SlideShare a Scribd company logo
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1639
Risk Management of Construction Projects by using Primavera Risk
Analysis
Mhetre K.V.1, Wagh Y.D.2, Bhujbal A.D.3, Patil S.M.4, Ranaware A.N.5
1Professor,Department of Civil Engineering, APCOER, Pune,Maharashtra, india
2,3,4,5 B.E. Undergraduate,Department of Civil Engineering, APCOER, Pune,Maharashtra, india
---------------------------------------------------------------------***----------------------------------------------------------
Abstract – In Indian construction industries like
resedential, commercial, educational,etcrisk isthemain factor
that can affects the period of construction of any work and
main cause for delay of construction work. In primavera risk
analysis software (PRA) risk are analyzed like financial risk,
environmental risk, ,material risk, labour risk, political risk,
etc. Scheduling is done properly by risk management to
obtaining the required time for contruction project and
probability of start and finish date of construction project by
Primavera Risk Analysis software.
Key Words: Risk management, project management,
Primavera software, Analysis.
1.INTRODUCTION
The risk are analysed by risk management software process
by using primavera risk analysis. The risk management
process firstly starts with the identification of risksfollowed
by their analysis, response and monitoring.Risk isdefinedas
an uncertainty of outcome, whether positive opportunity or
negative threat, of actions and events. The risk has to be
assessed in respect of the combination of the likelihood of
something happening, and the impact which arises if it does
actually happen. Non availibility of labours, funds and
weather conditions are the common risks.And the political,
environmental, etc.are the types of risks. We calculate the
period of construction by this risk analysis process by using
primavera risk analysis software and give 90% assurance
about duration of construction project.
1.1 FUTURE SCOPE
The schedule can also be loaded with cost parameters in the
PRA, which can be useful for economic or financial analysis
of project. In this current study only the time factor was
considered for the analysis. The same study can be
performed with cost parameters.
1.2 LIMITATION OF STUDY
The result obtained by this study are in terms of probability.
So, the limitation is it does not give 100% guarantee about
the expected results i.e; it is probabilistic approach.
2. LITERATURE REVIEW
Mohamed A Aderbag and Mohamad A Sherif (2018)
stated that in order tocarry the process perfectly,anefficient
program tool was used called the PERT-Master Primevera
risk analysis tool. By using informationgatheringtechniques
a total number of fourty four risk events related to different
risk categories were identified by the end of risk
identification process.
Danish Ali and Alvin Harison(2016) stated that the risk
management concept is essential in reducing losses. They
also includes safety management and occupational risks are
important parts of construction. Construction risks are
playing important role for construction contractor.
Mohammed Zaki Haider, Rajendra.S and Vijay.K.(2016)
indentified that the oracle primavera P6 web logic is highly
advance compare to primavera standard Oracle primavera
alone P6 in terms of planning, scheduling, and tracking for
any company project.
Divya Gupta, Manoj Sharma and Dr. Ashutosh Shankar
Trivedi(2015) suggested that risk management in the
construction project management context is a
comprehensive and systematic way ofidentifying,analyzing
and responding to risks to achieve the project objectives.
Divyang Solanki1 J.D.Raol (2015) found that using this
software we conclude that hatever work is going on if it is
collected in particular format we can easily identify the
problem among that and find alternatives.
X. Regina Mary and V.Rathinakumar (2015) stated
thatschedule made by using techniques that reduce the
constraints helps for the project to complete earlieroffive to
seven months from the actual base schedule of the project
and thereby increase the profit outcome from the project.
Joseph Ignatius Teye Buertey (2014) concluded that the
major risk factors affects the cost of construction. They said
that level of knowledge and the application of risk in work is
limited.Since this resesrch paper is not challenges in
estimation of cost of the construction project.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1640
Dr. Haitham H. Al-Shibly,Dr. Basem M. Louzi and
Mohammad A. Hiassat (2013) identified that o
management therisk effectively and efficiently, the
contractor must understand risk responsibilities, risk event
conditions, risk preference, and risk management
capabilities.
Satish K. Kamane and Sandip A. Mahadik(2013) found
that it may bestated that risk Management is the core of
project management. The success of every project depends
on how efficiently and effectively the Risk avoidance may
include a review of the overall project objectivesleadingtoa
reappraisal of the project as a whole.
Pethe S. And Adavi P.,(2013), suggested that project
management concepts are no longer theoretical buthave got
converted to technology drivenmeans.Therearesomemore
parameters of Primavera such as primavera architecture,
calendars, scheduling, work breakdown structure, resource
assigning, its analysis andleveling,updating, etc.Buthere we
have discussed the major parameters which affect the
construction industry in a far bigger way.
Belu Nadia, Anghel Daniel Constantin and Iliesorin
(2010) concluded that Primavera software products
management needs of organizations that manage large
numbers of project at one time. These integrated
applications use project management to support the
management needs of project teams in different locations
and at varying levels of the organization.
Ehsan N. and Alam M. ,(2010), suggested that formal risk
analysis and management techniques are rarely employed
by Pakistani construction industry owing to the lack of
experience and knowledge in the area. The industry also
