SlideShare a Scribd company logo
02 May 11   1
Scheduling a Project
                   At Different Levels
                Gui Ponce de Leon PhD, PE, PMP, LEED AP
                         Philip Spittler PMP
                    PMA Consultants, LLC
                            May 2,
                            M 2 2011
02 May 11   2
Schedule Level Resources




02 May 11   3
Scheduling a Project at the Right
                           Level at the Right Time
                           Level,

            An important consideration in planning and scheduling
            During management planning
               When executive and senior managers are involved
               Project-level schedules prevail
            Schedules become detailed as the planning horizon
            switches from the whole of the project to stages or
            phases
               With assumptions tested and information firmed-up
               Management can engage in detailed planning
            Various participants have different levels of interest
            Some consensus but yet to reach standard status
                                  y

02 May 11      4
Protocols Considered

            Jelen’s schedule levels
            The CII schedule levels
            Guide to the Forensic Scheduling Body of Knowledge
            Part I (FSBOK Guide)
            AACE International Recommended Practice No. 37R-06
            Schedule Levels of Detail─As Applied in Engineering,
            Procurement and Construction (RP 37)
                                            (      )
            The Chartered Institute of Building Guide to Good
            Practice in the Management of Time in Complex Projects
            (CIOB Guide)
            Mosaic’s Schedule Levels─Major Projects
            DOE Schedule Planning and Development Guide 1.8


02 May 11     5
Jelen s
                Jelen’s
                Levels




02 May 11   6
Varying Interpretations of Level 2
                      Schedules in Construction
                      S h d l i C          t ti




02 May 11   7
Recent Developments
            RP 37 describes a 5-level method based on schedule
            level requirements, levels of interest and the intended
            use of each schedule level
               This RP 37 method is based on Stephenson’s levels
            The CIOB Guide advocates five schedule reporting
            levels
            le els
               Levels 1 - 3 accomplished through summarizations
               Activity duration ranges vary within a schedule based on
               planning h i
                l    i horizon
            Neither the PMBOK Guide nor The Practice Standard
            for Scheduling deals with schedule levels
            Weaver/Mosaic offers a hierarchy of Level 1–5
            schedules, from summary- to detailed- level schedules
               Activity duration ranges may vary either based on schedule
                      y             g      y    y
               level or planning horizon within a schedule

02 May 11      8
The CSI Approach to
                           Construction WBS Hierarchy
            The Construction Specifications Institute publishes the
            MasterFormat, a master list th t classifies project work
            M t F         t      t li t that l    ifi      j t     k
            by deliverables and components and by construction
            practices
               General Requirements Division 01
               Facility Construction Divisions 02-19
               Facility Services Divisions 20-29
               Site and Infrastructure Divisions 30-39
               Process Equipment Divisions 40-49
            The MasterFormat is one scheme
            that can be used to organize the project
            WBS, detail cost accounts and
            activity codes

02 May 11      9
Guide to the Forensic Scheduling
                                 Body of Knowledge
            A schedule hierarchy for coherent summary and detailed
                                                               detailed-
            level schedules intended for mega contracts and major
            contracts, but scalable to other contracts; it advocates:
               Network-based
               Network based level 1 4 schedules
                                     1–4
               Maintaining the Level 1 schedule and Level 2 schedule─both in
               time-scaled network format─current for the duration of the project
               Limiting rolling wave planning techniques to Level 4 schedules
            Suitable to top-down and roll-up integration
               Top-down─base a lower-level schedule on the next higher level
               Roll-up─carry re-baselining and updating to higher levels
            By way of example, the hierarchy is aligned with the
            MasterFormat approach to construction WBS hierarchies


02 May 11     10
FSBOK Guide Level 1
                                   Executive Schedule
                                   E    ti S h d l
   General Intent and Format
            Establishes Contractual Milestones (if Included with
            the Request for Bids) or Demonstrates
            Conformance to Contractual and Other Milestones
            (if Included with the Bid and/or the Contract)
            Time-Scaled Network Diagram─Commonly One
                                       g               y
            Sheet
            Kept Current with Level 2
            Compares t RP 37 L
            C           to        Level 1 Wi k i et al. L
                                       l 1, Wickwire t l Level 1
                                                             l
            and Mosaic Level 1


02 May 11     11
FSBOK Guide Level 1
                                  Executive Schedule
                                  E    ti S h d l
   Scheduling Objective
            Portrays Controlling, Summary-Level Activity(ies)
            Between Milestones at CSI Division Grouping Level
            Key Procurement Scope and Overall Commissioning
            Sequence Included
            Empirical Mega Construction Activity Duration: 20%
            to 40% of Contract, Generally 6 to 18 Months
            Empirical Major Construction Activity Duration: 10%
                p       j                       y
            to 30% of Contract, Generally 3 to 12 Months



02 May 11     12
FSBOK Guide Level 2
                                 M
                                 Management S h d l
                                          t Schedule
   General Intent and Format
            Project Manager Input and Sign-Off
            Developed with the Bid or Before Mobilization
            Time-scaled Network Diagram
            Establishes the Critical Path, Near-Critical Paths and Key
            Target Dates for the Initial (Rev. 0) Progress Schedule
            Conforms to the Construction Plan, Including
            Constructability, Targeted Means and Methods, Craft
            Levels and Shared-Resource Dependencies
            Mostly Finish-to-Start Logic Ties
            Roll-Up of Level 3 Re-Baselining and Updating
            Compares to RP 37 Level 2 and Mosaic Level 2

