International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2006
EFFECTIVENESS OF RISK MANAGEMENT AND CHOSEN METHODS IN
CONSTRUCTION SECTOR
Shivani More1, Tejas Hirlekar2
1,2 Undergraduate, Dept. of Civil Engineering, Datta Meghe College of Engineering, Airoli, Navi Mumbai, India
---------------------------------------------------------------------***-----------------------------------------------------------------------
Abstract: Risk analysis is the most important aspect for
the selection of any project and maintenance of co-
ordination in construction sector. In general risk is
basically the deviation from what is normal, the expected
level. Risk is indeed considered as a central part of
uncertainty, in which the probability occurrence and
amount of damage can be determined. Risk management
is area which requires tremendous emphasis and
comprehensive approach by the various aspects or
participants of the sector. With the growing economy the
construction industry in India has gained enormous
attention and poised for exceptional growth prospectives.
This paper puts forth an attempt to bring out the
importance of risk management and the analysis and risk
management processes that should be undertaken for the
improvement of the construction industry in the long-run.
Result analysis and a short survey made in this regard has
been included which gives an overview about the current
practices relevant in the construction industry. An efficient
and effective risk management approach requires a
systematic methodology including knowledge and
experience about the construction works. Analysing the
risk is often considered as analysing the adverse
consequences during the stage of planning and
programming of construction project. The risk
management analysis not only enhances the decision-
making process but also provides additional information
which helps to select the optimal aspects of the
construction project.
Keywords: Risk Analysis, Risk management,
Uncertainty, Systematic methodology, Adverse
consequences, Decision-making process, Optimal
aspects.
1) INTRODUCTION:
The phenomenon of risk is the most important subject of
discussion for both theorists and practitioners. However,
only a few fraction of them realize the adversity and
undertake these problems in order to formulate the
problematic situations within the procedural framework.
Presently the construction industry occupies such a
position which has considerably caused the increase in
employment generation. Amidst such an encouraging
situation, the industry is still in the phase of many
challenges which faces limitations in aspects like
construction material, financial resources, human
resources, construction methodologies. Due to the rapid
growth in the infrastructure of the project huge quantum
of various resources and the nature of the complexities
of project, the management of risk plays a vital role in
the construction sector. Risk management can be
considerably improved by improving the performance
and the knowledge of labours, machinery, money,
materials etc. which facilitates the entire construction
industry. This paper outlines the important areas of risk
management in the construction industry and aims at
presenting the three methods used for the analysis of
risk and simultaneously pointing their features and
characteristics by highlighting the degree of credibility of
the discussed problems. The presented methods involve
solved decision-making and the usage of the data by
taking into consideration common features as well as
specific individual features of each one of them. Risk
being considered as a measureable part of uncertainty is
most often considered as possibility of incurring heavy
losses. The scope and the number of problems associated
with risk management, taking into consideration the
realization of the project is enormous before we delve
into analysis of risk, we should find answers to the
required three questions. Risk management being a
considerably vast aspect, should therefore be segregated
into 3 general forms which are:
1) Risk Identification
2) Risk Assessment
3) Measuring and controlling the reaction of risk
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2007
Risk management in construction industry
According to various publications the popularity of the
methods to clearly identify risk is based on various
aspects like the degree and quality of the obtained
results, verifications and specifications used in the
project, degree of complexity of calculation, use oof
computer softwares. The mentioned methods are
illustrated and outlined at a same time, taking into
consideration their characteristic feature in terms of
their analysis.
Characteristics of the methods stated:
 Requirement of necessary flexible approach,
taking into consideration some additional factors
by keeping in mind the specific list of problems
and hazards for each project.
 Limited scope or approach and inaccessable
information in the long-run.
 Based on the selection of criterion and
information in the process of decision-making, the
accomplished grades results are thoroughly
obtained from the same.
2) Methods chosen for identifying risks in
construction project:
Identifying the risk involved in construction project:
During identification stage various factors are noted
which are possible to occur during the entire cycle of the
project. The following methods for identification of risk
factors which are most frequently used are the Delphic
Technique, the brainstorming, the checklist method.
Now we will take a look at the suitability, limitation,
strength and weaknesses of all the risk identification
techniques Delphi technique, brainstorming and the
checklist. Before using all these three methods various
types of risks were classified and taken into
consideration like for example: 1) Technical risks: which
are mostly associated with complex and advanced
techniques,equipments,materials.2)Construction risks:
which are mainly associated with site precautions and
