WM2012 Conference, February 26 – March 1, 2012, Phoenix, Arizona, USA 
1 
Improving DOE Project Performance Using the DOD Integrated Master Plan – 12481 
Glen B. Alleman, DOD Programs, Project Time & Cost and Michael R. Nosbisch, Managing Principle, Western Region, Project Time & Cost 
ABSTRACT 
DOE O 413 measures a project’s progress to plan by the consumption of funding, the passage of time, and the meeting of milestones. In March of 2003, then Under Secretary, Energy, Science, Card received a memo directing the implementation of Project Management and the Project Management Manual, including the Integrated Master Plan and Integrated Master Schedule. This directive states “the integrated master plan and schedule tie together all project tasks by showing their logical relationships and any constraints controlling the start or finish of each task. This process results in a hierarchy of related functional and layered schedules derived from the Work Breakdown Structure that can be used for monitoring and controlling project progress.” This paper shows how restoring the IMP/IMS paradigm to DOE program management increases the probability of program success in ways not currently available using DOD O 413 processes alone. 
INTRODUCTION 
The measures of progress to plan in units meaningful to the decision maker are needed to answer the question – How Long Are We Willing to Wait before We Find out We Are Late? As recently as January of 2011 updates to DOE O 413.3B were made with focus on four philosophical goals. [3] With this 2011 directive and the 2003 memo to Robert Card (Project Management and the Project Management Manual) [1] addressing the use of Integrated Master Plans and Schedules in Section 6.5.1, the measures needed to answer this question are still not specifically stated in the most recent version of the DOE O 413 series. However, the DOD 5000.02 and Integrated Master Plan (IMP) paradigm provides the mechanism to answer the question and should be adopted by DOE. The IMP, as applied by the DOD, defines the incremental increase of a project’s maturity, assessed through Significant Accomplishments (SA) and Accomplishment Criteria (AC), using Measures of Effectiveness (MoE), Measures of Performance (MoP), and Technical Performance Measures (TPM). [2] 
The memo to Card reflects a nearly identical structure to the DOD Integrated Master Plan and establishes DOE M 413.3–1 (Project Management for the Acquisition of Capital Assets) as a primary guidance document using the IMP/IMS in 2003. But the current DOE O 413.3–1 does not include the use on an Integrated Master Plan (IMP) [7], [11]. 
Applying Card’s 2003 DOD IMP paradigm to DOE O 413 series projects will improve the probability of DOE project success through measures of increasing maturity of the deliverables defined in the Integrated Master Plan (IMP), in addition to measures of progress through cost and schedule performance and milestone compliance. [3] 
For motivation for this IMP/IMS approach, we need only look to recent reports that provide a sample of assessments: GAO–07–336 Major Construction Projects Need a Consistent Approach for Assessing Technology Readiness to Avoid Cost Increases and Delays [4], GAO– 09–406 Contract and Project Management Concerns at NNSA and Office of EM [5] and GAO– 08–1081 Nuclear Waste: Action Needed to Improve Accountability and Management of DOE’s Major Cleanup Projects [6].
2 
These GAO reports found that …: 
 … the cost increases and schedule delays that have occurred for most of these projects have been the result of inconsistent application of project management tools and techniques on the part of both DOE and its contractors.[5] 
 … exceeded their original cost or schedule estimates, principally because of ineffective DOE project oversight and poor contractor management. [4] 
 … had life cycle baseline cost increases, from a low of $139 million for one project to a high of nearly $9 billion for another, and life cycle baseline schedule delays from 2 to 15 years. These changes occurred primarily because the baselines we reviewed included schedule assumptions that were not linked to technical or budget realities and the scope of work included other assumptions that did not prove true. [6] 
Project success depends on answering 5 immutable questions, no matter the domain or the project context in that domain, the project management method, or the agency guidance. 
1. What does “Done” look like? 
2. What is the path to reaching “Done” on time, on budget, and technically compliant? 
3. What resources (time, money, staff, and facilities) are needed to reach “Done? 
4. What impediments will prevent reaching “Done”? 
5. How is physical progress to plan measured on the path to “Done?” 
Project success starts with describing what “Done” looks like in units of measure meaningful to the decision makers. These measures of performance (technical and programmatic) and effectiveness (the customer’s point of view) are derived from the elements of the Integrated Master Plan – Program Events, Significant Accomplishments, and the Accomplishment Criteria of the baselined Work Packages. 
DOE G 413.5 (Performance Measurement Baseline) describes the measurement of progress to plan through Key Performance Parameters (KPP), Cost, and Schedule Performance. These measures do not answer the 5 immutable questions stated above. The answers need to be in units of Increasing Maturity of the project outcomes. [8] 
DOE O 413.3b (Program and Project Management for the Acquisition of Capital Assets) mentions the term maturity 14 times. [9] DOE O 413.3–9 (Project Review Guide for Capital Asset Projects) mentions maturity 9 times.‡ DOE G 413.3–7A (Risk Management Guide) provides guidance for assessing increasing project maturity. [10] 
None of these Orders or Guides states HOW to measure increasing maturity or HOW to use these measures to increase the probability of success of the project. The DOD applies the Integrated Master Plan (IMP) paradigm, to assess the increasing maturity of the project through Measures of Effectiveness (MoE), Measures of Performance (MoP), Key Performance Parameters (KPP), and Technical Performance Measures (TPM) to assess the increasing Probability of Project Success (PoPS). The DOD approach is distinctly different from the horizontal master scheduling described in the DOE O 413 series guidance. 
EVENT BASED PLANNING IS THE BASIS OF STRATEGY MAKING 
From Card’s memo we have a clear and concise connection between the Integrated Master Plan (IMP) and the supporting Integrated Master Schedule (IMS) and the management of DOE projects guided by DOE O 413.3. The following words appear in §6.5.1 of Card’s memo and attached manual section [1]. 
‡ NASA style Technology Readiness Levels have been suggested for the DOE through GAO-07-336 [4]
3 
An integrated master plan is a very effective tool for project management. It is the contractor’s event–based plan for accomplishing the requirements contained in Statements of Work, Performance Work Statements, Work Authorizations, and other documents which communicate requirements to the contractors. The plan identifies the key activities, events, milestones, and reviews that make up the program or project. 
The program or project office, support contractors or the prime contractor may prepare the plan. The plan also identifies those events and activities that will be included in the integrated master schedule. The integrated master schedule is a networked multilayered schedule generated by the contractor that begins with all identified integrated master plan events, accomplishments, and criteria. It also shows the expected start and finish dates of these events and contains all contractually required events and milestones such as reviews, tests, completion dates, and deliveries specified in the Work Breakdown Structure. 
The integrated master plan is prepared prior to completion of the Conceptual Design process and is subsequently maintained by the government and the contractor through a collaborative effort involving all the stakeholders. The integrated master plan and schedule tie together all project tasks by showing their logical relationships and any constraints controlling the start or finish of each task. 
This process results in a hierarchy of related functional and layered schedules derived from the Work Breakdown Structure that can be used for monitoring and controlling project progress. * 
Strategy Making, IMP/IMS, and Systems Engineering 
Building products or facilities, providing services, or remediating environments is a systems engineering process. † Components, processes, participants, and their outcomes interact in ways that are described as a system. Engineering of these systems is an interdisciplinary process that deals with the work and tools that manage risk, technical activities, and the human centered disciplines need for success. The strategy for these activities is represented in the DOD by the Integrated Master Plan. 
The IMP/IMS is a step by step process to increase the probability of project success by: 
1. Creating A Vision Of The Outcome – described in the Concept of Operations (ConOps) or Statement of Objectives (SOO). 
2. Analyzing The Current Situation – to determine viable alternatives for the desired outcomes. 
3. Determining A Strategy – for moving from the current situation to the outcome, what “maturity increasing” activities must be performed to move forward. 
4. Selecting The Systems Development Activities – needed to move the “increasing maturity” forward through Significant Accomplishments (SA). 
5. Constructs A Plan Based On These Activities – arrange the SAs in a logical sequence for each Program Event (PE) to provide increasing level of maturity of the products or service. 
* These words taken directly from the attached Manual in the memo are nearly identical to DI–MGMT–81650, Integrated Master Schedule, with three levels of Master Schedules. The terms Significant Accomplishment and Accomplishment Criteria are used directly in Card’s memo they are connected from DID–81650 to the current – under review – is DI–MGMT–81466B, where the Integrated Master Plan (IMP) is mentioned. The DOD Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide shows how the connected the resulting IMP with the IMS mentioned in Card’s memo. 
† “Project Management vs. Systems Engineering Management: A Practitioners’ View on Integrating the Project and Product Domains,” Amira Sharon,Olivier L. de Weck, and Dov Dori, Systems Engineering, Volume 14, Number 4, 2011.
4 
6. Performing A Pilot Set Of Activities – to confirm they result in desirable outcomes. 
7. Evaluating These Results – “test” the logic of the SAs to assure increasing maturity will result. 
8. Executes The Processes – in steps 6 and 7 until the outcome is reached by developing the Accomplishment Criteria (AC) for each SA and the top activities for each AC. 
This IMP/IMS approach is the basis of all credible development activities in the DOD. The challenge for the DOE becomes finding how the details of each step are to be defined, developed, and executed in the context of DOE O 413.3b. 
STRUCTURE OF THE INTEGRATED MASTER PLAN IN THE DEPARTMENT OF DEFENSE 
The Integrated Master Plan showing how work is performed, the criteria for the compliance of that work with the Technical Performance Measures, and the Accomplishments needed to deliver a capability are shown in Figure 1. 
