SlideShare a Scribd company logo
1 of 21
Download to read offline
Testing of Transformer
BY – GEETESH VERMA
1
Why Testing of Transformer ?
•To validate design specifications
•To verify quality of manufacturing process
•To establish present condition and condition trend
•To determine if damage has occurred
•To detect winding deformation
•To detect displacements between high and low voltage windings
•To detect partial winding collapse
•To detect shorted or open turns
•To detect core movement
2
Important Tests done in site Periodically –
• Insulation Resistance Test or Megger Test
• Winding Resistance Test
• Ratio Measurements
• Magnetic Balance Test
• Tan(δ) test
• Dissolved Gas Analysis for Transformers
• Sweep Frequency Response Analysis Test | SFRA Test
3
Transformer Winding Resistance Test
•A DC test current is injected across the measured winding (-s), the voltage drop as well as the
test current is measured and the resistance is calculated.
•For purely resistive objects the measurement is trivial and very easy to perform.
•When the measurement circuit is highly inductive, measurement may become rather complex.
•Always try to saturate the core. This happens typically when the test current is about 1% of rated
current.
•The time required for readings to stabilize will vary based on the rating of the transformer, the
winding configuration, and the current output selected.
4
The mathematical expressions, where U is Voltage, R is resistance, I is current, L is inductance and t is
the time,
Winding resistance R
times the current I, i.e.
what we want to
measure.
“error” term
(inductance) x (change of current)
The solution to this issue is to keep
the test current constant over
time.
“error” term
(current) x (inductance change)
It is difficult to reduce. In practice
the only way is to wait for the
inductance change to stabilize.
5
6
TAP POS.
HV WINDING RESISTANCE (m-ohm)
UV UW VW
3 25.02 25.70 25.03
LV WINDING (m-ohm)
R-N Y-N B-N RY YB BR
4.130 4.111 4.153 7.955 7.92 7.755
Winding Resistance Test readings of a Transformer.
Transformer Ratio Measurements
1. The tap changer of transformer is kept in the
lowest position and LV terminals are kept open.
2. Apply 3-phase 415 V supply on HV terminals.
Measure the voltages applied on each phase
(Phase-phase) on HV and induced voltages at
LV terminals simultaneously.
3. After measuring the voltages at HV and LV
terminals, the tap changer of transformer
should be raised by one position and repeat
test.
7
8
TAP
POS.
Calculated
Ratio
Measure ratio
R Y B
3 1.59420 1.5925 1.5928 1.5926
Ratio Measurement test readings of a Transformer.
Magnetic Balance Test
It is performed to detect faults / defects in the magnetic core structure, shifting and/or de-
shaping of windings, failure in inter-turn insulation or fault in Tap Changer
These faults change the effective reluctance of the magnetic circuit which then affects the
magnetizing current required to establish flux in the core.
Test Procedure -
1. Connect single phase 230 Volts supply between first and second phase of primary side of
transformer (between 1U & 1V)
2. Measure voltages between 1U-1V, 1V-1W, and between 1W-1U,
3. Similarly measure voltages between 2U-2N, 2V-2N & 2W-2N
4. Then connect single-phase supply between second and third phase on primary side
(between 1V-1W)
9
5. Again Measure voltages between 1U-1V, 1V-1W, and between 1W-1U
6. Repeat Similar Procedure for LV side.
10
2U-2N 2V-2N 2W-2N
239.0 207.9 31.20
138.9 239.5 99.80
36.5 201.6 239.1
1U-1V 1V-1W 1W-1U
229.7 112.15 117.5
195.2 229.75 33.6
198.1 31.4 229.7
Magnetic Balance test readings of a Transformer.
*all readings in Volts
Dissipation factor measurement/ tan(δ) test
•Tan(δ) performed to investigate the condition of the insulation of power transformers and bushings.
•The dissipation factor/tan(δ), is the ratio of Resistive component of current to Capacitive component
of current flowing through a insulator.
•A pure insulator when is connected across line and earth, it behaves as a capacitor. There is no
resistive component of the current, as there is zero percent impurity.
•For good insulator, resistive component of leakage electric current is quite low.
11
• In the vector diagram, the system voltage is drawn along x-axis.
• Conductive electric current i.e. resistive component of leakage current, IR
will also be along x-axis.
• As the capacitive component of leakage electric current IC leads system
voltage by 90°, it will be drawn along y-axis.
• Total leakage electric current (IR+ IC) makes an angle δ (say) with y-axis.
• Now, from the diagram above, it is clear, the ratio, IR to IC is nothing but tanδ or tan delta.
• NB: This δ angle is known as loss angle.
12
Interpretation of tan(δ) Measurement
1. Comparing the results of previous tests to determine, the
deterioration of the condition of insulation due to ageing effect.
2. Determining the condition of insulation from the value of tanδ,
directly.
If the insulation is perfect
The loss factor will be
approximately same for all
range of test voltages.
If the insulation is not sufficient
The value of tan delta increases
in the higher range of test
voltage.
13
14
Meas.
Combination
Test Voltage Mode Capacitance(nF) Current(mA) Tan δ
HV-E
2 KV
GST-GA
2.89418 1.820 0.1988
5 KV 2.9004 4.56 0.3295
HV-LV
2 KV
UST-A
3.7693 2.3687 0.3349
5 KV 3.7681 5.9252 0.3099
LV-E 2 KV GST-GA 7.8876 4.9632 0.3205
Tan Delta test readings of a Transformer.
Dissolved Gas Analysis for Transformers
•Oil sample analysis is a useful, predictive, maintenance tool for determining transformer health.
•The breakdown of electrical insulating materials and related components inside a transformer
generates gases within the transformer.
•The identity of the gases being generated can be very useful information in any preventive
maintenance program.
•This method involves sampling the oil and testing the sample to measure the concentration of
the dissolved gases.
•It is recommended that DGA of the transformer oil be performed at least on an annual basis
with results compared from year to year.
15
Insulating mineral oils for transformers are mixtures of many different hydrocarbon molecules
The fundamental chemical reactions involve the breaking of carbon hydrogen and carbon-carbon
bonds.
Energy is needed for the breaking of the chemical bonds and this comes from the energy contained
in the fault of the transformer.
Gases Formed
16
17
Sweep Frequency Response Analysis Test
| SFRA Test
•A transformer can be considered as a complicated distributed network of resistance, inductance,
and capacitance or in other words a transformer is a complicated RLC circuit.
•Because of that each winding of a transformer exhibits a particular frequency response.
•In SFRA a sinusoidal voltage Vi is applied to one end of a winding and output voltage Vo is
measured at the other end of the winding. Other windings are kept open.
•As the winding is itself a distributed RLC circuit it will behave like RLC filter and gives different
output voltages at different frequencies.
18
After transportation, heavy short circuit faults, transient switching impulses and lightening impulses etc., if
we do same Sweep Frequency Response Analysis test and superimpose the present signature with the
earlier patterns and observe some deviation between these two graphs, we can assess that there is
mechanical displacement and deformation occurred in the winding.
Plot of output voltages against the corresponding frequencies.
19
Three methods are commonly used to assess the measured traces:
 Time-based – current SFRA results will be compared to previous results of the same unit.
 Type-based – SFRA of one transformer will be compared to an equal type of transformer.
 Phase comparison – SFRA results of one phase will be compared to the results of the other phases of
the same transformer.
20
THANK YOU
21