safety, workers safety, environmental conditions
,geotechnical conditions, construction procedures. 3)
Financial risks: these are mainly associated with
economic conditions, market instability, political
conditions and interference, exchange rates etc.
The table below shows the strengths and weaknesses or
limitations of the three risk identification methods:
STRENGTHS BRAIN
STORMING
DELPH
I
CHEC
KLIST
Short duration for setting
up the structure.
y y
Anonymous ideas y
Short time taken to
identify risks
y
Encouraging innovative
thinking.
y
Managing and enabling
interaction between
people from different
regions and areas.
y
Forecasting y y
Encouraging interactive
communication and
group thinking between
the participants.
Y
Enabling participants to
take their own time for
analyzing and observing
the problems.
y
LIMITATIONS
Inability of group
interaction and group
thinking
y y
Long-time duration for
setting up the structure
y
Improper behaviour of
the participants that
increases the possibility
of risks.
Y
Taking a long time to
achieve results and
coming to a end
conclusion.
Y
TABLE.1 (Symbol y signifies ‘’yes’’)
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2008
Suitability factor for risk identification:
Simple projects Complex projects
F C T F C T
Brainstorming M M H L M M
Delphi H L M L M L
Checklists M H M L M L
TABLE.2
M: moderate suitability, L: low suitability, H: high
suitability, F: financial risks, C: construction risks, T:
technical risks.
3) Chosen method for risk assessment in
construction sector.
Assessment of risk in construction industry:
The analysis or the assessment stage of the risk takes
into consideration various factors like degree of impact
of risk on construction sector, possibility of their
occurrence. The methods and tools for analysis and
estimation of risks, which are generally used are
probabilistic methods and probability theory, sensitivity
analysis, decision making methods, computer simulation
, cost benefit analysis, the fuzzy sets or fuzzy logic model,
neutral networks approach etc. Of all these methods the
most significant is the fuzzy sets method.
The fuzzy system enables us to deal with confusing
information and has ability to explain and make
understand the reasoning process which is of vital
importance in the field of the risk assessment. In brief
fuzzy logic model is used for the examination and
assessment of risk.
The fuzzy process can be divided into three steps:
a.) Fuzzification
b.) Fuzzy interference
c.) Defuzzification
The entire fuzzy method can be explained in simple basic
steps;
1.) Surveying and studying the risk related data and
information.
2.) Measuring risk criteria for analyzing risk
magnitude.
3.) Filling of design criteria values into fuzzy decision
network. Fuzzy decision network is mainly
divided into two main processes i.e fuzzification
and aggregation.
4.) Inputting the aggregation criteria into fuzzy
interference system.
5.) Last is defuzzification process.
Chart of fuzzy network
4) Controlling and managing risk in
construction industry.
The main aim of risk management is to determine the
undesirable factors and aspects which leads to cause
serious adversities and impacts time, size of the
construction project and meanwhile developing
alternatives and undertaking probable methods that will
in turn reduce the effect of risk on construction industry
which will further facilitate smooth running of the
project. At the final procedural stage it is desirable to
adopt response strategies which will help in minimizing
damages of the undesirable events and reduce its
consequential reaction on the project.
5) CONCLUSION:
The process of combating the problems of risk
management is very essential for effective planning and
organising of any construction project in any sector.
During this process, one must undertake the most
appropriate method of risk identification and risk
assessment. One can definitely be guided by the
reliability and usefulness of the method in analyzing and
examining the problems in risk management. The risk
management requires a flexible approach to analyze and
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2009
combat the adverse effects of risk factors and also
requires brief description about the mechanisms
involved during the duration of the project in the
construction organization. Also the most appropriate
method chosen should be such that it is easily available
and feasible under any possible circumstances.
Many methods are used for evaluating and examining
risk identification and risk assessment in risk
management, but the most important and generally used
ones are specified and explained in the paper above
which are the Delphi method for risk identification and
Fuzzy networks for risk assessment. However, degree of
difficulty and scope of application depends upon the
feasibility of the construction project and degree of risk
factor influencing the risk management. Hence
considering the feasibility of each and every method
under different conditions the process of identification
and assessment of risks should be carried out by making
use of the most appropriate method possible since risk
management is the most integral part of project
management in construction industries.
6) REFERENCES:
 S. Q. Wang and M. F. Dulami, “Risk management
frame work for construction projects in
developing countries,”2004.
 F. Y. Y. Ling and L. Hoi, “Risks faced by Singapore
firms when taking construction projects in
India,” 2006.
 Anna Klemetti” Risk management in
construction project network” Laboratory of
industrial management report 2006
 Chapman C.B. and Ward S.C., “Project Risk
Management: Process, Techniques and Insights”,
2nd Edition, 2003.
 Daniel Baloi, “Risk Analysis Techniques in
Construction Engineering Projects”, Journal of
Risk analysis and crisis response, 2012.
 Bennett, F.L., 2003. The Management of
Construction: A Project Lifecycle Approach,
2005.
 Project Management Institute, (2004). A Guide
to the Project Management Body of Knowledge.