holds disbelief that these techniques are suitable to be
employed in construction projects, much in the same
manner as employed in other industries.
3.OBJECTIVES
1.To prepare construction schedule for selected plan.
2.To assign uncertainity in the schedule prepared.
3.To perform simulation in order to get expectedduration of
the project.
4.To compare the result obtained in simulation with PERT
calculations.
5. To conclude on period of completion of construction of
project with the help of PRA.
4.METHODOLOGY
Fig.1: Flowchart
4.1 Selection of Plan
Identify Risks is the process of determining which risks may
affect the project and documenting their characteristics.
Identify risks is an iterative process, because new risks may
evolve or become known as the project progresses through
its life cycle.
4.2 Scheduled Preparation
Actual schedule preparation process starts with the
collection of data like project start date,activitiesinvolved in
the construction of Any structural activities sequences,
duration taken for each and every activities, resources
needed for each and every activities and its amount, cost
spent for each and every activities. The collected data are
entered in the software and therelations between the
activities are given as per its sequence of activities collected.
4.3 Duration Estimation
Quantitative risk analysis is the process of numerically
analyzing the effect of identified risks on overall project
objectives using modeling and simulation. By analyzing the
risk and scheduling we calculate the cost of the execution
work and expected period for the construction work of the
project.
4.4 Uncertainty / Risk Assignment
The effective development of infrastructure through
construction is issue of growing concern satisfaction and
study. One of the challenges to optimum construction is risk
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1641
and uncertainty that project face, due to evaluating and
immerging condition through the project lifecycles,
organization and environment. By analyzing the risk and
uncertainties we evaluate the effects on cost and duration of
construction work.
4.5 Simulation
Simulations are typically performedusingthePERTandPRA
technique in a simulation, the project model is computed
many times (iterated), with the input values (e.g., cost
estimates or activity durations) chosen at random for each
iteration from the probability distributions of these
variables. A histogram (e.g., total cost or completion date) is
calculated from the iterations.
5. RESULTS
After risk analysis in Primavera Softwere we obtained three
graphs as per follows:
5.1 Finish Date Graph: There is 35% probability to
complete construction project work in 55 days on
25/06/2019. 50% probability to complete construction
project work in 57 dayson27/06/2019and80%probability
to complete construction project work in 59 days on
29/06/2019. Therefore minimum possibility of completion
of work is on the date of 16/06/2019 and maximum
possibility of completion of work is on the date of
09/07/2019
Fig. 5.1 Finish Date Graph
5.2 Start Date Graph: To develop schedule risk model, we
used primavera risk analysis tool throughout importing the
original schedule ,the project starting in 02/05/2019 and it
is scheduled to be completed in 25/06/2019 (55working
days). There is 100% probability for Starting The work On
02/05/2019 date.
Fig 5.2 Start Date Graph
4.3 Duration Graph
There is 35% probability to complete construction project
work in 55 days on 25/06/2019, 50% probability to
complete construction project work in 57 days on
27/06/2019 and 80% probability to complete construction
project work in 59 days on 29/06/2019. Therefore
minimum 46 days required for complete construction
project work and maximum 69 days required for complete
construction project work
Fig 5.3 Duration Graph
6. CONCLUSIONS
1.You can predict the time required for any construction
project by using Primavera Risk Analysis.
2.By reffering to results of Primavera Risk Analysis, we can
assign the alternative activities. This will help in covering
the delay caused in the overall project.
3.The iterations is limited to 10000 only. This is not suitable
for large scale project in order to get accuracy in Risk
Analysis.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1642
REFERENCES
1. Ali D And Harison A, (2016), “Risk ManagementStrategies
In Construction Companies In India”,IJIRST,2(10),6-8.
2. Bodla B.S,(2013), “Financial Risk Management in India-
Evidence from Literature Review”, SDIMT,1(1), 7-15.
3. Ganame P and Chaudhari P,(2015),“ConstructionBuilding
Schedule Risk Analysis Using Monte-Carlo Simulation”,
IRJET,2(4),1402-1406.
4. Gupta, D.,Sharma,M. and Trivedi A.S,(2015), “Risk
Management In Construction Projects Of Developing
Countries”,ISSN,5(11),154-156.
5. Joseph Ignatius Teye Buertey,(2014), “Project Cost Risk
And Uncertainties: Towards A Concept Towards A
Conceptual Cost Contingency Estimation
Model”,IJRET,3(5),33-36.
6. Kamane S.K. And Mahadik S.A., (2013), “Risk Management
In Construction Industry”, IOSR, 4(6),59-65.
7. Kumar D.A., Rajeev A.S. and Dr. Narayan G,(2017),
“Analysis Of Risk Management In Residential Building Using
Primavera Web Software”, IJARIIE,3(4),204-207.
8. Mary.X.R. And Rathinakumar V, (2015), “Reducing
Construction Constraints Using Primavera”, IJOSAT, 8
(14)1,1-7.
9. Mhetre, K.V.,(2017), “Risk Analysis With The Use Of
Primavera Risk Analysis”,2(9),8-10.
10. Mohamed A. A. Saber K.EAndMohamedA.S,(2018),“Risk
Analysis Related To Costing And Scheduling Of Construction
Projects”,POICOIE,6(8).
11. Nadia B And Daniel A,(2010),“ProjectManagementUsing
Primavera For Enterprise System”,Fomate,9(19), 17-21.
12. Solanki D. And Raol J.D, (2015), “Minimize The
Fluctuation In Labour Productivity Using Primavera
P6”,IJSRD, 3(04),25-27.
13. Zakihaider M.,Rajendra.S,And Vijay.K,(2016), “Planning
Scheduling, Tracking And Application Administration Using
Primavera Web Logic P6”,IJRET,5(7),151-157.
14. Mubarak, Saleh, (2015), “Schedule Risk Management
Construction Project Scheduling And Control”, 3rd edition,
John Wiley and Sons, Canada,367-390.

