International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1811
Risk Management in Railway Projects
Mrunal Patil1, Prof.R.D.Shinde2, Prof.S.S.Hailkar3
1PG Student at RMDSSOE, Warje, Pune,
2Professor & HOD of Civil at RMDSSOE, Warje, Pune,
3Professor at SCOE, Wadgaon, Pune.
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract -Risk management is an important concept that
mainly aims at identifying, quantifying, mitigating and
reviewing of events that may have an adverse impact on the
organization. There is a strong link between the amount of
risk management undertaken in a project and the level of
success of the project. Properriskmanagementimpliescontrol
of possible future events and thus it is a measure of security to
the contractors who take up the projects and to the owners of
the projects. In this study the various aspects of railway
projects were investigated. Data reliability was established
and according to Weighted average analysis and Relative
importance index analysis results.
Key Words: Risk Management, Relative Importance
Index, Weighted Average Index Method, Railway
Projects.
1.INTRODUCTION
Railways are treated as an economic, efficient,
environmentally friendly and very safe mode of transport.
Also India’s biggest department is Railway Department i.e.
Indian Railway, which is having special and separate
financial budget in Indian polity i.e. Railway Budget. So it is
obvious that the occurrence of risks in Railway projects are
more. So it is necessary to do risk management in Railway
Projects.
Risk management may be described as “a specific
process of looking at areas of risk and consciously
determining how each should be treated. It isa management
tool that aims at identifying sources of risk and uncertainty,
determining their impact, and developing appropriate
management responses”. A systematic process of risk
management has been divided into risk classification, risk
identification, risk analysis and risk response, where risk
response has been further divided into four actions, i.e.
retention, reduction, transfer and avoidance [4]. Railway
projects are inherently complex and dynamic, and involving
multiple feedback processes. A lot of participants –
individuals and organisations are actively involved in the
railway project, and they interests may be positively or
negatively affected as a result of the project execution or
project completion. Different competitor with different
experience and skills usuallyhavedifferent expectationsand
interests. Which simply creates problems and confusion for
even the most experienced project managers and
contractors. Every Project ManagementInstituteknowledge
area in itself contains some or all of the project management
processes. For example, project risk management includes:
 Risk management planning;
 Risk identification;
 Qualitative risk analysis;
 Quantitative risk analysis;
 Risk response planning;
 Risk monitoring and control.
Hence comes the requirement to define, identify,
quantify and mitigate the risks in railway projects in India.
2. RESEARCHMETHODOLOGY&DATACOLLECTION
The data collected to determine the mostinfluential
factors on project management of the railway project was
done through a survey by explorative questionnaire to the
respondents involved in daily activities of construction and
design firms, railway department in various regionsofIndia.
The survey was calculated so that respondents can give the
rank to their responses based on their ideas. The analysis of
these data was done by a methodnamedrelativeimportance
index (RII) method as well as weighted average method
(WAM).
Present study tries to work out ranking of Risk
Factors in railway projects along with ranking of frequency
and impact of these Risks. Further this work includes the
ranking of various preventiveandremedial methodsusedby
railway ministry for Risk resolution. The survey
questionnaire was designed to get the ranking of above
issues by suitable technique. The risk factors are given in
appendix. The survey questionnaire is made up of 15 basic
and theoretical risk factors as studied in various research
papers and by observation.
Respondents have to give ranking under the
category for
Less Important (1),
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1812
Relevant (2),
Essential (3),
Important (4),
Most Important (5).
1.1 Questionnaire Survey
Detailed questionnaire was distributed to many of
Designing & Survey firms, construction firms who are
working for railways only and government railway
department. Total 150 questionnaire was distributed out of
which 80 replies received.
1.2 Data Collection
The target population included design&surveyfirmsand
construction firms who are working for Railway project and
railwaydepartment.Thedesignandsurveyconsultanciesand
the execution firms who work for railways and the
government railway department were targeted for survey.
The facts of several shareholders and total numbers of were
collected through internet. These facts were considered as
size of population to decide sample size of study.
In this studyaround150Questionnairesweredistributed,
out of which80 questionnairesreceived.Theanalysisofthese
surveys helped meto computetheRelativeImportanceIndex
and Important index of each clause. The present study is
going to receive responses from a pretty diverse group of
professionals i.e. owners, contractors, consultants, etc.
Below given formula was used to determine the sample
size of unlimited population (Creative Research Systems,
2001):
SS = [Z2 × P × (1-P)] / C2
Where,
SS = Sample Size.
Z = Z Value (e.g. 1.96 for 95% confidence interval).
P = Percentage picking a choice, expressed as decimal, (0.50
used for sample size needed).
C = Confidence interval (0.1)
POP is the Population
Correction for finite population:
SSnew =
A. Relative Importance Index Technique:
This technique is used to determine the relative importance
of the various causes and effects of delays. The method is
adopted in this study within various groups (i.e. project
engineers, proprietor and site supervisor, designers,
surveyors). The four-point scale ranged from 1 (very little
degree affect) to 5 (very high degree affect) is adopted and
transformed to relative importance indices (RII) for each
factor as follows:
RII = ΣW / (A*N)
Where,
W is the weighting given to each factor by the respondents
(ranging from 1 to 4),
A is the highest weight (i.e. 5 in this case), and
N is the total number of respondents.
Higher the value of RII, more important was the reason of
delays.
B. WEIGHTED AVERAGE METHOD:
Data of all these table were analyzed by a weighted
average was calculated for each type of claims as follows:
Weighted Average Index = (Wi* Xi) / N;
Where
Wi is the weight assigned to the ith option;
Xi is the number of respondents who selected the ith option;
and
N is the total number of respondents (80 in this study).
2. RESULTS AND DISCUSSION
Sample Size Calculation
The formula given below is used forthe calculationofsample
size.
SS = [Z2 × P × (1-P)] / C2
Where,
SS = Sample Size.
Z = Z Value (e.g. 1.96 for 95% confidence interval).
P = Percentage picking a choice, expressed as decimal, (0.50
used for sample size needed).
C = Confidence interval (0.1)
POP is the Population = 146
The Ministry of Railways has transferred 146 projects to
Rail VikasNigam Ltd (RVNL)forexecution,so that is whythe
population size is taken as 146.
SS = [1.962 × 0.5 × (1- 0.5)] /0 .12
= 96.04
Correction for finite population:
SS new =
= 58.172
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1813
