SlideShare a Scribd company logo
Favorite Delay Analysis Methodologies
  Best Practices and Guidelines for Schedule Impact Analysis
                          Volume 1

                                   Chris Carson, PSP, CCM, PMP
           Corporate Director of Project Controls, Alpha Corporation
                Managing Director, Scheduling Excellence Initiative



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
Based on AACE International Recommended Practice
        No. 29R-03, Forensic Schedule Analysis”




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
Observational
                3.1 Static – Gross
                        (As-Planned v. As-Built, Single Base)
                3.2 Static - Periodic
                        (As-Planned v. As-Built, Multiple Base)
                3.3 Dynamic – Contemporaneous “as-is”
                        (Contemporaneous Period Analysis)
                3.4 Dynamic – Contemporaneous “Split”
                        (Bifurcated Contemporaneous Period Analysis)
                3.5 Dynamic – Contemporaneous “Recreated”
                        (Contemporaneous Period Analysis, Recreated)


AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.1 Static – Gross (As-Planned v. As-Built, Single Base)
          • Applicable only to simple projects, short in duration, with a CP
            that’s unlikely to shift
          • Easy to understand, inexpensive to create
          • Not suitable to long or complicated projects because the
            projects change and the measuring point does not.
          • Use when no update schedules available
          • Need as-planned schedule and as-built data


AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.1 Static – Gross (As-Planned v. As-Built, Single Base)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.1 Static – Gross (As-Planned v. As-Built, Single Base)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.2. Static - Periodic                        (As-Planned v. As-Built, Multiple
        Base)
          • Similar to Single Base version
          • Measuring it in periods adds little since no new data?
          • May find updates useful – but if validated updates available, may
            use other methods that assess CP changes
          • Need as-planned schedule and as-built data
          • May provide for better presentation


AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.2. Static - Periodic               (As-Planned v. As-Built, Multiple Base)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.2. Static - Periodic               (As-Planned v. As-Built, Multiple Base)




        Continued next slide



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.2. Static - Periodic               (As-Planned v. As-Built, Multiple Base)

  Continued from previous slide




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.3. Dynamic – Contemporaneous “as-is”
                  (Contemporaneous Period Analysis)
          • Applicable on complicated projects
          • Uses contemporaneous updates as new baselines
          • If done monthly, then it could be called a “Windows” analysis
          • Handles many problems like concurrency well




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.3. Dynamic – Contemporaneous “as-is” (CPA)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.3. Dynamic – Contemporaneous “as-is” (CPA)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.4. Dynamic – Contemporaneous “Split”
                  (Bifurcated Contemporaneous Period)
          • Applicable on complicated projects
          • Uses contemporaneous updates as new baselines
          • If done monthly, then it could be called a “Windows” analysis
          • Handles many problems like concurrency well
          • The “split” separates Logic-type changes from Actual Progress



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.4. Dynamic – Contemporaneous “Split”        (Bifurcated CPA)




        Continued next slide



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.4. Dynamic – Contemporaneous “Split”        (Bifurcated CPA)
                                                               Continued from
                                                                previous slide




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.4. Dynamic – Contemporaneous “Split”        (Bifurcated CPA)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.5. Dynamic – Contemporaneous “Recreated”
                   (Contemporaneous Period Analysis)
          • Applicable on complicated projects
          • Uses RECREATED updates as new baselines
          • If done monthly, then it might be called a “Windows” analysis
          • Handles many problems like concurrency well
          • However – virtually all of the baselines are created by the
            analyst



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.5. Dynamic – Contemporaneous “Recreated”     (Recreated CPA)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.5. Dynamic – Contemporaneous “Recreated”                            (Recreated CPA)




                                                     Continued next slide
AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.5. Dynamic – Contemporaneous “Recreated”     (Recreated CPA)

                                                           Continued from
                                                            previous slide




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• Modeled
          • 3.6 Additive – Single Base          (Impacted as-planned)
          • 3.7 Additive – Multiple Base        (Retrospective TIA)
          • 3.8 Subtractive – Single Simulation (Collapsed as-built)
          • 3.9 Subtractive – Multiple Simulation




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.6 Additive – Single Base (Impacted As-Planned)
          • Accuracy very dependent on inclusiveness of fragnets and
            accuracy of as-planned schedule.
          • Also dependent on changes in Critical Path from As-Planned
          • Easy to understand
          • Can be purely hypothetical, generally does not prevail in
            litigation
          • Concurrency not addressed


AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.6 Additive – Single Base (Impacted As-Planned)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.6 Additive – Single Base (Impacted As-Planned)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.7 Additive – Multiple Base (Retrospective TIA)
          • Accuracy dependent on inclusiveness of fragnets and accuracy of
            updates – however more likely to include both owner and
            contractor issues
          • Easy to understand
          • No as-built required (although still useful)
          • Updates useful if used (failure to correlate creates problem)
          • Associated with actual events
          • Concurrency easily addressed by a two step process

AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.7 Additive – Multiple Base (Retrospective TIA)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.7 Additive – Multiple Base (Retrospective TIA)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.8 Subtractive – Single Simulation (Collapsed As-
        Built)
          • Accuracy dependent on creation of after the fact logic
          • Easy to understand
          • Uses actual events
          • Can be viewed as hypothetical
          • Critical path can be difficult to identify



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.8 Subtractive – Single Simulation (Collapsed As-Built)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.8 Subtractive – Single Simulation (Collapsed As-Built)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.9 Subtractive – Multiple Simulation
          • Only known practitioner – Long International?
          • Accuracy still dependent on creation of after the fact logic
          • Uses actual Events
          • Can be viewed as hypothetical
          • Critical path can be difficult to identify




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.1 Static – Gross (As-Planned v. As-Built, Single Base)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• 3.1 Static – Gross (As-Planned v. As-Built, Single Base)




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
Forensic Use of                            METHOD
       Analysis            3.1   3.2   3.3     3.4   3.5   3.6   3.7   3.8

    Non-Compensable
                           OK    OK    OK      OK    OK    OK    OK    OK
     Time Extension


   Compensable Delay       OK    OK    OK      OK    OK                OK


   Right to Finish Early
                                                                       OK
   Compensable Delay

   Entitlement to Early
                           OK    OK    OK      OK    OK    OK    OK    OK
   Completion Bonus

    Disruption Without
                           OK    OK    OK      OK    OK    OK    OK
      Project Delay

       Constructive
                                               OK          OK    OK
       Acceleration



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
•




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
•
            •   Must allow the source data to bear on the selection process
            •   Cannot predetermine a technique based on personal preference
            •   Balance client needs, budget, and time with sound analysis
                philosophy




AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• Observational?
         • Count
      • Modeled?
         • Count



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• Observational                                     • Observational
      • 3.1 Static – Gross                             • Count
      • 3.2 Static - Periodic                          • Count
      • 3.3 Dynamic – Contemporaneous “as-is”          • Count
      • 3.4 Dynamic – Contemporaneous “Split”          • Count
      • 3.5 Dynamic – Contemporaneous                  • Count
        “Recreated”



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis
• Modeled                                        • Modeled
         • 3.6 Additive – Single Base                  • Count
         • 3.7 Additive – Multiple Base                • Count
         • 3.8 Subtractive – Single Simulation         • Count
         • 3.9 Subtractive – Multiple Simulation       • Count



AACE International Recommended Practice No. 29R03,
Forensic Schedule Analysis

More Related Content

What's hot

50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
Tim Lloyd
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
Michael Pink
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Delay - EOT claims
Delay - EOT claimsDelay - EOT claims
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Chris Carson
 
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامسأسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
mohamed Ismail
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
ADITYA GHUMARE
 
Standard Forms of Construction Contracts
Standard Forms of Construction ContractsStandard Forms of Construction Contracts
Standard Forms of Construction Contracts
M Maged Hegazy, LLM, MBA, CCP, P3O
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
Moustafa Ismail Abu Dief
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Michael Pink
 
CCP Course - Introduction.pdf
CCP Course - Introduction.pdfCCP Course - Introduction.pdf
CCP Course - Introduction.pdf
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
Procept Associates
 
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEotمحاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
Khaled M. Al Kolfat MS.Eng,MoP,P3O,PMOC,PMP,M.ASCE
 
Claims
ClaimsClaims
Claims
Mike Debiak
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Project Controls Expo
 

What's hot (20)

50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Delay - EOT claims
Delay - EOT claimsDelay - EOT claims
Delay - EOT claims
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
 
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامسأسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
Standard Forms of Construction Contracts
Standard Forms of Construction ContractsStandard Forms of Construction Contracts
Standard Forms of Construction Contracts
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
CCP Course - Introduction.pdf
CCP Course - Introduction.pdfCCP Course - Introduction.pdf
CCP Course - Introduction.pdf
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEotمحاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
 
Claims
ClaimsClaims
Claims
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 

Viewers also liked

Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
katrin enders
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
Farhan Moosa
 
