SlideShare a Scribd company logo
“ 12 Step Program ”  for an  Integrated Master Schedule   ( Creating an “Installation Schedule” for the Military Customer from  available  Data) ,[object Object],[object Object],[object Object]
What is an  Integrated Master Schedule (IMS) ? ,[object Object],[object Object],[object Object],[object Object]
IMS Collaboration Field Office Construction Contractor Customer PDT District PDT
Benefits to Integrated Master Schedule (IMS) ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Helping the Program/Project Manager help the Customer ! ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Automated Information System (AIS) Components ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
PD2 5 P2 System P2 System OP3 Oracle Projects Primavera Project Manager CEFMS SWG CEFMS SWF CEFMS SWT CEFMS  SWL Primavision Update Project Update Budget OP to CEFMS transfer Transfer “CEFMS  Actuals ”  to OP Project Initiation Project Initiation OFA Reports Transfer  “ OP  Actuals ” to  PPM Submit  Budget - PPM to OP RMS CMI via PMBP Portal Staging Table CRMS CAPCES DD1391 Processor Number Project Initiation Form From  PMgr myPrimavera SWT RMS SWF RMS SPK RMS QCS ftps Contractor ’ s Schedule  Pay Activities with $ & SDEF Coding SDEF
Access to  QCS Download  &  User Guides http://www.rmssupport.com
User Guides  for QCS and SDEF
Scheduling Standards
Contractor’s Schedule Consolidation for IMS Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Customer IMS SDEF Activity Codes Activity ID Nomenclatures Resource Loaded IMS WBS IMS Activity Codes
Each USACE “contract” will have a Contractor’s Construction Schedule/QCS Interface ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Multiple P2 Projects containing Multiple Contracts ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
PD2/SPS/RMS/QCS Contract Detail Multiple Projects & Contracts (Ready for Invoice Processing) 0001  $$$$$$ 0002  $$$$$$ 0003  $$$$$$ 0001  $$$$$$ 0002  $$$$$$ 0001  $$$$$$ 0002  $$$$$$ 0003  $$$$$$ 0001  $$$$$$$ 0002  $$$$$$$ 0001  $$$$$$  0002  $$$$$$ RMS Balanced PD2/SPS CLINS (Contracting) RMS Balanced Project A: Pay Activity 8 Pay Activity 9 Pay Activity 12 Pay Activity 10 Pay Activity 11 Pay Activity 6 Pay Activity 7 Pay Activity 5 Pay Activity 3 Pay Activity 4 Pay Activity 1 Pay Activity 2 QCS-Contractor Schedule (Field Office) M2185575 FWI-6717GG Bldg 4 FA8903-06-D8520-0025 C.60000.61000.2 Contract-CONSTSVCS-C2 Bldg 4 M2185571 FWI-B74KGD Central Energy Plant FA8903-06-D8520-0025 C.60000.61000.1 Contract-CONSTSVCS-C1 CEP Project C: M2185572 FWI-740C4 Bldg 3 FA8903-06-D8520-0024 B.60000.61000.1 Contract-CONSTSVCS-B1 Bldg 3 Project B: M2185570 FWI-9638GD Bldg 2 FA8903-06-D8520-0023 A.60000.61000.2 Contract-CONSTSVCS-A2 Bldg 2 M2185569 FWI-6717CK Bldg1 FA8903-06-D8520-0022 A.60000.61000.1 Contract-CONSTSVCS-A1 Bldg 1 CEFMS-Funding (Program Analyst Contract Phase (Ph) & Title Linked to  Multiple  Contracts in RMS (RMS Coordinator) RMS Contract  Post  Award (RMS Coordinator) Primavera (PPM/P2) WBS Structure (SWF PMO) Project
Customer’s Integrated Installation  Primavera   Schedule Portfolio Each segment of this schedule represents a separate contracting action from the same or different contractor. Project A Bldg 1 Project A Bldg 2 Project B Bldg 3 Project C CEP Project C Bldg 4
