SlideShare a Scribd company logo
1 of 38
Download to read offline
Transformer Failure Due to Circuit Breaker
Induced Switching Transients
Part 1: Case Study Overview
David D. Shipp, PE
Fellow, IEEE
Eaton Electrical Group
130 Commonwealth Dr.
Warrendale, PA 15086
Thomas J. Dionise, PE
Senior Member, IEEE
Eaton Electrical Group
130 Commonwealth Dr.
Warrendale, PA 15086
Case Study Overview:
Data Center Transformer Failure
Attributed to
Circuit Breaker Induced
Switching Transients
System Configuration, Failure Analysis
and RC Snubber Fix
R. McFadden – JB&B – NY, NY
D. Shipp – Eaton Electrical – Pgh, PA
Presentation Purpose/Summary
• Purpose #1 Safety:
– Alert Design & User Community
– Drive Solutions Through Market Interest
• Unique Case History
– Forensic Evidence
– High Speed Power Quality Capture
• Presentation Summary
– Simplified System Overview
– Forensic Review
– Power Quality Snapshots
– Installed RC Snubber Fix
• Presentation Summary: David Shipp, Eaton
– Phenomenon Detailed Explanation
– Science of RC Snubber Design
Site Specifics
• Utility Service:
– 26kV
– Double Ended Loop Through
• Transformers
– (6) Total
– 26kV Primary, 480V Secondary
– VPI
– 3000kVA AA / 3990 kVA FA
– 150 kVbil
• Switching Device
– Vacuum Circuit Breaker
• Cable
– 35kV, 133% EPR Insulation, 1/3 Concentric Ground
M
T-A3
CRACs
Chillers
T-A2
UPS
T-A1
OTHER
40’
80’
100’+
26kv Utility “A”
To Normal Side
Of 480vac ATS
(Typical)
M
T-B3
CRACs
Chillers
T-B2
UPS
T-B1
OTHER
40’
80’
100’+
26kv Utility “B”
Simplified System Configuration
Failure/Sequence of Events
• All Transformers Fully Tested:
• Pre-functional: Turns Ratio, Insulation Resistance, etc
• Functional:UPS Full Load Tests, UPS Transient Tests, Data Center
Room Validation Testing
• Final Pull The Plug Test (PTP)
• 4 Electricians “simultaneously” open (4) 26KV vacuum breakers to
simulate a general utility outage.
• All systems successfully transfer to standby generation but:
• Loud Pop heard in Substation Room B
• Relay for VCB feeding TB3 signaling trip
• Decision made to shutdown generator test and investigate issue in
“B” substation room
• 2 Electricians “simultaneously” close (2) 26KV vacuum breakers to
Substation Room “A”
• Transformer TA3 fails catastrophically.
M
T-A3
CRACs
Chillers
T-A2
UPS
T-A1
OTHER
40’
80’
100’+
26kv Utility “A”
0.8MW
M
T-B3
CRACs
Chillers
T-B2
UPS
T-B1
OTHER
40’
80’
100’+
26kv Utility “B”
Pre-PTP Condition
1.5MW
0.9MW
1.3MW
M
T-A3
CRACs
Chillers
T-A2
UPS
T-A1
OTHER
40’
80’
100’+
26kv Utility “A”
M
T-B3
CRACs
Chillers
T-B2
UPS
T-B1
OTHER
40’
80’
100’+
26kv Utility “B”
Failure #1: De-Energization During PTP
Audible Pop
In Substation
Room
Relay
Signaling
Trip
M
T-A3
CRACs
Chillers
T-A2
UPS
T-A1
OTHER
40’
80’
100’+
26kv Utility “A”
M
T-B3
CRACs
Chillers
T-B2
UPS
T-B1
OTHER
40’
80’
100’+
26kv Utility “B”
Failure #2: Energization During PTP
Catastrophic
Failure
Relay Trips
VCB
Coil to Coil Tap
Burnt Off
Failure #2
Transformer Failure On Energization
Coil to Coil Conductor
Burnt Off
Suspected Area
of Initial Flash
Failure #2
Transformer Failure On Energization
Coil to Coil Tap
Burnt Off
Failure #2
Transformer Failure On Energization
Coil to Coil Tap
Burnt Off
Upward Twist
From Lower Blast
Failure #2
Transformer Failure On Energization
Flash/Burn Marks
Failure #1
Transformer Failure On De-Energization
Close up of
Flash/Burn Marks
Coil to Coil not
Winding to Winding
Failure #1
Transformer Failure On De-Energization
This Transformer was Returned
to the Factory and Passed all
Standard IEEE Tests!
This Transformer was Returned
to the Factory and Passed all
Standard IEEE Tests!
No Coil to Coil
Cable Supports
Some Burn
Marks Match
Point of
Cable Contact
15KV Cable
In 26KV
Transformer
Failure #1
Transformer Failure On De-Energization
Some Burn
Marks Match
Vicinity of Cable
Cable is Undamaged
Failure #1
Transformer Failure On De-Energization
Factory Installed
Cable Support
Unaffected Transformer
Current Transient: Failure #2
Transformer Energization
Event Initiated
A-B Phase 19,000 amp, 3 Phase
5 Cycle CB Clearing Time
Second Transformer
Inrush
AØ
BØ
CØ
AØ
BØ
CØ
Current Transient: Failure #1
Transformer DeEnergization
8000amp A-B
Phase
Approx ¼ Cycle
C Phase Shows
2nd Xfmr Load
& Event Duration
Breaker Induced
Switching Transients
Case 1
Hydro Dam, MT 2005
• MV Vac Bkr Replacements Vendor “A”
• 13.8 kV
• 20 feet of cable
• 50 kV BIL (W) ASL Dry Type Txmrs
• Customer Energized before Vendor OK
• Txmr Failed
• No Surge Protection Applied
CASE 2
Cleveland Hospital 3/06
• Vacuum Breakers – Vendor “A” and Vendor
“C”
• 13.8 kV
• 95 kV BIL
• Dry Type Txmr
• 27 feet of Cable
• Bkr Manufacturer Paid to Repair Failed 2500
KVA Txmr
• Surge Protection Added Afterwards
CASE 3
RAILROAD SUBSTATION 11/06
• Vacuum Breaker – Vendor “A”
• 26.4 kV
• 150 kV BIL
• Generic Liquid Filled Rectifier Txmr
• 37 feet of Cable
CASE 4
NJ DATA CENTER 12/06
• 26.4 kV – Vendor “B”
• 4 Txmrs Switched Under Light Load
• 2 Txmrs Failed-1 on Closing/1 on
Opening
• 40 Feet of Cable
• 2 other Txmrs Did Not Fail - 80 Feet of
Cable
• Arresters Were Present
CASE 5
OIL FIELD – AFRICA 6/07
• Vacuum Breaker – Vendor “D”
• 33 kV
• 7 Feet of Cable
• Dry Type Txmr in 36 Pulse VSD
• Arresters Were Applied
• Txmr Failed Upon Energization
CASE 9
Oil Drilling Ship – 6/2002
• Vendor “A” IEC Vac Bkrs in Vendor “D”
Swgr
• 11kV, 60 HZ
• Cast Coil Dry Type IEC VSD Propulsion
Txmr Failed (7500 kVA) – 75 kV BIL?
• < 30 feet of Cable
• Fed from Alternate Bus – Now 80 feet of
Cable
• No further Failures Reported
CASE 11
Hospital – Slide 1
• 13. 8 kV System
• Vendor C Breakers/
Vendor F Txmrs
• 2 Txmrs Failed During
Commissioning
• Differential Relay
Tripped During motor
Starting – under
Highly Inductive Load
CASE 11
Hospital – Slide 2
CASE 11
Hospital – Slide 3
CASE 12
Motor Starter Auto Txmr Failure
• 4160V
• 5000 HP
• Reduced Voltage
Auto Txmr Failed
• Arresters on Wye
Point
• Internal Resonance
• Layer Wound
• Failed Layer to Layer
CASE 12 Run Contactor Closes
3516 HZ
CASE 12 - Sweep Frequency Test
4500 HZ (Admittance)
CASE 12 - Run Contactor Closes
– 844 HZ With Snubber
SWITCHING TRANSIENTS DUE TO
VACUUM / SF6 BREAKERS
• Opening -- Current Chop
• Closing -- Prestrike/Re-ignition/Voltage
Escalation
• Vacuum Bkrs --Both Closing and
Opening
• SF6 -- Opening
• Air -- Generally Acceptable
Current Chop
Current Chop
Current Chop in Vacuum is a Material Problem
Current Chop
• All Types of
Interrupters Chop
Current
• This is not a Unique
Feature of Vacuum
Switching Inductive Circuits
• Closing
• Opening
• Voltage Escalation
• Surge Suppression
Switching Inductive Loads
CLOSING
Switching Inductive Loads
OPENING
Switching Inductive Loads
VOLTAGE ESCALATION
SWITCHING TRANSIENT THEORY
• “Thou Shalt Not Change Current
Instantaneously in an Inductor”
• Conservation of Energy –
– You Cannot Create or destroy Energy –
You Can Only Change Its Form
ENERGY EQUATION
22
2
1
2
1
CVLI 
OR
C
L
IV 
TOTAL VOLTAGE
• Vt = Venergy + Vdc + Vosc
• Venergy is from the Energy Equation
• Vdc = DC Off-set that Sometimes is
Present
• Vosc = the Oscillatory Ring Wave
TRANSFORMER LIMITS
• Magnitude – BIL Ratings
• Dv/dt Limits
• Both MUST Be Met
• Dry Type Txmrs Particularly
Susceptable
• Liquid Filled Not Immune.
• Consider “Hammer Effect”
ANALYSIS
• When Open Bkr, Txmr is Left
Ungrounded
• Ring Wave is a Function of its Natural
Frequency
LC
NF
2
1

