Introduction
 Any project involves planning, scheduling and controlling a
number of interrelated activities with use of limited resources,
namely, men, machines, materials, money and time.
 The projects may be extremely large and complex such as
construction of a housing , a highway, a shopping complex etc.
 introduction of new products and research and development
projects.
 It is required that managers must have a dynamic planning and
scheduling system to produce the best possible results and also
to react immediately to the changing conditions and make
necessary changes in the plan and schedule.
A convenient analytical and visual technique of PERT and
CPM prove extremely valuable in assisting the managers in
managing the projects.
PERT stands for Project Evaluation and Review
Technique developed during 1950’s. The technique was developed and
used in conjunction with the planning and designing of the Polaris missile
project.
CPM stands for Critical Path Method which was developed by
DuPont Company and applied first to the construction projects in the chemical
industry.
Though both PERT and CPM techniques have similarity in terms of
concepts, the basic difference is, PERT is used for analysis of project
scheduling problems. CPM has single time estimate and PERT has three
time estimates for activities and uses probability theory to find the chance
of reaching the scheduled time.
Project management generally consists of three phases.
Planning:
Planning involves setting the objectives of the project. Identifying
various activities to be performed and determining the requirement of
resources such as men, materials, machines, etc.
The cost and time for all the activities are estimated, and a network diagram is
developed showing sequential interrelationships (predecessor and successor)
between various activities during the planning stage.
Scheduling:
Basd on the time estimates, the start and finish times for each activity
are worked out by applying forward and backward pass techniques, critical
path is identified, along with the slack and float for the non-critical paths.
Controlling:
Controlling refers to analyzing and evaluating the actual progress
against the plan. Reallocation of resources, crashing and review of projects
with periodical reports are carried out.
COMPONENTS of PERT/CPM NETWORK
PERT / CPM networks contain two major components
i. Activities, and
ii. Events
Activity: An activity represents an action and consumption of
resources (time, money, energy) required to complete a portion of a
project. Activity is represented by an arrow, (Figure 8.1).
Event: An event (or node) will always occur at the beginning and end of an
activity. The event has no resources and is represented by a circle. The ith event
and jth event are the tail event and head event respectively, (Figure 8.2).
Merge and Burst Events
One or more activities can start and end simultaneously at an event (Figure 8.3 a, b).
Preceding and Succeeding Activities
Activities performed before given events are known as preceding activities (Figure
8.4), and activities performed after a given event are known as succeeding activities.
Activities A and B precede activities C and D respectively.
Dummy Activity
An imaginary activity which does not consume any resource and time is called a
dummy activity. Dummy activities are simply used to represent a connection
between events in order to maintain a logic in the network. It is represented by a
dotted line in a network, see Figure 8.5.
ERRORS TO BE AVOIDED IN CONSTRUCTING A NETWORK
a. Two activities starting from a tail event
must not have a same end event. To ensure
this, it is absolutely necessary to introduce a
dummy activity, as shown in Figure 8.6.
b. Looping error should not be formed in a
network, as it represents performance of
activities repeatedly in a cyclic manner, as
shown below in Figure 8.7.
c. In a network, there should be only one
start event and one ending event as shown
below, in Figure 8.8.
d. The direction of arrows should
flow from left to right avoiding
mixing of direction as shown in
Figure 8.9.
RULES IN CONSTRUCTING A NETWORK
1. No single activity can be represented more than once in a network.
The length of an arrow has no significance.
2. The event numbered 1 is the start event and an event with highest
number is the end event. Before an activity can be undertaken, all
activities preceding it must be completed. That is, the activities must
follow a logical sequence (or – interrelationship) between activities.
3. In assigning numbers to events, there should not be any duplication of
event numbers in a network.
4. Dummy activities must be used only if it is necessary to reduce the
complexity of a network.
5. A network should have only one start event and one end event.