More Related Content

What's hot

What's hot (20)

Power transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines rPower transformer testing and commissioning guidelines r
Power transformer testing and commissioning guidelines r
 
Transformer
TransformerTransformer
Transformer
 
Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guide
 
Transformer maintenance
Transformer maintenance Transformer maintenance
Transformer maintenance
 
Transformer testing on sight and off sight
Transformer testing on sight and off sightTransformer testing on sight and off sight
Transformer testing on sight and off sight
 
Transformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response AnalysisTransformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response Analysis
 
Transformer vector group_test_conditions
Transformer vector group_test_conditionsTransformer vector group_test_conditions
Transformer vector group_test_conditions
 
Parallel Operation of Transformers
Parallel Operation of TransformersParallel Operation of Transformers
Parallel Operation of Transformers
 
Testing and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation EquipmentsTesting and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation Equipments
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of Transformers
 
Power Transformer Differential protection
Power Transformer Differential protectionPower Transformer Differential protection
Power Transformer Differential protection
 
Power Transformer Parts And Functions
Power Transformer Parts And FunctionsPower Transformer Parts And Functions
Power Transformer Parts And Functions
 
Distribution Transformer testing, West Bengal, India
Distribution Transformer testing,  West Bengal, IndiaDistribution Transformer testing,  West Bengal, India
Distribution Transformer testing, West Bengal, India
 
Line Differential - Test report for Alstom make Micom P546 relay
Line Differential - Test report for Alstom make Micom P546 relayLine Differential - Test report for Alstom make Micom P546 relay
Line Differential - Test report for Alstom make Micom P546 relay
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
 
Transformer Parts and functions
Transformer Parts and functionsTransformer Parts and functions
Transformer Parts and functions
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
 
Transformer tests
Transformer testsTransformer tests
Transformer tests
 
Introduction to power transformers
Introduction to power transformersIntroduction to power transformers
Introduction to power transformers
 
Power system protection topic 1
Power system protection topic 1Power system protection topic 1
Power system protection topic 1
 

Similar to Testing of Transformers.