PD2/SPS/RMS/QCS Contract Schedule & Pay App (ENG090 ) (Schedule & RMS Update) 0001  $$$$$$ 0002  $$$$$$ 0003  $$$$$$ 0001  $$$$$$ 0002  $$$$$$ 0001  $$$$$$ 0002  $$$$$$ 0003  $$$$$$ 0001  $$$$$$$ 0002  $$$$$$$ 0001  $$$$$$  0002  $$$$$$ RMS Balanced PD2/SPS CLINS RMS Balanced Project A: Pay Activity 8 (5%) Pay Activity 9 Pay Activity 12 Pay Activity 10(15%) Pay Activity 11(10%) Pay Activity 6 (10%) Pay Activity 7 Pay Activity 5 Pay Activity 3 (20%) Pay Activity 4 Pay Activity 1 (50%) Pay Activity 2  QCS-Contractor Statused Schedule M2185575 FWI-6717GG Bldg 4 FA8903-06-D8520-0025 C.60000.61000.2 Contract-CONSTSVCS-C2 Bldg 4 M2185571 FWI-B74KGD Central Energy Plant FA8903-06-D8520-0025 C.60000.61000.1 Contract-CONSTSVCS-C1 CEP Project C: M2185572 FWI-740C4 Bldg 3 FA8903-06-D8520-0024 B.60000.61000.1 Contract-CONSTSVCS-B1 Bldg 3 Project B: M2185570 FWI-9638GD Bldg 2 FA8903-06-D8520-0023 A.60000.61000.2 Contract-CONSTSVCS-A2 Bldg 2 M2185569 FWI-6717CK Bldg1 FA8903-06-D8520-0022 A.60000.61000.1 Contract-CONSTSVCS-A1 Bldg 1 CEFMS-Funding Contract Phase (Ph) & Title Linked to  One  Contract in RMS RMS Contract  Post  Award Primavera (PPM/P2) WBS Structure Project
This sure looks like  a lot  of extra work! (Building an Integrated Master Schedule using Primavera software) ,[object Object],[object Object],[object Object]
Lackland AFB ,[object Object],[object Object],[object Object]
Lackland AFB, San Antonio, TX ATC Site
Using Primavera (P3 or P6) to “host” an Integrated Master Schedule ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Step Six : “Connecting the Dots” ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
USACE Projects DFAC#1 In Process Completed ATC #1-Small Business (SB) Customer Utility Projects TBD TBD ATC #2-SB ATC #3 & 4 TBD TBD DFAC #2 Customer TBD TBD ATC #4 Customer TBD TBD ATC #3 ATC# 1&2, Customer Projects TBD TBD DFAC #1 Customer Demo Projects TBD TBD ATC #2-LB Customer Demolition & Utilities/Roads Completed Completed ATC #1-Large Business (LB) Dependent Project Awarded/Const RMS/QCS Design/RFP Development USACE Project
Non-USACE Projects Demolish Bldg 9050 Completed Completed Renovate Carswell Ave ATC East Campus In-Progress Completed Upgrade Sewer Line ATC East Campus TBD TBD Upgrade COMM Duct Bank Demolish Bldg 6045-6048 Completed Completed Abate Bldg 6045-6048 Demolish Bldg 9050 Completed Completed Abate Bldg 9050 ATC#3 TBD Completed Demolish Bldg 6045-6048 New Road TBD TBD New Access Control Point ATC#1 In-Progress Completed Move Building 6359 ATC #1 Start Completed Completed Demolish Bldg 9050 Dependent Project Awarded/Const Design/RFP  Customer Project
Project Summary LACK/X1 MPX N/A Demolish Bldg 9050 LACK/X2 MPX N/A Renovate Carswell Ave LACK/X3 MSP 7 N/A Move Building 6359 LACK/X4 MSP 7 N/A Upgrade Sewer Line LACK/X9 MSP 7 N/A Abate Bldg 6045-6048 LACK/X8 MSP 7 N/A Abate Bldg 9050 LACK/X7 MSP 7 N/A Demolish Bldg 6045-6048 LACK/X6 MSP 7 N/A New Access Control Point LACK/X5 MSP 7 N/A Upgrade COMM Duct Bank Customer Project LACK/D2 TBD Not Completed DFAC #2 LACK/A4 TBD Not Completed ATC #4 LACK/A3 TBD Not Completed ATC #3 LACK/D1 TBD Not Completed DFAC #1 LACK/B2 TBD Not Completed ATC #2-SB LACK/A2 TBD Not Completed ATC #2-LB LACKB1 P3/PRX Not Completed ATC #1-Small Bus LACK/A1 P3/PRX Completed ATC #1-Large Bus Master Schedule Mapping Contractor’s Schedule Format QCS/RMS USACE Project