CASE 3
Waveforms Without Snubbers
CASE 3
Current – Without Snubbers
Ichop
CASE 3
Waveforms With Snubbers
CASE 4
Data Center 12/06
• 26.4 kV
• Vendor “B” Breakers
• 4 Bkrs Switched at Once
• 2 Dry Type Txmrs Failed (40 Ft of
Cable)
• 2 Txmrs Did not Fail (80 Ft of Cable)
• Unfaulted Txmr Winding Failed BIL
@162 kV ( Rated 150 kV)
CASE 4
Data Center, NJ 12/06 - W/O Snubbers
08-Jan-07 14.53.47
0 5 10 15 20 25
-200
-150
-100
-50
0
50
100
150
200
v [kV]
t [ms](42) XFMA3C (48) XFMB3C
Plot of the Transformer A3 and B3 primary voltage Phase C
Open circuit breaker with chopped current of 9 Amperes
-207 kV
CASE 4
Data Center, NJ 12/06-With Snubbers
09-Jan-07 10.50.25
0 5 10 15 20 25
-40
-30
-20
-10
0
10
20
30
40
v [kV]
t [ms](29) XFMA3B (35) XFMB3B
Plot of the Transformer A3 and B3 primary voltage Phase B
Open circuit breaker with chopped current of 9 Amperes
Application of the R-C snubber circuit
-39 kV
CASE 6
Data Center 2, NJ 12/06
• 13.2 kV
• Vendor “B” Breakers
• 3 MVA Dry Type Txmrs
• 60 ft Cable – Required Snubbers
• 157 ft Cable – Required Snubbers
• No Problem at Startup
CASE 6
13.2 kV SYSTEM – 119 kV @ 678 HZ
CASE 6
WITH SNUBBERS – 33.6 kV @ 236 HZ
CASE 7
Chemical Plant, NC 3/07
• 12.47 kV System
• 20+ Year Old Oil Filled Txmrs
• Vendor “A” Vacuum Bkrs retrofitted on
Primary
• 10 Feet of Cable
• No Problem at Startup
CASE 7
425 kV - 12. 47 kV - 23 kHZ Ring Wave
CASE 7
Added Snubbers – 12.47 kV
CASE 8
DATA CENTER – Indiana 6/07
• 12.47 kV System
• Vendor “A” Breakers
• 270 Feet of Cable
• No Additional Surge Protection
Required
CASE 8
-55 kV at 800 HZ
CASE 11 Hospital
186.9 kV / 2000 HZ
CASE 10 – Snubber
Reduced to 33.8 kV / 368 HZ
MITIGATING TECHNIQUES
• Arresters
• Surge Capacitors
• Snubbers (RC)
• Hybrid / Combinations
• Liquid vs Dry Type
• Electronic Zero Crossing Switching
Snubber - 3 Phase Capacitor
Generally Solidly Grounded System
• Paper Mill - AL
• 13.8 kV
Snubbers – 2nd paper mill - beta site
Snubber – Single Phase Capacitors
Low Resistance Grounded Systems
• Paper Mill
• Vendor “A” Swgr
• 13.8 kV
Snubber – Single Phase Capacitors
• Silicon “Chip” Plant
• Montana
• Very Specialized
Dry Type Txmrs
• 13.8 kV
• Cables < 100 feet
• Primary Fused
Switch AF Solution
• Vendor “A” Vac Bkrs
Capacitor
Resistor
Fuse
Lightning
Arrestor
Blown Fuse
Viewing Window
RC Snubber Installed – Case 4
RC Snubber Installed – Case 4
Capacitor
Resistor
RC Snubber Installed – Case 4
Fuse
Blown
Fuse
Indicator
SWITCHING TRANSIENT STUDY
• Quantifies Problem
• Predict Exposure / Risk
• Select Best / Most Cost Effective
Solution
• Do “What if” Cases
• Verify Results
RECOMMENDATIONS
• Factor into Design Up-front
• Do Study – Results Are Bkr Manufacturer
Specific
• Use Protection Only When / Where Needed
(if not there, cannot fail)
• Fused or Unfused Snubbers??
• Loss of Fuse Detection??
• Fear Not! - Mitigating Techniques Have Been
Proven.
• Discrete Snubber Components??
Conclusion/Next Steps
• This is a System Problem
– Transformer, Cable, Switching Device, Proximity
– Statistical Event , Possible Undetected Failures
• Data Centers Fall into the Highest Risk Category
– High Power Density
– Close Proximities
– Frequent Switching
• Draft IEEE C57.142
– A Guide To Describe The Occurrence and Mitigation Of Switching Transients
Induced By Transformer And Switching Device Interaction
– Does not accurately warn users of all areas of concern
– This case did not meet the areas of concern noted in Draft C57.142
– Need to push for formalization of the standard with new lessons learned
• RC Snubbers
– Transformer Manufacturer appears best positioned to implement the solution
– Limited Cataloged Product (One Manufacturer)
– Not embraced by all transformer manufacturers
– Design Parameters of RC Snubber not clearly defined
• Lives, Property and Uptime are all at risk
QUESTIONS ?

