.0%) have expected frequencies less than 5. The
minimum expected cell frequency is 1.0.
From the Table No. 2 and 3, we have observed that Weibull , Gamma and EE distributions are equally suitable
to know the nature of CPI and SPI. We accept the hypothesis that the distribution assumed for CPI and SPI is
same as the observed one.
CPI and SPI follows the Weibull and Gamma distribution according to 11
but EE also became an alternative
distribution to measure the CPI and SPI of the projects. This finding will help to measure the CPI and SPI in
case of weak performance of Weibull and Gamma distribution in forecasting models of project management.
VI. CONCLUSION
Project management is concerned with planning, controlling, checking project progress, monitoring milestones,
deliverables and managing risk in project execution. Earned Value Management provides the alarming signals to
project manager for making strategic decisions to avoid future loss. Earned Value Management technique helps
Project Manager to take corrective actions if project is not going as per schedule. It also helps to reduce the risk
Study of Probability Distributions of CPI and SPI in Earned Value Analysis….
www.theijes.com The IJES Page 136
involved in it by changing strategy and implementing corrective action to meet the dead lines and complete the
project in budgeted cost.
From the discussion , it has be concluded that along with Weibull and Gamma distribution ,Exponentiated
Exponential distribution is also most suitable distribution to study the cost and schedule performance indices .
In above discussion, Chi square test of hypothesis is applied to civil engineering project data. It has proved that
Exponentiated Exponential distribution can be suitable alternative to Weibull and Gamma distribution to study
the CPI and SPI in EVM.
The Chi square goodness of fit is applied to test the goodness of fit .The EE family of distribution has quite
similar properties as that of 2 parameter Weibull and Gamma distributions. Weibull distribution function and
Gamma distribution function showed the same result while EE family of distribution gave better results in some
data sets. Also it has been observed that in few cases Weibull is better distribution in terms of fitting of the
distribution to data set. Along with Weibull and Gamma distribution, EE also can be used very effectively to
forecast the project cost on the basis of schedule performance index.From this discussion, we expect that EE can
provide constructive result to know the exact nature of CPI and SPI in EVM.
This study confirms that EE family can be used as an alternative distribution to study CPI and SPI. Further
research can be carried out to study the effect of ratio of CPI and SPI which is significantly contributing and
other interdependency factors in variation in CPI and SPI. This work can be extended to compare the application
of properties of Weibull, Gamma and EE family of distributions in project management tools like EVM and
ES.The nature of CPI and SPI will help to develop the strategic action plan which reduces the risk of overrun
and over budgeted cost of the project/s in Project Management.
VII. RECOMMENDATIONS
The present study analyses the major projects which generally operates with traditional projects management
standards. It is a contribution which gives greater reliability application of EE in estimation of CPI and SPI of
the projects, because of equivalence among the Weibull, Gamma and EE distribution.
We recommend that the training of implementation of EVA and ES should be given to project Managers and
generate skills in the use of project management (EVA) and ES methodologies. The combination of these two
methodologies caters the need of the project planning and controlling in the Project management field.
Also the projects leaders should encourage the combined application of EVA and ES methodologies which
causes them to have greater certainty in the project delivery time and therefore the organization can maintain
their competitive advantage in a sustainable manner.
REFERENCES
[1]. C. R. Kothari, Research Methodology, Methods and techniques, 2nd
edition (2008), New age International publishers.
[2]. Hira and Gupta, Operation Research, 1st
Edition (2003), S Chand Publications.
[3]. Walt Lipke. Earned Schedule, Schedule performance analysis from EVM measures, PM World Today – January 2011 (Vol XIII,
Issue I), originally published in Projects and Profits magazine, India (January 2010, pp 53-61)
[4]. Kym Henderson, Education Director, Project Management Institute, Sydney Australia Chapter, Earned Schedule: A Breakthrough
Extension to Earned Value Management, © Kym Henderson Page 1 of 10, Originally published as a part of 2007 PMI Asia Pacific
Global Congress Proceedings – Hong Kong.
[5]. Walt Lipke, Earned Schedule Application to Small Projects, PM World Today – April 2011 (Vol. XIII, Issue IV)
[6]. Lipke, Walt. “Schedule is Different,” The Measurable News, March 2003: 10-15.
[7]. Siamak Noori, Morteza Bagherpour and Abalfazl Zareei, Department of Industrial Engineering, Iran University of Science and
Technology, Tehran, IranWorld, Applying Fuzzy Control Chart in Earned Value Analysis: A New Application Applied Sciences
Journal 3 (4): 684-690, 2008ISSN 1818-4952© IDOSI Publications, 2008
[8]. Henderson, Kym. “Further Developments in Earned Schedule,” The MeasurableNews, Spring 2004: 15-22.
[9]. PMIPractice Standard for Earned Value Management [PMI, 2005].
[10]. PMI. A Guide to The Project Management Body Of Knowledge. Upper Derby: PMI, 1996.
[11]. Byung cheol Kim,Texas A&M university, 2007,” Forecasting project progress and early warning of project overruns with
probabilistic methods .”
[12]. Rajesh Ganpat Virle1* and Sumedh Y Mhaske1, Int. J. Struct. & Civil Engg. Res. 2013, “ MONITORING OF CONSTRUCTION
PROJECTS USING EVM AND ESM TOOLS”.
[13]. Ricardo M. Olano, Luis F. Alarcon and Carlos Razuri, Proceedings for the 17th
Annual Conference of the International Group for
Lean Construction, “UNDERSTANDING THE RELATIONSHIP BETWEEN PLANNING RELIABILITY AND SCHEDULE
PERFORMANCE: A CASE STUDY”.
[14]. Danial M Brandon, Jr. ,Published in Project Management Journal, June 1998, “ Implementing Earned Value Easily and
Effectively”.
[15]. Lipke W, 2008a ‖Project duration forecasting : A comparison of earned value management methods to earned schedule ―, Cross
talk 10-
[16]. Lipke,W.,O.Zwikael,F.Anbari,K.Henderson. ―Prediction of project outcome, the application of statistical methods to Earned
Schedule performance indexes,‖ International Journal pf Project Management , 2009.
[17]. Rameshwar Gupta and Debasis Kundu ,”Exponentiated Exponential Family: An Alternative to Gamma and Weibull Distributions”,
Biometrical Journal 43(2001) 1 , 117-130.
[18]. Dr. Arsham's Statistics Site home.ubalt.edu/ntsbarsh/business-stat/opre504.htm visited on 2015-10-25.