All “Known Projects” Added to “Projects Group” LACK as Subprojects Convert MPX to P3, Copy to Group MPX LACK/X1 Demolish Bldg 9050 Convert MPX to P3, Copy to Group MPX LACK/X2 Renovate Carswell Ave XML 2007, Import P6 and Export as P3, Restore and Copy to Group MSP 7 LACK/X3 Move Building 6359 P3 Export Excel Template, Copy Paste to Template and Import to P3 file, Copy to Group Excel LACK/X4 Upgrade Sewer Line TBD MSP 7 LACK/X9 Abate Bldg 6045-6048 TBD MSP 7 LACK/X8 Abate Bldg 9050 TBD MSP 7 LACK/X7 Demolish Bldg 6045-6048 TBD MSP 7 LACK/X6 New Access Control Point TBD MSP 7 LACK/X5 Upgrade COMM Duct Bank Customer Project TBD TBD LACK/D2 DFAC #2 TBD TBD LACK/A4 ATC #4 TBD TBD LACK/A3 ATC #3 TBD TBD LACK/D1 DFAC #1 TBD TBD LACK/B2 ATC #2-SB TBD TBD LACK/A2 ATC #2-LB Restore PRX, Copy to Group P3/PRX LACKB1 ATC #1-Small Bus Restore PRX, Copy to Group P3/PRX LACK/A1 ATC #1-Large Bus P3 Conversion Instructions Current  Contractor’s Schedule Format P3 Master Schedule Mapping USACE Project
Conversion Reference Tables ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Summary Conversion Table   Export from PPM to P3, Copy new project to IMS Project Group Import .XER new project under Group EPS v 6.2.1 or later .XER (P6v6.2.1+) Export blank XLS from new Project created in IMS P3.1, Copy paste content of original XLS to new XLS, Import new Excel file into IMS P3.1 Export blank XLS from new Project created in IMS P6.2.1, Copy paste content of original XLS to new XLS, Import new Excel file into IMS P6.2.1 .xls (Excel) Convert file to XLS per convertor file from MS website, Export blank XLS from new Project created in IMS P3.1, Copy paste content of original XLS to new XLS, Import new Excel file into IMS P3.1 Convert file to XLS per convertor file from MS website, Export blank XLS from new Project created in IMS P6.2.1, Copy paste content of original XLS to new XLS, Import new Excel file into IMS P6.2.1 .xlsx (Excel 2007) Import .XER into v6.2.1, Export to P3, Copy new project to IMS Project Group (assign 2 chs Sub project ID) Import .XER new project under Group EPS v 6.2.1 .XER (P6v6.2.1) Export from PPM to P3, Copy new project to IMS Project Group Import .XER new project under Group EPS v 6.1 .XER (P6v6.1) Export from PPM to P3, Copy new project to IMS Project Group Import .XER new project under Group EPS v 6.0 .XER (P6) Export from PPM to P3, Copy new project to IMS Project Group Import .XER new project under Group EPS v 5.0 .XER (P5) Restore PRX to P3, restored P3 project copied to IMS Project Group (assign 2 chs Sub project ID) Restore PRX to P3, Import P3 project to P6.2.1 EPS as a new project under Group EPS PRX (P3) Import XML 2007 to P6.2.1, Export new project as P3, Restore to P3 and copied to IMS Project Group Import XML 2007 to new project in EPS XML 2007 (MSP) Import XML 2002/3 to P6.2.1, Export new project as P3, Restore to P3 and copied to IMS Project Group Import XML 2002/3 to new project in EPS XML 2002/2003 (MSP) Tools, MPX to P3, P3 project copied to IMS Project Group Import MPX as new project in EPS MPX (MSP) TO: P3.1 TO: P6.2.1 FROM File Format
Using Primavera (P3 or P6) to compile a Customer Master Schedule (cont) ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Benefits to Integrated Master Schedule (IMS) ,[object Object],[object Object],[object Object],[object Object],[object Object]
Customer’s Integrated Master  Primavera   Schedule Each segment of this schedule represents a separate contracting action or P2 Project from the same or different contractor. Demolition ATC#1 ATC#2 DFAC#1 ATC #3
Summary: Benefits to Integrated Master Schedule (IMS) ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Q & A
Contact Information ,[object Object],[object Object],[object Object]

