SlideShare a Scribd company logo
1
Transformer Failure Due to Circuit Breaker
Induced Switching Transients
Part 2: EMTP Modeling and Case Studies
David D. Shipp, PE
Fellow, IEEE
Eaton Electrical Group
130 Commonwealth Dr.
Warrendale, PA 15086
Thomas J. Dionise, PE
Senior Member, IEEE
Eaton Electrical Group
130 Commonwealth Dr.
Warrendale, PA 15086
2
2
Transient Analysis Tools
• Electromagnetic Transients Program (EMTP)
• Developed by Hermann Dommel brought to BPA
• Major contributors: Scott Meyer & Dr. Liu at BPA
• Alternative Transients Program (ATP)
• Alternative to commercialized EMTP
• Free to all if agree not to commercialize it
• EMTP-RV
• PSCAD EMT/DC
2
3
3
ATP
• ATP Draw interface
• 3-phase modeling
• Solution method - Trapezoidal integration
• Robust for wide variety of modeling needs
• Extensive library of models
• Many options and features
4
4
Source Model
• “3-phase wye cosine”
• Resistance in ohms
• Inductance in mili-Henries
• Source Impedance
• Z1 and X/R
• Z0 and X/R
SYSTEM SOURCE
AT 13.8 KV
XUTIL
RUTIL
VUTIL
UN
U UT
3
5
5
Cable Model
• “Pi Model”
• Resistance in ohms
• Inductance in mili-Henries
• Cable charging in micro-Farads
• ½ charging on sending end
• ½ charning on receiving end
• Multiple pi models in some cases
CABLE
13.8KV
C1 LCABLE
RCABLE C2
C/2C/2
6
6
Breaker Model
• “Switch”
• Time dependent switch
• Open or close at a specific time
• Opens at current zero unless specify otherwise
• Current dependent switch
• Needed for current chopping
• Define current at which to open switch
• Independent Poles (A, B and C independent)
• Data request
• Vacuum or SF6 breaker nameplate
• Current chop (ask manufacturer)
• Transient Recovery Voltage Ratings – T2, E2 and RRV
VCB
BKR
4
7
7
Transformer Model
• “Three Phase Model”
• Resistance in ohms
• Inductance in mili-Henries
• Magnetizing current
• Winding capacitance
• CH and CL for dry-types
• CHL for oil-filled
• More detailed modeling
• Saturation
• Hysteresis
• Data Request
• %Z and X/R, MVA
• BIL
TRANSFORMER
RLRG
LTRAN RTRANT1 T2
CH CL
N:1
8
8
Complete System Model
TRANSFORMER
RLRG
LTRAN
RTRANT1 T2
CH CL
N:1
CABLE
13.8KV
C1 LCABLE
RCABLE C2
C/2C/2
SYSTEM SOURCE
AT 13.8 KV
XUTIL
RUTIL
VUTIL
UN
U UT
VCB
BKR
5
9
9
Time Step
• Time Step – Integration Time Step
• Choice depends on frequency of expected transient
• Too large – miss high frequency effects
• Too small – excessive simulation times
• Nyquist Criteria
• Minimum sample rate = 2 x frequency
• Example 10-20KHz ring for VCB transient
10
10
Switching Transient Simulations
• Switching transient simulations
• EMTP and model requirements
• Case studies
• Data Center
• Ferry Propulsion
• Laddle Melt Furnace
• Successful techniques/solutions
6
11
11
Ferry Propulsion
Highlights
• 60K passengers per day
• 20M passengers per year
• 4160V distribution
• 3 x 2865kW diesel gens
• 2 x 1865KW forward propulsion motors
• 2 x 1865KW reverse propulsion
12
12
Problem
• Forward propulsion drives ferry
• Upon reaching dock, reverse propulsion stops ferry
• July 1, 2009, reverse propulsion was lost entering dock
• lost power and hit a pier at full speed
• one serious injury and nine minor injuries
• 750 to 800 passengers were aboard
• impact did not send any passengers overboard
• 1185KVA rectifier transformer failed on reverse propulsion
motor
• Evidence of insulation failure on first few turns of primary
winding
• Investigation into source of such failure VCB switching
7
13
13
Ferry - Oneline
Vacuum
Breaker
Short
Cable
Dry-Type
Transformer
Forward Reverse
14
14
Ferry – Electrical Highlights
• 3 x 2865kW diesel generators
• 4160V, 3-bus system
• Vacuum circuit breakers – 630A mains, ties,
feeders
• 2 x 1865kW motors (forward propulsion)
• 2 x 1865kW motors (reverse propulsion)
• 8 x 1185KVA dry-type transformers, 30kV BIL
• 3-winding rectifier transformers
• 12-pulse effective (6-pulse VFD per winding)
• Feeder cable lengths of 50 feet each
8
15
15
Worst Case Scenarios
• Feeder cable lengths of 50 feet
• Each 1185KVA transformer has one 4160V feeder
• Need to examine both feeders for each transformer
• “Worst Case” Switching Transient Simulations
• Close 4160V VCB to transf. with 50ft. cable (model validation)
• Close 4160V VCB to transf. with 50ft. cable (re-ignition)
• Open 4160V VCB to transf. with 50ft. cable (current chop)
• Repeat each case with Snubber
16
16
Measurements
Transient Overvoltages at Primary of Rectifier Transformer – VCB Closes
9
17
17
Study Cases
• Case 1 – Closing the 4.16 kV feeder breaker feeding the three
winding rectifier transformer with the distance of 50 feet.
Simulated to match the Siemens measurements to ensure that
the computer model is accurate. (Model Validation)
• Case 2 – Same as Case 1, except with the RC snubber.
• Case 3 - Closing the 4.16 kV feeder breaker feeding the three
winding rectifier transformer, then the 4.16 kV feeder breaker
opens during the inrush current. Shows the possibility of the
vacuum breaker re-ignition. (Re-ignition)
• Case 4 - Same as Case 3, except with the RC snubber.
• Case 5 - Open the 4.16 kV feeder breaker feeding the three
winding rectifier transformer under the light load condition.
(Current Chop)
• Case 6 – Same as Case 5, except with the RC snubber.
18
18
Case 1 – Model Validation
Transformer primary voltage
V max of 4.96kV < 30kV BIL
Oscillation of 20,203Hz > 1000Hz
10
19
19
Case 2 – Valid Model with Snubber
Transformer primary voltage
V max of 3.982kV < 30kV BIL
Oscillation of < 1000Hz
20
20
Case 3 – Re-ignition
Transient Recovery Voltage (TRV) at VCB
11
21
21
Case 4 – Re-ignition with Snubber
Transient Recovery Voltage (TRV) at VCB
22
22
Case 5 – Current Chop
Transformer primary voltage
V max of 31.9kV > 30kV BIL
Oscillation of 958Hz ~ 1000Hz
12
23
23
Case 6 – Current Chop with Snubber
Transformer primary voltage
V max of 8.9kV < 30kV BIL
Oscillation of 299Hz < 1000Hz
24
24
Summary of Current Chop Cases
13
25
25
Summary of Re-Ignition Cases
26
26
Recommendations
• Install snubber at primary of each 1185KVA
rectifier transformer
• 40ohm resistor
• Non-inductive
• Peak voltage – 6 kVpeak
• Peak energy – 2100 Joules
• Average power – 190 Watt
• 0.5uF capacitor
• Rated voltage - 4.16kV
14
27
27
Data Center
Highlights
• Tier III
• LEEDS Certified
