RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
ROHIT DEOKAR1, ROHIT SALGUDE2
1Student, Mtech in Construction Management, Maharashtra Institute of Technology, World Peace University, Kothrud,
Pune, India
2Asst. Prof., Department of Civil Engineering, Maharashtra Institute of Technology, World Peace University, Kothrud,
Pune, India.
---------------------------------------------------------------------------***------------------------------------------------------------------------
ABSTRACT: The construction industry has now turned out to be one of the fastest growing industries of today that has
significant effect on the economy of India Large development projects when deferred cause increment in the general spending
plan. The undertaking must be planned and sorted out property and precisely to finish it inside given time with good quality
work. This study specify that all the construction projects, all over the world, have huge number of risks and to complete the
project, efficiently and successfully, risk management is essential. The risks can be recognized by questionnaire survey. The
risks are identified and then it is evaluated by various technique like qualitative analysis to know the occurrence probability of
risk and impact of these risk on project goals. When any risk arises, they have severe or simple impact on project and it affects
cost, schedule of project, time, and quality. Therefore, for the project to be succeed, the risk management is required.
1.0 INTRODUCTION
The construction industry has now turned out to be one of the fastest growing industries of today that has significant effect on
the economy of India. If we were to take a case, in the greater part of the creating nations the primary development exercises
which if carried out add to right around 85% of the average capital resources, around 15% of their Gross domestic product,
and more than around half of the capital that is been put resources into the fixed assets. The construction business always
gives high work openings. Numerous tasks experience both significant time and cost overruns. Large development projects
when deferred cause increment in the general spending plan. The undertaking must be planned and sorted out property and
precisely to finish it inside given time with good quality work. This has expanded the competition between the construction
firms in the country. The construction firms and the customer's behavior have made changes because of these events.
OBJECTIVES OF THE RESEARCH
 To analyse and make a brief study on various risks those are very often to occur in the construction project.
 Segmenting and classifying the risks depending on the different matrix and then categorize the risk as high, moderate,
and low.
 Formulate a risk mitigation plan.
 To make a work to increase the probability of occurrence of positive events by proper prediction of risks.
 Providing practical recommendation and ideas for development of the risk management method and develop their
performances.
2.0 LITERATURE REVIEW
The following literature survey includes summary of research papers presented in popular journals on topics almost like
current field of study.
(1)J.G Perry, R.W. Hayes .
This paper displays about idea of the risk management inside the management of construction projects. The primary
importance is on the commitment which can be made on the elusion of cost and time, attacks ordinarily connected with main
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1339
projects. The three major stages of risk management is identification, investigation and reaction are conserved and details
about theory briefly explained out. The risk management especially fit under three phases of life of construction projects, pre-
sanction and development of agreement strategy and arrangement of documents and its application to every one of these
stages are represented.
(2)Kinnaresh patel .
There are many challenging projects ongoing in the world which include variety of complexion procedures working
simultaniously. Dealing with these procedures can be a quite challenge for the management. One of the measure task is
identifying the risk that is involved. Risk management contains identifying risk, evaluating risk either quantitatively or
subjectively, picking the correct technique for handling of risk, and after that controlling or recording the risk. This study
distinguishes the strategies for risk recognizable proof, management and its observation from the Indian construction
industrial players. Time and cost management fully consolidated with the identification process and time limitations and
project management with adequate experience are basic while identifying the level of risk for mega projects as well as
complex projects. The objective of this study is to advocate for a method of risk mitigation which includes a very well-
documented process, which helps as a one stop-solution to all the risks that would arise in the future.
(3)M.J. Mawdesley .
This paper describes about how to understand and it gives solution for the construction risks, actual on the human risk
factors. For this purpose many questionnaires are created and it is implemented in personal interviews with construction
experts. Now a days risk management has been normally applied across construction sectors. It is very hardly includes the
outcome of human factorals. This paper classifies the human risk factors mainly in the construction, the human risk factors are
cannot be ignored at any cost these are considered to be in the project risk management. Another procedure of evaluating risk
to similarly incorporate human risk components have to be created, in which human risk factors are recognized and examined
symmetrically, all through the risk and significance is given for incorporating human risk factors in the improvement project
management.
(4)Pattel Ankit Mahendra Et.Cl.
Conducted study on risk management for applying in construction project which includes new procedures for all types of risks