More Related Content

What's hot

RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITYRISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITYA Makwana
 
Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...IJLT EMAS
 
Ijirt100070 paper
Ijirt100070 paperIjirt100070 paper
Ijirt100070 paperMolay Reja
 
Establishing risk management factors for construction projects in iraq
Establishing risk management factors for construction projects in iraqEstablishing risk management factors for construction projects in iraq
Establishing risk management factors for construction projects in iraqIAEME Publication
 
A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingA fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingAlexander Decker
 
risk management: a better approach
risk management: a better approachrisk management: a better approach
risk management: a better approachMadhumanti Samaddar
 
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...IAEME Publication
 
IRJET- Projects in Constructions due to Inadequate Risk Management
IRJET-  	  Projects in Constructions due to Inadequate Risk ManagementIRJET-  	  Projects in Constructions due to Inadequate Risk Management
IRJET- Projects in Constructions due to Inadequate Risk ManagementIRJET Journal
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET Journal
 
IRJET - A Study on Identification of Risks at Various Phases of Road Const...
IRJET - 	  A Study on Identification of Risks at Various Phases of Road Const...IRJET - 	  A Study on Identification of Risks at Various Phases of Road Const...
IRJET - A Study on Identification of Risks at Various Phases of Road Const...IRJET Journal
 
A Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsA Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsIJMER
 
IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk AnalysisIRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk AnalysisIRJET Journal
 
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...IJCMESJOURNAL
 
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...ijtsrd
 

What's hot (19)

RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITYRISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
 
Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Ijirt100070 paper
Ijirt100070 paperIjirt100070 paper
Ijirt100070 paper
 
Establishing risk management factors for construction projects in iraq
Establishing risk management factors for construction projects in iraqEstablishing risk management factors for construction projects in iraq
Establishing risk management factors for construction projects in iraq
 
A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingA fuzzy ahp model in risk ranking
A fuzzy ahp model in risk ranking
 
H0341034041
H0341034041H0341034041
H0341034041
 
risk management: a better approach
risk management: a better approachrisk management: a better approach
risk management: a better approach
 
QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...
QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...
QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...
 
