SlideShare a Scribd company logo
1 of 12
Download to read offline
1
Transformer Failure Due to Circuit Breaker
Induced Switching Transients
David D. Shipp, PE
Fellow, IEEE
Eaton Electrical Group
130 Commonwealth Dr.
Warrendale, PA 15086
Thomas J. Dionise, PE
Senior Member, IEEE
Eaton Electrical Group
130 Commonwealth Dr.
Warrendale, PA 15086
Visuth Lorch
Eaton Electrical Group
130 Commonwealth Dr.
Warrendale, PA 15086
Bill G Mac Farlane, PE
Member, IEEE
Eaton Electrical Group
130 Commonwealth Dr.
Warrendale, PA 15086
2
2
Introduction
• Switching transients associated with circuit breakers
observed for many years
• Breaking opening/closing interacts with the circuit
elements producing a transient
• The severity of the transient is magnified by breaker
characteristics
• Current chopping on opening
• Pre-strike or re-ignition on closing
• In limited instances, the transient overvoltage exceeds
transformer BIL resulting in failure
• RC snubber in combination with surge arrester
mitigates the transient
2
3
3
Introduction
• Forensic evidence and history of failures
• Underlying concepts
• Predicting performance with simulations
• Mitigating the transients with snubbers
• Concerns for the pulp and paper industry
• Custom designing the snubber
• Snubber performance measurements
4
4
Unique Case – Forensic Evidence
• Four electricians “simultaneously”
opened four 26kV VCBs
• simulate utility outage
• systems transferred to
standby generation
• “loud pop” in Sub Rm B
• the relay for VCB feeding
transformer TB3 signaled trip
• Minutes later, two electricians
“simultaneously” closed two 26kV
VCBs
• breakers to Sub Rm A
• transformer TA3 failed
catastrophically
3
5
5
Transformer Failure #2 - Energization
• Examination of
primary windings
• Coil-to-coil tap burn off
• Winding showed an
upward twist
• Burn marks from the
initial blast
• Transient on first turns
of windings
6
6
Transformer Failure #1 – De-energization
• Examination of primary windings
• Flash and burn marks on b-phase at bottom & middle
• Bottom - Indicate a coil-to-coil flashover (high dv/dt)
• Middle – cable used to make delta swung free (lack of support)
• Transformer passed BIL test at 150kV but failed at 162kV
Both failed units:
• 40 feet of cable
• High efficiency
design
• VCB switching
4
7
7
History of Failures – Forensic Review
Case Facility Voltage
Cable
Feet Bil Type Arrester
Failure
Mode Vendor Switching
1* Hydro Dam 13.80 20 50 Dry No 1st turn A Close
2 Hospital 13.80 27 95 Dry No 1st turn A Close
3 Railroad 26.40 37 150 Liquid N/A middle A Open
4 Data Center 26.40 40 150 Cast coil Yes 1st turn B Close/Open
80 150 Cast coil Yes None B Close
5 Oil Field 33.00 7 Dry No 1st turn C Close
6** Oil Drill Ship 11.00 <30 75 Cast coil Yes 1st turn C Close
Notes: * = 40-50yrs. old with new breaker. ** = 2 yrs. old. All others new.
*** = All transformers unloaded or lightly loaded when switched.
Circuit Vacuum BreakerTransformer***
8
8
Common Parameters
“Rules of Thumb” to screen applications:
• Generally, short distance between circuit breaker and
transformer
• about 200 feet or less
• Dry-type transformer
• oil filled and cast coil not immune and low BIL
• Inductive load being switched
• transformer, motor, etc. (light load or no load)
• Circuit breaker switching characteristics:
• chop (vacuum or SF6) or restrike (vacuum)
5
9
9
Underlying Concepts - Current Chop
• VCB opens, arc burns metal
vapor
• Heat supplied by current
• As current goes to zero,
metal vapor ceases
• Arc ceases or “chops”
• All breaker chop current
• low end 3 – 5A
• high end 21A
Contact Material Average (A) Maximum (A)
CU 15 21
Ag 4 7
Cr 7 16
W 14 50
Cr-Cu (75 wt %) 3 5
Cr-Cu-Bi (5 wt %) 1 3
Cr-Cu-Sb (9 wt %) 4 11
Cu-Bi (0.15 wt %) 6 21
WC-Ag (50 wt %) 1.5 2.5
W-Cu (30 wt %) 5 10
Co-AG-SE 0.4 0.8
Cu-Bi-Pb 1 9
6A current
chop
Modern VI
Older VI
10
10
Reignition and Voltage Escalation
• Current chop plus
system C and L imposes
high frequency TRV on
VCB contacts
• If TRV exceeds breaker
rated TRV, then
reignition occurs
• VCB closes and then
opens high frequency
current
• Multiple reignitions lead
to voltage escalation
6
11
11
Switching inductive circuits
• Current cannot change instantaneously in an
inductor (conservation of energy)
