SlideShare a Scribd company logo
INDUSTRIAL SEMINAR PRESENTATION
ON
“STUDY OF VARIOUS ELECTRICAL
EQUIPMENTS
&
DESIGN OF POWER DISTRIBUTION
SYSTEM”
ARGHA DUTTA
4th YEAR ELECTRICAL ENGINEERING
ROLL NO - 129010093
A BRIEF OVERVIEW
33kv &6.6v air
insulated
switchgear
Power transformer
and accessories
AC motors and
controls
Protective devices Cabling Eathing
CABLES:
 Types of power cables:
PVC CABLES:
1.1 kV grade and have excellent electrical insulating properties.
FRLS CABLES:
Also known as flame reterdant low smoke cables and used in
hazardous zones such as power plant , chemical plants.
XLPE CABLES:
These cables are a form of polyethylene with crossed links. They are
suitable for working voltage of 240V to 500KV.
APPLICATIONS: underwater cables , underwater burials.
EARTHING:
 Earthing includes UNEARTHED SYSTEM, SOLIDLY EARTHED
SYSTEM, RESISTANCE EARTHING AND REACTANCE
EARTHING.
 Earthing resistance Measurement:
 Two point
 Three point
 Fall of potential
 Four point
TT connection – This type of connection is used in INDIA.
33 kv and 6.6 kv air insulated switchgear
• Three phase indoor floor mounted metal clad switchboard with
air insulated bus bar.
• Control voltage – 110/220V DC
• Metal clad switchgear with steel sheet enclosure having
degree of protection IP5X
• Internal wiring consists of 1.1kV grade, 1 core stranded
copper conductor, PVC insulated wire
DESIGN OF POWER DISTRIBUTION SYSTEM
AND DEVELOPMENT OF SINGLE LINE DIAGRAM
FOR 33KV/6.6KV/415V SYSTEM
 Selection of transformer is done on considering the following factors:
Total working load
Demand factor
Power factor
Diversity factor
Margin for future expansion
STEPS FOR CALCULATION:
• First total working load is calculated
• Then maximum demand is calculated.
• Considering 20% spare margin minimum capacity of the transformer
is calculated
• Here in all cases ONAN cooled transformers with Dyn11
connections are considered.
POWER FACTOR COMPENSATION BY
USING CAPACITOR BANK:
 Power factor compensation has been provided for improvement of
overall power factors of the plant using CAPACITOR BANKS.
Compensation has been considered both at LT side and HT side.
STEPS FOR CALCULATION:
• Active power P is calculated.
• Additional power factor needed to be supplied for improvement of
power factor is calculated by the differences of power factors of old
and new reactive powers.
• Installed capacity is approximated to the nearest value.
CALCULATION OF CIRCUIT BREAKER
RATING AND CT RATIO OF HT FEEDERS
 The rated current is calculated and then it is approximated to the
nearest standard ratings
 Standard rating of ACB available in the market are
630/800/1250/2500/3200A
 Standard rating of MCCB available in the market are
32/63/100/200/250/315/400A up to 1250A
Selection of fuse rating for HT motors :
First the load current is calculated, then the starting current of the
motor is calculated which is usually 6 times the load current.
Rated fuse current is then calculated from the reference chart.
SELECTION OF CABLE SIZE:
 In HT feeders the short time withstand duration have been selected
as 0.5s for circuit breaker feeders and 0.02 seconds for vacuum
contactor feeders.
 Three core cables are selected for HT system and 3–1/2 core cables
are selected for LT systems.
 The required size of cables are selected from the chart available in
the market.
AN OVERVIEW OF SINGLE LINE DIAGRAM:
 33kv distribution system:
power is received at 33kv from the 33kv switchboard of sending end
substation. At substation 33kv outdoor equipment and indoor
equipment is provided.it will be fed to 33/6.9kv transformers for
delivering 6.6kv power.
• 6.6kv distribution system:
6.6kV switchboard uses single bus system in which two incomers
feed the two bus sections.
6.6kV HVMCC s are provided with two
incomers , bus couplers with VCB and vacuum contractors.
TRANSFORMERS:
Total 10 no of transformers are considered for the total plant area.
POWER FACTOR COMPENSATION
EQUIPMENT:
Capacitor bank has been considered for compensation of power factor.
Power factor is considered both for LT and HT system. In LT section
reactive power compensation has been considered to reduce the
reactive power component of power and thereby increases the power
factor capacity through cable feeders.
THANK YOU…

