Project KOHINOOR 2010 
Engineering Procurement and 
Construction (EPC)
EPC Capabilities Analysis framework 
EPC projects involve enhancement of certain specific capabilities apart from strong 
project management and risk management functions 
Risk Management 
Project Management 
2 
EPC Projects 
Engineering Procurement Construction
Issues need to be analyzed in each stage of the EPC project lifecycle 
3 
EPC Project Lifecycle 
ENGINEERING 
Basic 
engineering 
Detail 
engineering 
Vendor 
negotiation 
Floating 
enquiries 
Vendor 
approvals 
Vendor 
manufacturing 
PROCUREMENT 
Site 
erection 
CONSTRUCTION 
Commissio 
ning 
Performance 
Guarantee
Agenda / Management Summary 
4 
Summary of Key EPC Issues 
Engineering 
 Quantity variation 
 Delay in receipt of drawings at site 
 Constructability 
Procurement 
 Variance in delivery schedule 
 Post manufacturing rework 
Construction 
 Limited focus on commissioning, take over / 
performance guarantee tests 
Organization Structure 
 Limited empowerment of Project Manager
Engineering Issues - Quantity Variation 
Impact due to design quantity variation in a sample of only 6 EPC projects 
was ~ 50 INR Cr in 04-05 
Case Study RCV 
(Rs Cr.) 
5 
Quantity Variation* 
Rs Cr. (% of RCV) Key Items with Variation 
60.75 15.67 (25.8%) 
 Concrete 
 Rebar 
52.5 9 (17.1%)  Pipes and pipe fittings 
20.87 3.51 (16.8%) 
 Pipes and pipe fittings 
 Instrumentation 
171.31 15 (8.8%)  Steel 
120 6 (5%)  Steel 
30.87 0.80 (2.6%) 
 Hopper 
 Counterweight 
Project 1 
Project 2 
Project 3 
Project 4 
Project 5 
Instances of significant quantity variation 
in EPC projects across BUs 
Project 6 
* Quantity variations computed with respect to tender 
(contract) estimates 
Source: Interviews with Project Managers / Coordinators of respective projects
Quantity variation - Root cause analysis 
Lack of clarity of requirements 
from basic engineering 
Design capacity 
constraint Inadequate domain 
Inadequate site exposure 
6 
People 
Changes in customer inputs / 
scope / basic engineering 
Technology Process 
Quantity 
Variation 
Organization 
Limited 
ownership of 
design and 
quantities 
knowledge of 
designers 
Inadequate rigor in site / 
soil Investigation 
Lack of use of 
quantity survey 
software 
Design team during 
execution is different 
from the one during 
tendering 
Design partner 
evaluation process 
Lack of incentives / 
penalties for design 
team 
Insufficient value 
Lack of standard designs engineering in execution 
Limited use of for frequently used items 
knowledge 
management 
systems 
Lack of norms / indices 
to facilitate accurate 
estimation Inadequate internal / 3rd party 
quality assurance processes
Engineering Issues - Drawings delay at site 
Delay in receipt of drawings at site for EPC projects impacting utilization of 
Case Study: EPC Project 
May’ 04 Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun July Apr’ 2006 
7 
Project Duration 
Planned 
Actual 
4 months 
7 months 
Kick-off 
meeting 
Site 
mobilized 
End 
date 
Drawings Release 
Schedule 
Idling of 
resources 
Crashing of resources 
resources and PBIT 
ACE Margin: 11% 
JCR Margin: 9.6%
Drawings delay at site - Root cause analysis 
8 
People 
High 
attrition 
rate 
Inadequate site 
exposure 
Technology Process 
Drawings 
delay at 
site 
Organization 
Limited 
involvement in 
project plan 
Shortage of 
manpower 
Various disciplines in EDRC 
not working in project team 
approach 
Design capacity 
constraint 
Inadequate domain 
knowledge of 
designers 
Delay in receipt of inputs 
from customer basic 
engg. / BU / vendors 
Co-ordination 
between Kolkatta & 
Chennai EDRC 
locations 
Lack of standard designs for 
frequently used items 
Limited use of 
knowledge 
management 
systems 
Changes in inputs 
from customer / basic 
engg. / BU / vendors
Engineering Issues- Constructability 
Designs not optimized due to limited focus on ‘constructability’ 
Examples of designs with poor ‘constructability’ 
 Varying size throughout the depth of track hopper foundation leading to an increase in shuttering 
costs and reduced productivity 
 Use of greater quantity of lesser thickness bracings leading to a drop in subcontractor productivity 
Salient features of a construction sensitive design 
 Optimize construction and design cost 
 Use of repetitive elements and 
modularization 
 Clear design details and easy enough to 
build with minimum risk 
Maximum savings result when constructability concepts are 
applied during early stages of the project 
9 
 Sequence of material delivery based on 
construction input 
 Use of innovative construction methods 
such as hand tools and temporary 
construction materials
10 
Design / Engineering 
Recommendations 
• Increase end-to-end involvement of design team and establish processes to 
develop/retain technical resources 
• Design team involved in tendering stage should also be involved in execution stage 
• Talent retention & development 
– Enhance HR processes 
– ‘Mentors’ to handhold new joiners 
– Knowledge sharing sessions to facilitate transfer of learnings across projects 
– Expert lectures from industry experts / in-house experienced personnel 
– Site exposure of design personnel to incorporate ‘constructability’ principles in design 
• Encourage design standardization and develop design norms / indices for standard 
items 
• Establish database of key design indices for standard items and update the same based on 
project experiences 
•Quality assurance process for verifying engineering quantities 
• 3rd party quality assurance to verify quantities especially for critical projects / projects where 
in-house technical knowledge is nascent 