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
 
IRJET- Projects in Constructions due to Inadequate Risk Management
IRJET-  	  Projects in Constructions due to Inadequate Risk ManagementIRJET-  	  Projects in Constructions due to Inadequate Risk Management
IRJET- Projects in Constructions due to Inadequate Risk Management
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
 
Ijetcas14 370
Ijetcas14 370Ijetcas14 370
Ijetcas14 370
 
IRJET - A Study on Identification of Risks at Various Phases of Road Const...
IRJET - 	  A Study on Identification of Risks at Various Phases of Road Const...IRJET - 	  A Study on Identification of Risks at Various Phases of Road Const...
IRJET - A Study on Identification of Risks at Various Phases of Road Const...
 
Project risk management
Project risk managementProject risk management
Project risk management
 
A Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsA Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction Projects
 
IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk AnalysisIRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
 
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
 
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...
 

Similar to Effectiveness of Risk Management and Chosen Methods in Construction Sector

Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsIRJET Journal
 
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...IRJET Journal
 
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...
IRJET- A Review Paper on Risk Management using Primavera for Residential ...IRJET Journal
 
IRJET- Analysis of Risk Management in Construction Sector using Fault Tree...
IRJET- 	  Analysis of Risk Management in Construction Sector using Fault Tree...IRJET- 	  Analysis of Risk Management in Construction Sector using Fault Tree...
IRJET- Analysis of Risk Management in Construction Sector using Fault Tree...IRJET Journal
 
Risk Management in Medium Sized Commercial Buildings
Risk Management in Medium Sized Commercial BuildingsRisk Management in Medium Sized Commercial Buildings
Risk Management in Medium Sized Commercial BuildingsIRJET Journal
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...IRJET Journal
 
IRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET Journal
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential SectorIRJET Journal
 
Risk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectRisk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectIRJET Journal
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSvivatechijri
 
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIORISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIOIAEME Publication
 
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET Journal
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsIRJET Journal
 
Minimization of Risks in Construction projects
Minimization of Risks in Construction projectsMinimization of Risks in Construction projects
Minimization of Risks in Construction projectsIRJET Journal
 
Risk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesRisk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesIRJET Journal
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSIRJET Journal
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSIRJET Journal
 
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET Journal
 
A Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksA Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksIRJET Journal
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 

Similar to Effectiveness of Risk Management and Chosen Methods in Construction Sector (20)

Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction Projects
 
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
 
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
 
IRJET- Analysis of Risk Management in Construction Sector using Fault Tree...
IRJET- 	  Analysis of Risk Management in Construction Sector using Fault Tree...IRJET- 	  Analysis of Risk Management in Construction Sector using Fault Tree...
IRJET- Analysis of Risk Management in Construction Sector using Fault Tree...
 
Risk Management in Medium Sized Commercial Buildings
Risk Management in Medium Sized Commercial BuildingsRisk Management in Medium Sized Commercial Buildings
Risk Management in Medium Sized Commercial Buildings
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
 
IRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera Software
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential Sector
 
Risk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectRisk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure project
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
 
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIORISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
 
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction Projects
 
Minimization of Risks in Construction projects
Minimization of Risks in Construction projectsMinimization of Risks in Construction projects
Minimization of Risks in Construction projects
 
Risk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesRisk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction Industries
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
 
A Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksA Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction Risks
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 