• 12.5MVA Capacity
• 13.2KV Ring Bus
28
28
Data Center - Oneline
Vacuum
Breaker
Short
Cable
Cast-Coil
Transformer
15
29
29
Data Center – Electrical Highlights
• 2 x 24.9 kV lines from Factory Shoals and Buzzard
Roast
• 2 x 12.5 MVA transformers
• 13.2 kV “ring-bus” configuration
• MSA and MSB and generator bus GPS
• Vacuum circuit breakers – 600A mains & ties, 200A feeders
• 3 x 2250 KW generators
• 6 x 3750KVA cast coil transformers, 90kV BIL
• 3 x DE Subs CSA, CSB and CSC
• 3 x SE Subs MDSA, MDSB and MLB
• Feeder cable lengths vary from 109 to 249 Feet
30
30
Worst Case Scenario
• Feeder cable lengths vary from 109 to 249 Feet
• Each 3750KVA transformer has two 13.2kV feeders
• Need to examine both feeders for each transformer
• Shortest of all 13.2kV cable runs to 3750KVA
Transformers
• MSB to Transformer CSC – 109 feet
• MSA to Transformer CSC – 111 feet
• “Worst Case” Switching Transient Simulation
• Open 13.2 kV VCB at MSB to CSC with 109ft. cable
• Open 13.2 kV VCB at MSA to CSC with 111ft. cable
16
31
31
Worst Case – Study Case 13
• Study Case 13 - Open the 13.2 kV feeder breaker at
Bus MSB feeding the 3,750 kVA dry type transformer
CSC with the shorter distance of 109 feet. The result
for this case will represent the “worst-case” condition,
the other feeder from Bus MSA has a longer feeder
distance of 111 feet.
• Study Case 14 – Same as Case 13, except with the
application of the 0.25 μF surge capacitor.
• Study Case 15 – Same as Case 13, except with the
application of the snubber circuit with 30ohm and 0.25
μF surge capacitor.
32
32
Case 13 – no surge protection
Load current at 13.2kV VCB
Load current of 10A
Chopped current of 6A
17
33
33
Case 13 – no surge protection
Transformer CSC primary voltage
VC max of 65.3kV > 95kV BIL
VB max of 116kV > 95kV BIL
VA max of 123kV > 95kV BIL
Oscillation of 969Hz > 1000Hz
34
34
Case 14 – 0.25uF surge cap
Load current at 13.2kV VCB
Load current of 10A
Chopped current of 6A
18
35
35
Case 14 – 0.25uF surge cap
Transformer CSC primary voltage
VA max of 29.4kV < 95kV BIL
VB max of 19.1kV < 95kV BIL
VC max of 15.7kV < 95kV BIL
Oscillation of 215Hz < 1000Hz
36
36
Case 15 – snubber 30ohm and 0.25uF
Load current at 13.2kV VCB
Load current of 10A
Chopped current of 6A
19
37
37
Case 15 – snubber 30ohm and 0.25uF
Transformer CSC primary voltage
VB max of 28.6kV < 95kV BIL
VA max of 19.4kV < 95kV BIL
VC max of 15.9kV < 95kV BIL
Oscillation of 215Hz < 1000Hz
38
38
Case 15 – snubber 30ohm and 0.25uF
Snubber Current – important for duty on resistor and capacitor
IC peak of 7.7A
IB peak of 8.0A
IA peak of 6.8A
20
39
39
Comparison of Results
No
Snubber
0.25uF
surge cap
Snubber
R=30ohm
C=0.25uF
40
40
Measured Transients with Snubber
21
41
41
Recommendations
• Install snubber at primary of each 3750KVA cast coil
transformer 30ohm and 0.25uF
• Install surge caps 0.25uF at each emergency
generator
• Install surge arresters at the following locations:
• both incoming power transformers
• every distribution dry type transformer
• every generator
• line side of both main circuit breakers
• line side of the three generator circuit breakers
• load side of every feeder breaker and every tie circuit breaker
42
42
Laddle Melt Furnace
Highlights
• Retiring 3 x 38MW EAFs
• Adding 1 x 155MVA EAF
• Adding 2 x 138kV lines to new EAF
• Adding SVC at 34.5kV
• Adding 1 x 20MW LMF
22
43
43
LMF & EAF - Oneline
Vacuum
Breaker
Short
Bus
Oil-Filled
Transformer
Existing
EAF New
LMF
44
44
138KV
UTILITY
4713MVA 3PH SC
9.26 X/R
50/66/83MVA
135.3/26.4KV
7.5%Z
SF-6 BREAKER
2000A
1600A
27KV
13OHM
AUTO LTC
56MVA
27-10KV
3.3%Z
ALUMINUM
IPS BUS
53FEET
VACUUM BREAKER
1200A
LMF XFMR
50/56MVA
25/.53KV
2.5%Z
HEAVY DUTY
COPPER PIPE
28FEET
LMF
20MW
LMF
Vacuum
Breaker
Short
Bus
Oil-Filled
Furnace
Transformer
New
LMF
SF6
Breaker
Short
Bus
Oil-Filled
Auto-Regulating
Transformer
23
45
45
LMF Circuit – Electrical Highlights
• 50MVA Power Transformer 135/26.4kV
• 27kV system
• SF6 circuit breaker – 2000A
• Bus length of 53 feet
• 56MVA autoregulating transformer, 200kV BIL
• Vacuum circuit breaker – 1200A
• Bus length of 28 feet
• 50MVA oil-filled LMF transformer, 200kV BIL
• 20MW LMF
46
46
Worst Case Scenarios
• Examine switching transients at both transformers
• “Worst Case” Switching Transients for Auto-Reg Transf
• Open SF6 breaker to transf. with 53ft. bus (6A current chop)
• 3 cycles after energizing Auto-Reg Tran, open SF6 bkr to transf.
with 53ft. bus (re-ignition) highly inductive current
• “Worst Case” Switching Transients for LMF Transf
• Open VCB to transf. with 28ft. bus (6A current chop)
• 3 cycles after energizing LMF Tran, open VCB to transf. with
28ft. bus (re-ignition) highly inductive current
• Repeat each case with Snubber
24
47
47
Case 1 – Open VCB
LMF Transformer primary voltage
V max of 386kV > 200kV BIL
Oscillation of 1217Hz > 1000Hz
48
48
Case 2 – Open VCB with Snubber
LMF Transformer primary voltage
V max of 56.4kV < 200kV BIL
Oscillation of 200Hz < 1000Hz
25
49
49
Case 3 – Open SF6 Breaker
Auto-regulating Transformer primary voltage
V max of 23kV < 200kV BIL
No oscillating frequency
50
50
Case 4 – Open SF6 Breaker with Snubber
Auto-regulating Transformer primary voltage
VB max of 54.7kV < 200kV BIL
Oscillation of 197Hz < 1000Hz
26
51
51
Case 5 – VCB Re-ignition
Transient Recovery Voltage for VCB
52
52
Case 5 – Highly Inductive Current
Inrush current to LMF transformer
6000A Peak
Inrush
VCB
Opens
VCB
Closes
27
53
53
Case 6 – VCB Re-ignition & Snubber
Transient Recovery Voltage for VCB
54
54
Case 7 – SF6 Breaker Re-ignition
Transient Recovery Voltage for Siemens SF6
28
55
55
Case 7 – Highly Inductive Current
Inrush current to Auto-Regulating transformer
14000A Peak
Inrush
SF6 CB
Opens
SF6 CB
Closes
56
56
Case 8 – SF6 Breaker Re-ignition & Snubber
Transient Recovery Voltage for SF6 Breaker
29
57
57
Summary of Current Chop Cases
58
58
Summary of Re-Ignition Cases
30
59
59
Recommendations
• Install snubber (100ohm and 0.15uF) at primary of
each transformer
• 100ohm resistor
• Non-inductive
• Peak voltage – 38 kVpeak
• Peak energy – 17,500 Joules
• Average power – 1000 Watt
• 0.15uF, 34.5kV surge capacitor (not available)
• 1-pole, 24kV, 0.13uF
• 2-pole, 14.4kV, 0.5uF
• Series combination gives 0.103uF

