SlideShare a Scribd company logo
Probabilistic Activity Times
Probabilistic Time Estimates
Carrine Kezia Aulia :: 102183022
• Single time estimates
• Didn’t allow for any variation
• AT treated as if they are known for
certain
COMPARISON CPM AND
PERTREVIEW
• Multiple time estimates
• Allow for any variation
• AT treated as probabilistic
PERT uses probabilistic activity times
CPM PERT
Approach to estimating activity times
WHAT IS PROBABILISTIC ACTIVITY
TIMES?What’s it all about?
• Completion time estimates can be estimated using the
Three Time EstimateThree Time Estimate approachapproach
• In this approach, three time estimates are required for each activity
MOST LIKELY TIME (m)
THREE TIME ESTIMATES
OPTIMISTIC TIME (a)
PESSIMISTIC TIME (b)
1
2
3
most frequently occur if the activity were
repeated many times
the shortest possible time to complete the
activity if everything went right
the longest possible time to complete the
activity if everything went wrong
with THREE TIME estimates, the activity completion
time
can be approximated by a BETA DISTRIBUTION
BETA DISTRIBUTION
BETA DISTRIBUTIONS CAN COME IN A VARIETY OF SHAPES :
FORMULA
MEAN AND VARIANCE
a + 4m + b
6
b - a
6
2
mean (expected time)
variance σ2
t
MOST LIKELY TIME (m)
OPTIMISTIC TIME (a)
PESSIMISTIC TIME (b)
EXAMPLEA PROJECT NETWORK WITH PROBABILISTIC TIME ESTIMATE
EXAMPLEACTIVITY TIME ESTIMATES
a + 4m + b
6
b - a
6
2
t σ2
EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK
EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK
0
8
8 8
5
13
0
6
6
3
0 3
3
6 9
4
3 7
2
3 5
7
9 16
4
9 13
4
13 17
9
16 25
2516
2521
2116
169
1612
1614
95
52
9660
91
EXPECTED TIME : 25
CRITICAL PATH :
2-5-8-11
EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK
25
WEEKS
6,89
WEEKS
EXAMPLEPROBABILISTIC ANALYSIS OF THE PROJECT NETWORK
ADD ALL THE σ2
OFF THE CRITICAL
PATH
S
D
what does this formula means?
what does these numbers mean?
EXAMPLEPROBABILISTIC ANALYSIS OF THE PROJECT NETWORK
25
WEEKS
6,89
WEEKS
2,62
WEEKS
EXPECTED TIME
μ
σ2
σ
EXAMPLEPROBABILISTIC ANALYSIS OF THE PROJECT NETWORK
25
WEEKS
EXPECTED TIME
μ
30
WEEKS
PROPOSED PROJECT TIME
X WHAT IS THE
PROBABILITY THAT
THE SYSTEM WILL BE
READY BY THAT
TIME?
WHAT IS THE
PROBABILITY THAT
THE SYSTEM WILL BE
READY BY THAT
TIME?
EXAMPLEPROBABILISTIC ANALYSIS OF THE PROJECT NETWORK
Z =
X – μ
σ
30
WEEKS
25
WEEKS
2.62
-
= 1.911.91
EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK
z = 1.91
EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK
EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK
0.9719
probability of completing
the project in 30 days
0.9719
probability of completing
the project in 30 days
EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK
www.measuringusability.com
EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK
z = 1.91
97.19 %
Probabilistic Activity Time

More Related Content

What's hot

Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
El Moro
 
How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)
Amr Morsy
 
crashing of project
crashing of project crashing of project
crashing of project
Mir Zafarullah
 
5. transportation problems
5. transportation problems5. transportation problems
5. transportation problems
Hakeem-Ur- Rehman
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
Ajeesh Mk
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM
Mubashir Ali
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
Naveed Salman
 
Bba 3274 qm week 6 part 2 forecasting
Bba 3274 qm week 6 part 2 forecastingBba 3274 qm week 6 part 2 forecasting
Bba 3274 qm week 6 part 2 forecasting
Stephen Ong
 
(Aoa) and (aon) networks
(Aoa) and (aon) networks(Aoa) and (aon) networks
(Aoa) and (aon) networks
Dr. Mahmoud Al-Naimi
 