This approach provides tangible evidence of progress to plan in units of measure meaningful to the decision makers. These units include Measures of Effectiveness (MoE) from the customer’s point of view, Measures of Performance (MoP) from the contractor’s or owner’s point of view, the agreed Key Performance Indicators (KPP), and the Technical Performance Measures (TPM) for all work activities. 
The trends in these measures (MoP, MoE, KPP, and TPM) reveal project progress and when compared with standard contingency values, highlight when corrective actions should be considered. These measures of the system technical performance have been chosen because they are indicators of increasing maturity of the project outcomes that impact the probability of project success. They are based on high risk or significant driving requirements or technical parameters. These measures are analogous to the programmatic measures of expected total cost or estimated time–to–completion (Earned Value Management measures). 
Actual versus planned progress of these measures are tracked through the IMP/IMS so engineers, constructors, and project managers can assess progress and the risk associated with each measure. These measures are attached to each Significant Accomplishment and Accomplishment Criteria shown in Figure 1 to provide measures of increasing maturity, as well as other measures needed to assess the probability of project success. 
These measures are distinctly different from measures of cost and schedule performance and their related milestone compliance. Cost, schedule, and milestone compliance are necessary, but do not sufficient to provide visibility into the effectiveness of the project for the customer. Measures of Effectiveness (MoE) are operational measures of. Measures of Performance (MoP) characterize physical or functional attributes relating to the system operation, measured or estimated under specific conditions. Key Performance Parameters (KPP) represents the capabilities and characteristics significant enough that failure to meet them can be cause for reevaluation, reassessing, or termination of the project. 
These three measures (MoE, MoP, and KPP) are the heart of the IMP/IMS Significant Accomplishments and their Accomplishment Criteria that provide direct measure of increasing maturity of the projects outcomes.
5 
Department of Defense Processes Integrated with DOE O 413.3b and 413.5 
The U.S. Department of Defense (DOD) makes use of Event Based Plans to define the integrated product development and integration using measures of increasing maturity. This approach enhances project planning, scheduling, and successful execution. This plan is a hierarchy of Project Event(s), each event supported by specific Accomplishments, and each accomplishment associated with specific Criteria to be satisfied for its completion. 
This approach is different from the traditional horizontal schedule that measures progress through cost and schedule performance. While deliverables are defined in the Integrated Master Schedule (IMS), measures of Effectiveness (MoE), Performance (MoP), and its related Key Performance Parameters (KPP) and Technical Performance Measures (TPM) are not embedded in the Performance Measurement Baseline (PMB). 
By applying the IMP paradigm, a vertical Plan is created where each Accomplishment defines the desired result(s) prior to the completion of an Event that indicates a level of the project’s progress. Accomplishment Criteria provide tangible evidence that a specific accomplishment has been completed according to its Measure of Effectiveness and Measure of Performance. 
Figure 1 – The work performed in the sequence Work Packages is assessed for compliance with Technical Performance Measures, Measures of Effectiveness (MoE), and Measures of Performance (MoP). The result is a description of the increasing maturity of the product or service resulting from the project.
6 
DOE G 413.5 Performance Measurement Baseline defines the Scope, Design, Key Performance Parameters, Cost, Schedule, and supporting Documentation for the project. But this PMB does not define the Accomplishments and Criteria that must be met to successfully deliver the outcomes of the project. 
Using the IMP paradigm, units of measure of performance meaningful to the decision makers are installed in the PMB from the Accomplishments and Criteria for the detailed work activities. This approach makes the Integrated Master Schedule (IMS) clearer by showing what DONE looks like in terms of deliverables and the criteria for success of those deliverables embedded in the IMS. 
The connection of the performance of work efforts to the Criteria, Accomplishments, and Project Events is the Earned Value Management (EVM) System. The EVM System defines the measures of progress to plan at the work performance level. These measures are used to define progress for each Criteria and Accomplishment. This provides Project Management with direct measures of physical percent complete for each deliverable from the project. 
Figure 1 shows the programmatic structure needed to improve the probability of project success, using the Integrated Master Schedule paradigm, with Accomplishments, and Criteria as measures of project performance based on MoE, MoP, and TPMs. Figure 2 shows how each of these measures is related to produce visibility to the performance of the project. 
How the Department of Defense Measures Maturity of the Project’s Outcomes 
DOE O 413.3b mentions maturity 14 times in the context of design, procurement, and technology readiness assessment. The measure of maturity has two sides of a project – the buyer side and the producer side, i.e. The Customer and the Builder. 
 Measures of Effectiveness – are closely related to the achievements of the mission or operational objectives evaluated in the operational environment, under a specific set of conditions. MoE’s are stated in units meaningful to the buyer and focus on the capabilities independent of any technical implementation, and are connected to the mission success. 
 Measures of Performance – characterize physical or functional attributes relating to the system operation measured or estimated under specific conditions. MoP’s are attributes that assure the system has the capability to perform and assure the design requirements can satisfy the Measures of Effectiveness. 
Along with the Measures of Effectiveness and Measures of Performance, two other measures are needed to “connect the dots.” 
 Key Performance Parameters (KPP) – Represent the capabilities and characteristics so significant that failure to meet them can be cause for reevaluation, reassessing, or termination of the project. KPPs have a threshold or objective value. These characterize the major drivers of performance and are considered Critical to Customer (CTC). 
 Technical Performance Measures (TPM) – are attributes that determine how well a system or system element is satisfying or expected to satisfy a technical requirement or goal. These measures assess the design process, define compliance to performance requirements, and identify technical risk, including projected performance. The TPMs are limited to critical thresholds.
7 
Figure 2 – connecting the measures needed for assessing increasing project maturity assures there is visibility to project performance in units of measure meaningful to the decision makers. 
CONNECTING DOE O 413.3B WITH DOD MEASURES OF MATURITY 
Table 1 is a summary of DOE O 413.3b’s Critical Design stages and the activities performed at each stage. For each of these, we’ll demonstrate how they would be applied in the Department of Defense Integrated Master Plan and Integrated Master Schedule paradigm and show how these connections can add value and increase the probability of success for DOE projects. 
Connections between the Critical Design stages and the elements of the Integrated Master Plan are shown in Table 2. These connections can be applied to current DOE O 413 series projects, guided with the Card memo [1] and the Bosco order [3]. 
The outcome of this approach is a programmatic architecture where performance is measured through cost and schedule adherence as well as direct measures of increasing maturity supported by measures of effectiveness and performance needed to assessing the probability of project success. 
Used Earned Value for activities contained in Work Packages, measures of physical percent complete toward the Accomplishment Criteria are provided. These Accomplishment Criteria are then direct measures of progress toward the Significant Accomplishments needed to measure this increasing maturity of each Program Event. 
This architecture is shown in Figure 1, where both vertical traceability to increasing maturity and horizontal traceability to activity progress are integrated in a single Performance Measurement Baseline.
8 
Project Acquisition Process and Critical Decisions 
Project Planning Phase 
Project Execution Phase 
Mission 
Pre–conceptual Design 
Conceptual Design 
Preliminary Design 
Final Design 
Construction 
Operations 
CD–0 CD–1 CD–2 CD–3 CD–4 
Actions Authorized by the Critical Design Approval 
 Proceed with the conceptual design. 
 Request PED funding. 
 Allow expenditure of PED funds. 
 Establish baseline budget for construction. 
 Continue design. 
 Request construction funding. 
 Approve expenditure of funds for construction. 
 Allow start of operations or project close out. Critical Design Pre–Requisites 
 Justification of mission need. 
 Acquisition strategy 
 Pre–conceptual planning. 
 Mission need. 
 Independent Project Review. 
 Acquisition plan. 
 Conceptual design. 
 Preliminary project execution plan and baseline range. 
 Project data sheet for design 
 Verification of mission need. 
 Preliminary hazard analysis report. 
 Preliminary design. 
 Review of contractor project management system. 
 Final project execution plan and performance baseline. 
 Independent cost estimate. 
 NEPA 
 Project data sheet for construction. 
 Draft preliminary Safety Analysis Report. 
 Performance Baseline External Independent Review. 
 Update project execution Plan and Performance Baseline 
 Final design and procurement packages. 
 Verification of mission need. 
 Budget and congressional authorization and appropriation enacted. 
 Approval of safety documentation. 
 Execution readiness Independent Review. 
 Operational readiness review. 
 Project transition to operations. 
 Final safety report. 
Table 1 – summary of CD activities from DOE O 413.3b, 29 November 2010 describe the attributes or exit criteria for each of the Critical Decision. The documents that define the processes and content of many of these deliverables do not directly speak to the increasing maturity of the project’s outcome. The terms “preliminary, draft, approved verified, and final,” are used but the Significant Accomplishments and the Accomplishment Criteria needed assessment the maturity of the project at each of these reviews is not defined.
9 
Mapping the IMP/IMS Paradigm to the DOE Critical Design Reviews 
The DOE O 413 series defines activities to be performed during the execution of a project. The DOD Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide defines how to build the IMP and IMS that will increase the probability of success for the project [2]. 
DOE O 413.3–9 and 413.3–16 Guidance DOD IMP/IMS Guidance CD–0: Approve Mission Need Understand the Project 
 Identification of a mission–related need and translation of this gap into functional requirements for filling the need. 
 The mission need is independent of a particular solution and should not be defined by equipment, facility, technological solution, or physical end item (413.3A). 