More Related Content

What's hot

Method of voltage control
Method of voltage controlMethod of voltage control
Method of voltage control
Vaibhav Singh
 
Presentation on KESCO sub-station, kanpur
Presentation on KESCO sub-station, kanpurPresentation on KESCO sub-station, kanpur
Presentation on KESCO sub-station, kanpur
Shubham Sachan
 
Facts devices
Facts devicesFacts devices
Facts devices
Vinod Srivastava
 
INTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLERINTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLER
Nitish NIT
 
electric plan distribution design for large campus building
electric plan distribution design for large campus building electric plan distribution design for large campus building
electric plan distribution design for large campus building
Somesh Siddharth
 
Facts
FactsFacts
statcom
statcomstatcom
statcom
D Målîk
 
automatic power factor controller
automatic power factor controllerautomatic power factor controller
automatic power factor controller
singh1515
 
Basic types of facts controllers
Basic types of facts controllersBasic types of facts controllers
Basic types of facts controllers
Ayyarao T S L V
 
DPL Transmission And Distribution
DPL Transmission And DistributionDPL Transmission And Distribution
DPL Transmission And Distribution
Subhojeet Sinha ☁
 
Statcom
StatcomStatcom
Statcom
jawaharramaya
 
Electricity generation, distribution and transmission
Electricity generation, distribution and transmissionElectricity generation, distribution and transmission
Electricity generation, distribution and transmission
Ashar143
 
STUDY OF ELECTRICAL POWER GENERATION, TRANSMISSION AND DISTRIBUTION IN BANG...
STUDY OF  ELECTRICAL POWER GENERATION,  TRANSMISSION AND DISTRIBUTION IN BANG...STUDY OF  ELECTRICAL POWER GENERATION,  TRANSMISSION AND DISTRIBUTION IN BANG...
STUDY OF ELECTRICAL POWER GENERATION, TRANSMISSION AND DISTRIBUTION IN BANG...
Tania Marzia
 
Different types of Transformers used in Generating Station
Different types of Transformers used in Generating StationDifferent types of Transformers used in Generating Station
Different types of Transformers used in Generating Station
Vasanthan Ravichandran
 
Autotramsformer
AutotramsformerAutotramsformer
Autotramsformer
Dr.Raja Masood Larik
 
Sssc
SsscSssc
Introduction to electric power transmission and distribution
Introduction to electric power transmission and distributionIntroduction to electric power transmission and distribution
Introduction to electric power transmission and distribution
ABDULRAHMANALGHANIM
 
Electric system
Electric systemElectric system
Electric system
SayanSarkar55
 
Presentation on 132 kv gss
Presentation on 132 kv gssPresentation on 132 kv gss
Presentation on 132 kv gss
medhashandilya
 
Flexible ac transmission system
Flexible ac transmission systemFlexible ac transmission system
Flexible ac transmission system
Uday Wankar
 

What's hot (20)

Method of voltage control
Method of voltage controlMethod of voltage control
Method of voltage control
 
Presentation on KESCO sub-station, kanpur
Presentation on KESCO sub-station, kanpurPresentation on KESCO sub-station, kanpur
Presentation on KESCO sub-station, kanpur
 
Facts devices
Facts devicesFacts devices
Facts devices
 
INTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLERINTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLER
 
electric plan distribution design for large campus building
electric plan distribution design for large campus building electric plan distribution design for large campus building
electric plan distribution design for large campus building
 
Facts
FactsFacts
Facts
 
statcom
statcomstatcom
statcom
 
automatic power factor controller
automatic power factor controllerautomatic power factor controller
automatic power factor controller
 
Basic types of facts controllers
Basic types of facts controllersBasic types of facts controllers
Basic types of facts controllers
 
DPL Transmission And Distribution
DPL Transmission And DistributionDPL Transmission And Distribution
DPL Transmission And Distribution
 
Statcom
StatcomStatcom
Statcom
 
Electricity generation, distribution and transmission
Electricity generation, distribution and transmissionElectricity generation, distribution and transmission
Electricity generation, distribution and transmission
 
STUDY OF ELECTRICAL POWER GENERATION, TRANSMISSION AND DISTRIBUTION IN BANG...
STUDY OF  ELECTRICAL POWER GENERATION,  TRANSMISSION AND DISTRIBUTION IN BANG...STUDY OF  ELECTRICAL POWER GENERATION,  TRANSMISSION AND DISTRIBUTION IN BANG...
STUDY OF ELECTRICAL POWER GENERATION, TRANSMISSION AND DISTRIBUTION IN BANG...
 