02 May 11     13
FSBOK Guide Level 2
                                   M
                                   Management S h d l
                                             t Schedule
   Scheduling Objective
      Driving Path for Structures & Major P
      D i i P th f St t             M j Process S t
                                                  Systems at CSI
                                                             t
      Division Level (e.g., Earthwork, Foundations, Framing, etc.)
      May Subdivide Into Area Grouping or Tier Grouping
      Constructability and Normal Adverse Weather-Validated
      Long-Lead Equipment & Material Procurements and Critical
      Commissioning Sequences
      Empirical Construction Activity Duration:
            Mega contracts: 10% to 20% of Contract, Generally 3 to 9 Months
            Major Contracts: 5% to15% of Contract, Generally 2 to 6 Months
      Lower end is for activities for which hard logic applies
      Upper limit is for activities scoping bulk commodities

02 May 11    14
FSBOK Guide Level 3
                                    P
                                    Progress S h d l
                                             Schedule
   General Intent and Format
            Site/Construction Manager Input and Sign-Off
            Time-scaled Network Diagram or Bar Chart with Logic
            Drives the Updating Process
            Integrates Vendor Design, Fab/Delivery, Construction,
            System Completion and Commissioning
            May be Craft Loaded (Typically, Critical Crafts) and Rely
            on Critical Shared-Resource Dependencies (e.g.,
            Shared Crane)  )
            Activity Cost Loading, if Contractually Required
            Compares to RP 37 Level 3, Wickwire et al. Level 2 and
            Mosaic Level 3

02 May 11    15
FSBOK Guide Level 3
                                   P
                                   Progress S h d l
                                            Schedule
   Scheduling Objective
            Grouping of CSI Divisions in Areas or Elevations for
            Structures and Major Process Systems
            Level 2 Earthwork, Foundation, Framing etc Subdivided
                    Earthwork Foundation Framing, etc.
            into Component Chunks
            Normal Adverse Weather-Validated
            Detailed Delivery Sequences and Integrated, Detailed
            Commissioning Sequence
            Formula Mega Construction Activity Duration: 2% to 5%
                         g                    y
            of Contract, Generally 3 to 12 Weeks
            Formula Major Construction Activity Duration: 1% to 3%
            of Contract, 2 to 6 Weeks
               Contract

02 May 11     16
FSBOK Guide Level 4
                                     W ki S h d l
                                     Working Schedules
   General Intent and Format
            Supervision Input and Sign-Off
            Developed Before Starting a Phase or Area
            Often Developed as Separate Schedules
                          p        p
            Time-scaled Network Diagrams or Bar Charts with Logic
            Coordinated with Field Supervision (Contractor) and
            Subcontractor Input
            Trade Coordination
            May be Craft Loaded and Detail Crew Movements and other
            Means & Methods
            May be Done on a Rolling Wave Basis (e.g., Every 3 Months)
            Compares to RP 37 Level 4, Wickwire et al. Level 3 and
            Mosaic L
            M    i Level 4
                        l

02 May 11     17
FSBOK Guide Level 4
                               W ki S h d l
                               Working Schedules
   Scheduling Objective
       Groups CSI Sections Within Elevation or Area for
       Structure or Process System
       Level 3 Earthwork, Foundation, Framing Enclosure MEP
                 Earthwork Foundation Framing, Enclosure,
       & Process Installations Subdivided into Fragnets;
       Activities Biased Towards a Subcontractor or Trade
       Normal Ad
       N       l Adverse W th V lid t d
                         Weather-Validated
       Working-Level Detail in Procurement and Commissioning
       Formula Mega Construction Activity Duration: 1% to 3%
                     g                   y
       of Contract, Generally 2 to 6 Weeks
       Formula Major Construction Activity Duration: 1% to 2%
       of Contract, Generally 2 to 4 Weeks
          Contract

02 May 11   18
FSBOK Guide Level 5
                         L k Ah d S h d l
                         Look-Ahead Schedule
   General Intent and Format
     Subdivide Progress and Upcoming Level 3 or
     Level 4 Activities into Tasks for the Next 2 to 3
     Weeks
     Developed by Crew Foreman Typically in Bar
     Charts or Similar Format
     Tasks are Crew Loaded
     Reviewed in Site Progress Meetings
                            g             g
     Compares to RP 37 Level 5 and Mosaic Level 5


02 May 11   19
FSBOK Guide Level 5
                               L k Ah d S h d l
                               Look-Ahead Schedule
   Scheduling Objective
            Work Assigned to Crews
            Broken Down by Specific Components, Based
                             y p            p
            on Verification That Work Can Proceed and
            That Materials, Design Documentation and
            Other Installation Information are Packaged and
            Made Available to Crew Foremen
            Task Duration: From a Few Days to Three
                                            y
            Weeks



02 May 11     20
FSBOK Guide Advocates Network-
                   Based Level 1 4 S h d l
                   B    dL    l 1-4 Schedules
   Absent Contrary Contractual Language:
                 y                g g
            Level 2 schedules and Level 3 schedules are
            appropriate forecasting tools to evaluate:
              Timely performance
              Delay and disruption, and
              Time extension requests
            Whether
              When
              Wh such ih issues arise, or
                                  i
              Where the evaluation is undertaken post-completion


02 May 11    21
FSBOK Guide View of Level
                                    2S h d l
                                      Schedules
                                             g
   A Relevant and Reliable Forecasting Tool if:
    In a time-scaled network format
    It portrays the contractor’s plan at contract award
    at an appropriate granularity
      t            i t        l it
    It remains current and in conformance to the
    contract
    It establishes the critical/near-critical paths based:
            On contract dates
            On the construction plan, e.g., means and methods, etc.
            On normal adverse weather
            On key deliveries
02 May 11    22
FSBOK Guide View of Level
                              3S h d l
                                Schedules
   As Source Document for Forensic Modeling         g
    Depending on the analysis method used, a Level 3
    schedule may be overly detailed, particularly where
    not relevant to the facts of the case
       t l      t t th f t f th
    Forensic analysis using a Level 3 schedule may
    divert attention to non issues and detract from the
                        non-issues
    issues in dispute without gaining analysis accuracy
     Where this compromises analysis accuracy, an
                      p              y           y,
    acceptable protocol is to generate a reliable
    summarization of the Level 3 schedule