 The focus for Technology Assessment, at this stage, is on clear statement of the requirements of the input and the desired output of the process. 
 Define mission outcome as a Concept of Operations (ConOps) 
 Partition system capabilities into classes of service within operational scenarios. 
 Connect the capabilities to system requirements using some visual modeling notation. 
 Define Measures of Effectiveness (MoE) and Measures of Performance (MoP). 
 Define the delivery schedule for each measure of performance and effectiveness. CD–1: Alternative Selection and Cost Range Develop Project Structure 
 Identification of the preferred technological alternative, preparation of a conceptual design, and development of initial cost estimates 
 Assign costs to each system element using a value flow model. 
 Assure risk, probabilistic cost and benefit performance attributes are defined. 
 Use cost, schedule and technical performance probabilistic models to forecast potential risks to project performance. CD–2: Performance Baseline Create IMP / IMS 
 Completion of preliminary design, development of a performance baseline that contains a detailed scope, schedule, and cost estimate. 
 The process of technology development, in accordance with the approved TMP should support all CTEs reaching TRL 6; attainment of TRL 6 is preferable and indicates that the technology is ready for insertion into detailed design. 
 Decompose scope into work packages 
 Assign responsibility for deliverables 
 Arrange work packages in a logical order 
 Develop BCWS for work packages 
 Assign work package measures of performance 
 Set Performance Measurement Baseline CD–3: Start of Construction Execute Performance Measurement Baseline 
 Completion of essentially all design and engineering and beginning of construction, implementation, procurement, or fabrication. A TRA is only required if there is significant technology modification as detailed design work progresses. 
 If substantial modification of a technology occurs, the TRA should be performed and a focused TMP developed or updated to ensure that the modified technology has attained TRL 6, if possible, prior to its insertion into the detailed design and baseline. 
 Performance authorized work 
 Accumulate and report work package information 
 Analyze work package performance 
 Take corrective management action 
 Maintain Performance Measurement Baseline 
Table 2 – for each 413 CD, specific IMP/IMS guidance can be applied to increase the probability of project success, by creating evidence of increasing maturity in units of measure meaningful to the decision makers.
10 
CHANGING THE PROGRAM PLANNING PARADIGM FROM HORIZONTAL TO VERTICAL 
Building an IMP / IMS requires a change in the normal paradigm of project management. This change means stopping the measurement of progress as the passage of time and consumption of funding – to measuring progress by the completion of Accomplishment Criteria and the fulfillment of Significant Accomplishments. 
It means moving from horizontal scheduling to vertical planning. These words are probably meaningless at this point. The description of this paradigm provides an understanding of this concept, the benefits to the project management, and the processes needed to deliver these benefits. In many cases, the horizontal schedules are the starting point for the project. This occurs for several reasons: 
 The project started without an IMP or a real IMS. They first built a horizontal schedule in the manner of “shop floor” schedule. This is usually for the Period of Performance of the Program. 
 The project was inherited from a higher or lower level process. Either as a subcontractor or a part of on IPT team, the schedule is focused on the functional aspects of the project. 
In many cases, the conversion from horizontal to vertical planning is required or desired. The effort to do this conversion involves several steps: 
 Identify the Program Events and where in the schedule these events take place. 
 Identify which work in the schedule “lands” on which event. If there is work that crosses an Event boundary, then it will need to be “broken” into two (2) parts. One that “lands” on the Event and one that restarts at the completion of the Event. 
IMP / IMS FEATURES AND BENEFITS 
The IMP and IMS focuses on specific areas of the project, which have been shown to be problems with more traditional approaches. The primary focus is on project maturity Event based planning provides a “singularly” focused process allowing each IPT to answer the question – “what do I need to do for a specific event?” For example Preliminary Design Review (PDR): List all the accomplishments needed for PDR? What activities need to performed for each of these accomplishments? When all the activities are completed, the criteria satisfied, and the accomplishments completed then a measurement of “maturity” can take place? This approach is not described in the DOE O 413 series of guidance. Features of IMP/IMS Benefits to the Program Provides an understanding and alignment of required tasks with events starting with the proposal Drives down cost of execution by connecting changes with the impact of changes that occur early in the project life cycle when costs are lower are made visible from day one. 
Integrates relationships of products and development processes 
Improves management visibility by connecting activities with events Permits better understanding of risk and how it impacts cost, schedule, performance A disciplined approach to planning and implementation activities Provides a framework for using integrated tools, teams, and processes with vertical traceability Serves as foundation for systematic programmatic improvement efforts 
Iterative planning, tracking, and reporting process 
Allows project flexibility – on ramps and off ramps tied to events Highlights details early – ties maturity events with activities Event–Driven Planning Relates project events in terms of success – Accomplishments and Criteria Reduces risk by ensuring that maturity of the plan is incrementally demonstrated prior to starting follow–on activities 
Increases visibility of entire project to the project team 
Improves measurable maturity and impact analysis Promotes project buy–in and team commitment through shared events Fosters proactive management at all levels through measurable outcomes
11 
Features of IMP/IMS Benefits to the Program Resource and Earned Value Loadable Provides foundation for Earned Value Reporting and EVMS 
Key customer events included 
Encourages a win–win attitude with customers Clear communication of how the team views the project Improves effectiveness through a common set of tools, measurements and defined outcomes 
Table 3 – IMP/IMS features and that are not directly provided by executing DOE O 413 series guided projects using measures of cost, schedule, and milestone performance. 
THE PIECES NEEDED TO INCREASE THE PROBABILITY OF PROJECT SUCCESS 
Using the DOE Critical Decision (CD) review guide, the Integrated Master Plan paradigm is applied to increase the probability of project success. DOE CD Outcomes IMP / IMS Processes to create outcomes CD–0: Approve Mission Need 
 Developing the mission need and acquisition strategy 
 Define the Significant Accomplishment needed to fulfill the mission need and implementation strategy. 
 Define these in units of performance, effectiveness, and technical compliance. 
 Define the Measures of Effectiveness (MoE) and Measures of Performance (MoP) for each mission need. (see Figure 2 for relationship between these measures).  Pre–conceptual planning  Define the “increasing maturity” flow for the work needed to fulfill the mission need and acquisition strategy.  Define the Technical Performance Measures (TPM) for each outcome at the planned level of maturity – in the DOE language the Technology Readiness Level (TRL) has similar words CD–1: Alternative Selection and Cost Range  Preliminary project execution plan  Verification of mission need  Integrated Master Plan logical “Value” flow, showing how each outcome from the work efforts satisfies the Accomplishment Criteria in units of Measures of Effectiveness (MoE) and Measures of Performance (MoP) measured against the planned MoE and MoP.  Develop Basis of Estimate (BoE) for each Significant Accomplishment and Accomplishment Criteria (see Figure 1 for IMP/IMS structure).  Connect the BoEs with each measure of maturity and the planned cost to reach that level of maturity. CD–2: Performance (Measurement) Baseline  Preliminary design review  Review project management system  Final project execution plan  Independent cost estimate  External independent review  PDR and other reviews assess planned and actual maturity of Significant Accomplishments (SA) and the Accomplishment Criteria (AC).  Probabilistic assessment of cost, schedule, and technical performance for each SA and AC. CD–3: Start Construction  Final design review  Execution readiness review  Execute the Performance Baseline  Starting with the Work Packages, execute each Accomplishment Criteria and measure actual performance against planned performance using MoE and MoP. 
Table 4 – for each 413 CD, specific IMP/IMS processes and their outcomes increase the probability of project success through tangible evidence of increasing maturity in units of measure meaningful to the decision makers.
12 
CONCLUSION 
Using DOE O 413 series guidance, adding the Integrated Master Plan and Integrated Master Schedule paradigm would provide a hierarchical set of performance measures for each “package of work,” that provides measureable visibility to the increasing maturity of the project. 
This measureable maturity provides the mechanism to forecast future performance of cost, schedule, and technical outcomes in ways not available using just the activities in DOE O 413. With this information project managers have another tool available to address the issues identified in GAO–07–336 and GAO–09–406. 
REFERENCES 
[1] Memorandum for Robert G, Card, Undersecretary, Energy, Science, and Environment, March 31, 2003 from Kyle E. McSlarrow, “Project Management and the Project Management Manual.” http://www.fnal.gov/directorate/OPMO/DOE/o413/m4133-1.pdf 
[2] “Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide,” Version 0.9, August 15, 2005, Office of the Secretary of Defense (OSD), www.acq.osd.mil/se/docs/IMP_IMS_Guide_v9.pdf 
[3] “Significant Changes to DOE Order 413.3B,” January 21, 2011, Paul Bosco, Director, Office of Engineering and Construction Management. http://1.usa.gov/v6V5z6 
[4] GAO–07–336 Major Construction Projects Need a Consistent Approach for Assessing Technology Readiness to Avoid Cost Increases and Delays. 
[5] GAO–09–406, Contract and Project Management Concerns at NNSA and Office of EM 
[6] GAO–08–1081, Nuclear Waste: Action Needed to Improve Accountability and Management of DOE’s Major Cleanup Projects. 
[7] DOE O 413.3, Program and Project Management for the Acquisition of Capital Assets, included in Memo to Robert Card, March 31, 2003 from Kyle E. McSlarrow. Memo available at http://www.fnal.gov/directorate/OPMO/DOE/o413/m4133-1.pdf 
[8] DOE G 413.5, Performance Measurement Baseline. 
[9] DOE O 413.3b Program and Project Management for the Acquisition of Capital Assets. 
[10] DOE G 413.3–7A Risk Management Guide. 
[11] “Integrated Master Plan Analysis: The PMAG Approach,” Col. Mun H. Kwon, USAF, Defense AT&L, January–February, 2010, pp. 39–43.