Different types of Transformers used in Generating Station
Different types of Transformers used in Generating StationDifferent types of Transformers used in Generating Station
Different types of Transformers used in Generating Station
 
Autotramsformer
AutotramsformerAutotramsformer
Autotramsformer
 
Sssc
SsscSssc
Sssc
 
Introduction to electric power transmission and distribution
Introduction to electric power transmission and distributionIntroduction to electric power transmission and distribution
Introduction to electric power transmission and distribution
 
Electric system
Electric systemElectric system
Electric system
 
Presentation on 132 kv gss
Presentation on 132 kv gssPresentation on 132 kv gss
Presentation on 132 kv gss
 
Flexible ac transmission system
Flexible ac transmission systemFlexible ac transmission system
Flexible ac transmission system
 

Viewers also liked

Industrial safety.
Industrial safety.Industrial safety.
Industrial safety.
psc2015
 
INTRODUCTION TO WIRELESS COMMUNICATION
INTRODUCTION TO WIRELESS COMMUNICATIONINTRODUCTION TO WIRELESS COMMUNICATION
INTRODUCTION TO WIRELESS COMMUNICATION
SANDIP BURNWAL
 
01 introduction to wireless communications
01   introduction to wireless communications01   introduction to wireless communications
01 introduction to wireless communications
Hussein Khaleel
 
MPEB, MPPKVVCL Indore 15 days Training Seminar
MPEB, MPPKVVCL Indore 15 days Training SeminarMPEB, MPPKVVCL Indore 15 days Training Seminar
MPEB, MPPKVVCL Indore 15 days Training Seminar
Suraj Talreja
 
Training report of 33/11kv substation Mohamdabad, Tundla
Training report of 33/11kv substation Mohamdabad, TundlaTraining report of 33/11kv substation Mohamdabad, Tundla
Training report of 33/11kv substation Mohamdabad, Tundla
shashanksltor
 
Industrial health and safety seminar
Industrial health and safety seminarIndustrial health and safety seminar
Industrial health and safety seminar
Fahad Shaikh
 
NFI - Industrial Pneumatics
NFI - Industrial PneumaticsNFI - Industrial Pneumatics
Nuclear Battery Seminar Report
Nuclear Battery Seminar ReportNuclear Battery Seminar Report
Nuclear Battery Seminar Report
Pratik Patil
 
Seminar presentation on nuclear batteries
Seminar presentation on nuclear batteriesSeminar presentation on nuclear batteries
Seminar presentation on nuclear batteries
Pratik Patil
 
Nuclear battery (1)
Nuclear battery (1)Nuclear battery (1)
Nuclear battery (1)
Nithin Krishna
 
Nuclear power plant
Nuclear power plantNuclear power plant
Nuclear power plant
college
 
Nuclear Battery PPT
Nuclear Battery PPTNuclear Battery PPT
Nuclear Battery PPT
Seminar Links
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
moiz89
 
Systematic, toolchain JS
Systematic, toolchain JSSystematic, toolchain JS
Systematic, toolchain JS
Raphaël Boucher
 
Finale_Pub non nucleare fino al 2012_00
Finale_Pub non nucleare fino al 2012_00Finale_Pub non nucleare fino al 2012_00
Finale_Pub non nucleare fino al 2012_00Fabio Pistella
 
상상유니브 기획서 우리집 녹음실
상상유니브 기획서 우리집 녹음실상상유니브 기획서 우리집 녹음실
상상유니브 기획서 우리집 녹음실
HANHUIGON
 
Resume
ResumeResume
Resume
AMIT GUPTA
 
Portfolio
PortfolioPortfolio
Portfolio
Moses Florian
 
Subrat resume (final 424242)
Subrat resume (final 424242)Subrat resume (final 424242)
Subrat resume (final 424242)
Subrat Pattnaik
 
Построение Saas-стартапа на django и angular
Построение Saas-стартапа на django и angularПостроение Saas-стартапа на django и angular
Построение Saas-стартапа на django и angular
Alexander Lifanov
 

Viewers also liked (20)

Industrial safety.
Industrial safety.Industrial safety.
Industrial safety.
 