More Related Content

What's hot

Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Pedram Danesh-Mand
 
Project control
Project controlProject control
Project control
monisha pattnaik
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
Krishna Murthy RVN
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11PMA Consultants
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
Amit Kumar Senapati, PMP®
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
Michael Pink
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
McLachlan Lister Pty Limited
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
The Vertex Companies, LLC
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
ignitetribes
 
Interview questions-for-planning-engineers
Interview questions-for-planning-engineersInterview questions-for-planning-engineers
Interview questions-for-planning-engineers
workbreakdown
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
Glen Alleman
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Project Control
Project ControlProject Control
Project Control
Martin Sillaots
 

What's hot (20)

Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
 
Project control
Project controlProject control
Project control
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Interview questions-for-planning-engineers
Interview questions-for-planning-engineersInterview questions-for-planning-engineers
Interview questions-for-planning-engineers
 
Schedule-Delay Analysis
Schedule-Delay AnalysisSchedule-Delay Analysis
Schedule-Delay Analysis
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Project Control
Project ControlProject Control
Project Control
 

Similar to Integrated Master Schedule

Project management
Project managementProject management
Project management
ervinod
 
1.01 Introduction from DMRC side for project management information system
1.01 Introduction from DMRC side for project management information system1.01 Introduction from DMRC side for project management information system
1.01 Introduction from DMRC side for project management information system
RinkuMandal7
 
Alexander Joy Cartwright Iv Cpa V4
Alexander  Joy Cartwright Iv Cpa V4Alexander  Joy Cartwright Iv Cpa V4
Alexander Joy Cartwright Iv Cpa V4mrbaseball
 
Sorge.les
Sorge.lesSorge.les
Sorge.lesNASAPMC
 
Cloud pmo beta (17)
Cloud pmo beta (17)Cloud pmo beta (17)
Cloud pmo beta (17)
Synapse Information Ltd
 
Capex opex
Capex opexCapex opex
Capex opex
Raju_p1
 
Oracle Primavera contractor
Oracle Primavera  contractorOracle Primavera  contractor
Advanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial ProjectsAdvanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial Projects
Jeremie Averous
 
Scrum With Ms Project
Scrum With Ms ProjectScrum With Ms Project
Scrum With Ms Project
bobby
 
As-built Programmes - Part 2
As-built Programmes - Part 2As-built Programmes - Part 2
As-built Programmes - Part 2
David Greig
 
Dynamics 365 Bid Management for Construction Projects
Dynamics 365 Bid Management for Construction ProjectsDynamics 365 Bid Management for Construction Projects
Dynamics 365 Bid Management for Construction Projects
Dynamic Netsoft
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
Glen Alleman
 
Project accounting an introduction
Project accounting an introductionProject accounting an introduction
Project accounting an introduction
Ismail Hamzah
 
Cadison project-engineer
Cadison project-engineerCadison project-engineer
Cadison project-engineerCADISON
 
Cadison project-engineer
Cadison project-engineerCadison project-engineer
Cadison project-engineer
CADISON
 
Project Engineer
Project EngineerProject Engineer
Project Engineer
CADISON
 
Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015
Dr Ezzat Mansour
 
00 project control tools
00 project control tools00 project control tools
00 project control tools
AHMED NADIM JILANI
 

Similar to Integrated Master Schedule (20)

Project management
Project managementProject management
Project management
 
1.01 Introduction from DMRC side for project management information system
1.01 Introduction from DMRC side for project management information system1.01 Introduction from DMRC side for project management information system
1.01 Introduction from DMRC side for project management information system
 
Alexander Joy Cartwright Iv Cpa V4
Alexander  Joy Cartwright Iv Cpa V4Alexander  Joy Cartwright Iv Cpa V4
Alexander Joy Cartwright Iv Cpa V4
 
Sorge.les
Sorge.lesSorge.les
Sorge.les
 
Cloud pmo beta (17)
Cloud pmo beta (17)Cloud pmo beta (17)
Cloud pmo beta (17)
 
Capex opex
Capex opexCapex opex
Capex opex
 
Oracle Primavera contractor
Oracle Primavera  contractorOracle Primavera  contractor
Oracle Primavera contractor
 
Advanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial ProjectsAdvanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial Projects
 
EP Project Charter OpenWells2.3
EP Project Charter OpenWells2.3EP Project Charter OpenWells2.3
EP Project Charter OpenWells2.3
 
Scrum With Ms Project
Scrum With Ms ProjectScrum With Ms Project
Scrum With Ms Project
 
ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)
 