More Related Content

What's hot

Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Mohammad Lemar ZALMAİ
 
Economics of project evaluation cpm module2
Economics of project evaluation cpm module2Economics of project evaluation cpm module2
Economics of project evaluation cpm module2ahsanrabbani
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costsharwoodr
 
Project Scheduling and Control Projects
Project Scheduling and Control ProjectsProject Scheduling and Control Projects
Project Scheduling and Control Projectsharoldtaylor1113
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Shabaz Khan
 
Cost management basics for Construction Engineers
Cost management basics for Construction EngineersCost management basics for Construction Engineers
Cost management basics for Construction EngineersAmit Kumar Senapati, PMP®
 
Network analysis cpm module3
Network analysis cpm module3Network analysis cpm module3
Network analysis cpm module3ahsanrabbani
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management EssentialsGlen Alleman
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
8 applying-es-to-critical-path-and-more
8 applying-es-to-critical-path-and-more8 applying-es-to-critical-path-and-more
8 applying-es-to-critical-path-and-moreatifaizan
 
Planning, scheduling and resource allocation
Planning, scheduling and resource allocationPlanning, scheduling and resource allocation
Planning, scheduling and resource allocationJatin Mandhyan
 
Project Controls Processes
Project Controls ProcessesProject Controls Processes
Project Controls ProcessesPMA Consultants
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSHafiz JUNAID
 

What's hot (20)

Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
 
Economics of project evaluation cpm module2
Economics of project evaluation cpm module2Economics of project evaluation cpm module2
Economics of project evaluation cpm module2
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs3 pm3 c_2-%20estimating%20costs
3 pm3 c_2-%20estimating%20costs
 
Project Scheduling and Control Projects
Project Scheduling and Control ProjectsProject Scheduling and Control Projects
Project Scheduling and Control Projects
 
PERT
PERTPERT
PERT
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
 
Cost management basics for Construction Engineers
Cost management basics for Construction EngineersCost management basics for Construction Engineers
Cost management basics for Construction Engineers
 
CCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost ControlCCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost Control
 
Network analysis cpm module3
Network analysis cpm module3Network analysis cpm module3
Network analysis cpm module3
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management Essentials
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Project cost management
Project cost managementProject cost management
Project cost management
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
8 applying-es-to-critical-path-and-more
8 applying-es-to-critical-path-and-more8 applying-es-to-critical-path-and-more
8 applying-es-to-critical-path-and-more
 
Planning, scheduling and resource allocation
Planning, scheduling and resource allocationPlanning, scheduling and resource allocation
Planning, scheduling and resource allocation
 
Project Controls Processes
Project Controls ProcessesProject Controls Processes
Project Controls Processes
 
CCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost EstimatingCCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost Estimating
 
H1303055462
H1303055462H1303055462
H1303055462
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
 

Viewers also liked

Predicting Software Defects Using Bayesian Network Approach
Predicting Software Defects Using Bayesian Network ApproachPredicting Software Defects Using Bayesian Network Approach
Predicting Software Defects Using Bayesian Network Approachtheijes
 
Methods for Risk Management of Mining Excavator through FMEA and FMECA
Methods for Risk Management of Mining Excavator through FMEA and FMECAMethods for Risk Management of Mining Excavator through FMEA and FMECA
Methods for Risk Management of Mining Excavator through FMEA and FMECAtheijes
 
Design and Analysis of a Brake Caliper
Design and Analysis of a Brake CaliperDesign and Analysis of a Brake Caliper
Design and Analysis of a Brake Calipertheijes
 
Performance Analysis of Apodized Fiber Bragg Gratings Formats in Optical Comm...
Performance Analysis of Apodized Fiber Bragg Gratings Formats in Optical Comm...Performance Analysis of Apodized Fiber Bragg Gratings Formats in Optical Comm...
Performance Analysis of Apodized Fiber Bragg Gratings Formats in Optical Comm...theijes
 
Testing and Evaluation of Particle Motion in a Multi-Pass VibroFluidized Bed ...
Testing and Evaluation of Particle Motion in a Multi-Pass VibroFluidized Bed ...Testing and Evaluation of Particle Motion in a Multi-Pass VibroFluidized Bed ...
Testing and Evaluation of Particle Motion in a Multi-Pass VibroFluidized Bed ...theijes
 
Illuminance Performance of Design Block Windows in Public Basic Schools in Ta...
Illuminance Performance of Design Block Windows in Public Basic Schools in Ta...Illuminance Performance of Design Block Windows in Public Basic Schools in Ta...
Illuminance Performance of Design Block Windows in Public Basic Schools in Ta...theijes
 
