SlideShare a Scribd company logo
1 of 33
Chapter 8:
Scheduling Resources and Costs
A Report in Project Research and
Development
By Mr. Cristan A. Marquez
The Resource Problem
• Resources and Priorities
– Project network times are not a schedule until
resources have been assigned.
• The implicit assumption is that resources will be available in the
required amounts when needed.
• Adding new projects requires making realistic judgments of
resource availability and project durations.
• Resource leveling (or smoothing)
– involves attempting to even out demands on
resources by using slack (delaying non-critical
activities) to manage resource utilization.
• Resource-Constrained Scheduling
– Involves delaying some activities if the resources
are enough to meet peak demand
Types of Project Constraints
• Technical or Logic Constraints
– Constraints related to the networked sequence in which
project activities must occur
• Physical constraints
• Resource Constraints
– The absence, shortage, or unique interrelationship and
interaction characteristics of resources that require a
particular sequencing of project activities
– Types of resource constraints
• People
• Materials
• Equipment
• Working Capital
Constraint Examples
FIGURE 8.1
Classification of a Scheduling Problem
• Classification of Problem
– Using a priority matrix will help determine if the project is time
or resource constrained
• Time Constrained Project
– A project that must be completed by an imposed date
• Time is fixed, resources are flexible: additional resources are
required to ensure project meets schedule.
• Resource Constrained Project
– A project in which the level of resources available cannot be
exceeded
• Resources are fixed, time is flexible: inadequate resources will delay
the project.
Resource Allocation Methods
• Limiting Assumptions
– Splitting activities is not allowed—once an activity is
start, it is carried to completion.
– Level of resource used for an activity cannot be
changed.
– Activities with the most slack pose the least risk.
– Reduction of flexibility does not increase risk.
– The nature of an activity (easy, complex) doesn’t
increase risk.
Resource Allocation Methods (cont’d)
• Time-Constrained Projects
– Projects that must be completed by an imposed date
– Require the use of leveling techniques that focus on balancing
or smoothing resource demands by using positive slack
(delaying noncritical activities) to manage resource utilization
over the duration of the project
• Peak resource demands are reduced.
• Resources over the life of the project are reduced.
• Fluctuation in resource demand is minimized.
Botanical Garden
FIGURE 8.2
A
B
C
D
E
F
G
Botanical Garden (cont’d)
FIGURE 8.2 (cont’d)
Resource Allocation Methods (cont’d)
• Resource Demand Leveling Techniques for Time-Constrained
Projects
– Advantages
• Peak resource demands are reduced.
• Resources over the life of the project are reduced.
• Fluctuation in resource demand is minimized.
– Disadvantages
• Loss of flexibility that occurs from reducing slack
• Increases in the criticality of all activities
• Resource-Constrained Projects
– Projects that involve resources that are limited in quantity or by
their availability
– Scheduling of activities requires the use of heuristics (rules-of-
thumb) that focus on:
1. Minimum slack
2. Smallest (least) duration
3. Lowest activity identification number
– The parallel method is used to apply heuristics.
• An iterative process that starts at the first time period of the project
and schedules period-by-period any activities scheduled to start using
the three priority rules
Resource Allocation Methods (cont’d)
The Parallel Method
Resource-Constrained Schedule through Period 2–3
FIGURE 8.3
Resource-Constrained Schedule through Period 2–3
FIGURE 8.3 (cont’d)
ES resource load chart
Resource-Constrained Schedule through Period 2–3
FIGURE 8.3 (cont’d)
Resource-constrained schedule through period 2–3
Resource-Constrained Schedule through Period 5–6
FIGURE 8.4
Resource-constrained schedule through period 5–6
Resource-Constrained Schedule through Period 5–6
FIGURE 8.4 (cont’d)
Final resource-constrained schedule
Resource-Constrained Schedule through Period 5–6
FIGURE 8.4 (cont’d)
New, resource-constrained network
The Impacts of Resource-Constrained Scheduling
• Reduces delay but reduces flexibility
• Increases sensitivity of the network
• Increases scheduling complexity
• May make traditional critical path no longer meaningful
• Can break sequence of events
• May cause parallel activities to become sequential and
critical activities with slack to become noncritical
Splitting/Multitasking
• A scheduling technique use to get a better
project schedule and/or increase resource
utilization
– Involves interrupting work on an activity to employ
the resource on another activity, then returning the
resource to finish the interrupted work
– Is feasible when startup and shutdown costs are
low
– Is considered the major reason why projects fail to
meet schedule
Splitting/Multitasking
FIGURE 8.10
Assigning Project Work
• Factors to Consider in Assigning Work:
– Don’t always pick the same people for the toughest
assignments.
– Choose people with an eye to fostering their development
through participation on the project.
– Pick people with compatible work habits and personalities but
who complement each other.
– Team-up veterans with new hires to share experience and
socialize newcomers into the organization.
– Select people who may need to learn work together on later
stages of the project or other projects.
Multiproject Resource Schedules
• Multiproject Scheduling Problems
– Overall project slippage
• Delay on one project creates delays for other projects.
– Inefficient resource application
• The peaks and valleys of resource demands create
scheduling problems and delays for projects.
– Resource bottlenecks
• Shortages of critical resources required for multiple projects
cause delays and schedule extensions.
Multiproject Resource Schedules
• Managing Multiproject Scheduling
– Create project offices or departments to oversee the
scheduling of resources across projects.
– Use a project priority queuing system: first come, first
served for resources.
– Centralize project management: treat all projects as a
part of a “megaproject.”
– Outsource projects to reduce the number of projects
handled internally.
Creating a Time-Phased Budget
Creating a Time-Phased Budget (cont’d)
Creating a Time-Phased Budget (cont’d)
Creating a Time-Phased Budget (cont’d)
Creating a Time-Phased Budget (cont’d)
Monthly Cash Flow Statement
Resource Usage Table