02 May 11   23
FSBOK Guide View of Level 4
                           and L
                             d Level 1 S h d l
                                   l Schedules
     The subdivisions of Level 3 schedule activities
     existing in a Level 4 schedule are often suitable
     bases for time impact analysis at the fragnet level
     A Level 1 schedule i a time-scaled network f
       L     l    h d l in i           l d       k format
     that is coherent with the Level 2 schedule is a valid
     source for a forensic demonstrative provided:
                            demonstrative,
            It portrays controlling summary activities between
            milestones at the CSI Division Grouping Level or
            equivalent indenture in another WBS scheme
            It includes critical procurement activities, commissioning
            activities and, possibly, schedule reserve


02 May 11    24
Example of a Level 1 Schedule




02 May 11   25
Schedule Granularity vs.
                                       Schedule Density

            When the
            Wh th project i scheduled i multi-level schedules
                     j t is h d l d in    lti l   l h d l
              For instance, where separate rolling wave Level 4 schedules are
              generated, it is practical to design Level 2 and Level 3 schedules
              with uniform activity duration ranges
            Where duration range is uniform for the duration of level
            2-3 schedules, appropriate to the level in the hierarchy
              The
              Th term activity or schedule granularity i used rather than
                          i i       h d l       l i is      d h h
              schedule density
            CIOB Guide schedule density implies varying duration
            ranges within a schedule
                      ithi    h d l
            FSBOK Guide schedule granularity prescribes a uniform
            duration range for each schedule
                           g

02 May 11     26
Recapping the
                                  FSBOK Guide Hierarchy
   Main Points
      Network-based schedules at all levels but for look-ahead
            Better ensures relevant and reliable forecasting tools
      ALLevel 2 schedule k t current f th project d ti
             l     h d l kept        t for the  j t duration
      promotes continuing executive and senior management
      involvement when re-baselining schedule performance
      Derive a lower-level schedule from the next higher-level
      Limit use of rolling wave planning techniques to Level 4
      Hold schedule granularity uniform as opposed to varying
      schedule density with planning horizon
      Interplay between WBS and Schedule level


02 May 11    27
The Downside of Schedules that Become
           Massive as D
           M     i     Density I
                            it Increases

      When the schedule multiplies in the number of activities as
      schedule density increases from update to update, its
      usefulness as a relevant reliable forecasting tool degrades
                      relevant,
            Schedule integrity is affected by data machinations the scheduler
            may have engaged in to attain realistic dates and critical paths
            Ever-growing multi-thousand activity schedules trend toward a
            highly-disordered schedule document




02 May 11    28
FSBOK and CIOB Guidance on
                      Activity Duration R
                      A i i D       i Ranges




02 May 11   29
FSBOK Guide Schedule Hierarchy
                              in Summary




02 May 11   30
The Sayonara Conclusion


            The time has come to bid farewell to bar chart
            techniques for Level 1 and Level 2 schedules,
            as well as Level 4 schedules
            This will not only promote more coherent
            p
            planning, but will allow all contemporaneous
                    g,                         p
            schedules to play a role in forensic scheduling




02 May 11     31
The TMI Conclusion

            An alternative to working with Level 3 schedules
            that become massive as schedule density
            increases is to approach the scheduling of a project
            in a multi-level schedule sequence that involves
              Deriving a lower-level schedule from the next higher-level
              schedule
              Limiting reliance on rolling wave planning techniques to
              the network-based Level 4 schedules
            For any schedule in the hierarchy, maintaining
            granularity unniform, from beginning to end, better
            ensures a highly-ordered network of realistic dates
            and reasonable floats, ergo a relevant and reliable
            forecasting document

02 May 11     32
The Less is More…
                   You Had Me at Level 2 Conclusion
            The activity granularity designed into a Level 2
            schedule is likely to yield a relevant and reliable
            source document for forensic schedule analysis
            Because of the activity granularity typically
            followed, a Level 3 schedule may detail paths not
            relevant to the facts of the case; analyzing non-
                                                           non
            issues may detract from and confuse the issues in
            dispute without gaining analysis accuracy
            The d t il i
            Th detail in a Level 3 schedule used i f
                            L    l     h d l       d in forensic
                                                              i
            schedule analysis should be made proportionate to
            the facts at issue by means of reliable
            summarizations
02 May 11     33
The New Standard Conclusion

            Favor approaching the scheduling of a project
            in separate but coherent summary- and
            detailed-level schedules, each schedule with
            uniform granularity
            Note ─the principles discussed are adaptable to
            schedule level approaches that are based on
                             pp
            one schedule designed at different levels of
            detail by varying schedule density based on
            planning horizon



02 May 11     34
Thank You
                 For Attending!


02 May 11   35

More Related Content

What's hot

Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
Chris Carson
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
Anupama holla
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
McLachlan Lister Pty Limited
 
Delay - EOT claims
Delay - EOT claimsDelay - EOT claims
Construction delays
Construction delaysConstruction delays
Construction delays
Saida Njim
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
Chris Carson
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
Farhan Moosa
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
Nam N.N Tran M.Eng, PMP
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
Vîñõđ Kůmåř
 
Integrated Master Schedule
Integrated Master ScheduleIntegrated Master Schedule
Integrated Master Schedule
ellefsonj
 