Analysis Of Physic-Chemical Characteristics Of Polluted Water Samples And Eva...
Analysis Of Physic-Chemical Characteristics Of Polluted Water Samples And Eva...Analysis Of Physic-Chemical Characteristics Of Polluted Water Samples And Eva...
Analysis Of Physic-Chemical Characteristics Of Polluted Water Samples And Eva...theijes
 
Boost Converter with Improved Voltage Conversion Ratio Using Bootstrap Capaci...
Boost Converter with Improved Voltage Conversion Ratio Using Bootstrap Capaci...Boost Converter with Improved Voltage Conversion Ratio Using Bootstrap Capaci...
Boost Converter with Improved Voltage Conversion Ratio Using Bootstrap Capaci...theijes
 
The Concept of Control and Manage Plastic Pollution of India/World
The Concept of Control and Manage Plastic Pollution of India/WorldThe Concept of Control and Manage Plastic Pollution of India/World
The Concept of Control and Manage Plastic Pollution of India/Worldtheijes
 
Improvement of MFSK -BER Performance Using MIMO Technology on Multipath Non L...
Improvement of MFSK -BER Performance Using MIMO Technology on Multipath Non L...Improvement of MFSK -BER Performance Using MIMO Technology on Multipath Non L...
Improvement of MFSK -BER Performance Using MIMO Technology on Multipath Non L...theijes
 
Improved Sugar Yield for Bioethanol Production by Modelling Enzymatic Hydroly...
Improved Sugar Yield for Bioethanol Production by Modelling Enzymatic Hydroly...Improved Sugar Yield for Bioethanol Production by Modelling Enzymatic Hydroly...
Improved Sugar Yield for Bioethanol Production by Modelling Enzymatic Hydroly...theijes
 
Numerical Solution of Third Order Time-Invariant Linear Differential Equation...
Numerical Solution of Third Order Time-Invariant Linear Differential Equation...Numerical Solution of Third Order Time-Invariant Linear Differential Equation...
Numerical Solution of Third Order Time-Invariant Linear Differential Equation...theijes
 
Evaluation of Various Polymorphs by Different Techniques and Their Characteri...
Evaluation of Various Polymorphs by Different Techniques and Their Characteri...Evaluation of Various Polymorphs by Different Techniques and Their Characteri...
Evaluation of Various Polymorphs by Different Techniques and Their Characteri...theijes
 
Microstructural and Dielectric Characterization of Sr doped Ba(Fe0.5Ta0.5)O3 ...
Microstructural and Dielectric Characterization of Sr doped Ba(Fe0.5Ta0.5)O3 ...Microstructural and Dielectric Characterization of Sr doped Ba(Fe0.5Ta0.5)O3 ...
Microstructural and Dielectric Characterization of Sr doped Ba(Fe0.5Ta0.5)O3 ...theijes
 
Yanamadurru Drain Water Quality Assessment during 12-13 March, 2016
Yanamadurru Drain Water Quality Assessment during 12-13 March, 2016Yanamadurru Drain Water Quality Assessment during 12-13 March, 2016
Yanamadurru Drain Water Quality Assessment during 12-13 March, 2016theijes
 
Gesture Controlled Chair
Gesture Controlled ChairGesture Controlled Chair
Gesture Controlled Chairtheijes
 
Fish Larval Nutrition: A Review on New Developments
Fish Larval Nutrition: A Review on New DevelopmentsFish Larval Nutrition: A Review on New Developments
Fish Larval Nutrition: A Review on New Developmentstheijes
 
The Analysis of Men’s Emotional State from Heart Rate Using Daq & Labview
The Analysis of Men’s Emotional State from Heart Rate Using Daq & LabviewThe Analysis of Men’s Emotional State from Heart Rate Using Daq & Labview
The Analysis of Men’s Emotional State from Heart Rate Using Daq & Labviewtheijes
 
Reaction of consumers against the rising milk prices in Vietnam: A case study...
Reaction of consumers against the rising milk prices in Vietnam: A case study...Reaction of consumers against the rising milk prices in Vietnam: A case study...
Reaction of consumers against the rising milk prices in Vietnam: A case study...theijes
 

Viewers also liked (19)

Predicting Software Defects Using Bayesian Network Approach
Predicting Software Defects Using Bayesian Network ApproachPredicting Software Defects Using Bayesian Network Approach
Predicting Software Defects Using Bayesian Network Approach
 
Methods for Risk Management of Mining Excavator through FMEA and FMECA
Methods for Risk Management of Mining Excavator through FMEA and FMECAMethods for Risk Management of Mining Excavator through FMEA and FMECA
Methods for Risk Management of Mining Excavator through FMEA and FMECA
 
Design and Analysis of a Brake Caliper
Design and Analysis of a Brake CaliperDesign and Analysis of a Brake Caliper
Design and Analysis of a Brake Caliper
 
Performance Analysis of Apodized Fiber Bragg Gratings Formats in Optical Comm...
Performance Analysis of Apodized Fiber Bragg Gratings Formats in Optical Comm...Performance Analysis of Apodized Fiber Bragg Gratings Formats in Optical Comm...
Performance Analysis of Apodized Fiber Bragg Gratings Formats in Optical Comm...
 
Testing and Evaluation of Particle Motion in a Multi-Pass VibroFluidized Bed ...
Testing and Evaluation of Particle Motion in a Multi-Pass VibroFluidized Bed ...Testing and Evaluation of Particle Motion in a Multi-Pass VibroFluidized Bed ...
Testing and Evaluation of Particle Motion in a Multi-Pass VibroFluidized Bed ...
 
Illuminance Performance of Design Block Windows in Public Basic Schools in Ta...
Illuminance Performance of Design Block Windows in Public Basic Schools in Ta...Illuminance Performance of Design Block Windows in Public Basic Schools in Ta...
Illuminance Performance of Design Block Windows in Public Basic Schools in Ta...
 
