Project Management
(AOA) and (AON) Network Construction and
Critical Path Calculations
(Using Four Methods)
Dr. Mahmoud Abbas Mahmoud
Assistant Professor
(AOA) and (AON) Network Construction and
Critical Path Calculations
(Using Four Methods)
EXAMPLE:
Construct the (AOA) and (AON) networks for the project whose activities,
their durations and their precedence relationships are as given in the table,
also find:
i) [ES, EF, LS, LF, Slack] for all activities.
ii) Critical path(s).
iii) Project completion time.
Activity
Predecessor
Activity
Duration
(days)
A - 2
B A 8
C A 10
D B 6
E B 3
F C 3
G C 7
H D, F 5
I E 2
J G 8
Solution (1):
(AOA) network
Activity
Path
(i - j)
Duration
(days)
ES EF LS LF
TF
(Slack)
Critical
A (1 – 2) 2 0 2 0 2 0* Yes
B (2 – 3) 8 2 10 8 16 6 No
C (2 – 4) 10 2 12 2 12 0* Yes
D (3 – 5) 6 10 16 16 22 6 No
E (3 – 6) 3 10 13 22 25 12 No
F (4 – 5) 3 12 15 19 22 7 No
G (4 – 7) 7 12 19 12 19 0* Yes
H (5 – 8) 5 16 21 22 27 6 No
I (6 – 8) 2 13 15 25 27 12 No
J (7 – 8) 8 19 27 19 27 0* Yes
Therefore:
Critical path: A --- C --- G --- J
Project completion time = 27 days
Solution (2):
(AOA) network (calculations in node)
Activity
Path
(i - j)
Duration
(days)
ES EF LS LF
TF
(Slack)
Critical
A (1 – 2) 2 0 2 0 2 0* Yes
B (2 – 3) 8 2 10 8 16 6 No
C (2 – 4) 10 2 12 2 12 0* Yes
D (3 – 5) 6 10 16 16 22 6 No
E (3 – 6) 3 10 13 22 25 12 No
F (4 – 5) 3 12 15 19 22 7 No
G (4 – 7) 7 12 19 12 19 0* Yes
H (5 – 8) 5 16 21 22 27 6 No
I (6 – 8) 2 13 15 25 27 12 No
J (7 – 8) 8 19 27 19 27 0* Yes
Note: (LC = LF) & (EC = EF)
Therefore:
Critical path: A --- C --- G --- J
Project completion time = 27 days
Solution (3):
(AOA) network (calculations on arrow)
Activity
Path
(i - j)
Duration
(days)
ES EF LS LF
TF
(Slack)
Critical
A (1 – 2) 2 0 2 0 2 0* Yes
B (2 – 3) 8 2 10 8 16 6 No
C (2 – 4) 10 2 12 2 12 0* Yes
D (3 – 5) 6 10 16 16 22 6 No
E (3 – 6) 3 10 13 22 25 12 No
F (4 – 5) 3 12 15 19 22 7 No
G (4 – 7) 7 12 19 12 19 0* Yes
H (5 – 8) 5 16 21 22 27 6 No
I (6 – 8) 2 13 15 25 27 12 No
J (7 – 8) 8 19 27 19 27 0* Yes
Therefore:
Critical path: A --- C --- G --- J
Project completion time = 27 days
Solution (4):
(AON) network
Activity
Path
(i - j)
Duration
(days)
ES EF LS LF
TF
(Slack)
Critical
A (1 – 2) 2 0 2 0 2 0* Yes
B (2 – 3) 8 2 10 8 16 6 No
C (2 – 4) 10 2 12 2 12 0* Yes
D (3 – 5) 6 10 16 16 22 6 No
E (3 – 6) 3 10 13 22 25 12 No
F (4 – 5) 3 12 15 19 22 7 No
G (4 – 7) 7 12 19 12 19 0* Yes
H (5 – 8) 5 16 21 22 27 6 No
I (6 – 8) 2 13 15 25 27 12 No
J (7 – 8) 8 19 27 19 27 0* Yes
Therefore:
Critical path: A --- C --- G --- J
Project completion time = 27 days

More Related Content

What's hot

Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Alecsis Roe Frasco
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadium
SLIIT, Sri Lanka
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
Asif Sultan Razu
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
Ajeesh Mk
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
dmdk12
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
adeelmunir158
 
5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planningJeanette C. Patindol
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
tutor2u
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
hoang tung
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Mr. Ramesh Nayaka
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
Pulchowk Campus
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
North Warwickshie & Hinckley college
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
S.Vijaya Bhaskar
 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path Ppt
Jeff Hilton
 