Here, in this case total 80 replies are there,whichisprovento
be good for present study.
3. COMPARISON OF RII & WAM
Risk Factor
RII
Ind
i
RII
Overal
l
WA
M
Indi
WAM
Overal
l
1 FINANCIAL RISK
1.1
Delayed
payments on
contract 1
5
1
5
1.2
Unmanaged cash
flow 2 2
1.3 Inflation 4 4
1.4
Financial failure
of the contractor 3 3
1.5
Construction cost
overruns 6 6
1.6
Labor and
Material Costs
(Contract,
Outsourced) 5 5
1.7
Interest Rate
Changes (Credit
and Interest Rate
Risks) 7 7
2 DESIGN RISK
2.1
Defective design
(incorrect) 1
3
1
3
2.2 Design Changes 2 2
2.3
Awarding the
design to
inexperience
Designer 3 3
3 POLITICAL RISK
3.1
New
governmental
acts or
legislations 1
14
1
14
4 LEGAL RISK
4.1
Ambiguity of
work legislations 3 11 3 10
4.2 Difficulty to get
2 2
permits
4.3
Disputes among
the parties of
contract 1 1
5
MANAGEMENT
RISK
5.1
Poor
communication
between involved
Parties 3
7
3
6
5.2
Improper
planning 4 4
5.3
Changes in
management
ways 5 5
5.4
Resource
management 1 1
5.5
Management of
Contracts & Joint
Ventures 2 2
6 MATERIAL RISK
6.1
Material not
conforming to the
specification 1 2 1 1
6.2
Availability of
material 2 2
7 SITE SAFETY
7.1
Occurrence of
accidents
because of poor
safety procedures
2
6
2
8
7.2 Labor safety 1 1
7.3
Security of
material and
equipment 3 3
7.4
Varied labour
and equipment
productivity 4 4
8 SITE RISK
8.1
Improper site
investigation 3
1
3
2
8.2 Land use and
acquisition/
1 1
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1814
resettlement and
rehabilitation
risk
8.3
Poor
communications
between the site
and head offices
(contractor side) 2 2
9
ENVIRONMENTA
L
9.1
Adverse weather
conditions 2
13
2
12
9.2
Difficulty to
access the site
(very far) 3 3
9.3
Environmental
factors (floods,
earthquakes, etc.) 1 1
9.4
Environmental
norms 4 4
9.5
Weather
Volatility
(Seasonality,
Catastrophes
(Cat) Risk 5 5
10 CULTURAL
10.1 Religion 1
15
1
15
10.2 Cultural custom 2 2
11 CONSTRUCTION
11.1
Gaps between the
Implementation
and the
specifications due
to
misunderstandin
g of drawings and
specifications 1
10
1
9
11.2
Actual quantities
differ from the
contract
Quantities 3 8
11.3
Lower work
quality in
presence of time
Constraints 4 3
11.4 Undocumented 10 10
change orders
11.5
Expired
temporary
construction
permits 11 11
11.6
Contradictions in
the construction
document 5 4
11.7
High competition
in bids 6 5
11.8
Quality Control
and Time
Management 7 6
11.9
Supplier
provisioning risk 8 7
11.1
0
Operations
failure Risk 9 9
11.1
1
Construction
Defects 2 2
12 EXTERNAL RISKS
12.1
New
stakeholders
emerge and
request changes 4
12
4
11
12.2 Public objections 2 2
12.3
Laws and local
standards change 6 6
12.4 Tax change 3 3
12.5
Major
dependence on
one client 1 1
12.6 Reputation Risk 5 5
13
ORGANIZATIONA
L RISKS
13.1
Inexperienced
workforce and
staff turnover 3
8
3
7
13.2
Delayed
deliveries 1 1
13.3
Lack of
protection on a
construction site 2 2
14
CONTRACTUAL
RISK &
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1815
EXPOSURES
14.1
Contractual
Liability (Breach,
Third Party
Action) 3
4
3
414.2
Liquidated,
Consequential
and Punitive
Damages Clauses 4 4
14.3
Force Majeure
Clauses
(Schedule Delay) 2 2
14.4
Subcontractor
Default,
Abandonment 1 1
15
HUMAN
RESOURCE RISK
15.1
Inadequate
succession
planning 1
9
1
13
15.2
Inability to
attract quality
personnel 3 3
15.3
Manpower Risks-
Specialized
manpower
leaving the jobs 2 2
Here the results gotfrom boththemethodareapproximately
same, which proves that ranking given by respondents are
right and data is correct.
4. RISK MITIGATION MEASURES
1. Site Risk
The risk associated with the land acquisition can be
mitigated with the project starting only afterall therequired
land is procured and handed over by the government. Also
by sending pre notice to the land owner for the acquisition,
so that acquisition process can easily be done. For proper
site investigation, the Daily Project Report (DPR) system
should be installed properly, and the format of DPR should
contain site photographs, daily material consumption, daily
manpower used, and amount of work done etc.
2. Material Risk
Material risk is one of the major risk found in not
only the railway projects but also other construction
projects. To achieve such a risk the engineers of railway
department should first aware about the purchasing of the
materials, the dealers of the material should be approved by
ISO certification. Also they should provide the quality
certificate for each materials, like ballast, sleepers, rails etc.
which are majorly used in laying of railway line.
Again, the department shouldhavemultipleoptions
i.e. multiple number of dealers of the materials.Sothatif one
fails due to deliver the requiredmaterial ontime,othercould
deliver that particular item on site on time, to avoid risk
associated with delay.
3. Design Risk
As the major time required for the completion in
railway project is Design and survey phase, Perfect design is
must necessary in railway projects, as millions of kg of load
is going to transfer on that particular way.
So railway department spends more time for
preparation of design and survey reports. Here in this case
the tender wining firm, who is preparing the design and
survey reports of this project have six month to complete
whole reports which includes GADs (General arrangements
of sheet), Hydrology of every major and minor bridge,
Railway curves, Track details with varying chain age.
So it can be mitigated by ensuring good design
report and vetted by owner and consultant before the
project commences. And also byhiringexperiencesurveyors
and designers or giving proper training to the fresher
employee under the guidance of experts such a risk can be
mitigated.
Also by providing Defect liability clause in contract
it can be done. [7]
4. Contractual risk & Exposures
The contractual Liability types of risk found very
serious effect on project, here in this case for design phase
one private consultancy firm failedtocarrythewholesurvey
of particular route, so breach of contract happens, to
complete such an incomplete work, railway ministry has to
out again another tender, and after all the tediousprocedure
of tendering some another consultancy firm will take the
responsibility to completetheremainingwork,whichcauses
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1816
lots of miss interpretation and tedious work. To mitigate
such a risk the ministry of railway should be strictly aware
on breaching of contract initially in tendering process.
5. Financial Risk
After identifying the risk involved in a Railway
project, it is very important to look at the techniques for
analyzing project cash flow, which is a major function of risk
management process. [8]
Unmanaged cash flow
The basic cash flow management technique says
that, in first two phase and last two phaseoftheconstruction
phase, the expenditure of the projectshouldbe8%to10% of
the total expenditure and in remaining duration, it varies
with increasing in starting, highest in middle anddecreasing
in ending, which follows a “bell curve”.
6. Site Safety
Such a risk found to be a very common in not only
the railway projects but also in every construction
industries. And the measures to mitigate such a risk is also
very common like wearing safety equipment like helmets,
hand glows, boots, goggles etc. most of the government
enterprises and private firms do not follow sucha measures,
which they should be aware of.
Apart from this, many acts are there for the welfare
of labors for example
 The Workmen’s compensation act, 1923