most likely happens during total life of project uncertainty and risk are picked up or collect from various sources in project,
that are composite or difficulty in nature with the record of submission of risk not suitable in construction projects. The
journal paper defines techniques of identifying the risks, evaluating and analyzing the risks involved. The risk management
carryout especially protected by the project team members and then handled with care. Due to insufficient knowledge about
risk managemental processes, it is not applied or useful in the construction projects. This paper describes the risk
management should be conducted at the starting stage for the betterment of the project results. It has been concluded that
there is requirement for all around recorded way to deal with unravel every one of the risk in projects.
(5)Pawel szymanski
This paper helps in identification and classification of the risks as the risk is present everywhere and every area of life in one
such is construction industry where the risk always present. Analysis is done in part or in detail, including escorts and even
stake holders by doing this we can effectively manage the risk coming in future and can be translated into clear benefits to
project. The first step is identify the risk in the very main stage and determining which type of risk, how it is affecting to the
project,and characteristics of risk and estimating possibility of its incidence to project. This paper reviews different type of
risks present in stages of construction.
(6)Saied A. Kartam .
This paper informs, the work is done on the basis of questionnaire survey on biggest Kuwaiti country contractors, and the
main thing they consider is risk under construction projects. The important thing risk under construction management are
time and the cost of the projects. In this study the Kuwaiti contractors first give concentration on the evaluation, allocation and
risk on site areas. This paper represent two types risk management procedures, the priors is preventive, these risks were
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1340
occurs at the beginning of the project works and mitigative, which are the main object to resolve during process of
construction in less time. The exploration found that temporary workers demonstrate more readiness to acknowledge risks,
that are authoritative and lawful related as opposed to different kinds of risks. The exploration comes about similarly showed
that the utilization of the formal hazard investigation strategies in the Kuwaiti development industry is restrictial.
3.0 METHODOLOGY
3.1 Risk identification
Risk identification is a repetitive process because as the project progresses new risk develop through the project life cycle. The
risk valuation format should be continuous to allow the comparison between the effects of one risk even on the other. The
identification process in the organization includes the project team members. For the purpose, the several risk arising in the
construction process from the formulation, mobilization and construction stage are categorized and listed.
3.2 Questionnaire survey
The questionnaire survey has been conducted on construction companies and the case study and the rating were given.
3.3 Qualitative risks analysis
Qualitative risk analysis involves evaluating the probability and impact of the various risks and listing the risks so as to
improve the performance of the project by making the risks with high priority. The valuation of the priority identified risks is
done on basis of likelihood or probability of occurrence of risks, the corresponding impact of the risks if it happens and as well
as urgency of risk response.
3.4 Risk Response planning
The Risk Response planning includes determining methods to decrease or take out any threats to the project, also the
chances to decrease their impact. It is followed by the qualitative risk analysis. Risks with high priority are addressed by risk
response plan. A risk response owner or risk expert will be allotted to take the responsibility of controlling the risk by
introducing essential activities and resources to the budget, project schedule and management plan as required. The risk
response also responsible for reducing the probability and impact of threats and sometimes to increase the probability and
impact opportunities.
Data identification / Risk
identification
Conduct questionnaire
survey
Qualitative risk analysis
Risk response planning
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1341
4. RESULTS AND DISCUSSIONS
DATA COLLECTION
The questionnaire survey done on ten construction companies and their average results are shown below:
In the table,
 P - Probability
 I - Impact
 U - Urgency
 PR – Priority
TECHNICAL RISKS
SL.No. RISKS P I U PR
1 Type of contract T1 2 2 2 3
2 Project preliminary plan T2 3 4 4 4
3 Delays occurs in design and drawings than expected T3 3 4 4 4
4 Managing resources T4 4 4 4 4
5 Inadequate investigation on site T5 3 4 4 3
6 Unknown productivity of resources T6 3 4 4 4
7 Changes in project scope and requirement T7 2 3 3 3
8 Design errors and faults T8 3 4 4 4
9 Subcontractors T9 2 2 2 2
10 Insufficient contractor experience T10 2 2 2 3
11 Failure to carry work as per planning, scheduling T11 2 3 3 3
12 Improper scheduling and delay of contactor T12 3 4 4 3
13 Controlling and monitoring and execution T13 2 3 3 3
FINANCIAL RISKS
SL.No. RISKS P I U PR
1 Investment on projects F1 2 2 3 3
2 Availability and undulation in foreign exchange F2
3 Delays in worker wages F3 3 4 4 4
4 Increase in cost of materials F4 3 4 3 4
5 Releasing of funds F5 2 2 3 3
6 Import procedures F6 2 2 2 3
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1342
LOGISTICS AND CONSTRUCTION RISKS
SL.No RISKS P I U PR
1 Non availability of transportation services L1 2 3 2 2
2 Difficulties in disposing plant and equipment’s L2 2 2 2 2
3 Unfamiliarity with local bodies C1 2 2 3 2
4 Demands on use of local firms and C2 2 2 2 2
agents
5 Technologies C3 2 3 3 3
6 Absence of protection on construction site C4 3 4 4 3
MANAGEMENT RISKS