More Related Content

What's hot

Introduction à la GPP - Gestion de portefeuille de projets
Introduction à la GPP - Gestion de portefeuille de projetsIntroduction à la GPP - Gestion de portefeuille de projets
Introduction à la GPP - Gestion de portefeuille de projetsClaude Emond
 
PM Project-Charter.pptx
PM Project-Charter.pptxPM Project-Charter.pptx
PM Project-Charter.pptxNimra zaman
 
Integrated Master Schedule
Integrated Master ScheduleIntegrated Master Schedule
Integrated Master Scheduleellefsonj
 
Synthèse : démarche de mise en oeuvre d'un portefeuille projets
Synthèse : démarche de mise en oeuvre d'un portefeuille projetsSynthèse : démarche de mise en oeuvre d'un portefeuille projets
Synthèse : démarche de mise en oeuvre d'un portefeuille projetsCOMPETENSIS
 
3 levels of a pmo to support program and project management
3 levels of a pmo to support program and project management3 levels of a pmo to support program and project management
3 levels of a pmo to support program and project managementPMOfficers PMOAcademy
 
Program Management Playbook
Program Management PlaybookProgram Management Playbook
Program Management PlaybookLenovo
 
How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)Insaf Ali Soomro PMP
 
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptxWajihAnsari7
 
The project management process groups a case study
The project management process groups a case studyThe project management process groups a case study
The project management process groups a case studyAfdalArifAmandaPutra
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
PRINCE2 - Presentation
PRINCE2 - PresentationPRINCE2 - Presentation
PRINCE2 - PresentationMatt Trigg
 
Performance Improvement Culture
Performance Improvement CulturePerformance Improvement Culture
Performance Improvement CultureAnand Subramaniam
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
Business Case Template
Business Case TemplateBusiness Case Template
Business Case TemplateDemand Metric
 
Project Manager Job Description
Project Manager Job DescriptionProject Manager Job Description
Project Manager Job DescriptionDemand Metric
 
Goal Setting for PMO with OKR
Goal Setting for PMO with OKRGoal Setting for PMO with OKR
Goal Setting for PMO with OKRJohn McIntyre
 

What's hot (20)

PMO as a service
PMO as a servicePMO as a service
PMO as a service
 
Introduction à la GPP - Gestion de portefeuille de projets
Introduction à la GPP - Gestion de portefeuille de projetsIntroduction à la GPP - Gestion de portefeuille de projets
Introduction à la GPP - Gestion de portefeuille de projets
 
PM Project-Charter.pptx
PM Project-Charter.pptxPM Project-Charter.pptx
PM Project-Charter.pptx
 
Integrated Master Schedule
Integrated Master ScheduleIntegrated Master Schedule
Integrated Master Schedule
 
OKR Playbook v1.0
OKR Playbook v1.0OKR Playbook v1.0
OKR Playbook v1.0
 
Synthèse : démarche de mise en oeuvre d'un portefeuille projets
Synthèse : démarche de mise en oeuvre d'un portefeuille projetsSynthèse : démarche de mise en oeuvre d'un portefeuille projets
Synthèse : démarche de mise en oeuvre d'un portefeuille projets
 
3 levels of a pmo to support program and project management
3 levels of a pmo to support program and project management3 levels of a pmo to support program and project management
3 levels of a pmo to support program and project management
 
Program Management Playbook
Program Management PlaybookProgram Management Playbook
Program Management Playbook
 
How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)
 
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
 
The project management process groups a case study
The project management process groups a case studyThe project management process groups a case study
The project management process groups a case study
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
PRINCE2 - Presentation
PRINCE2 - PresentationPRINCE2 - Presentation
PRINCE2 - Presentation
 
Performance Improvement Culture
Performance Improvement CulturePerformance Improvement Culture
Performance Improvement Culture
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Business Case Template
Business Case TemplateBusiness Case Template
Business Case Template
 
Opm3 050607 hkcs
Opm3 050607 hkcsOpm3 050607 hkcs
Opm3 050607 hkcs
 
Project Manager Job Description
Project Manager Job DescriptionProject Manager Job Description
Project Manager Job Description
 
Goal Setting for PMO with OKR
Goal Setting for PMO with OKRGoal Setting for PMO with OKR
Goal Setting for PMO with OKR
 
PMO 101
PMO 101PMO 101
PMO 101
 

Viewers also liked

Deliverables Based Planning
Deliverables Based PlanningDeliverables Based Planning
Deliverables Based PlanningGlen Alleman
 
Risk management using risk+ (v5)
Risk management using risk+ (v5)Risk management using risk+ (v5)
Risk management using risk+ (v5)Glen Alleman
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News WebinarGlen Alleman
 
Agile in the government
Agile in the government Agile in the government
Agile in the government Glen Alleman
 
Capabilities based planning (v2)
Capabilities based planning (v2)Capabilities based planning (v2)
Capabilities based planning (v2)Glen Alleman
 
Paradigm of agile project management
Paradigm of agile project managementParadigm of agile project management
Paradigm of agile project managementGlen Alleman
 
Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®Glen Alleman
 
Building the perfect schedule (v6)
Building the perfect schedule (v6)Building the perfect schedule (v6)
Building the perfect schedule (v6)Glen Alleman
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleGlen Alleman
 