 The Employees Compensation act, 1923
 The Trade Unions Act, 1926
 The Payment of Wages Act, 1936
 The Employers Liability Act, 1938 and
many more.
7. Management Risk
Management risk are found to be very important
risk in such a projects who are dealing with public
enterprises. Here railway ministry outs the tender to the
private entities, and private entities work in their comfort
according to available resources. Sometimes resources are
not available on time so to mitigate such a risk they should
have alternate options of dealers available, so that project
should not stop due to unavailability of resources.
8. Organizational Risks
Again, in this case study such a kind of risk happens
in private consultancies who are going to work for Railway
Ministry, the subcontracted items and other design reports
like GADs, Hydrological reports etc. could not reach on time
to the head office or respective site locations, which aims to
delay in getting permits and delay in execution of work as
well. So to overcome such a risk the private consultancies
should manage proper transportation systems.
Also, the materials stored on site should be
protected well against rain, wind and other unnecessary
things like thief, wasting etc.
9. HUMAN RESOURCE RISK
Here, such a risks again happens majorly with
private consultancies, due to some trained employees
working on such big projects leaves the jobs, so the
companies have to hire some other newemployeesandhave
to train them first, which consumes too much time which
indirectly effects the project delay.
10. CONSTRUCTION
Such a risks aremorecommonineveryconstruction
industries, generally such a risk happens at the time of
execution phase of the projects. The specification given in
the drawings and design reports aregettingdifferatsite, due
to misunderstanding. To resolve sucha risk thesiteengineer
should first discuss whole the plan with senior engineer.
Also the execution process should be doneproperly
as millions of kg of weight is going to transfer on that route.
Modern equipment should be utilized bythegovernment for
easy and quality construction instead of ethic traditional
methods.
11. Legal Risk
Many of government agencies/civicbodiesetc.that
are affected in one or other by the development of this
Railway line, had to grant various approvals for the project,
which is going to be a complex and time consuming process
during the construction period. So, the government should
provide a single window clearance for a project of this
magnitude. [8]
12. EXTERNAL RISKS
Major dependence on one client
Here in this case study, it is found that due to
uneconomical site conditions and lack of site data available,
the government employees are providingincorrectrowdata
required for the design, which aims to repetition of work
again and again, so the government forced to consultancies
to work over there, in their site location for designing also.
Which aims to unnecessary comfort and unnecessary extra
expenditures like printing of drawing, design reports
establishment of new set ups etc.
So it is found that private consultancies who work
for such a government body should establish their office on
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1817
every particular site locations to overcome such an
unnecessary cost and comfort.
New stakeholders emerge and request changes
Unsupportive stakeholders & loggerhead between
shareholders are the major source of such a risks.Whichcan
be mitigated by working closelywiththemajorstakeholders
and by knowing their aspirations.
13. ENVIRONMENTAL
It is found that such a risk are not affecting majorly
on projects, because railway ministryarecarrying thedesign
phase in rainy seasons and execution phase in non-rainy
seasons.
But to reducethepollutioncreating bythe execution
work, the ministry and other contractors should follow the
environmental acts.
14. POLITICAL RISK
New governmental acts or legislations
15. CULTURAL
Political and cultural risk are the risk that
civil/political problems may surface as a result of project,
manifesting in boycotts, sabotage etc. such a disturbance
may arrive from a number of different concerns, public
objection to imposition of tariff public discontent with the
environmental impact of civil work or other features of the
project an event similar to any of above could impair the
capability of concessionaire to collect revenue thereby
affecting project viability.
Thus, the project should be designed that provides
adequate cover against these risk.[8]
5.CONCLUSION
Present study finds that which risk is having first
Rank among all Risk factors.
According to above analysis of collected data it is
conclude that Site risks, Material risk are most important in
Railway projects.
According to preventive method analysis it is
concluded that generally risk is transferred to otherparty or
they refer previous and ongoing similar projects.
 Whenever project objectives are suffer
they
 closely coordinate with their
subcontractors,
 Increase manpower and
 Increase working hours.
REFERENCES
[1] Er.Amit Bijon Dutta,”Study of Risk Management In
Construction Projects”, International Journal of
Management, Volume 5
[2] S.M.H Mojtahedi,”ANon-ParametricStatistical Approach
for Analyzing Risk Factor Data in Risk Management
Process”, Journal of Applied Science, 2009
[3] Pejman Rezakhani,”Current state of existingprojectrisk
modelling and analysis methods withfocusonfuzzyrisk
assessment-Literature Review”, IGF-ESIS, 2012
[4] Jonathan K. Fabi,”A Study of Risk Management Practice
of Highway Projects in Nigeria”, JESD, Vol 6, 2015
[5] Ranking of “Risk Factors” and “Risk Management
Actions” Affecting Building Construction Projects in
Gujarat , Patel Kishan, Dr.Rajiv Bhatt,
Prof.J.J.Bhavsar,IJAERD, Volume 2, May 2015
[6] RII & IMPI:Effective Techniques for Finding Delay In
Construction Project, Mamata Rajgor, Chauhan Paresh,
Patel Dhruv, Panchal chirag, Bhavsar Dhrmesh,
Volume:03, Jan 2016
[7] Risk Management in Motorway PPP Projects:Empirical-
based Guidelines, ublin Institute of Technology
ARROW@DIT, Nunzia Carbonara, April 2014
[8] Risk Assessment of BOT Road Projects, Engineer Rinaj
Pathan & Prof.Dr.S.S.Pimplikar, IOSR Journal of
Mechnical and Civil Engineering(IOSR-JMCE),Volume5,
Issue 3, Jan-Feb 2013
[9] Risk Analysis of Infrastructure Projects under Public
Private Partnerships, M.A.Ravindhar Raja, IJCIET, Vol:6,
June 2015
[10] Safety Risk Analsis and Proposing Risk Mitigation
Straregies for Operations and Maintenance Activities in
Highways: A Qualitative Methods, Sayanti
MUKHOPADHYAY, Jennifer S.SHANE, PhD, and Kelly C.
STRONG, ASCE 2012
[11] Qualitative Risk Assessment and Mitigation Measures
For Real Estate Projects In Maharashtra, Sneha
Khedekar, Dr.A.W.Dhawal, IJTRA, Volume 3, July Aug
2015
[12] Risk Assessment: A Case Study for Transportation
Projects in India, T.H. Nguyen, G.Bhagavatulya and
F.Jacob, Volume 3, Issue 9, September 2014
[13] Identifying and Evaluating Risk of Construction Projects
in Fuzzy Environment: A case Study in Iranian
Construction Industry, Sotoodeh Gohar, M.Khanzadi,
Maryam Farmani, IJST, Vol:5, Nov 2012
[14] Project Risk Identifucation Methods for Construction
Planning and Execution, Robert G.Batson, M.ASCE,2012
[15] Integrating Risk Assessment in Planning forSustainable
for InfrastructureProjects,MohamedF.DiabMBA,Ph.D.,
A.M.ASCE, 2013
[16] Risk Assessment in Construction of Highway Project,
Ankit Vishwakarma, IJERT, Volume:5, Feb 2016
[17] 13th Annual Report 2015-16, RVNL (Rail Vikas Nigam
Limited)