More Related Content

What's hot

Chap 2 Organization Strategy
Chap 2 Organization StrategyChap 2 Organization Strategy
Chap 2 Organization Strategyproject management
 
Fundamentals of Project Planning, Scheduling, Monitoring & Control
Fundamentals of Project Planning, Scheduling, Monitoring & ControlFundamentals of Project Planning, Scheduling, Monitoring & Control
Fundamentals of Project Planning, Scheduling, Monitoring & ControlAssociation for Project Management
 
Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)FahadHasan36
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksPrasad Thanthratey
 
Project cost control techniques
Project cost control techniquesProject cost control techniques
Project cost control techniquesWissem Amara
 
Strategic portfolio management
Strategic portfolio managementStrategic portfolio management
Strategic portfolio managementGlen Alleman
 
Project controls
Project controlsProject controls
Project controlsAshok Kumar
 
Chapter 1 An Overview Of Project Management
Chapter 1  An Overview Of Project ManagementChapter 1  An Overview Of Project Management
Chapter 1 An Overview Of Project ManagementMahesh Bendigeri
 
Chap 1 Modern Project Management
Chap 1 Modern Project ManagementChap 1 Modern Project Management
Chap 1 Modern Project Managementproject management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementAnand Subramaniam
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementMartin Sillaots
 
Project Management
Project ManagementProject Management
Project Managementajithsrc
 
Project Selection Methods
Project Selection MethodsProject Selection Methods
Project Selection MethodsManikandan M
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 

What's hot (20)

Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Chap 2 Organization Strategy
Chap 2 Organization StrategyChap 2 Organization Strategy
Chap 2 Organization Strategy
 
Fundamentals of Project Planning, Scheduling, Monitoring & Control
Fundamentals of Project Planning, Scheduling, Monitoring & ControlFundamentals of Project Planning, Scheduling, Monitoring & Control
Fundamentals of Project Planning, Scheduling, Monitoring & Control
 
Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
Project cost control techniques
Project cost control techniquesProject cost control techniques
Project cost control techniques
 
Strategic portfolio management
Strategic portfolio managementStrategic portfolio management
Strategic portfolio management
 
Project controls
Project controlsProject controls
Project controls
 
Chapter 1 An Overview Of Project Management
Chapter 1  An Overview Of Project ManagementChapter 1  An Overview Of Project Management
Chapter 1 An Overview Of Project Management
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Chap 1 Modern Project Management
Chap 1 Modern Project ManagementChap 1 Modern Project Management
Chap 1 Modern Project Management
 
Chap008
Chap008Chap008
Chap008
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project Management
Project ManagementProject Management
Project Management
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Project Selection Methods
Project Selection MethodsProject Selection Methods
Project Selection Methods
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 