SL.No. RISKS P I U PR
1 Company relation problems M1 1 1 2 2
2 Inadequate assigning works M2 2 2 2 3
3 Unsatisfactory skilled staff M3 2 2 2 3
4 Uncertainty about relationship between
project employees
M4 2 2 2 2
5 Clashes between project group M5 1 2 2 2
6 Resource allocation M6 2 2 3 3
POLITICAL RISKS
SL.No. RISKS P I U PR
1 Before tendering P1 2 2 2 2
2 Acceptance of contract P2 1 2 2 2
3 Public complaints P3 2 2 2 2
4 Finalization of contract P4 1 1 1 2
5 Resident tolls P5 1 2 2 2
6 Permissions, clearance, approvals P6 3 4 4 3
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1343
ENVIRONMENTAL RISKS
SL.NO. RISKS P I U PR
1 Natural disasters E1
2 Weather and seasonal variations E2 3 4 3 3
3 EIA reports E3
5.REMEDIES AND SUGGESTIONS
• Project description: Clear understanding of what the project is, how it is to be achieved and explaining the complete
results of the project.
• Project purpose: Suitably defining the purpose of the project and if possible tying the purpose of the project with the
planned goals and objectives of the management.
• Project goals: This is one of the most essential elements in project preliminary investigation. Providing clear,
assessable and actionable objectives, so that the project can be measured against the goals after completing. Clear
documentation of the goals is necessary as the ultimate success of the project depends upon the success of its definite
goals.
• Project requirements: Finding the requirements of the service or product that is to be developed. Requirements
contain elements such as time, cost, quality and safety.
• Project assumption: Assumptions made with respect to the budget, schedule, at the beginning have to be considered.
• Project milestone: Setting up of milestones, helps to track the schedule and finish the project on time.
• Well defined project scope: The project preliminary survey should be carried properly. The need, scope,
requirements of the project should be thoroughly studied.
• Involvement of client: The client or his representative should be involved in the process of planning. Any
modifications in the plan should be carried to the notice of concerned individual and modification should be done in
the plan.
• Conducting frequent meetings with client: Common meetings should be conducted with the clients to brief him
about the flow process of planning and designing. This will improve the connection with the client and increase client’s
satisfaction.
• Issuing deadlines: The staff involved in process of planning should work professionally to finish the work in time.
Providing deadlines will give maximum output of staff.
• Following up fund requirements, need and gap.
• Suitable supervision and assignment of activity by explained staff.
• Recording the cash flow, and noting the transactions and constraints on their use.
• Agreement at several phases of process should be prepared.
• Management has to adopt the most useful ways get best production by utilizing materials, machine, men and energy at
lowest cost.
• Plants and equipment’s should existing with all supporting resources for maximum efficiency, which can support in
completing project goals associated to costs, time, scope, and schedule.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1344
6.CONCLUSION
The methods to classify project risks, that have been particularized for construction projects, have been presented
from various point of view from construction companies and firms that may be helping the development of dealing with
project in the planning and construction stages.
The project has studied various factors related to risks and some of outcomes are listed below:
• The risks management process starts prior to project itself.
• There must be proper coordination between every distinct involved with project to implement better risk
management practices.
• Record of all the risk occurred and occurring, occurs in future should be maintained.
• Every organization big or small should be adopt risk management practices to reduce effect of risks arising in the
project and its impact to reach the project goals.
• The project should be properly scheduled and monitored.
• Clear understanding of the project scope explaining of the complete outcome of project.
• Repetitively changes in design should be avoided in the projects.
• Wages of the workers should not be delayed.
• Procurement of materials should be timely on site.
From the results, it is safe to say that majority of the construction projects have no systematic procedure in place to deal
with risks. Risk management is done in a very informal mode..
7.REFERENCES
[1] Agnieszka Dziadoz, Mariusz Rejment “Risk analysis in construction projects-chosen method”, operational research
in sustainable development and civil engineering – meeting of euro working group and 15th German-Lithunain-
polish colloquium(ORSDE2015), PP 258-265.
[2] Absulmaten Taroun, “Towards a better modeling and assessment of construction risk”, Journal of Civil Engineering
Research 2014, 4(2A),volume 32, PP 101-105.
[3] Ana I, Irimia-Dieguez, Alvaro sanchez-carzola, Rafaela alfalla-luque “Risk management in megaprojects”, science
direct procedia – social and behavioral sciences, vol.119 (2014), PP 407-416.
[4] He Zhi “Risk management for overseas project management”, International Journal of Project Management,Volume
13, PP 231-237.
[5] J.G Perry, R.W. Hayes “Risk management in construction projects”, Asia-Pacific Journal of Management Research
and Innovation, Volume: 7, issue: 3, Article first published online: July 1, 2011; Issue published: July 1, 2011, PP:
107-120.
[6] Kinnaresh Patel “A study on risk assessment and its management in India”,American Journal of Civil Engineering.
Vol. No 1, Vol. No. 2, 2013, PP. 64-67.
[7] M.J. Mawdesley “Perception of human risk factors in construction projects: An exploratory study”, Article in
International Journal of Project Management22(2):131137, February 2004, volume 22, PP 131-137.
[8] Pattel Ankit Mahendra Et.Cl “Risk analysis in construction projects - chosen methods”, Internet source.