More Related Content

Similar to Risk Management in Railway Projects

Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsIRJET Journal
 
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...IRJET Journal
 
IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk AnalysisIRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk AnalysisIRJET Journal
 
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET Journal
 
Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsIRJET Journal
 
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET Journal
 
IRJET- Development of Conceptual Model for Effective Selection of Subcontract...
IRJET- Development of Conceptual Model for Effective Selection of Subcontract...IRJET- Development of Conceptual Model for Effective Selection of Subcontract...
IRJET- Development of Conceptual Model for Effective Selection of Subcontract...IRJET Journal
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET Journal
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET Journal
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET Journal
 
Risk Mitigation Design of Supply Chain at Blacksmith Metal Craft Industry Cen...
Risk Mitigation Design of Supply Chain at Blacksmith Metal Craft Industry Cen...Risk Mitigation Design of Supply Chain at Blacksmith Metal Craft Industry Cen...
Risk Mitigation Design of Supply Chain at Blacksmith Metal Craft Industry Cen...IRJET Journal
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSIRJET Journal
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSIRJET Journal
 
IRJET- Assessment of Role of Material Management in Construction Projects
IRJET- 	  Assessment of Role of Material Management in Construction ProjectsIRJET- 	  Assessment of Role of Material Management in Construction Projects
IRJET- Assessment of Role of Material Management in Construction ProjectsIRJET Journal
 
IRJET- Feasibility Study of Residential Building
IRJET- Feasibility Study of Residential BuildingIRJET- Feasibility Study of Residential Building
IRJET- Feasibility Study of Residential BuildingIRJET Journal
 
IRJET- Construction Equipment Monitoring: By using Relative Important Ind...
IRJET-  	  Construction Equipment Monitoring: By using Relative Important Ind...IRJET-  	  Construction Equipment Monitoring: By using Relative Important Ind...
IRJET- Construction Equipment Monitoring: By using Relative Important Ind...IRJET Journal
 
Risk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectRisk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectIRJET Journal
 
ASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTS
ASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTSASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTS
ASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTSIAEME Publication
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential SectorIRJET Journal
 

Similar to Risk Management in Railway Projects (20)

Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction Projects
 
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
 
IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk AnalysisIRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
 
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
 
Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction Projects
 
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
 
IRJET- Development of Conceptual Model for Effective Selection of Subcontract...
IRJET- Development of Conceptual Model for Effective Selection of Subcontract...IRJET- Development of Conceptual Model for Effective Selection of Subcontract...
IRJET- Development of Conceptual Model for Effective Selection of Subcontract...
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction Projects
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
 
Risk Mitigation Design of Supply Chain at Blacksmith Metal Craft Industry Cen...
Risk Mitigation Design of Supply Chain at Blacksmith Metal Craft Industry Cen...Risk Mitigation Design of Supply Chain at Blacksmith Metal Craft Industry Cen...
Risk Mitigation Design of Supply Chain at Blacksmith Metal Craft Industry Cen...
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
IRJET- Assessment of Role of Material Management in Construction Projects
IRJET- 	  Assessment of Role of Material Management in Construction ProjectsIRJET- 	  Assessment of Role of Material Management in Construction Projects
IRJET- Assessment of Role of Material Management in Construction Projects
 
IRJET- Feasibility Study of Residential Building
IRJET- Feasibility Study of Residential BuildingIRJET- Feasibility Study of Residential Building
IRJET- Feasibility Study of Residential Building
 
IRJET- Construction Equipment Monitoring: By using Relative Important Ind...
IRJET-  	  Construction Equipment Monitoring: By using Relative Important Ind...IRJET-  	  Construction Equipment Monitoring: By using Relative Important Ind...
IRJET- Construction Equipment Monitoring: By using Relative Important Ind...
 