352735340 rsh-qam11-tif-12-doc
352735340 rsh-qam11-tif-12-doc352735340 rsh-qam11-tif-12-doc
352735340 rsh-qam11-tif-12-doc
Firas Husseini
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptx
ssuser85ddaa
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
Zulfiquer Ahmed Amin
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...
Dr. Mahmoud Al-Naimi
 
Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
Kaizer Dave
 
PMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with AnswersPMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with Answers
Thanh Nguyen
 
Estimating Time & Costs
 Estimating Time & Costs Estimating Time & Costs
Estimating Time & Costs
mairemic
 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pert
DagnaygebawGoshme
 
Project Management CH9 Project Scheduling
Project Management CH9 Project SchedulingProject Management CH9 Project Scheduling
Project Management CH9 Project SchedulingIzah Asmadi
 

What's hot (20)

Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network Analysis- CPM ppt..pptx
 
How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)
 
crashing of project
crashing of project crashing of project
crashing of project
 
5. transportation problems
5. transportation problems5. transportation problems
5. transportation problems
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
Bba 3274 qm week 6 part 2 forecasting
Bba 3274 qm week 6 part 2 forecastingBba 3274 qm week 6 part 2 forecasting
Bba 3274 qm week 6 part 2 forecasting
 
(Aoa) and (aon) networks
(Aoa) and (aon) networks(Aoa) and (aon) networks
(Aoa) and (aon) networks
 
352735340 rsh-qam11-tif-12-doc
352735340 rsh-qam11-tif-12-doc352735340 rsh-qam11-tif-12-doc
352735340 rsh-qam11-tif-12-doc
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptx
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...
 
Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
 
PMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with AnswersPMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with Answers
 
Estimating Time & Costs
 Estimating Time & Costs Estimating Time & Costs
Estimating Time & Costs
 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pert
 
Project Management CH9 Project Scheduling
Project Management CH9 Project SchedulingProject Management CH9 Project Scheduling
Project Management CH9 Project Scheduling
 

Viewers also liked

3.time management
3.time management3.time management
3.time management
Panos Fitsilis
 
Building Brand Equity with Environmental Communication
Building Brand Equity with Environmental CommunicationBuilding Brand Equity with Environmental Communication
Building Brand Equity with Environmental Communication
Carrine Aulia
 
Time and Motion Studies
Time and Motion StudiesTime and Motion Studies
Time and Motion Studies
Carrine Aulia
 
Financial statement, taxes, and cash flow
Financial statement, taxes, and cash flowFinancial statement, taxes, and cash flow
Financial statement, taxes, and cash flow
Carrine Aulia
 
RevoSport - Presentation r1-1
RevoSport - Presentation r1-1RevoSport - Presentation r1-1
RevoSport - Presentation r1-1Nasar Mohamed
 
Comparing Journal Articles
Comparing Journal ArticlesComparing Journal Articles
Comparing Journal Articles
Carrine Aulia
 
Team pathbreakers lifebuoy activation idea
Team pathbreakers lifebuoy activation ideaTeam pathbreakers lifebuoy activation idea
Team pathbreakers lifebuoy activation ideaSIMC Competitions
 
Public Relations Campaign for 50th Anniversary Commemoration
Public Relations Campaign for 50th Anniversary CommemorationPublic Relations Campaign for 50th Anniversary Commemoration
Public Relations Campaign for 50th Anniversary Commemoration
Abel Ahing
 
Tata Himalayan Natural Water Bottle_Enzo_Blitzkrieg
Tata Himalayan Natural Water Bottle_Enzo_BlitzkriegTata Himalayan Natural Water Bottle_Enzo_Blitzkrieg
Tata Himalayan Natural Water Bottle_Enzo_Blitzkrieg
SIMC Competitions
 
marketing strategy of PARLE G
marketing strategy of PARLE Gmarketing strategy of PARLE G
marketing strategy of PARLE GAnkita Kamble
 