More Related Content

What's hot

IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET Journal
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSvivatechijri
 
risk management: a better approach
risk management: a better approachrisk management: a better approach
risk management: a better approachMadhumanti Samaddar
 
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET Journal
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential SectorIRJET Journal
 
Analysis, perception and aspects of risk management in the construction secto...
Analysis, perception and aspects of risk management in the construction secto...Analysis, perception and aspects of risk management in the construction secto...
Analysis, perception and aspects of risk management in the construction secto...Alexander Decker
 
A STUDY ON THE IMPLEMENTATION OF PRE- CONSTRUCTION HEALTH AND SAFETY PLANNING...
A STUDY ON THE IMPLEMENTATION OF PRE- CONSTRUCTION HEALTH AND SAFETY PLANNING...A STUDY ON THE IMPLEMENTATION OF PRE- CONSTRUCTION HEALTH AND SAFETY PLANNING...
A STUDY ON THE IMPLEMENTATION OF PRE- CONSTRUCTION HEALTH AND SAFETY PLANNING...AM Publications
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET Journal
 
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...
IRJET- A Review Paper on Risk Management using Primavera for Residential ...IRJET Journal
 
Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...IJLT EMAS
 
A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...eSAT Journals
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassanOyeniyi Samuel
 
Earned Value Management for Design and Construction Project
Earned Value Management for Design and Construction ProjectEarned Value Management for Design and Construction Project
Earned Value Management for Design and Construction Projectijtsrd
 
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...IJSRED
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET Journal
 