Effectiveness of Risk Management and Chosen Methods in Construction Sector

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2006 EFFECTIVENESS OF RISK MANAGEMENT AND CHOSEN METHODS IN CONSTRUCTION SECTOR Shivani More1, Tejas Hirlekar2 1,2 Undergraduate, Dept. of Civil Engineering, Datta Meghe College of Engineering, Airoli, Navi Mumbai, India ---------------------------------------------------------------------***----------------------------------------------------------------------- Abstract: Risk analysis is the most important aspect for the selection of any project and maintenance of co- ordination in construction sector. In general risk is basically the deviation from what is normal, the expected level. Risk is indeed considered as a central part of uncertainty, in which the probability occurrence and amount of damage can be determined. Risk management is area which requires tremendous emphasis and comprehensive approach by the various aspects or participants of the sector. With the growing economy the construction industry in India has gained enormous attention and poised for exceptional growth prospectives. This paper puts forth an attempt to bring out the importance of risk management and the analysis and risk management processes that should be undertaken for the improvement of the construction industry in the long-run. Result analysis and a short survey made in this regard has been included which gives an overview about the current practices relevant in the construction industry. An efficient and effective risk management approach requires a systematic methodology including knowledge and experience about the construction works. Analysing the risk is often considered as analysing the adverse consequences during the stage of planning and programming of construction project. The risk management analysis not only enhances the decision- making process but also provides additional information which helps to select the optimal aspects of the construction project. Keywords: Risk Analysis, Risk management, Uncertainty, Systematic methodology, Adverse consequences, Decision-making process, Optimal aspects. 1) INTRODUCTION: The phenomenon of risk is the most important subject of discussion for both theorists and practitioners. However, only a few fraction of them realize the adversity and undertake these problems in order to formulate the problematic situations within the procedural framework. Presently the construction industry occupies such a position which has considerably caused the increase in employment generation. Amidst such an encouraging situation, the industry is still in the phase of many challenges which faces limitations in aspects like construction material, financial resources, human resources, construction methodologies. Due to the rapid growth in the infrastructure of the project huge quantum of various resources and the nature of the complexities of project, the management of risk plays a vital role in the construction sector. Risk management can be considerably improved by improving the performance and the knowledge of labours, machinery, money, materials etc. which facilitates the entire construction industry. This paper outlines the important areas of risk management in the construction industry and aims at presenting the three methods used for the analysis of risk and simultaneously pointing their features and characteristics by highlighting the degree of credibility of the discussed problems. The presented methods involve solved decision-making and the usage of the data by taking into consideration common features as well as specific individual features of each one of them. Risk being considered as a measureable part of uncertainty is most often considered as possibility of incurring heavy losses. The scope and the number of problems associated with risk management, taking into consideration the realization of the project is enormous before we delve into analysis of risk, we should find answers to the required three questions. Risk management being a considerably vast aspect, should therefore be segregated into 3 general forms which are: 1) Risk Identification 2) Risk Assessment 3) Measuring and controlling the reaction of risk
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2007 Risk management in construction industry According to various publications the popularity of the methods to clearly identify risk is based on various aspects like the degree and quality of the obtained results, verifications and specifications used in the project, degree of complexity of calculation, use oof computer softwares. The mentioned methods are illustrated and outlined at a same time, taking into consideration their characteristic feature in terms of their analysis. Characteristics of the methods stated:  Requirement of necessary flexible approach, taking into consideration some additional factors by keeping in mind the specific list of problems and hazards for each project.  Limited scope or approach and inaccessable information in the long-run.  Based on the selection of criterion and information in the process of decision-making, the accomplished grades results are thoroughly obtained from the same. 2) Methods chosen for identifying risks in construction project: Identifying the risk involved in construction project: During identification stage various factors are noted which are possible to occur during the entire cycle of the project. The following methods for identification of risk factors which are most frequently used are the Delphic Technique, the brainstorming, the checklist method. Now we will take a look at the suitability, limitation, strength and weaknesses of all the risk identification techniques Delphi technique, brainstorming and the checklist. Before using all these three methods various types of risks were classified and taken into consideration like for example: 1) Technical risks: which are mostly associated with complex and advanced techniques,equipments,materials.2)Construction risks: which are mainly associated with site precautions and safety, workers safety, environmental conditions ,geotechnical conditions, construction procedures. 