SlideShare a Scribd company logo
1 of 206
Download to read offline
EA Technology Partial Discharge Forum 26 03 2015
Partial Discharge monitoring of HV assets
- experience from Tata Steel site, Scunthorpe.
Highlighting defects with specific switchgear which led to Partial Discharge, and the methods
implemented to manage these assets.
Mikolaj Kukawski MIET
Customer Networks Manager
ESM Power
Content of presentation
• My background
• TATA Steel HV Distribution Network
• Integrated Steelworks Processes
• Partial Discharge Case Studies (14)
• Special thanks and questions
My background
Education:
• 2001-2006 - University of Lublin, Poland
- Master’s degree in Electrical Engineering – Power Systems
Work experience:
• 2006-2007 - Elektromontaz Lublin, Poland
- Design Engineer for MV Switchgear Manufacturer – 1 year
• 2007-2008 - Corus Power & Distribution (P&D), Scunthorpe, UK
- HV Electrician Team Member – 18 months
My background
Work experience:
• 2008-2014 - Corus / TATA Steel P&D, Scunthorpe, UK
- Distribution Engineer - 6 years
• 2014 Dec - currently - ESM Power, Scunthorpe, UK
- Customer Networks Manager
Integrated Steelworks HV Distribution Network
Integrated Steelworks 33kV Distribution Network Block Diagram
Integrated Steelworks 33kV Distribution Network Block Diagram
Integrated Steelworks Site Map showing 12 main plants
TATA STEEL Integrated Steelworks - Scunthorpe Site
Integrated Steelworks Process Block Diagram
Integrated Steelworks Process Block Diagram
Immingham
Bulk
Terminal
Immingham Bulk
Terminal
Unloading iron ore
from the ship
A train with coal wagons
unloads at Dawes Lane
Coal Handling Plant
A train with Iron Ore arrives at Scunthorpe Ore Blending Plant
Blending
the various
iron ores
and lime
Sinter
Plant
Coolers
Coal stocks
at the Coal
Handling
Plant
Pushing
a coke
oven
Blast Furnaces
also known as
The Four Queens:
– Mary, Bess,
Anne & Victoria
Queen Bess blast
furnace casting
Molten iron is
transported to
Steelmaking Plant
using torpedo wagons
Molten iron is
transported to
Steelmaking Plant
using torpedo wagons
Charging molten iron
into BOS converter
Charging scrap into
BOS converter
Ladle Arc Furnace -
secondary steelmaking
Twin strand bloom
caster tundish
8 strand Billet Caster
A pack of billets
on the BBM
cooling bank
Bloom Caster 4
Slab Caster
A slab leaves the
Plate Mill reheater
furnace
Rolling plate at
Heavy Plate Mill
Plate cooling bank
at Heavy Plate Mill
Scunthorpe Rod Mill
Laying head at
Scunthorpe Rod Mill
Scunthorpe
Rail and
Section Mill
Area 3
also known as
Rail Service
Centre
Partial Discharge Case Studies
1 - Central Power Station 33 kV Substation
2 - Central Power Station 3.3 kV
3 - Blast Furnaces 11 kV
4 - Bloom Mill 11 kV
5 - BOS Waste Gas Recovery 11 kV
6 - Ore Blending Plant Main 11 kV
7 - Blast Furnaces No. 2 6.6 kV
8 - BOS Waste Gas Recovery 11 kV Busbar Outage
9 - Heavy Section Mill to Scunthorpe Rod Mill 33 kV Interconnector Reactor Terminations
10 - Broughton to Seraphim 33 kV Interconnector
11 - Seraphim 33 kV Reyrolle L42T VT
12 - CONCAST Water Treatment Plant 11 kV GEC BVP 17 Busbar
13 - Heavy Plate Mill Roughing Mill Transformer Cast Resin Transformer 33 kV
14 - Bloom Caster 11 kV
Partial Discharge Monitor
Integrated Steelworks HV Distribution Network
Integrated Steelworks HV Distribution Network
Case Study 1 - Central Power Station 33 kV Substation
Affected Asset details:
1. Equipment Circuit VT
2. Make Reyrolle
3. Model L800T
4. Operating voltage 33kV
5. Number of panels 13 (Section 3 only 2 circuits)
6. Age 40 years
Reyrolle L800T 33kV Switchgear
(single busbar system) cross
section drawing
Reyrolle L800T 33kV Switchgear
(single busbar system) cross
section drawing
CPS 33kV
Substation
Reyrolle
L800T
33kV
Switchgear
CPS 33kV Substation Reyrolle
L800T 33kV Switchgear –
Section 3
Case Study 1 - Central Power Station 33 kV Substation
Investigation details:
1. Partial discharge initial detection method - CPS power controller detected red TEV
using hand held UltraTEV detector during daily substation checks – informed duty
engineer
2. Follow up investigation method – Distribution Engineer and Team Leader joint
investigation using UltraTEV +. Switchboard tested Left to Right, Front to Rear and
Top to Bottom. Conclusion: On the circuit: 33/11kV 12/24MVA Transformer No.3 (T3)
the higher the measurement was taken the higher the TEV reading was (up to 50dB).
Decided to test Circuit VT located on the top of the switchgear. Confirmed that the
TEV reading was even higher (60dB).
3. Action taken - decided to isolate T3 circuit
T3 circuit VT
fixed portion L2
(yellow) phase
spout
T3 circuit VT
fixed portion L2
(yellow) phase
spout
T3 circuit VT
moving portion
L1 and L2
(red and yellow)
phases spouts
T3 circuit VT
moving portion
L2 and L3
(yellow and blue)
phases spouts
T3 circuit VT
moving portion
L2 (yellow) phase
spout
T3 circuit VT
moving portion
L2 (yellow) phase
spout
T3 circuit VT
moving portion
L2 (yellow)
phase spout
Case Study 1 - Central Power Station 33 kV Substation
Outage requirement to enable investigation and repair
1. Equipment Section 3 bus bars at CPS 33kV, CPS 33/11kV 12/24MVA
Transformer No.3 circuit, CPS to HPM 33kV Interconnector
2. Timescale 2 hours on the T3 circuit, 15 minutes HPM stopped rolling to
enable T3 33kV OCB re-closure without its circuit VT.
Case Study 1 - Central Power Station 33 kV Substation
Actions taken to rectify the fault
1. Resources Investigation TATA, Siemens for VT repair
2. Discharge elimination Circuit VT withdrawn,
3. Repair method Cracked VT bushing to be replaced
4. Estimated cost of repair circa £ 10k
Has PD activity stopped? YES – TEV level went back to green
Possible cause of partial discharge VT Bushing damaged during installation
Loss estimation in worst case scenario:
Circa £ 200k for 2 33kV switchgear panels replacement and potentially HPM production loss and
internal generation limited due to 1 of 3 33/11kV transformers outage.
Case Study 2 - Central Power Station 3.3 kV
Affected Asset details:
1. Equipment Single core 3.3kV unarmoured cable
2. Make GEC
3. Model BTVP17 and HMC
4. Operating voltage 3.3kV
5. Number of panels 15
6. Age 40 years
GEC BTVP17 3.3kV Switchgear
(double busbar system) cross section
drawing
GEC BTVP17 3.3kV Switchgear
(double busbar system) cross section
drawing
CPS 3.3kV
Substation GEC
BTVP17 3.3kV
Switchgear
(rear view)
Case Study 2 - Central Power Station 3.3 kV
Investigation details:
1. Partial discharge initial detection method - CPS power controller detected red TEV on
Incomer from 5MVA No.1 Transformer using hand held UltraTEV detector during daily
substation checks – informed duty engineer
2. Follow up investigation method – Distribution Engineer investigated the switchboard using
UltraTEV +. Switchboard tested Left to Right, Front to Rear and Top to Bottom. Conclusion:
On the Incomer No.1 circuit the lower the measurement was taken the higher the TEV
reading was (up to 44dB). Decided to Inspect cable box. No evidence of Partial Discharge
found. Tested switchboard Using Partial Discharge Monitor. Tested switchboard again using
UltraTEV + and realised that that the TEV reading was even higher on the bottom of cable
box support channel – near the floor (60dB). Question asked: What is underneath the
substation? It turned out to be mezzanine floor with cables installed on metal trays system.
Found one core stuck against metal support construction channel with signs of partial
discharge.
CPS 3.3kV
Substation GEC
BTVP17 3.3kV
Switchgear
(Incomer from
5MVA No.1
Transformer -
cable box
inspection)
Case Study 2 - Central Power Station 3.3 kV
Investigation details:
3. Action taken – Circuit isolated, tested IR of the cable – 4 Mega Ohms - asked
experienced jointer for advice – suggested using triple layer of HV heat shrink
tape around damaged area of the cable. Cable repaired. Circuit reenergised. TEV
levels dropped down to 30dB at the repair point and down to 27 dB above the
repair point, investigated further the cable route – found cables tightened with
twisted steel wire armouring to form two trefoil formations (instead of using
proper trefoil cleats). Steel wire armouring is cutting through PVC insulation of
unarmoured cables on the majority of the cable routes. Decided to replace all
3.3kV cables for both No.1 and No.2 5MVA Transformers Incomers.
CPS 3.3kV
Substation
mezzanine floor
(Incomer from
5MVA No.1
Transformer -
Single core
unarmoured
cables)
CPS 3.3kV
Substation
mezzanine floor
(Incomer from
5MVA No.1
Transformer -
Single core
unarmoured
cables)
CPS 3.3kV
Substation
mezzanine floor
(Incomer from