INTRODUCTION TO WIRELESS COMMUNICATION
INTRODUCTION TO WIRELESS COMMUNICATIONINTRODUCTION TO WIRELESS COMMUNICATION
INTRODUCTION TO WIRELESS COMMUNICATION
 
01 introduction to wireless communications
01   introduction to wireless communications01   introduction to wireless communications
01 introduction to wireless communications
 
MPEB, MPPKVVCL Indore 15 days Training Seminar
MPEB, MPPKVVCL Indore 15 days Training SeminarMPEB, MPPKVVCL Indore 15 days Training Seminar
MPEB, MPPKVVCL Indore 15 days Training Seminar
 
Training report of 33/11kv substation Mohamdabad, Tundla
Training report of 33/11kv substation Mohamdabad, TundlaTraining report of 33/11kv substation Mohamdabad, Tundla
Training report of 33/11kv substation Mohamdabad, Tundla
 
Industrial health and safety seminar
Industrial health and safety seminarIndustrial health and safety seminar
Industrial health and safety seminar
 
NFI - Industrial Pneumatics
NFI - Industrial PneumaticsNFI - Industrial Pneumatics
NFI - Industrial Pneumatics
 
Nuclear Battery Seminar Report
Nuclear Battery Seminar ReportNuclear Battery Seminar Report
Nuclear Battery Seminar Report
 
Seminar presentation on nuclear batteries
Seminar presentation on nuclear batteriesSeminar presentation on nuclear batteries
Seminar presentation on nuclear batteries
 
Nuclear battery (1)
Nuclear battery (1)Nuclear battery (1)
Nuclear battery (1)
 
Nuclear power plant
Nuclear power plantNuclear power plant
Nuclear power plant
 
Nuclear Battery PPT
Nuclear Battery PPTNuclear Battery PPT
Nuclear Battery PPT
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
 
Systematic, toolchain JS
Systematic, toolchain JSSystematic, toolchain JS
Systematic, toolchain JS
 
Finale_Pub non nucleare fino al 2012_00
Finale_Pub non nucleare fino al 2012_00Finale_Pub non nucleare fino al 2012_00
Finale_Pub non nucleare fino al 2012_00
 
상상유니브 기획서 우리집 녹음실
상상유니브 기획서 우리집 녹음실상상유니브 기획서 우리집 녹음실
상상유니브 기획서 우리집 녹음실
 
Resume
ResumeResume
Resume
 
Portfolio
PortfolioPortfolio
Portfolio
 
Subrat resume (final 424242)
Subrat resume (final 424242)Subrat resume (final 424242)
Subrat resume (final 424242)
 
Построение Saas-стартапа на django и angular
Построение Saas-стартапа на django и angularПостроение Saas-стартапа на django и angular
Построение Saas-стартапа на django и angular
 

Similar to INDUSTRIAL SEMINAR PRESENTATION

A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITY
Rohitashav Goyal
 
Faculty of Engineering and Technology.pptx
Faculty of Engineering and Technology.pptxFaculty of Engineering and Technology.pptx
Faculty of Engineering and Technology.pptx
anshumaansingh310
 
Internship doc 33 11 kv substation
Internship doc 33 11 kv substation  Internship doc 33 11 kv substation
Internship doc 33 11 kv substation
Madeen Kumar
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptx
ShubhoDas5
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
Philippe AGULLO
 
Energy Efficiency in Electrical Systems.pptx
Energy  Efficiency in Electrical Systems.pptxEnergy  Efficiency in Electrical Systems.pptx
Energy Efficiency in Electrical Systems.pptx
PoojaAnupGarg
 
Design of substation
Design of substationDesign of substation
Design of substation
SayanSarkar55
 
Ssfcl
SsfclSsfcl
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptx
AkshaiSai2
 