More Related Content

What's hot

Modeling and analysis of power transformers under ferroresonance phenomenon
Modeling and analysis of power transformers under ferroresonance phenomenonModeling and analysis of power transformers under ferroresonance phenomenon
Modeling and analysis of power transformers under ferroresonance phenomenonGilberto Mejía
 
High voltage truck protection and fire prevention Paul Edwards
High voltage truck protection and fire prevention   Paul EdwardsHigh voltage truck protection and fire prevention   Paul Edwards
High voltage truck protection and fire prevention Paul EdwardsNSW Environment and Planning
 
Interconnet protection of
Interconnet protection ofInterconnet protection of
Interconnet protection ofmichaeljmack
 
ABB switchgear safety hazards passive & active arc fault protection by David ...
ABB switchgear safety hazards passive & active arc fault protection by David ...ABB switchgear safety hazards passive & active arc fault protection by David ...
ABB switchgear safety hazards passive & active arc fault protection by David ...Keren Meers
 
Managing earthing hazards around pole top transformers at mines and quarries ...
Managing earthing hazards around pole top transformers at mines and quarries ...Managing earthing hazards around pole top transformers at mines and quarries ...
Managing earthing hazards around pole top transformers at mines and quarries ...NSW Environment and Planning
 
Pd Maintenance
Pd MaintenancePd Maintenance
Pd Maintenancedwessin
 
Uninterruptible power supply installations at mines Murray Timpson
Uninterruptible power supply installations at mines  Murray TimpsonUninterruptible power supply installations at mines  Murray Timpson
Uninterruptible power supply installations at mines Murray TimpsonNSW Environment and Planning
 
Generator grounding
Generator groundingGenerator grounding
Generator groundingmichaeljmack
 
Selective Coordination
Selective CoordinationSelective Coordination
Selective Coordinationmichaeljmack
 
891 Switchboard vs. 1558 Switchgear
891 Switchboard vs. 1558 Switchgear891 Switchboard vs. 1558 Switchgear
891 Switchboard vs. 1558 Switchgearmichaeljmack
 
Brett Roberts - Some aspects of electrical power system protection in undergr...
Brett Roberts - Some aspects of electrical power system protection in undergr...Brett Roberts - Some aspects of electrical power system protection in undergr...
Brett Roberts - Some aspects of electrical power system protection in undergr...NSW Environment and Planning
 
2015 Arc Flash Conference MV Switchgear Standards
2015 Arc Flash Conference MV Switchgear Standards2015 Arc Flash Conference MV Switchgear Standards
2015 Arc Flash Conference MV Switchgear StandardsBryan Johnson
 
Optimal Cable Sizing in PV Systems: Case Study
Optimal Cable Sizing in PV Systems: Case StudyOptimal Cable Sizing in PV Systems: Case Study
Optimal Cable Sizing in PV Systems: Case StudyLeonardo ENERGY
 