• BU personnel to have basic technical knowledge to verify design quantities
11 
Design / Engineering 
Recommendations 
• Follow robust design partner evaluation process for external agencies 
• Evaluation criteria to include expertise related aspects as well as past experiences in 
previous projects 
• Include incentives / penalties in contract for quantity variation and constructabilty issues 
• Improve co-ordination between various departments involved in project / within 
EDRC 
• Location of BU representatives at EDRC during engineering stage and at region during 
execution stage of the project 
• EDRC project co-ordinator to facilitate co-ordination / integration across various EDRC 
disciplines and locations
Inadequate monitoring & control of critical items leading to defective parts / delays 
Case Study: EPC Project 
May’ 05 Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 
Seemingly small deviations from planned schedule have cascading effect on overall project 
timelines (and hence costs) due to various interdependencies 
12 
Procurement Issues 
7 months delay in 
2 months delay in Multiplier effect 
commencing supply 
project duration 
Supply 
Erection 
9 months 
May Jun Jul Aug Sep Oct Nov Dec‘ 06 
14 months 
9 months 
13 months 
Planned 
Actual 
Planned 
Actual 
2 months 7 months
Procurement Issues - Root cause analysis 
13 
People 
Technology Process 
Site stores incharge lacks BU 
specific technical knowledge 
Procurement 
Issues 
Organization 
Delay in finalization 
of PO 
Delays between 
vendor and BU due to 
clarifications on 
inputs 
Limited support from materials 
department for specialized procurements 
due to their lack of technical knowledge 
Limited database 
of vendors for 
specialized items 
Delays in internal 
approvals / release of 
advance 
Limited pre-tender 
tie ups 
Weak vendor manufacturing / 
Inadequate follow- quality processes 
up with vendors 
Changes / delays 
in engineering 
specifications 
Limited control over 
internal suppliers 
Limited visibility into 
internal suppliers’ 
processes / costs 
Inadequate quality assurance 
processes
14 
Procurement 
Recommendations 
• Review internal approval procedures for releasing high value POs 
• Review limit for high value POs - currently Rs 25 lacs (Rs 45 lacs for TFL projects) 
• BU Head to be authorized to approve release of PO if procurement costs are within ACE 
• Leverage IT to speed up approvals process / reduce paperwork 
• Institutionalize vendor alignment meeting especially for package supplies 
• All potential vendors to be invited in a joint forum for clarifications on technical/commercial 
project requirements 
• Decide standard formats / processes to be used by all vendors for submitting quotes to 
enable one-to-one comparison 
• Vendor kick-off meeting after final vendor selection 
• Representatives from EDRC, BU, consultant to attend the meeting 
• Upfront agreement between all parties on inputs required and timelines for clarifications on 
the same 
• Regular follow-up meetings to be held at a mutually agreed frequency to monitor progress 
against set timelines
15 
Procurement 
Recommendations 
• Establish BU specific vendor database / pre-tender tie-ups for specialized items 
• Tie-ups with regularly used vendors / vendors supplying frequently required items 
• Minimize site rework 
• Mock-up assembly at vendor works 
• 3rd party inspection - even for critical indigenous supplies 
• Logistics issues to be considered at the time of bid selection / tendering and 
logistics plan to be prepared after award of contract 
• Especially critical for ODC cargo / overseas projects 
• Consider tie-ups with specialized 3PL players
•Assign dedicated resource as Supplier Technical Assistant (STA) to collaborate 
between Project and critical suppliers 
16 
Procurement 
CPO1 - project X 
CPO2 
……. 
FPO1 
FPO2 - project X 
…….. 
CPO1 
FPO2 
……. 
Roles & Responsibilities (R&R) 
Information 
flow across 
agencies 
Information 
flow across 
agencies 
EExxppeedditiitningg 
Supplier - Castings 
Supplier - Forgings 
STA - Project X 
Technical / 
quality 
support 
Technical / 
quality 
support 
Delivery to 
Delivery to 
site 
site 
Recommendations
17 
Erection / Construction 
Recommendations 
•Adhere to established construction / erection standards to ensure robust 
methodology and quality 
• Gain upfront agreement with client on standards to be followed 
• Agree any deviations from standards with client and involve independent 3rd parties for 
technical clarifications if required 
• Deploy dedicated commissioning team after completion of site erection activities 
• Ensure smooth handover (technical / commercial) to client 
• Provide specific technical support required for take over / performance guarantee tests 
• Follow a BU specific commissioning checklist to provide quality assurance 
• Obtain client agreement on checklist parameters 
• Continuously update checklist based on past project experiences
Organization Structure Issues 
Complexity in managing EPC projects since BU based Project Manager coordinates 
among various agencies over which he has no direct control 
Sector Head RPM Sector Head Head - Supply 
18 
Chain 
Internal Vendors Region EDRC Materials 
PROJECT 
MANAGER 
L&T in-house 
vendors such as 
EWL 
• Construction 
Manager 
• Other staff 
• P&M 
• EDRC coordinator 
–Civil 
–Mechanical 
–Electrical 
–Instrumentation 
Procurement 
personnel for 
commodities 
common across 
BUs (steel, 
concrete, etc) 
BU Head 
BU procurement 
Procurement 
personnel for BU 
specific items 
(valves, etc) 
Dashed line indicates no direct reporting
 Include to-be org structure slide 
19