More Related Content

What's hot

Energy conservation Activites of thermal power plant
Energy conservation Activites of thermal power plantEnergy conservation Activites of thermal power plant
Energy conservation Activites of thermal power plant
MANOJ KUMAR MAHARANA
 
Power Topologies_Full Deck_04251964_Mappus
Power Topologies_Full Deck_04251964_MappusPower Topologies_Full Deck_04251964_Mappus
Power Topologies_Full Deck_04251964_MappusSteve Mappus
 
Wide Vin DC/DC Converters: Reliable Power for Demanding Applications
		 Wide Vin DC/DC Converters: Reliable Power for Demanding Applications		 Wide Vin DC/DC Converters: Reliable Power for Demanding Applications
Wide Vin DC/DC Converters: Reliable Power for Demanding ApplicationsDesign World
 
Protection settings calculation
Protection settings calculationProtection settings calculation
Protection settings calculation
LANOGWA RODGERS
 
Current_Shap_Strat_Buck_PFC
Current_Shap_Strat_Buck_PFCCurrent_Shap_Strat_Buck_PFC
Current_Shap_Strat_Buck_PFCSteve Mappus
 
Cuk dc dc+converter
Cuk dc dc+converterCuk dc dc+converter
Cuk dc dc+converter
Air University
 
Simple SF6 CB Testing for Switchyard Equipment.
Simple SF6 CB Testing for Switchyard Equipment.Simple SF6 CB Testing for Switchyard Equipment.
Simple SF6 CB Testing for Switchyard Equipment.
SARAVANAN A
 
Transformer tests
Transformer testsTransformer tests
Transformer tests
pandiyarajanc
 
Fat procedure for lv switchboards
Fat procedure for lv switchboardsFat procedure for lv switchboards
Fat procedure for lv switchboards
khongai
 
40 MVA TX
40 MVA TX40 MVA TX
40 MVA TX
LANOGWA RODGERS
 
Meter Multiplier
Meter MultiplierMeter Multiplier
Meter Multiplierpplunkett
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
SMRITI KESHARWANI
 
Meter Shunt (Ammeter)
Meter Shunt (Ammeter)Meter Shunt (Ammeter)
Meter Shunt (Ammeter)pplunkett
 
Low dropout regulator(ldo)
Low dropout regulator(ldo)Low dropout regulator(ldo)
Low dropout regulator(ldo)altaf423
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjar
Mukesh gurjar
 
Distribution Transformer testing, West Bengal, India
Distribution Transformer testing,  West Bengal, IndiaDistribution Transformer testing,  West Bengal, India
Distribution Transformer testing, West Bengal, India
RajuMondal18
 