More Related Content

Similar to RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS

IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET Journal
 
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...IRJET Journal
 
Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Sibo Kanyambari Aimable
 
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...Sibo Kanyambari Aimable
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET Journal
 
IRJET- Projects in Constructions due to Inadequate Risk Management
IRJET-  	  Projects in Constructions due to Inadequate Risk ManagementIRJET-  	  Projects in Constructions due to Inadequate Risk Management
IRJET- Projects in Constructions due to Inadequate Risk ManagementIRJET Journal
 
Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...IRJET Journal
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...IRJET Journal
 
risks-07-00024.pdf
risks-07-00024.pdfrisks-07-00024.pdf
risks-07-00024.pdfRidaShahid36
 
Risk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectRisk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectIRJET Journal
 
IRJET- Risk Management in the Construction Project: Review
IRJET-  	  Risk Management in the Construction Project: ReviewIRJET-  	  Risk Management in the Construction Project: Review
IRJET- Risk Management in the Construction Project: ReviewIRJET Journal
 
A Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksA Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksIRJET Journal
 
Software Project Risk Management Practice in Oman
Software Project Risk Management Practice in OmanSoftware Project Risk Management Practice in Oman
Software Project Risk Management Practice in OmanEECJOURNAL
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)inventionjournals
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
Risk Management in Retrofitting Projects
Risk Management in Retrofitting ProjectsRisk Management in Retrofitting Projects
Risk Management in Retrofitting ProjectsIRJET Journal
 
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITYRISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITYA Makwana
 
Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsIRJET Journal
 
IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk AnalysisIRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk AnalysisIRJET Journal
 

Similar to RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS (20)

IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature Review
 
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
 
Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...
 