More Related Content

What's hot

Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...John Buchovecky
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsNam N.N Tran M.Eng, PMP
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesThe Vertex Companies, LLC
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baronignitetribes
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2Chris Carson
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draftignitetribes
 
Modularization: How Going Modular Can Mitigate Project Risk and Deliver Proje...
Modularization: How Going Modular Can Mitigate Project Risk and Deliver Proje...Modularization: How Going Modular Can Mitigate Project Risk and Deliver Proje...
Modularization: How Going Modular Can Mitigate Project Risk and Deliver Proje...Koch Modular Process Systems, LLC.
 
Construction project management
Construction project managementConstruction project management
Construction project managementSenthil Kannan
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessAlberto Sanchez
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparisonhelensuni
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...HIMADRI BANERJI
 

What's hot (20)

Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
 
Modularization: How Going Modular Can Mitigate Project Risk and Deliver Proje...
Modularization: How Going Modular Can Mitigate Project Risk and Deliver Proje...Modularization: How Going Modular Can Mitigate Project Risk and Deliver Proje...
Modularization: How Going Modular Can Mitigate Project Risk and Deliver Proje...
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Claims
ClaimsClaims
Claims
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 

Viewers also liked

Conference Board 03 May 05 Tyco Rfid
Conference Board 03 May 05 Tyco RfidConference Board 03 May 05 Tyco Rfid
Conference Board 03 May 05 Tyco RfidGeorge Reynolds
 
Network Management System (Contact: info@exceleron-communications.com)
Network Management System (Contact: info@exceleron-communications.com)Network Management System (Contact: info@exceleron-communications.com)
Network Management System (Contact: info@exceleron-communications.com)Nadeem Khan
 
EPC Services Capability Tra International limited
EPC Services Capability  Tra International limitedEPC Services Capability  Tra International limited
EPC Services Capability Tra International limitedHimanshu9974
 