Some conventions of network diagram are shown in Figure 8.10
(a), (b), (c), (d) below:
PROCEDURE FOR NUMBERING THE EVENTS
USING FULKERSON'S RULE
Step1: Number the start or initial event as 1.
Step2: From event 1, strike off all outgoing activities. This would have
made one or more events as initial events (event which do not have
incoming activities). Number that event as 2.
Step3: Repeat step 2 for event 2, event 3 and till the end event. The end
event must have the highest number
Example 1:
Draw a network for a house construction project. The sequence of
activities with their predecessors are given in Table 8.1, below.
The network diagram in Figure 8.11 shows the procedure relationship
between the activities. Activity A (preparation of house plan), has a start
event 1 as well as an ending event 2. Activity B (Construction of house)
begins at event 2 and ends at event 3. The activity B cannot start until
activity A has been completed. Activities C and D cannot begin until
activity B has been completed, but they can be performed
simultaneously. Similarly, activities E and F can start only after
completion of activities C and D respectively. Both activities E and F
finish at the end of event 6.
Example 2: Consider the project given in Table 8.2 and construct a
network diagram. Table 8.2: Sequence of Activities for Building
Construction Project
Solution:
The activities C and D have a common predecessor A. The network
representation shown in Figure 8.12 (a), (b) violates the rule that no two activities
can begin and end at the same events. It appears as if activity B is a predecessor of
activity C, which is not the case. To construct the network in a logical order, it is
necessary to introduce a dummy activity as shown in Figure 8.12.
Example 3:
Construct a network for a project whose activities and their predecessor relationship
are given in Table 8.3.
Solution: The network diagram for the given problem is shown in Figure 8.14
with activities A, B and C starting simultaneously.
Example 4: Draw a network diagram for
a project given in Table 8.4.
Solution: An activity network diagram describing the project is shown in
Figure 8.15, below:
CRITICAL PATH ANALYSIS
The critical path for any network is the longest path through the entire network.
Since all activities must be completed to complete the entire project, the length
of the critical path is also the shortest time allowable for completion of the
project.
Thus if the project is to be completed in that shortest time, all activities on the
critical path must be started as soon as possible.
These activities are called critical activities.
If the project has to be completed ahead of the schedule, then the time required
for at least one of the critical activity must be reduced.
Further, any delay in completing the critical activities will increase the project
duration.
The activity, which does not lie on the critical path, is called non-critical
activity.
These non-critical activities may have some slack time.
The slack is the amount of time by which the start of an activity may be
delayed without affecting the overall completion time of the project.
But a critical activity has no slack.
To reduce the overall project time, it would require more resources (at
extra cost) to reduce the time taken by the critical activities to complete.
Scheduling of Activities: Earliest Time (TE) and Latest
Time(TL)
Before the critical path in a network is determined, it is necessary to
find the earliest and latest time of each event to know the earliest
expected time (TE) at which the activities originating from the event
can be started and to know the latest allowable time (TL) at which
activities terminating at the event can be completed.
Forward Pass Computations (to calculate Earliest, Time TE)
Step 1: Begin from the start event and move towards the end event.
Step 2: Put TE = 0 for the start event.
Step 3: Go to the next event (i.e node 2) if there is an incoming activity for event 2,
add calculate TE of previous event (i.e event 1) and activity time.
Note: If there are more than one incoming activities, calculate TE for all incoming
activities and take the maximum value. This value is the TE for event 2.
Step 4: Repeat the same procedure from step 3 till the end event.
Backward Pass Computations (to calculate Latest Time TL)
Procedure :
Step 1: Begin from end event and move towards the start event. Assume that
the direction of arrows is reversed.
Step 2: Latest Time TL for the last event is the earliest time. TE of the last
event.
Step 3: Go to the next event, if there is an incoming activity, subtract the value
of TL of previous event from the activity duration time. The arrived value is