Analysis Of Physic-Chemical Characteristics Of Polluted Water Samples And Eva...
Analysis Of Physic-Chemical Characteristics Of Polluted Water Samples And Eva...Analysis Of Physic-Chemical Characteristics Of Polluted Water Samples And Eva...
Analysis Of Physic-Chemical Characteristics Of Polluted Water Samples And Eva...
 
Boost Converter with Improved Voltage Conversion Ratio Using Bootstrap Capaci...
Boost Converter with Improved Voltage Conversion Ratio Using Bootstrap Capaci...Boost Converter with Improved Voltage Conversion Ratio Using Bootstrap Capaci...
Boost Converter with Improved Voltage Conversion Ratio Using Bootstrap Capaci...
 
The Concept of Control and Manage Plastic Pollution of India/World
The Concept of Control and Manage Plastic Pollution of India/WorldThe Concept of Control and Manage Plastic Pollution of India/World
The Concept of Control and Manage Plastic Pollution of India/World
 
Improvement of MFSK -BER Performance Using MIMO Technology on Multipath Non L...
Improvement of MFSK -BER Performance Using MIMO Technology on Multipath Non L...Improvement of MFSK -BER Performance Using MIMO Technology on Multipath Non L...
Improvement of MFSK -BER Performance Using MIMO Technology on Multipath Non L...
 
Improved Sugar Yield for Bioethanol Production by Modelling Enzymatic Hydroly...
Improved Sugar Yield for Bioethanol Production by Modelling Enzymatic Hydroly...Improved Sugar Yield for Bioethanol Production by Modelling Enzymatic Hydroly...
Improved Sugar Yield for Bioethanol Production by Modelling Enzymatic Hydroly...
 
Numerical Solution of Third Order Time-Invariant Linear Differential Equation...
Numerical Solution of Third Order Time-Invariant Linear Differential Equation...Numerical Solution of Third Order Time-Invariant Linear Differential Equation...
Numerical Solution of Third Order Time-Invariant Linear Differential Equation...
 
Evaluation of Various Polymorphs by Different Techniques and Their Characteri...
Evaluation of Various Polymorphs by Different Techniques and Their Characteri...Evaluation of Various Polymorphs by Different Techniques and Their Characteri...
Evaluation of Various Polymorphs by Different Techniques and Their Characteri...
 
Microstructural and Dielectric Characterization of Sr doped Ba(Fe0.5Ta0.5)O3 ...
Microstructural and Dielectric Characterization of Sr doped Ba(Fe0.5Ta0.5)O3 ...Microstructural and Dielectric Characterization of Sr doped Ba(Fe0.5Ta0.5)O3 ...
Microstructural and Dielectric Characterization of Sr doped Ba(Fe0.5Ta0.5)O3 ...
 
Yanamadurru Drain Water Quality Assessment during 12-13 March, 2016
Yanamadurru Drain Water Quality Assessment during 12-13 March, 2016Yanamadurru Drain Water Quality Assessment during 12-13 March, 2016
Yanamadurru Drain Water Quality Assessment during 12-13 March, 2016
 
Gesture Controlled Chair
Gesture Controlled ChairGesture Controlled Chair
Gesture Controlled Chair
 
Fish Larval Nutrition: A Review on New Developments
Fish Larval Nutrition: A Review on New DevelopmentsFish Larval Nutrition: A Review on New Developments
Fish Larval Nutrition: A Review on New Developments
 
The Analysis of Men’s Emotional State from Heart Rate Using Daq & Labview
The Analysis of Men’s Emotional State from Heart Rate Using Daq & LabviewThe Analysis of Men’s Emotional State from Heart Rate Using Daq & Labview
The Analysis of Men’s Emotional State from Heart Rate Using Daq & Labview
 
Reaction of consumers against the rising milk prices in Vietnam: A case study...
Reaction of consumers against the rising milk prices in Vietnam: A case study...Reaction of consumers against the rising milk prices in Vietnam: A case study...
Reaction of consumers against the rising milk prices in Vietnam: A case study...
 

Similar to Study of Probability Distributions of Cpi and Spi in Earned Value Analysis

Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...IRJET Journal
 
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...IJERA Editor
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxSudipBalLama
 
Earned Value Management Meets Big Data
Earned Value Management Meets Big DataEarned Value Management Meets Big Data
Earned Value Management Meets Big DataGlen Alleman
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementIRJET Journal
 
Forecasting cost and schedule performance
Forecasting cost and schedule performanceForecasting cost and schedule performance
Forecasting cost and schedule performanceGlen Alleman
 
Agile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementAgile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementGlen Alleman
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfMadhusha15
 
Running head critical path method1 critical path method7critic
Running head critical path method1 critical path method7criticRunning head critical path method1 critical path method7critic
Running head critical path method1 critical path method7criticDIPESH30
 
Cost management
Cost managementCost management
Cost managementshkadry
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...IRJET Journal
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government ContractingGlen Alleman
 
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...Aravind NC
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part twoHossam Maghrabi
 
Increasing the probability of program success
Increasing the probability of program successIncreasing the probability of program success
Increasing the probability of program successGlen Alleman
 

Similar to Study of Probability Distributions of Cpi and Spi in Earned Value Analysis (20)

Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
 
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptx
 
Earned Value Management Meets Big Data
Earned Value Management Meets Big DataEarned Value Management Meets Big Data
Earned Value Management Meets Big Data
 