Ranvir amol sit lowsize
Ranvir amol sit lowsizeRanvir amol sit lowsize
Ranvir amol sit lowsizeAmol Dudhate
 
ASME Code and Quality assurance for construction of nuclear facilitiesASME Co...
ASME Code and Quality assurance for construction of nuclear facilitiesASME Co...ASME Code and Quality assurance for construction of nuclear facilitiesASME Co...
ASME Code and Quality assurance for construction of nuclear facilitiesASME Co...Mark Mitchell
 
Student Development Presentation
Student Development PresentationStudent Development Presentation
Student Development PresentationBonner Foundation
 
Site Inspection Guidelines and Protocol
Site Inspection Guidelines and ProtocolSite Inspection Guidelines and Protocol
Site Inspection Guidelines and ProtocolJose Agustin Gonzalez
 
Kpi analysis
Kpi analysisKpi analysis
Kpi analysisavneesh7
 
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...Optimus BT
 
The Importance of an Integrated Network Management System
The Importance of an Integrated Network Management SystemThe Importance of an Integrated Network Management System
The Importance of an Integrated Network Management SystemIRIS Network Systems
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principlestltiede
 
Piping components, materials, codes and standards part 1- pipe
Piping components, materials, codes and standards   part 1- pipePiping components, materials, codes and standards   part 1- pipe
Piping components, materials, codes and standards part 1- pipeAlireza Niakani
 

Viewers also liked (17)

Conference Board 03 May 05 Tyco Rfid
Conference Board 03 May 05 Tyco RfidConference Board 03 May 05 Tyco Rfid
Conference Board 03 May 05 Tyco Rfid
 
Network Management System (Contact: info@exceleron-communications.com)
Network Management System (Contact: info@exceleron-communications.com)Network Management System (Contact: info@exceleron-communications.com)
Network Management System (Contact: info@exceleron-communications.com)
 
EPC Quality Process Rev.00
EPC Quality Process Rev.00EPC Quality Process Rev.00
EPC Quality Process Rev.00
 
IT Value Realization
IT Value Realization IT Value Realization
IT Value Realization
 
Epc projects and cad tools
Epc projects and cad toolsEpc projects and cad tools
Epc projects and cad tools
 
EPC Services Capability Tra International limited
EPC Services Capability  Tra International limitedEPC Services Capability  Tra International limited
EPC Services Capability Tra International limited
 
Ranvir amol sit lowsize
Ranvir amol sit lowsizeRanvir amol sit lowsize
Ranvir amol sit lowsize
 
ASME Code and Quality assurance for construction of nuclear facilitiesASME Co...
ASME Code and Quality assurance for construction of nuclear facilitiesASME Co...ASME Code and Quality assurance for construction of nuclear facilitiesASME Co...
ASME Code and Quality assurance for construction of nuclear facilitiesASME Co...
 
Student Development Presentation
Student Development PresentationStudent Development Presentation
Student Development Presentation
 
Site Inspection Guidelines and Protocol
Site Inspection Guidelines and ProtocolSite Inspection Guidelines and Protocol
Site Inspection Guidelines and Protocol
 
WSN IN IOT
WSN IN IOTWSN IN IOT
WSN IN IOT
 
Aug12 sridhar
Aug12 sridharAug12 sridhar
Aug12 sridhar
 
Kpi analysis
Kpi analysisKpi analysis
Kpi analysis
 
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...
 
The Importance of an Integrated Network Management System
The Importance of an Integrated Network Management SystemThe Importance of an Integrated Network Management System
The Importance of an Integrated Network Management System
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
Piping components, materials, codes and standards part 1- pipe
Piping components, materials, codes and standards   part 1- pipePiping components, materials, codes and standards   part 1- pipe
Piping components, materials, codes and standards part 1- pipe
 

Similar to Epc issues and recommendations

Turnkey implementation of distribution projects
Turnkey implementation of distribution projectsTurnkey implementation of distribution projects
Turnkey implementation of distribution projectsD.Pawan Kumar
 
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsResume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsNirav Mistry
 
Integrated-Information-Technology.ppt
Integrated-Information-Technology.pptIntegrated-Information-Technology.ppt
Integrated-Information-Technology.pptSanjeebJha3
 