5MVA No.1
Transformer -
Single core
unarmoured
cables)
CPS 3.3kV
Substation
mezzanine floor
(Incomer from
5MVA No.1
Transformer -
Single core
unarmoured cable
repaired)
CPS 3.3kV Substation mezzanine floor
(Incomer from 5MVA No.1 Transformer -
Single core unarmoured cable repaired –
TEV level dropped to 30dB)
CPS 3.3kV Substation mezzanine floor
(Incomer from 5MVA No.1 Transformer -
Single core unarmoured cable repaired –
TEV level dropped to 27dB above repair
point)
CPS 3.3kV Substation mezzanine floor
(Incomer from 5MVA No.1 Transformer
- Single core unarmoured cable
repaired – TEV level dropped to 30dB)
Single core
unarmoured cables
tightened with
twisted steel wire
armourings
Original cable schedule dated 1974 showing the type and route of the cables
Case Study 2 - Central Power Station 3.3 kV
Outage requirement to enable investigation and repair
1. Equipment No.1 5MVA 11/3.3kV Transformer at CPS 3.3kV,
2. Timescale 6 hours for the cable box inspection, 4 hours for cable repair
Case Study 2 - Central Power Station 3.3 kV
Actions taken to rectify the fault
1. Resources Investigation TATA, SPEC for cable repair
2. Discharge elimination Cable replacement,
3. Repair method New cables installation with correct trefoil cleats
4. Estimated cost of repair circa £ 20k
Has PD activity stopped? NO – however TEV level reduced to amber level on the
switchboard
Possible cause of partial discharge Cable damaged due to incorrect installation method
Loss estimation in worst case scenario:
Potentially loss of internal generation since 3.3kV switchboard feeds auxiliary equipment essential for
steam raising processes. Possible knock on effect on process steam system for the whole site.
Case Study 3 - Blast Furnaces 11 kV
Affected Asset details:
1. Equipment Vacuum Circuit Breakers (VCB)
2. Make GEC
3. Model VMX
4. Operating voltage 11kV
5. Number of panels 19 (5 VCB’s affected)
6. Age 26 years
GEC VMX 11kV Switchgear
(single busbar system)
cross section drawing
GEC VMX 11kV Switchgear
(single busbar system)
cross section drawing
GEC VMX 11kV Switchgear
(single busbar system)
cross section drawing
GEC VMX 11kV
Vacuum Circuit Breaker (VCB)
cross section drawing
GEC VMX 11kV
Vacuum Circuit Breaker (VCB)
cross section drawing
Blast Furnaces
11 kV Substation
GEC VMX 11kV
Switchgear
(single busbar
system)
Case Study 3 - Blast Furnaces 11 kV
Investigation details:
1. Partial discharge initial detection method – TATA Steel Power and Distribution
craftsmen detected red TEV using hand held UltraTEV detector during weekly
substation checks – informed duty engineer
2. Follow up investigation method – Distribution Engineer investigated switchboard
using UltraTEV +. Switchboard tested Left to Right, Front to Rear and Top to Bottom.
Conclusion: On the circuit: 33/11kV 12/24MVA Transformer Incomer No.1 the
highest TEV level measured was at the front of VCB (up to 40dB). In conjunction with
BF Engineers decided to take the suspected VCB out of service.
3. Action taken – Incomer No.1 VCB isolated and retested the switchboard with
UltraTEV + - TEV level back to green
Incomer No.1 GEC VMX
11kV VCB L2 (yellow phase)
front isolating contact
front – busbar,
rear - circuit
Incomer No.1 GEC VMX 11kV VCB L2 (yellow phase) front isolating contact
New VMX unit for Incomer No.1 - showing L2 (yellow phase) front isolating contact
Case Study 3 - Blast Furnaces 11 kV
Outage requirement to enable investigation and repair
1. Equipment Incomer No.1 from 33/11kV 12/24MVA Transformer circuit
2. Timescale 2 hours to replace VCB with the new or refurbished unit from
Schneider
Case Study 3 - Blast Furnaces 11 kV
Actions taken to rectify the fault
1. Resources Investigation TATA, new or refurbished VMX unit – Schneider
2. Discharge elimination VMX VCB replacement,
3. Repair method VMX body moulding replaced and ball bearing added to the
drive shaft
Estimated cost of repair VMX refurbishment circa £ 5k, new VMX unit circa £ 14k
Has PD activity stopped? Yes
Possible cause of partial discharge – partial discharge possibly due to continuous charging and
discharging of unearthed metal drive shaft which goes through the middle of VMX body
moulding.
Loss estimation in worst case scenario:
Potentially loss of production on crucial iron making plant since 11kV switchboard feeds
charging side of all four blast furnaces essential for iron making processes. Possible site-wide
knock on effect including steelmaking and mills.
Other VMX circuit breakers affected by partial discharge – bus section
Other VMX circuit breakers affected by partial discharge – bus section
Other VMX
circuit breakers
affected by
partial discharge
– Queen Anne
2MVA No.2
Transformer
VCB
Other VMX
circuit breakers
affected by
partial discharge
– Queen Anne
2MVA No.2
Transformer
VCB
Other VMX circuit
breakers affected by
partial discharge –
Substation Auxiliary
2MVA Transformer
No.2 VCB
Other VMX circuit breakers affected by partial discharge – incomer No.2
Other VMX circuit breakers
affected by partial discharge
– incomer No.2
Case Study 4 - Bloom Mill 11 kV
Affected Asset details:
1. Equipment Busbar Voltage Transformer (VT)
2. Make GEC
3. Model BVP17
4. Operating voltage 11kV
5. Number of panels 16 (Section 2 Busbar VT affected)
6. Age 45 years
Bloom Mill 11kV
Substation GEC BVP17
11kV Switchgear
(single busbar system)
- showing Section 2 of
the switchboard
isolated and Section 2
busbars earthed
GEC BVP17
VT cross
section
drawing
– showing
indentation
in the rail to
prevent VT
movement
whilst in
service
position
GEC BVP17
VT cross
section
drawing
– showing
indentation
in the rail to
prevent VT
movement
whilst in
service
position
Bloom Mill 11kV
Section 2 Busbar VT
Bloom Mill 11kV
Section 2 Busbar VT
Bloom Mill 11kV
Section 2 Busbar VT
Bloom Mill 11kV
Section 2 Busbar VT
Bloom Mill 11kV
Section 2 Busbar VT
Case Study 4 - Bloom Mill 11 kV
Investigation details:
1. Partial discharge initial detection method – BBM engineer informed duty engineer
about audible discharge in Section 2 Switchroom of Bloom Mill 11kV Substation.
2. Follow up investigation method – Distribution Engineer arrived on site and located
the discharge near Section 2 Busbar VT.
3. Action taken - decided to isolate suspected Section 2 Busbar VT
Case Study 5 - BOS Waste Gas Recovery 11 kV
Affected Asset details:
1. Equipment Vacuum Circuit Breakers (VCB)
2. Make GEC
3. Model VMX
4. Operating voltage 11kV
5. Number of panels 9 (5 VCB’s affected)
6. Age 26 years
BOS Waste Gas Recovery 11 kV
Substation - bus section GEC
VMX VCB L2 (yellow phase)
front isolating contact
Bus section GEC VMX 11kV VCB L2 (yellow phase) front isolating contact
Other VMX
circuit breakers
affected by
partial discharge
– Incomer No.2
Other VMX
circuit breakers
affected by
partial discharge
– Incomer No.2
Other VMX
circuit breakers
affected by
partial discharge
– Incomer No.2
Other VMX
circuit breakers
affected by
partial discharge
– Incomer No.2
Other VMX
circuit breakers
affected by
partial discharge
– Incomer No.2
Other VMX
circuit breakers
affected by
partial discharge
– Incomer No.2
Case Study 6 - Ore Blending Plant Main 11 kV
Affected Asset details:
1. Equipment Current Transformers (CT’s)
2. Make GEC
3. Model BVP17
4. Operating voltage 11kV
5. Number of panels 6 (1 OCB panel circuit chamber affected)
6. Age 27 years
GEC BVP17 11kV Switchgear (single busbar system) cross section drawing
Ore Blending Plant
Main 11 kV
Substation
Ore Blending Plant
Main 11 kV
Substation
Incomer No.1 CT’s
affected by partial
discharge
Ore Blending Plant Main 11 kV Substation Incomer No.1 CT’s
affected by partial discharge
Case Study 6 - Ore Blending Plant Main 11 kV
Actions taken to rectify the fault
1. Resources Investigation TATA, CT’s & bushings repairs – Schneider
2. Discharge elimination Incomer No.1 circuit isolated
3. Repair method CT’s removed, repaired and fitted by OEM
Estimated cost of repair CT’s repairs: labour circa £ 8k, materials circa £ 2.5k
Has PD activity stopped? Yes
Possible cause of partial discharge – partial discharge possibly due to broken CT’s earth
clamps. It is likely that high humidity within substation was a contributing factor.
Loss estimation in worst case scenario:
Potential loss of production on Ore Blending Plant – crucial for Sinter making process.
Possible site-wide knock on effect including ironmaking, steelmaking and mills.
Case Study 7 - Blast Furnaces No. 2 6.6 kV
Affected Asset details:
1. Equipment Cable terminations
2. Make Brush
3. Model VMVD
4. Operating voltage 6.6kV
5. Number of panels 23 (2 VCB panels cable terminations affected)
6. Age 25 years