2.11 risk management 1
2.11 risk management 12.11 risk management 1
2.11 risk management 1reddvise
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectIRJET Journal
 
Reasons for Delaying the Constriction Projects in Iraq
Reasons for Delaying the Constriction Projects in IraqReasons for Delaying the Constriction Projects in Iraq
Reasons for Delaying the Constriction Projects in IraqDr. Amarjeet Singh
 
Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...eSAT Journals
 

What's hot (20)

IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
 
risk management: a better approach
risk management: a better approachrisk management: a better approach
risk management: a better approach
 
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential Sector
 
Analysis, perception and aspects of risk management in the construction secto...
Analysis, perception and aspects of risk management in the construction secto...Analysis, perception and aspects of risk management in the construction secto...
Analysis, perception and aspects of risk management in the construction secto...
 
A STUDY ON THE IMPLEMENTATION OF PRE- CONSTRUCTION HEALTH AND SAFETY PLANNING...
A STUDY ON THE IMPLEMENTATION OF PRE- CONSTRUCTION HEALTH AND SAFETY PLANNING...A STUDY ON THE IMPLEMENTATION OF PRE- CONSTRUCTION HEALTH AND SAFETY PLANNING...
A STUDY ON THE IMPLEMENTATION OF PRE- CONSTRUCTION HEALTH AND SAFETY PLANNING...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
 
Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...
 
A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan
 
Earned Value Management for Design and Construction Project
Earned Value Management for Design and Construction ProjectEarned Value Management for Design and Construction Project
Earned Value Management for Design and Construction Project
 
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
Project risk management
Project risk managementProject risk management
Project risk management
 
2.11 risk management 1
2.11 risk management 12.11 risk management 1
2.11 risk management 1
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 
Reasons for Delaying the Constriction Projects in Iraq
Reasons for Delaying the Constriction Projects in IraqReasons for Delaying the Constriction Projects in Iraq
Reasons for Delaying the Constriction Projects in Iraq
 
Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...
 

Similar to IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis

IRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET Journal
 
Health and Safety Framework Using Analytic Hierarchy Process For Construction...
Health and Safety Framework Using Analytic Hierarchy Process For Construction...Health and Safety Framework Using Analytic Hierarchy Process For Construction...
Health and Safety Framework Using Analytic Hierarchy Process For Construction...IRJET Journal
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSIRJET Journal
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSIRJET Journal
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET Journal
 
Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsIRJET Journal
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET Journal
 
IRJET- Redevelopment of Structure with the Help of Building Information M...
IRJET-  	  Redevelopment of Structure with the Help of Building Information M...IRJET-  	  Redevelopment of Structure with the Help of Building Information M...
IRJET- Redevelopment of Structure with the Help of Building Information M...IRJET Journal
 
Risk Management in Retrofitting Projects
Risk Management in Retrofitting ProjectsRisk Management in Retrofitting Projects
Risk Management in Retrofitting ProjectsIRJET Journal
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsIRJET Journal
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET Journal
 
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET Journal
 
risks-07-00024.pdf
risks-07-00024.pdfrisks-07-00024.pdf
risks-07-00024.pdfRidaShahid36
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET Journal
 
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET Journal
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...IRJET Journal
 
IRJET- The Health and Safety Management Performance of Construction Smes i...
IRJET- 	  The Health and Safety Management Performance of Construction Smes i...IRJET- 	  The Health and Safety Management Performance of Construction Smes i...
IRJET- The Health and Safety Management Performance of Construction Smes i...IRJET Journal
 
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET Journal
 

Similar to IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis (20)

IRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera Software
 
Health and Safety Framework Using Analytic Hierarchy Process For Construction...
Health and Safety Framework Using Analytic Hierarchy Process For Construction...Health and Safety Framework Using Analytic Hierarchy Process For Construction...
Health and Safety Framework Using Analytic Hierarchy Process For Construction...
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
 
Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction Projects
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature Review
 
IRJET- Redevelopment of Structure with the Help of Building Information M...
IRJET-  	  Redevelopment of Structure with the Help of Building Information M...IRJET-  	  Redevelopment of Structure with the Help of Building Information M...
IRJET- Redevelopment of Structure with the Help of Building Information M...
 