Project Delivery Education Program
Project Delivery Education ProgramProject Delivery Education Program
Project Delivery Education ProgramFrank Cunha
 
Fundamentals of Managing the Data Center Life Cycle for Owners
Fundamentals of Managing the Data Center Life Cycle for OwnersFundamentals of Managing the Data Center Life Cycle for Owners
Fundamentals of Managing the Data Center Life Cycle for OwnersSchneider Electric
 
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanhVGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanhVietnam Green Building Council
 
Supply chain management in project
Supply chain management in projectSupply chain management in project
Supply chain management in projectMukesh Doshi
 
Korea Koso PLM and Supply Chain
Korea Koso PLM and Supply ChainKorea Koso PLM and Supply Chain
Korea Koso PLM and Supply ChainAras
 
Specification writing
Specification writingSpecification writing
Specification writingBSRIA
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectivessombat nirund
 
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedMajor CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedEnergy Construction Forum
 
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsResume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsNirav Mistry
 
Model Format for Building Services Specifications
Model Format for Building Services SpecificationsModel Format for Building Services Specifications
Model Format for Building Services SpecificationsBSRIA
 

Similar to Epc issues and recommendations (20)

COE
COECOE
COE
 
Turnkey implementation of distribution projects
Turnkey implementation of distribution projectsTurnkey implementation of distribution projects
Turnkey implementation of distribution projects
 
CV
CVCV
CV
 
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsResume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
 
Integrated-Information-Technology.ppt
Integrated-Information-Technology.pptIntegrated-Information-Technology.ppt
Integrated-Information-Technology.ppt
 
Project Delivery Education Program
Project Delivery Education ProgramProject Delivery Education Program
Project Delivery Education Program
 
Fundamentals of Managing the Data Center Life Cycle for Owners
Fundamentals of Managing the Data Center Life Cycle for OwnersFundamentals of Managing the Data Center Life Cycle for Owners
Fundamentals of Managing the Data Center Life Cycle for Owners
 
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanhVGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
VGBC Online Series, Phần 10: Quản lý dự án Công trình xanh
 
Varun Garg_CV
Varun Garg_CVVarun Garg_CV
Varun Garg_CV
 
1PROF_RESUME
1PROF_RESUME1PROF_RESUME
1PROF_RESUME
 
Supply chain management in project
Supply chain management in projectSupply chain management in project
Supply chain management in project
 
sravankumar
sravankumarsravankumar
sravankumar
 
Korea Koso PLM and Supply Chain
Korea Koso PLM and Supply ChainKorea Koso PLM and Supply Chain
Korea Koso PLM and Supply Chain
 
Specification writing
Specification writingSpecification writing
Specification writing
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectives
 
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedMajor CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
 
SANTHOSH KUMAR UP RCV
SANTHOSH KUMAR UP RCVSANTHOSH KUMAR UP RCV
SANTHOSH KUMAR UP RCV
 
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package UnitsResume_Lead Mechanical Engineer - Static Equipment and Package Units
Resume_Lead Mechanical Engineer - Static Equipment and Package Units
 
Project Delivery Method Selection Tool
Project Delivery Method Selection ToolProject Delivery Method Selection Tool
Project Delivery Method Selection Tool
 
Model Format for Building Services Specifications
Model Format for Building Services SpecificationsModel Format for Building Services Specifications
Model Format for Building Services Specifications
 