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
ssuserb4074f
 
Claims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays AnalysisClaims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays Analysis
Planning Engineer Est.
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
ignitetribes
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
katrin enders
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryPMI Chennai Chapter
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendationsubk1411
 

What's hot (20)

Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Delay - EOT claims
Delay - EOT claimsDelay - EOT claims
Delay - EOT claims
 
Construction delays
Construction delaysConstruction delays
Construction delays
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Integrated Master Schedule
Integrated Master ScheduleIntegrated Master Schedule
Integrated Master Schedule
 
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
 
Claims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays AnalysisClaims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays Analysis
 
Claims
ClaimsClaims
Claims
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendations
 

Viewers also liked

Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated master
Glen Alleman
 
What You Should Be Doing with Your Master Schedule
What You Should Be Doing with Your Master ScheduleWhat You Should Be Doing with Your Master Schedule
What You Should Be Doing with Your Master Schedule
Blackbaud
 
In Pursuit of Reliable Schedules
In Pursuit of Reliable SchedulesIn Pursuit of Reliable Schedules
In Pursuit of Reliable Schedules
PMA Consultants
 
101116 Risk-based Planning & Scheduling (My SAIT Slides)
101116 Risk-based Planning & Scheduling (My SAIT Slides)101116 Risk-based Planning & Scheduling (My SAIT Slides)
101116 Risk-based Planning & Scheduling (My SAIT Slides)
PM SOLUTION PRO| Risk-based Management and Services Inc.
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
Glen Alleman
 
FTA Construction Management Handbook - 2012
FTA Construction Management Handbook - 2012FTA Construction Management Handbook - 2012
FTA Construction Management Handbook - 2012
Yusuf Yıldız
 
080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1 080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1
PM SOLUTION PRO| Risk-based Management and Services Inc.
 

Viewers also liked (8)

Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated master
 
What You Should Be Doing with Your Master Schedule
What You Should Be Doing with Your Master ScheduleWhat You Should Be Doing with Your Master Schedule
What You Should Be Doing with Your Master Schedule
 
In Pursuit of Reliable Schedules
In Pursuit of Reliable SchedulesIn Pursuit of Reliable Schedules
In Pursuit of Reliable Schedules
 
101116 Risk-based Planning & Scheduling (My SAIT Slides)
101116 Risk-based Planning & Scheduling (My SAIT Slides)101116 Risk-based Planning & Scheduling (My SAIT Slides)
101116 Risk-based Planning & Scheduling (My SAIT Slides)
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 
Project Control Handbook
Project Control HandbookProject Control Handbook
Project Control Handbook
 
FTA Construction Management Handbook - 2012
FTA Construction Management Handbook - 2012FTA Construction Management Handbook - 2012
FTA Construction Management Handbook - 2012
 
080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1 080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1
 

Similar to Schedule levels-as-presented 02-may11

unit-vpart-2.ppt
unit-vpart-2.pptunit-vpart-2.ppt
unit-vpart-2.ppt
TejaTeja57
 
Petze.lara
Petze.laraPetze.lara
Petze.laraNASAPMC
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
Glen Alleman
 
Improving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanImproving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master Plan
Glen Alleman
 
Acumen presentation (final)
Acumen presentation (final)Acumen presentation (final)
Acumen presentation (final)
Glen Alleman
 
Lecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdfLecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdf
TanzeelShahid5
 
Vonnie simonsen
Vonnie simonsenVonnie simonsen
Vonnie simonsenNASAPMC
 
Vonnie simonsen
Vonnie simonsenVonnie simonsen
Vonnie simonsenNASAPMC
 
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11Robert (Bob) Owens
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
SydneyJaydeanKhanyil
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
SHAZEBALIKHAN1
 
PositioningPositioning of Product or ServiceParis based weig.docx
PositioningPositioning of Product or ServiceParis based weig.docxPositioningPositioning of Product or ServiceParis based weig.docx
PositioningPositioning of Product or ServiceParis based weig.docx
ChantellPantoja184
 
Pmi Project Management Core Problems Uet Dec 22 09
Pmi Project Management Core Problems   Uet Dec 22 09Pmi Project Management Core Problems   Uet Dec 22 09
Pmi Project Management Core Problems Uet Dec 22 09
Khalid0211
 
Dlpks Cwmf Technical Briefing
Dlpks Cwmf Technical BriefingDlpks Cwmf Technical Briefing
Dlpks Cwmf Technical Briefing
joregan
 
Define the Project
Define the ProjectDefine the Project
Define the Project
pmSPECFramework
 
Project Management Skills unit-4 Notes
Project Management Skills unit-4 NotesProject Management Skills unit-4 Notes
Project Management Skills unit-4 Notes
SamarthVarpe
 
Team Final_Scope Management
Team Final_Scope ManagementTeam Final_Scope Management
Team Final_Scope Management
RKDickey
 
Lecture 2. project management – Description (1)
Lecture 2. project management – Description (1)Lecture 2. project management – Description (1)
Lecture 2. project management – Description (1)
Dania Abdel-aziz
 
As-built Programmes - Part 2
As-built Programmes - Part 2As-built Programmes - Part 2
As-built Programmes - Part 2
David Greig
 

Similar to Schedule levels-as-presented 02-may11 (20)

unit-vpart-2.ppt
unit-vpart-2.pptunit-vpart-2.ppt
unit-vpart-2.ppt
 
Petze.lara
Petze.laraPetze.lara
Petze.lara
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
 
Improving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanImproving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master Plan
 
Acumen presentation (final)
Acumen presentation (final)Acumen presentation (final)
Acumen presentation (final)
 
Lecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdfLecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdf
 