Brush VMVD 6.6kV
(double busbar system)
cross section drawing
Brush VMVD 6.6kV
(double busbar system)
cross section drawing
Brush VMVD 6.6kV substandard cable terminations
Brush VMVD 6.6kV -substandard cable terminations
Brush VMVD 6.6kV
new cable terminations
Case Study 7 - Blast Furnaces No. 2 6.6 kV
Actions taken to rectify the fault
1. Resources Investigation TATA, cable terminations repairs – SPEC
2. Discharge elimination 2 circuits isolated
3. Repair method cable terminations removed, cables cut, jointed new
pieces of cable in the basement and terminated with
Raychem heat shrink termination kits
Estimated cost of repair new cables, joints and terminations circa £ 7k
Has PD activity stopped? Yes
Possible cause of partial discharge – partial discharge possibly due to substandard cable
terminations.
Loss estimation in worst case scenario:
Potential loss of production on ironmaking. Possible site-wide knock on effect including
steelmaking and mills.
Air Cooled Transformer Partial Discharge in the substation next door
Air Cooled Transformer Partial Discharge in the substation next door
Air Cooled Transformer Partial Discharge in the substation next door
Air Cooled Transformer Partial Discharge in the substation next door
Air Cooled Transformer Partial Discharge in the substation next door
Air Cooled Transformer Partial Discharge in the substation next door
Case Study 8 - BOS Waste Gas Recovery 11 kV Busbar Outage
Affected Asset details:
1. Equipment Air insulated busbars
2. Make GEC
3. Model VMX
4. Operating voltage 11kV
5. Number of panels 9
6. Age 26 years
GEC VMX 11kV Switchgear
(single busbar system)
cross section drawing
GEC VMX 11kV
Switchgear
(single busbar system)
2 Section switchboard
View from the top
- showing busbars
arrangement
Section 1 Section 2
GEC VMX 11kV
Switchgear
(single busbar system)
2 Section switchboard
View from the top
- showing busbars
arrangement
Section 1 Section 2
BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
Case Study 9 - Heavy Section Mill to Scunthorpe Rod Mill 33 kV
Interconnector Reactor Terminations
Affected Asset details:
1. Equipment 33kV cable terminations inside air cable box of reactor
2. Make Yorkshire Electric Transformer Company Ltd.
3. Model 21 MVA to British Standard Specification 171/1956
4. Operating voltage 33kV
5. Number of panels N/A
6. Age 41 years (refurbished by SPEC in 2006)
Blast Furnace to Scunthorpe Rod Mill 33 kV Interconnector Reactor
Blast Furnace to Scunthorpe Rod Mill 33 kV Interconnector Reactor
Heavy Section Mill to Scunthorpe Rod Mill 33 kV Interconnector Reactor Terminations
Heavy Section Mill to Scunthorpe Rod Mill
33 kV Interconnector Reactor Terminations
Heavy Section Mill to
Scunthorpe Rod Mill
33 kV Interconnector
Reactor Terminations
Heavy Section Mill to Scunthorpe
Rod Mill 33 kV Interconnector
Reactor Terminations
Heavy Section Mill to
Scunthorpe Rod Mill
33 kV Interconnector
Reactor Terminations
Heavy Section Mill to
Scunthorpe Rod Mill 33 kV
Interconnector Reactor
Terminations
Case Study 9 - Heavy Section Mill to Scunthorpe Rod Mill 33 kV
Interconnector Reactor Terminations
Actions taken to rectify the fault
1. Resources Investigation TATA, cable terminations repairs – SPEC
2. Discharge elimination 33kV Interconnector circuit isolated
3. Repair method cables re-terminated
Estimated cost of repair new terminations circa £ 7k
Has PD activity stopped? Yes
Possible cause of partial discharge – partial discharge possibly due to substandard cable
terminations (i.e. clearances between termination sheds not sufficient)
Loss estimation in worst case scenario:
Security of site power supplies compromised – SRM down to 3 out of 4 Interconnectors.
Blast Furnace to Rod Mill 33 kV Interconnector Reactor Cable Terminations Failure
Blast Furnace to Rod Mill 33 kV Interconnector Reactor Cable Terminations Failure
Blast Furnace to Rod Mill 33 kV Interconnector Reactor Cable Terminations Partial Discharge
Blast Furnace to Rod Mill 33 kV Interconnector Reactor Cable Terminations Partial Discharge
Case Study 10 - Broughton to Seraphim 33 kV Interconnector VT and
Case Study 11 - Seraphim to BF Interconnector VT
Affected Asset details:
1. Equipment Circuit VT
2. Make Reyrolle
3. Model L42T
4. Operating voltage 33kV
5. Number of panels 23
6. Age circa 40 years
Reyrolle L42T 33kV Switchgear
(single busbar system) cross
section drawing
Broughton to Seraphim 33 kV Interconnector
Reyrolle L42T 33kV Switchgear
Circuit VT removed from traversing carriage
onto mono rail in readiness to be removed from
site and tested at Siemens Hepburn Works
Reyrolle L42T
33kV Switchgear
Cable box fitted
with UltraTEV
Alarm Hub and
ultrasonic
microphone
Siemens 8DA10
33kV standalone
switchgear panel
fitted with
UltraTEV Alarm
Hub and
ultrasonic
microphone
UltraTEV Alarm System
with SCADA interface
(remote I/O connection)
Installed at Grid Supply
Point Broughton 33kV
Substation – 1 system
per Section
Seraphim 33 kV Substation
Reyrolle L42T
33kV Switchgear
Cable box fitted
with UltraTEV
Alarm Hub and
ultrasonic
microphone
Case Study 12 - CONCAST Water Treatment Plant 11 kV Busbars
Affected Asset details:
1. Equipment Busbars
2. Make GEC
3. Model BVP17
4. Operating voltage 11kV
5. Number of panels 11
6. Age circa 40 years
Concast Plant
11kV Substation
role within
Steelmaking
11kV distribution
system
GEC BVP17 11kV
Switchgear
(single busbar system)
3 Section switchboard
View from the top
- showing busbars
arrangement
3 circuits per Section
Section 1 Section 2
GEC BVP17 11kV
Switchgear
(single busbar system)
3 Section switchboard
View from the top
- showing busbars
arrangement
3 circuits per Section
Section 1 Section 2
Concast Plant 11kV Switchboard
– Section 2 busbars at the back
of Bus Section 1 – 2 OCB panel
Concast Plant 11kV Switchboard –
damage to the L2 (yellow phase)
busbar sleeve
Concast Plant 11kV Switchboard –
damage to bakelite busbar
spacing fittings with rubber
inserts
Concast Plant 11kV
Switchboard
– busbars removed
and taken to
Schneider factory
for repairs and
resleeving
Case Study 12 - CONCAST Water Treatment Plant 11 kV Busbars
Actions taken to rectify the fault
1. Resources Investigation & busbars removal/installation – TATA,
busbars repairs and new busbar spacing materials –
Schneider
2. Discharge elimination 11kV busbars Sections 1&2, 2nd outage sections 2&3
isolated.
3. Repair method busbars re-sleeved and new busbar spacing fitted
Estimated cost of repair total cost of all repairs circa £ 25k
Has PD activity stopped? Yes
Possible cause of partial discharge – PD due to poor substation heating in winter time
which led to high humidity levels (90%) and water condensation on substation ceiling.
Loss estimation in worst case scenario:
Slab caster loss of production with possible knock on effect on Plate Mill.
Case Study 13 - Heavy Plate Mill Roughing Mill Transformer Cast
Resin Transformer 33 kV
Affected Asset details:
1. Equipment Cast Resin Transformer
2. Make ABB
3. Model 4.1MVA
4. Operating voltage 33/1kV
5. Number of panels N/A
6. Age 7 years
Heavy Plate Mill
Roughing Mill
Main Drive Cast
Resin Transformer
33/1 kV 4.1MVA
Heavy Plate Mill
Roughing Mill
Main Drive Cast
Resin Transformer
33/1 kV 4.1MVA –
loose eye bolt nut
Heavy Plate Mill
Roughing Mill
Main Drive Cast
Resin Transformer
33/1 kV 4.1MVA –
substandard LV
cable connection
Heavy Plate Mill Roughing Mill Main Drive
Cast Resin Transformer 33/1 kV 4.1MVA –
PD found on 33kV CT’s connections
Case Study 14 - Bloom Caster 11 kV
Affected Asset details:
1. Equipment Vacuum Circuit Breakers (VCB)
2. Make GEC
3. Model VMX
4. Operating voltage 11kV
5. Number of panels 11 (2 VCB’s affected)
6. Age 19 years
GEC VMX 11kV Switchgear
(single busbar system)
cross section drawing
GEC VMX 11kV Switchgear
(single busbar system)
cross section drawing
GEC VMX 11kV VCB – incomer No.1 L2
(yellow phase) front isolating contact
GEC VMX 11kV VCB
– incomer No.1
L2 (yellow phase)
front isolating
contact
GEC VMX 11kV VCB
– incomer No.1
L2 (yellow phase)
front isolating
contact
GEC VMX 11kV VCB – incomer No.1
L2 (yellow phase) front isolating contact
Special thanks
This presentation was made thanks to 8 years of experience in
maintaining on one of the largest private HV network – TATA Steel in
Scunthorpe, North Lincolnshire, UK
Presentation prepared with permission of:
John Simpson – TATA Steel Scunthorpe Electrical Infrastructure, SRCS
and DSEAR Engineer, HV Engineer in Charge for Scunthorpe &
Immingham Works
Special thanks to Paul Wilson for Scunthorpe Steelworks photographs
Special thanks
to my wife Gosia!
Any questions?
Thank you.