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction Projects
 
IRJET- Projects in Constructions due to Inadequate Risk Management
IRJET-  	  Projects in Constructions due to Inadequate Risk ManagementIRJET-  	  Projects in Constructions due to Inadequate Risk Management
IRJET- Projects in Constructions due to Inadequate Risk Management
 
Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...
 
C1303032126
C1303032126C1303032126
C1303032126
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
 
risks-07-00024.pdf
risks-07-00024.pdfrisks-07-00024.pdf
risks-07-00024.pdf
 
Risk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectRisk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure project
 
IRJET- Risk Management in the Construction Project: Review
IRJET-  	  Risk Management in the Construction Project: ReviewIRJET-  	  Risk Management in the Construction Project: Review
IRJET- Risk Management in the Construction Project: Review
 
A Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksA Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction Risks
 
Software Project Risk Management Practice in Oman
Software Project Risk Management Practice in OmanSoftware Project Risk Management Practice in Oman
Software Project Risk Management Practice in Oman
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Risk Management in Retrofitting Projects
Risk Management in Retrofitting ProjectsRisk Management in Retrofitting Projects
Risk Management in Retrofitting Projects
 
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITYRISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
 
Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction Projects
 
IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk AnalysisIRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 

Recently uploaded (20)

Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 

RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1338 RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS ROHIT DEOKAR1, ROHIT SALGUDE2 1Student, Mtech in Construction Management, Maharashtra Institute of Technology, World Peace University, Kothrud, Pune, India 2Asst. Prof., Department of Civil Engineering, Maharashtra Institute of Technology, World Peace University, Kothrud, Pune, India. ---------------------------------------------------------------------------***------------------------------------------------------------------------ ABSTRACT: The construction industry has now turned out to be one of the fastest growing industries of today that has significant effect on the economy of India Large development projects when deferred cause increment in the general spending plan. The undertaking must be planned and sorted out property and precisely to finish it inside given time with good quality work. This study specify that all the construction projects, all over the world, have huge number of risks and to complete the project, efficiently and successfully, risk management is essential. The risks can be recognized by questionnaire survey. The risks are identified and then it is evaluated by various technique like qualitative analysis to know the occurrence probability of risk and impact of these risk on project goals. When any risk arises, they have severe or simple impact on project and it affects cost, schedule of project, time, and quality. Therefore, for the project to be succeed, the risk management is required. 1.0 INTRODUCTION The construction industry has now turned out to be one of the fastest growing industries of today that has significant effect on the economy of India. If we were to take a case, in the greater part of the creating nations the primary development exercises which if carried out add to right around 85% of the average capital resources, around 15% of their Gross domestic product, and more than around half of the capital that is been put resources into the fixed assets. The construction business always gives high work openings. Numerous tasks experience both significant time and cost overruns. Large development projects when deferred cause increment in the general spending plan. The undertaking must be planned and sorted out property and precisely to finish it inside given time with good quality work. This has expanded the competition between the construction firms in the country. The construction firms and the customer's behavior have made changes because of these events. OBJECTIVES OF THE RESEARCH  To analyse and make a brief study on various risks those are very often to occur in the construction project.  Segmenting and classifying the risks depending on the different matrix and then categorize the risk as high, moderate, and low.  Formulate a risk mitigation plan.  To make a work to increase the probability of occurrence of positive events by proper prediction of risks.  Providing practical recommendation and ideas for development of the risk management method and develop their performances. 2.0 LITERATURE REVIEW The following literature survey includes summary of research papers presented in popular journals on topics almost like current field of study. (1)J.G Perry, R.W. Hayes . This paper displays about idea of the risk management inside the management of construction projects. The primary importance is on the commitment which can be made on the elusion of cost and time, attacks ordinarily connected with main