• Energy Equation ½ LI2 = ½ CV2 or V = I L/C
• Vtransient = Venergy + Vdc + Vosc
• Venergy is from the Energy Equation
• Vdc = DC Off-set due to system X/R
• Vosc = the Oscillatory Ring Wave
12
12
Predicting Performance – EMTP Simulations
TRANSFORMER
RLRG
LTRANRTRAN T1T2
CHCL
N:1
CABLE
13.8KV
C1LCABLERCABLEC2
C/2 C/2
SYSTEM SOURCE
AT 13.8 KV
XUTIL RUTIL
VUTIL
UN
UUT
VCB
BKR
• For purposes of screening applications for damaging TOVs
• Source, breaker, cable and transformer modeled
• Breaker models for current chop and re-ignition
7
13
13
Matching model to measurements
Vacuum
Breaker
Short
Cable
30KV
BIL
V max of 4.96kV < 30kV BIL
Oscillation of 20.2kHz
3 x 2865KW Gens
1865KW motors
1185KVA
630A
14
14
Transient Mitigation
• Surge Arrester
• Overvoltage protection (magnitude only)
• Surge Arrester + Surge Capacitor
• Overvoltage protection
• Slows down rate-of-rise
• Surge Arrester + RC Snubber
• Overvoltage protection
• Slows down rate-of-rise
• Reduces DC offset and provides damping
8
15
15
Breaker opening followed by reignition
R = 40ohm
C = 0.5uF
TRV exceeds
limit
TRV within
limit
C37.011
C37.011
16
16
A Borderline Case
• Tier III Data Center
• 2x 24.8kV lines
• 2 x 12.5MVA service
• 13.2kV ring bus
• 2 x 2250KW generators
• 6 x 3750KVA cast-coil
transformers 90kV BIL
• VCBs on primary side
• 109 – 249 ft. cables
123kV
969Hz
38.6kV
215Hz
R = 30ohm
C = 0.25uF
9
17
17
Switching a Highly Inductive Circuit
386kV
1217Hz
56.4kV
200Hz
R = 100ohm
C = 0.25uF
138KV
UTILITY
4713MVA 3PH SC
9.26 X/R
50/66/83MVA
135.3/26.4KV
7.5%Z
SF-6 BREAKER
2000A
1600A
27KV
13OHM
AUTO LTC
56MVA
27-10KV
3.3%Z
ALUMINUM
IPS BUS
53FEET
VACUUM BREAKER
1200A
LMF XFMR
50/56MVA
25/.53KV
2.5%Z
HEAVYDUTY
COPPER PIPE
28FEET
LMF
20MW
Vacuum
Breaker
Short
Bus
200KV
BIL
18
18
Concerns for the Pulp & Paper Industry
• VCB retrofit for primary load break switch (LBS)
• Units subs with LBS and no secondary main
• Arc flash issues on sec main (no room to install secondary
main breaker)
• Retrofit VCB in LBS box solves AF issue
• VCB for rectifier (or isolation) transformer
• DC drives for feed water pumps
• VCB on primary
• Short run of cable to transformer (often dry type)
• New unit sub with primary VCB
• Metal enclosed vacuum switchgear
• 7500KVA transformer for gen boilers to meet EPA requirement
• 5 feet of bus
10
19
19
Designing the Snubber
• 15kV typical snubber & arrester
• transformer protection
• non-inductive ceramic resistor
• 25 ohms to 50 ohms
• surge capacitor
• Standard capacitor ratings
0.15 μF to 0.35 μF
• 3-phase 13.8kV solidly ground
• 1-phase 13.8kV LRG
R
C
SA
TX
Surge
Arrester
Resistor
Surge
Cap
20
20
Top hat and switchgear designs
15kV snubber above the
transformer (top hat)
15kV snubber in MV
switchgear
13.8kV snubber in metal
enclosed switchgear
11
21
21
Design Options – Detect Functionality
• nothing (oversized but treated like a
lightning arrester)
• Glow tube indicators
• visible through a window in the switchgear door
• provide a visual indication of snubber continuity
• current sensors
• monitor the continuity of the resistor and fuse
• alarm on loss of continuity
• Some industries mandate fused protection
• alarm signal can be sent to the plant DCS or
SCADA system
• alert the operating personnel that these
snubber components have failed
Glow Tube
Current Sensor
22
22
Custom Designs for Pulp & Paper
• 13.8 kV solidly grounded system
• VCB retrofit for load break switch
• 3-phase surge cap
• 13.8 kV low resistance grounded
• VCB retrofit for Load break switch
• 1-phase surge cap
• 2 x resistors in parallel
• 13.8 kV low resistance grounded
• new VCB
• New 13.8/2.4kV 7500 KVA transformer
• 1-phase surge caps and single resistors
12
23
23
Snubber Performance Measurements
Hookup at
arrester
24
24
Conclusions
• Not all VCB primary switching of transformers require
snubbers
• Transformer failures due to primary VCB switching
transients do occur
• Current chop and re-ignition combine with unique
circuit parameters
• “Rule of Thumb” - Vacuum breaker, short cable or bus
and dry type transformer (aged or low BIL liquid filled)
• Snubbers plus arresters mitigate the transient
• Retrofits require custom design of snubber
• Field measurements confirm snubber performance