Your electrical safety specilist for all equipments Powered AC and DC
Your electrical safety specilist for all equipments   Powered AC and DCYour electrical safety specilist for all equipments   Powered AC and DC
Your electrical safety specilist for all equipments Powered AC and DCMahesh Chandra Manav
 
Starting First
Starting FirstStarting First
Starting FirstPana Mann
 
Electrical Systems Safety
Electrical Systems SafetyElectrical Systems Safety
Electrical Systems SafetyTalia Carbis
 
Differential protection of power transformer
Differential protection of power transformerDifferential protection of power transformer
Differential protection of power transformerSaad Muftah
 
High voltage engineering
High voltage engineeringHigh voltage engineering
High voltage engineeringHari Kumar
 

What's hot (20)

Modeling and analysis of power transformers under ferroresonance phenomenon
Modeling and analysis of power transformers under ferroresonance phenomenonModeling and analysis of power transformers under ferroresonance phenomenon
Modeling and analysis of power transformers under ferroresonance phenomenon
 
High voltage truck protection and fire prevention Paul Edwards
High voltage truck protection and fire prevention   Paul EdwardsHigh voltage truck protection and fire prevention   Paul Edwards
High voltage truck protection and fire prevention Paul Edwards
 
5220 l11
5220 l115220 l11
5220 l11
 
Interconnet protection of
Interconnet protection ofInterconnet protection of
Interconnet protection of
 
High voltage megger electric shock Omer Saeed
High voltage megger electric shock   Omer SaeedHigh voltage megger electric shock   Omer Saeed
High voltage megger electric shock Omer Saeed
 
ABB switchgear safety hazards passive & active arc fault protection by David ...
ABB switchgear safety hazards passive & active arc fault protection by David ...ABB switchgear safety hazards passive & active arc fault protection by David ...
ABB switchgear safety hazards passive & active arc fault protection by David ...
 
Managing earthing hazards around pole top transformers at mines and quarries ...
Managing earthing hazards around pole top transformers at mines and quarries ...Managing earthing hazards around pole top transformers at mines and quarries ...
Managing earthing hazards around pole top transformers at mines and quarries ...
 
Pd Maintenance
Pd MaintenancePd Maintenance
Pd Maintenance
 
Uninterruptible power supply installations at mines Murray Timpson
Uninterruptible power supply installations at mines  Murray TimpsonUninterruptible power supply installations at mines  Murray Timpson
Uninterruptible power supply installations at mines Murray Timpson
 
Generator grounding
Generator groundingGenerator grounding
Generator grounding
 
Selective Coordination
Selective CoordinationSelective Coordination
Selective Coordination
 
891 Switchboard vs. 1558 Switchgear
891 Switchboard vs. 1558 Switchgear891 Switchboard vs. 1558 Switchgear
891 Switchboard vs. 1558 Switchgear
 
Brett Roberts - Some aspects of electrical power system protection in undergr...
Brett Roberts - Some aspects of electrical power system protection in undergr...Brett Roberts - Some aspects of electrical power system protection in undergr...
Brett Roberts - Some aspects of electrical power system protection in undergr...
 
2015 Arc Flash Conference MV Switchgear Standards
2015 Arc Flash Conference MV Switchgear Standards2015 Arc Flash Conference MV Switchgear Standards
2015 Arc Flash Conference MV Switchgear Standards
 
Optimal Cable Sizing in PV Systems: Case Study
Optimal Cable Sizing in PV Systems: Case StudyOptimal Cable Sizing in PV Systems: Case Study
Optimal Cable Sizing in PV Systems: Case Study
 
Your electrical safety specilist for all equipments Powered AC and DC
Your electrical safety specilist for all equipments   Powered AC and DCYour electrical safety specilist for all equipments   Powered AC and DC
Your electrical safety specilist for all equipments Powered AC and DC
 
Starting First
Starting FirstStarting First
Starting First
 
Electrical Systems Safety
Electrical Systems SafetyElectrical Systems Safety
Electrical Systems Safety
 
Differential protection of power transformer
Differential protection of power transformerDifferential protection of power transformer
Differential protection of power transformer
 
High voltage engineering
High voltage engineeringHigh voltage engineering
High voltage engineering
 

Viewers also liked

Methods to determine the overall health and condition of large power transfor...
Methods to determine the overall health and condition of large power transfor...Methods to determine the overall health and condition of large power transfor...
Methods to determine the overall health and condition of large power transfor...Alexander Decker
 
Combined use of tap-changing transformer and static VAR compensator for enhan...
Combined use of tap-changing transformer and static VAR compensator for enhan...Combined use of tap-changing transformer and static VAR compensator for enhan...
Combined use of tap-changing transformer and static VAR compensator for enhan...ijsrd.com
 
statcom-svc
statcom-svcstatcom-svc
statcom-svcvahidmon
 
D Var Statcom Introduction
D Var Statcom IntroductionD Var Statcom Introduction
D Var Statcom Introductionjohnwrightsmith
 
AMSC D-VAR Solutions 2015
AMSC D-VAR Solutions 2015AMSC D-VAR Solutions 2015
AMSC D-VAR Solutions 2015johnwrightsmith
 
Control and Analysis of VSC Based High Voltage DC Transmission
Control and Analysis of VSC Based High Voltage DC TransmissionControl and Analysis of VSC Based High Voltage DC Transmission
Control and Analysis of VSC Based High Voltage DC Transmissionijsrd.com
 
Report on oltc by Ankit
Report on oltc by AnkitReport on oltc by Ankit
Report on oltc by AnkitAnkit Sisodiya
 
Project on STATCOM
Project on STATCOMProject on STATCOM
Project on STATCOMSutirtha Das
 
On load tap changer in a.c. locomotive transformer &amp; air blast circuit b...
On load tap changer in a.c. locomotive transformer  &amp; air blast circuit b...On load tap changer in a.c. locomotive transformer  &amp; air blast circuit b...
On load tap changer in a.c. locomotive transformer &amp; air blast circuit b...vishalgohel12195
 