Simple Current Transformer (CT) Testing for Switchyard Equipment.
Simple Current Transformer (CT) Testing for Switchyard Equipment.Simple Current Transformer (CT) Testing for Switchyard Equipment.
Simple Current Transformer (CT) Testing for Switchyard Equipment.
SARAVANAN A
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.
Geetesh Verma
 

What's hot (20)

Energy conservation Activites of thermal power plant
Energy conservation Activites of thermal power plantEnergy conservation Activites of thermal power plant
Energy conservation Activites of thermal power plant
 
Power Topologies_Full Deck_04251964_Mappus
Power Topologies_Full Deck_04251964_MappusPower Topologies_Full Deck_04251964_Mappus
Power Topologies_Full Deck_04251964_Mappus
 
Wide Vin DC/DC Converters: Reliable Power for Demanding Applications
		 Wide Vin DC/DC Converters: Reliable Power for Demanding Applications		 Wide Vin DC/DC Converters: Reliable Power for Demanding Applications
Wide Vin DC/DC Converters: Reliable Power for Demanding Applications
 
Protection settings calculation
Protection settings calculationProtection settings calculation
Protection settings calculation
 
Current_Shap_Strat_Buck_PFC
Current_Shap_Strat_Buck_PFCCurrent_Shap_Strat_Buck_PFC
Current_Shap_Strat_Buck_PFC
 
Flyback Converters v4
Flyback Converters v4Flyback Converters v4
Flyback Converters v4
 
Cuk dc dc+converter
Cuk dc dc+converterCuk dc dc+converter
Cuk dc dc+converter
 
Project 2 Cascode
Project 2 CascodeProject 2 Cascode
Project 2 Cascode
 
Simple SF6 CB Testing for Switchyard Equipment.
Simple SF6 CB Testing for Switchyard Equipment.Simple SF6 CB Testing for Switchyard Equipment.
Simple SF6 CB Testing for Switchyard Equipment.
 
Transformer tests
Transformer testsTransformer tests
Transformer tests
 
Fat procedure for lv switchboards
Fat procedure for lv switchboardsFat procedure for lv switchboards
Fat procedure for lv switchboards
 
40 MVA TX
40 MVA TX40 MVA TX
40 MVA TX
 
Meter Multiplier
Meter MultiplierMeter Multiplier
Meter Multiplier
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Meter Shunt (Ammeter)
Meter Shunt (Ammeter)Meter Shunt (Ammeter)
Meter Shunt (Ammeter)
 
Low dropout regulator(ldo)
Low dropout regulator(ldo)Low dropout regulator(ldo)
Low dropout regulator(ldo)
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjar
 
Distribution Transformer testing, West Bengal, India
Distribution Transformer testing,  West Bengal, IndiaDistribution Transformer testing,  West Bengal, India
Distribution Transformer testing, West Bengal, India
 
Simple Current Transformer (CT) Testing for Switchyard Equipment.
Simple Current Transformer (CT) Testing for Switchyard Equipment.Simple Current Transformer (CT) Testing for Switchyard Equipment.
Simple Current Transformer (CT) Testing for Switchyard Equipment.
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.
 

Viewers also liked

Stranke u dnevnoj štampi - 24.03.-19.04.2016
Stranke u dnevnoj štampi - 24.03.-19.04.2016Stranke u dnevnoj štampi - 24.03.-19.04.2016
Stranke u dnevnoj štampi - 24.03.-19.04.2016
Ninamedia
 
psicomotricidad
psicomotricidadpsicomotricidad
psicomotricidad
Tumente Empoderando
 
Arttherapyworkshopposter
ArttherapyworkshopposterArttherapyworkshopposter
ArttherapyworkshopposterLena Wegenaar
 
Kazakh law 1
Kazakh law 1Kazakh law 1
Kazakh law 1
Archie Parker
 
Mehalithic
MehalithicMehalithic
Mehalithic
Achu Jose
 
Reference_Wates_10Oct08
Reference_Wates_10Oct08Reference_Wates_10Oct08
Reference_Wates_10Oct08Simon Banwell
 
VAISAKH- Resume
VAISAKH- ResumeVAISAKH- Resume
VAISAKH- ResumeVaisakh Ev
 
How To Use SCRIBD.pdf
How To Use SCRIBD.pdfHow To Use SCRIBD.pdf
How To Use SCRIBD.pdf
noniefer20
 
Digital Archiving and Process Centralization for Financial and Insurance Comp...
Digital Archiving and Process Centralization for Financial and Insurance Comp...Digital Archiving and Process Centralization for Financial and Insurance Comp...
Digital Archiving and Process Centralization for Financial and Insurance Comp...
soft Xpansion GmbH & Co. KG
 
Ent101 - Product Development (by Minalytix)
Ent101 - Product Development (by Minalytix)Ent101 - Product Development (by Minalytix)
Ent101 - Product Development (by Minalytix)
NORCAT
 
Samrat Travel Presentation
Samrat Travel PresentationSamrat Travel Presentation
Samrat Travel Presentation
Samrat Tours & Travels Pvt. Ltd.
 
The art of one device fits all
The art of one device fits allThe art of one device fits all
The art of one device fits all
Jill Gilbert
 
Minimum wages ppt
Minimum wages pptMinimum wages ppt
Minimum wages ppt
ankur shrivastava
 
Approaches for the Integration of Visual and Computational Analysis of Biomed...
Approaches for the Integration of Visual and Computational Analysis of Biomed...Approaches for the Integration of Visual and Computational Analysis of Biomed...
Approaches for the Integration of Visual and Computational Analysis of Biomed...
Nils Gehlenborg
 
Ramayana Tour Legend Comes Alive in Sri Lanka
Ramayana Tour Legend Comes Alive in Sri LankaRamayana Tour Legend Comes Alive in Sri Lanka
Ramayana Tour Legend Comes Alive in Sri Lanka
Apna Bharat Tours & Travels
 

Viewers also liked (19)