As-built Programmes - Part 2
As-built Programmes - Part 2As-built Programmes - Part 2
As-built Programmes - Part 2
 
Dynamics 365 Bid Management for Construction Projects
Dynamics 365 Bid Management for Construction ProjectsDynamics 365 Bid Management for Construction Projects
Dynamics 365 Bid Management for Construction Projects
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 
Project accounting an introduction
Project accounting an introductionProject accounting an introduction
Project accounting an introduction
 
Cadison project-engineer
Cadison project-engineerCadison project-engineer
Cadison project-engineer
 
Cadison project-engineer
Cadison project-engineerCadison project-engineer
Cadison project-engineer
 
Project Engineer
Project EngineerProject Engineer
Project Engineer
 
Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015
 
00 project control tools
00 project control tools00 project control tools
00 project control tools
 

Integrated Master Schedule

  • 1.
  • 2.
  • 3. IMS Collaboration Field Office Construction Contractor Customer PDT District PDT
  • 4.
  • 5.
  • 6.
  • 7. PD2 5 P2 System P2 System OP3 Oracle Projects Primavera Project Manager CEFMS SWG CEFMS SWF CEFMS SWT CEFMS SWL Primavision Update Project Update Budget OP to CEFMS transfer Transfer “CEFMS Actuals ” to OP Project Initiation Project Initiation OFA Reports Transfer “ OP Actuals ” to PPM Submit Budget - PPM to OP RMS CMI via PMBP Portal Staging Table CRMS CAPCES DD1391 Processor Number Project Initiation Form From PMgr myPrimavera SWT RMS SWF RMS SPK RMS QCS ftps Contractor ’ s Schedule Pay Activities with $ & SDEF Coding SDEF
  • 8. Access to QCS Download & User Guides http://www.rmssupport.com
  • 9. User Guides for QCS and SDEF
  • 11. Contractor’s Schedule Consolidation for IMS Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Contractor’s Schedule Customer IMS SDEF Activity Codes Activity ID Nomenclatures Resource Loaded IMS WBS IMS Activity Codes
  • 12.
  • 13.
  • 14. PD2/SPS/RMS/QCS Contract Detail Multiple Projects & Contracts (Ready for Invoice Processing) 0001 $$$$$$ 0002 $$$$$$ 0003 $$$$$$ 0001 $$$$$$ 0002 $$$$$$ 0001 $$$$$$ 0002 $$$$$$ 0003 $$$$$$ 0001 $$$$$$$ 0002 $$$$$$$ 0001 $$$$$$ 0002 $$$$$$ RMS Balanced PD2/SPS CLINS (Contracting) RMS Balanced Project A: Pay Activity 8 Pay Activity 9 Pay Activity 12 Pay Activity 10 Pay Activity 11 Pay Activity 6 Pay Activity 7 Pay Activity 5 Pay Activity 3 Pay Activity 4 Pay Activity 1 Pay Activity 2 QCS-Contractor Schedule (Field Office) M2185575 FWI-6717GG Bldg 4 FA8903-06-D8520-0025 C.60000.61000.2 Contract-CONSTSVCS-C2 Bldg 4 M2185571 FWI-B74KGD Central Energy Plant FA8903-06-D8520-0025 C.60000.61000.1 Contract-CONSTSVCS-C1 CEP Project C: M2185572 FWI-740C4 Bldg 3 FA8903-06-D8520-0024 B.60000.61000.1 Contract-CONSTSVCS-B1 Bldg 3 Project B: M2185570 FWI-9638GD Bldg 2 FA8903-06-D8520-0023 A.60000.61000.2 Contract-CONSTSVCS-A2 Bldg 2 M2185569 FWI-6717CK Bldg1 FA8903-06-D8520-0022 A.60000.61000.1 Contract-CONSTSVCS-A1 Bldg 1 CEFMS-Funding (Program Analyst Contract Phase (Ph) & Title Linked to Multiple Contracts in RMS (RMS Coordinator) RMS Contract Post Award (RMS Coordinator) Primavera (PPM/P2) WBS Structure (SWF PMO) Project
  • 15. Customer’s Integrated Installation Primavera Schedule Portfolio Each segment of this schedule represents a separate contracting action from the same or different contractor. Project A Bldg 1 Project A Bldg 2 Project B Bldg 3 Project C CEP Project C Bldg 4