More Related Content

What's hot

11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...Thorne & Derrick International
 
Protection settings calculation
Protection settings calculationProtection settings calculation
Protection settings calculationLANOGWA RODGERS
 
Seminar on Partial Discharge detection methods
Seminar on Partial Discharge detection methodsSeminar on Partial Discharge detection methods
Seminar on Partial Discharge detection methodsHarshit Bhandari
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and detailsMahesh Sontyal
 
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...Thorne & Derrick International
 
ETAP - Arc flash introduction
ETAP - Arc flash introductionETAP - Arc flash introduction
ETAP - Arc flash introductionHimmelstern
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersSARAVANAN A
 
Unit 02 - Fuse and circuit breakers
Unit  02 -  Fuse and circuit breakersUnit  02 -  Fuse and circuit breakers
Unit 02 - Fuse and circuit breakersPremanandDesai
 
Vignettes in Grounding
Vignettes in GroundingVignettes in Grounding
Vignettes in Groundingmichaeljmack
 
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)Thorne & Derrick International
 
Earthing Concepts
Earthing ConceptsEarthing Concepts
Earthing Conceptsmvrkprasad
 
Partial Discharge Test - Switchgear
Partial Discharge Test - Switchgear Partial Discharge Test - Switchgear
Partial Discharge Test - Switchgear RajuGupta88
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersLiving Online
 

What's hot (20)

Earthing
EarthingEarthing
Earthing
 
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...
 
Protection settings calculation
Protection settings calculationProtection settings calculation
Protection settings calculation
 
Seminar on Partial Discharge detection methods
Seminar on Partial Discharge detection methodsSeminar on Partial Discharge detection methods
Seminar on Partial Discharge detection methods
 
Earthing
EarthingEarthing
Earthing
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and details
 
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
 
Basics of busbar protection
Basics of busbar protectionBasics of busbar protection
Basics of busbar protection
 
ETAP - Arc flash introduction
ETAP - Arc flash introductionETAP - Arc flash introduction
ETAP - Arc flash introduction
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
 
Partial discharge testing
Partial discharge testingPartial discharge testing
Partial discharge testing
 
tower spotting
tower spottingtower spotting
tower spotting
 
Unit 02 - Fuse and circuit breakers
Unit  02 -  Fuse and circuit breakersUnit  02 -  Fuse and circuit breakers
Unit 02 - Fuse and circuit breakers
 
Vignettes in Grounding
Vignettes in GroundingVignettes in Grounding
Vignettes in Grounding
 
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)
Baur - Cable Fault Locators & Location Specialists (LV MV HV Cables)
 
1. panel listrik
1. panel listrik1. panel listrik
1. panel listrik
 
Earthing Concepts
Earthing ConceptsEarthing Concepts
Earthing Concepts
 
Partial Discharge Test - Switchgear
Partial Discharge Test - Switchgear Partial Discharge Test - Switchgear
Partial Discharge Test - Switchgear
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of Transformers
 
Relay testing procedure
Relay testing procedure Relay testing procedure
Relay testing procedure
 

Similar to Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe

UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREUNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREPremanandDesai
 
overvoltage in distribution network
overvoltage in distribution networkovervoltage in distribution network
overvoltage in distribution networkmegala venkatesan
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transientsmichaeljmack
 
Michael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case studyMichael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case studyNSW Environment and Planning
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transientsmichaeljmack
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfDevesh54
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptAshutosh Srivastava
 