SanDiegoPresentation
SanDiegoPresentationSanDiegoPresentation
SanDiegoPresentation
Anders Axelson
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
Chris Carson
 
The Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact AnalysisThe Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact Analysis
Lisa Dehner
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
Chris Carson
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
Chris Carson
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
Chris Carson
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
Chris Carson
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
Chris Carson
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls Pp
Chris Carson
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
Chris Carson
 
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1
Chris Carson
 
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
Chris Carson
 
Bdsm intro PART II/2/B
Bdsm intro PART II/2/BBdsm intro PART II/2/B
Bdsm intro PART II/2/B
Cree Stetler
 
Piezo roads new
Piezo roads newPiezo roads new
Piezo roads new
Soma Giri
 
REPORT PPT
REPORT PPTREPORT PPT
REPORT PPT
sanjay sarda
 

Viewers also liked (19)

Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
SanDiegoPresentation
SanDiegoPresentationSanDiegoPresentation
SanDiegoPresentation
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
The Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact AnalysisThe Vertex Companies, Inc. - Time Impact Analysis
The Vertex Companies, Inc. - Time Impact Analysis
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls Pp
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1
 
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
Bdsm intro PART II/2/B
Bdsm intro PART II/2/BBdsm intro PART II/2/B
Bdsm intro PART II/2/B
 
Piezo roads new
Piezo roads newPiezo roads new
Piezo roads new
 
REPORT PPT
REPORT PPTREPORT PPT
REPORT PPT
 

Similar to Favorite Delay Analysis Methodologies Town Hall SEI

Scalable Software Testing and Verification of Non-Functional Properties throu...
Scalable Software Testing and Verification of Non-Functional Properties throu...Scalable Software Testing and Verification of Non-Functional Properties throu...
Scalable Software Testing and Verification of Non-Functional Properties throu...
Lionel Briand
 
Database performance improvement, a six sigma project (mesure) by nirav shah
Database performance improvement, a six sigma project (mesure) by nirav shah Database performance improvement, a six sigma project (mesure) by nirav shah
Database performance improvement, a six sigma project (mesure) by nirav shah
Nirav Shah
 
MCA Daemon: Hybrid Throughput Analysis Beyond Basic Blocks
MCA Daemon: Hybrid Throughput Analysis Beyond Basic BlocksMCA Daemon: Hybrid Throughput Analysis Beyond Basic Blocks
MCA Daemon: Hybrid Throughput Analysis Beyond Basic Blocks
Min-Yih Hsu
 
Automating Speed: A Proven Approach to Preventing Performance Regressions in ...
Automating Speed: A Proven Approach to Preventing Performance Regressions in ...Automating Speed: A Proven Approach to Preventing Performance Regressions in ...
Automating Speed: A Proven Approach to Preventing Performance Regressions in ...
HostedbyConfluent
 
Test Estimation
Test Estimation Test Estimation
Test Estimation
SQALab
 
Mit16 30 f10_lec01
Mit16 30 f10_lec01Mit16 30 f10_lec01
Mit16 30 f10_lec01
Masrufaiyah Masrufauyah
 
SOFTWARE TESTING.pptx
SOFTWARE TESTING.pptxSOFTWARE TESTING.pptx
SOFTWARE TESTING.pptx
DrTThendralCompSci
 
Time series
Time seriesTime series
Time series
Haitham Ahmed
 
11 generalsisation of fluent
11 generalsisation of fluent11 generalsisation of fluent
11 generalsisation of fluent
chowdavaramsaiprasad
 
Schedule Analysis Methods - AACE 29R-03 Recommended.pdf
Schedule Analysis Methods - AACE 29R-03 Recommended.pdfSchedule Analysis Methods - AACE 29R-03 Recommended.pdf
Schedule Analysis Methods - AACE 29R-03 Recommended.pdf
Anwar379976
 
Cs 331 Data Structures
Cs 331 Data StructuresCs 331 Data Structures
Schedulability of Rate Monotonic Algorithm using Improved Time Demand Analysi...
Schedulability of Rate Monotonic Algorithm using Improved Time Demand Analysi...Schedulability of Rate Monotonic Algorithm using Improved Time Demand Analysi...
Schedulability of Rate Monotonic Algorithm using Improved Time Demand Analysi...
IJECEIAES
 