6.5 The Forward and Backward Pass (Critical Path)
6.5 The Forward and Backward Pass (Critical Path)6.5 The Forward and Backward Pass (Critical Path)
6.5 The Forward and Backward Pass (Critical Path)
DavidMcLachlan1
 
PERT
PERTPERT
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
Prasad Thanthratey
 
Project Management Case Study .EC Harris International Ltd. (Al Wahda Mast...
Project Management Case Study .EC Harris International Ltd.   (Al Wahda Mast...Project Management Case Study .EC Harris International Ltd.   (Al Wahda Mast...
Project Management Case Study .EC Harris International Ltd. (Al Wahda Mast...
Malik Liaqat Ali
 

What's hot (20)

Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadium
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planning
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path Ppt
 
6.5 The Forward and Backward Pass (Critical Path)
6.5 The Forward and Backward Pass (Critical Path)6.5 The Forward and Backward Pass (Critical Path)
6.5 The Forward and Backward Pass (Critical Path)
 
PERT
PERTPERT
PERT
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
Project Management Case Study .EC Harris International Ltd. (Al Wahda Mast...
Project Management Case Study .EC Harris International Ltd.   (Al Wahda Mast...Project Management Case Study .EC Harris International Ltd.   (Al Wahda Mast...
Project Management Case Study .EC Harris International Ltd. (Al Wahda Mast...
 

Similar to (AOA) and (AON) Network construction and critical path calculations (using four methods)

CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
LJay7
 
Scheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxScheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docx
kenjordan97598
 
Management Network Lec 3
Management Network Lec 3Management Network Lec 3
Management Network Lec 3
cairo university
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
Shadina Shah
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
Nikka Lopez
 
Productions & Operations Management Chapter 03
Productions & Operations Management Chapter 03Productions & Operations Management Chapter 03
Productions & Operations Management Chapter 03
jncgw5t6xq
 
Lecture - Project, Planning and Control.pdf
Lecture - Project, Planning and Control.pdfLecture - Project, Planning and Control.pdf
Lecture - Project, Planning and Control.pdf
lucky141651
 
Lecture 5.pdf
Lecture 5.pdfLecture 5.pdf
Lecture 5.pdf
JamalKhan696508
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
Anand Bobade
 
Chapter 5 - PERT-CPM
Chapter 5 - PERT-CPM Chapter 5 - PERT-CPM
Chapter 5 - PERT-CPM
maggieget
 
606CPM1.ppt
606CPM1.ppt606CPM1.ppt
606CPM1.ppt
UpulHettiarachchi5
 
Pert analysis
Pert analysisPert analysis
Pert analysis
Hashamuddin Yaakob
 
Hard Rock
Hard RockHard Rock
Hard Rock
Jeevan Rathod
 
Project management
Project managementProject management
Project management
Anurag Srivastava
 
8th Semester Civil Engineering Question Papers June/july 2018
8th Semester Civil Engineering Question Papers June/july 20188th Semester Civil Engineering Question Papers June/july 2018
8th Semester Civil Engineering Question Papers June/july 2018
BGS Institute of Technology, Adichunchanagiri University (ACU)
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
Vignesh Jayakumar
 
Project network math solution
Project network math solutionProject network math solution
Project network math solution
Md.Nazrul Islam
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Chandi Mohanty
 
Jpw 2 latihan lvl 3
Jpw 2 latihan lvl 3Jpw 2 latihan lvl 3
Jpw 2 latihan lvl 3
ejataiman
 

Similar to (AOA) and (AON) Network construction and critical path calculations (using four methods) (20)

CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
 
Scheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxScheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docx
 
Management Network Lec 3
Management Network Lec 3Management Network Lec 3
Management Network Lec 3
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Productions & Operations Management Chapter 03
Productions & Operations Management Chapter 03Productions & Operations Management Chapter 03
Productions & Operations Management Chapter 03
 
Lecture - Project, Planning and Control.pdf
Lecture - Project, Planning and Control.pdfLecture - Project, Planning and Control.pdf
Lecture - Project, Planning and Control.pdf
 
Lecture 5.pdf
Lecture 5.pdfLecture 5.pdf
Lecture 5.pdf
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
Chapter 5 - PERT-CPM
Chapter 5 - PERT-CPM Chapter 5 - PERT-CPM
Chapter 5 - PERT-CPM
 