MWAPE KAMPILIMBA FINAL REPORT
MWAPE KAMPILIMBA FINAL REPORTMWAPE KAMPILIMBA FINAL REPORT
MWAPE KAMPILIMBA FINAL REPORTKampilimba Mwape
 
final year project report
final year project reportfinal year project report
final year project reportAnuj Kumar
 
Principles Control & Protection of HVDC Schemes
Principles Control & Protection of HVDC SchemesPrinciples Control & Protection of HVDC Schemes
Principles Control & Protection of HVDC SchemesPower System Operation
 
Electrical and Electronics lab manual
Electrical and Electronics lab manualElectrical and Electronics lab manual
Electrical and Electronics lab manualCyber4Tech
 
per_unit_system.pptx
per_unit_system.pptxper_unit_system.pptx
per_unit_system.pptxPaylamKanal
 
High Reliability and Efficiency Single phase Transformerless Inverter for Gri...
High Reliability and Efficiency Single phase Transformerless Inverter for Gri...High Reliability and Efficiency Single phase Transformerless Inverter for Gri...
High Reliability and Efficiency Single phase Transformerless Inverter for Gri...Anoop kumar Niravuparambil
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxLiewChiaPing
 

Similar to Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe (20)

UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREUNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
 
Fault level calculations
Fault level calculationsFault level calculations
Fault level calculations
 
overvoltage in distribution network
overvoltage in distribution networkovervoltage in distribution network
overvoltage in distribution network
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
 
Michael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case studyMichael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case study
 
220kv substation
220kv substation220kv substation
220kv substation
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation ppt
 
MWAPE KAMPILIMBA FINAL REPORT
MWAPE KAMPILIMBA FINAL REPORTMWAPE KAMPILIMBA FINAL REPORT
MWAPE KAMPILIMBA FINAL REPORT
 
final year project report
final year project reportfinal year project report
final year project report
 
Principles Control & Protection of HVDC Schemes
Principles Control & Protection of HVDC SchemesPrinciples Control & Protection of HVDC Schemes
Principles Control & Protection of HVDC Schemes
 
Electrical and Electronics lab manual
Electrical and Electronics lab manualElectrical and Electronics lab manual
Electrical and Electronics lab manual
 
kamal project ppt
kamal project pptkamal project ppt
kamal project ppt
 
220 66 kv nrs sub report
220 66 kv nrs sub report220 66 kv nrs sub report
220 66 kv nrs sub report
 
High voltage
High voltageHigh voltage
High voltage
 
per_unit_system.pptx
per_unit_system.pptxper_unit_system.pptx
per_unit_system.pptx
 
High Reliability and Efficiency Single phase Transformerless Inverter for Gri...
High Reliability and Efficiency Single phase Transformerless Inverter for Gri...High Reliability and Efficiency Single phase Transformerless Inverter for Gri...
High Reliability and Efficiency Single phase Transformerless Inverter for Gri...
 
Reactors
ReactorsReactors
Reactors
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
 

Recently uploaded

VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 

Recently uploaded (20)