Big Data Day LA 2016/ Use Case Driven track - Shaping the Role of Data Scienc...
Big Data Day LA 2016/ Use Case Driven track - Shaping the Role of Data Scienc...Big Data Day LA 2016/ Use Case Driven track - Shaping the Role of Data Scienc...
Big Data Day LA 2016/ Use Case Driven track - Shaping the Role of Data Scienc...
Data Con LA
 
Scalable and Cost-Effective Model-Based Software Verification and Testing
Scalable and Cost-Effective Model-Based Software Verification and TestingScalable and Cost-Effective Model-Based Software Verification and Testing
Scalable and Cost-Effective Model-Based Software Verification and Testing
Lionel Briand
 
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
Egyptian Engineers Association
 
How to conduct abstract screening for systematic review – Pubrica
How to conduct abstract screening for systematic review – PubricaHow to conduct abstract screening for systematic review – Pubrica
How to conduct abstract screening for systematic review – Pubrica
Pubrica
 
Software Testing- Principles of testing- Mazenet Solution
Software Testing- Principles of testing- Mazenet SolutionSoftware Testing- Principles of testing- Mazenet Solution
Software Testing- Principles of testing- Mazenet Solution
Mazenetsolution
 
Chapter 3 - Analytical Techniques
Chapter 3 - Analytical TechniquesChapter 3 - Analytical Techniques
Chapter 3 - Analytical Techniques
Neeraj Kumar Singh
 
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHM
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHMSTUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHM
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHM
Avay Minni
 
Real time Scheduling in Operating System for Msc CS
Real time Scheduling in Operating System for Msc CSReal time Scheduling in Operating System for Msc CS
Real time Scheduling in Operating System for Msc CS
Thanveen
 

Similar to Favorite Delay Analysis Methodologies Town Hall SEI (20)

Scalable Software Testing and Verification of Non-Functional Properties throu...
Scalable Software Testing and Verification of Non-Functional Properties throu...Scalable Software Testing and Verification of Non-Functional Properties throu...
Scalable Software Testing and Verification of Non-Functional Properties throu...
 
Database performance improvement, a six sigma project (mesure) by nirav shah
Database performance improvement, a six sigma project (mesure) by nirav shah Database performance improvement, a six sigma project (mesure) by nirav shah
Database performance improvement, a six sigma project (mesure) by nirav shah
 
MCA Daemon: Hybrid Throughput Analysis Beyond Basic Blocks
MCA Daemon: Hybrid Throughput Analysis Beyond Basic BlocksMCA Daemon: Hybrid Throughput Analysis Beyond Basic Blocks
MCA Daemon: Hybrid Throughput Analysis Beyond Basic Blocks
 
Automating Speed: A Proven Approach to Preventing Performance Regressions in ...
Automating Speed: A Proven Approach to Preventing Performance Regressions in ...Automating Speed: A Proven Approach to Preventing Performance Regressions in ...
Automating Speed: A Proven Approach to Preventing Performance Regressions in ...
 
Test Estimation
Test Estimation Test Estimation
Test Estimation
 
Mit16 30 f10_lec01
Mit16 30 f10_lec01Mit16 30 f10_lec01
Mit16 30 f10_lec01
 
SOFTWARE TESTING.pptx
SOFTWARE TESTING.pptxSOFTWARE TESTING.pptx
SOFTWARE TESTING.pptx
 
Time series
Time seriesTime series
Time series
 
11 generalsisation of fluent
11 generalsisation of fluent11 generalsisation of fluent
11 generalsisation of fluent
 
Schedule Analysis Methods - AACE 29R-03 Recommended.pdf
Schedule Analysis Methods - AACE 29R-03 Recommended.pdfSchedule Analysis Methods - AACE 29R-03 Recommended.pdf
Schedule Analysis Methods - AACE 29R-03 Recommended.pdf
 
Cs 331 Data Structures
Cs 331 Data StructuresCs 331 Data Structures
Cs 331 Data Structures
 
Schedulability of Rate Monotonic Algorithm using Improved Time Demand Analysi...
Schedulability of Rate Monotonic Algorithm using Improved Time Demand Analysi...Schedulability of Rate Monotonic Algorithm using Improved Time Demand Analysi...
Schedulability of Rate Monotonic Algorithm using Improved Time Demand Analysi...
 
Big Data Day LA 2016/ Use Case Driven track - Shaping the Role of Data Scienc...
Big Data Day LA 2016/ Use Case Driven track - Shaping the Role of Data Scienc...Big Data Day LA 2016/ Use Case Driven track - Shaping the Role of Data Scienc...
Big Data Day LA 2016/ Use Case Driven track - Shaping the Role of Data Scienc...
 