Project maturity flow is the incremental delivery of business value
Project maturity flow is the incremental delivery of business valueProject maturity flow is the incremental delivery of business value
Project maturity flow is the incremental delivery of business valueGlen Alleman
 
Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated masterGlen Alleman
 
Cpm 200 c technical performance measures - alleman (ppm)
Cpm 200 c   technical performance measures - alleman (ppm)Cpm 200 c   technical performance measures - alleman (ppm)
Cpm 200 c technical performance measures - alleman (ppm)Glen Alleman
 
Managing in the presence of uncertainty
Managing in the presence of uncertaintyManaging in the presence of uncertainty
Managing in the presence of uncertaintyGlen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Glen Alleman
 
Probabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost AnalysisProbabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost AnalysisGlen Alleman
 
Big data meets evm (submitted).pptx
Big data meets evm (submitted).pptxBig data meets evm (submitted).pptx
Big data meets evm (submitted).pptxGlen Alleman
 
A possible cure 2014 may9
A possible cure 2014 may9A possible cure 2014 may9
A possible cure 2014 may9Glen Alleman
 
Customer Intelligence & Social Media
Customer Intelligence & Social MediaCustomer Intelligence & Social Media
Customer Intelligence & Social MediaAmplified Analytics
 

Viewers also liked (20)

Deliverables Based Planning
Deliverables Based PlanningDeliverables Based Planning
Deliverables Based Planning
 
Risk management using risk+ (v5)
Risk management using risk+ (v5)Risk management using risk+ (v5)
Risk management using risk+ (v5)
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News Webinar
 
Agile in the government
Agile in the government Agile in the government
Agile in the government
 
Capabilities based planning (v2)
Capabilities based planning (v2)Capabilities based planning (v2)
Capabilities based planning (v2)
 
Paradigm of agile project management
Paradigm of agile project managementParadigm of agile project management
Paradigm of agile project management
 
Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®
 
Control systems
Control systemsControl systems
Control systems
 
Building the perfect schedule (v6)
Building the perfect schedule (v6)Building the perfect schedule (v6)
Building the perfect schedule (v6)
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master schedule
 
Project maturity flow is the incremental delivery of business value
Project maturity flow is the incremental delivery of business valueProject maturity flow is the incremental delivery of business value
Project maturity flow is the incremental delivery of business value
 
Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated master
 
Cpm 200 c technical performance measures - alleman (ppm)
Cpm 200 c   technical performance measures - alleman (ppm)Cpm 200 c   technical performance measures - alleman (ppm)
Cpm 200 c technical performance measures - alleman (ppm)
 
Managing in the presence of uncertainty
Managing in the presence of uncertaintyManaging in the presence of uncertainty
Managing in the presence of uncertainty
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)
 
Probabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost AnalysisProbabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost Analysis
 
Big data meets evm (submitted).pptx
Big data meets evm (submitted).pptxBig data meets evm (submitted).pptx
Big data meets evm (submitted).pptx
 
A possible cure 2014 may9
A possible cure 2014 may9A possible cure 2014 may9
A possible cure 2014 may9
 
Customer Intelligence & Social Media
Customer Intelligence & Social MediaCustomer Intelligence & Social Media
Customer Intelligence & Social Media
 

Similar to Improving DOE Project Performance Using the DOD Integrated Master Plan

Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOEGlen Alleman
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.pptTinotendaChivese
 
Increasing the probability of program success
Increasing the probability of program successIncreasing the probability of program success
Increasing the probability of program successGlen Alleman
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET Journal
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
New approach for solving software project scheduling problem using differenti...
New approach for solving software project scheduling problem using differenti...New approach for solving software project scheduling problem using differenti...
New approach for solving software project scheduling problem using differenti...ijfcstjournal
 
Chapter 02 project planning
Chapter 02 project planningChapter 02 project planning
Chapter 02 project planningCharith Sathish
 
Efficacy of Project Management,
Efficacy of Project Management, Efficacy of Project Management,
Efficacy of Project Management, Assignment Studio
 
From arms race to green space
From arms race to green spaceFrom arms race to green space
From arms race to green spaceGlen Alleman
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleGlen Alleman
 
Lecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdfLecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdfTanzeelShahid5
 
Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)Jeffrey Cheah
 
Student guide for unit 9
Student guide for unit 9Student guide for unit 9
Student guide for unit 9Peter R Breach
 

Similar to Improving DOE Project Performance Using the DOD Integrated Master Plan (20)

Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Stopping the insanity
Stopping the insanityStopping the insanity
Stopping the insanity
 
Increasing the probability of program success
Increasing the probability of program successIncreasing the probability of program success
Increasing the probability of program success
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Project Management
Project ManagementProject Management
Project Management
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
PERT
PERTPERT
PERT
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
New approach for solving software project scheduling problem using differenti...
New approach for solving software project scheduling problem using differenti...New approach for solving software project scheduling problem using differenti...
New approach for solving software project scheduling problem using differenti...
 
Chapter 02 project planning
Chapter 02 project planningChapter 02 project planning
Chapter 02 project planning
 
Efficacy of Project Management,
Efficacy of Project Management, Efficacy of Project Management,
Efficacy of Project Management,
 
From arms race to green space
From arms race to green spaceFrom arms race to green space
From arms race to green space
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 
Lecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdfLecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdf
 
Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)
 
Student guide for unit 9
Student guide for unit 9Student guide for unit 9
Student guide for unit 9
 
Assignment
Assignment Assignment
Assignment
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Recently uploaded

Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?XfilesPro
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Snow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter RoadsSnow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter RoadsHyundai Motor Group
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraDeakin University
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 

Recently uploaded (20)

Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptxVulnerability_Management_GRC_by Sohang Sengupta.pptx
Vulnerability_Management_GRC_by Sohang Sengupta.pptx
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Snow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter RoadsSnow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter Roads
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food Manufacturing
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning era
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 