★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 

Partial discharge monitoring of High Voltage Assets - TATA Steel Scunthorpe

  • 1. EA Technology Partial Discharge Forum 26 03 2015 Partial Discharge monitoring of HV assets - experience from Tata Steel site, Scunthorpe. Highlighting defects with specific switchgear which led to Partial Discharge, and the methods implemented to manage these assets. Mikolaj Kukawski MIET Customer Networks Manager ESM Power
  • 2. Content of presentation • My background • TATA Steel HV Distribution Network • Integrated Steelworks Processes • Partial Discharge Case Studies (14) • Special thanks and questions
  • 3. My background Education: • 2001-2006 - University of Lublin, Poland - Master’s degree in Electrical Engineering – Power Systems Work experience: • 2006-2007 - Elektromontaz Lublin, Poland - Design Engineer for MV Switchgear Manufacturer – 1 year • 2007-2008 - Corus Power & Distribution (P&D), Scunthorpe, UK - HV Electrician Team Member – 18 months
  • 4. My background Work experience: • 2008-2014 - Corus / TATA Steel P&D, Scunthorpe, UK - Distribution Engineer - 6 years • 2014 Dec - currently - ESM Power, Scunthorpe, UK - Customer Networks Manager
  • 5. Integrated Steelworks HV Distribution Network
  • 6. Integrated Steelworks 33kV Distribution Network Block Diagram
  • 7. Integrated Steelworks 33kV Distribution Network Block Diagram
  • 8. Integrated Steelworks Site Map showing 12 main plants
  • 9. TATA STEEL Integrated Steelworks - Scunthorpe Site
  • 14. A train with coal wagons unloads at Dawes Lane Coal Handling Plant
  • 15. A train with Iron Ore arrives at Scunthorpe Ore Blending Plant
  • 18. Coal stocks at the Coal Handling Plant
  • 20. Blast Furnaces also known as The Four Queens: – Mary, Bess, Anne & Victoria
  • 22. Molten iron is transported to Steelmaking Plant using torpedo wagons
  • 23. Molten iron is transported to Steelmaking Plant using torpedo wagons
  • 24. Charging molten iron into BOS converter
  • 26. Ladle Arc Furnace - secondary steelmaking
  • 28. 8 strand Billet Caster
  • 29. A pack of billets on the BBM cooling bank
  • 32. A slab leaves the Plate Mill reheater furnace
  • 34. Plate cooling bank at Heavy Plate Mill
  • 37. Scunthorpe Rail and Section Mill Area 3 also known as Rail Service Centre
  • 38. Partial Discharge Case Studies 1 - Central Power Station 33 kV Substation 2 - Central Power Station 3.3 kV 3 - Blast Furnaces 11 kV 4 - Bloom Mill 11 kV 5 - BOS Waste Gas Recovery 11 kV 6 - Ore Blending Plant Main 11 kV 7 - Blast Furnaces No. 2 6.6 kV 8 - BOS Waste Gas Recovery 11 kV Busbar Outage 9 - Heavy Section Mill to Scunthorpe Rod Mill 33 kV Interconnector Reactor Terminations 10 - Broughton to Seraphim 33 kV Interconnector 11 - Seraphim 33 kV Reyrolle L42T VT 12 - CONCAST Water Treatment Plant 11 kV GEC BVP 17 Busbar 13 - Heavy Plate Mill Roughing Mill Transformer Cast Resin Transformer 33 kV 14 - Bloom Caster 11 kV
  • 40. Integrated Steelworks HV Distribution Network
  • 41. Integrated Steelworks HV Distribution Network
  • 42. Case Study 1 - Central Power Station 33 kV Substation Affected Asset details: 1. Equipment Circuit VT 2. Make Reyrolle 3. Model L800T 4. Operating voltage 33kV 5. Number of panels 13 (Section 3 only 2 circuits) 6. Age 40 years
  • 43.
  • 44.
  • 45. Reyrolle L800T 33kV Switchgear (single busbar system) cross section drawing
  • 46. Reyrolle L800T 33kV Switchgear (single busbar system) cross section drawing
  • 48. CPS 33kV Substation Reyrolle L800T 33kV Switchgear – Section 3
  • 49. Case Study 1 - Central Power Station 33 kV Substation Investigation details: 1. Partial discharge initial detection method - CPS power controller detected red TEV using hand held UltraTEV detector during daily substation checks – informed duty engineer 2. Follow up investigation method – Distribution Engineer and Team Leader joint investigation using UltraTEV +. Switchboard tested Left to Right, Front to Rear and Top to Bottom. Conclusion: On the circuit: 33/11kV 12/24MVA Transformer No.3 (T3) the higher the measurement was taken the higher the TEV reading was (up to 50dB). Decided to test Circuit VT located on the top of the switchgear. Confirmed that the TEV reading was even higher (60dB). 3. Action taken - decided to isolate T3 circuit
  • 50. T3 circuit VT fixed portion L2 (yellow) phase spout
  • 51. T3 circuit VT fixed portion L2 (yellow) phase spout
  • 52. T3 circuit VT moving portion L1 and L2 (red and yellow) phases spouts
  • 53. T3 circuit VT moving portion L2 and L3 (yellow and blue) phases spouts
  • 54. T3 circuit VT moving portion L2 (yellow) phase spout
  • 55. T3 circuit VT moving portion L2 (yellow) phase spout
  • 56. T3 circuit VT moving portion L2 (yellow) phase spout
  • 57. Case Study 1 - Central Power Station 33 kV Substation Outage requirement to enable investigation and repair 1. Equipment Section 3 bus bars at CPS 33kV, CPS 33/11kV 12/24MVA Transformer No.3 circuit, CPS to HPM 33kV Interconnector 2. Timescale 2 hours on the T3 circuit, 15 minutes HPM stopped rolling to enable T3 33kV OCB re-closure without its circuit VT.
  • 58. Case Study 1 - Central Power Station 33 kV Substation Actions taken to rectify the fault 1. Resources Investigation TATA, Siemens for VT repair 2. Discharge elimination Circuit VT withdrawn, 3. Repair method Cracked VT bushing to be replaced 4. Estimated cost of repair circa £ 10k Has PD activity stopped? YES – TEV level went back to green Possible cause of partial discharge VT Bushing damaged during installation Loss estimation in worst case scenario: Circa £ 200k for 2 33kV switchgear panels replacement and potentially HPM production loss and internal generation limited due to 1 of 3 33/11kV transformers outage.
  • 59. Case Study 2 - Central Power Station 3.3 kV Affected Asset details: 1. Equipment Single core 3.3kV unarmoured cable 2. Make GEC 3. Model BTVP17 and HMC 4. Operating voltage 3.3kV 5. Number of panels 15 6. Age 40 years
  • 60.
  • 61.
  • 62. GEC BTVP17 3.3kV Switchgear (double busbar system) cross section drawing
  • 63. GEC BTVP17 3.3kV Switchgear (double busbar system) cross section drawing
  • 64. CPS 3.3kV Substation GEC BTVP17 3.3kV Switchgear (rear view)
  • 65. Case Study 2 - Central Power Station 3.3 kV Investigation details: 1. Partial discharge initial detection method - CPS power controller detected red TEV on Incomer from 5MVA No.1 Transformer using hand held UltraTEV detector during daily substation checks – informed duty engineer 2. Follow up investigation method – Distribution Engineer investigated the switchboard using UltraTEV +. Switchboard tested Left to Right, Front to Rear and Top to Bottom. Conclusion: On the Incomer No.1 circuit the lower the measurement was taken the higher the TEV reading was (up to 44dB). Decided to Inspect cable box. No evidence of Partial Discharge found. Tested switchboard Using Partial Discharge Monitor. Tested switchboard again using UltraTEV + and realised that that the TEV reading was even higher on the bottom of cable box support channel – near the floor (60dB). Question asked: What is underneath the substation? It turned out to be mezzanine floor with cables installed on metal trays system. Found one core stuck against metal support construction channel with signs of partial discharge.
  • 66. CPS 3.3kV Substation GEC BTVP17 3.3kV Switchgear (Incomer from 5MVA No.1 Transformer - cable box inspection)
  • 67. Case Study 2 - Central Power Station 3.3 kV Investigation details: 3. Action taken – Circuit isolated, tested IR of the cable – 4 Mega Ohms - asked experienced jointer for advice – suggested using triple layer of HV heat shrink tape around damaged area of the cable. Cable repaired. Circuit reenergised. TEV levels dropped down to 30dB at the repair point and down to 27 dB above the repair point, investigated further the cable route – found cables tightened with twisted steel wire armouring to form two trefoil formations (instead of using proper trefoil cleats). Steel wire armouring is cutting through PVC insulation of unarmoured cables on the majority of the cable routes. Decided to replace all 3.3kV cables for both No.1 and No.2 5MVA Transformers Incomers.
  • 68. CPS 3.3kV Substation mezzanine floor (Incomer from 5MVA No.1 Transformer - Single core unarmoured cables)
  • 69. CPS 3.3kV Substation mezzanine floor (Incomer from 5MVA No.1 Transformer - Single core unarmoured cables)
  • 70. CPS 3.3kV Substation mezzanine floor (Incomer from 5MVA No.1 Transformer - Single core unarmoured cables)
  • 71. CPS 3.3kV Substation mezzanine floor (Incomer from 5MVA No.1 Transformer - Single core unarmoured cable repaired)
  • 72. CPS 3.3kV Substation mezzanine floor (Incomer from 5MVA No.1 Transformer - Single core unarmoured cable repaired – TEV level dropped to 30dB)
  • 73. CPS 3.3kV Substation mezzanine floor (Incomer from 5MVA No.1 Transformer - Single core unarmoured cable repaired – TEV level dropped to 27dB above repair point)
  • 74. CPS 3.3kV Substation mezzanine floor (Incomer from 5MVA No.1 Transformer - Single core unarmoured cable repaired – TEV level dropped to 30dB)