TL for that event. If there are more than one incoming activities, take the
minimum TE value.
Step 4: Repeat the same procedure from step 2 till the start event.
DETERMINATION OF FLOAT AND SLACK TIMES
As discussed earlier, the non – critical activities have some slack or float.
The float of an activity is the amount of time available by which it is
possible to delay its completion time without extending the overall
project completion time.
tij = duration of activity
TE = earliest expected time
TL = latest allowable time
ESij = earliest start time of the activity
EFij = earliest finish time of the activity
LSij = latest start time of the activity
LFij = latest finish time of the activity
Total Float TFij: The total float of an activity is the difference between the
latest start time and the earliest start time of that activity.
TFij = LS ij – ESij ....................(1)
or
TFij = (TL – TE) – tij …………..(ii)
Free Float FFij: The time by which the completion of an activity can be
delayed from its earliest finish time without affecting the earliest start
time of the succeeding activity is called free float.
FF ij = (Ej – Ei) – tij ....................(3)
FFij = Total float – Head event slack
Independent Float IFij: The amount of time by which the start of an activity
can be delayed without affecting the earliest start time of any immediately
following activities, assuming that the preceding activity has finished at its
latest finish time.
IF ij = (Ej – Li) – tij ....................(4)
IFij = Free float – Tail event slack Where tail event slack = Li – Ei
The negative value of independent float is considered to be zero.
Critical Path:
After determining the earliest and the latest scheduled times for
various activities, the minimum time required to complete the
project is calculated. In a network, among various paths, the
longest path which determines the total time duration of the
project is called the critical path. The following conditions must
be satisfied in locating the critical path of a network.
An activity is said to be critical only if both the conditions are satisfied.
1. TL – TE = 0
2. TLj – tij – TEj = 0
Example :
A project schedule has the following characteristics as shown in Table
i. Construct PERT network.
ii. Compute TE and TL for
each activity.
iii. Find the critical path.
(i) From the data given in the problem, the activity network is constructed as
shown in Figure given below
(ii) To determine the critical path, compute the earliest, time TE and
latest time TL for each of the activity of the project. The calculations of TE
and TL are as follows:,
To calculate TE for all activities
TE1 = 0
TE2 = TE1 + t1, 2 = 0 + 4 = 4
TE3 = TE1 + t1, 3 = 0 + 1 =1
TE4 = max (TE2 + t2, 4 and TE3 + t3, 4)
= max (4 + 1 and 1 + 1) = max (5, 2)
= 5 days
TE5 = TE3 + t3, 6 = 1 + 6 = 7
TE6 = TE5 + t5, 6 = 7 + 4 = 11
TE7 = TE5 + t5, 7 = 7 + 8 = 15
TE8 = max (TE6 + t6, 8 and TE7 + t7, 8)
= max (11 + 1 and 15 + 2) = max (12, 17)
= 17 days
TE9 = TE4 + t4, 9 = 5 + 5 = 10
TE10 = max (TE9 + t9, 10 and TE8 + t8, 10)
= max (10 + 7 and 17 + 5) = max (17, 22)
= 22 days
To calculate TL for all activities
TL10 = TE10 = 22
TL9 = TE10 – t9,10 = 22 – 7 = 15
TL8 = TE10 – t8, 10 = 22 – 5 = 17
TL7 = TE8 – t7, 8 = 17 – 2 = 15
TL6 = TE8 – t6, 8 = 17 – 1 = 16
TL5 = min (TE6 – t5, 6 and TE7 – t5, 7)
= min (16 – 4 and 15 –8) = min (12, 7)
= 7 days
TL4 = TL9 – t4, 9 = 15 – 5 =10
TL3 = min (TL4 – t3, 4 and TL5 – t3, 5 )
= min (10 – 1 and 7 – 6) = min (9, 1)
= 1 day
TL2 = TL4 – t2, 4 = 10 – 1 = 9
TL1 = Min (TL2 – t1, 2 and TL3 – t1, 3)
= Min (9 – 4 and 1 – 1) = 0
(iii) From the Table 8.6, we observe that the
activities 1 – 3, 3 – 5, 5 – 7,7 – 8 and 8 – 10 are
critical activities as their floats are zero.
PROJECT EVALUATION REVIEW TECHNIQUE, (PERT)
In the critical path method, the time estimates are assumed to be
known with certainty. In certain projects like research and
development, new product introductions, it is difficult to estimate
the time of various activities.
Hence PERT is used in such projects with a probabilistic method using three time
estimates for an activity, rather than a single estimate, as shown in Figure 8.22.
Optimistic time tO:
It is the shortest time taken to complete the
activity. It means that if everything goes well
then there is more chance of completing the
activity within this time.
Most likely time tm:
It is the normal time taken to complete an activity,
if the activity were frequently repeated under the
same conditions.
Pessimistic time tp:
It is the longest time that an activity would take to
complete. It is the worst time estimate that an
activity would take if unexpected problems are
faced.
Taking all these time estimates into consideration, the expected time
of an activity is arrived at.