More Related Content

What's hot

891 Switchboard vs. 1558 Switchgear
891 Switchboard vs. 1558 Switchgear891 Switchboard vs. 1558 Switchgear
891 Switchboard vs. 1558 Switchgear
michaeljmack
 
Interconnet protection of
Interconnet protection ofInterconnet protection of
Interconnet protection of
michaeljmack
 
Electrical Systems Safety
Electrical Systems SafetyElectrical Systems Safety
Electrical Systems Safety
Talia Carbis
 
Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"
michaeljmack
 

What's hot (20)

Modeling and analysis of power transformers under ferroresonance phenomenon
Modeling and analysis of power transformers under ferroresonance phenomenonModeling and analysis of power transformers under ferroresonance phenomenon
Modeling and analysis of power transformers under ferroresonance phenomenon
 
High voltage truck protection and fire prevention Paul Edwards
High voltage truck protection and fire prevention   Paul EdwardsHigh voltage truck protection and fire prevention   Paul Edwards
High voltage truck protection and fire prevention Paul Edwards
 
891 Switchboard vs. 1558 Switchgear
891 Switchboard vs. 1558 Switchgear891 Switchboard vs. 1558 Switchgear
891 Switchboard vs. 1558 Switchgear
 
5220 l11
5220 l115220 l11
5220 l11
 
Selective Coordination
Selective CoordinationSelective Coordination
Selective Coordination
 
Managing earthing hazards around pole top transformers at mines and quarries ...
Managing earthing hazards around pole top transformers at mines and quarries ...Managing earthing hazards around pole top transformers at mines and quarries ...
Managing earthing hazards around pole top transformers at mines and quarries ...
 