Similar to Lecture-8-Scheduling-Resources-and-Cost.pptx

Chap008.ppt
Chap008.pptChap008.ppt
Chap008.pptLucasMogaka
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptxTecnicoItca
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptTecnicoItca
 
PM Session 6
PM Session 6PM Session 6
PM Session 6dmdk12
 
Allocating Resources To The Project
Allocating Resources To The ProjectAllocating Resources To The Project
Allocating Resources To The ProjectJeff Brooks
 
Network diagrams
Network diagramsNetwork diagrams
Network diagramsLii Van
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertRaj J Das
 
Techniques of OR.pptx
Techniques of OR.pptxTechniques of OR.pptx
Techniques of OR.pptxArdraSabu
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)ShudipPal
 
Time management pressent
Time management pressentTime management pressent
Time management pressentiklil fairuz
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.pptTecnicoItca
 
Chapter EightScheduling Resources and Costs© 2021 McGraw-H
Chapter EightScheduling Resources and Costs© 2021 McGraw-HChapter EightScheduling Resources and Costs© 2021 McGraw-H
Chapter EightScheduling Resources and Costs© 2021 McGraw-HJinElias52
 
Project Management Notes 3
Project Management Notes 3Project Management Notes 3
Project Management Notes 3Golam Bitonsir
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system projecta23ccb
 

Similar to Lecture-8-Scheduling-Resources-and-Cost.pptx (20)

Chap008.ppt
Chap008.pptChap008.ppt
Chap008.ppt
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptx
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.ppt
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
 
Allocating Resources To The Project
Allocating Resources To The ProjectAllocating Resources To The Project
Allocating Resources To The Project
 
Ch09 (1).pptx
Ch09 (1).pptxCh09 (1).pptx
Ch09 (1).pptx
 
Allocating resources
Allocating resourcesAllocating resources
Allocating resources
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
 
Techniques of OR.pptx
Techniques of OR.pptxTechniques of OR.pptx
Techniques of OR.pptx
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
Time management pressent
Time management pressentTime management pressent
Time management pressent
 
ch09s.ppt
ch09s.pptch09s.ppt
ch09s.ppt
 
Time management
Time managementTime management
Time management
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
Chapter EightScheduling Resources and Costs© 2021 McGraw-H
Chapter EightScheduling Resources and Costs© 2021 McGraw-HChapter EightScheduling Resources and Costs© 2021 McGraw-H
Chapter EightScheduling Resources and Costs© 2021 McGraw-H
 
Project Management Notes 3
Project Management Notes 3Project Management Notes 3
Project Management Notes 3
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
 
EpM
EpMEpM
EpM
 

More from TecnicoItca

tipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdftipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdfTecnicoItca
 
-Interes-Simple.ppt
-Interes-Simple.ppt-Interes-Simple.ppt
-Interes-Simple.pptTecnicoItca
 
Tesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptxTesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptxTecnicoItca
 
Gestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.pptGestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.pptTecnicoItca
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.pptTecnicoItca
 
Project-Progress-Presentation.pptx
Project-Progress-Presentation.pptxProject-Progress-Presentation.pptx
Project-Progress-Presentation.pptxTecnicoItca
 
-Project-Management.ppt
-Project-Management.ppt-Project-Management.ppt
-Project-Management.pptTecnicoItca
 
Telsys-Case-International-Management.ppt
Telsys-Case-International-Management.pptTelsys-Case-International-Management.ppt
Telsys-Case-International-Management.pptTecnicoItca
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptxTecnicoItca
 
Project-Management.ppt
Project-Management.pptProject-Management.ppt
Project-Management.pptTecnicoItca
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxTecnicoItca
 
Project-Management-Introduction.ppt
Project-Management-Introduction.pptProject-Management-Introduction.ppt
Project-Management-Introduction.pptTecnicoItca
 
Project-Manager.ppt
Project-Manager.pptProject-Manager.ppt
Project-Manager.pptTecnicoItca
 
-PM-09-7.ppt
-PM-09-7.ppt-PM-09-7.ppt
-PM-09-7.pptTecnicoItca
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptTecnicoItca
 
Clases-de-Bonos-matematica.ppt
Clases-de-Bonos-matematica.pptClases-de-Bonos-matematica.ppt
Clases-de-Bonos-matematica.pptTecnicoItca
 