Kamal final presentation eee reb- comilla
Kamal final presentation eee  reb- comillaKamal final presentation eee  reb- comilla
Kamal final presentation eee reb- comilla
siam hossain
 
Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)
FunExplode
 
Hvdc dad
Hvdc dadHvdc dad
Hvdc dad
dharmesh dabhi
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
LiewChiaPing
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)
saurabhVEC
 
A03540109
A03540109A03540109
A03540109
ijceronline
 
220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx
ssuser1b3e431
 
Techno economic study of series current limiting reactor and its impact in th...
Techno economic study of series current limiting reactor and its impact in th...Techno economic study of series current limiting reactor and its impact in th...
Techno economic study of series current limiting reactor and its impact in th...
Alexander Decker
 
132 KV GSS NPH jodhpur treaning report
132 KV GSS NPH jodhpur treaning report 132 KV GSS NPH jodhpur treaning report
132 KV GSS NPH jodhpur treaning report
imkanhaiyalal
 
OPERATION & MAINTENANCE OF 33/11 kV SUBSTATION AT DHAKA PALLI BIDYUT SAMITY-1
OPERATION & MAINTENANCE OF 33/11 kV SUBSTATION AT DHAKA PALLI BIDYUT SAMITY-1OPERATION & MAINTENANCE OF 33/11 kV SUBSTATION AT DHAKA PALLI BIDYUT SAMITY-1
OPERATION & MAINTENANCE OF 33/11 kV SUBSTATION AT DHAKA PALLI BIDYUT SAMITY-1
md muzahidul haque
 
132 KV GSS CHAMBAL JAIPUR
132 KV GSS CHAMBAL JAIPUR132 KV GSS CHAMBAL JAIPUR
132 KV GSS CHAMBAL JAIPUR
Vaibhav Bhargava
 

Similar to INDUSTRIAL SEMINAR PRESENTATION (20)

A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITY
 
Faculty of Engineering and Technology.pptx
Faculty of Engineering and Technology.pptxFaculty of Engineering and Technology.pptx
Faculty of Engineering and Technology.pptx
 
Internship doc 33 11 kv substation
Internship doc 33 11 kv substation  Internship doc 33 11 kv substation
Internship doc 33 11 kv substation
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptx
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
Energy Efficiency in Electrical Systems.pptx
Energy  Efficiency in Electrical Systems.pptxEnergy  Efficiency in Electrical Systems.pptx
Energy Efficiency in Electrical Systems.pptx
 
Design of substation
Design of substationDesign of substation
Design of substation
 
Ssfcl
SsfclSsfcl
Ssfcl
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptx
 
Kamal final presentation eee reb- comilla
Kamal final presentation eee  reb- comillaKamal final presentation eee  reb- comilla
Kamal final presentation eee reb- comilla
 
Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)
 
Hvdc dad
Hvdc dadHvdc dad
Hvdc dad
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)
 
A03540109
A03540109A03540109
A03540109
 
220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx
 
Techno economic study of series current limiting reactor and its impact in th...
Techno economic study of series current limiting reactor and its impact in th...Techno economic study of series current limiting reactor and its impact in th...
Techno economic study of series current limiting reactor and its impact in th...
 
132 KV GSS NPH jodhpur treaning report
132 KV GSS NPH jodhpur treaning report 132 KV GSS NPH jodhpur treaning report
132 KV GSS NPH jodhpur treaning report
 
OPERATION & MAINTENANCE OF 33/11 kV SUBSTATION AT DHAKA PALLI BIDYUT SAMITY-1
OPERATION & MAINTENANCE OF 33/11 kV SUBSTATION AT DHAKA PALLI BIDYUT SAMITY-1OPERATION & MAINTENANCE OF 33/11 kV SUBSTATION AT DHAKA PALLI BIDYUT SAMITY-1
OPERATION & MAINTENANCE OF 33/11 kV SUBSTATION AT DHAKA PALLI BIDYUT SAMITY-1
 