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1339 projects. The three major stages of risk management is identification, investigation and reaction are conserved and details about theory briefly explained out. The risk management especially fit under three phases of life of construction projects, pre- sanction and development of agreement strategy and arrangement of documents and its application to every one of these stages are represented. (2)Kinnaresh patel . There are many challenging projects ongoing in the world which include variety of complexion procedures working simultaniously. Dealing with these procedures can be a quite challenge for the management. One of the measure task is identifying the risk that is involved. Risk management contains identifying risk, evaluating risk either quantitatively or subjectively, picking the correct technique for handling of risk, and after that controlling or recording the risk. This study distinguishes the strategies for risk recognizable proof, management and its observation from the Indian construction industrial players. Time and cost management fully consolidated with the identification process and time limitations and project management with adequate experience are basic while identifying the level of risk for mega projects as well as complex projects. The objective of this study is to advocate for a method of risk mitigation which includes a very well- documented process, which helps as a one stop-solution to all the risks that would arise in the future. (3)M.J. Mawdesley . This paper describes about how to understand and it gives solution for the construction risks, actual on the human risk factors. For this purpose many questionnaires are created and it is implemented in personal interviews with construction experts. Now a days risk management has been normally applied across construction sectors. It is very hardly includes the outcome of human factorals. This paper classifies the human risk factors mainly in the construction, the human risk factors are cannot be ignored at any cost these are considered to be in the project risk management. Another procedure of evaluating risk to similarly incorporate human risk components have to be created, in which human risk factors are recognized and examined symmetrically, all through the risk and significance is given for incorporating human risk factors in the improvement project management. (4)Pattel Ankit Mahendra Et.Cl. Conducted study on risk management for applying in construction project which includes new procedures for all types of risks most likely happens during total life of project uncertainty and risk are picked up or collect from various sources in project, that are composite or difficulty in nature with the record of submission of risk not suitable in construction projects. The journal paper defines techniques of identifying the risks, evaluating and analyzing the risks involved. The risk management carryout especially protected by the project team members and then handled with care. Due to insufficient knowledge about risk managemental processes, it is not applied or useful in the construction projects. This paper describes the risk management should be conducted at the starting stage for the betterment of the project results. It has been concluded that there is requirement for all around recorded way to deal with unravel every one of the risk in projects. (5)Pawel szymanski This paper helps in identification and classification of the risks as the risk is present everywhere and every area of life in one such is construction industry where the risk always present. Analysis is done in part or in detail, including escorts and even stake holders by doing this we can effectively manage the risk coming in future and can be translated into clear benefits to project. The first step is identify the risk in the very main stage and determining which type of risk, how it is affecting to the project,and characteristics of risk and estimating possibility of its incidence to project. This paper reviews different type of risks present in stages of construction. (6)Saied A. Kartam . This paper informs, the work is done on the basis of questionnaire survey on biggest Kuwaiti country contractors, and the main thing they consider is risk under construction projects. The important thing risk under construction management are time and the cost of the projects. In this study the Kuwaiti contractors first give concentration on the evaluation, allocation and risk on site areas. This paper represent two types risk management procedures, the priors is preventive, these risks were