Risk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectRisk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure project
 
ASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTS
ASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTSASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTS
ASSESEMENT ON FACTORS DECLINING LABOUR PRODUCTIVTY IN CONSTRUCTION PROJECTS
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential Sector
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxMustafa Ahmed
 
ALCOHOL PRODUCTION- Beer Brewing Process.pdf
ALCOHOL PRODUCTION- Beer Brewing Process.pdfALCOHOL PRODUCTION- Beer Brewing Process.pdf
ALCOHOL PRODUCTION- Beer Brewing Process.pdfMadan Karki
 
Online crime reporting system project.pdf
Online crime reporting system project.pdfOnline crime reporting system project.pdf
Online crime reporting system project.pdfKamal Acharya
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docxrahulmanepalli02
 
Diploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdfDiploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdfJNTUA
 
electrical installation and maintenance.
electrical installation and maintenance.electrical installation and maintenance.
electrical installation and maintenance.benjamincojr
 
Dynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxDynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxMustafa Ahmed
 
Introduction to Arduino Programming: Features of Arduino
Introduction to Arduino Programming: Features of ArduinoIntroduction to Arduino Programming: Features of Arduino
Introduction to Arduino Programming: Features of ArduinoAbhimanyu Sangale
 
analog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptxanalog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptxKarpagam Institute of Teechnology
 
SLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptxSLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptxCHAIRMAN M
 
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...Roi Lipman
 
Developing a smart system for infant incubators using the internet of things ...
Developing a smart system for infant incubators using the internet of things ...Developing a smart system for infant incubators using the internet of things ...
Developing a smart system for infant incubators using the internet of things ...IJECEIAES
 
Piping and instrumentation diagram p.pdf
Piping and instrumentation diagram p.pdfPiping and instrumentation diagram p.pdf
Piping and instrumentation diagram p.pdfAshrafRagab14
 
Autodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxAutodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxMustafa Ahmed
 
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...drjose256
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...josephjonse
 
Electrical shop management system project report.pdf
Electrical shop management system project report.pdfElectrical shop management system project report.pdf
Electrical shop management system project report.pdfKamal Acharya
 
Linux Systems Programming: Semaphores, Shared Memory, and Message Queues
Linux Systems Programming: Semaphores, Shared Memory, and Message QueuesLinux Systems Programming: Semaphores, Shared Memory, and Message Queues
Linux Systems Programming: Semaphores, Shared Memory, and Message QueuesRashidFaridChishti
 
Microkernel in Operating System | Operating System
Microkernel in Operating System | Operating SystemMicrokernel in Operating System | Operating System
Microkernel in Operating System | Operating SystemSampad Kar
 
Seizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networksSeizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networksIJECEIAES
 

Recently uploaded (20)

Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
ALCOHOL PRODUCTION- Beer Brewing Process.pdf
ALCOHOL PRODUCTION- Beer Brewing Process.pdfALCOHOL PRODUCTION- Beer Brewing Process.pdf
ALCOHOL PRODUCTION- Beer Brewing Process.pdf
 
Online crime reporting system project.pdf
Online crime reporting system project.pdfOnline crime reporting system project.pdf
Online crime reporting system project.pdf
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx
 
Diploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdfDiploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdf
 
electrical installation and maintenance.
electrical installation and maintenance.electrical installation and maintenance.
electrical installation and maintenance.
 
Dynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxDynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptx
 
Introduction to Arduino Programming: Features of Arduino
Introduction to Arduino Programming: Features of ArduinoIntroduction to Arduino Programming: Features of Arduino
Introduction to Arduino Programming: Features of Arduino
 
analog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptxanalog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptx
 
SLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptxSLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptx
 
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
 
Developing a smart system for infant incubators using the internet of things ...
Developing a smart system for infant incubators using the internet of things ...Developing a smart system for infant incubators using the internet of things ...
Developing a smart system for infant incubators using the internet of things ...
 
Piping and instrumentation diagram p.pdf
Piping and instrumentation diagram p.pdfPiping and instrumentation diagram p.pdf
Piping and instrumentation diagram p.pdf
 
Autodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxAutodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptx
 
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Electrical shop management system project report.pdf
Electrical shop management system project report.pdfElectrical shop management system project report.pdf
Electrical shop management system project report.pdf
 
Linux Systems Programming: Semaphores, Shared Memory, and Message Queues
Linux Systems Programming: Semaphores, Shared Memory, and Message QueuesLinux Systems Programming: Semaphores, Shared Memory, and Message Queues
Linux Systems Programming: Semaphores, Shared Memory, and Message Queues
 
Microkernel in Operating System | Operating System
Microkernel in Operating System | Operating SystemMicrokernel in Operating System | Operating System
Microkernel in Operating System | Operating System
 
Seizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networksSeizure stage detection of epileptic seizure using convolutional neural networks
Seizure stage detection of epileptic seizure using convolutional neural networks
 