  • 16. PD2/SPS/RMS/QCS Contract Schedule & Pay App (ENG090 ) (Schedule & RMS Update) 0001 $$$$$$ 0002 $$$$$$ 0003 $$$$$$ 0001 $$$$$$ 0002 $$$$$$ 0001 $$$$$$ 0002 $$$$$$ 0003 $$$$$$ 0001 $$$$$$$ 0002 $$$$$$$ 0001 $$$$$$ 0002 $$$$$$ RMS Balanced PD2/SPS CLINS RMS Balanced Project A: Pay Activity 8 (5%) Pay Activity 9 Pay Activity 12 Pay Activity 10(15%) Pay Activity 11(10%) Pay Activity 6 (10%) Pay Activity 7 Pay Activity 5 Pay Activity 3 (20%) Pay Activity 4 Pay Activity 1 (50%) Pay Activity 2 QCS-Contractor Statused Schedule M2185575 FWI-6717GG Bldg 4 FA8903-06-D8520-0025 C.60000.61000.2 Contract-CONSTSVCS-C2 Bldg 4 M2185571 FWI-B74KGD Central Energy Plant FA8903-06-D8520-0025 C.60000.61000.1 Contract-CONSTSVCS-C1 CEP Project C: M2185572 FWI-740C4 Bldg 3 FA8903-06-D8520-0024 B.60000.61000.1 Contract-CONSTSVCS-B1 Bldg 3 Project B: M2185570 FWI-9638GD Bldg 2 FA8903-06-D8520-0023 A.60000.61000.2 Contract-CONSTSVCS-A2 Bldg 2 M2185569 FWI-6717CK Bldg1 FA8903-06-D8520-0022 A.60000.61000.1 Contract-CONSTSVCS-A1 Bldg 1 CEFMS-Funding Contract Phase (Ph) & Title Linked to One Contract in RMS RMS Contract Post Award Primavera (PPM/P2) WBS Structure Project
  • 17.
  • 18.
  • 19. Lackland AFB, San Antonio, TX ATC Site
  • 20.
  • 21.
  • 22. USACE Projects DFAC#1 In Process Completed ATC #1-Small Business (SB) Customer Utility Projects TBD TBD ATC #2-SB ATC #3 & 4 TBD TBD DFAC #2 Customer TBD TBD ATC #4 Customer TBD TBD ATC #3 ATC# 1&2, Customer Projects TBD TBD DFAC #1 Customer Demo Projects TBD TBD ATC #2-LB Customer Demolition & Utilities/Roads Completed Completed ATC #1-Large Business (LB) Dependent Project Awarded/Const RMS/QCS Design/RFP Development USACE Project
  • 23. Non-USACE Projects Demolish Bldg 9050 Completed Completed Renovate Carswell Ave ATC East Campus In-Progress Completed Upgrade Sewer Line ATC East Campus TBD TBD Upgrade COMM Duct Bank Demolish Bldg 6045-6048 Completed Completed Abate Bldg 6045-6048 Demolish Bldg 9050 Completed Completed Abate Bldg 9050 ATC#3 TBD Completed Demolish Bldg 6045-6048 New Road TBD TBD New Access Control Point ATC#1 In-Progress Completed Move Building 6359 ATC #1 Start Completed Completed Demolish Bldg 9050 Dependent Project Awarded/Const Design/RFP Customer Project
  • 24. Project Summary LACK/X1 MPX N/A Demolish Bldg 9050 LACK/X2 MPX N/A Renovate Carswell Ave LACK/X3 MSP 7 N/A Move Building 6359 LACK/X4 MSP 7 N/A Upgrade Sewer Line LACK/X9 MSP 7 N/A Abate Bldg 6045-6048 LACK/X8 MSP 7 N/A Abate Bldg 9050 LACK/X7 MSP 7 N/A Demolish Bldg 6045-6048 LACK/X6 MSP 7 N/A New Access Control Point LACK/X5 MSP 7 N/A Upgrade COMM Duct Bank Customer Project LACK/D2 TBD Not Completed DFAC #2 LACK/A4 TBD Not Completed ATC #4 LACK/A3 TBD Not Completed ATC #3 LACK/D1 TBD Not Completed DFAC #1 LACK/B2 TBD Not Completed ATC #2-SB LACK/A2 TBD Not Completed ATC #2-LB LACKB1 P3/PRX Not Completed ATC #1-Small Bus LACK/A1 P3/PRX Completed ATC #1-Large Bus Master Schedule Mapping Contractor’s Schedule Format QCS/RMS USACE Project