TRANSFORMER WINDING DEFORMATION ANALYSIS USING SFRA TECHNIQUE
TRANSFORMER WINDING DEFORMATION ANALYSIS USING SFRA TECHNIQUETRANSFORMER WINDING DEFORMATION ANALYSIS USING SFRA TECHNIQUE
TRANSFORMER WINDING DEFORMATION ANALYSIS USING SFRA TECHNIQUEJournal For Research
 
High frequency induction heating
High frequency induction heatingHigh frequency induction heating
High frequency induction heatingsilviusoft
 
OLTC Function Selection, Operation
OLTC Function Selection, OperationOLTC Function Selection, Operation
OLTC Function Selection, OperationMax Philipp
 
Enhancement of power quality in distribution system by using D-STATCOM
Enhancement of power quality in distribution system by using D-STATCOMEnhancement of power quality in distribution system by using D-STATCOM
Enhancement of power quality in distribution system by using D-STATCOMEng Ahmed Salad Osman
 
Reactive power management and voltage control by using statcom
Reactive power management and voltage control by using statcomReactive power management and voltage control by using statcom
Reactive power management and voltage control by using statcomHussain Ali
 
Analysis and Improved Operation of PEBB Based 5-Level Voltage Source Convert...
Analysis and Improved Operation of PEBB Based 5-Level  Voltage Source Convert...Analysis and Improved Operation of PEBB Based 5-Level  Voltage Source Convert...
Analysis and Improved Operation of PEBB Based 5-Level Voltage Source Convert...IJMER
 

Viewers also liked (20)

Methods to determine the overall health and condition of large power transfor...
Methods to determine the overall health and condition of large power transfor...Methods to determine the overall health and condition of large power transfor...
Methods to determine the overall health and condition of large power transfor...
 
Combined use of tap-changing transformer and static VAR compensator for enhan...
Combined use of tap-changing transformer and static VAR compensator for enhan...Combined use of tap-changing transformer and static VAR compensator for enhan...
Combined use of tap-changing transformer and static VAR compensator for enhan...
 
statcom-svc
statcom-svcstatcom-svc
statcom-svc
 
D Var Statcom Introduction
D Var Statcom IntroductionD Var Statcom Introduction
D Var Statcom Introduction
 
AMSC D-VAR Solutions 2015
AMSC D-VAR Solutions 2015AMSC D-VAR Solutions 2015
AMSC D-VAR Solutions 2015
 
Control and Analysis of VSC Based High Voltage DC Transmission
Control and Analysis of VSC Based High Voltage DC TransmissionControl and Analysis of VSC Based High Voltage DC Transmission
Control and Analysis of VSC Based High Voltage DC Transmission
 
Testing
TestingTesting
Testing
 
Report on oltc by Ankit
Report on oltc by AnkitReport on oltc by Ankit
Report on oltc by Ankit
 
Project on STATCOM
Project on STATCOMProject on STATCOM
Project on STATCOM
 
On load tap changer in a.c. locomotive transformer &amp; air blast circuit b...
On load tap changer in a.c. locomotive transformer  &amp; air blast circuit b...On load tap changer in a.c. locomotive transformer  &amp; air blast circuit b...
On load tap changer in a.c. locomotive transformer &amp; air blast circuit b...
 
TRANSFORMER WINDING DEFORMATION ANALYSIS USING SFRA TECHNIQUE
TRANSFORMER WINDING DEFORMATION ANALYSIS USING SFRA TECHNIQUETRANSFORMER WINDING DEFORMATION ANALYSIS USING SFRA TECHNIQUE
TRANSFORMER WINDING DEFORMATION ANALYSIS USING SFRA TECHNIQUE
 
High frequency induction heating
High frequency induction heatingHigh frequency induction heating
High frequency induction heating
 
OLTC Function Selection, Operation
OLTC Function Selection, OperationOLTC Function Selection, Operation
OLTC Function Selection, Operation
 
Enhancement of power quality in distribution system by using D-STATCOM
Enhancement of power quality in distribution system by using D-STATCOMEnhancement of power quality in distribution system by using D-STATCOM
Enhancement of power quality in distribution system by using D-STATCOM
 
Reactive power management and voltage control by using statcom
Reactive power management and voltage control by using statcomReactive power management and voltage control by using statcom
Reactive power management and voltage control by using statcom
 
Dstatcom
DstatcomDstatcom
Dstatcom
 
Reactive power compensation using statcom
Reactive power compensation using statcomReactive power compensation using statcom
Reactive power compensation using statcom
 
statcom
statcomstatcom
statcom
 
Analysis and Improved Operation of PEBB Based 5-Level Voltage Source Convert...
Analysis and Improved Operation of PEBB Based 5-Level  Voltage Source Convert...Analysis and Improved Operation of PEBB Based 5-Level  Voltage Source Convert...
Analysis and Improved Operation of PEBB Based 5-Level Voltage Source Convert...
 
Statcom
StatcomStatcom
Statcom
 

Similar to Data Center Transformer Failure Due to Circuit Breaker Switching Transients

Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transientsmichaeljmack
 
Chapter 1 Introduction to power Electronic Devices.pdf
Chapter 1 Introduction to power Electronic Devices.pdfChapter 1 Introduction to power Electronic Devices.pdf
Chapter 1 Introduction to power Electronic Devices.pdfLiewChiaPing
 
Principles Control & Protection of HVDC Schemes
Principles Control & Protection of HVDC SchemesPrinciples Control & Protection of HVDC Schemes
Principles Control & Protection of HVDC SchemesPower System Operation
 
Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)FunExplode
 
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.MY PROJECT-automatic load sharing of transformer by using GSM tecnique.
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.nikhilhiware
 
220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptxssuser1b3e431
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transientsmichaeljmack
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxShubhoDas5
 
Power transformers rating
Power transformers ratingPower transformers rating
Power transformers ratingLeonardo ENERGY
 