Risk Management in Railway Projects

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1811 Risk Management in Railway Projects Mrunal Patil1, Prof.R.D.Shinde2, Prof.S.S.Hailkar3 1PG Student at RMDSSOE, Warje, Pune, 2Professor & HOD of Civil at RMDSSOE, Warje, Pune, 3Professor at SCOE, Wadgaon, Pune. ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract -Risk management is an important concept that mainly aims at identifying, quantifying, mitigating and reviewing of events that may have an adverse impact on the organization. There is a strong link between the amount of risk management undertaken in a project and the level of success of the project. Properriskmanagementimpliescontrol of possible future events and thus it is a measure of security to the contractors who take up the projects and to the owners of the projects. In this study the various aspects of railway projects were investigated. Data reliability was established and according to Weighted average analysis and Relative importance index analysis results. Key Words: Risk Management, Relative Importance Index, Weighted Average Index Method, Railway Projects. 1.INTRODUCTION Railways are treated as an economic, efficient, environmentally friendly and very safe mode of transport. Also India’s biggest department is Railway Department i.e. Indian Railway, which is having special and separate financial budget in Indian polity i.e. Railway Budget. So it is obvious that the occurrence of risks in Railway projects are more. So it is necessary to do risk management in Railway Projects. Risk management may be described as “a specific process of looking at areas of risk and consciously determining how each should be treated. It isa management tool that aims at identifying sources of risk and uncertainty, determining their impact, and developing appropriate management responses”. A systematic process of risk management has been divided into risk classification, risk identification, risk analysis and risk response, where risk response has been further divided into four actions, i.e. retention, reduction, transfer and avoidance [4]. Railway projects are inherently complex and dynamic, and involving multiple feedback processes. A lot of participants – individuals and organisations are actively involved in the railway project, and they interests may be positively or negatively affected as a result of the project execution or project completion. Different competitor with different experience and skills usuallyhavedifferent expectationsand interests. Which simply creates problems and confusion for even the most experienced project managers and contractors. Every Project ManagementInstituteknowledge area in itself contains some or all of the project management processes. For example, project risk management includes:  Risk management planning;  Risk identification;  Qualitative risk analysis;  Quantitative risk analysis;  Risk response planning;  Risk monitoring and control. Hence comes the requirement to define, identify, quantify and mitigate the risks in railway projects in India. 2. RESEARCHMETHODOLOGY&DATACOLLECTION The data collected to determine the mostinfluential factors on project management of the railway project was done through a survey by explorative questionnaire to the respondents involved in daily activities of construction and design firms, railway department in various regionsofIndia. The survey was calculated so that respondents can give the rank to their responses based on their ideas. The analysis of these data was done by a methodnamedrelativeimportance index (RII) method as well as weighted average method (WAM). Present study tries to work out ranking of Risk Factors in railway projects along with ranking of frequency and impact of these Risks. Further this work includes the ranking of various preventiveandremedial methodsusedby railway ministry for Risk resolution. The survey questionnaire was designed to get the ranking of above issues by suitable technique. The risk factors are given in appendix. The survey questionnaire is made up of 15 basic and theoretical risk factors as studied in various research papers and by observation. Respondents have to give ranking under the category for Less Important (1),
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1812 Relevant (2), Essential (3), Important (4), Most Important (5). 1.1 Questionnaire Survey Detailed questionnaire was distributed to many of Designing & Survey firms, construction firms who are working for railways only and government railway department. Total 150 questionnaire was distributed out of which 80 replies received. 1.2 Data Collection The target population included design&surveyfirmsand construction firms who are working for Railway project and railwaydepartment.Thedesignandsurveyconsultanciesand the execution firms who work for railways and the government railway department were targeted for survey. The facts of several shareholders and total numbers of were collected through internet. These facts were considered as size of population to decide sample size of study. In this studyaround150Questionnairesweredistributed, out of which80 questionnairesreceived.Theanalysisofthese surveys helped meto computetheRelativeImportanceIndex and Important index of each clause. The present study is going to receive responses from a pretty diverse group of professionals i.e. owners, contractors, consultants, etc. Below given formula was used to determine the sample size of unlimited population (Creative Research Systems, 2001): SS = [Z2 × P × (1-P)] / C2 Where, SS = Sample Size. Z = Z Value (e.g. 1.96 for 95% confidence interval). P = Percentage picking a choice, expressed as decimal, (0.50 used for sample size needed). C = Confidence interval (0.1) POP is the Population Correction for finite population: SSnew = A. Relative Importance Index Technique: This technique is used to determine the relative importance of the various causes and effects of delays. The method is adopted in this study within various groups (i.e. project engineers, proprietor and site supervisor, designers, surveyors). The four-point scale ranged from 1 (very little degree affect) to 5 (very high degree affect) is adopted and transformed to relative importance indices (RII) for each factor as follows: RII = ΣW / (A*N) Where, W is the weighting given to each factor by the respondents (ranging from 1 to 4), A is the highest weight (i.e. 5 in this case), and N is the total number of respondents. Higher the value of RII, more important was the reason of delays. B. WEIGHTED AVERAGE METHOD: Data of all these table were analyzed by a weighted average was calculated for each type of claims as follows: Weighted Average Index = (Wi* Xi) / N; Where Wi is the weight assigned to the ith option; Xi is the number of respondents who selected the ith option; and N is the total number of respondents (80 in this study). 2. RESULTS AND DISCUSSION Sample Size Calculation The formula given below is used forthe calculationofsample size. SS = [Z2 × P × (1-P)] / C2 Where, SS = Sample Size. Z = Z Value (e.g. 1.96 for 95% confidence interval). P = Percentage picking a choice, expressed as decimal, (0.50 used for sample size needed). C = Confidence interval (0.1) POP is the Population = 146 The Ministry of Railways has transferred 146 projects to Rail VikasNigam Ltd (RVNL)forexecution,so that is whythe population size is taken as 146. SS = [1.962 × 0.5 × (1- 0.5)] /0 .12 = 96.04 Correction for finite population: SS new = = 58.172