Best transformer-test-procedures-en
Best transformer-test-procedures-enBest transformer-test-procedures-en
Best transformer-test-procedures-en
Suresh Patil
 

Similar to Testing of Transformers. (20)

TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
 
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
 
Frequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformerFrequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformer
 
tcee-161003100321.pptx
tcee-161003100321.pptxtcee-161003100321.pptx
tcee-161003100321.pptx
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjar
 
Unit 1-2-b
Unit 1-2-bUnit 1-2-b
Unit 1-2-b
 
Transformers pptxx.ppt
Transformers pptxx.pptTransformers pptxx.ppt
Transformers pptxx.ppt
 
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuitsModule 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
 
Impulse testing of transformer
Impulse testing of transformerImpulse testing of transformer
Impulse testing of transformer
 
TRANSFORMER DESIGN.pptx
TRANSFORMER DESIGN.pptxTRANSFORMER DESIGN.pptx
TRANSFORMER DESIGN.pptx
 
Best transformer-test-procedures-en
Best transformer-test-procedures-enBest transformer-test-procedures-en
Best transformer-test-procedures-en
 
Voltage Regulation
Voltage RegulationVoltage Regulation
Voltage Regulation
 
Open circuit and Short circuit test on transformer
Open circuit and Short circuit test on transformerOpen circuit and Short circuit test on transformer
Open circuit and Short circuit test on transformer
 
Testing of transformer.pptx
Testing of transformer.pptxTesting of transformer.pptx
Testing of transformer.pptx
 
Best-transformer-test-procedures-en
  Best-transformer-test-procedures-en  Best-transformer-test-procedures-en
Best-transformer-test-procedures-en
 
H06 elo g
H06 elo g H06 elo g
H06 elo g
 
Testing of power_transformers_kt_80_gb_2
Testing of power_transformers_kt_80_gb_2Testing of power_transformers_kt_80_gb_2
Testing of power_transformers_kt_80_gb_2
 
Transformer Course Lab.pdf
Transformer Course Lab.pdfTransformer Course Lab.pdf
Transformer Course Lab.pdf
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier ppt
 

Recently uploaded

Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systems
meharikiros2
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
hublikarsn
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
pritamlangde
 

Recently uploaded (20)

Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systems
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 

Testing of Transformers.