  • 75. Single core unarmoured cables tightened with twisted steel wire armourings
  • 76. Original cable schedule dated 1974 showing the type and route of the cables
  • 77. Case Study 2 - Central Power Station 3.3 kV Outage requirement to enable investigation and repair 1. Equipment No.1 5MVA 11/3.3kV Transformer at CPS 3.3kV, 2. Timescale 6 hours for the cable box inspection, 4 hours for cable repair
  • 78. Case Study 2 - Central Power Station 3.3 kV Actions taken to rectify the fault 1. Resources Investigation TATA, SPEC for cable repair 2. Discharge elimination Cable replacement, 3. Repair method New cables installation with correct trefoil cleats 4. Estimated cost of repair circa £ 20k Has PD activity stopped? NO – however TEV level reduced to amber level on the switchboard Possible cause of partial discharge Cable damaged due to incorrect installation method Loss estimation in worst case scenario: Potentially loss of internal generation since 3.3kV switchboard feeds auxiliary equipment essential for steam raising processes. Possible knock on effect on process steam system for the whole site.
  • 79. Case Study 3 - Blast Furnaces 11 kV Affected Asset details: 1. Equipment Vacuum Circuit Breakers (VCB) 2. Make GEC 3. Model VMX 4. Operating voltage 11kV 5. Number of panels 19 (5 VCB’s affected) 6. Age 26 years
  • 80.
  • 81.
  • 82. GEC VMX 11kV Switchgear (single busbar system) cross section drawing
  • 83. GEC VMX 11kV Switchgear (single busbar system) cross section drawing
  • 84. GEC VMX 11kV Switchgear (single busbar system) cross section drawing
  • 85. GEC VMX 11kV Vacuum Circuit Breaker (VCB) cross section drawing
  • 86. GEC VMX 11kV Vacuum Circuit Breaker (VCB) cross section drawing
  • 87. Blast Furnaces 11 kV Substation GEC VMX 11kV Switchgear (single busbar system)
  • 88. Case Study 3 - Blast Furnaces 11 kV Investigation details: 1. Partial discharge initial detection method – TATA Steel Power and Distribution craftsmen detected red TEV using hand held UltraTEV detector during weekly substation checks – informed duty engineer 2. Follow up investigation method – Distribution Engineer investigated switchboard using UltraTEV +. Switchboard tested Left to Right, Front to Rear and Top to Bottom. Conclusion: On the circuit: 33/11kV 12/24MVA Transformer Incomer No.1 the highest TEV level measured was at the front of VCB (up to 40dB). In conjunction with BF Engineers decided to take the suspected VCB out of service. 3. Action taken – Incomer No.1 VCB isolated and retested the switchboard with UltraTEV + - TEV level back to green
  • 89. Incomer No.1 GEC VMX 11kV VCB L2 (yellow phase) front isolating contact front – busbar, rear - circuit
  • 90. Incomer No.1 GEC VMX 11kV VCB L2 (yellow phase) front isolating contact
  • 91. New VMX unit for Incomer No.1 - showing L2 (yellow phase) front isolating contact
  • 92. Case Study 3 - Blast Furnaces 11 kV Outage requirement to enable investigation and repair 1. Equipment Incomer No.1 from 33/11kV 12/24MVA Transformer circuit 2. Timescale 2 hours to replace VCB with the new or refurbished unit from Schneider
  • 93. Case Study 3 - Blast Furnaces 11 kV Actions taken to rectify the fault 1. Resources Investigation TATA, new or refurbished VMX unit – Schneider 2. Discharge elimination VMX VCB replacement, 3. Repair method VMX body moulding replaced and ball bearing added to the drive shaft Estimated cost of repair VMX refurbishment circa £ 5k, new VMX unit circa £ 14k Has PD activity stopped? Yes Possible cause of partial discharge – partial discharge possibly due to continuous charging and discharging of unearthed metal drive shaft which goes through the middle of VMX body moulding. Loss estimation in worst case scenario: Potentially loss of production on crucial iron making plant since 11kV switchboard feeds charging side of all four blast furnaces essential for iron making processes. Possible site-wide knock on effect including steelmaking and mills.
  • 94. Other VMX circuit breakers affected by partial discharge – bus section
  • 95. Other VMX circuit breakers affected by partial discharge – bus section
  • 96. Other VMX circuit breakers affected by partial discharge – Queen Anne 2MVA No.2 Transformer VCB
  • 97. Other VMX circuit breakers affected by partial discharge – Queen Anne 2MVA No.2 Transformer VCB
  • 98. Other VMX circuit breakers affected by partial discharge – Substation Auxiliary 2MVA Transformer No.2 VCB
  • 99. Other VMX circuit breakers affected by partial discharge – incomer No.2
  • 100. Other VMX circuit breakers affected by partial discharge – incomer No.2
  • 101. Case Study 4 - Bloom Mill 11 kV Affected Asset details: 1. Equipment Busbar Voltage Transformer (VT) 2. Make GEC 3. Model BVP17 4. Operating voltage 11kV 5. Number of panels 16 (Section 2 Busbar VT affected) 6. Age 45 years
  • 102.
  • 103.
  • 104. Bloom Mill 11kV Substation GEC BVP17 11kV Switchgear (single busbar system) - showing Section 2 of the switchboard isolated and Section 2 busbars earthed
  • 105. GEC BVP17 VT cross section drawing – showing indentation in the rail to prevent VT movement whilst in service position
  • 106. GEC BVP17 VT cross section drawing – showing indentation in the rail to prevent VT movement whilst in service position
  • 107. Bloom Mill 11kV Section 2 Busbar VT
  • 108. Bloom Mill 11kV Section 2 Busbar VT
  • 109. Bloom Mill 11kV Section 2 Busbar VT
  • 110. Bloom Mill 11kV Section 2 Busbar VT
  • 111. Bloom Mill 11kV Section 2 Busbar VT
  • 112. Case Study 4 - Bloom Mill 11 kV Investigation details: 1. Partial discharge initial detection method – BBM engineer informed duty engineer about audible discharge in Section 2 Switchroom of Bloom Mill 11kV Substation. 2. Follow up investigation method – Distribution Engineer arrived on site and located the discharge near Section 2 Busbar VT. 3. Action taken - decided to isolate suspected Section 2 Busbar VT
  • 113. Case Study 5 - BOS Waste Gas Recovery 11 kV Affected Asset details: 1. Equipment Vacuum Circuit Breakers (VCB) 2. Make GEC 3. Model VMX 4. Operating voltage 11kV 5. Number of panels 9 (5 VCB’s affected) 6. Age 26 years
  • 114. BOS Waste Gas Recovery 11 kV Substation - bus section GEC VMX VCB L2 (yellow phase) front isolating contact
  • 115. Bus section GEC VMX 11kV VCB L2 (yellow phase) front isolating contact
  • 116. Other VMX circuit breakers affected by partial discharge – Incomer No.2
  • 117. Other VMX circuit breakers affected by partial discharge – Incomer No.2
  • 118. Other VMX circuit breakers affected by partial discharge – Incomer No.2
  • 119. Other VMX circuit breakers affected by partial discharge – Incomer No.2
  • 120. Other VMX circuit breakers affected by partial discharge – Incomer No.2
  • 121. Other VMX circuit breakers affected by partial discharge – Incomer No.2
  • 122. Case Study 6 - Ore Blending Plant Main 11 kV Affected Asset details: 1. Equipment Current Transformers (CT’s) 2. Make GEC 3. Model BVP17 4. Operating voltage 11kV 5. Number of panels 6 (1 OCB panel circuit chamber affected) 6. Age 27 years
  • 123. GEC BVP17 11kV Switchgear (single busbar system) cross section drawing
  • 124. Ore Blending Plant Main 11 kV Substation
  • 125. Ore Blending Plant Main 11 kV Substation Incomer No.1 CT’s affected by partial discharge
  • 126. Ore Blending Plant Main 11 kV Substation Incomer No.1 CT’s affected by partial discharge
  • 127. Case Study 6 - Ore Blending Plant Main 11 kV Actions taken to rectify the fault 1. Resources Investigation TATA, CT’s & bushings repairs – Schneider 2. Discharge elimination Incomer No.1 circuit isolated 3. Repair method CT’s removed, repaired and fitted by OEM Estimated cost of repair CT’s repairs: labour circa £ 8k, materials circa £ 2.5k Has PD activity stopped? Yes Possible cause of partial discharge – partial discharge possibly due to broken CT’s earth clamps. It is likely that high humidity within substation was a contributing factor. Loss estimation in worst case scenario: Potential loss of production on Ore Blending Plant – crucial for Sinter making process. Possible site-wide knock on effect including ironmaking, steelmaking and mills.
  • 128. Case Study 7 - Blast Furnaces No. 2 6.6 kV Affected Asset details: 1. Equipment Cable terminations 2. Make Brush 3. Model VMVD 4. Operating voltage 6.6kV 5. Number of panels 23 (2 VCB panels cable terminations affected) 6. Age 25 years
  • 129. Brush VMVD 6.6kV (double busbar system) cross section drawing
  • 130. Brush VMVD 6.6kV (double busbar system) cross section drawing
  • 131. Brush VMVD 6.6kV substandard cable terminations
  • 132. Brush VMVD 6.6kV -substandard cable terminations
  • 133. Brush VMVD 6.6kV new cable terminations