Vonnie simonsen
Vonnie simonsenVonnie simonsen
Vonnie simonsen
 
Vonnie simonsen
Vonnie simonsenVonnie simonsen
Vonnie simonsen
 
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
Ch3 planning
Ch3 planningCh3 planning
Ch3 planning
 
PositioningPositioning of Product or ServiceParis based weig.docx
PositioningPositioning of Product or ServiceParis based weig.docxPositioningPositioning of Product or ServiceParis based weig.docx
PositioningPositioning of Product or ServiceParis based weig.docx
 
Pmi Project Management Core Problems Uet Dec 22 09
Pmi Project Management Core Problems   Uet Dec 22 09Pmi Project Management Core Problems   Uet Dec 22 09
Pmi Project Management Core Problems Uet Dec 22 09
 
Dlpks Cwmf Technical Briefing
Dlpks Cwmf Technical BriefingDlpks Cwmf Technical Briefing
Dlpks Cwmf Technical Briefing
 
Define the Project
Define the ProjectDefine the Project
Define the Project
 
Project Management Skills unit-4 Notes
Project Management Skills unit-4 NotesProject Management Skills unit-4 Notes
Project Management Skills unit-4 Notes
 
Team Final_Scope Management
Team Final_Scope ManagementTeam Final_Scope Management
Team Final_Scope Management
 
Lecture 2. project management – Description (1)
Lecture 2. project management – Description (1)Lecture 2. project management – Description (1)
Lecture 2. project management – Description (1)
 
As-built Programmes - Part 2
As-built Programmes - Part 2As-built Programmes - Part 2
As-built Programmes - Part 2
 

More from PMA Consultants

Practical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital ProjectsPractical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital Projects
PMA Consultants
 
Project Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons LearntProject Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons Learnt
PMA Consultants
 
PANDEMIC RESILIENTSCHOOLS
PANDEMIC RESILIENTSCHOOLSPANDEMIC RESILIENTSCHOOLS
PANDEMIC RESILIENTSCHOOLS
PMA Consultants
 
BioPharma Projects: Essentials in Project Controls
BioPharma Projects: Essentials in Project ControlsBioPharma Projects: Essentials in Project Controls
BioPharma Projects: Essentials in Project Controls
PMA Consultants
 
How to Implement a Project Management Information System
How to Implement a Project Management Information SystemHow to Implement a Project Management Information System
How to Implement a Project Management Information System
PMA Consultants
 
Top Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule ReliabilityTop Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule Reliability
PMA Consultants
 
What are the disadvantages of Gantt charts?
What are the disadvantages of Gantt charts?What are the disadvantages of Gantt charts?
What are the disadvantages of Gantt charts?
PMA Consultants
 
BIM and VDC for Megaproject Construction Projects
BIM and VDC for Megaproject Construction ProjectsBIM and VDC for Megaproject Construction Projects
BIM and VDC for Megaproject Construction Projects
PMA Consultants
 
Setting up Filters & Layouts in P6
Setting up Filters & Layouts in P6Setting up Filters & Layouts in P6
Setting up Filters & Layouts in P6
PMA Consultants
 
How to Choose a Project Delivery Method
How to Choose a Project Delivery MethodHow to Choose a Project Delivery Method
How to Choose a Project Delivery Method
PMA Consultants
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry Klanac
PMA Consultants
 
Project Controls Processes
Project Controls ProcessesProject Controls Processes
Project Controls Processes
PMA Consultants
 
Work Breakdown Structure Planning in NetPoint
Work Breakdown Structure Planning in NetPointWork Breakdown Structure Planning in NetPoint
Work Breakdown Structure Planning in NetPoint
PMA Consultants
 
How to Import/Export a Schedule between NetPoint and Microsft Excel
How to Import/Export a Schedule between NetPoint and Microsft ExcelHow to Import/Export a Schedule between NetPoint and Microsft Excel
How to Import/Export a Schedule between NetPoint and Microsft Excel
PMA Consultants
 
Smarter Planning with Microsoft Excel
Smarter Planning with Microsoft ExcelSmarter Planning with Microsoft Excel
Smarter Planning with Microsoft Excel
PMA Consultants
 
Leveraging NetPoint & Excel for Template-Based Project Planning
Leveraging NetPoint & Excel for Template-Based Project PlanningLeveraging NetPoint & Excel for Template-Based Project Planning
Leveraging NetPoint & Excel for Template-Based Project Planning
PMA Consultants
 
Risk 2196 Removing the Early-Dates Bias in CPM Risk Analysis
Risk 2196 Removing the Early-Dates Bias in CPM Risk AnalysisRisk 2196 Removing the Early-Dates Bias in CPM Risk Analysis
Risk 2196 Removing the Early-Dates Bias in CPM Risk Analysis
PMA Consultants
 
The Value of Project Risk Management
The Value of Project Risk ManagementThe Value of Project Risk Management
The Value of Project Risk Management
PMA Consultants
 
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
PMA Consultants
 

More from PMA Consultants (20)

Practical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital ProjectsPractical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital Projects
 
Project Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons LearntProject Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons Learnt
 
PANDEMIC RESILIENTSCHOOLS
PANDEMIC RESILIENTSCHOOLSPANDEMIC RESILIENTSCHOOLS
PANDEMIC RESILIENTSCHOOLS
 
BioPharma Projects: Essentials in Project Controls
BioPharma Projects: Essentials in Project ControlsBioPharma Projects: Essentials in Project Controls
BioPharma Projects: Essentials in Project Controls
 
How to Implement a Project Management Information System
How to Implement a Project Management Information SystemHow to Implement a Project Management Information System
How to Implement a Project Management Information System
 
Top Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule ReliabilityTop Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule Reliability
 
What are the disadvantages of Gantt charts?
What are the disadvantages of Gantt charts?What are the disadvantages of Gantt charts?
What are the disadvantages of Gantt charts?
 