Digital Lab SXSW Recap -- Trends in Social, Creative Technology, Production, ...
Digital Lab SXSW Recap -- Trends in Social, Creative Technology, Production, ...Digital Lab SXSW Recap -- Trends in Social, Creative Technology, Production, ...
Digital Lab SXSW Recap -- Trends in Social, Creative Technology, Production, ...
BBDO
 
The Big Idea. Dead or Alive?
The Big Idea. Dead or Alive?The Big Idea. Dead or Alive?
The Big Idea. Dead or Alive?
edward boches
 
Dunkin Donuts India - Event & Activation Strategy Idea
Dunkin Donuts India - Event & Activation Strategy IdeaDunkin Donuts India - Event & Activation Strategy Idea
Dunkin Donuts India - Event & Activation Strategy Idea
Soumitra Roy
 
Toolmaker’s microscope(tmm)
Toolmaker’s microscope(tmm)Toolmaker’s microscope(tmm)
Toolmaker’s microscope(tmm)
Venkat Vijay Kumar Pentapati
 
The seagulls parleagrobailley
The seagulls parleagrobailleyThe seagulls parleagrobailley
The seagulls parleagrobailleySIMC Competitions
 
Absenteeism, Turn Over and Retention
Absenteeism, Turn Over and RetentionAbsenteeism, Turn Over and Retention
Absenteeism, Turn Over and Retention
Carrine Aulia
 
Zara - Study Case
Zara - Study CaseZara - Study Case
Zara - Study Case
Carrine Aulia
 
We Are Social's Guide To Building A Connected Strategy
We Are Social's Guide To Building A Connected StrategyWe Are Social's Guide To Building A Connected Strategy
We Are Social's Guide To Building A Connected Strategy
We Are Social Singapore
 

Viewers also liked (20)

Comparing Rates
Comparing RatesComparing Rates
Comparing Rates
 
3.time management
3.time management3.time management
3.time management
 
Building Brand Equity with Environmental Communication
Building Brand Equity with Environmental CommunicationBuilding Brand Equity with Environmental Communication
Building Brand Equity with Environmental Communication
 
Time and Motion Studies
Time and Motion StudiesTime and Motion Studies
Time and Motion Studies
 
Financial statement, taxes, and cash flow
Financial statement, taxes, and cash flowFinancial statement, taxes, and cash flow
Financial statement, taxes, and cash flow
 
RevoSport - Presentation r1-1
RevoSport - Presentation r1-1RevoSport - Presentation r1-1
RevoSport - Presentation r1-1
 
Comparing Journal Articles
Comparing Journal ArticlesComparing Journal Articles
Comparing Journal Articles
 
Team pathbreakers lifebuoy activation idea
Team pathbreakers lifebuoy activation ideaTeam pathbreakers lifebuoy activation idea
Team pathbreakers lifebuoy activation idea
 
Public Relations Campaign for 50th Anniversary Commemoration
Public Relations Campaign for 50th Anniversary CommemorationPublic Relations Campaign for 50th Anniversary Commemoration
Public Relations Campaign for 50th Anniversary Commemoration
 
ASEAN
ASEANASEAN
ASEAN
 
Tata Himalayan Natural Water Bottle_Enzo_Blitzkrieg
Tata Himalayan Natural Water Bottle_Enzo_BlitzkriegTata Himalayan Natural Water Bottle_Enzo_Blitzkrieg
Tata Himalayan Natural Water Bottle_Enzo_Blitzkrieg
 
marketing strategy of PARLE G
marketing strategy of PARLE Gmarketing strategy of PARLE G
marketing strategy of PARLE G
 
Digital Lab SXSW Recap -- Trends in Social, Creative Technology, Production, ...
Digital Lab SXSW Recap -- Trends in Social, Creative Technology, Production, ...Digital Lab SXSW Recap -- Trends in Social, Creative Technology, Production, ...
Digital Lab SXSW Recap -- Trends in Social, Creative Technology, Production, ...
 
The Big Idea. Dead or Alive?
The Big Idea. Dead or Alive?The Big Idea. Dead or Alive?
The Big Idea. Dead or Alive?
 