  • 134. Case Study 7 - Blast Furnaces No. 2 6.6 kV Actions taken to rectify the fault 1. Resources Investigation TATA, cable terminations repairs – SPEC 2. Discharge elimination 2 circuits isolated 3. Repair method cable terminations removed, cables cut, jointed new pieces of cable in the basement and terminated with Raychem heat shrink termination kits Estimated cost of repair new cables, joints and terminations circa £ 7k Has PD activity stopped? Yes Possible cause of partial discharge – partial discharge possibly due to substandard cable terminations. Loss estimation in worst case scenario: Potential loss of production on ironmaking. Possible site-wide knock on effect including steelmaking and mills.
  • 135. Air Cooled Transformer Partial Discharge in the substation next door
  • 136. Air Cooled Transformer Partial Discharge in the substation next door
  • 137. Air Cooled Transformer Partial Discharge in the substation next door
  • 138. Air Cooled Transformer Partial Discharge in the substation next door
  • 139. Air Cooled Transformer Partial Discharge in the substation next door
  • 140. Air Cooled Transformer Partial Discharge in the substation next door
  • 141. Case Study 8 - BOS Waste Gas Recovery 11 kV Busbar Outage Affected Asset details: 1. Equipment Air insulated busbars 2. Make GEC 3. Model VMX 4. Operating voltage 11kV 5. Number of panels 9 6. Age 26 years
  • 142. GEC VMX 11kV Switchgear (single busbar system) cross section drawing
  • 143. GEC VMX 11kV Switchgear (single busbar system) 2 Section switchboard View from the top - showing busbars arrangement Section 1 Section 2
  • 144. GEC VMX 11kV Switchgear (single busbar system) 2 Section switchboard View from the top - showing busbars arrangement Section 1 Section 2
  • 145. BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
  • 146. BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
  • 147. BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
  • 148. BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
  • 149. BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
  • 150. BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
  • 151. BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
  • 152. BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
  • 153. BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
  • 154. BOS Waste Gas Recovery 11 kV Switchboard – Section 2 busbar inspection
  • 155. Case Study 9 - Heavy Section Mill to Scunthorpe Rod Mill 33 kV Interconnector Reactor Terminations Affected Asset details: 1. Equipment 33kV cable terminations inside air cable box of reactor 2. Make Yorkshire Electric Transformer Company Ltd. 3. Model 21 MVA to British Standard Specification 171/1956 4. Operating voltage 33kV 5. Number of panels N/A 6. Age 41 years (refurbished by SPEC in 2006)
  • 156.
  • 157.
  • 158. Blast Furnace to Scunthorpe Rod Mill 33 kV Interconnector Reactor
  • 159. Blast Furnace to Scunthorpe Rod Mill 33 kV Interconnector Reactor
  • 160. Heavy Section Mill to Scunthorpe Rod Mill 33 kV Interconnector Reactor Terminations
  • 161. Heavy Section Mill to Scunthorpe Rod Mill 33 kV Interconnector Reactor Terminations
  • 162. Heavy Section Mill to Scunthorpe Rod Mill 33 kV Interconnector Reactor Terminations
  • 163. Heavy Section Mill to Scunthorpe Rod Mill 33 kV Interconnector Reactor Terminations
  • 164. Heavy Section Mill to Scunthorpe Rod Mill 33 kV Interconnector Reactor Terminations
  • 165. Heavy Section Mill to Scunthorpe Rod Mill 33 kV Interconnector Reactor Terminations
  • 166. Case Study 9 - Heavy Section Mill to Scunthorpe Rod Mill 33 kV Interconnector Reactor Terminations Actions taken to rectify the fault 1. Resources Investigation TATA, cable terminations repairs – SPEC 2. Discharge elimination 33kV Interconnector circuit isolated 3. Repair method cables re-terminated Estimated cost of repair new terminations circa £ 7k Has PD activity stopped? Yes Possible cause of partial discharge – partial discharge possibly due to substandard cable terminations (i.e. clearances between termination sheds not sufficient) Loss estimation in worst case scenario: Security of site power supplies compromised – SRM down to 3 out of 4 Interconnectors.
  • 167. Blast Furnace to Rod Mill 33 kV Interconnector Reactor Cable Terminations Failure
  • 168. Blast Furnace to Rod Mill 33 kV Interconnector Reactor Cable Terminations Failure
  • 169. Blast Furnace to Rod Mill 33 kV Interconnector Reactor Cable Terminations Partial Discharge
  • 170. Blast Furnace to Rod Mill 33 kV Interconnector Reactor Cable Terminations Partial Discharge
  • 171. Case Study 10 - Broughton to Seraphim 33 kV Interconnector VT and Case Study 11 - Seraphim to BF Interconnector VT Affected Asset details: 1. Equipment Circuit VT 2. Make Reyrolle 3. Model L42T 4. Operating voltage 33kV 5. Number of panels 23 6. Age circa 40 years
  • 172. Reyrolle L42T 33kV Switchgear (single busbar system) cross section drawing
  • 173. Broughton to Seraphim 33 kV Interconnector
  • 174. Reyrolle L42T 33kV Switchgear Circuit VT removed from traversing carriage onto mono rail in readiness to be removed from site and tested at Siemens Hepburn Works
  • 175. Reyrolle L42T 33kV Switchgear Cable box fitted with UltraTEV Alarm Hub and ultrasonic microphone
  • 176. Siemens 8DA10 33kV standalone switchgear panel fitted with UltraTEV Alarm Hub and ultrasonic microphone
  • 177. UltraTEV Alarm System with SCADA interface (remote I/O connection) Installed at Grid Supply Point Broughton 33kV Substation – 1 system per Section
  • 178. Seraphim 33 kV Substation
  • 179. Reyrolle L42T 33kV Switchgear Cable box fitted with UltraTEV Alarm Hub and ultrasonic microphone
  • 180. Case Study 12 - CONCAST Water Treatment Plant 11 kV Busbars Affected Asset details: 1. Equipment Busbars 2. Make GEC 3. Model BVP17 4. Operating voltage 11kV 5. Number of panels 11 6. Age circa 40 years
  • 181. Concast Plant 11kV Substation role within Steelmaking 11kV distribution system
  • 182. GEC BVP17 11kV Switchgear (single busbar system) 3 Section switchboard View from the top - showing busbars arrangement 3 circuits per Section Section 1 Section 2
  • 183. GEC BVP17 11kV Switchgear (single busbar system) 3 Section switchboard View from the top - showing busbars arrangement 3 circuits per Section Section 1 Section 2
  • 184. Concast Plant 11kV Switchboard – Section 2 busbars at the back of Bus Section 1 – 2 OCB panel
  • 185. Concast Plant 11kV Switchboard – damage to the L2 (yellow phase) busbar sleeve
  • 186. Concast Plant 11kV Switchboard – damage to bakelite busbar spacing fittings with rubber inserts
  • 187. Concast Plant 11kV Switchboard – busbars removed and taken to Schneider factory for repairs and resleeving
  • 188. Case Study 12 - CONCAST Water Treatment Plant 11 kV Busbars Actions taken to rectify the fault 1. Resources Investigation & busbars removal/installation – TATA, busbars repairs and new busbar spacing materials – Schneider 2. Discharge elimination 11kV busbars Sections 1&2, 2nd outage sections 2&3 isolated. 3. Repair method busbars re-sleeved and new busbar spacing fitted Estimated cost of repair total cost of all repairs circa £ 25k Has PD activity stopped? Yes Possible cause of partial discharge – PD due to poor substation heating in winter time which led to high humidity levels (90%) and water condensation on substation ceiling. Loss estimation in worst case scenario: Slab caster loss of production with possible knock on effect on Plate Mill.
  • 189. Case Study 13 - Heavy Plate Mill Roughing Mill Transformer Cast Resin Transformer 33 kV Affected Asset details: 1. Equipment Cast Resin Transformer 2. Make ABB 3. Model 4.1MVA 4. Operating voltage 33/1kV 5. Number of panels N/A 6. Age 7 years
  • 190.
  • 191. Heavy Plate Mill Roughing Mill Main Drive Cast Resin Transformer 33/1 kV 4.1MVA
  • 192. Heavy Plate Mill Roughing Mill Main Drive Cast Resin Transformer 33/1 kV 4.1MVA – loose eye bolt nut
  • 193. Heavy Plate Mill Roughing Mill Main Drive Cast Resin Transformer 33/1 kV 4.1MVA – substandard LV cable connection
  • 194. Heavy Plate Mill Roughing Mill Main Drive Cast Resin Transformer 33/1 kV 4.1MVA – PD found on 33kV CT’s connections
  • 195. Case Study 14 - Bloom Caster 11 kV Affected Asset details: 1. Equipment Vacuum Circuit Breakers (VCB) 2. Make GEC 3. Model VMX 4. Operating voltage 11kV 5. Number of panels 11 (2 VCB’s affected) 6. Age 19 years
  • 196. GEC VMX 11kV Switchgear (single busbar system) cross section drawing
  • 197. GEC VMX 11kV Switchgear (single busbar system) cross section drawing
  • 198. GEC VMX 11kV VCB – incomer No.1 L2 (yellow phase) front isolating contact
  • 199. GEC VMX 11kV VCB – incomer No.1 L2 (yellow phase) front isolating contact
  • 200. GEC VMX 11kV VCB – incomer No.1 L2 (yellow phase) front isolating contact
  • 201. GEC VMX 11kV VCB – incomer No.1 L2 (yellow phase) front isolating contact
  • 203. This presentation was made thanks to 8 years of experience in maintaining on one of the largest private HV network – TATA Steel in Scunthorpe, North Lincolnshire, UK Presentation prepared with permission of: John Simpson – TATA Steel Scunthorpe Electrical Infrastructure, SRCS and DSEAR Engineer, HV Engineer in Charge for Scunthorpe & Immingham Works Special thanks to Paul Wilson for Scunthorpe Steelworks photographs
  • 204. Special thanks to my wife Gosia!