Standards
StandardsStandards
Standards
 
Circuit Breakers Interrupting Capacity and Short-Time Current Rating
Circuit Breakers Interrupting Capacity and Short-Time Current Rating Circuit Breakers Interrupting Capacity and Short-Time Current Rating
Circuit Breakers Interrupting Capacity and Short-Time Current Rating
 
High voltage megger electric shock Omer Saeed
High voltage megger electric shock   Omer SaeedHigh voltage megger electric shock   Omer Saeed
High voltage megger electric shock Omer Saeed
 
Starting First
Starting FirstStarting First
Starting First
 
Interconnet protection of
Interconnet protection ofInterconnet protection of
Interconnet protection of
 
Electrical Systems Safety
Electrical Systems SafetyElectrical Systems Safety
Electrical Systems Safety
 
8. Arthur Hartsuiker - CN Rood
8. Arthur Hartsuiker - CN Rood8. Arthur Hartsuiker - CN Rood
8. Arthur Hartsuiker - CN Rood
 
Fat procedure for lv switchboards
Fat procedure for lv switchboardsFat procedure for lv switchboards
Fat procedure for lv switchboards
 
Differential protection of power transformer
Differential protection of power transformerDifferential protection of power transformer
Differential protection of power transformer
 
Uninterruptible power supply installations at mines Murray Timpson
Uninterruptible power supply installations at mines  Murray TimpsonUninterruptible power supply installations at mines  Murray Timpson
Uninterruptible power supply installations at mines Murray Timpson
 
Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"
 
Your electrical safety specilist for all equipments Powered AC and DC
Your electrical safety specilist for all equipments   Powered AC and DCYour electrical safety specilist for all equipments   Powered AC and DC
Your electrical safety specilist for all equipments Powered AC and DC
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakers
 
Optimal Cable Sizing in PV Systems: Case Study
Optimal Cable Sizing in PV Systems: Case StudyOptimal Cable Sizing in PV Systems: Case Study
Optimal Cable Sizing in PV Systems: Case Study
 

Similar to Transformer Failure Due to Circuit Breaker Induced Switching Transients

Hvdc circuit breaker
Hvdc circuit breakerHvdc circuit breaker
Hvdc circuit breaker
Clinton Charalse
 
Service cabinetandtransformerbreakersizing1082004
Service cabinetandtransformerbreakersizing1082004Service cabinetandtransformerbreakersizing1082004
Service cabinetandtransformerbreakersizing1082004
michaeljmack
 

Similar to Transformer Failure Due to Circuit Breaker Induced Switching Transients (20)

Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
 
ABB Price List of Capacitors 008
ABB Price List of Capacitors 008ABB Price List of Capacitors 008
ABB Price List of Capacitors 008
 
Cooper Power Connectors - MV-HV Specifiers Guide 5kV-35kV
Cooper Power Connectors - MV-HV Specifiers Guide 5kV-35kVCooper Power Connectors - MV-HV Specifiers Guide 5kV-35kV
Cooper Power Connectors - MV-HV Specifiers Guide 5kV-35kV
 
Decoupler Interaction With CP Systems - Mike Tachick
Decoupler Interaction With CP Systems - Mike TachickDecoupler Interaction With CP Systems - Mike Tachick
Decoupler Interaction With CP Systems - Mike Tachick
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
 
Principles Control & Protection of HVDC Schemes
Principles Control & Protection of HVDC SchemesPrinciples Control & Protection of HVDC Schemes
Principles Control & Protection of HVDC Schemes
 
Power transformers rating
Power transformers ratingPower transformers rating
Power transformers rating
 
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuitsModule 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
 
132 KV GSS CHAMBAL JAIPUR
132 KV GSS CHAMBAL JAIPUR132 KV GSS CHAMBAL JAIPUR
132 KV GSS CHAMBAL JAIPUR
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
 