132 KV GSS CHAMBAL JAIPUR
132 KV GSS CHAMBAL JAIPUR132 KV GSS CHAMBAL JAIPUR
132 KV GSS CHAMBAL JAIPUR
 

INDUSTRIAL SEMINAR PRESENTATION

  • 1. INDUSTRIAL SEMINAR PRESENTATION ON “STUDY OF VARIOUS ELECTRICAL EQUIPMENTS & DESIGN OF POWER DISTRIBUTION SYSTEM” ARGHA DUTTA 4th YEAR ELECTRICAL ENGINEERING ROLL NO - 129010093
  • 2. A BRIEF OVERVIEW 33kv &6.6v air insulated switchgear Power transformer and accessories AC motors and controls Protective devices Cabling Eathing
  • 3. CABLES:  Types of power cables: PVC CABLES: 1.1 kV grade and have excellent electrical insulating properties. FRLS CABLES: Also known as flame reterdant low smoke cables and used in hazardous zones such as power plant , chemical plants. XLPE CABLES: These cables are a form of polyethylene with crossed links. They are suitable for working voltage of 240V to 500KV. APPLICATIONS: underwater cables , underwater burials.
  • 4. EARTHING:  Earthing includes UNEARTHED SYSTEM, SOLIDLY EARTHED SYSTEM, RESISTANCE EARTHING AND REACTANCE EARTHING.  Earthing resistance Measurement:  Two point  Three point  Fall of potential  Four point TT connection – This type of connection is used in INDIA.
  • 5. 33 kv and 6.6 kv air insulated switchgear • Three phase indoor floor mounted metal clad switchboard with air insulated bus bar. • Control voltage – 110/220V DC • Metal clad switchgear with steel sheet enclosure having degree of protection IP5X • Internal wiring consists of 1.1kV grade, 1 core stranded copper conductor, PVC insulated wire
  • 6. DESIGN OF POWER DISTRIBUTION SYSTEM AND DEVELOPMENT OF SINGLE LINE DIAGRAM FOR 33KV/6.6KV/415V SYSTEM  Selection of transformer is done on considering the following factors: Total working load Demand factor Power factor Diversity factor Margin for future expansion STEPS FOR CALCULATION: • First total working load is calculated • Then maximum demand is calculated. • Considering 20% spare margin minimum capacity of the transformer is calculated • Here in all cases ONAN cooled transformers with Dyn11 connections are considered.
  • 7. POWER FACTOR COMPENSATION BY USING CAPACITOR BANK:  Power factor compensation has been provided for improvement of overall power factors of the plant using CAPACITOR BANKS. Compensation has been considered both at LT side and HT side. STEPS FOR CALCULATION: • Active power P is calculated. • Additional power factor needed to be supplied for improvement of power factor is calculated by the differences of power factors of old and new reactive powers. • Installed capacity is approximated to the nearest value.
  • 8. CALCULATION OF CIRCUIT BREAKER RATING AND CT RATIO OF HT FEEDERS  The rated current is calculated and then it is approximated to the nearest standard ratings  Standard rating of ACB available in the market are 630/800/1250/2500/3200A  Standard rating of MCCB available in the market are 32/63/100/200/250/315/400A up to 1250A Selection of fuse rating for HT motors : First the load current is calculated, then the starting current of the motor is calculated which is usually 6 times the load current. Rated fuse current is then calculated from the reference chart.
  • 9. SELECTION OF CABLE SIZE:  In HT feeders the short time withstand duration have been selected as 0.5s for circuit breaker feeders and 0.02 seconds for vacuum contactor feeders.  Three core cables are selected for HT system and 3–1/2 core cables are selected for LT systems.  The required size of cables are selected from the chart available in the market.
  • 10. AN OVERVIEW OF SINGLE LINE DIAGRAM:  33kv distribution system: power is received at 33kv from the 33kv switchboard of sending end substation. At substation 33kv outdoor equipment and indoor equipment is provided.it will be fed to 33/6.9kv transformers for delivering 6.6kv power. • 6.6kv distribution system: 6.6kV switchboard uses single bus system in which two incomers feed the two bus sections. 6.6kV HVMCC s are provided with two incomers , bus couplers with VCB and vacuum contractors.
  • 11. TRANSFORMERS: Total 10 no of transformers are considered for the total plant area. POWER FACTOR COMPENSATION EQUIPMENT: Capacitor bank has been considered for compensation of power factor. Power factor is considered both for LT and HT system. In LT section reactive power compensation has been considered to reduce the reactive power component of power and thereby increases the power factor capacity through cable feeders.