Improving DOE Project Performance Using the DOD Integrated Master Plan

  • 1. WM2012 Conference, February 26 – March 1, 2012, Phoenix, Arizona, USA 1 Improving DOE Project Performance Using the DOD Integrated Master Plan – 12481 Glen B. Alleman, DOD Programs, Project Time & Cost and Michael R. Nosbisch, Managing Principle, Western Region, Project Time & Cost ABSTRACT DOE O 413 measures a project’s progress to plan by the consumption of funding, the passage of time, and the meeting of milestones. In March of 2003, then Under Secretary, Energy, Science, Card received a memo directing the implementation of Project Management and the Project Management Manual, including the Integrated Master Plan and Integrated Master Schedule. This directive states “the integrated master plan and schedule tie together all project tasks by showing their logical relationships and any constraints controlling the start or finish of each task. This process results in a hierarchy of related functional and layered schedules derived from the Work Breakdown Structure that can be used for monitoring and controlling project progress.” This paper shows how restoring the IMP/IMS paradigm to DOE program management increases the probability of program success in ways not currently available using DOD O 413 processes alone. INTRODUCTION The measures of progress to plan in units meaningful to the decision maker are needed to answer the question – How Long Are We Willing to Wait before We Find out We Are Late? As recently as January of 2011 updates to DOE O 413.3B were made with focus on four philosophical goals. [3] With this 2011 directive and the 2003 memo to Robert Card (Project Management and the Project Management Manual) [1] addressing the use of Integrated Master Plans and Schedules in Section 6.5.1, the measures needed to answer this question are still not specifically stated in the most recent version of the DOE O 413 series. However, the DOD 5000.02 and Integrated Master Plan (IMP) paradigm provides the mechanism to answer the question and should be adopted by DOE. The IMP, as applied by the DOD, defines the incremental increase of a project’s maturity, assessed through Significant Accomplishments (SA) and Accomplishment Criteria (AC), using Measures of Effectiveness (MoE), Measures of Performance (MoP), and Technical Performance Measures (TPM). [2] The memo to Card reflects a nearly identical structure to the DOD Integrated Master Plan and establishes DOE M 413.3–1 (Project Management for the Acquisition of Capital Assets) as a primary guidance document using the IMP/IMS in 2003. But the current DOE O 413.3–1 does not include the use on an Integrated Master Plan (IMP) [7], [11]. Applying Card’s 2003 DOD IMP paradigm to DOE O 413 series projects will improve the probability of DOE project success through measures of increasing maturity of the deliverables defined in the Integrated Master Plan (IMP), in addition to measures of progress through cost and schedule performance and milestone compliance. [3] For motivation for this IMP/IMS approach, we need only look to recent reports that provide a sample of assessments: GAO–07–336 Major Construction Projects Need a Consistent Approach for Assessing Technology Readiness to Avoid Cost Increases and Delays [4], GAO– 09–406 Contract and Project Management Concerns at NNSA and Office of EM [5] and GAO– 08–1081 Nuclear Waste: Action Needed to Improve Accountability and Management of DOE’s Major Cleanup Projects [6].
  • 2. 2 These GAO reports found that …:  … the cost increases and schedule delays that have occurred for most of these projects have been the result of inconsistent application of project management tools and techniques on the part of both DOE and its contractors.[5]  … exceeded their original cost or schedule estimates, principally because of ineffective DOE project oversight and poor contractor management. [4]  … had life cycle baseline cost increases, from a low of $139 million for one project to a high of nearly $9 billion for another, and life cycle baseline schedule delays from 2 to 15 years. These changes occurred primarily because the baselines we reviewed included schedule assumptions that were not linked to technical or budget realities and the scope of work included other assumptions that did not prove true. [6] Project success depends on answering 5 immutable questions, no matter the domain or the project context in that domain, the project management method, or the agency guidance. 1. What does “Done” look like? 2. What is the path to reaching “Done” on time, on budget, and technically compliant? 3. What resources (time, money, staff, and facilities) are needed to reach “Done? 4. What impediments will prevent reaching “Done”? 5. How is physical progress to plan measured on the path to “Done?” Project success starts with describing what “Done” looks like in units of measure meaningful to the decision makers. These measures of performance (technical and programmatic) and effectiveness (the customer’s point of view) are derived from the elements of the Integrated Master Plan – Program Events, Significant Accomplishments, and the Accomplishment Criteria of the baselined Work Packages. DOE G 413.5 (Performance Measurement Baseline) describes the measurement of progress to plan through Key Performance Parameters (KPP), Cost, and Schedule Performance. These measures do not answer the 5 immutable questions stated above. The answers need to be in units of Increasing Maturity of the project outcomes. [8] DOE O 413.3b (Program and Project Management for the Acquisition of Capital Assets) mentions the term maturity 14 times. [9] DOE O 413.3–9 (Project Review Guide for Capital Asset Projects) mentions maturity 9 times.‡ DOE G 413.3–7A (Risk Management Guide) provides guidance for assessing increasing project maturity. [10] None of these Orders or Guides states HOW to measure increasing maturity or HOW to use these measures to increase the probability of success of the project. The DOD applies the Integrated Master Plan (IMP) paradigm, to assess the increasing maturity of the project through Measures of Effectiveness (MoE), Measures of Performance (MoP), Key Performance Parameters (KPP), and Technical Performance Measures (TPM) to assess the increasing Probability of Project Success (PoPS). The DOD approach is distinctly different from the horizontal master scheduling described in the DOE O 413 series guidance. EVENT BASED PLANNING IS THE BASIS OF STRATEGY MAKING From Card’s memo we have a clear and concise connection between the Integrated Master Plan (IMP) and the supporting Integrated Master Schedule (IMS) and the management of DOE projects guided by DOE O 413.3. The following words appear in §6.5.1 of Card’s memo and attached manual section [1]. ‡ NASA style Technology Readiness Levels have been suggested for the DOE through GAO-07-336 [4]
  • 3. 3 An integrated master plan is a very effective tool for project management. It is the contractor’s event–based plan for accomplishing the requirements contained in Statements of Work, Performance Work Statements, Work Authorizations, and other documents which communicate requirements to the contractors. The plan identifies the key activities, events, milestones, and reviews that make up the program or project. The program or project office, support contractors or the prime contractor may prepare the plan. The plan also identifies those events and activities that will be included in the integrated master schedule. The integrated master schedule is a networked multilayered schedule generated by the contractor that begins with all identified integrated master plan events, accomplishments, and criteria. It also shows the expected start and finish dates of these events and contains all contractually required events and milestones such as reviews, tests, completion dates, and deliveries specified in the Work Breakdown Structure. The integrated master plan is prepared prior to completion of the Conceptual Design process and is subsequently maintained by the government and the contractor through a collaborative effort involving all the stakeholders. The integrated master plan and schedule tie together all project tasks by showing their logical relationships and any constraints controlling the start or finish of each task. This process results in a hierarchy of related functional and layered schedules derived from the Work Breakdown Structure that can be used for monitoring and controlling project progress. * Strategy Making, IMP/IMS, and Systems Engineering Building products or facilities, providing services, or remediating environments is a systems engineering process. † Components, processes, participants, and their outcomes interact in ways that are described as a system. Engineering of these systems is an interdisciplinary process that deals with the work and tools that manage risk, technical activities, and the human centered disciplines need for success. The strategy for these activities is represented in the DOD by the Integrated Master Plan. The IMP/IMS is a step by step process to increase the probability of project success by: 1. Creating A Vision Of The Outcome – described in the Concept of Operations (ConOps) or Statement of Objectives (SOO). 2. Analyzing The Current Situation – to determine viable alternatives for the desired outcomes. 3. Determining A Strategy – for moving from the current situation to the outcome, what “maturity increasing” activities must be performed to move forward. 4. Selecting The Systems Development Activities – needed to move the “increasing maturity” forward through Significant Accomplishments (SA). 5. Constructs A Plan Based On These Activities – arrange the SAs in a logical sequence for each Program Event (PE) to provide increasing level of maturity of the products or service. * These words taken directly from the attached Manual in the memo are nearly identical to DI–MGMT–81650, Integrated Master Schedule, with three levels of Master Schedules. The terms Significant Accomplishment and Accomplishment Criteria are used directly in Card’s memo they are connected from DID–81650 to the current – under review – is DI–MGMT–81466B, where the Integrated Master Plan (IMP) is mentioned. The DOD Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide shows how the connected the resulting IMP with the IMS mentioned in Card’s memo. † “Project Management vs. Systems Engineering Management: A Practitioners’ View on Integrating the Project and Product Domains,” Amira Sharon,Olivier L. de Weck, and Dov Dori, Systems Engineering, Volume 14, Number 4, 2011.