Transient Recovery Voltage (TRV) Studies.pdf
Transient Recovery Voltage (TRV) Studies.pdfTransient Recovery Voltage (TRV) Studies.pdf
Transient Recovery Voltage (TRV) Studies.pdf
 
IEEE Blue Book
IEEE Blue BookIEEE Blue Book
IEEE Blue Book
 
10 lm 555 timer
10 lm 555 timer10 lm 555 timer
10 lm 555 timer
 
ct pt testing...........................................
ct pt testing...........................................ct pt testing...........................................
ct pt testing...........................................
 
L2 thyristors
L2 thyristorsL2 thyristors
L2 thyristors
 
Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)
 
Hvdc circuit breaker
Hvdc circuit breakerHvdc circuit breaker
Hvdc circuit breaker
 
HIGH VOLTAGE PANEL SWITCHGEAR PRESENTATION
HIGH VOLTAGE PANEL SWITCHGEAR PRESENTATIONHIGH VOLTAGE PANEL SWITCHGEAR PRESENTATION
HIGH VOLTAGE PANEL SWITCHGEAR PRESENTATION
 
Service cabinetandtransformerbreakersizing1082004
Service cabinetandtransformerbreakersizing1082004Service cabinetandtransformerbreakersizing1082004
Service cabinetandtransformerbreakersizing1082004
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 

More from michaeljmack

Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
michaeljmack
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
michaeljmack
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
michaeljmack
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protection
michaeljmack
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systems
michaeljmack
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spaces
michaeljmack
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
michaeljmack
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distribution
michaeljmack
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulator
michaeljmack
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
michaeljmack
 

More from michaeljmack (20)

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbook
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbook
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgear
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protection
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systems
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spaces
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distribution
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performance
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulator
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plants
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Stories
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentals
 

Recently uploaded

Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systems
meharikiros2
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
HenryBriggs2
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
hublikarsn
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 

Recently uploaded (20)

UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systems
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
 
Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 

Transformer Failure Due to Circuit Breaker Induced Switching Transients

  • 1. 1 Transformer Failure Due to Circuit Breaker Induced Switching Transients David D. Shipp, PE Fellow, IEEE Eaton Electrical Group 130 Commonwealth Dr. Warrendale, PA 15086 Thomas J. Dionise, PE Senior Member, IEEE Eaton Electrical Group 130 Commonwealth Dr. Warrendale, PA 15086 Visuth Lorch Eaton Electrical Group 130 Commonwealth Dr. Warrendale, PA 15086 Bill G Mac Farlane, PE Member, IEEE Eaton Electrical Group 130 Commonwealth Dr. Warrendale, PA 15086 2 2 Introduction • Switching transients associated with circuit breakers observed for many years • Breaking opening/closing interacts with the circuit elements producing a transient • The severity of the transient is magnified by breaker characteristics • Current chopping on opening • Pre-strike or re-ignition on closing • In limited instances, the transient overvoltage exceeds transformer BIL resulting in failure • RC snubber in combination with surge arrester mitigates the transient
  • 2. 2 3 3 Introduction • Forensic evidence and history of failures • Underlying concepts • Predicting performance with simulations • Mitigating the transients with snubbers • Concerns for the pulp and paper industry • Custom designing the snubber • Snubber performance measurements 4 4 Unique Case – Forensic Evidence • Four electricians “simultaneously” opened four 26kV VCBs • simulate utility outage • systems transferred to standby generation • “loud pop” in Sub Rm B • the relay for VCB feeding transformer TB3 signaled trip • Minutes later, two electricians “simultaneously” closed two 26kV VCBs • breakers to Sub Rm A • transformer TA3 failed catastrophically
  • 3. 3 5 5 Transformer Failure #2 - Energization • Examination of primary windings • Coil-to-coil tap burn off • Winding showed an upward twist • Burn marks from the initial blast • Transient on first turns of windings 6 6 Transformer Failure #1 – De-energization • Examination of primary windings • Flash and burn marks on b-phase at bottom & middle • Bottom - Indicate a coil-to-coil flashover (high dv/dt) • Middle – cable used to make delta swung free (lack of support) • Transformer passed BIL test at 150kV but failed at 162kV Both failed units: • 40 feet of cable • High efficiency design • VCB switching
  • 4. 4 7 7 History of Failures – Forensic Review Case Facility Voltage Cable Feet Bil Type Arrester Failure Mode Vendor Switching 1* Hydro Dam 13.80 20 50 Dry No 1st turn A Close 2 Hospital 13.80 27 95 Dry No 1st turn A Close 3 Railroad 26.40 37 150 Liquid N/A middle A Open 4 Data Center 26.40 40 150 Cast coil Yes 1st turn B Close/Open 80 150 Cast coil Yes None B Close 5 Oil Field 33.00 7 Dry No 1st turn C Close 6** Oil Drill Ship 11.00 <30 75 Cast coil Yes 1st turn C Close Notes: * = 40-50yrs. old with new breaker. ** = 2 yrs. old. All others new. *** = All transformers unloaded or lightly loaded when switched. Circuit Vacuum BreakerTransformer*** 8 8 Common Parameters “Rules of Thumb” to screen applications: • Generally, short distance between circuit breaker and transformer • about 200 feet or less • Dry-type transformer • oil filled and cast coil not immune and low BIL • Inductive load being switched • transformer, motor, etc. (light load or no load) • Circuit breaker switching characteristics: • chop (vacuum or SF6) or restrike (vacuum)
  • 5. 5 9 9 Underlying Concepts - Current Chop • VCB opens, arc burns metal vapor • Heat supplied by current • As current goes to zero, metal vapor ceases • Arc ceases or “chops” • All breaker chop current • low end 3 – 5A • high end 21A Contact Material Average (A) Maximum (A) CU 15 21 Ag 4 7 Cr 7 16 W 14 50 Cr-Cu (75 wt %) 3 5 Cr-Cu-Bi (5 wt %) 1 3 Cr-Cu-Sb (9 wt %) 4 11 Cu-Bi (0.15 wt %) 6 21 WC-Ag (50 wt %) 1.5 2.5 W-Cu (30 wt %) 5 10 Co-AG-SE 0.4 0.8 Cu-Bi-Pb 1 9 6A current chop Modern VI Older VI 10 10 Reignition and Voltage Escalation • Current chop plus system C and L imposes high frequency TRV on VCB contacts • If TRV exceeds breaker rated TRV, then reignition occurs • VCB closes and then opens high frequency current • Multiple reignitions lead to voltage escalation