DPPM1
DPPM1DPPM1
DPPM1
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
 
Forecasting cost and schedule performance
Forecasting cost and schedule performanceForecasting cost and schedule performance
Forecasting cost and schedule performance
 
Agile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementAgile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value Management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
 
Running head critical path method1 critical path method7critic
Running head critical path method1 critical path method7criticRunning head critical path method1 critical path method7critic
Running head critical path method1 critical path method7critic
 
Cost management
Cost managementCost management
Cost management
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government Contracting
 
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
 
Increasing the probability of program success
Increasing the probability of program successIncreasing the probability of program success
Increasing the probability of program success
 

Recently uploaded

Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...soginsider
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086anil_gaur
 

Recently uploaded (20)

Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 

Study of Probability Distributions of Cpi and Spi in Earned Value Analysis

  • 1. The International Journal Of Engineering And Science (IJES) || Volume || 5 || Issue || 5 || Pages || PP -131-136 || 2016 || ISSN (e): 2319 – 1813 ISSN (p): 2319 – 1805 www.theijes.com The IJES Page 131 Study of Probability Distributions of Cpi and Spi in Earned Value Analysis Priya Deshpande1 , Harihar S. Lunge2 1 Institute of Industrial and Computer management and Research, Nigdi , Pune.(M.S.) 2 Shri Shivaji Science college, Amaravati , (M.S.) --------------------------------------------------------ABSTRACT----------------------------------------------------------- Earned Value analysis (EVA) is the most efficient tool used for transitional review of project execution .It is helpful to project managers and management team to value the progress of project work throughout the project life cycle. The Earned Schedule (ES) is used to approximate the time or duration of project/ s for appropriate evaluation of project execution. ES also help to forecast the time required to complete the project. When combined with schedule analysis, ES can enhance the project. EVA provides the controlling tool for better decision making in project management. The paper discuss about the probability distribution of Cost performance Index (CPI) and Schedule performance Index (SPI). Best fitted distribution will help for forecasting project duration effectively. This helps the Project Manager to prevent the over budgeted cost in future. So an attempt is made to find the alternative distribution of CPI and SPI for better decision making. If the project schedule performance shows poor results then manager need to take the corrective action with the help of this tool. Weibull, Gamma and Exponentiated Exponential Distribution functions are used to study the effect of SPI on CPI. For making better decision in project scheduling, Project managers can review the parameters using EVM tool. The tool is useful in all types of civil engineering and software engineering projects. Keywords: Earned Value Analysis(EVA), Earned Value Management(EVM), Cost Performance Index(CPI), Scheduled Performance Index(SPI) , Probability distribution. ------------------------------------------------------------------------------------------------------------------------------------- Date of Submission: 06 May 2016 Date of Accepted: 25 May 2016 -------------------------------------------------------------------------------------------------------------------------------------- I. INTRODUCTION In project management, it is very important to keep the completion deadlines and project cost in control .Each project should be completed in scheduled time and in budgeted cost and as per customer‟s dynamic expectation, is a big task. Guiding the project team in appropriate direction with proper risk assessment associated with project activities is not a very easy task. If the project manager is capable of executing the project plan as per schedule with minimum variation, then it will certainly shows better performance as the project progresses. If some problem arises during project execution, then some reserved sources are used to compensate that impact on project. EVA minimizes the use of reserves by anticipating and estimating the performance of activities during the execution of project. The effective use of EVA and ES will create good opportunities to complete the project within time and cost. In EVM, Earned value analysis (EVA) is used for measuring project progress in an effective way. EVA has the capability to measurements of scope, schedule, and cost collectively. Earned value is the cumulative value of work completed at that point of time. Planned value is the budgeted cost for accomplishing that activity. Actual cost is the cumulative money spent to accomplish that activity at given point of time. The Earned Value Management (EVM) indicators are Schedule Variance (SV) is used to compute the cost difference, i.e.SV= Earned Value –Planned Value, while the Cost Variance (CV) = Earned Value – Actual Cost. The Cost and Schedule Performance Indexes, CPI and SPI, respectively, are ratios. SPI is computed from the ratio, EV/PV, while CPI equals EV/AC. The cost indicators behave differently from those for schedule. The cost indicators appear to establish a trend with some variation. Similarly, the schedule indicators initially appear to establish a trend, The study of Cost Performance Index (CPI), Schedule Performance Index (SPI), will be studied to develop the new regression model to forecast the project cost. This paper discusses about effectiveness of Earned Value Management and Earned Schedule for better results and proper decision making in Project and risk management. By knowing the over exact function form of CPI and SPI, Project manager can work better on cost and time so as to reduce delay time. Project manager can prepare alternative contingency plan to reduce risk and avoid the delay in project completion in minimal over budget cast.