The average or mean (ta) value of
the activity duration is given by,
The variance of the activity time
is calculated using the formula,
The probability of completing the
project within the scheduled time (Ts) or
contracted time may be obtained by
using the standard normal deviate
where Te is the expected time of project
completion.
Probability for Project Duration
Probability of completing the project
within the scheduled time is,
An R & D project has a list of tasks to be performed whose time estimates are
given in the Table 8.11, as follows.
Example
a. Draw the project network.
b. Find the critical path.
c. Find the probability that the project is completed in 19 days. If the
probability is less that 20%, find the probability of completing it in 24 days.
Time expected for each activity is
calculated using the formula (5):
Similarly, the expected time is
calculated for all the activities.
The variance of activity time is
calculated using the formula (6).
Similarly, variances of all the
activities are calculated.
calculate the time earliest, TE and
time Latest TL for all the activities.
Construct a network diagram:
From the network diagram Figure 8.24, the critical path is identified as
1-4, 4-6, 6-7, with a project duration of 22 days.
The probability of completing the project within 19 days is given by, P (Z< Z0)
To find Z0 ,
we know, P (Z <Z Network Model 0) = 0.5 – z (1.3416) (from normal tables, z (1.3416) = 0.4099)
= 0.5 – 0.4099
= 0.0901
= 9.01% Thus, the probability of completing the R & D project in 19 days is 9.01%.
Since the probability of completing the project in 19 days is less than 20% As in
question, we find the probability of completing it in 24 days.
COST ANALYSIS
The two important components of any activity are the cost and time. Cost is
directly proportional to time and vice versa.
For example, in constructing a shopping complex, the expected time of completion
can be calculated using be time estimates of various activities. But if the
construction has to the finished earlier, it requires additional cost to complete the
project. We need to arrive at a time / cost trade-off between total cost of project
and total time required to complete it.
Normal time:
Normal time is the time required to complete
the activity at normal conditions and cost.
Crash time:
Crash time is the shortest possible activity
time; crashing more than the normal time
will increase the direct cost.
Cost Slope
Cost slope is the increase in cost per unit of
time saved by crashing. A linear cost curve
is shown in Figure 8.27.
An activity takes 4 days to complete at a normal cost of Rs. 500.00. If it is possible
to complete the activity in 2 days with an additional cost of Rs. 700.00, what is the
incremental cost of the activity?
Example
Incremental Cost or Cost Slope
It means, if one day is reduced we have to spend Rs. 100/- extra per day.
Project Crashing
Procedure for crashing
Step1: Draw the network diagram and mark the Normal time and Crash time.
Step2: Calculate TE and TL for all the activities.
Step3: Find the critical path and other paths.
Step 4: Find the slope for all activities and rank them in ascending order.
Step 5: Establish a tabular column with required field.
Step 6: Select the lowest ranked activity; check whether it is a critical activity. If
so,crash the activity, else go to the next highest ranked activity.
Note: The critical path must remain critical while crashing.
Step 7: Calculate the total cost of project for each crashing
Step 8: Repeat Step 6 until all the activities in the critical path are fully
crashed.
Example
The following Table
8.13 gives the activities
of a construction
project and other data.
If the indirect cost is Rs. 20 per day, crash the activities to find the
minimum duration of the project and the project cost associated.
From the data provided in the table, draw the network diagram (Figure 8.28)
and find the critical path.
Solution
From the diagram, we observe that the
critical path is 1-2-5 with project duration of
14 days
The cost slope for all activities and their rank
is calculated as shown in Table 8.14
The available paths of the network are listed down in Table 8.15
indicating the sequence of crashing (see Figure 8.29).
The sequence of crashing and
the total cost involved is given
in Table 8.16 Initial direct cost
= sum of all normal costs given
= Rs. 490.00
It is not possible to crash more than 10 days, as all the activities in
the critical path are fully crashed. Hence the minimum project
duration is 10 days with the total cost of Rs. 970.00.
Assignment
a. Draw the project network diagram.
b. Calculate the length and variance of the critical path.
c. What is the probability that the jobs on the critical path can be
completed in 41 days?