  • 6. 6 11 11 Switching inductive circuits • Current cannot change instantaneously in an inductor (conservation of energy) • Energy Equation ½ LI2 = ½ CV2 or V = I L/C • Vtransient = Venergy + Vdc + Vosc • Venergy is from the Energy Equation • Vdc = DC Off-set due to system X/R • Vosc = the Oscillatory Ring Wave 12 12 Predicting Performance – EMTP Simulations TRANSFORMER RLRG LTRANRTRAN T1T2 CHCL N:1 CABLE 13.8KV C1LCABLERCABLEC2 C/2 C/2 SYSTEM SOURCE AT 13.8 KV XUTIL RUTIL VUTIL UN UUT VCB BKR • For purposes of screening applications for damaging TOVs • Source, breaker, cable and transformer modeled • Breaker models for current chop and re-ignition
  • 7. 7 13 13 Matching model to measurements Vacuum Breaker Short Cable 30KV BIL V max of 4.96kV < 30kV BIL Oscillation of 20.2kHz 3 x 2865KW Gens 1865KW motors 1185KVA 630A 14 14 Transient Mitigation • Surge Arrester • Overvoltage protection (magnitude only) • Surge Arrester + Surge Capacitor • Overvoltage protection • Slows down rate-of-rise • Surge Arrester + RC Snubber • Overvoltage protection • Slows down rate-of-rise • Reduces DC offset and provides damping
  • 8. 8 15 15 Breaker opening followed by reignition R = 40ohm C = 0.5uF TRV exceeds limit TRV within limit C37.011 C37.011 16 16 A Borderline Case • Tier III Data Center • 2x 24.8kV lines • 2 x 12.5MVA service • 13.2kV ring bus • 2 x 2250KW generators • 6 x 3750KVA cast-coil transformers 90kV BIL • VCBs on primary side • 109 – 249 ft. cables 123kV 969Hz 38.6kV 215Hz R = 30ohm C = 0.25uF
  • 9. 9 17 17 Switching a Highly Inductive Circuit 386kV 1217Hz 56.4kV 200Hz R = 100ohm C = 0.25uF 138KV UTILITY 4713MVA 3PH SC 9.26 X/R 50/66/83MVA 135.3/26.4KV 7.5%Z SF-6 BREAKER 2000A 1600A 27KV 13OHM AUTO LTC 56MVA 27-10KV 3.3%Z ALUMINUM IPS BUS 53FEET VACUUM BREAKER 1200A LMF XFMR 50/56MVA 25/.53KV 2.5%Z HEAVYDUTY COPPER PIPE 28FEET LMF 20MW Vacuum Breaker Short Bus 200KV BIL 18 18 Concerns for the Pulp & Paper Industry • VCB retrofit for primary load break switch (LBS) • Units subs with LBS and no secondary main • Arc flash issues on sec main (no room to install secondary main breaker) • Retrofit VCB in LBS box solves AF issue • VCB for rectifier (or isolation) transformer • DC drives for feed water pumps • VCB on primary • Short run of cable to transformer (often dry type) • New unit sub with primary VCB • Metal enclosed vacuum switchgear • 7500KVA transformer for gen boilers to meet EPA requirement • 5 feet of bus
  • 10. 10 19 19 Designing the Snubber • 15kV typical snubber & arrester • transformer protection • non-inductive ceramic resistor • 25 ohms to 50 ohms • surge capacitor • Standard capacitor ratings 0.15 μF to 0.35 μF • 3-phase 13.8kV solidly ground • 1-phase 13.8kV LRG R C SA TX Surge Arrester Resistor Surge Cap 20 20 Top hat and switchgear designs 15kV snubber above the transformer (top hat) 15kV snubber in MV switchgear 13.8kV snubber in metal enclosed switchgear
  • 11. 11 21 21 Design Options – Detect Functionality • nothing (oversized but treated like a lightning arrester) • Glow tube indicators • visible through a window in the switchgear door • provide a visual indication of snubber continuity • current sensors • monitor the continuity of the resistor and fuse • alarm on loss of continuity • Some industries mandate fused protection • alarm signal can be sent to the plant DCS or SCADA system • alert the operating personnel that these snubber components have failed Glow Tube Current Sensor 22 22 Custom Designs for Pulp & Paper • 13.8 kV solidly grounded system • VCB retrofit for load break switch • 3-phase surge cap • 13.8 kV low resistance grounded • VCB retrofit for Load break switch • 1-phase surge cap • 2 x resistors in parallel • 13.8 kV low resistance grounded • new VCB • New 13.8/2.4kV 7500 KVA transformer • 1-phase surge caps and single resistors
  • 12. 12 23 23 Snubber Performance Measurements Hookup at arrester 24 24 Conclusions • Not all VCB primary switching of transformers require snubbers • Transformer failures due to primary VCB switching transients do occur • Current chop and re-ignition combine with unique circuit parameters • “Rule of Thumb” - Vacuum breaker, short cable or bus and dry type transformer (aged or low BIL liquid filled) • Snubbers plus arresters mitigate the transient • Retrofits require custom design of snubber • Field measurements confirm snubber performance