Risk Management in Retrofitting Projects
Risk Management in Retrofitting ProjectsRisk Management in Retrofitting Projects
Risk Management in Retrofitting Projects
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction Projects
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
 
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...
 
risks-07-00024.pdf
risks-07-00024.pdfrisks-07-00024.pdf
risks-07-00024.pdf
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
 
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
 
IRJET- The Health and Safety Management Performance of Construction Smes i...
IRJET- 	  The Health and Safety Management Performance of Construction Smes i...IRJET- 	  The Health and Safety Management Performance of Construction Smes i...
IRJET- The Health and Safety Management Performance of Construction Smes i...
 
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
IRJET- Risk Modelling in Highway Construction Project using Regression and Fa...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Explosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdfExplosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdf884710SadaqatAli
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopEmre Günaydın
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234AafreenAbuthahir2
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...Amil baba
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxMd. Shahidul Islam Prodhan
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfKamal Acharya
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Aryaabh.arya
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdfKamal Acharya
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfPipe Restoration Solutions
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdfKamal Acharya
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdfKamal Acharya
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdfKamal Acharya
 
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfDanfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfNurvisNavarroSanchez
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfKamal Acharya
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Krakówbim.edu.pl
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdffxintegritypublishin
 
Antenna efficency lecture course chapter 3.pdf
Antenna  efficency lecture course chapter 3.pdfAntenna  efficency lecture course chapter 3.pdf
Antenna efficency lecture course chapter 3.pdfAbrahamGadissa
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
 

Recently uploaded (20)

Explosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdfExplosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdf
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Fruit shop management system project report.pdf
Fruit shop management system project report.pdfFruit shop management system project report.pdf
Fruit shop management system project report.pdf
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfDanfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Kraków
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Antenna efficency lecture course chapter 3.pdf
Antenna  efficency lecture course chapter 3.pdfAntenna  efficency lecture course chapter 3.pdf
Antenna efficency lecture course chapter 3.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 

IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1639 Risk Management of Construction Projects by using Primavera Risk Analysis Mhetre K.V.1, Wagh Y.D.2, Bhujbal A.D.3, Patil S.M.4, Ranaware A.N.5 1Professor,Department of Civil Engineering, APCOER, Pune,Maharashtra, india 2,3,4,5 B.E. Undergraduate,Department of Civil Engineering, APCOER, Pune,Maharashtra, india ---------------------------------------------------------------------***---------------------------------------------------------- Abstract – In Indian construction industries like resedential, commercial, educational,etcrisk isthemain factor that can affects the period of construction of any work and main cause for delay of construction work. In primavera risk analysis software (PRA) risk are analyzed like financial risk, environmental risk, ,material risk, labour risk, political risk, etc. Scheduling is done properly by risk management to obtaining the required time for contruction project and probability of start and finish date of construction project by Primavera Risk Analysis software. Key Words: Risk management, project management, Primavera software, Analysis. 1.INTRODUCTION The risk are analysed by risk management software process by using primavera risk analysis. The risk management process firstly starts with the identification of risksfollowed by their analysis, response and monitoring.Risk isdefinedas an uncertainty of outcome, whether positive opportunity or negative threat, of actions and events. The risk has to be assessed in respect of the combination of the likelihood of something happening, and the impact which arises if it does actually happen. Non availibility of labours, funds and weather conditions are the common risks.And the political, environmental, etc.are the types of risks. We calculate the period of construction by this risk analysis process by using primavera risk analysis software and give 90% assurance about duration of construction project. 1.1 FUTURE SCOPE The schedule can also be loaded with cost parameters in the PRA, which can be useful for economic or financial analysis of project. In this current study only the time factor was considered for the analysis. The same study can be performed with cost parameters. 1.2 LIMITATION OF STUDY The result obtained by this study are in terms of probability. So, the limitation is it does not give 100% guarantee about the expected results i.e; it is probabilistic approach. 2. LITERATURE REVIEW Mohamed A Aderbag and Mohamad A Sherif (2018) stated that in order tocarry the process perfectly,anefficient program tool was used called the PERT-Master Primevera risk analysis tool. By using informationgatheringtechniques a total number of fourty four risk events related to different risk categories were identified by the end of risk identification process. Danish Ali and Alvin Harison(2016) stated that the risk management concept is essential in reducing losses. They also includes safety management and occupational risks are important parts of construction. Construction risks are playing important role for construction contractor. Mohammed Zaki Haider, Rajendra.S and Vijay.K.(2016) indentified that the oracle primavera P6 web logic is highly advance compare to primavera standard Oracle primavera alone P6 in terms of planning, scheduling, and tracking for any company project. Divya Gupta, Manoj Sharma and Dr. Ashutosh Shankar Trivedi(2015) suggested that risk management in the construction project management context is a comprehensive and systematic way ofidentifying,analyzing and responding to risks to achieve the project objectives. Divyang Solanki1 J.D.Raol (2015) found that using this software we conclude that hatever work is going on if it is collected in particular format we can easily identify the problem among that and find alternatives. X. Regina Mary and V.Rathinakumar (2015) stated thatschedule made by using techniques that reduce the constraints helps for the project to complete earlieroffive to seven months from the actual base schedule of the project and thereby increase the profit outcome from the project. Joseph Ignatius Teye Buertey (2014) concluded that the major risk factors affects the cost of construction. They said that level of knowledge and the application of risk in work is limited.Since this resesrch paper is not challenges in estimation of cost of the construction project.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1640 Dr. Haitham H. Al-Shibly,Dr. Basem M. Louzi and Mohammad A. Hiassat (2013) identified that o management therisk effectively and efficiently, the contractor must understand risk responsibilities, risk event conditions, risk preference, and risk management capabilities. Satish K. Kamane and Sandip A. Mahadik(2013) found that it may bestated that risk Management is the core of project management. The success of every project depends on how efficiently and effectively the Risk avoidance may include a review of the overall project objectivesleadingtoa reappraisal of the project as a whole. Pethe S. And Adavi P.,(2013), suggested that project management concepts are no longer theoretical buthave got converted to technology drivenmeans.Therearesomemore parameters of Primavera such as primavera architecture, calendars, scheduling, work breakdown structure, resource assigning, its analysis andleveling,updating, etc.Buthere we have discussed the major parameters which affect the construction industry in a far bigger way. Belu Nadia, Anghel Daniel Constantin and Iliesorin (2010) concluded that Primavera software products management needs of organizations that manage large numbers of project at one time. These integrated applications use project management to support the management needs of project teams in different locations and at varying levels of the organization. Ehsan N. and Alam M. ,(2010), suggested that formal risk analysis and management techniques are rarely employed by Pakistani construction industry owing to the lack of experience and knowledge in the area. The industry also holds disbelief that these techniques are suitable to be employed in construction projects, much in the same manner as employed in other industries. 