Stranke u dnevnoj štampi - 24.03.-19.04.2016
Stranke u dnevnoj štampi - 24.03.-19.04.2016Stranke u dnevnoj štampi - 24.03.-19.04.2016
Stranke u dnevnoj štampi - 24.03.-19.04.2016
 
FTI CEO Transition Study
FTI CEO Transition StudyFTI CEO Transition Study
FTI CEO Transition Study
 
psicomotricidad
psicomotricidadpsicomotricidad
psicomotricidad
 
Arttherapyworkshopposter
ArttherapyworkshopposterArttherapyworkshopposter
Arttherapyworkshopposter
 
Kazakh law 1
Kazakh law 1Kazakh law 1
Kazakh law 1
 
Aula Marca Pós-Moderna
Aula Marca Pós-ModernaAula Marca Pós-Moderna
Aula Marca Pós-Moderna
 
Mehalithic
MehalithicMehalithic
Mehalithic
 
Reference_Wates_10Oct08
Reference_Wates_10Oct08Reference_Wates_10Oct08
Reference_Wates_10Oct08
 
VAISAKH- Resume
VAISAKH- ResumeVAISAKH- Resume
VAISAKH- Resume
 
How To Use SCRIBD.pdf
How To Use SCRIBD.pdfHow To Use SCRIBD.pdf
How To Use SCRIBD.pdf
 
Digital Archiving and Process Centralization for Financial and Insurance Comp...
Digital Archiving and Process Centralization for Financial and Insurance Comp...Digital Archiving and Process Centralization for Financial and Insurance Comp...
Digital Archiving and Process Centralization for Financial and Insurance Comp...
 
Ent101 - Product Development (by Minalytix)
Ent101 - Product Development (by Minalytix)Ent101 - Product Development (by Minalytix)
Ent101 - Product Development (by Minalytix)
 
Samrat Travel Presentation
Samrat Travel PresentationSamrat Travel Presentation
Samrat Travel Presentation
 
The art of one device fits all
The art of one device fits allThe art of one device fits all
The art of one device fits all
 
Minimum wages ppt
Minimum wages pptMinimum wages ppt
Minimum wages ppt
 
Travel tips for kailash mansarovar yatra
Travel tips for kailash mansarovar yatraTravel tips for kailash mansarovar yatra
Travel tips for kailash mansarovar yatra
 
Contrato pedagógico
Contrato pedagógicoContrato pedagógico
Contrato pedagógico
 
Approaches for the Integration of Visual and Computational Analysis of Biomed...
Approaches for the Integration of Visual and Computational Analysis of Biomed...Approaches for the Integration of Visual and Computational Analysis of Biomed...
Approaches for the Integration of Visual and Computational Analysis of Biomed...
 
Ramayana Tour Legend Comes Alive in Sri Lanka
Ramayana Tour Legend Comes Alive in Sri LankaRamayana Tour Legend Comes Alive in Sri Lanka
Ramayana Tour Legend Comes Alive in Sri Lanka
 

Similar to Transformer Failure Due to Circuit Breaker Induced Switching Transients

Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
michaeljmack
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
michaeljmack
 
ABB Price List of Capacitors 008
ABB Price List of Capacitors 008ABB Price List of Capacitors 008
ABB Price List of Capacitors 008
R Sanghavi Mercantile Pvt Ltd
 
High Voltage Capacitors Webinar
High Voltage Capacitors Webinar High Voltage Capacitors Webinar
High Voltage Capacitors Webinar
Randall Ghany
 
Chapter 3 Generation of high voltages and current
Chapter 3 Generation of high voltages and currentChapter 3 Generation of high voltages and current
Chapter 3 Generation of high voltages and current
mukund mukund.m
 
Power transformers rating
Power transformers ratingPower transformers rating
Power transformers rating
Leonardo ENERGY
 
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuitsModule 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Asha Anu Kurian
 
Cooper Power Connectors - MV-HV Specifiers Guide 5kV-35kV
Cooper Power Connectors - MV-HV Specifiers Guide 5kV-35kVCooper Power Connectors - MV-HV Specifiers Guide 5kV-35kV
Cooper Power Connectors - MV-HV Specifiers Guide 5kV-35kV
Thorne & Derrick International
 
Hvdc dad
Hvdc dadHvdc dad
Hvdc dad
dharmesh dabhi
 
220kv substation
220kv substation220kv substation
220kv substation
Anbarasu Balakrishnan
 
220 66 kv nrs sub report
220 66 kv nrs sub report220 66 kv nrs sub report
220 66 kv nrs sub report
Mayur Dhanaji Rane
 
INDUSTRIAL SEMINAR PRESENTATION
INDUSTRIAL SEMINAR PRESENTATIONINDUSTRIAL SEMINAR PRESENTATION
INDUSTRIAL SEMINAR PRESENTATIONArgha Dutta
 
Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe
Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe
Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe
Mikolaj Kukawski
 
Pamphlet on important psi parameters rdso
Pamphlet on important psi parameters rdsoPamphlet on important psi parameters rdso
Pamphlet on important psi parameters rdso
sonu200186
 
per_unit_system.pptx
per_unit_system.pptxper_unit_system.pptx
per_unit_system.pptx
PaylamKanal
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)saurabhVEC
 
ct pt testing...........................................
ct pt testing...........................................ct pt testing...........................................
ct pt testing...........................................
hiiarindam
 
Transformers.ppt
Transformers.pptTransformers.ppt
Transformers.ppt
aditya40570
 
UNIT -I per unit calculation,EQUIVALENT CIRCUIT
UNIT -I per unit calculation,EQUIVALENT CIRCUITUNIT -I per unit calculation,EQUIVALENT CIRCUIT
UNIT -I per unit calculation,EQUIVALENT CIRCUIT
Abinaya Saraswathy T
 
Deltatron or Engetron
Deltatron or EngetronDeltatron or Engetron
Deltatron or Engetron
Abdul Rahman Ibrahim
 

Similar to Transformer Failure Due to Circuit Breaker Induced Switching Transients (20)

Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
 
ABB Price List of Capacitors 008
ABB Price List of Capacitors 008ABB Price List of Capacitors 008
ABB Price List of Capacitors 008
 