Epc issues and recommendations

  • 1. Project KOHINOOR 2010 Engineering Procurement and Construction (EPC)
  • 2. EPC Capabilities Analysis framework EPC projects involve enhancement of certain specific capabilities apart from strong project management and risk management functions Risk Management Project Management 2 EPC Projects Engineering Procurement Construction
  • 3. Issues need to be analyzed in each stage of the EPC project lifecycle 3 EPC Project Lifecycle ENGINEERING Basic engineering Detail engineering Vendor negotiation Floating enquiries Vendor approvals Vendor manufacturing PROCUREMENT Site erection CONSTRUCTION Commissio ning Performance Guarantee
  • 4. Agenda / Management Summary 4 Summary of Key EPC Issues Engineering  Quantity variation  Delay in receipt of drawings at site  Constructability Procurement  Variance in delivery schedule  Post manufacturing rework Construction  Limited focus on commissioning, take over / performance guarantee tests Organization Structure  Limited empowerment of Project Manager
  • 5. Engineering Issues - Quantity Variation Impact due to design quantity variation in a sample of only 6 EPC projects was ~ 50 INR Cr in 04-05 Case Study RCV (Rs Cr.) 5 Quantity Variation* Rs Cr. (% of RCV) Key Items with Variation 60.75 15.67 (25.8%)  Concrete  Rebar 52.5 9 (17.1%)  Pipes and pipe fittings 20.87 3.51 (16.8%)  Pipes and pipe fittings  Instrumentation 171.31 15 (8.8%)  Steel 120 6 (5%)  Steel 30.87 0.80 (2.6%)  Hopper  Counterweight Project 1 Project 2 Project 3 Project 4 Project 5 Instances of significant quantity variation in EPC projects across BUs Project 6 * Quantity variations computed with respect to tender (contract) estimates Source: Interviews with Project Managers / Coordinators of respective projects
  • 6. Quantity variation - Root cause analysis Lack of clarity of requirements from basic engineering Design capacity constraint Inadequate domain Inadequate site exposure 6 People Changes in customer inputs / scope / basic engineering Technology Process Quantity Variation Organization Limited ownership of design and quantities knowledge of designers Inadequate rigor in site / soil Investigation Lack of use of quantity survey software Design team during execution is different from the one during tendering Design partner evaluation process Lack of incentives / penalties for design team Insufficient value Lack of standard designs engineering in execution Limited use of for frequently used items knowledge management systems Lack of norms / indices to facilitate accurate estimation Inadequate internal / 3rd party quality assurance processes
  • 7. Engineering Issues - Drawings delay at site Delay in receipt of drawings at site for EPC projects impacting utilization of Case Study: EPC Project May’ 04 Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun July Apr’ 2006 7 Project Duration Planned Actual 4 months 7 months Kick-off meeting Site mobilized End date Drawings Release Schedule Idling of resources Crashing of resources resources and PBIT ACE Margin: 11% JCR Margin: 9.6%
  • 8. Drawings delay at site - Root cause analysis 8 People High attrition rate Inadequate site exposure Technology Process Drawings delay at site Organization Limited involvement in project plan Shortage of manpower Various disciplines in EDRC not working in project team approach Design capacity constraint Inadequate domain knowledge of designers Delay in receipt of inputs from customer basic engg. / BU / vendors Co-ordination between Kolkatta & Chennai EDRC locations Lack of standard designs for frequently used items Limited use of knowledge management systems Changes in inputs from customer / basic engg. / BU / vendors
  • 9. Engineering Issues- Constructability Designs not optimized due to limited focus on ‘constructability’ Examples of designs with poor ‘constructability’  Varying size throughout the depth of track hopper foundation leading to an increase in shuttering costs and reduced productivity  Use of greater quantity of lesser thickness bracings leading to a drop in subcontractor productivity Salient features of a construction sensitive design  Optimize construction and design cost  Use of repetitive elements and modularization  Clear design details and easy enough to build with minimum risk Maximum savings result when constructability concepts are applied during early stages of the project 9  Sequence of material delivery based on construction input  Use of innovative construction methods such as hand tools and temporary construction materials
  • 10. 10 Design / Engineering Recommendations • Increase end-to-end involvement of design team and establish processes to develop/retain technical resources • Design team involved in tendering stage should also be involved in execution stage • Talent retention & development – Enhance HR processes – ‘Mentors’ to handhold new joiners – Knowledge sharing sessions to facilitate transfer of learnings across projects – Expert lectures from industry experts / in-house experienced personnel – Site exposure of design personnel to incorporate ‘constructability’ principles in design • Encourage design standardization and develop design norms / indices for standard items • Establish database of key design indices for standard items and update the same based on project experiences •Quality assurance process for verifying engineering quantities • 3rd party quality assurance to verify quantities especially for critical projects / projects where in-house technical knowledge is nascent • BU personnel to have basic technical knowledge to verify design quantities