  • 2. Study of Probability Distributions of CPI and SPI in Earned Value Analysis…. www.theijes.com The IJES Page 132 1.2.1 Problem statement: How to control the risk, delay in time and cost of the project using Earned Value Management and Earned Scheduled? 1.2.2 Research objective: The main objective of this paper is to study the best suited distribution for CPI and SPI to reduce risk, to study delay time in completion and to estimate the minimum budgeted cost. H0: The assumed distribution of the data set is same as the observed one. H1: The assumed distribution of the data set is not same as the observed one II. LITERATURE REVIEW (ES) is an extension to Earned Value Management (EVM) providing the capability of schedule analysis. ES was introduced in 2003 by Lipke in article “Schedule Is Different” 6 . “Connecting Earned Value to the Schedule,” 6 “ES can be used for much more. It facilitates the ability to identify constraints, impediments, and the possibility of rework at the task level. This information is very useful for management purposes, but it does not provide performance indicators below the project level. ES can be applied to sub-levels of the project. Using this capability, the project manager can analyze schedule performance at virtually any level desired – control accounts, work packages, and critical path activities.”6 Earned Value Management is a system which integrate the scope, cost and time management of project by using the resource –loaded project schedule and facilitate the systematic measurement of various factors involved in it.11 EVM is endorsed by the Project management Institute 10 and is implemented by public and private organization for project progress evaluation .The main benefit of EVM is that it is applicable to all types and sizes of projects. Furthermore, the method is being used in research, instructed in several universities, and is included in recent project management texts and the newer EVM analysis tools. Presently an appendix describing ES is being prepared for inclusion in the PMIPractice Standard for Earned Value Management 9 . III. TERMINOLOGY AND METHODS 3.1 Project Management There are many tools to measure the project progress and evaluate the performance of the project. But EVA and ES gives the efficient way of measuring the performance using cost performance index , schedule performance index, ,earned scheduled and the various indices associated with it. During project execution if CPI = 1, it indicates that the project is as per scheduled and completed at planned or budgeted cost. If SPI = 1 then it indicates that the project is on schedule and it will be completed in estimated time. Now the project manager is capable of estimating the delay time and over budgeted cost and can use the reserved resources to complete the project in forecasted time and with minimal use of reserved resources. 3.1.1 Elements of Earned Value Management There are 3 major elements of project management: scope, cost and time management. In EVM the review is taken after specific interval of time and continuous monitoring is required to find the actual expenses and actual amount of work completed. The periodic comparison is done between actual expenses and planned or budgeted cost of that work done and ii) actual amount of work done and scheduled amount of work to be done in that period. In this regard, two performance indices SPI and CPI are measured in terms of four indicators using three functions. 3.1.2 Three functions of EVM: 1) Planned value,(PV) 2) Earned value (EV) and 3) Actual cost (AC) Four factors and indicators used to in Earned value Analysis: - 1) Cost variance (CV) = EV – AC 2) Cost Performance Index (CPI) = EV /AC 3) Schedule Variance (SV) = EV – PV 4) Schedule Performance Index (SPI) = EV/ PV Earned Value Management (EVM) has been applied to various projects from several years. It has proven to be a successful tool to project planning, tracking, and decision-making. And, the Reporting methods of EVM are proved a very good tool for communicating with management ,customers and stakeholders. From many years, in the Software Development Industry ,the EVM is applied to study the project performance . Statistical techniques are used to predict project outcomes, and past data is used for new project planning. To confidently apply EVM data for outcome prediction and project planning, data must be recorded in correct and accurate manner. It is identified that the schedule indicators of EVM fall short to provide correct and good information. To overcome this deficiency, the Software Development Industry has been applying the concept and methods of “Earned Schedule”.
  • 3. Study of Probability Distributions of CPI and SPI in Earned Value Analysis…. www.theijes.com The IJES Page 133 3.2 Earned Value Analysis (EVA): Earned Value Analysis is computed by taking product os budgeted cost per activity and completion percentage and sum all activities in the project. Basic elements required for Earned Value Analysis are :Budget At Completion (BAC). Total budgeted cost of project. Planned value (PV): Earlier it is also called as Budgeted Cost of Work Scheduled (BCWS). Budgeted cost of work performed (BCWP): Budgeted cost of work that is completed in given point of time in project. Actual cost (AC) or Actual Cost of Work Performed (ACWP). 3.3 ES: Earned Schedule ES method is largely measured to be a important advancement to the practice of EVM. Canada, India, Japan and other countries, as ES is being used majorly in all industries where EVM is applied for all sizes of projects. The measure of ES has provided schedule analysis and forecasting capacity to those using EVM. ES facilitates a simple calculation for the forecasting of project duration and completion dates. In addition, it has been shown that the forecasting is improved through the application of statistical methods 16 . “Earned Schedule is a fairly new method for analyzing schedule performance; it is a derived application of Earned Value Management (EVM) data. Created three years ago, the method has propagated to several countries and been used for various types of work spanning a large and varied range of project sizes. 