High Voltage Capacitors Webinar
High Voltage Capacitors Webinar High Voltage Capacitors Webinar
High Voltage Capacitors Webinar
 
Chapter 3 Generation of high voltages and current
Chapter 3 Generation of high voltages and currentChapter 3 Generation of high voltages and current
Chapter 3 Generation of high voltages and current
 
Power transformers rating
Power transformers ratingPower transformers rating
Power transformers rating
 
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuitsModule 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
 
Cooper Power Connectors - MV-HV Specifiers Guide 5kV-35kV
Cooper Power Connectors - MV-HV Specifiers Guide 5kV-35kVCooper Power Connectors - MV-HV Specifiers Guide 5kV-35kV
Cooper Power Connectors - MV-HV Specifiers Guide 5kV-35kV
 
Hvdc dad
Hvdc dadHvdc dad
Hvdc dad
 
220kv substation
220kv substation220kv substation
220kv substation
 
220 66 kv nrs sub report
220 66 kv nrs sub report220 66 kv nrs sub report
220 66 kv nrs sub report
 
INDUSTRIAL SEMINAR PRESENTATION
INDUSTRIAL SEMINAR PRESENTATIONINDUSTRIAL SEMINAR PRESENTATION
INDUSTRIAL SEMINAR PRESENTATION
 
Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe
Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe
Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe
 
Pamphlet on important psi parameters rdso
Pamphlet on important psi parameters rdsoPamphlet on important psi parameters rdso
Pamphlet on important psi parameters rdso
 
per_unit_system.pptx
per_unit_system.pptxper_unit_system.pptx
per_unit_system.pptx
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)
 
ct pt testing...........................................
ct pt testing...........................................ct pt testing...........................................
ct pt testing...........................................
 
Transformers.ppt
Transformers.pptTransformers.ppt
Transformers.ppt
 
UNIT -I per unit calculation,EQUIVALENT CIRCUIT
UNIT -I per unit calculation,EQUIVALENT CIRCUITUNIT -I per unit calculation,EQUIVALENT CIRCUIT
UNIT -I per unit calculation,EQUIVALENT CIRCUIT
 
Deltatron or Engetron
Deltatron or EngetronDeltatron or Engetron
Deltatron or Engetron
 

More from michaeljmack

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993
michaeljmack
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbook
michaeljmack
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbook
michaeljmack
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
michaeljmack
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
michaeljmack
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
michaeljmack
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgear
michaeljmack
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
michaeljmack
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
michaeljmack
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protection
michaeljmack
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systems
michaeljmack
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spaces
michaeljmack
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
michaeljmack
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distribution
michaeljmack
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performance
michaeljmack
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulator
michaeljmack
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plants
michaeljmack
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Stories
michaeljmack
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
michaeljmack
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentals
michaeljmack
 

More from michaeljmack (20)

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbook
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbook
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgear
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protection
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systems
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spaces
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distribution
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performance
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulator
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plants
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Stories
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentals
 

Recently uploaded

power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 

Recently uploaded (20)