Thyristors, its types
Thyristors, its typesThyristors, its types
Thyristors, its typesSaleem Ahmed
 
Training from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Training from 220kv GSS Sanganer, which is located on Muhana Road, JaipurTraining from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Training from 220kv GSS Sanganer, which is located on Muhana Road, JaipurR-One Power
 

Similar to Data Center Transformer Failure Due to Circuit Breaker Switching Transients (20)

Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
 
Chapter 1 Introduction to power Electronic Devices.pdf
Chapter 1 Introduction to power Electronic Devices.pdfChapter 1 Introduction to power Electronic Devices.pdf
Chapter 1 Introduction to power Electronic Devices.pdf
 
132 KV GSS CHAMBAL JAIPUR
132 KV GSS CHAMBAL JAIPUR132 KV GSS CHAMBAL JAIPUR
132 KV GSS CHAMBAL JAIPUR
 
Principles Control & Protection of HVDC Schemes
Principles Control & Protection of HVDC SchemesPrinciples Control & Protection of HVDC Schemes
Principles Control & Protection of HVDC Schemes
 
ABB Price List of Capacitors 008
ABB Price List of Capacitors 008ABB Price List of Capacitors 008
ABB Price List of Capacitors 008
 
Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)
 
FAULT ANALYSIS IN HVDC & HVAC TRANSMISSION LINE
FAULT ANALYSIS IN HVDC & HVAC TRANSMISSION LINEFAULT ANALYSIS IN HVDC & HVAC TRANSMISSION LINE
FAULT ANALYSIS IN HVDC & HVAC TRANSMISSION LINE
 
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.MY PROJECT-automatic load sharing of transformer by using GSM tecnique.
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.
 
220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx
 
L2 thyristors
L2 thyristorsL2 thyristors
L2 thyristors
 
Basics of hvdc
Basics of hvdc Basics of hvdc
Basics of hvdc
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptx
 
Power transformers rating
Power transformers ratingPower transformers rating
Power transformers rating
 
IEEE Blue Book
IEEE Blue BookIEEE Blue Book
IEEE Blue Book
 
Thyristors, its types
Thyristors, its typesThyristors, its types
Thyristors, its types
 
kamal project ppt
kamal project pptkamal project ppt
kamal project ppt
 
Hvdc circuit breaker
Hvdc circuit breakerHvdc circuit breaker
Hvdc circuit breaker
 
Training from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Training from 220kv GSS Sanganer, which is located on Muhana Road, JaipurTraining from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
Training from 220kv GSS Sanganer, which is located on Muhana Road, Jaipur
 

More from michaeljmack

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993michaeljmack
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbookmichaeljmack
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbookmichaeljmack
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systemsmichaeljmack
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flashmichaeljmack
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgearmichaeljmack
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrushmichaeljmack
 
Building information modeling
Building information modelingBuilding information modeling
Building information modelingmichaeljmack
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protectionmichaeljmack
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systemsmichaeljmack
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spacesmichaeljmack
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708michaeljmack
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distributionmichaeljmack
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performancemichaeljmack
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulatormichaeljmack
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plantsmichaeljmack
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Storiesmichaeljmack
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Sheddingmichaeljmack
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentalsmichaeljmack
 

More from michaeljmack (20)

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbook
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbook
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgear
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protection
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systems
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spaces
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distribution
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performance
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulator
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plants
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Stories
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentals
 

Recently uploaded

Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 

Recently uploaded (20)

Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 

Data Center Transformer Failure Due to Circuit Breaker Switching Transients

  • 1. Transformer Failure Due to Circuit Breaker Induced Switching Transients Part 1: Case Study Overview David D. Shipp, PE Fellow, IEEE Eaton Electrical Group 130 Commonwealth Dr. Warrendale, PA 15086 Thomas J. Dionise, PE Senior Member, IEEE Eaton Electrical Group 130 Commonwealth Dr. Warrendale, PA 15086 Case Study Overview: Data Center Transformer Failure Attributed to Circuit Breaker Induced Switching Transients System Configuration, Failure Analysis and RC Snubber Fix R. McFadden – JB&B – NY, NY D. Shipp – Eaton Electrical – Pgh, PA
  • 2. Presentation Purpose/Summary • Purpose #1 Safety: – Alert Design & User Community – Drive Solutions Through Market Interest • Unique Case History – Forensic Evidence – High Speed Power Quality Capture • Presentation Summary – Simplified System Overview – Forensic Review – Power Quality Snapshots – Installed RC Snubber Fix • Presentation Summary: David Shipp, Eaton – Phenomenon Detailed Explanation – Science of RC Snubber Design Site Specifics • Utility Service: – 26kV – Double Ended Loop Through • Transformers – (6) Total – 26kV Primary, 480V Secondary – VPI – 3000kVA AA / 3990 kVA FA – 150 kVbil • Switching Device – Vacuum Circuit Breaker • Cable – 35kV, 133% EPR Insulation, 1/3 Concentric Ground
  • 3. M T-A3 CRACs Chillers T-A2 UPS T-A1 OTHER 40’ 80’ 100’+ 26kv Utility “A” To Normal Side Of 480vac ATS (Typical) M T-B3 CRACs Chillers T-B2 UPS T-B1 OTHER 40’ 80’ 100’+ 26kv Utility “B” Simplified System Configuration Failure/Sequence of Events • All Transformers Fully Tested: • Pre-functional: Turns Ratio, Insulation Resistance, etc • Functional:UPS Full Load Tests, UPS Transient Tests, Data Center Room Validation Testing • Final Pull The Plug Test (PTP) • 4 Electricians “simultaneously” open (4) 26KV vacuum breakers to simulate a general utility outage. • All systems successfully transfer to standby generation but: • Loud Pop heard in Substation Room B • Relay for VCB feeding TB3 signaling trip • Decision made to shutdown generator test and investigate issue in “B” substation room • 2 Electricians “simultaneously” close (2) 26KV vacuum breakers to Substation Room “A” • Transformer TA3 fails catastrophically.
  • 4. M T-A3 CRACs Chillers T-A2 UPS T-A1 OTHER 40’ 80’ 100’+ 26kv Utility “A” 0.8MW M T-B3 CRACs Chillers T-B2 UPS T-B1 OTHER 40’ 80’ 100’+ 26kv Utility “B” Pre-PTP Condition 1.5MW 0.9MW 1.3MW M T-A3 CRACs Chillers T-A2 UPS T-A1 OTHER 40’ 80’ 100’+ 26kv Utility “A” M T-B3 CRACs Chillers T-B2 UPS T-B1 OTHER 40’ 80’ 100’+ 26kv Utility “B” Failure #1: De-Energization During PTP Audible Pop In Substation Room Relay Signaling Trip
  • 5. M T-A3 CRACs Chillers T-A2 UPS T-A1 OTHER 40’ 80’ 100’+ 26kv Utility “A” M T-B3 CRACs Chillers T-B2 UPS T-B1 OTHER 40’ 80’ 100’+ 26kv Utility “B” Failure #2: Energization During PTP Catastrophic Failure Relay Trips VCB Coil to Coil Tap Burnt Off Failure #2 Transformer Failure On Energization
  • 6. Coil to Coil Conductor Burnt Off Suspected Area of Initial Flash Failure #2 Transformer Failure On Energization Coil to Coil Tap Burnt Off Failure #2 Transformer Failure On Energization
  • 7. Coil to Coil Tap Burnt Off Upward Twist From Lower Blast Failure #2 Transformer Failure On Energization Flash/Burn Marks Failure #1 Transformer Failure On De-Energization
  • 8. Close up of Flash/Burn Marks Coil to Coil not Winding to Winding Failure #1 Transformer Failure On De-Energization This Transformer was Returned to the Factory and Passed all Standard IEEE Tests! This Transformer was Returned to the Factory and Passed all Standard IEEE Tests! No Coil to Coil Cable Supports Some Burn Marks Match Point of Cable Contact 15KV Cable In 26KV Transformer Failure #1 Transformer Failure On De-Energization
  • 9. Some Burn Marks Match Vicinity of Cable Cable is Undamaged Failure #1 Transformer Failure On De-Energization Factory Installed Cable Support Unaffected Transformer
  • 10. Current Transient: Failure #2 Transformer Energization Event Initiated A-B Phase 19,000 amp, 3 Phase 5 Cycle CB Clearing Time Second Transformer Inrush AØ BØ CØ AØ BØ CØ Current Transient: Failure #1 Transformer DeEnergization 8000amp A-B Phase Approx ¼ Cycle C Phase Shows 2nd Xfmr Load & Event Duration
  • 11. Breaker Induced Switching Transients Case 1 Hydro Dam, MT 2005 • MV Vac Bkr Replacements Vendor “A” • 13.8 kV • 20 feet of cable • 50 kV BIL (W) ASL Dry Type Txmrs • Customer Energized before Vendor OK • Txmr Failed • No Surge Protection Applied
  • 12. CASE 2 Cleveland Hospital 3/06 • Vacuum Breakers – Vendor “A” and Vendor “C” • 13.8 kV • 95 kV BIL • Dry Type Txmr • 27 feet of Cable • Bkr Manufacturer Paid to Repair Failed 2500 KVA Txmr • Surge Protection Added Afterwards CASE 3 RAILROAD SUBSTATION 11/06 • Vacuum Breaker – Vendor “A” • 26.4 kV • 150 kV BIL • Generic Liquid Filled Rectifier Txmr • 37 feet of Cable
  • 13. CASE 4 NJ DATA CENTER 12/06 • 26.4 kV – Vendor “B” • 4 Txmrs Switched Under Light Load • 2 Txmrs Failed-1 on Closing/1 on Opening • 40 Feet of Cable • 2 other Txmrs Did Not Fail - 80 Feet of Cable • Arresters Were Present CASE 5 OIL FIELD – AFRICA 6/07 • Vacuum Breaker – Vendor “D” • 33 kV • 7 Feet of Cable • Dry Type Txmr in 36 Pulse VSD • Arresters Were Applied • Txmr Failed Upon Energization
  • 14. CASE 9 Oil Drilling Ship – 6/2002 • Vendor “A” IEC Vac Bkrs in Vendor “D” Swgr • 11kV, 60 HZ • Cast Coil Dry Type IEC VSD Propulsion Txmr Failed (7500 kVA) – 75 kV BIL? • < 30 feet of Cable • Fed from Alternate Bus – Now 80 feet of Cable • No further Failures Reported CASE 11 Hospital – Slide 1 • 13. 8 kV System • Vendor C Breakers/ Vendor F Txmrs • 2 Txmrs Failed During Commissioning • Differential Relay Tripped During motor Starting – under Highly Inductive Load