3.4 Forecasts “A significant advantage from applying ES is that the method provides the capability to forecast the project duration and the expected completion date. Other methods exist; however, through studies it has been shown that ES is the most reliable forecasting method using EVM data.” 15 3.4.1 Elements of Earned Schedule Management Various parameters used in Earned Value Management and Earned Schedule: Actual Time (AT): This is the duration from the beginning of the project to status date. Schedule at Completion (SAC): This is the original planned completion duration of the project. Earned Schedule (ES): This is the duration from the beginning of the project to the date on which PV should have been equal to the current value of EV. ES = % Complete x SAC Time Variance (TV): The Time variance is a measure of schedule performance in time units rather than cost units. TV = ES – AT If TV value is negative the project is behind schedule, and if it is positive it is ahead of schedule. Planned Value (PV) is the estimated value of the work planned to be done. Earned Value (EV) is the estimated value of the work actually accomplished. Actual Cost (AC) is the actual cost incurred for the work accomplished. Cost Variance CV = EV - AC If it is negative then project is going to be over Budget. Cost Performance Index (CPI) = EV / AC Critical Ratio (CR) = CPI * SPI Overall Performance of the Project. IV. PROBABILITY DISTRIBUTIONS The basic need of knowing the exact form of distribution followed by CPI and SPI is to understand the nature of these parameters. With the help of accurate function form of CPI and SPI, forecasting models can be developed based on these distributions to reduce delay time and ultimately project cost. Alternative distribution function forms will be available for predictive analysis which will enhance the application domain area of the predictive models based on these distribution in Project management. Diversity in projects causes the limitation for application of specific distribution in forecasting or predictive models of project management. To overcome this limitation, the paper discusses the set of various distributions which will be available to develop the models for different types of projects. Following distributions are used in project forecasting models: 4.1 Gamma-Type Density Function: The Gamma-Type Density Function is having both a shape and a scale parameter. In Gamma distribution the shape and scale parameters equal to 1, this results in the exponential density function. The p.d.f. of Gamma distribution is: f (x, α, α) = ( αα /αα) xα– 1 e- αx ; α, α, x >0
  • 4. Study of Probability Distributions of CPI and SPI in Earned Value Analysis…. www.theijes.com The IJES Page 134 Applications: It is used for the variables which are one sided bounded at one side ; for example x greater than or equal to zero. The gamma density gives distribution of time required for exactly k independent events to occur, assuming events take place at a constant rate. It is used frequently in queuing theory, reliability, and other industrial applications. The parameters of Gamma distribution describes the scale and shape of the distribution. The distribution shows great flexibility for analysis for positive real data. Comments: Erlangian, Exponential, and Chi-square distributions are special cases. The negative binomial is an similar to gamma distribution with discrete random variable. Limitations of Gamma distribution: The distribution function or survival function cannot be expressed in a closed form if shape parameter is not integer17 . 4.2 Exponentiated Exponential distribution:The Probability density function of exponentiated exponential is defined by Gupta and Kunda (2001) with parameters α and λ as f (x,α, α) =αα(1αeααx )α α.eααx 1 Where α, α, x > 0 Here α is the shape parameter and λ is the scale parameter. When α=1 it represent the exponential family. Application: It gives distribution of time between independent events occurring at a constant rate. Example: Distribution of time between arrival of jobs at a machine. It is useful in framing the strategy and techniques in preventive maintenance. 4.3 Weibull distribution: Weibull distribution is more popular than Gamma distribution according to Gupta and Kundu for analysis of lifetime data. 17 The p.d.f. of Weibull distribution is as follows: f (x, α, α) = αα(x α)α-1 e(- αα) ; α, α, x >0 Application: Weibull distribution is generally useful for random variables which are left side bounded. To determine the hazard rate of a system Weibull distribution is widely used. The Weibull distribution is often used to model "time until failure." In this manner, it is applied in actuarial science and in engineering work. Example: Life distribution for some capacitors, ball bearings, relays, and similar variables.. Comments: Rayleigh and exponential distribution are special cases. Advantage of Weibull distribution over Gamma distribution: Weibull distribution has an important property that distribution function of Weibull distribution can be expressed in closed form for fractional and integer value which does not hold true in Gamma distribution. Due to this property, Weibull distribution is useful for any type of data. Extreme value Distribution: Application: Limiting model for the distribution of the maximum or minimum of N values selected from an "exponential-type" distribution, such as the normal, gamma, or exponential. Example: Distribution of breaking strength of some materials, capacitor breakdown voltage, gust velocities encountered by airplanes, bacteria extinction times. These distributions are useful in Civil and Mechanical engineering project management. V. DATA SOURCES The Secondary data 14 of eight projects is used.CPI and SPI of projects are computed from the data available using SPSS version 20.The correlation between CPI and SPI is shown in the Table no.1 5.1 Data analysis for CPI and SPI in EVM and ES for performance measures Data analysis is done using MS- Excel and SPSS Version 20 .Chi- square test is used to test the goodness of fit. The chi-square test is used to test the validity of a distribution assumed for a random phenomenon. The test evaluates the null hypotheses H0: The data are governed by the assumed distribution against H1 : The data are not drawn from the assumed distribution. Comparison of Correlation and regression coefficient using Weibull , Gamma, and Exponential distribution.
  • 5. Study of Probability Distributions of CPI and SPI in Earned Value Analysis…. www.theijes.com The IJES Page 135 Function Weibull Gamma Exponetial CPI and SPI Correlation coefficient 0.4692 0.4692 0.4586 Regression coefficient 0.4968 0.4968 0.4843 Table 1 Graph 1 The correlation is used to describe the existence of relationship between variables. Pearson Correlation coefficients is used to evaluate the correlation between two variables is. It is denoted by „r‟ and it lies between -1 and 1. If r = 1, then there is prefect positive correlation between variables under consideration. Gamma distribution: The table shows 2 and 3 the results of test of Goodness of fit using SPSS version 20. Outcome of Chi- square Test of Goodness of Fit Table 2 Test Statistics EE_SPI weibull_SPI Gamma_SPI Chi-Square .000a .000a .000a Df 7 7 7 Asymp. Sig. 1.000 1.000 1.000 a. 8 cells (100.0%) have expected frequencies less than 5. The minimum expected cell frequency is 1.0. Table 3 Test Statistics Weibull_CPI Gamma_CPI EE_CPI Chi-Square .000a .000a .000a Df 7 7 7 Asymp. Sig. 1.000 1.000 1.000 a. 8 cells (100.0%) have expected frequencies less than 5. The minimum expected cell frequency is 1.0. From the Table No. 2 and 3, we have observed that Weibull , Gamma and EE distributions are equally suitable to know the nature of CPI and SPI. We accept the hypothesis that the distribution assumed for CPI and SPI is same as the observed one. CPI and SPI follows the Weibull and Gamma distribution according to 11 but EE also became an alternative distribution to measure the CPI and SPI of the projects. This finding will help to measure the CPI and SPI in case of weak performance of Weibull and Gamma distribution in forecasting models of project management. VI. CONCLUSION Project management is concerned with planning, controlling, checking project progress, monitoring milestones, deliverables and managing risk in project execution. Earned Value Management provides the alarming signals to project manager for making strategic decisions to avoid future loss. Earned Value Management technique helps Project Manager to take corrective actions if project is not going as per schedule. It also helps to reduce the risk