power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 

Transformer Failure Due to Circuit Breaker Induced Switching Transients

  • 1. 1 Transformer Failure Due to Circuit Breaker Induced Switching Transients Part 2: EMTP Modeling and Case Studies David D. Shipp, PE Fellow, IEEE Eaton Electrical Group 130 Commonwealth Dr. Warrendale, PA 15086 Thomas J. Dionise, PE Senior Member, IEEE Eaton Electrical Group 130 Commonwealth Dr. Warrendale, PA 15086 2 2 Transient Analysis Tools • Electromagnetic Transients Program (EMTP) • Developed by Hermann Dommel brought to BPA • Major contributors: Scott Meyer & Dr. Liu at BPA • Alternative Transients Program (ATP) • Alternative to commercialized EMTP • Free to all if agree not to commercialize it • EMTP-RV • PSCAD EMT/DC
  • 2. 2 3 3 ATP • ATP Draw interface • 3-phase modeling • Solution method - Trapezoidal integration • Robust for wide variety of modeling needs • Extensive library of models • Many options and features 4 4 Source Model • “3-phase wye cosine” • Resistance in ohms • Inductance in mili-Henries • Source Impedance • Z1 and X/R • Z0 and X/R SYSTEM SOURCE AT 13.8 KV XUTIL RUTIL VUTIL UN U UT
  • 3. 3 5 5 Cable Model • “Pi Model” • Resistance in ohms • Inductance in mili-Henries • Cable charging in micro-Farads • ½ charging on sending end • ½ charning on receiving end • Multiple pi models in some cases CABLE 13.8KV C1 LCABLE RCABLE C2 C/2C/2 6 6 Breaker Model • “Switch” • Time dependent switch • Open or close at a specific time • Opens at current zero unless specify otherwise • Current dependent switch • Needed for current chopping • Define current at which to open switch • Independent Poles (A, B and C independent) • Data request • Vacuum or SF6 breaker nameplate • Current chop (ask manufacturer) • Transient Recovery Voltage Ratings – T2, E2 and RRV VCB BKR
  • 4. 4 7 7 Transformer Model • “Three Phase Model” • Resistance in ohms • Inductance in mili-Henries • Magnetizing current • Winding capacitance • CH and CL for dry-types • CHL for oil-filled • More detailed modeling • Saturation • Hysteresis • Data Request • %Z and X/R, MVA • BIL TRANSFORMER RLRG LTRAN RTRANT1 T2 CH CL N:1 8 8 Complete System Model TRANSFORMER RLRG LTRAN RTRANT1 T2 CH CL N:1 CABLE 13.8KV C1 LCABLE RCABLE C2 C/2C/2 SYSTEM SOURCE AT 13.8 KV XUTIL RUTIL VUTIL UN U UT VCB BKR
  • 5. 5 9 9 Time Step • Time Step – Integration Time Step • Choice depends on frequency of expected transient • Too large – miss high frequency effects • Too small – excessive simulation times • Nyquist Criteria • Minimum sample rate = 2 x frequency • Example 10-20KHz ring for VCB transient 10 10 Switching Transient Simulations • Switching transient simulations • EMTP and model requirements • Case studies • Data Center • Ferry Propulsion • Laddle Melt Furnace • Successful techniques/solutions
  • 6. 6 11 11 Ferry Propulsion Highlights • 60K passengers per day • 20M passengers per year • 4160V distribution • 3 x 2865kW diesel gens • 2 x 1865KW forward propulsion motors • 2 x 1865KW reverse propulsion 12 12 Problem • Forward propulsion drives ferry • Upon reaching dock, reverse propulsion stops ferry • July 1, 2009, reverse propulsion was lost entering dock • lost power and hit a pier at full speed • one serious injury and nine minor injuries • 750 to 800 passengers were aboard • impact did not send any passengers overboard • 1185KVA rectifier transformer failed on reverse propulsion motor • Evidence of insulation failure on first few turns of primary winding • Investigation into source of such failure VCB switching
  • 7. 7 13 13 Ferry - Oneline Vacuum Breaker Short Cable Dry-Type Transformer Forward Reverse 14 14 Ferry – Electrical Highlights • 3 x 2865kW diesel generators • 4160V, 3-bus system • Vacuum circuit breakers – 630A mains, ties, feeders • 2 x 1865kW motors (forward propulsion) • 2 x 1865kW motors (reverse propulsion) • 8 x 1185KVA dry-type transformers, 30kV BIL • 3-winding rectifier transformers • 12-pulse effective (6-pulse VFD per winding) • Feeder cable lengths of 50 feet each
  • 8. 8 15 15 Worst Case Scenarios • Feeder cable lengths of 50 feet • Each 1185KVA transformer has one 4160V feeder • Need to examine both feeders for each transformer • “Worst Case” Switching Transient Simulations • Close 4160V VCB to transf. with 50ft. cable (model validation) • Close 4160V VCB to transf. with 50ft. cable (re-ignition) • Open 4160V VCB to transf. with 50ft. cable (current chop) • Repeat each case with Snubber 16 16 Measurements Transient Overvoltages at Primary of Rectifier Transformer – VCB Closes
  • 9. 9 17 17 Study Cases • Case 1 – Closing the 4.16 kV feeder breaker feeding the three winding rectifier transformer with the distance of 50 feet. Simulated to match the Siemens measurements to ensure that the computer model is accurate. (Model Validation) • Case 2 – Same as Case 1, except with the RC snubber. • Case 3 - Closing the 4.16 kV feeder breaker feeding the three winding rectifier transformer, then the 4.16 kV feeder breaker opens during the inrush current. Shows the possibility of the vacuum breaker re-ignition. (Re-ignition) • Case 4 - Same as Case 3, except with the RC snubber. • Case 5 - Open the 4.16 kV feeder breaker feeding the three winding rectifier transformer under the light load condition. (Current Chop) • Case 6 – Same as Case 5, except with the RC snubber. 18 18 Case 1 – Model Validation Transformer primary voltage V max of 4.96kV < 30kV BIL Oscillation of 20,203Hz > 1000Hz
  • 10. 10 19 19 Case 2 – Valid Model with Snubber Transformer primary voltage V max of 3.982kV < 30kV BIL Oscillation of < 1000Hz 20 20 Case 3 – Re-ignition Transient Recovery Voltage (TRV) at VCB
  • 11. 11 21 21 Case 4 – Re-ignition with Snubber Transient Recovery Voltage (TRV) at VCB 22 22 Case 5 – Current Chop Transformer primary voltage V max of 31.9kV > 30kV BIL Oscillation of 958Hz ~ 1000Hz
  • 12. 12 23 23 Case 6 – Current Chop with Snubber Transformer primary voltage V max of 8.9kV < 30kV BIL Oscillation of 299Hz < 1000Hz 24 24 Summary of Current Chop Cases
  • 13. 13 25 25 Summary of Re-Ignition Cases 26 26 Recommendations • Install snubber at primary of each 1185KVA rectifier transformer • 40ohm resistor • Non-inductive • Peak voltage – 6 kVpeak • Peak energy – 2100 Joules • Average power – 190 Watt • 0.5uF capacitor • Rated voltage - 4.16kV