3.OBJECTIVES 1.To prepare construction schedule for selected plan. 2.To assign uncertainity in the schedule prepared. 3.To perform simulation in order to get expectedduration of the project. 4.To compare the result obtained in simulation with PERT calculations. 5. To conclude on period of completion of construction of project with the help of PRA. 4.METHODOLOGY Fig.1: Flowchart 4.1 Selection of Plan Identify Risks is the process of determining which risks may affect the project and documenting their characteristics. Identify risks is an iterative process, because new risks may evolve or become known as the project progresses through its life cycle. 4.2 Scheduled Preparation Actual schedule preparation process starts with the collection of data like project start date,activitiesinvolved in the construction of Any structural activities sequences, duration taken for each and every activities, resources needed for each and every activities and its amount, cost spent for each and every activities. The collected data are entered in the software and therelations between the activities are given as per its sequence of activities collected. 4.3 Duration Estimation Quantitative risk analysis is the process of numerically analyzing the effect of identified risks on overall project objectives using modeling and simulation. By analyzing the risk and scheduling we calculate the cost of the execution work and expected period for the construction work of the project. 4.4 Uncertainty / Risk Assignment The effective development of infrastructure through construction is issue of growing concern satisfaction and study. One of the challenges to optimum construction is risk
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1641 and uncertainty that project face, due to evaluating and immerging condition through the project lifecycles, organization and environment. By analyzing the risk and uncertainties we evaluate the effects on cost and duration of construction work. 4.5 Simulation Simulations are typically performedusingthePERTandPRA technique in a simulation, the project model is computed many times (iterated), with the input values (e.g., cost estimates or activity durations) chosen at random for each iteration from the probability distributions of these variables. A histogram (e.g., total cost or completion date) is calculated from the iterations. 5. RESULTS After risk analysis in Primavera Softwere we obtained three graphs as per follows: 5.1 Finish Date Graph: There is 35% probability to complete construction project work in 55 days on 25/06/2019. 50% probability to complete construction project work in 57 dayson27/06/2019and80%probability to complete construction project work in 59 days on 29/06/2019. Therefore minimum possibility of completion of work is on the date of 16/06/2019 and maximum possibility of completion of work is on the date of 09/07/2019 Fig. 5.1 Finish Date Graph 5.2 Start Date Graph: To develop schedule risk model, we used primavera risk analysis tool throughout importing the original schedule ,the project starting in 02/05/2019 and it is scheduled to be completed in 25/06/2019 (55working days). There is 100% probability for Starting The work On 02/05/2019 date. Fig 5.2 Start Date Graph 4.3 Duration Graph There is 35% probability to complete construction project work in 55 days on 25/06/2019, 50% probability to complete construction project work in 57 days on 27/06/2019 and 80% probability to complete construction project work in 59 days on 29/06/2019. Therefore minimum 46 days required for complete construction project work and maximum 69 days required for complete construction project work Fig 5.3 Duration Graph 6. CONCLUSIONS 1.You can predict the time required for any construction project by using Primavera Risk Analysis. 2.By reffering to results of Primavera Risk Analysis, we can assign the alternative activities. This will help in covering the delay caused in the overall project. 3.The iterations is limited to 10000 only. This is not suitable for large scale project in order to get accuracy in Risk Analysis.
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1642 REFERENCES 1. Ali D And Harison A, (2016), “Risk ManagementStrategies In Construction Companies In India”,IJIRST,2(10),6-8. 2. Bodla B.S,(2013), “Financial Risk Management in India- Evidence from Literature Review”, SDIMT,1(1), 7-15. 3. Ganame P and Chaudhari P,(2015),“ConstructionBuilding Schedule Risk Analysis Using Monte-Carlo Simulation”, IRJET,2(4),1402-1406. 4. Gupta, D.,Sharma,M. and Trivedi A.S,(2015), “Risk Management In Construction Projects Of Developing Countries”,ISSN,5(11),154-156. 5. Joseph Ignatius Teye Buertey,(2014), “Project Cost Risk And Uncertainties: Towards A Concept Towards A Conceptual Cost Contingency Estimation Model”,IJRET,3(5),33-36. 6. Kamane S.K. And Mahadik S.A., (2013), “Risk Management In Construction Industry”, IOSR, 4(6),59-65. 7. Kumar D.A., Rajeev A.S. and Dr. Narayan G,(2017), “Analysis Of Risk Management In Residential Building Using Primavera Web Software”, IJARIIE,3(4),204-207. 8. Mary.X.R. And Rathinakumar V, (2015), “Reducing Construction Constraints Using Primavera”, IJOSAT, 8 (14)1,1-7. 9. Mhetre, K.V.,(2017), “Risk Analysis With The Use Of Primavera Risk Analysis”,2(9),8-10. 10. Mohamed A. A. Saber K.EAndMohamedA.S,(2018),“Risk Analysis Related To Costing And Scheduling Of Construction Projects”,POICOIE,6(8). 11. Nadia B And Daniel A,(2010),“ProjectManagementUsing Primavera For Enterprise System”,Fomate,9(19), 17-21. 12. Solanki D. And Raol J.D, (2015), “Minimize The Fluctuation In Labour Productivity Using Primavera P6”,IJSRD, 3(04),25-27. 13. Zakihaider M.,Rajendra.S,And Vijay.K,(2016), “Planning Scheduling, Tracking And Application Administration Using Primavera Web Logic P6”,IJRET,5(7),151-157. 14. Mubarak, Saleh, (2015), “Schedule Risk Management Construction Project Scheduling And Control”, 3rd edition, John Wiley and Sons, Canada,367-390.