  • 4. 4 6. Performing A Pilot Set Of Activities – to confirm they result in desirable outcomes. 7. Evaluating These Results – “test” the logic of the SAs to assure increasing maturity will result. 8. Executes The Processes – in steps 6 and 7 until the outcome is reached by developing the Accomplishment Criteria (AC) for each SA and the top activities for each AC. This IMP/IMS approach is the basis of all credible development activities in the DOD. The challenge for the DOE becomes finding how the details of each step are to be defined, developed, and executed in the context of DOE O 413.3b. STRUCTURE OF THE INTEGRATED MASTER PLAN IN THE DEPARTMENT OF DEFENSE The Integrated Master Plan showing how work is performed, the criteria for the compliance of that work with the Technical Performance Measures, and the Accomplishments needed to deliver a capability are shown in Figure 1. This approach provides tangible evidence of progress to plan in units of measure meaningful to the decision makers. These units include Measures of Effectiveness (MoE) from the customer’s point of view, Measures of Performance (MoP) from the contractor’s or owner’s point of view, the agreed Key Performance Indicators (KPP), and the Technical Performance Measures (TPM) for all work activities. The trends in these measures (MoP, MoE, KPP, and TPM) reveal project progress and when compared with standard contingency values, highlight when corrective actions should be considered. These measures of the system technical performance have been chosen because they are indicators of increasing maturity of the project outcomes that impact the probability of project success. They are based on high risk or significant driving requirements or technical parameters. These measures are analogous to the programmatic measures of expected total cost or estimated time–to–completion (Earned Value Management measures). Actual versus planned progress of these measures are tracked through the IMP/IMS so engineers, constructors, and project managers can assess progress and the risk associated with each measure. These measures are attached to each Significant Accomplishment and Accomplishment Criteria shown in Figure 1 to provide measures of increasing maturity, as well as other measures needed to assess the probability of project success. These measures are distinctly different from measures of cost and schedule performance and their related milestone compliance. Cost, schedule, and milestone compliance are necessary, but do not sufficient to provide visibility into the effectiveness of the project for the customer. Measures of Effectiveness (MoE) are operational measures of. Measures of Performance (MoP) characterize physical or functional attributes relating to the system operation, measured or estimated under specific conditions. Key Performance Parameters (KPP) represents the capabilities and characteristics significant enough that failure to meet them can be cause for reevaluation, reassessing, or termination of the project. These three measures (MoE, MoP, and KPP) are the heart of the IMP/IMS Significant Accomplishments and their Accomplishment Criteria that provide direct measure of increasing maturity of the projects outcomes.
  • 5. 5 Department of Defense Processes Integrated with DOE O 413.3b and 413.5 The U.S. Department of Defense (DOD) makes use of Event Based Plans to define the integrated product development and integration using measures of increasing maturity. This approach enhances project planning, scheduling, and successful execution. This plan is a hierarchy of Project Event(s), each event supported by specific Accomplishments, and each accomplishment associated with specific Criteria to be satisfied for its completion. This approach is different from the traditional horizontal schedule that measures progress through cost and schedule performance. While deliverables are defined in the Integrated Master Schedule (IMS), measures of Effectiveness (MoE), Performance (MoP), and its related Key Performance Parameters (KPP) and Technical Performance Measures (TPM) are not embedded in the Performance Measurement Baseline (PMB). By applying the IMP paradigm, a vertical Plan is created where each Accomplishment defines the desired result(s) prior to the completion of an Event that indicates a level of the project’s progress. Accomplishment Criteria provide tangible evidence that a specific accomplishment has been completed according to its Measure of Effectiveness and Measure of Performance. Figure 1 – The work performed in the sequence Work Packages is assessed for compliance with Technical Performance Measures, Measures of Effectiveness (MoE), and Measures of Performance (MoP). The result is a description of the increasing maturity of the product or service resulting from the project.
  • 6. 6 DOE G 413.5 Performance Measurement Baseline defines the Scope, Design, Key Performance Parameters, Cost, Schedule, and supporting Documentation for the project. But this PMB does not define the Accomplishments and Criteria that must be met to successfully deliver the outcomes of the project. Using the IMP paradigm, units of measure of performance meaningful to the decision makers are installed in the PMB from the Accomplishments and Criteria for the detailed work activities. This approach makes the Integrated Master Schedule (IMS) clearer by showing what DONE looks like in terms of deliverables and the criteria for success of those deliverables embedded in the IMS. The connection of the performance of work efforts to the Criteria, Accomplishments, and Project Events is the Earned Value Management (EVM) System. The EVM System defines the measures of progress to plan at the work performance level. These measures are used to define progress for each Criteria and Accomplishment. This provides Project Management with direct measures of physical percent complete for each deliverable from the project. Figure 1 shows the programmatic structure needed to improve the probability of project success, using the Integrated Master Schedule paradigm, with Accomplishments, and Criteria as measures of project performance based on MoE, MoP, and TPMs. Figure 2 shows how each of these measures is related to produce visibility to the performance of the project. How the Department of Defense Measures Maturity of the Project’s Outcomes DOE O 413.3b mentions maturity 14 times in the context of design, procurement, and technology readiness assessment. The measure of maturity has two sides of a project – the buyer side and the producer side, i.e. The Customer and the Builder.  Measures of Effectiveness – are closely related to the achievements of the mission or operational objectives evaluated in the operational environment, under a specific set of conditions. MoE’s are stated in units meaningful to the buyer and focus on the capabilities independent of any technical implementation, and are connected to the mission success.  Measures of Performance – characterize physical or functional attributes relating to the system operation measured or estimated under specific conditions. MoP’s are attributes that assure the system has the capability to perform and assure the design requirements can satisfy the Measures of Effectiveness. Along with the Measures of Effectiveness and Measures of Performance, two other measures are needed to “connect the dots.”  Key Performance Parameters (KPP) – Represent the capabilities and characteristics so significant that failure to meet them can be cause for reevaluation, reassessing, or termination of the project. KPPs have a threshold or objective value. These characterize the major drivers of performance and are considered Critical to Customer (CTC).  Technical Performance Measures (TPM) – are attributes that determine how well a system or system element is satisfying or expected to satisfy a technical requirement or goal. These measures assess the design process, define compliance to performance requirements, and identify technical risk, including projected performance. The TPMs are limited to critical thresholds.
  • 7. 7 Figure 2 – connecting the measures needed for assessing increasing project maturity assures there is visibility to project performance in units of measure meaningful to the decision makers. CONNECTING DOE O 413.3B WITH DOD MEASURES OF MATURITY Table 1 is a summary of DOE O 413.3b’s Critical Design stages and the activities performed at each stage. For each of these, we’ll demonstrate how they would be applied in the Department of Defense Integrated Master Plan and Integrated Master Schedule paradigm and show how these connections can add value and increase the probability of success for DOE projects. Connections between the Critical Design stages and the elements of the Integrated Master Plan are shown in Table 2. These connections can be applied to current DOE O 413 series projects, guided with the Card memo [1] and the Bosco order [3]. The outcome of this approach is a programmatic architecture where performance is measured through cost and schedule adherence as well as direct measures of increasing maturity supported by measures of effectiveness and performance needed to assessing the probability of project success. Used Earned Value for activities contained in Work Packages, measures of physical percent complete toward the Accomplishment Criteria are provided. These Accomplishment Criteria are then direct measures of progress toward the Significant Accomplishments needed to measure this increasing maturity of each Program Event. This architecture is shown in Figure 1, where both vertical traceability to increasing maturity and horizontal traceability to activity progress are integrated in a single Performance Measurement Baseline.
  • 8. 8 Project Acquisition Process and Critical Decisions Project Planning Phase Project Execution Phase Mission Pre–conceptual Design Conceptual Design Preliminary Design Final Design Construction Operations CD–0 CD–1 CD–2 CD–3 CD–4 Actions Authorized by the Critical Design Approval  Proceed with the conceptual design.  Request PED funding.  Allow expenditure of PED funds.  Establish baseline budget for construction.  Continue design.  Request construction funding.  Approve expenditure of funds for construction.  Allow start of operations or project close out. Critical Design Pre–Requisites  Justification of mission need.  Acquisition strategy  Pre–conceptual planning.  Mission need.  Independent Project Review.  Acquisition plan.  Conceptual design.  Preliminary project execution plan and baseline range.  Project data sheet for design  Verification of mission need.  Preliminary hazard analysis report.  Preliminary design.  Review of contractor project management system.  Final project execution plan and performance baseline.  Independent cost estimate.  NEPA  Project data sheet for construction.  Draft preliminary Safety Analysis Report.  Performance Baseline External Independent Review.  Update project execution Plan and Performance Baseline  Final design and procurement packages.  Verification of mission need.  Budget and congressional authorization and appropriation enacted.  Approval of safety documentation.  Execution readiness Independent Review.  Operational readiness review.  Project transition to operations.  Final safety report. Table 1 – summary of CD activities from DOE O 413.3b, 29 November 2010 describe the attributes or exit criteria for each of the Critical Decision. The documents that define the processes and content of many of these deliverables do not directly speak to the increasing maturity of the project’s outcome. The terms “preliminary, draft, approved verified, and final,” are used but the Significant Accomplishments and the Accomplishment Criteria needed assessment the maturity of the project at each of these reviews is not defined.