  • 6. Study of Probability Distributions of CPI and SPI in Earned Value Analysis…. www.theijes.com The IJES Page 136 involved in it by changing strategy and implementing corrective action to meet the dead lines and complete the project in budgeted cost. From the discussion , it has be concluded that along with Weibull and Gamma distribution ,Exponentiated Exponential distribution is also most suitable distribution to study the cost and schedule performance indices . In above discussion, Chi square test of hypothesis is applied to civil engineering project data. It has proved that Exponentiated Exponential distribution can be suitable alternative to Weibull and Gamma distribution to study the CPI and SPI in EVM. The Chi square goodness of fit is applied to test the goodness of fit .The EE family of distribution has quite similar properties as that of 2 parameter Weibull and Gamma distributions. Weibull distribution function and Gamma distribution function showed the same result while EE family of distribution gave better results in some data sets. Also it has been observed that in few cases Weibull is better distribution in terms of fitting of the distribution to data set. Along with Weibull and Gamma distribution, EE also can be used very effectively to forecast the project cost on the basis of schedule performance index.From this discussion, we expect that EE can provide constructive result to know the exact nature of CPI and SPI in EVM. This study confirms that EE family can be used as an alternative distribution to study CPI and SPI. Further research can be carried out to study the effect of ratio of CPI and SPI which is significantly contributing and other interdependency factors in variation in CPI and SPI. This work can be extended to compare the application of properties of Weibull, Gamma and EE family of distributions in project management tools like EVM and ES.The nature of CPI and SPI will help to develop the strategic action plan which reduces the risk of overrun and over budgeted cost of the project/s in Project Management. VII. RECOMMENDATIONS The present study analyses the major projects which generally operates with traditional projects management standards. It is a contribution which gives greater reliability application of EE in estimation of CPI and SPI of the projects, because of equivalence among the Weibull, Gamma and EE distribution. We recommend that the training of implementation of EVA and ES should be given to project Managers and generate skills in the use of project management (EVA) and ES methodologies. The combination of these two methodologies caters the need of the project planning and controlling in the Project management field. Also the projects leaders should encourage the combined application of EVA and ES methodologies which causes them to have greater certainty in the project delivery time and therefore the organization can maintain their competitive advantage in a sustainable manner. REFERENCES [1]. C. R. Kothari, Research Methodology, Methods and techniques, 2nd edition (2008), New age International publishers. [2]. Hira and Gupta, Operation Research, 1st Edition (2003), S Chand Publications. [3]. Walt Lipke. Earned Schedule, Schedule performance analysis from EVM measures, PM World Today – January 2011 (Vol XIII, Issue I), originally published in Projects and Profits magazine, India (January 2010, pp 53-61) [4]. Kym Henderson, Education Director, Project Management Institute, Sydney Australia Chapter, Earned Schedule: A Breakthrough Extension to Earned Value Management, © Kym Henderson Page 1 of 10, Originally published as a part of 2007 PMI Asia Pacific Global Congress Proceedings – Hong Kong. [5]. Walt Lipke, Earned Schedule Application to Small Projects, PM World Today – April 2011 (Vol. XIII, Issue IV) [6]. Lipke, Walt. “Schedule is Different,” The Measurable News, March 2003: 10-15. [7]. Siamak Noori, Morteza Bagherpour and Abalfazl Zareei, Department of Industrial Engineering, Iran University of Science and Technology, Tehran, IranWorld, Applying Fuzzy Control Chart in Earned Value Analysis: A New Application Applied Sciences Journal 3 (4): 684-690, 2008ISSN 1818-4952© IDOSI Publications, 2008 [8]. Henderson, Kym. “Further Developments in Earned Schedule,” The MeasurableNews, Spring 2004: 15-22. [9]. PMIPractice Standard for Earned Value Management [PMI, 2005]. [10]. PMI. A Guide to The Project Management Body Of Knowledge. Upper Derby: PMI, 1996. [11]. Byung cheol Kim,Texas A&M university, 2007,” Forecasting project progress and early warning of project overruns with probabilistic methods .” [12]. Rajesh Ganpat Virle1* and Sumedh Y Mhaske1, Int. J. Struct. & Civil Engg. Res. 2013, “ MONITORING OF CONSTRUCTION PROJECTS USING EVM AND ESM TOOLS”. [13]. Ricardo M. Olano, Luis F. Alarcon and Carlos Razuri, Proceedings for the 17th Annual Conference of the International Group for Lean Construction, “UNDERSTANDING THE RELATIONSHIP BETWEEN PLANNING RELIABILITY AND SCHEDULE PERFORMANCE: A CASE STUDY”. [14]. Danial M Brandon, Jr. ,Published in Project Management Journal, June 1998, “ Implementing Earned Value Easily and Effectively”. [15]. Lipke W, 2008a ‖Project duration forecasting : A comparison of earned value management methods to earned schedule ―, Cross talk 10- [16]. Lipke,W.,O.Zwikael,F.Anbari,K.Henderson. ―Prediction of project outcome, the application of statistical methods to Earned Schedule performance indexes,‖ International Journal pf Project Management , 2009. [17]. Rameshwar Gupta and Debasis Kundu ,”Exponentiated Exponential Family: An Alternative to Gamma and Weibull Distributions”, Biometrical Journal 43(2001) 1 , 117-130. [18]. Dr. Arsham's Statistics Site home.ubalt.edu/ntsbarsh/business-stat/opre504.htm visited on 2015-10-25.