  • 25. All “Known Projects” Added to “Projects Group” LACK as Subprojects Convert MPX to P3, Copy to Group MPX LACK/X1 Demolish Bldg 9050 Convert MPX to P3, Copy to Group MPX LACK/X2 Renovate Carswell Ave XML 2007, Import P6 and Export as P3, Restore and Copy to Group MSP 7 LACK/X3 Move Building 6359 P3 Export Excel Template, Copy Paste to Template and Import to P3 file, Copy to Group Excel LACK/X4 Upgrade Sewer Line TBD MSP 7 LACK/X9 Abate Bldg 6045-6048 TBD MSP 7 LACK/X8 Abate Bldg 9050 TBD MSP 7 LACK/X7 Demolish Bldg 6045-6048 TBD MSP 7 LACK/X6 New Access Control Point TBD MSP 7 LACK/X5 Upgrade COMM Duct Bank Customer Project TBD TBD LACK/D2 DFAC #2 TBD TBD LACK/A4 ATC #4 TBD TBD LACK/A3 ATC #3 TBD TBD LACK/D1 DFAC #1 TBD TBD LACK/B2 ATC #2-SB TBD TBD LACK/A2 ATC #2-LB Restore PRX, Copy to Group P3/PRX LACKB1 ATC #1-Small Bus Restore PRX, Copy to Group P3/PRX LACK/A1 ATC #1-Large Bus P3 Conversion Instructions Current Contractor’s Schedule Format P3 Master Schedule Mapping USACE Project
  • 26.
  • 27. Summary Conversion Table Export from PPM to P3, Copy new project to IMS Project Group Import .XER new project under Group EPS v 6.2.1 or later .XER (P6v6.2.1+) Export blank XLS from new Project created in IMS P3.1, Copy paste content of original XLS to new XLS, Import new Excel file into IMS P3.1 Export blank XLS from new Project created in IMS P6.2.1, Copy paste content of original XLS to new XLS, Import new Excel file into IMS P6.2.1 .xls (Excel) Convert file to XLS per convertor file from MS website, Export blank XLS from new Project created in IMS P3.1, Copy paste content of original XLS to new XLS, Import new Excel file into IMS P3.1 Convert file to XLS per convertor file from MS website, Export blank XLS from new Project created in IMS P6.2.1, Copy paste content of original XLS to new XLS, Import new Excel file into IMS P6.2.1 .xlsx (Excel 2007) Import .XER into v6.2.1, Export to P3, Copy new project to IMS Project Group (assign 2 chs Sub project ID) Import .XER new project under Group EPS v 6.2.1 .XER (P6v6.2.1) Export from PPM to P3, Copy new project to IMS Project Group Import .XER new project under Group EPS v 6.1 .XER (P6v6.1) Export from PPM to P3, Copy new project to IMS Project Group Import .XER new project under Group EPS v 6.0 .XER (P6) Export from PPM to P3, Copy new project to IMS Project Group Import .XER new project under Group EPS v 5.0 .XER (P5) Restore PRX to P3, restored P3 project copied to IMS Project Group (assign 2 chs Sub project ID) Restore PRX to P3, Import P3 project to P6.2.1 EPS as a new project under Group EPS PRX (P3) Import XML 2007 to P6.2.1, Export new project as P3, Restore to P3 and copied to IMS Project Group Import XML 2007 to new project in EPS XML 2007 (MSP) Import XML 2002/3 to P6.2.1, Export new project as P3, Restore to P3 and copied to IMS Project Group Import XML 2002/3 to new project in EPS XML 2002/2003 (MSP) Tools, MPX to P3, P3 project copied to IMS Project Group Import MPX as new project in EPS MPX (MSP) TO: P3.1 TO: P6.2.1 FROM File Format
  • 28.
  • 29.
  • 30. Customer’s Integrated Master Primavera Schedule Each segment of this schedule represents a separate contracting action or P2 Project from the same or different contractor. Demolition ATC#1 ATC#2 DFAC#1 ATC #3
  • 31.
  • 32. Q & A
  • 33.

Editor's Notes

  1. Read through this list of the various P2 components that are interfaced or need to be kept synchronized via the established process understand that A
  2. Within RMS, each contract phase now has a specific set of CLINS associated with a specific “contract phase”.
  3. Within RMS, each contract phase now has a specific set of CLINS associated with a specific “contract phase”.