More Related Content

What's hot

Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
hoang tung
 
Pert cpm
Pert cpmPert cpm
Pert cpm
haithamallibhai
 
Network analysis & cpm
Network analysis & cpmNetwork analysis & cpm
Network analysis & cpm
Ganesh Kandalkar
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
El Moro
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
S.Vijaya Bhaskar
 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pert
DagnaygebawGoshme
 
Pert cpm-22-3-21
Pert cpm-22-3-21Pert cpm-22-3-21
Pert cpm-22-3-21
Chhaya Narvekar
 
Applications of pert
Applications of pertApplications of pert
Applications of pert
nitigga92
 
Network diagrams
Network diagramsNetwork diagrams
Network diagramsNicola2903
 
PERT
PERTPERT
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Rules for Network Construction
Rules for Network ConstructionRules for Network Construction
Rules for Network Construction
Raja Adapa
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
sushantvwaghmare
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network DiagramsNicola2903
 
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
Shashank Kapoor
 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path Ppt
Jeff Hilton
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Abhishek Pachisia
 

What's hot (20)

Pert
PertPert
Pert
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Network analysis & cpm
Network analysis & cpmNetwork analysis & cpm
Network analysis & cpm
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pert
 
Pert cpm-22-3-21
Pert cpm-22-3-21Pert cpm-22-3-21
Pert cpm-22-3-21
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
Applications of pert
Applications of pertApplications of pert
Applications of pert
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
PERT
PERTPERT
PERT
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Rules for Network Construction
Rules for Network ConstructionRules for Network Construction
Rules for Network Construction
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
 
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path Ppt
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 

Similar to Network problem cpm and pert BY MITESH KUMAR

Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01
Sonali Srivastava
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
Pulchowk Campus
 
PERT-CPM PPT.pptx
PERT-CPM PPT.pptxPERT-CPM PPT.pptx
PERT-CPM PPT.pptx
DhesinghRajaLekha
 
CPM and PERT
CPM and  PERTCPM and  PERT
CPM and PERT
Mamatha Upadhya
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
IrtizaMalik
 
Pert & cpm
Pert & cpmPert & cpm
Pert & cpm
Moudud Hasan
 
ch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþttttttttttttttch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþtttttttttttttt
AbdisalamMohamud5
 
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysis
Dr.R. SELVAM
 
PERT-Overview1.pdf
PERT-Overview1.pdfPERT-Overview1.pdf
PERT-Overview1.pdf
IrfanPathan88
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
BetshaTizazu2
 
Chap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxChap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptx
mohammad_bilal
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOL
Siddanna Balapgol
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
Naganna Chetty
 
Network analysis
Network analysisNetwork analysis
Network analysis
Mohit Mahajan
 
CPM PERT.pptx
CPM PERT.pptxCPM PERT.pptx
CPM PERT.pptx
MumtazAli889808
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
TecnicoItca
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdf
Salahudin Babar
 
Lecture 2 PERT-CPM.pdf
Lecture 2 PERT-CPM.pdfLecture 2 PERT-CPM.pdf
Lecture 2 PERT-CPM.pdf
AbdulMajeetMohamed
 
Project Management
Project ManagementProject Management
Project Management
Nandi Sudheer
 

Similar to Network problem cpm and pert BY MITESH KUMAR (20)

Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01Appliedresearchmethodologylecture1 111207045430-phpapp01
Appliedresearchmethodologylecture1 111207045430-phpapp01
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Ovi project
Ovi  projectOvi  project
Ovi project
 
PERT-CPM PPT.pptx
PERT-CPM PPT.pptxPERT-CPM PPT.pptx
PERT-CPM PPT.pptx
 
CPM and PERT
CPM and  PERTCPM and  PERT
CPM and PERT
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
 
Pert & cpm
Pert & cpmPert & cpm
Pert & cpm
 
ch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþttttttttttttttch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþtttttttttttttt
 
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysis
 
PERT-Overview1.pdf
PERT-Overview1.pdfPERT-Overview1.pdf
PERT-Overview1.pdf
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Chap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxChap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptx
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOL
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
Network analysis
Network analysisNetwork analysis
Network analysis
 
CPM PERT.pptx
CPM PERT.pptxCPM PERT.pptx
CPM PERT.pptx
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdf
 
Lecture 2 PERT-CPM.pdf
Lecture 2 PERT-CPM.pdfLecture 2 PERT-CPM.pdf
Lecture 2 PERT-CPM.pdf
 
Project Management
Project ManagementProject Management
Project Management
 

More from Mitesh Kumar

Embeded system by Mitesh Kumar
Embeded system by Mitesh KumarEmbeded system by Mitesh Kumar
Embeded system by Mitesh Kumar
Mitesh Kumar
 