  • 14. 14 27 27 Data Center Highlights • Tier III • LEEDS Certified • 12.5MVA Capacity • 13.2KV Ring Bus 28 28 Data Center - Oneline Vacuum Breaker Short Cable Cast-Coil Transformer
  • 15. 15 29 29 Data Center – Electrical Highlights • 2 x 24.9 kV lines from Factory Shoals and Buzzard Roast • 2 x 12.5 MVA transformers • 13.2 kV “ring-bus” configuration • MSA and MSB and generator bus GPS • Vacuum circuit breakers – 600A mains & ties, 200A feeders • 3 x 2250 KW generators • 6 x 3750KVA cast coil transformers, 90kV BIL • 3 x DE Subs CSA, CSB and CSC • 3 x SE Subs MDSA, MDSB and MLB • Feeder cable lengths vary from 109 to 249 Feet 30 30 Worst Case Scenario • Feeder cable lengths vary from 109 to 249 Feet • Each 3750KVA transformer has two 13.2kV feeders • Need to examine both feeders for each transformer • Shortest of all 13.2kV cable runs to 3750KVA Transformers • MSB to Transformer CSC – 109 feet • MSA to Transformer CSC – 111 feet • “Worst Case” Switching Transient Simulation • Open 13.2 kV VCB at MSB to CSC with 109ft. cable • Open 13.2 kV VCB at MSA to CSC with 111ft. cable
  • 16. 16 31 31 Worst Case – Study Case 13 • Study Case 13 - Open the 13.2 kV feeder breaker at Bus MSB feeding the 3,750 kVA dry type transformer CSC with the shorter distance of 109 feet. The result for this case will represent the “worst-case” condition, the other feeder from Bus MSA has a longer feeder distance of 111 feet. • Study Case 14 – Same as Case 13, except with the application of the 0.25 μF surge capacitor. • Study Case 15 – Same as Case 13, except with the application of the snubber circuit with 30ohm and 0.25 μF surge capacitor. 32 32 Case 13 – no surge protection Load current at 13.2kV VCB Load current of 10A Chopped current of 6A
  • 17. 17 33 33 Case 13 – no surge protection Transformer CSC primary voltage VC max of 65.3kV > 95kV BIL VB max of 116kV > 95kV BIL VA max of 123kV > 95kV BIL Oscillation of 969Hz > 1000Hz 34 34 Case 14 – 0.25uF surge cap Load current at 13.2kV VCB Load current of 10A Chopped current of 6A
  • 18. 18 35 35 Case 14 – 0.25uF surge cap Transformer CSC primary voltage VA max of 29.4kV < 95kV BIL VB max of 19.1kV < 95kV BIL VC max of 15.7kV < 95kV BIL Oscillation of 215Hz < 1000Hz 36 36 Case 15 – snubber 30ohm and 0.25uF Load current at 13.2kV VCB Load current of 10A Chopped current of 6A
  • 19. 19 37 37 Case 15 – snubber 30ohm and 0.25uF Transformer CSC primary voltage VB max of 28.6kV < 95kV BIL VA max of 19.4kV < 95kV BIL VC max of 15.9kV < 95kV BIL Oscillation of 215Hz < 1000Hz 38 38 Case 15 – snubber 30ohm and 0.25uF Snubber Current – important for duty on resistor and capacitor IC peak of 7.7A IB peak of 8.0A IA peak of 6.8A
  • 20. 20 39 39 Comparison of Results No Snubber 0.25uF surge cap Snubber R=30ohm C=0.25uF 40 40 Measured Transients with Snubber
  • 21. 21 41 41 Recommendations • Install snubber at primary of each 3750KVA cast coil transformer 30ohm and 0.25uF • Install surge caps 0.25uF at each emergency generator • Install surge arresters at the following locations: • both incoming power transformers • every distribution dry type transformer • every generator • line side of both main circuit breakers • line side of the three generator circuit breakers • load side of every feeder breaker and every tie circuit breaker 42 42 Laddle Melt Furnace Highlights • Retiring 3 x 38MW EAFs • Adding 1 x 155MVA EAF • Adding 2 x 138kV lines to new EAF • Adding SVC at 34.5kV • Adding 1 x 20MW LMF
  • 22. 22 43 43 LMF & EAF - Oneline Vacuum Breaker Short Bus Oil-Filled Transformer Existing EAF New LMF 44 44 138KV UTILITY 4713MVA 3PH SC 9.26 X/R 50/66/83MVA 135.3/26.4KV 7.5%Z SF-6 BREAKER 2000A 1600A 27KV 13OHM AUTO LTC 56MVA 27-10KV 3.3%Z ALUMINUM IPS BUS 53FEET VACUUM BREAKER 1200A LMF XFMR 50/56MVA 25/.53KV 2.5%Z HEAVY DUTY COPPER PIPE 28FEET LMF 20MW LMF Vacuum Breaker Short Bus Oil-Filled Furnace Transformer New LMF SF6 Breaker Short Bus Oil-Filled Auto-Regulating Transformer
  • 23. 23 45 45 LMF Circuit – Electrical Highlights • 50MVA Power Transformer 135/26.4kV • 27kV system • SF6 circuit breaker – 2000A • Bus length of 53 feet • 56MVA autoregulating transformer, 200kV BIL • Vacuum circuit breaker – 1200A • Bus length of 28 feet • 50MVA oil-filled LMF transformer, 200kV BIL • 20MW LMF 46 46 Worst Case Scenarios • Examine switching transients at both transformers • “Worst Case” Switching Transients for Auto-Reg Transf • Open SF6 breaker to transf. with 53ft. bus (6A current chop) • 3 cycles after energizing Auto-Reg Tran, open SF6 bkr to transf. with 53ft. bus (re-ignition) highly inductive current • “Worst Case” Switching Transients for LMF Transf • Open VCB to transf. with 28ft. bus (6A current chop) • 3 cycles after energizing LMF Tran, open VCB to transf. with 28ft. bus (re-ignition) highly inductive current • Repeat each case with Snubber
  • 24. 24 47 47 Case 1 – Open VCB LMF Transformer primary voltage V max of 386kV > 200kV BIL Oscillation of 1217Hz > 1000Hz 48 48 Case 2 – Open VCB with Snubber LMF Transformer primary voltage V max of 56.4kV < 200kV BIL Oscillation of 200Hz < 1000Hz
  • 25. 25 49 49 Case 3 – Open SF6 Breaker Auto-regulating Transformer primary voltage V max of 23kV < 200kV BIL No oscillating frequency 50 50 Case 4 – Open SF6 Breaker with Snubber Auto-regulating Transformer primary voltage VB max of 54.7kV < 200kV BIL Oscillation of 197Hz < 1000Hz
  • 26. 26 51 51 Case 5 – VCB Re-ignition Transient Recovery Voltage for VCB 52 52 Case 5 – Highly Inductive Current Inrush current to LMF transformer 6000A Peak Inrush VCB Opens VCB Closes
  • 27. 27 53 53 Case 6 – VCB Re-ignition & Snubber Transient Recovery Voltage for VCB 54 54 Case 7 – SF6 Breaker Re-ignition Transient Recovery Voltage for Siemens SF6
  • 28. 28 55 55 Case 7 – Highly Inductive Current Inrush current to Auto-Regulating transformer 14000A Peak Inrush SF6 CB Opens SF6 CB Closes 56 56 Case 8 – SF6 Breaker Re-ignition & Snubber Transient Recovery Voltage for SF6 Breaker
  • 29. 29 57 57 Summary of Current Chop Cases 58 58 Summary of Re-Ignition Cases
  • 30. 30 59 59 Recommendations • Install snubber (100ohm and 0.15uF) at primary of each transformer • 100ohm resistor • Non-inductive • Peak voltage – 38 kVpeak • Peak energy – 17,500 Joules • Average power – 1000 Watt • 0.15uF, 34.5kV surge capacitor (not available) • 1-pole, 24kV, 0.13uF • 2-pole, 14.4kV, 0.5uF • Series combination gives 0.103uF