3) Financial risks: these are mainly associated with economic conditions, market instability, political conditions and interference, exchange rates etc. The table below shows the strengths and weaknesses or limitations of the three risk identification methods: STRENGTHS BRAIN STORMING DELPH I CHEC KLIST Short duration for setting up the structure. y y Anonymous ideas y Short time taken to identify risks y Encouraging innovative thinking. y Managing and enabling interaction between people from different regions and areas. y Forecasting y y Encouraging interactive communication and group thinking between the participants. Y Enabling participants to take their own time for analyzing and observing the problems. y LIMITATIONS Inability of group interaction and group thinking y y Long-time duration for setting up the structure y Improper behaviour of the participants that increases the possibility of risks. Y Taking a long time to achieve results and coming to a end conclusion. Y TABLE.1 (Symbol y signifies ‘’yes’’)
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2008 Suitability factor for risk identification: Simple projects Complex projects F C T F C T Brainstorming M M H L M M Delphi H L M L M L Checklists M H M L M L TABLE.2 M: moderate suitability, L: low suitability, H: high suitability, F: financial risks, C: construction risks, T: technical risks. 3) Chosen method for risk assessment in construction sector. Assessment of risk in construction industry: The analysis or the assessment stage of the risk takes into consideration various factors like degree of impact of risk on construction sector, possibility of their occurrence. The methods and tools for analysis and estimation of risks, which are generally used are probabilistic methods and probability theory, sensitivity analysis, decision making methods, computer simulation , cost benefit analysis, the fuzzy sets or fuzzy logic model, neutral networks approach etc. Of all these methods the most significant is the fuzzy sets method. The fuzzy system enables us to deal with confusing information and has ability to explain and make understand the reasoning process which is of vital importance in the field of the risk assessment. In brief fuzzy logic model is used for the examination and assessment of risk. The fuzzy process can be divided into three steps: a.) Fuzzification b.) Fuzzy interference c.) Defuzzification The entire fuzzy method can be explained in simple basic steps; 1.) Surveying and studying the risk related data and information. 2.) Measuring risk criteria for analyzing risk magnitude. 3.) Filling of design criteria values into fuzzy decision network. Fuzzy decision network is mainly divided into two main processes i.e fuzzification and aggregation. 4.) Inputting the aggregation criteria into fuzzy interference system. 5.) Last is defuzzification process. Chart of fuzzy network 4) Controlling and managing risk in construction industry. The main aim of risk management is to determine the undesirable factors and aspects which leads to cause serious adversities and impacts time, size of the construction project and meanwhile developing alternatives and undertaking probable methods that will in turn reduce the effect of risk on construction industry which will further facilitate smooth running of the project. At the final procedural stage it is desirable to adopt response strategies which will help in minimizing damages of the undesirable events and reduce its consequential reaction on the project. 5) CONCLUSION: The process of combating the problems of risk management is very essential for effective planning and organising of any construction project in any sector. During this process, one must undertake the most appropriate method of risk identification and risk assessment. One can definitely be guided by the reliability and usefulness of the method in analyzing and examining the problems in risk management. The risk management requires a flexible approach to analyze and
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2009 combat the adverse effects of risk factors and also requires brief description about the mechanisms involved during the duration of the project in the construction organization. Also the most appropriate method chosen should be such that it is easily available and feasible under any possible circumstances. Many methods are used for evaluating and examining risk identification and risk assessment in risk management, but the most important and generally used ones are specified and explained in the paper above which are the Delphi method for risk identification and Fuzzy networks for risk assessment. However, degree of difficulty and scope of application depends upon the feasibility of the construction project and degree of risk factor influencing the risk management. Hence considering the feasibility of each and every method under different conditions the process of identification and assessment of risks should be carried out by making use of the most appropriate method possible since risk management is the most integral part of project management in construction industries. 6) REFERENCES:  S. Q. Wang and M. F. Dulami, “Risk management frame work for construction projects in developing countries,”2004.  F. Y. Y. Ling and L. Hoi, “Risks faced by Singapore firms when taking construction projects in India,” 2006.  Anna Klemetti” Risk management in construction project network” Laboratory of industrial management report 2006  Chapman C.B. and Ward S.C., “Project Risk Management: Process, Techniques and Insights”, 2nd Edition, 2003.  Daniel Baloi, “Risk Analysis Techniques in Construction Engineering Projects”, Journal of Risk analysis and crisis response, 2012.  Bennett, F.L., 2003. The Management of Construction: A Project Lifecycle Approach, 2005.  Project Management Institute, (2004). A Guide to the Project Management Body of Knowledge.