  • 15. CASE 11 Hospital – Slide 2 CASE 11 Hospital – Slide 3
  • 16. CASE 12 Motor Starter Auto Txmr Failure • 4160V • 5000 HP • Reduced Voltage Auto Txmr Failed • Arresters on Wye Point • Internal Resonance • Layer Wound • Failed Layer to Layer CASE 12 Run Contactor Closes 3516 HZ
  • 17. CASE 12 - Sweep Frequency Test 4500 HZ (Admittance) CASE 12 - Run Contactor Closes – 844 HZ With Snubber
  • 18. SWITCHING TRANSIENTS DUE TO VACUUM / SF6 BREAKERS • Opening -- Current Chop • Closing -- Prestrike/Re-ignition/Voltage Escalation • Vacuum Bkrs --Both Closing and Opening • SF6 -- Opening • Air -- Generally Acceptable Current Chop
  • 19. Current Chop Current Chop in Vacuum is a Material Problem Current Chop • All Types of Interrupters Chop Current • This is not a Unique Feature of Vacuum
  • 20. Switching Inductive Circuits • Closing • Opening • Voltage Escalation • Surge Suppression Switching Inductive Loads CLOSING
  • 21. Switching Inductive Loads OPENING Switching Inductive Loads VOLTAGE ESCALATION
  • 22. SWITCHING TRANSIENT THEORY • “Thou Shalt Not Change Current Instantaneously in an Inductor” • Conservation of Energy – – You Cannot Create or destroy Energy – You Can Only Change Its Form ENERGY EQUATION 22 2 1 2 1 CVLI  OR C L IV 
  • 23. TOTAL VOLTAGE • Vt = Venergy + Vdc + Vosc • Venergy is from the Energy Equation • Vdc = DC Off-set that Sometimes is Present • Vosc = the Oscillatory Ring Wave TRANSFORMER LIMITS • Magnitude – BIL Ratings • Dv/dt Limits • Both MUST Be Met • Dry Type Txmrs Particularly Susceptable • Liquid Filled Not Immune. • Consider “Hammer Effect”
  • 24. ANALYSIS • When Open Bkr, Txmr is Left Ungrounded • Ring Wave is a Function of its Natural Frequency LC NF 2 1  CASE 3 Waveforms Without Snubbers
  • 25. CASE 3 Current – Without Snubbers Ichop CASE 3 Waveforms With Snubbers
  • 26. CASE 4 Data Center 12/06 • 26.4 kV • Vendor “B” Breakers • 4 Bkrs Switched at Once • 2 Dry Type Txmrs Failed (40 Ft of Cable) • 2 Txmrs Did not Fail (80 Ft of Cable) • Unfaulted Txmr Winding Failed BIL @162 kV ( Rated 150 kV) CASE 4 Data Center, NJ 12/06 - W/O Snubbers 08-Jan-07 14.53.47 0 5 10 15 20 25 -200 -150 -100 -50 0 50 100 150 200 v [kV] t [ms](42) XFMA3C (48) XFMB3C Plot of the Transformer A3 and B3 primary voltage Phase C Open circuit breaker with chopped current of 9 Amperes -207 kV
  • 27. CASE 4 Data Center, NJ 12/06-With Snubbers 09-Jan-07 10.50.25 0 5 10 15 20 25 -40 -30 -20 -10 0 10 20 30 40 v [kV] t [ms](29) XFMA3B (35) XFMB3B Plot of the Transformer A3 and B3 primary voltage Phase B Open circuit breaker with chopped current of 9 Amperes Application of the R-C snubber circuit -39 kV CASE 6 Data Center 2, NJ 12/06 • 13.2 kV • Vendor “B” Breakers • 3 MVA Dry Type Txmrs • 60 ft Cable – Required Snubbers • 157 ft Cable – Required Snubbers • No Problem at Startup
  • 28. CASE 6 13.2 kV SYSTEM – 119 kV @ 678 HZ CASE 6 WITH SNUBBERS – 33.6 kV @ 236 HZ
  • 29. CASE 7 Chemical Plant, NC 3/07 • 12.47 kV System • 20+ Year Old Oil Filled Txmrs • Vendor “A” Vacuum Bkrs retrofitted on Primary • 10 Feet of Cable • No Problem at Startup CASE 7 425 kV - 12. 47 kV - 23 kHZ Ring Wave
  • 30. CASE 7 Added Snubbers – 12.47 kV CASE 8 DATA CENTER – Indiana 6/07 • 12.47 kV System • Vendor “A” Breakers • 270 Feet of Cable • No Additional Surge Protection Required
  • 31. CASE 8 -55 kV at 800 HZ CASE 11 Hospital 186.9 kV / 2000 HZ
  • 32. CASE 10 – Snubber Reduced to 33.8 kV / 368 HZ MITIGATING TECHNIQUES • Arresters • Surge Capacitors • Snubbers (RC) • Hybrid / Combinations • Liquid vs Dry Type • Electronic Zero Crossing Switching
  • 33. Snubber - 3 Phase Capacitor Generally Solidly Grounded System • Paper Mill - AL • 13.8 kV Snubbers – 2nd paper mill - beta site
  • 34. Snubber – Single Phase Capacitors Low Resistance Grounded Systems • Paper Mill • Vendor “A” Swgr • 13.8 kV Snubber – Single Phase Capacitors • Silicon “Chip” Plant • Montana • Very Specialized Dry Type Txmrs • 13.8 kV • Cables < 100 feet • Primary Fused Switch AF Solution • Vendor “A” Vac Bkrs
  • 35. Capacitor Resistor Fuse Lightning Arrestor Blown Fuse Viewing Window RC Snubber Installed – Case 4 RC Snubber Installed – Case 4 Capacitor Resistor
  • 36. RC Snubber Installed – Case 4 Fuse Blown Fuse Indicator SWITCHING TRANSIENT STUDY • Quantifies Problem • Predict Exposure / Risk • Select Best / Most Cost Effective Solution • Do “What if” Cases • Verify Results
  • 37. RECOMMENDATIONS • Factor into Design Up-front • Do Study – Results Are Bkr Manufacturer Specific • Use Protection Only When / Where Needed (if not there, cannot fail) • Fused or Unfused Snubbers?? • Loss of Fuse Detection?? • Fear Not! - Mitigating Techniques Have Been Proven. • Discrete Snubber Components?? Conclusion/Next Steps • This is a System Problem – Transformer, Cable, Switching Device, Proximity – Statistical Event , Possible Undetected Failures • Data Centers Fall into the Highest Risk Category – High Power Density – Close Proximities – Frequent Switching • Draft IEEE C57.142 – A Guide To Describe The Occurrence and Mitigation Of Switching Transients Induced By Transformer And Switching Device Interaction – Does not accurately warn users of all areas of concern – This case did not meet the areas of concern noted in Draft C57.142 – Need to push for formalization of the standard with new lessons learned • RC Snubbers – Transformer Manufacturer appears best positioned to implement the solution – Limited Cataloged Product (One Manufacturer) – Not embraced by all transformer manufacturers – Design Parameters of RC Snubber not clearly defined • Lives, Property and Uptime are all at risk