Dunkin Donuts India - Event & Activation Strategy Idea
Dunkin Donuts India - Event & Activation Strategy IdeaDunkin Donuts India - Event & Activation Strategy Idea
Dunkin Donuts India - Event & Activation Strategy Idea
 
Toolmaker’s microscope(tmm)
Toolmaker’s microscope(tmm)Toolmaker’s microscope(tmm)
Toolmaker’s microscope(tmm)
 
The seagulls parleagrobailley
The seagulls parleagrobailleyThe seagulls parleagrobailley
The seagulls parleagrobailley
 
Absenteeism, Turn Over and Retention
Absenteeism, Turn Over and RetentionAbsenteeism, Turn Over and Retention
Absenteeism, Turn Over and Retention
 
Zara - Study Case
Zara - Study CaseZara - Study Case
Zara - Study Case
 
We Are Social's Guide To Building A Connected Strategy
We Are Social's Guide To Building A Connected StrategyWe Are Social's Guide To Building A Connected Strategy
We Are Social's Guide To Building A Connected Strategy
 

Similar to Probabilistic Activity Time

chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.ppt
DejeneDay
 
Ch 06 - CPM PERT (1).pptx
Ch 06 - CPM  PERT (1).pptxCh 06 - CPM  PERT (1).pptx
Ch 06 - CPM PERT (1).pptx
sitinorhafizabintiab1
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii reference
ahsanrabbani
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpasyamputra
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
BLESSY ALOSHIOUS
 
construction resource optimization 1.pptx
construction resource optimization 1.pptxconstruction resource optimization 1.pptx
construction resource optimization 1.pptx
kimkov119
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
Deepak Paithankar
 
PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
Snehal Athawale
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Pert
PertPert
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
Shashank Kapoor
 
Benchmarking Elastic Cloud Big Data Services under SLA Constraints
Benchmarking Elastic Cloud Big Data Services under SLA ConstraintsBenchmarking Elastic Cloud Big Data Services under SLA Constraints
Benchmarking Elastic Cloud Big Data Services under SLA Constraints
Nicolas Poggi
 
#NoEstimates project planning using Monte Carlo simulation
#NoEstimates project planning using Monte Carlo simulation#NoEstimates project planning using Monte Carlo simulation
#NoEstimates project planning using Monte Carlo simulation
Dimitar Bakardzhiev
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
salsa moyara
 
Sequence step algorithm repetitive project scheduling for project with probab...
Sequence step algorithm repetitive project scheduling for project with probab...Sequence step algorithm repetitive project scheduling for project with probab...
Sequence step algorithm repetitive project scheduling for project with probab...
Chachrist Srisuwanrat
 
Project management@ ppt doms
Project management@ ppt doms Project management@ ppt doms
Project management@ ppt doms
Babasab Patil
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
ShwetaMahdole
 
PERT
PERTPERT
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
Sachin Kapoor
 

Similar to Probabilistic Activity Time (20)

chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.ppt
 
Ch 06 - CPM PERT (1).pptx
Ch 06 - CPM  PERT (1).pptxCh 06 - CPM  PERT (1).pptx
Ch 06 - CPM PERT (1).pptx
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii reference
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpa
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
construction resource optimization 1.pptx
construction resource optimization 1.pptxconstruction resource optimization 1.pptx
construction resource optimization 1.pptx
 
Chap03
Chap03Chap03
Chap03
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Pert
PertPert
Pert
 
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
 
Benchmarking Elastic Cloud Big Data Services under SLA Constraints
Benchmarking Elastic Cloud Big Data Services under SLA ConstraintsBenchmarking Elastic Cloud Big Data Services under SLA Constraints
Benchmarking Elastic Cloud Big Data Services under SLA Constraints
 
#NoEstimates project planning using Monte Carlo simulation
#NoEstimates project planning using Monte Carlo simulation#NoEstimates project planning using Monte Carlo simulation
#NoEstimates project planning using Monte Carlo simulation
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Sequence step algorithm repetitive project scheduling for project with probab...
Sequence step algorithm repetitive project scheduling for project with probab...Sequence step algorithm repetitive project scheduling for project with probab...
Sequence step algorithm repetitive project scheduling for project with probab...
 