  • 9. 9 Mapping the IMP/IMS Paradigm to the DOE Critical Design Reviews The DOE O 413 series defines activities to be performed during the execution of a project. The DOD Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide defines how to build the IMP and IMS that will increase the probability of success for the project [2]. DOE O 413.3–9 and 413.3–16 Guidance DOD IMP/IMS Guidance CD–0: Approve Mission Need Understand the Project  Identification of a mission–related need and translation of this gap into functional requirements for filling the need.  The mission need is independent of a particular solution and should not be defined by equipment, facility, technological solution, or physical end item (413.3A).  The focus for Technology Assessment, at this stage, is on clear statement of the requirements of the input and the desired output of the process.  Define mission outcome as a Concept of Operations (ConOps)  Partition system capabilities into classes of service within operational scenarios.  Connect the capabilities to system requirements using some visual modeling notation.  Define Measures of Effectiveness (MoE) and Measures of Performance (MoP).  Define the delivery schedule for each measure of performance and effectiveness. CD–1: Alternative Selection and Cost Range Develop Project Structure  Identification of the preferred technological alternative, preparation of a conceptual design, and development of initial cost estimates  Assign costs to each system element using a value flow model.  Assure risk, probabilistic cost and benefit performance attributes are defined.  Use cost, schedule and technical performance probabilistic models to forecast potential risks to project performance. CD–2: Performance Baseline Create IMP / IMS  Completion of preliminary design, development of a performance baseline that contains a detailed scope, schedule, and cost estimate.  The process of technology development, in accordance with the approved TMP should support all CTEs reaching TRL 6; attainment of TRL 6 is preferable and indicates that the technology is ready for insertion into detailed design.  Decompose scope into work packages  Assign responsibility for deliverables  Arrange work packages in a logical order  Develop BCWS for work packages  Assign work package measures of performance  Set Performance Measurement Baseline CD–3: Start of Construction Execute Performance Measurement Baseline  Completion of essentially all design and engineering and beginning of construction, implementation, procurement, or fabrication. A TRA is only required if there is significant technology modification as detailed design work progresses.  If substantial modification of a technology occurs, the TRA should be performed and a focused TMP developed or updated to ensure that the modified technology has attained TRL 6, if possible, prior to its insertion into the detailed design and baseline.  Performance authorized work  Accumulate and report work package information  Analyze work package performance  Take corrective management action  Maintain Performance Measurement Baseline Table 2 – for each 413 CD, specific IMP/IMS guidance can be applied to increase the probability of project success, by creating evidence of increasing maturity in units of measure meaningful to the decision makers.
  • 10. 10 CHANGING THE PROGRAM PLANNING PARADIGM FROM HORIZONTAL TO VERTICAL Building an IMP / IMS requires a change in the normal paradigm of project management. This change means stopping the measurement of progress as the passage of time and consumption of funding – to measuring progress by the completion of Accomplishment Criteria and the fulfillment of Significant Accomplishments. It means moving from horizontal scheduling to vertical planning. These words are probably meaningless at this point. The description of this paradigm provides an understanding of this concept, the benefits to the project management, and the processes needed to deliver these benefits. In many cases, the horizontal schedules are the starting point for the project. This occurs for several reasons:  The project started without an IMP or a real IMS. They first built a horizontal schedule in the manner of “shop floor” schedule. This is usually for the Period of Performance of the Program.  The project was inherited from a higher or lower level process. Either as a subcontractor or a part of on IPT team, the schedule is focused on the functional aspects of the project. In many cases, the conversion from horizontal to vertical planning is required or desired. The effort to do this conversion involves several steps:  Identify the Program Events and where in the schedule these events take place.  Identify which work in the schedule “lands” on which event. If there is work that crosses an Event boundary, then it will need to be “broken” into two (2) parts. One that “lands” on the Event and one that restarts at the completion of the Event. IMP / IMS FEATURES AND BENEFITS The IMP and IMS focuses on specific areas of the project, which have been shown to be problems with more traditional approaches. The primary focus is on project maturity Event based planning provides a “singularly” focused process allowing each IPT to answer the question – “what do I need to do for a specific event?” For example Preliminary Design Review (PDR): List all the accomplishments needed for PDR? What activities need to performed for each of these accomplishments? When all the activities are completed, the criteria satisfied, and the accomplishments completed then a measurement of “maturity” can take place? This approach is not described in the DOE O 413 series of guidance. Features of IMP/IMS Benefits to the Program Provides an understanding and alignment of required tasks with events starting with the proposal Drives down cost of execution by connecting changes with the impact of changes that occur early in the project life cycle when costs are lower are made visible from day one. Integrates relationships of products and development processes Improves management visibility by connecting activities with events Permits better understanding of risk and how it impacts cost, schedule, performance A disciplined approach to planning and implementation activities Provides a framework for using integrated tools, teams, and processes with vertical traceability Serves as foundation for systematic programmatic improvement efforts Iterative planning, tracking, and reporting process Allows project flexibility – on ramps and off ramps tied to events Highlights details early – ties maturity events with activities Event–Driven Planning Relates project events in terms of success – Accomplishments and Criteria Reduces risk by ensuring that maturity of the plan is incrementally demonstrated prior to starting follow–on activities Increases visibility of entire project to the project team Improves measurable maturity and impact analysis Promotes project buy–in and team commitment through shared events Fosters proactive management at all levels through measurable outcomes
  • 11. 11 Features of IMP/IMS Benefits to the Program Resource and Earned Value Loadable Provides foundation for Earned Value Reporting and EVMS Key customer events included Encourages a win–win attitude with customers Clear communication of how the team views the project Improves effectiveness through a common set of tools, measurements and defined outcomes Table 3 – IMP/IMS features and that are not directly provided by executing DOE O 413 series guided projects using measures of cost, schedule, and milestone performance. THE PIECES NEEDED TO INCREASE THE PROBABILITY OF PROJECT SUCCESS Using the DOE Critical Decision (CD) review guide, the Integrated Master Plan paradigm is applied to increase the probability of project success. DOE CD Outcomes IMP / IMS Processes to create outcomes CD–0: Approve Mission Need  Developing the mission need and acquisition strategy  Define the Significant Accomplishment needed to fulfill the mission need and implementation strategy.  Define these in units of performance, effectiveness, and technical compliance.  Define the Measures of Effectiveness (MoE) and Measures of Performance (MoP) for each mission need. (see Figure 2 for relationship between these measures).  Pre–conceptual planning  Define the “increasing maturity” flow for the work needed to fulfill the mission need and acquisition strategy.  Define the Technical Performance Measures (TPM) for each outcome at the planned level of maturity – in the DOE language the Technology Readiness Level (TRL) has similar words CD–1: Alternative Selection and Cost Range  Preliminary project execution plan  Verification of mission need  Integrated Master Plan logical “Value” flow, showing how each outcome from the work efforts satisfies the Accomplishment Criteria in units of Measures of Effectiveness (MoE) and Measures of Performance (MoP) measured against the planned MoE and MoP.  Develop Basis of Estimate (BoE) for each Significant Accomplishment and Accomplishment Criteria (see Figure 1 for IMP/IMS structure).  Connect the BoEs with each measure of maturity and the planned cost to reach that level of maturity. CD–2: Performance (Measurement) Baseline  Preliminary design review  Review project management system  Final project execution plan  Independent cost estimate  External independent review  PDR and other reviews assess planned and actual maturity of Significant Accomplishments (SA) and the Accomplishment Criteria (AC).  Probabilistic assessment of cost, schedule, and technical performance for each SA and AC. CD–3: Start Construction  Final design review  Execution readiness review  Execute the Performance Baseline  Starting with the Work Packages, execute each Accomplishment Criteria and measure actual performance against planned performance using MoE and MoP. Table 4 – for each 413 CD, specific IMP/IMS processes and their outcomes increase the probability of project success through tangible evidence of increasing maturity in units of measure meaningful to the decision makers.
  • 12. 12 CONCLUSION Using DOE O 413 series guidance, adding the Integrated Master Plan and Integrated Master Schedule paradigm would provide a hierarchical set of performance measures for each “package of work,” that provides measureable visibility to the increasing maturity of the project. This measureable maturity provides the mechanism to forecast future performance of cost, schedule, and technical outcomes in ways not available using just the activities in DOE O 413. With this information project managers have another tool available to address the issues identified in GAO–07–336 and GAO–09–406. REFERENCES [1] Memorandum for Robert G, Card, Undersecretary, Energy, Science, and Environment, March 31, 2003 from Kyle E. McSlarrow, “Project Management and the Project Management Manual.” http://www.fnal.gov/directorate/OPMO/DOE/o413/m4133-1.pdf [2] “Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide,” Version 0.9, August 15, 2005, Office of the Secretary of Defense (OSD), www.acq.osd.mil/se/docs/IMP_IMS_Guide_v9.pdf [3] “Significant Changes to DOE Order 413.3B,” January 21, 2011, Paul Bosco, Director, Office of Engineering and Construction Management. http://1.usa.gov/v6V5z6 [4] GAO–07–336 Major Construction Projects Need a Consistent Approach for Assessing Technology Readiness to Avoid Cost Increases and Delays. [5] GAO–09–406, Contract and Project Management Concerns at NNSA and Office of EM [6] GAO–08–1081, Nuclear Waste: Action Needed to Improve Accountability and Management of DOE’s Major Cleanup Projects. [7] DOE O 413.3, Program and Project Management for the Acquisition of Capital Assets, included in Memo to Robert Card, March 31, 2003 from Kyle E. McSlarrow. Memo available at http://www.fnal.gov/directorate/OPMO/DOE/o413/m4133-1.pdf [8] DOE G 413.5, Performance Measurement Baseline. [9] DOE O 413.3b Program and Project Management for the Acquisition of Capital Assets. [10] DOE G 413.3–7A Risk Management Guide. [11] “Integrated Master Plan Analysis: The PMAG Approach,” Col. Mun H. Kwon, USAF, Defense AT&L, January–February, 2010, pp. 39–43.