BIM and VDC for Megaproject Construction Projects
BIM and VDC for Megaproject Construction ProjectsBIM and VDC for Megaproject Construction Projects
BIM and VDC for Megaproject Construction Projects
 
Setting up Filters & Layouts in P6
Setting up Filters & Layouts in P6Setting up Filters & Layouts in P6
Setting up Filters & Layouts in P6
 
How to Choose a Project Delivery Method
How to Choose a Project Delivery MethodHow to Choose a Project Delivery Method
How to Choose a Project Delivery Method
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry Klanac
 
Project Controls Processes
Project Controls ProcessesProject Controls Processes
Project Controls Processes
 
Work Breakdown Structure Planning in NetPoint
Work Breakdown Structure Planning in NetPointWork Breakdown Structure Planning in NetPoint
Work Breakdown Structure Planning in NetPoint
 
How to Import/Export a Schedule between NetPoint and Microsft Excel
How to Import/Export a Schedule between NetPoint and Microsft ExcelHow to Import/Export a Schedule between NetPoint and Microsft Excel
How to Import/Export a Schedule between NetPoint and Microsft Excel
 
Smarter Planning with Microsoft Excel
Smarter Planning with Microsoft ExcelSmarter Planning with Microsoft Excel
Smarter Planning with Microsoft Excel
 
Leveraging NetPoint & Excel for Template-Based Project Planning
Leveraging NetPoint & Excel for Template-Based Project PlanningLeveraging NetPoint & Excel for Template-Based Project Planning
Leveraging NetPoint & Excel for Template-Based Project Planning
 
Risk 2196 Removing the Early-Dates Bias in CPM Risk Analysis
Risk 2196 Removing the Early-Dates Bias in CPM Risk AnalysisRisk 2196 Removing the Early-Dates Bias in CPM Risk Analysis
Risk 2196 Removing the Early-Dates Bias in CPM Risk Analysis
 
The Value of Project Risk Management
The Value of Project Risk ManagementThe Value of Project Risk Management
The Value of Project Risk Management
 
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
 
P6 tips tricks-client
P6 tips tricks-clientP6 tips tricks-client
P6 tips tricks-client
 

Recently uploaded

What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).pptENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
zechu97
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
Ben Wann
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
LR1709MUSIC
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
SynapseIndia
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
awaisafdar
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
KaiNexus
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
Bojamma2
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
uae taxgpt
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 

Recently uploaded (20)

What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).pptENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 