Project management@ ppt doms
Project management@ ppt doms Project management@ ppt doms
Project management@ ppt doms
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
 
PERT
PERTPERT
PERT
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 

More from Carrine Aulia

Articles, Ethical Standard, and Manuscript
Articles, Ethical Standard, and ManuscriptArticles, Ethical Standard, and Manuscript
Articles, Ethical Standard, and Manuscript
Carrine Aulia
 
Paper Presentation - Marketing Management
Paper Presentation - Marketing ManagementPaper Presentation - Marketing Management
Paper Presentation - Marketing Management
Carrine Aulia
 
Paper Presentation - Human Resources
Paper Presentation - Human ResourcesPaper Presentation - Human Resources
Paper Presentation - Human Resources
Carrine Aulia
 
Extended Pro Forma Statement
Extended Pro Forma StatementExtended Pro Forma Statement
Extended Pro Forma Statement
Carrine Aulia
 
American Management Style
American Management StyleAmerican Management Style
American Management Style
Carrine Aulia
 
Dove - Marketing Plan
Dove - Marketing PlanDove - Marketing Plan
Dove - Marketing Plan
Carrine Aulia
 

More from Carrine Aulia (7)

Articles, Ethical Standard, and Manuscript
Articles, Ethical Standard, and ManuscriptArticles, Ethical Standard, and Manuscript
Articles, Ethical Standard, and Manuscript
 
Paper Presentation - Marketing Management
Paper Presentation - Marketing ManagementPaper Presentation - Marketing Management
Paper Presentation - Marketing Management
 
Absenteeism
AbsenteeismAbsenteeism
Absenteeism
 
Paper Presentation - Human Resources
Paper Presentation - Human ResourcesPaper Presentation - Human Resources
Paper Presentation - Human Resources
 
Extended Pro Forma Statement
Extended Pro Forma StatementExtended Pro Forma Statement
Extended Pro Forma Statement
 
American Management Style
American Management StyleAmerican Management Style
American Management Style
 
Dove - Marketing Plan
Dove - Marketing PlanDove - Marketing Plan
Dove - Marketing Plan
 

Recently uploaded

一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
gcljeuzdu
 
Risk-Management-presentation for cooperatives
Risk-Management-presentation for cooperativesRisk-Management-presentation for cooperatives
Risk-Management-presentation for cooperatives
bernanbumatay1
 
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
William (Bill) H. Bender, FCSI
 
Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...
Ram V Chary
 
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
tdt5v4b
 
Comparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile SystemsComparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile Systems
Rob Healy
 
Public Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdfPublic Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdf
Pinta Partners
 
12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve
Pierre E. NEIS
 
Addiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdfAddiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdf
Bill641377
 
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
tdt5v4b
 
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish GermanCV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
EUS+ Management & Consulting Excellence
 
Enriching engagement with ethical review processes
Enriching engagement with ethical review processesEnriching engagement with ethical review processes
Enriching engagement with ethical review processes
strikingabalance
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
Muhammad Adil Jamil
 
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
tdt5v4b
 
Case Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of ManagementCase Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of Management
A. F. M. Rubayat-Ul Jannat
 
Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™
Alexey Krivitsky
 
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
tdt5v4b
 
Senior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdfSenior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdf
Jim Smith
 
The Management Guide: From Projects to Portfolio
The Management Guide: From Projects to PortfolioThe Management Guide: From Projects to Portfolio
The Management Guide: From Projects to Portfolio
Ahmed AbdelMoneim
 
20240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 202420240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 2024
Matthew Sinclair
 

Recently uploaded (20)

一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
 
Risk-Management-presentation for cooperatives
Risk-Management-presentation for cooperativesRisk-Management-presentation for cooperatives
Risk-Management-presentation for cooperatives
 
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
 
Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...
 