Scalable and Cost-Effective Model-Based Software Verification and Testing
Scalable and Cost-Effective Model-Based Software Verification and TestingScalable and Cost-Effective Model-Based Software Verification and Testing
Scalable and Cost-Effective Model-Based Software Verification and Testing
 
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
 
How to conduct abstract screening for systematic review – Pubrica
How to conduct abstract screening for systematic review – PubricaHow to conduct abstract screening for systematic review – Pubrica
How to conduct abstract screening for systematic review – Pubrica
 
Software Testing- Principles of testing- Mazenet Solution
Software Testing- Principles of testing- Mazenet SolutionSoftware Testing- Principles of testing- Mazenet Solution
Software Testing- Principles of testing- Mazenet Solution
 
Chapter 3 - Analytical Techniques
Chapter 3 - Analytical TechniquesChapter 3 - Analytical Techniques
Chapter 3 - Analytical Techniques
 
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHM
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHMSTUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHM
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHM
 
Real time Scheduling in Operating System for Msc CS
Real time Scheduling in Operating System for Msc CSReal time Scheduling in Operating System for Msc CS
Real time Scheduling in Operating System for Msc CS
 

More from Chris Carson

Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Chris Carson
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry Scheduling
Chris Carson
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
Chris Carson
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
Chris Carson
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
Chris Carson
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
Chris Carson
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
Chris Carson
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Chris Carson
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
Chris Carson
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful Mediation
Chris Carson
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
Chris Carson
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
Chris Carson
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
Chris Carson
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
Chris Carson
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
Chris Carson
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony Mistakes
Chris Carson
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
Chris Carson
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor Scheduling
Chris Carson
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMI
Chris Carson
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.
Chris Carson
 

More from Chris Carson (20)

Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry Scheduling
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful Mediation
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony Mistakes
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor Scheduling
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMI
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.
 