Schedule levels-as-presented 02-may11

  • 2. Scheduling a Project At Different Levels Gui Ponce de Leon PhD, PE, PMP, LEED AP Philip Spittler PMP PMA Consultants, LLC May 2, M 2 2011 02 May 11 2
  • 4. Scheduling a Project at the Right Level at the Right Time Level, An important consideration in planning and scheduling During management planning When executive and senior managers are involved Project-level schedules prevail Schedules become detailed as the planning horizon switches from the whole of the project to stages or phases With assumptions tested and information firmed-up Management can engage in detailed planning Various participants have different levels of interest Some consensus but yet to reach standard status y 02 May 11 4
  • 5. Protocols Considered Jelen’s schedule levels The CII schedule levels Guide to the Forensic Scheduling Body of Knowledge Part I (FSBOK Guide) AACE International Recommended Practice No. 37R-06 Schedule Levels of Detail─As Applied in Engineering, Procurement and Construction (RP 37) ( ) The Chartered Institute of Building Guide to Good Practice in the Management of Time in Complex Projects (CIOB Guide) Mosaic’s Schedule Levels─Major Projects DOE Schedule Planning and Development Guide 1.8 02 May 11 5
  • 6. Jelen s Jelen’s Levels 02 May 11 6
  • 7. Varying Interpretations of Level 2 Schedules in Construction S h d l i C t ti 02 May 11 7
  • 8. Recent Developments RP 37 describes a 5-level method based on schedule level requirements, levels of interest and the intended use of each schedule level This RP 37 method is based on Stephenson’s levels The CIOB Guide advocates five schedule reporting levels le els Levels 1 - 3 accomplished through summarizations Activity duration ranges vary within a schedule based on planning h i l i horizon Neither the PMBOK Guide nor The Practice Standard for Scheduling deals with schedule levels Weaver/Mosaic offers a hierarchy of Level 1–5 schedules, from summary- to detailed- level schedules Activity duration ranges may vary either based on schedule y g y y level or planning horizon within a schedule 02 May 11 8
  • 9. The CSI Approach to Construction WBS Hierarchy The Construction Specifications Institute publishes the MasterFormat, a master list th t classifies project work M t F t t li t that l ifi j t k by deliverables and components and by construction practices General Requirements Division 01 Facility Construction Divisions 02-19 Facility Services Divisions 20-29 Site and Infrastructure Divisions 30-39 Process Equipment Divisions 40-49 The MasterFormat is one scheme that can be used to organize the project WBS, detail cost accounts and activity codes 02 May 11 9
  • 10. Guide to the Forensic Scheduling Body of Knowledge A schedule hierarchy for coherent summary and detailed detailed- level schedules intended for mega contracts and major contracts, but scalable to other contracts; it advocates: Network-based Network based level 1 4 schedules 1–4 Maintaining the Level 1 schedule and Level 2 schedule─both in time-scaled network format─current for the duration of the project Limiting rolling wave planning techniques to Level 4 schedules Suitable to top-down and roll-up integration Top-down─base a lower-level schedule on the next higher level Roll-up─carry re-baselining and updating to higher levels By way of example, the hierarchy is aligned with the MasterFormat approach to construction WBS hierarchies 02 May 11 10
  • 11. FSBOK Guide Level 1 Executive Schedule E ti S h d l General Intent and Format Establishes Contractual Milestones (if Included with the Request for Bids) or Demonstrates Conformance to Contractual and Other Milestones (if Included with the Bid and/or the Contract) Time-Scaled Network Diagram─Commonly One g y Sheet Kept Current with Level 2 Compares t RP 37 L C to Level 1 Wi k i et al. L l 1, Wickwire t l Level 1 l and Mosaic Level 1 02 May 11 11
  • 12. FSBOK Guide Level 1 Executive Schedule E ti S h d l Scheduling Objective Portrays Controlling, Summary-Level Activity(ies) Between Milestones at CSI Division Grouping Level Key Procurement Scope and Overall Commissioning Sequence Included Empirical Mega Construction Activity Duration: 20% to 40% of Contract, Generally 6 to 18 Months Empirical Major Construction Activity Duration: 10% p j y to 30% of Contract, Generally 3 to 12 Months 02 May 11 12
  • 13. FSBOK Guide Level 2 M Management S h d l t Schedule General Intent and Format Project Manager Input and Sign-Off Developed with the Bid or Before Mobilization Time-scaled Network Diagram Establishes the Critical Path, Near-Critical Paths and Key Target Dates for the Initial (Rev. 0) Progress Schedule Conforms to the Construction Plan, Including Constructability, Targeted Means and Methods, Craft Levels and Shared-Resource Dependencies Mostly Finish-to-Start Logic Ties Roll-Up of Level 3 Re-Baselining and Updating Compares to RP 37 Level 2 and Mosaic Level 2 02 May 11 13
  • 14. FSBOK Guide Level 2 M Management S h d l t Schedule Scheduling Objective Driving Path for Structures & Major P D i i P th f St t M j Process S t Systems at CSI t Division Level (e.g., Earthwork, Foundations, Framing, etc.) May Subdivide Into Area Grouping or Tier Grouping Constructability and Normal Adverse Weather-Validated Long-Lead Equipment & Material Procurements and Critical Commissioning Sequences Empirical Construction Activity Duration: Mega contracts: 10% to 20% of Contract, Generally 3 to 9 Months Major Contracts: 5% to15% of Contract, Generally 2 to 6 Months Lower end is for activities for which hard logic applies Upper limit is for activities scoping bulk commodities 02 May 11 14
  • 15. FSBOK Guide Level 3 P Progress S h d l Schedule General Intent and Format Site/Construction Manager Input and Sign-Off Time-scaled Network Diagram or Bar Chart with Logic Drives the Updating Process Integrates Vendor Design, Fab/Delivery, Construction, System Completion and Commissioning May be Craft Loaded (Typically, Critical Crafts) and Rely on Critical Shared-Resource Dependencies (e.g., Shared Crane) ) Activity Cost Loading, if Contractually Required Compares to RP 37 Level 3, Wickwire et al. Level 2 and Mosaic Level 3 02 May 11 15
  • 16. FSBOK Guide Level 3 P Progress S h d l Schedule Scheduling Objective Grouping of CSI Divisions in Areas or Elevations for Structures and Major Process Systems Level 2 Earthwork, Foundation, Framing etc Subdivided Earthwork Foundation Framing, etc. into Component Chunks Normal Adverse Weather-Validated Detailed Delivery Sequences and Integrated, Detailed Commissioning Sequence Formula Mega Construction Activity Duration: 2% to 5% g y of Contract, Generally 3 to 12 Weeks Formula Major Construction Activity Duration: 1% to 3% of Contract, 2 to 6 Weeks Contract 02 May 11 16
  • 17. FSBOK Guide Level 4 W ki S h d l Working Schedules General Intent and Format Supervision Input and Sign-Off Developed Before Starting a Phase or Area Often Developed as Separate Schedules p p Time-scaled Network Diagrams or Bar Charts with Logic Coordinated with Field Supervision (Contractor) and Subcontractor Input Trade Coordination May be Craft Loaded and Detail Crew Movements and other Means & Methods May be Done on a Rolling Wave Basis (e.g., Every 3 Months) Compares to RP 37 Level 4, Wickwire et al. Level 3 and Mosaic L M i Level 4 l 02 May 11 17