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
 
Comparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile SystemsComparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile Systems
 
Public Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdfPublic Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdf
 
12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve12 steps to transform your organization into the agile org you deserve
12 steps to transform your organization into the agile org you deserve
 
Addiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdfAddiction to Winning Across Diverse Populations.pdf
Addiction to Winning Across Diverse Populations.pdf
 
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
 
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish GermanCV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
 
Enriching engagement with ethical review processes
Enriching engagement with ethical review processesEnriching engagement with ethical review processes
Enriching engagement with ethical review processes
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
 
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
 
Case Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of ManagementCase Analysis - The Sky is the Limit | Principles of Management
Case Analysis - The Sky is the Limit | Principles of Management
 
Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™
 
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
 
Senior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdfSenior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdf
 
The Management Guide: From Projects to Portfolio
The Management Guide: From Projects to PortfolioThe Management Guide: From Projects to Portfolio
The Management Guide: From Projects to Portfolio
 
20240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 202420240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 2024
 

Probabilistic Activity Time

  • 1. Probabilistic Activity Times Probabilistic Time Estimates Carrine Kezia Aulia :: 102183022
  • 2. • Single time estimates • Didn’t allow for any variation • AT treated as if they are known for certain COMPARISON CPM AND PERTREVIEW • Multiple time estimates • Allow for any variation • AT treated as probabilistic PERT uses probabilistic activity times CPM PERT
  • 3. Approach to estimating activity times WHAT IS PROBABILISTIC ACTIVITY TIMES?What’s it all about? • Completion time estimates can be estimated using the Three Time EstimateThree Time Estimate approachapproach • In this approach, three time estimates are required for each activity
  • 4. MOST LIKELY TIME (m) THREE TIME ESTIMATES OPTIMISTIC TIME (a) PESSIMISTIC TIME (b) 1 2 3 most frequently occur if the activity were repeated many times the shortest possible time to complete the activity if everything went right the longest possible time to complete the activity if everything went wrong
  • 5. with THREE TIME estimates, the activity completion time can be approximated by a BETA DISTRIBUTION BETA DISTRIBUTION BETA DISTRIBUTIONS CAN COME IN A VARIETY OF SHAPES :
  • 6. FORMULA MEAN AND VARIANCE a + 4m + b 6 b - a 6 2 mean (expected time) variance σ2 t MOST LIKELY TIME (m) OPTIMISTIC TIME (a) PESSIMISTIC TIME (b)
  • 7. EXAMPLEA PROJECT NETWORK WITH PROBABILISTIC TIME ESTIMATE
  • 8. EXAMPLEACTIVITY TIME ESTIMATES a + 4m + b 6 b - a 6 2 t σ2
  • 9. EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK
  • 10. EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK 0 8 8 8 5 13 0 6 6 3 0 3 3 6 9 4 3 7 2 3 5 7 9 16 4 9 13 4 13 17 9 16 25 2516 2521 2116 169 1612 1614 95 52 9660 91 EXPECTED TIME : 25 CRITICAL PATH : 2-5-8-11
  • 11. EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK 25 WEEKS 6,89 WEEKS
  • 12. EXAMPLEPROBABILISTIC ANALYSIS OF THE PROJECT NETWORK ADD ALL THE σ2 OFF THE CRITICAL PATH S D what does this formula means? what does these numbers mean?
  • 13. EXAMPLEPROBABILISTIC ANALYSIS OF THE PROJECT NETWORK 25 WEEKS 6,89 WEEKS 2,62 WEEKS EXPECTED TIME μ σ2 σ
  • 14. EXAMPLEPROBABILISTIC ANALYSIS OF THE PROJECT NETWORK 25 WEEKS EXPECTED TIME μ 30 WEEKS PROPOSED PROJECT TIME X WHAT IS THE PROBABILITY THAT THE SYSTEM WILL BE READY BY THAT TIME? WHAT IS THE PROBABILITY THAT THE SYSTEM WILL BE READY BY THAT TIME?
  • 15. EXAMPLEPROBABILISTIC ANALYSIS OF THE PROJECT NETWORK Z = X – μ σ 30 WEEKS 25 WEEKS 2.62 - = 1.911.91
  • 16. EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK z = 1.91
  • 17. EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK
  • 18. EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK 0.9719 probability of completing the project in 30 days 0.9719 probability of completing the project in 30 days
  • 19. EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK www.measuringusability.com
  • 20. EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK z = 1.91 97.19 %

Editor's Notes

  1. CPM : A single estimates for activity times did not allow for any variation in activity times Activity times were treated as if they were known for certain PERT: multiple time estimates allow for variation in activity times