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1340 occurs at the beginning of the project works and mitigative, which are the main object to resolve during process of construction in less time. The exploration found that temporary workers demonstrate more readiness to acknowledge risks, that are authoritative and lawful related as opposed to different kinds of risks. The exploration comes about similarly showed that the utilization of the formal hazard investigation strategies in the Kuwaiti development industry is restrictial. 3.0 METHODOLOGY 3.1 Risk identification Risk identification is a repetitive process because as the project progresses new risk develop through the project life cycle. The risk valuation format should be continuous to allow the comparison between the effects of one risk even on the other. The identification process in the organization includes the project team members. For the purpose, the several risk arising in the construction process from the formulation, mobilization and construction stage are categorized and listed. 3.2 Questionnaire survey The questionnaire survey has been conducted on construction companies and the case study and the rating were given. 3.3 Qualitative risks analysis Qualitative risk analysis involves evaluating the probability and impact of the various risks and listing the risks so as to improve the performance of the project by making the risks with high priority. The valuation of the priority identified risks is done on basis of likelihood or probability of occurrence of risks, the corresponding impact of the risks if it happens and as well as urgency of risk response. 3.4 Risk Response planning The Risk Response planning includes determining methods to decrease or take out any threats to the project, also the chances to decrease their impact. It is followed by the qualitative risk analysis. Risks with high priority are addressed by risk response plan. A risk response owner or risk expert will be allotted to take the responsibility of controlling the risk by introducing essential activities and resources to the budget, project schedule and management plan as required. The risk response also responsible for reducing the probability and impact of threats and sometimes to increase the probability and impact opportunities. Data identification / Risk identification Conduct questionnaire survey Qualitative risk analysis Risk response planning
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1341 4. RESULTS AND DISCUSSIONS DATA COLLECTION The questionnaire survey done on ten construction companies and their average results are shown below: In the table,  P - Probability  I - Impact  U - Urgency  PR – Priority TECHNICAL RISKS SL.No. RISKS P I U PR 1 Type of contract T1 2 2 2 3 2 Project preliminary plan T2 3 4 4 4 3 Delays occurs in design and drawings than expected T3 3 4 4 4 4 Managing resources T4 4 4 4 4 5 Inadequate investigation on site T5 3 4 4 3 6 Unknown productivity of resources T6 3 4 4 4 7 Changes in project scope and requirement T7 2 3 3 3 8 Design errors and faults T8 3 4 4 4 9 Subcontractors T9 2 2 2 2 10 Insufficient contractor experience T10 2 2 2 3 11 Failure to carry work as per planning, scheduling T11 2 3 3 3 12 Improper scheduling and delay of contactor T12 3 4 4 3 13 Controlling and monitoring and execution T13 2 3 3 3 FINANCIAL RISKS SL.No. RISKS P I U PR 1 Investment on projects F1 2 2 3 3 2 Availability and undulation in foreign exchange F2 3 Delays in worker wages F3 3 4 4 4 4 Increase in cost of materials F4 3 4 3 4 5 Releasing of funds F5 2 2 3 3 6 Import procedures F6 2 2 2 3
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1342 LOGISTICS AND CONSTRUCTION RISKS SL.No RISKS P I U PR 1 Non availability of transportation services L1 2 3 2 2 2 Difficulties in disposing plant and equipment’s L2 2 2 2 2 3 Unfamiliarity with local bodies C1 2 2 3 2 4 Demands on use of local firms and C2 2 2 2 2 agents 5 Technologies C3 2 3 3 3 6 Absence of protection on construction site C4 3 4 4 3 MANAGEMENT RISKS SL.No. RISKS P I U PR 1 Company relation problems M1 1 1 2 2 2 Inadequate assigning works M2 2 2 2 3 3 Unsatisfactory skilled staff M3 2 2 2 3 4 Uncertainty about relationship between project employees M4 2 2 2 2 5 Clashes between project group M5 1 2 2 2 6 Resource allocation M6 2 2 3 3 POLITICAL RISKS SL.No. RISKS P I U PR 1 Before tendering P1 2 2 2 2 2 Acceptance of contract P2 1 2 2 2 3 Public complaints P3 2 2 2 2 4 Finalization of contract P4 1 1 1 2 5 Resident tolls P5 1 2 2 2 6 Permissions, clearance, approvals P6 3 4 4 3