  • 18. FSBOK Guide Level 4 W ki S h d l Working Schedules Scheduling Objective Groups CSI Sections Within Elevation or Area for Structure or Process System Level 3 Earthwork, Foundation, Framing Enclosure MEP Earthwork Foundation Framing, Enclosure, & Process Installations Subdivided into Fragnets; Activities Biased Towards a Subcontractor or Trade Normal Ad N l Adverse W th V lid t d Weather-Validated Working-Level Detail in Procurement and Commissioning Formula Mega Construction Activity Duration: 1% to 3% g y of Contract, Generally 2 to 6 Weeks Formula Major Construction Activity Duration: 1% to 2% of Contract, Generally 2 to 4 Weeks Contract 02 May 11 18
  • 19. FSBOK Guide Level 5 L k Ah d S h d l Look-Ahead Schedule General Intent and Format Subdivide Progress and Upcoming Level 3 or Level 4 Activities into Tasks for the Next 2 to 3 Weeks Developed by Crew Foreman Typically in Bar Charts or Similar Format Tasks are Crew Loaded Reviewed in Site Progress Meetings g g Compares to RP 37 Level 5 and Mosaic Level 5 02 May 11 19
  • 20. FSBOK Guide Level 5 L k Ah d S h d l Look-Ahead Schedule Scheduling Objective Work Assigned to Crews Broken Down by Specific Components, Based y p p on Verification That Work Can Proceed and That Materials, Design Documentation and Other Installation Information are Packaged and Made Available to Crew Foremen Task Duration: From a Few Days to Three y Weeks 02 May 11 20
  • 21. FSBOK Guide Advocates Network- Based Level 1 4 S h d l B dL l 1-4 Schedules Absent Contrary Contractual Language: y g g Level 2 schedules and Level 3 schedules are appropriate forecasting tools to evaluate: Timely performance Delay and disruption, and Time extension requests Whether When Wh such ih issues arise, or i Where the evaluation is undertaken post-completion 02 May 11 21
  • 22. FSBOK Guide View of Level 2S h d l Schedules g A Relevant and Reliable Forecasting Tool if: In a time-scaled network format It portrays the contractor’s plan at contract award at an appropriate granularity t i t l it It remains current and in conformance to the contract It establishes the critical/near-critical paths based: On contract dates On the construction plan, e.g., means and methods, etc. On normal adverse weather On key deliveries 02 May 11 22
  • 23. FSBOK Guide View of Level 3S h d l Schedules As Source Document for Forensic Modeling g Depending on the analysis method used, a Level 3 schedule may be overly detailed, particularly where not relevant to the facts of the case t l t t th f t f th Forensic analysis using a Level 3 schedule may divert attention to non issues and detract from the non-issues issues in dispute without gaining analysis accuracy Where this compromises analysis accuracy, an p y y, acceptable protocol is to generate a reliable summarization of the Level 3 schedule 02 May 11 23
  • 24. FSBOK Guide View of Level 4 and L d Level 1 S h d l l Schedules The subdivisions of Level 3 schedule activities existing in a Level 4 schedule are often suitable bases for time impact analysis at the fragnet level A Level 1 schedule i a time-scaled network f L l h d l in i l d k format that is coherent with the Level 2 schedule is a valid source for a forensic demonstrative provided: demonstrative, It portrays controlling summary activities between milestones at the CSI Division Grouping Level or equivalent indenture in another WBS scheme It includes critical procurement activities, commissioning activities and, possibly, schedule reserve 02 May 11 24
  • 25. Example of a Level 1 Schedule 02 May 11 25
  • 26. Schedule Granularity vs. Schedule Density When the Wh th project i scheduled i multi-level schedules j t is h d l d in lti l l h d l For instance, where separate rolling wave Level 4 schedules are generated, it is practical to design Level 2 and Level 3 schedules with uniform activity duration ranges Where duration range is uniform for the duration of level 2-3 schedules, appropriate to the level in the hierarchy The Th term activity or schedule granularity i used rather than i i h d l l i is d h h schedule density CIOB Guide schedule density implies varying duration ranges within a schedule ithi h d l FSBOK Guide schedule granularity prescribes a uniform duration range for each schedule g 02 May 11 26
  • 27. Recapping the FSBOK Guide Hierarchy Main Points Network-based schedules at all levels but for look-ahead Better ensures relevant and reliable forecasting tools ALLevel 2 schedule k t current f th project d ti l h d l kept t for the j t duration promotes continuing executive and senior management involvement when re-baselining schedule performance Derive a lower-level schedule from the next higher-level Limit use of rolling wave planning techniques to Level 4 Hold schedule granularity uniform as opposed to varying schedule density with planning horizon Interplay between WBS and Schedule level 02 May 11 27
  • 28. The Downside of Schedules that Become Massive as D M i Density I it Increases When the schedule multiplies in the number of activities as schedule density increases from update to update, its usefulness as a relevant reliable forecasting tool degrades relevant, Schedule integrity is affected by data machinations the scheduler may have engaged in to attain realistic dates and critical paths Ever-growing multi-thousand activity schedules trend toward a highly-disordered schedule document 02 May 11 28
  • 29. FSBOK and CIOB Guidance on Activity Duration R A i i D i Ranges 02 May 11 29
  • 30. FSBOK Guide Schedule Hierarchy in Summary 02 May 11 30
  • 31. The Sayonara Conclusion The time has come to bid farewell to bar chart techniques for Level 1 and Level 2 schedules, as well as Level 4 schedules This will not only promote more coherent p planning, but will allow all contemporaneous g, p schedules to play a role in forensic scheduling 02 May 11 31
  • 32. The TMI Conclusion An alternative to working with Level 3 schedules that become massive as schedule density increases is to approach the scheduling of a project in a multi-level schedule sequence that involves Deriving a lower-level schedule from the next higher-level schedule Limiting reliance on rolling wave planning techniques to the network-based Level 4 schedules For any schedule in the hierarchy, maintaining granularity unniform, from beginning to end, better ensures a highly-ordered network of realistic dates and reasonable floats, ergo a relevant and reliable forecasting document 02 May 11 32
  • 33. The Less is More… You Had Me at Level 2 Conclusion The activity granularity designed into a Level 2 schedule is likely to yield a relevant and reliable source document for forensic schedule analysis Because of the activity granularity typically followed, a Level 3 schedule may detail paths not relevant to the facts of the case; analyzing non- non issues may detract from and confuse the issues in dispute without gaining analysis accuracy The d t il i Th detail in a Level 3 schedule used i f L l h d l d in forensic i schedule analysis should be made proportionate to the facts at issue by means of reliable summarizations 02 May 11 33
  • 34. The New Standard Conclusion Favor approaching the scheduling of a project in separate but coherent summary- and detailed-level schedules, each schedule with uniform granularity Note ─the principles discussed are adaptable to schedule level approaches that are based on pp one schedule designed at different levels of detail by varying schedule density based on planning horizon 02 May 11 34
  • 35. Thank You For Attending! 02 May 11 35