606CPM1.ppt
606CPM1.ppt606CPM1.ppt
606CPM1.ppt
 
Pert analysis
Pert analysisPert analysis
Pert analysis
 
Hard Rock
Hard RockHard Rock
Hard Rock
 
Project management
Project managementProject management
Project management
 
8th Semester Civil Engineering Question Papers June/july 2018
8th Semester Civil Engineering Question Papers June/july 20188th Semester Civil Engineering Question Papers June/july 2018
8th Semester Civil Engineering Question Papers June/july 2018
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Project network math solution
Project network math solutionProject network math solution
Project network math solution
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Jpw 2 latihan lvl 3
Jpw 2 latihan lvl 3Jpw 2 latihan lvl 3
Jpw 2 latihan lvl 3
 

More from Dr. Mahmoud Al-Naimi

أسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfأسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdf
Dr. Mahmoud Al-Naimi
 
Certificate - Dr. Mahmoud AL-Naimi
Certificate  - Dr. Mahmoud AL-NaimiCertificate  - Dr. Mahmoud AL-Naimi
Certificate - Dr. Mahmoud AL-Naimi
Dr. Mahmoud Al-Naimi
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريع
Dr. Mahmoud Al-Naimi
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
Dr. Mahmoud Al-Naimi
 
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةكيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
Dr. Mahmoud Al-Naimi
 
أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)
Dr. Mahmoud Al-Naimi
 
Applications dr. mahmoud al-naimi
Applications   dr. mahmoud al-naimiApplications   dr. mahmoud al-naimi
Applications dr. mahmoud al-naimi
Dr. Mahmoud Al-Naimi
 
Product design and manufacture lecture 1
Product design and manufacture lecture  1Product design and manufacture lecture  1
Product design and manufacture lecture 1
Dr. Mahmoud Al-Naimi
 
Easy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsEasy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projects
Dr. Mahmoud Al-Naimi
 
Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations
Dr. Mahmoud Al-Naimi
 
ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق
Dr. Mahmoud Al-Naimi
 
Control charts for variables
Control charts for variables Control charts for variables
Control charts for variables
Dr. Mahmoud Al-Naimi
 
Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)
Dr. Mahmoud Al-Naimi
 
Evolution of mrp type systems
Evolution of mrp type systemsEvolution of mrp type systems
Evolution of mrp type systems
Dr. Mahmoud Al-Naimi
 
Computer in Design and Manufacturing
Computer in Design and Manufacturing Computer in Design and Manufacturing
Computer in Design and Manufacturing
Dr. Mahmoud Al-Naimi
 
إنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةإنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكية
Dr. Mahmoud Al-Naimi
 
Network construction
Network construction  Network construction
Network construction
Dr. Mahmoud Al-Naimi
 
Production planning hierarchy
Production planning hierarchyProduction planning hierarchy
Production planning hierarchy
Dr. Mahmoud Al-Naimi
 
Material and capacity requirements planning (mrp and crp) part 2
Material and capacity requirements planning (mrp and crp) part  2Material and capacity requirements planning (mrp and crp) part  2
Material and capacity requirements planning (mrp and crp) part 2
Dr. Mahmoud Al-Naimi
 
Material and capacity requirements planning (mrp and crp) part 1
Material and capacity requirements planning (mrp and crp) part  1Material and capacity requirements planning (mrp and crp) part  1
Material and capacity requirements planning (mrp and crp) part 1
Dr. Mahmoud Al-Naimi
 

More from Dr. Mahmoud Al-Naimi (20)

أسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfأسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdf
 
Certificate - Dr. Mahmoud AL-Naimi
Certificate  - Dr. Mahmoud AL-NaimiCertificate  - Dr. Mahmoud AL-Naimi
Certificate - Dr. Mahmoud AL-Naimi
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريع
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةكيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
 
أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)
 
Applications dr. mahmoud al-naimi
Applications   dr. mahmoud al-naimiApplications   dr. mahmoud al-naimi
Applications dr. mahmoud al-naimi
 
Product design and manufacture lecture 1
Product design and manufacture lecture  1Product design and manufacture lecture  1
Product design and manufacture lecture 1
 
Easy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsEasy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projects
 
Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations
 
ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق
 
Control charts for variables
Control charts for variables Control charts for variables
Control charts for variables
 
Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)
 
Evolution of mrp type systems
Evolution of mrp type systemsEvolution of mrp type systems
Evolution of mrp type systems
 
Computer in Design and Manufacturing
Computer in Design and Manufacturing Computer in Design and Manufacturing
Computer in Design and Manufacturing
 
إنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةإنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكية
 
Network construction
Network construction  Network construction
Network construction
 