Fiber optics measurement Technique by mitesh kumar
Fiber optics measurement Technique by mitesh kumarFiber optics measurement Technique by mitesh kumar
Fiber optics measurement Technique by mitesh kumar
Mitesh Kumar
 
Microcontroller 8051 By Mitesh kumar
Microcontroller 8051 By Mitesh kumarMicrocontroller 8051 By Mitesh kumar
Microcontroller 8051 By Mitesh kumar
Mitesh Kumar
 
Temperature measurement By Mitesh Kumar
Temperature  measurement By Mitesh KumarTemperature  measurement By Mitesh Kumar
Temperature measurement By Mitesh Kumar
Mitesh Kumar
 
Synchronous machine by Mitesh Kumar
Synchronous machine by Mitesh KumarSynchronous machine by Mitesh Kumar
Synchronous machine by Mitesh Kumar
Mitesh Kumar
 
Three phase induction motor By Mitesh Kumar
Three phase induction motor By Mitesh KumarThree phase induction motor By Mitesh Kumar
Three phase induction motor By Mitesh Kumar
Mitesh Kumar
 
Transmitter By MItesh Kumar
Transmitter By MItesh KumarTransmitter By MItesh Kumar
Transmitter By MItesh Kumar
Mitesh Kumar
 
Temperature measurement By Mitesh Kumar
Temperature  measurement By Mitesh KumarTemperature  measurement By Mitesh Kumar
Temperature measurement By Mitesh Kumar
Mitesh Kumar
 
Resistance Temperature Detector By Mitesh Kumar
Resistance Temperature Detector By Mitesh KumarResistance Temperature Detector By Mitesh Kumar
Resistance Temperature Detector By Mitesh Kumar
Mitesh Kumar
 
Synchronous machine Mitesh Kumar
Synchronous machine Mitesh KumarSynchronous machine Mitesh Kumar
Synchronous machine Mitesh Kumar
Mitesh Kumar
 
Pressure measurement id Mitesh Kuamr
Pressure measurement id Mitesh KuamrPressure measurement id Mitesh Kuamr
Pressure measurement id Mitesh Kuamr
Mitesh Kumar
 
Piezoelectric pressure sensor Mitesh Kumar
Piezoelectric pressure sensor Mitesh KumarPiezoelectric pressure sensor Mitesh Kumar
Piezoelectric pressure sensor Mitesh Kumar
Mitesh Kumar
 
Optical measurent Mitesh kumar
Optical measurent Mitesh kumarOptical measurent Mitesh kumar
Optical measurent Mitesh kumar
Mitesh Kumar
 
Net neutrality by Mitesh Kumar
Net neutrality by Mitesh KumarNet neutrality by Mitesh Kumar
Net neutrality by Mitesh Kumar
Mitesh Kumar
 
Dc to Ac inverter By Mitesh Kumar
Dc to Ac inverter By Mitesh KumarDc to Ac inverter By Mitesh Kumar
Dc to Ac inverter By Mitesh Kumar
Mitesh Kumar
 
Pid controller by Mitesh Kumar
Pid controller by Mitesh KumarPid controller by Mitesh Kumar
Pid controller by Mitesh Kumar
Mitesh Kumar
 
Water pollution treatment BY Mitesh Kumar
Water pollution treatment BY Mitesh KumarWater pollution treatment BY Mitesh Kumar
Water pollution treatment BY Mitesh Kumar
Mitesh Kumar
 
Biomass ppt By Mitesh Kumar
Biomass ppt By Mitesh KumarBiomass ppt By Mitesh Kumar
Biomass ppt By Mitesh Kumar
Mitesh Kumar
 
Humanoid robot by mitesh kumar
Humanoid robot by mitesh kumarHumanoid robot by mitesh kumar
Humanoid robot by mitesh kumar
Mitesh Kumar
 
Humanoid robot by Mitesh kumar
Humanoid robot by Mitesh kumar Humanoid robot by Mitesh kumar
Humanoid robot by Mitesh kumar
Mitesh Kumar
 

More from Mitesh Kumar (20)

Embeded system by Mitesh Kumar
Embeded system by Mitesh KumarEmbeded system by Mitesh Kumar
Embeded system by Mitesh Kumar
 