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1813 Here, in this case total 80 replies are there,whichisprovento be good for present study. 3. COMPARISON OF RII & WAM Risk Factor RII Ind i RII Overal l WA M Indi WAM Overal l 1 FINANCIAL RISK 1.1 Delayed payments on contract 1 5 1 5 1.2 Unmanaged cash flow 2 2 1.3 Inflation 4 4 1.4 Financial failure of the contractor 3 3 1.5 Construction cost overruns 6 6 1.6 Labor and Material Costs (Contract, Outsourced) 5 5 1.7 Interest Rate Changes (Credit and Interest Rate Risks) 7 7 2 DESIGN RISK 2.1 Defective design (incorrect) 1 3 1 3 2.2 Design Changes 2 2 2.3 Awarding the design to inexperience Designer 3 3 3 POLITICAL RISK 3.1 New governmental acts or legislations 1 14 1 14 4 LEGAL RISK 4.1 Ambiguity of work legislations 3 11 3 10 4.2 Difficulty to get 2 2 permits 4.3 Disputes among the parties of contract 1 1 5 MANAGEMENT RISK 5.1 Poor communication between involved Parties 3 7 3 6 5.2 Improper planning 4 4 5.3 Changes in management ways 5 5 5.4 Resource management 1 1 5.5 Management of Contracts & Joint Ventures 2 2 6 MATERIAL RISK 6.1 Material not conforming to the specification 1 2 1 1 6.2 Availability of material 2 2 7 SITE SAFETY 7.1 Occurrence of accidents because of poor safety procedures 2 6 2 8 7.2 Labor safety 1 1 7.3 Security of material and equipment 3 3 7.4 Varied labour and equipment productivity 4 4 8 SITE RISK 8.1 Improper site investigation 3 1 3 2 8.2 Land use and acquisition/ 1 1
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1814 resettlement and rehabilitation risk 8.3 Poor communications between the site and head offices (contractor side) 2 2 9 ENVIRONMENTA L 9.1 Adverse weather conditions 2 13 2 12 9.2 Difficulty to access the site (very far) 3 3 9.3 Environmental factors (floods, earthquakes, etc.) 1 1 9.4 Environmental norms 4 4 9.5 Weather Volatility (Seasonality, Catastrophes (Cat) Risk 5 5 10 CULTURAL 10.1 Religion 1 15 1 15 10.2 Cultural custom 2 2 11 CONSTRUCTION 11.1 Gaps between the Implementation and the specifications due to misunderstandin g of drawings and specifications 1 10 1 9 11.2 Actual quantities differ from the contract Quantities 3 8 11.3 Lower work quality in presence of time Constraints 4 3 11.4 Undocumented 10 10 change orders 11.5 Expired temporary construction permits 11 11 11.6 Contradictions in the construction document 5 4 11.7 High competition in bids 6 5 11.8 Quality Control and Time Management 7 6 11.9 Supplier provisioning risk 8 7 11.1 0 Operations failure Risk 9 9 11.1 1 Construction Defects 2 2 12 EXTERNAL RISKS 12.1 New stakeholders emerge and request changes 4 12 4 11 12.2 Public objections 2 2 12.3 Laws and local standards change 6 6 12.4 Tax change 3 3 12.5 Major dependence on one client 1 1 12.6 Reputation Risk 5 5 13 ORGANIZATIONA L RISKS 13.1 Inexperienced workforce and staff turnover 3 8 3 7 13.2 Delayed deliveries 1 1 13.3 Lack of protection on a construction site 2 2 14 CONTRACTUAL RISK &
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1815 EXPOSURES 14.1 Contractual Liability (Breach, Third Party Action) 3 4 3 414.2 Liquidated, Consequential and Punitive Damages Clauses 4 4 14.3 Force Majeure Clauses (Schedule Delay) 2 2 14.4 Subcontractor Default, Abandonment 1 1 15 HUMAN RESOURCE RISK 15.1 Inadequate succession planning 1 9 1 13 15.2 Inability to attract quality personnel 3 3 15.3 Manpower Risks- Specialized manpower leaving the jobs 2 2 Here the results gotfrom boththemethodareapproximately same, which proves that ranking given by respondents are right and data is correct. 4. RISK MITIGATION MEASURES 1. Site Risk The risk associated with the land acquisition can be mitigated with the project starting only afterall therequired land is procured and handed over by the government. Also by sending pre notice to the land owner for the acquisition, so that acquisition process can easily be done. For proper site investigation, the Daily Project Report (DPR) system should be installed properly, and the format of DPR should contain site photographs, daily material consumption, daily manpower used, and amount of work done etc. 2. Material Risk Material risk is one of the major risk found in not only the railway projects but also other construction projects. To achieve such a risk the engineers of railway department should first aware about the purchasing of the materials, the dealers of the material should be approved by ISO certification. Also they should provide the quality certificate for each materials, like ballast, sleepers, rails etc. which are majorly used in laying of railway line. Again, the department shouldhavemultipleoptions i.e. multiple number of dealers of the materials.Sothatif one fails due to deliver the requiredmaterial ontime,othercould deliver that particular item on site on time, to avoid risk associated with delay. 3. Design Risk As the major time required for the completion in railway project is Design and survey phase, Perfect design is must necessary in railway projects, as millions of kg of load is going to transfer on that particular way. So railway department spends more time for preparation of design and survey reports. Here in this case the tender wining firm, who is preparing the design and survey reports of this project have six month to complete whole reports which includes GADs (General arrangements of sheet), Hydrology of every major and minor bridge, Railway curves, Track details with varying chain age. So it can be mitigated by ensuring good design report and vetted by owner and consultant before the project commences. And also byhiringexperiencesurveyors and designers or giving proper training to the fresher employee under the guidance of experts such a risk can be mitigated. Also by providing Defect liability clause in contract it can be done. [7] 4. Contractual risk & Exposures The contractual Liability types of risk found very serious effect on project, here in this case for design phase one private consultancy firm failedtocarrythewholesurvey of particular route, so breach of contract happens, to complete such an incomplete work, railway ministry has to out again another tender, and after all the tediousprocedure of tendering some another consultancy firm will take the responsibility to completetheremainingwork,whichcauses
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1816 lots of miss interpretation and tedious work. To mitigate such a risk the ministry of railway should be strictly aware on breaching of contract initially in tendering process. 5. Financial Risk After identifying the risk involved in a Railway project, it is very important to look at the techniques for analyzing project cash flow, which is a major function of risk management process. [8] Unmanaged cash flow The basic cash flow management technique says that, in first two phase and last two phaseoftheconstruction phase, the expenditure of the projectshouldbe8%to10% of the total expenditure and in remaining duration, it varies with increasing in starting, highest in middle anddecreasing in ending, which follows a “bell curve”. 