Production planning hierarchy
Production planning hierarchyProduction planning hierarchy
Production planning hierarchy
 
Material and capacity requirements planning (mrp and crp) part 2
Material and capacity requirements planning (mrp and crp) part  2Material and capacity requirements planning (mrp and crp) part  2
Material and capacity requirements planning (mrp and crp) part 2
 
Material and capacity requirements planning (mrp and crp) part 1
Material and capacity requirements planning (mrp and crp) part  1Material and capacity requirements planning (mrp and crp) part  1
Material and capacity requirements planning (mrp and crp) part 1
 

Recently uploaded

Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 

Recently uploaded (20)

Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 

(AOA) and (AON) Network construction and critical path calculations (using four methods)

  • 1. Project Management (AOA) and (AON) Network Construction and Critical Path Calculations (Using Four Methods) Dr. Mahmoud Abbas Mahmoud Assistant Professor
  • 2. (AOA) and (AON) Network Construction and Critical Path Calculations (Using Four Methods) EXAMPLE: Construct the (AOA) and (AON) networks for the project whose activities, their durations and their precedence relationships are as given in the table, also find: i) [ES, EF, LS, LF, Slack] for all activities. ii) Critical path(s). iii) Project completion time. Activity Predecessor Activity Duration (days) A - 2 B A 8 C A 10 D B 6 E B 3 F C 3 G C 7 H D, F 5 I E 2 J G 8
  • 3. Solution (1): (AOA) network Activity Path (i - j) Duration (days) ES EF LS LF TF (Slack) Critical A (1 – 2) 2 0 2 0 2 0* Yes B (2 – 3) 8 2 10 8 16 6 No C (2 – 4) 10 2 12 2 12 0* Yes D (3 – 5) 6 10 16 16 22 6 No E (3 – 6) 3 10 13 22 25 12 No F (4 – 5) 3 12 15 19 22 7 No G (4 – 7) 7 12 19 12 19 0* Yes H (5 – 8) 5 16 21 22 27 6 No I (6 – 8) 2 13 15 25 27 12 No J (7 – 8) 8 19 27 19 27 0* Yes Therefore: Critical path: A --- C --- G --- J Project completion time = 27 days
  • 4. Solution (2): (AOA) network (calculations in node) Activity Path (i - j) Duration (days) ES EF LS LF TF (Slack) Critical A (1 – 2) 2 0 2 0 2 0* Yes B (2 – 3) 8 2 10 8 16 6 No C (2 – 4) 10 2 12 2 12 0* Yes D (3 – 5) 6 10 16 16 22 6 No E (3 – 6) 3 10 13 22 25 12 No F (4 – 5) 3 12 15 19 22 7 No G (4 – 7) 7 12 19 12 19 0* Yes H (5 – 8) 5 16 21 22 27 6 No I (6 – 8) 2 13 15 25 27 12 No J (7 – 8) 8 19 27 19 27 0* Yes Note: (LC = LF) & (EC = EF) Therefore: Critical path: A --- C --- G --- J Project completion time = 27 days
  • 5. Solution (3): (AOA) network (calculations on arrow) Activity Path (i - j) Duration (days) ES EF LS LF TF (Slack) Critical A (1 – 2) 2 0 2 0 2 0* Yes B (2 – 3) 8 2 10 8 16 6 No C (2 – 4) 10 2 12 2 12 0* Yes D (3 – 5) 6 10 16 16 22 6 No E (3 – 6) 3 10 13 22 25 12 No F (4 – 5) 3 12 15 19 22 7 No G (4 – 7) 7 12 19 12 19 0* Yes H (5 – 8) 5 16 21 22 27 6 No I (6 – 8) 2 13 15 25 27 12 No J (7 – 8) 8 19 27 19 27 0* Yes Therefore: Critical path: A --- C --- G --- J Project completion time = 27 days
  • 6. Solution (4): (AON) network Activity Path (i - j) Duration (days) ES EF LS LF TF (Slack) Critical A (1 – 2) 2 0 2 0 2 0* Yes B (2 – 3) 8 2 10 8 16 6 No C (2 – 4) 10 2 12 2 12 0* Yes D (3 – 5) 6 10 16 16 22 6 No E (3 – 6) 3 10 13 22 25 12 No F (4 – 5) 3 12 15 19 22 7 No G (4 – 7) 7 12 19 12 19 0* Yes H (5 – 8) 5 16 21 22 27 6 No I (6 – 8) 2 13 15 25 27 12 No J (7 – 8) 8 19 27 19 27 0* Yes Therefore: Critical path: A --- C --- G --- J Project completion time = 27 days