  • 11. 11 Design / Engineering Recommendations • Follow robust design partner evaluation process for external agencies • Evaluation criteria to include expertise related aspects as well as past experiences in previous projects • Include incentives / penalties in contract for quantity variation and constructabilty issues • Improve co-ordination between various departments involved in project / within EDRC • Location of BU representatives at EDRC during engineering stage and at region during execution stage of the project • EDRC project co-ordinator to facilitate co-ordination / integration across various EDRC disciplines and locations
  • 12. Inadequate monitoring & control of critical items leading to defective parts / delays Case Study: EPC Project May’ 05 Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Seemingly small deviations from planned schedule have cascading effect on overall project timelines (and hence costs) due to various interdependencies 12 Procurement Issues 7 months delay in 2 months delay in Multiplier effect commencing supply project duration Supply Erection 9 months May Jun Jul Aug Sep Oct Nov Dec‘ 06 14 months 9 months 13 months Planned Actual Planned Actual 2 months 7 months
  • 13. Procurement Issues - Root cause analysis 13 People Technology Process Site stores incharge lacks BU specific technical knowledge Procurement Issues Organization Delay in finalization of PO Delays between vendor and BU due to clarifications on inputs Limited support from materials department for specialized procurements due to their lack of technical knowledge Limited database of vendors for specialized items Delays in internal approvals / release of advance Limited pre-tender tie ups Weak vendor manufacturing / Inadequate follow- quality processes up with vendors Changes / delays in engineering specifications Limited control over internal suppliers Limited visibility into internal suppliers’ processes / costs Inadequate quality assurance processes
  • 14. 14 Procurement Recommendations • Review internal approval procedures for releasing high value POs • Review limit for high value POs - currently Rs 25 lacs (Rs 45 lacs for TFL projects) • BU Head to be authorized to approve release of PO if procurement costs are within ACE • Leverage IT to speed up approvals process / reduce paperwork • Institutionalize vendor alignment meeting especially for package supplies • All potential vendors to be invited in a joint forum for clarifications on technical/commercial project requirements • Decide standard formats / processes to be used by all vendors for submitting quotes to enable one-to-one comparison • Vendor kick-off meeting after final vendor selection • Representatives from EDRC, BU, consultant to attend the meeting • Upfront agreement between all parties on inputs required and timelines for clarifications on the same • Regular follow-up meetings to be held at a mutually agreed frequency to monitor progress against set timelines
  • 15. 15 Procurement Recommendations • Establish BU specific vendor database / pre-tender tie-ups for specialized items • Tie-ups with regularly used vendors / vendors supplying frequently required items • Minimize site rework • Mock-up assembly at vendor works • 3rd party inspection - even for critical indigenous supplies • Logistics issues to be considered at the time of bid selection / tendering and logistics plan to be prepared after award of contract • Especially critical for ODC cargo / overseas projects • Consider tie-ups with specialized 3PL players
  • 16. •Assign dedicated resource as Supplier Technical Assistant (STA) to collaborate between Project and critical suppliers 16 Procurement CPO1 - project X CPO2 ……. FPO1 FPO2 - project X …….. CPO1 FPO2 ……. Roles & Responsibilities (R&R) Information flow across agencies Information flow across agencies EExxppeedditiitningg Supplier - Castings Supplier - Forgings STA - Project X Technical / quality support Technical / quality support Delivery to Delivery to site site Recommendations
  • 17. 17 Erection / Construction Recommendations •Adhere to established construction / erection standards to ensure robust methodology and quality • Gain upfront agreement with client on standards to be followed • Agree any deviations from standards with client and involve independent 3rd parties for technical clarifications if required • Deploy dedicated commissioning team after completion of site erection activities • Ensure smooth handover (technical / commercial) to client • Provide specific technical support required for take over / performance guarantee tests • Follow a BU specific commissioning checklist to provide quality assurance • Obtain client agreement on checklist parameters • Continuously update checklist based on past project experiences
  • 18. Organization Structure Issues Complexity in managing EPC projects since BU based Project Manager coordinates among various agencies over which he has no direct control Sector Head RPM Sector Head Head - Supply 18 Chain Internal Vendors Region EDRC Materials PROJECT MANAGER L&T in-house vendors such as EWL • Construction Manager • Other staff • P&M • EDRC coordinator –Civil –Mechanical –Electrical –Instrumentation Procurement personnel for commodities common across BUs (steel, concrete, etc) BU Head BU procurement Procurement personnel for BU specific items (valves, etc) Dashed line indicates no direct reporting
  • 19.  Include to-be org structure slide 19