6. Site Safety Such a risk found to be a very common in not only the railway projects but also in every construction industries. And the measures to mitigate such a risk is also very common like wearing safety equipment like helmets, hand glows, boots, goggles etc. most of the government enterprises and private firms do not follow sucha measures, which they should be aware of. Apart from this, many acts are there for the welfare of labors for example  The Workmen’s compensation act, 1923  The Employees Compensation act, 1923  The Trade Unions Act, 1926  The Payment of Wages Act, 1936  The Employers Liability Act, 1938 and many more. 7. Management Risk Management risk are found to be very important risk in such a projects who are dealing with public enterprises. Here railway ministry outs the tender to the private entities, and private entities work in their comfort according to available resources. Sometimes resources are not available on time so to mitigate such a risk they should have alternate options of dealers available, so that project should not stop due to unavailability of resources. 8. Organizational Risks Again, in this case study such a kind of risk happens in private consultancies who are going to work for Railway Ministry, the subcontracted items and other design reports like GADs, Hydrological reports etc. could not reach on time to the head office or respective site locations, which aims to delay in getting permits and delay in execution of work as well. So to overcome such a risk the private consultancies should manage proper transportation systems. Also, the materials stored on site should be protected well against rain, wind and other unnecessary things like thief, wasting etc. 9. HUMAN RESOURCE RISK Here, such a risks again happens majorly with private consultancies, due to some trained employees working on such big projects leaves the jobs, so the companies have to hire some other newemployeesandhave to train them first, which consumes too much time which indirectly effects the project delay. 10. CONSTRUCTION Such a risks aremorecommonineveryconstruction industries, generally such a risk happens at the time of execution phase of the projects. The specification given in the drawings and design reports aregettingdifferatsite, due to misunderstanding. To resolve sucha risk thesiteengineer should first discuss whole the plan with senior engineer. Also the execution process should be doneproperly as millions of kg of weight is going to transfer on that route. Modern equipment should be utilized bythegovernment for easy and quality construction instead of ethic traditional methods. 11. Legal Risk Many of government agencies/civicbodiesetc.that are affected in one or other by the development of this Railway line, had to grant various approvals for the project, which is going to be a complex and time consuming process during the construction period. So, the government should provide a single window clearance for a project of this magnitude. [8] 12. EXTERNAL RISKS Major dependence on one client Here in this case study, it is found that due to uneconomical site conditions and lack of site data available, the government employees are providingincorrectrowdata required for the design, which aims to repetition of work again and again, so the government forced to consultancies to work over there, in their site location for designing also. Which aims to unnecessary comfort and unnecessary extra expenditures like printing of drawing, design reports establishment of new set ups etc. So it is found that private consultancies who work for such a government body should establish their office on
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1817 every particular site locations to overcome such an unnecessary cost and comfort. New stakeholders emerge and request changes Unsupportive stakeholders & loggerhead between shareholders are the major source of such a risks.Whichcan be mitigated by working closelywiththemajorstakeholders and by knowing their aspirations. 13. ENVIRONMENTAL It is found that such a risk are not affecting majorly on projects, because railway ministryarecarrying thedesign phase in rainy seasons and execution phase in non-rainy seasons. But to reducethepollutioncreating bythe execution work, the ministry and other contractors should follow the environmental acts. 14. POLITICAL RISK New governmental acts or legislations 15. CULTURAL Political and cultural risk are the risk that civil/political problems may surface as a result of project, manifesting in boycotts, sabotage etc. such a disturbance may arrive from a number of different concerns, public objection to imposition of tariff public discontent with the environmental impact of civil work or other features of the project an event similar to any of above could impair the capability of concessionaire to collect revenue thereby affecting project viability. Thus, the project should be designed that provides adequate cover against these risk.[8] 5.CONCLUSION Present study finds that which risk is having first Rank among all Risk factors. According to above analysis of collected data it is conclude that Site risks, Material risk are most important in Railway projects. According to preventive method analysis it is concluded that generally risk is transferred to otherparty or they refer previous and ongoing similar projects.  Whenever project objectives are suffer they  closely coordinate with their subcontractors,  Increase manpower and  Increase working hours. REFERENCES [1] Er.Amit Bijon Dutta,”Study of Risk Management In Construction Projects”, International Journal of Management, Volume 5 [2] S.M.H Mojtahedi,”ANon-ParametricStatistical Approach for Analyzing Risk Factor Data in Risk Management Process”, Journal of Applied Science, 2009 [3] Pejman Rezakhani,”Current state of existingprojectrisk modelling and analysis methods withfocusonfuzzyrisk assessment-Literature Review”, IGF-ESIS, 2012 [4] Jonathan K. Fabi,”A Study of Risk Management Practice of Highway Projects in Nigeria”, JESD, Vol 6, 2015 [5] Ranking of “Risk Factors” and “Risk Management Actions” Affecting Building Construction Projects in Gujarat , Patel Kishan, Dr.Rajiv Bhatt, Prof.J.J.Bhavsar,IJAERD, Volume 2, May 2015 [6] RII & IMPI:Effective Techniques for Finding Delay In Construction Project, Mamata Rajgor, Chauhan Paresh, Patel Dhruv, Panchal chirag, Bhavsar Dhrmesh, Volume:03, Jan 2016 [7] Risk Management in Motorway PPP Projects:Empirical- based Guidelines, ublin Institute of Technology ARROW@DIT, Nunzia Carbonara, April 2014 [8] Risk Assessment of BOT Road Projects, Engineer Rinaj Pathan & Prof.Dr.S.S.Pimplikar, IOSR Journal of Mechnical and Civil Engineering(IOSR-JMCE),Volume5, Issue 3, Jan-Feb 2013 [9] Risk Analysis of Infrastructure Projects under Public Private Partnerships, M.A.Ravindhar Raja, IJCIET, Vol:6, June 2015 [10] Safety Risk Analsis and Proposing Risk Mitigation Straregies for Operations and Maintenance Activities in Highways: A Qualitative Methods, Sayanti MUKHOPADHYAY, Jennifer S.SHANE, PhD, and Kelly C. STRONG, ASCE 2012 [11] Qualitative Risk Assessment and Mitigation Measures For Real Estate Projects In Maharashtra, Sneha Khedekar, Dr.A.W.Dhawal, IJTRA, Volume 3, July Aug 2015 [12] Risk Assessment: A Case Study for Transportation Projects in India, T.H. Nguyen, G.Bhagavatulya and F.Jacob, Volume 3, Issue 9, September 2014 [13] Identifying and Evaluating Risk of Construction Projects in Fuzzy Environment: A case Study in Iranian Construction Industry, Sotoodeh Gohar, M.Khanzadi, Maryam Farmani, IJST, Vol:5, Nov 2012 [14] Project Risk Identifucation Methods for Construction Planning and Execution, Robert G.Batson, M.ASCE,2012 [15] Integrating Risk Assessment in Planning forSustainable for InfrastructureProjects,MohamedF.DiabMBA,Ph.D., A.M.ASCE, 2013 [16] Risk Assessment in Construction of Highway Project, Ankit Vishwakarma, IJERT, Volume:5, Feb 2016 [17] 13th Annual Report 2015-16, RVNL (Rail Vikas Nigam Limited)