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1343 ENVIRONMENTAL RISKS SL.NO. RISKS P I U PR 1 Natural disasters E1 2 Weather and seasonal variations E2 3 4 3 3 3 EIA reports E3 5.REMEDIES AND SUGGESTIONS • Project description: Clear understanding of what the project is, how it is to be achieved and explaining the complete results of the project. • Project purpose: Suitably defining the purpose of the project and if possible tying the purpose of the project with the planned goals and objectives of the management. • Project goals: This is one of the most essential elements in project preliminary investigation. Providing clear, assessable and actionable objectives, so that the project can be measured against the goals after completing. Clear documentation of the goals is necessary as the ultimate success of the project depends upon the success of its definite goals. • Project requirements: Finding the requirements of the service or product that is to be developed. Requirements contain elements such as time, cost, quality and safety. • Project assumption: Assumptions made with respect to the budget, schedule, at the beginning have to be considered. • Project milestone: Setting up of milestones, helps to track the schedule and finish the project on time. • Well defined project scope: The project preliminary survey should be carried properly. The need, scope, requirements of the project should be thoroughly studied. • Involvement of client: The client or his representative should be involved in the process of planning. Any modifications in the plan should be carried to the notice of concerned individual and modification should be done in the plan. • Conducting frequent meetings with client: Common meetings should be conducted with the clients to brief him about the flow process of planning and designing. This will improve the connection with the client and increase client’s satisfaction. • Issuing deadlines: The staff involved in process of planning should work professionally to finish the work in time. Providing deadlines will give maximum output of staff. • Following up fund requirements, need and gap. • Suitable supervision and assignment of activity by explained staff. • Recording the cash flow, and noting the transactions and constraints on their use. • Agreement at several phases of process should be prepared. • Management has to adopt the most useful ways get best production by utilizing materials, machine, men and energy at lowest cost. • Plants and equipment’s should existing with all supporting resources for maximum efficiency, which can support in completing project goals associated to costs, time, scope, and schedule.
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | June 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1344 6.CONCLUSION The methods to classify project risks, that have been particularized for construction projects, have been presented from various point of view from construction companies and firms that may be helping the development of dealing with project in the planning and construction stages. The project has studied various factors related to risks and some of outcomes are listed below: • The risks management process starts prior to project itself. • There must be proper coordination between every distinct involved with project to implement better risk management practices. • Record of all the risk occurred and occurring, occurs in future should be maintained. • Every organization big or small should be adopt risk management practices to reduce effect of risks arising in the project and its impact to reach the project goals. • The project should be properly scheduled and monitored. • Clear understanding of the project scope explaining of the complete outcome of project. • Repetitively changes in design should be avoided in the projects. • Wages of the workers should not be delayed. • Procurement of materials should be timely on site. From the results, it is safe to say that majority of the construction projects have no systematic procedure in place to deal with risks. Risk management is done in a very informal mode.. 7.REFERENCES [1] Agnieszka Dziadoz, Mariusz Rejment “Risk analysis in construction projects-chosen method”, operational research in sustainable development and civil engineering – meeting of euro working group and 15th German-Lithunain- polish colloquium(ORSDE2015), PP 258-265. [2] Absulmaten Taroun, “Towards a better modeling and assessment of construction risk”, Journal of Civil Engineering Research 2014, 4(2A),volume 32, PP 101-105. [3] Ana I, Irimia-Dieguez, Alvaro sanchez-carzola, Rafaela alfalla-luque “Risk management in megaprojects”, science direct procedia – social and behavioral sciences, vol.119 (2014), PP 407-416. [4] He Zhi “Risk management for overseas project management”, International Journal of Project Management,Volume 13, PP 231-237. [5] J.G Perry, R.W. Hayes “Risk management in construction projects”, Asia-Pacific Journal of Management Research and Innovation, Volume: 7, issue: 3, Article first published online: July 1, 2011; Issue published: July 1, 2011, PP: 107-120. [6] Kinnaresh Patel “A study on risk assessment and its management in India”,American Journal of Civil Engineering. Vol. No 1, Vol. No. 2, 2013, PP. 64-67. [7] M.J. Mawdesley “Perception of human risk factors in construction projects: An exploratory study”, Article in International Journal of Project Management22(2):131137, February 2004, volume 22, PP 131-137. [8] Pattel Ankit Mahendra Et.Cl “Risk analysis in construction projects - chosen methods”, Internet source.