Valoracion-de-Bonos.pptx
Valoracion-de-Bonos.pptxValoracion-de-Bonos.pptx
Valoracion-de-Bonos.pptxTecnicoItca
 
Bonos-Clase.ppt
Bonos-Clase.pptBonos-Clase.ppt
Bonos-Clase.pptTecnicoItca
 
Valuacion-de-Bonos-3.ppt
Valuacion-de-Bonos-3.pptValuacion-de-Bonos-3.ppt
Valuacion-de-Bonos-3.pptTecnicoItca
 

More from TecnicoItca (20)

tipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdftipos-de-organizacion-empresarial.pdf
tipos-de-organizacion-empresarial.pdf
 
-Interes-Simple.ppt
-Interes-Simple.ppt-Interes-Simple.ppt
-Interes-Simple.ppt
 
Tesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptxTesis-de-gerencia-de-proyectos (1).pptx
Tesis-de-gerencia-de-proyectos (1).pptx
 
Gestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.pptGestion-Financiera-Semestre-2016-0-ppt.ppt
Gestion-Financiera-Semestre-2016-0-ppt.ppt
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
 
Project-Progress-Presentation.pptx
Project-Progress-Presentation.pptxProject-Progress-Presentation.pptx
Project-Progress-Presentation.pptx
 
-Project-Management.ppt
-Project-Management.ppt-Project-Management.ppt
-Project-Management.ppt
 
Telsys-Case-International-Management.ppt
Telsys-Case-International-Management.pptTelsys-Case-International-Management.ppt
Telsys-Case-International-Management.ppt
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptx
 
Project-Management.ppt
Project-Management.pptProject-Management.ppt
Project-Management.ppt
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
Project-Management-Introduction.ppt
Project-Management-Introduction.pptProject-Management-Introduction.ppt
Project-Management-Introduction.ppt
 
Project-Manager.ppt
Project-Manager.pptProject-Manager.ppt
Project-Manager.ppt
 
ch10s.ppt
ch10s.pptch10s.ppt
ch10s.ppt
 
-PM-09-7.ppt
-PM-09-7.ppt-PM-09-7.ppt
-PM-09-7.ppt
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.ppt
 
Clases-de-Bonos-matematica.ppt
Clases-de-Bonos-matematica.pptClases-de-Bonos-matematica.ppt
Clases-de-Bonos-matematica.ppt
 
Valoracion-de-Bonos.pptx
Valoracion-de-Bonos.pptxValoracion-de-Bonos.pptx
Valoracion-de-Bonos.pptx
 
Bonos-Clase.ppt
Bonos-Clase.pptBonos-Clase.ppt
Bonos-Clase.ppt
 
Valuacion-de-Bonos-3.ppt
Valuacion-de-Bonos-3.pptValuacion-de-Bonos-3.ppt
Valuacion-de-Bonos-3.ppt
 

Recently uploaded

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 

Recently uploaded (20)

Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 

Lecture-8-Scheduling-Resources-and-Cost.pptx

  • 1. Chapter 8: Scheduling Resources and Costs A Report in Project Research and Development By Mr. Cristan A. Marquez
  • 2.
  • 3. The Resource Problem • Resources and Priorities – Project network times are not a schedule until resources have been assigned. • The implicit assumption is that resources will be available in the required amounts when needed. • Adding new projects requires making realistic judgments of resource availability and project durations. • Resource leveling (or smoothing) – involves attempting to even out demands on resources by using slack (delaying non-critical activities) to manage resource utilization. • Resource-Constrained Scheduling – Involves delaying some activities if the resources are enough to meet peak demand
  • 4. Types of Project Constraints • Technical or Logic Constraints – Constraints related to the networked sequence in which project activities must occur • Physical constraints • Resource Constraints – The absence, shortage, or unique interrelationship and interaction characteristics of resources that require a particular sequencing of project activities – Types of resource constraints • People • Materials • Equipment • Working Capital
  • 6. Classification of a Scheduling Problem • Classification of Problem – Using a priority matrix will help determine if the project is time or resource constrained • Time Constrained Project – A project that must be completed by an imposed date • Time is fixed, resources are flexible: additional resources are required to ensure project meets schedule. • Resource Constrained Project – A project in which the level of resources available cannot be exceeded • Resources are fixed, time is flexible: inadequate resources will delay the project.
  • 7. Resource Allocation Methods • Limiting Assumptions – Splitting activities is not allowed—once an activity is start, it is carried to completion. – Level of resource used for an activity cannot be changed. – Activities with the most slack pose the least risk. – Reduction of flexibility does not increase risk. – The nature of an activity (easy, complex) doesn’t increase risk.
  • 8. Resource Allocation Methods (cont’d) • Time-Constrained Projects – Projects that must be completed by an imposed date – Require the use of leveling techniques that focus on balancing or smoothing resource demands by using positive slack (delaying noncritical activities) to manage resource utilization over the duration of the project • Peak resource demands are reduced. • Resources over the life of the project are reduced. • Fluctuation in resource demand is minimized.
  • 11. Resource Allocation Methods (cont’d) • Resource Demand Leveling Techniques for Time-Constrained Projects – Advantages • Peak resource demands are reduced. • Resources over the life of the project are reduced. • Fluctuation in resource demand is minimized. – Disadvantages • Loss of flexibility that occurs from reducing slack • Increases in the criticality of all activities
  • 12. • Resource-Constrained Projects – Projects that involve resources that are limited in quantity or by their availability – Scheduling of activities requires the use of heuristics (rules-of- thumb) that focus on: 1. Minimum slack 2. Smallest (least) duration 3. Lowest activity identification number – The parallel method is used to apply heuristics. • An iterative process that starts at the first time period of the project and schedules period-by-period any activities scheduled to start using the three priority rules Resource Allocation Methods (cont’d)
  • 14. Resource-Constrained Schedule through Period 2–3 FIGURE 8.3
  • 15. Resource-Constrained Schedule through Period 2–3 FIGURE 8.3 (cont’d) ES resource load chart
  • 16. Resource-Constrained Schedule through Period 2–3 FIGURE 8.3 (cont’d) Resource-constrained schedule through period 2–3
  • 17.
  • 18. Resource-Constrained Schedule through Period 5–6 FIGURE 8.4 Resource-constrained schedule through period 5–6
  • 19. Resource-Constrained Schedule through Period 5–6 FIGURE 8.4 (cont’d) Final resource-constrained schedule
  • 20. Resource-Constrained Schedule through Period 5–6 FIGURE 8.4 (cont’d) New, resource-constrained network
  • 21. The Impacts of Resource-Constrained Scheduling • Reduces delay but reduces flexibility • Increases sensitivity of the network • Increases scheduling complexity • May make traditional critical path no longer meaningful • Can break sequence of events • May cause parallel activities to become sequential and critical activities with slack to become noncritical
  • 22. Splitting/Multitasking • A scheduling technique use to get a better project schedule and/or increase resource utilization – Involves interrupting work on an activity to employ the resource on another activity, then returning the resource to finish the interrupted work – Is feasible when startup and shutdown costs are low – Is considered the major reason why projects fail to meet schedule
  • 24. Assigning Project Work • Factors to Consider in Assigning Work: – Don’t always pick the same people for the toughest assignments. – Choose people with an eye to fostering their development through participation on the project. – Pick people with compatible work habits and personalities but who complement each other. – Team-up veterans with new hires to share experience and socialize newcomers into the organization. – Select people who may need to learn work together on later stages of the project or other projects.
  • 25. Multiproject Resource Schedules • Multiproject Scheduling Problems – Overall project slippage • Delay on one project creates delays for other projects. – Inefficient resource application • The peaks and valleys of resource demands create scheduling problems and delays for projects. – Resource bottlenecks • Shortages of critical resources required for multiple projects cause delays and schedule extensions.
  • 26. Multiproject Resource Schedules • Managing Multiproject Scheduling – Create project offices or departments to oversee the scheduling of resources across projects. – Use a project priority queuing system: first come, first served for resources. – Centralize project management: treat all projects as a part of a “megaproject.” – Outsource projects to reduce the number of projects handled internally.
  • 28. Creating a Time-Phased Budget (cont’d)
  • 29. Creating a Time-Phased Budget (cont’d)
  • 30. Creating a Time-Phased Budget (cont’d)
  • 31. Creating a Time-Phased Budget (cont’d)
  • 32. Monthly Cash Flow Statement