  • 1. Testing of Transformer BY – GEETESH VERMA 1
  • 2. Why Testing of Transformer ? •To validate design specifications •To verify quality of manufacturing process •To establish present condition and condition trend •To determine if damage has occurred •To detect winding deformation •To detect displacements between high and low voltage windings •To detect partial winding collapse •To detect shorted or open turns •To detect core movement 2
  • 3. Important Tests done in site Periodically – • Insulation Resistance Test or Megger Test • Winding Resistance Test • Ratio Measurements • Magnetic Balance Test • Tan(δ) test • Dissolved Gas Analysis for Transformers • Sweep Frequency Response Analysis Test | SFRA Test 3
  • 4. Transformer Winding Resistance Test •A DC test current is injected across the measured winding (-s), the voltage drop as well as the test current is measured and the resistance is calculated. •For purely resistive objects the measurement is trivial and very easy to perform. •When the measurement circuit is highly inductive, measurement may become rather complex. •Always try to saturate the core. This happens typically when the test current is about 1% of rated current. •The time required for readings to stabilize will vary based on the rating of the transformer, the winding configuration, and the current output selected. 4
  • 5. The mathematical expressions, where U is Voltage, R is resistance, I is current, L is inductance and t is the time, Winding resistance R times the current I, i.e. what we want to measure. “error” term (inductance) x (change of current) The solution to this issue is to keep the test current constant over time. “error” term (current) x (inductance change) It is difficult to reduce. In practice the only way is to wait for the inductance change to stabilize. 5
  • 6. 6 TAP POS. HV WINDING RESISTANCE (m-ohm) UV UW VW 3 25.02 25.70 25.03 LV WINDING (m-ohm) R-N Y-N B-N RY YB BR 4.130 4.111 4.153 7.955 7.92 7.755 Winding Resistance Test readings of a Transformer.
  • 7. Transformer Ratio Measurements 1. The tap changer of transformer is kept in the lowest position and LV terminals are kept open. 2. Apply 3-phase 415 V supply on HV terminals. Measure the voltages applied on each phase (Phase-phase) on HV and induced voltages at LV terminals simultaneously. 3. After measuring the voltages at HV and LV terminals, the tap changer of transformer should be raised by one position and repeat test. 7
  • 8. 8 TAP POS. Calculated Ratio Measure ratio R Y B 3 1.59420 1.5925 1.5928 1.5926 Ratio Measurement test readings of a Transformer.
  • 9. Magnetic Balance Test It is performed to detect faults / defects in the magnetic core structure, shifting and/or de- shaping of windings, failure in inter-turn insulation or fault in Tap Changer These faults change the effective reluctance of the magnetic circuit which then affects the magnetizing current required to establish flux in the core. Test Procedure - 1. Connect single phase 230 Volts supply between first and second phase of primary side of transformer (between 1U & 1V) 2. Measure voltages between 1U-1V, 1V-1W, and between 1W-1U, 3. Similarly measure voltages between 2U-2N, 2V-2N & 2W-2N 4. Then connect single-phase supply between second and third phase on primary side (between 1V-1W) 9
  • 10. 5. Again Measure voltages between 1U-1V, 1V-1W, and between 1W-1U 6. Repeat Similar Procedure for LV side. 10 2U-2N 2V-2N 2W-2N 239.0 207.9 31.20 138.9 239.5 99.80 36.5 201.6 239.1 1U-1V 1V-1W 1W-1U 229.7 112.15 117.5 195.2 229.75 33.6 198.1 31.4 229.7 Magnetic Balance test readings of a Transformer. *all readings in Volts
  • 11. Dissipation factor measurement/ tan(δ) test •Tan(δ) performed to investigate the condition of the insulation of power transformers and bushings. •The dissipation factor/tan(δ), is the ratio of Resistive component of current to Capacitive component of current flowing through a insulator. •A pure insulator when is connected across line and earth, it behaves as a capacitor. There is no resistive component of the current, as there is zero percent impurity. •For good insulator, resistive component of leakage electric current is quite low. 11
  • 12. • In the vector diagram, the system voltage is drawn along x-axis. • Conductive electric current i.e. resistive component of leakage current, IR will also be along x-axis. • As the capacitive component of leakage electric current IC leads system voltage by 90°, it will be drawn along y-axis. • Total leakage electric current (IR+ IC) makes an angle δ (say) with y-axis. • Now, from the diagram above, it is clear, the ratio, IR to IC is nothing but tanδ or tan delta. • NB: This δ angle is known as loss angle. 12
  • 13. Interpretation of tan(δ) Measurement 1. Comparing the results of previous tests to determine, the deterioration of the condition of insulation due to ageing effect. 2. Determining the condition of insulation from the value of tanδ, directly. If the insulation is perfect The loss factor will be approximately same for all range of test voltages. If the insulation is not sufficient The value of tan delta increases in the higher range of test voltage. 13
  • 14. 14 Meas. Combination Test Voltage Mode Capacitance(nF) Current(mA) Tan δ HV-E 2 KV GST-GA 2.89418 1.820 0.1988 5 KV 2.9004 4.56 0.3295 HV-LV 2 KV UST-A 3.7693 2.3687 0.3349 5 KV 3.7681 5.9252 0.3099 LV-E 2 KV GST-GA 7.8876 4.9632 0.3205 Tan Delta test readings of a Transformer.
  • 15. Dissolved Gas Analysis for Transformers •Oil sample analysis is a useful, predictive, maintenance tool for determining transformer health. •The breakdown of electrical insulating materials and related components inside a transformer generates gases within the transformer. •The identity of the gases being generated can be very useful information in any preventive maintenance program. •This method involves sampling the oil and testing the sample to measure the concentration of the dissolved gases. •It is recommended that DGA of the transformer oil be performed at least on an annual basis with results compared from year to year. 15
  • 16. Insulating mineral oils for transformers are mixtures of many different hydrocarbon molecules The fundamental chemical reactions involve the breaking of carbon hydrogen and carbon-carbon bonds. Energy is needed for the breaking of the chemical bonds and this comes from the energy contained in the fault of the transformer. Gases Formed 16
  • 17. 17
  • 18. Sweep Frequency Response Analysis Test | SFRA Test •A transformer can be considered as a complicated distributed network of resistance, inductance, and capacitance or in other words a transformer is a complicated RLC circuit. •Because of that each winding of a transformer exhibits a particular frequency response. •In SFRA a sinusoidal voltage Vi is applied to one end of a winding and output voltage Vo is measured at the other end of the winding. Other windings are kept open. •As the winding is itself a distributed RLC circuit it will behave like RLC filter and gives different output voltages at different frequencies. 18
  • 19. After transportation, heavy short circuit faults, transient switching impulses and lightening impulses etc., if we do same Sweep Frequency Response Analysis test and superimpose the present signature with the earlier patterns and observe some deviation between these two graphs, we can assess that there is mechanical displacement and deformation occurred in the winding. Plot of output voltages against the corresponding frequencies. 19
  • 20. Three methods are commonly used to assess the measured traces:  Time-based – current SFRA results will be compared to previous results of the same unit.  Type-based – SFRA of one transformer will be compared to an equal type of transformer.  Phase comparison – SFRA results of one phase will be compared to the results of the other phases of the same transformer. 20