Favorite Delay Analysis Methodologies Town Hall SEI

  • 1. Favorite Delay Analysis Methodologies Best Practices and Guidelines for Schedule Impact Analysis Volume 1 Chris Carson, PSP, CCM, PMP Corporate Director of Project Controls, Alpha Corporation Managing Director, Scheduling Excellence Initiative AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 2. Based on AACE International Recommended Practice No. 29R-03, Forensic Schedule Analysis” AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 3. Observational 3.1 Static – Gross (As-Planned v. As-Built, Single Base) 3.2 Static - Periodic (As-Planned v. As-Built, Multiple Base) 3.3 Dynamic – Contemporaneous “as-is” (Contemporaneous Period Analysis) 3.4 Dynamic – Contemporaneous “Split” (Bifurcated Contemporaneous Period Analysis) 3.5 Dynamic – Contemporaneous “Recreated” (Contemporaneous Period Analysis, Recreated) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 4. • 3.1 Static – Gross (As-Planned v. As-Built, Single Base) • Applicable only to simple projects, short in duration, with a CP that’s unlikely to shift • Easy to understand, inexpensive to create • Not suitable to long or complicated projects because the projects change and the measuring point does not. • Use when no update schedules available • Need as-planned schedule and as-built data AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 5. • 3.1 Static – Gross (As-Planned v. As-Built, Single Base) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 6. • 3.1 Static – Gross (As-Planned v. As-Built, Single Base) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 7. • 3.2. Static - Periodic (As-Planned v. As-Built, Multiple Base) • Similar to Single Base version • Measuring it in periods adds little since no new data? • May find updates useful – but if validated updates available, may use other methods that assess CP changes • Need as-planned schedule and as-built data • May provide for better presentation AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 8. • 3.2. Static - Periodic (As-Planned v. As-Built, Multiple Base) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 9. • 3.2. Static - Periodic (As-Planned v. As-Built, Multiple Base) Continued next slide AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 10. • 3.2. Static - Periodic (As-Planned v. As-Built, Multiple Base) Continued from previous slide AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 11. • 3.3. Dynamic – Contemporaneous “as-is” (Contemporaneous Period Analysis) • Applicable on complicated projects • Uses contemporaneous updates as new baselines • If done monthly, then it could be called a “Windows” analysis • Handles many problems like concurrency well AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 12. • 3.3. Dynamic – Contemporaneous “as-is” (CPA) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 13. • 3.3. Dynamic – Contemporaneous “as-is” (CPA) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 14. • 3.4. Dynamic – Contemporaneous “Split” (Bifurcated Contemporaneous Period) • Applicable on complicated projects • Uses contemporaneous updates as new baselines • If done monthly, then it could be called a “Windows” analysis • Handles many problems like concurrency well • The “split” separates Logic-type changes from Actual Progress AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 15. • 3.4. Dynamic – Contemporaneous “Split” (Bifurcated CPA) Continued next slide AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 16. • 3.4. Dynamic – Contemporaneous “Split” (Bifurcated CPA) Continued from previous slide AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 17. • 3.4. Dynamic – Contemporaneous “Split” (Bifurcated CPA) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 18. • 3.5. Dynamic – Contemporaneous “Recreated” (Contemporaneous Period Analysis) • Applicable on complicated projects • Uses RECREATED updates as new baselines • If done monthly, then it might be called a “Windows” analysis • Handles many problems like concurrency well • However – virtually all of the baselines are created by the analyst AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 19. • 3.5. Dynamic – Contemporaneous “Recreated” (Recreated CPA) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 20. • 3.5. Dynamic – Contemporaneous “Recreated” (Recreated CPA) Continued next slide AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 21. • 3.5. Dynamic – Contemporaneous “Recreated” (Recreated CPA) Continued from previous slide AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 22. • Modeled • 3.6 Additive – Single Base (Impacted as-planned) • 3.7 Additive – Multiple Base (Retrospective TIA) • 3.8 Subtractive – Single Simulation (Collapsed as-built) • 3.9 Subtractive – Multiple Simulation AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 23. • 3.6 Additive – Single Base (Impacted As-Planned) • Accuracy very dependent on inclusiveness of fragnets and accuracy of as-planned schedule. • Also dependent on changes in Critical Path from As-Planned • Easy to understand • Can be purely hypothetical, generally does not prevail in litigation • Concurrency not addressed AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 24. • 3.6 Additive – Single Base (Impacted As-Planned) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 25. • 3.6 Additive – Single Base (Impacted As-Planned) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 26. • 3.7 Additive – Multiple Base (Retrospective TIA) • Accuracy dependent on inclusiveness of fragnets and accuracy of updates – however more likely to include both owner and contractor issues • Easy to understand • No as-built required (although still useful) • Updates useful if used (failure to correlate creates problem) • Associated with actual events • Concurrency easily addressed by a two step process AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 27. • 3.7 Additive – Multiple Base (Retrospective TIA) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 28. • 3.7 Additive – Multiple Base (Retrospective TIA) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 29. • 3.8 Subtractive – Single Simulation (Collapsed As- Built) • Accuracy dependent on creation of after the fact logic • Easy to understand • Uses actual events • Can be viewed as hypothetical • Critical path can be difficult to identify AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 30. • 3.8 Subtractive – Single Simulation (Collapsed As-Built) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 31. • 3.8 Subtractive – Single Simulation (Collapsed As-Built) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 32. • 3.9 Subtractive – Multiple Simulation • Only known practitioner – Long International? • Accuracy still dependent on creation of after the fact logic • Uses actual Events • Can be viewed as hypothetical • Critical path can be difficult to identify AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 33. • 3.1 Static – Gross (As-Planned v. As-Built, Single Base) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 34. • 3.1 Static – Gross (As-Planned v. As-Built, Single Base) AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 35. Forensic Use of METHOD Analysis 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 Non-Compensable OK OK OK OK OK OK OK OK Time Extension Compensable Delay OK OK OK OK OK OK Right to Finish Early OK Compensable Delay Entitlement to Early OK OK OK OK OK OK OK OK Completion Bonus Disruption Without OK OK OK OK OK OK OK Project Delay Constructive OK OK OK Acceleration AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 36. AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 37. AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 38. • AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 39. • Must allow the source data to bear on the selection process • Cannot predetermine a technique based on personal preference • Balance client needs, budget, and time with sound analysis philosophy AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 40. • Observational? • Count • Modeled? • Count AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 41. • Observational • Observational • 3.1 Static – Gross • Count • 3.2 Static - Periodic • Count • 3.3 Dynamic – Contemporaneous “as-is” • Count • 3.4 Dynamic – Contemporaneous “Split” • Count • 3.5 Dynamic – Contemporaneous • Count “Recreated” AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis
  • 42. • Modeled • Modeled • 3.6 Additive – Single Base • Count • 3.7 Additive – Multiple Base • Count • 3.8 Subtractive – Single Simulation • Count • 3.9 Subtractive – Multiple Simulation • Count AACE International Recommended Practice No. 29R03, Forensic Schedule Analysis