Fiber optics measurement Technique by mitesh kumar
Fiber optics measurement Technique by mitesh kumarFiber optics measurement Technique by mitesh kumar
Fiber optics measurement Technique by mitesh kumar
 
Microcontroller 8051 By Mitesh kumar
Microcontroller 8051 By Mitesh kumarMicrocontroller 8051 By Mitesh kumar
Microcontroller 8051 By Mitesh kumar
 
Temperature measurement By Mitesh Kumar
Temperature  measurement By Mitesh KumarTemperature  measurement By Mitesh Kumar
Temperature measurement By Mitesh Kumar
 
Synchronous machine by Mitesh Kumar
Synchronous machine by Mitesh KumarSynchronous machine by Mitesh Kumar
Synchronous machine by Mitesh Kumar
 
Three phase induction motor By Mitesh Kumar
Three phase induction motor By Mitesh KumarThree phase induction motor By Mitesh Kumar
Three phase induction motor By Mitesh Kumar
 
Transmitter By MItesh Kumar
Transmitter By MItesh KumarTransmitter By MItesh Kumar
Transmitter By MItesh Kumar
 
Temperature measurement By Mitesh Kumar
Temperature  measurement By Mitesh KumarTemperature  measurement By Mitesh Kumar
Temperature measurement By Mitesh Kumar
 
Resistance Temperature Detector By Mitesh Kumar
Resistance Temperature Detector By Mitesh KumarResistance Temperature Detector By Mitesh Kumar
Resistance Temperature Detector By Mitesh Kumar
 
Synchronous machine Mitesh Kumar
Synchronous machine Mitesh KumarSynchronous machine Mitesh Kumar
Synchronous machine Mitesh Kumar
 
Pressure measurement id Mitesh Kuamr
Pressure measurement id Mitesh KuamrPressure measurement id Mitesh Kuamr
Pressure measurement id Mitesh Kuamr
 
Piezoelectric pressure sensor Mitesh Kumar
Piezoelectric pressure sensor Mitesh KumarPiezoelectric pressure sensor Mitesh Kumar
Piezoelectric pressure sensor Mitesh Kumar
 
Optical measurent Mitesh kumar
Optical measurent Mitesh kumarOptical measurent Mitesh kumar
Optical measurent Mitesh kumar
 
Net neutrality by Mitesh Kumar
Net neutrality by Mitesh KumarNet neutrality by Mitesh Kumar
Net neutrality by Mitesh Kumar
 
Dc to Ac inverter By Mitesh Kumar
Dc to Ac inverter By Mitesh KumarDc to Ac inverter By Mitesh Kumar
Dc to Ac inverter By Mitesh Kumar
 
Pid controller by Mitesh Kumar
Pid controller by Mitesh KumarPid controller by Mitesh Kumar
Pid controller by Mitesh Kumar
 
Water pollution treatment BY Mitesh Kumar
Water pollution treatment BY Mitesh KumarWater pollution treatment BY Mitesh Kumar
Water pollution treatment BY Mitesh Kumar
 
Biomass ppt By Mitesh Kumar
Biomass ppt By Mitesh KumarBiomass ppt By Mitesh Kumar
Biomass ppt By Mitesh Kumar
 
Humanoid robot by mitesh kumar
Humanoid robot by mitesh kumarHumanoid robot by mitesh kumar
Humanoid robot by mitesh kumar
 
Humanoid robot by Mitesh kumar
Humanoid robot by Mitesh kumar Humanoid robot by Mitesh kumar
Humanoid robot by Mitesh kumar
 

Recently uploaded

Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
DianaGray10
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
Prayukth K V
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
Alan Dix
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
James Anderson
 
ODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User GroupODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User Group
CatarinaPereira64715
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
UiPathCommunity
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
OnBoard
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
Thijs Feryn
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
Sri Ambati
 
PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)
Ralf Eggert
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Product School
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
91mobiles
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance
 
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxIOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
Abida Shariff
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
Product School
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Thierry Lestable
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Jeffrey Haguewood
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
DianaGray10
 

Recently uploaded (20)

Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
 
ODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User GroupODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User Group
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 
PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxIOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
 

Network problem cpm and pert BY MITESH KUMAR

  • 1. MITESH KUMAR Rall No-13/ EI/26 Applied Electronics & Instrumentation Engg. Haldia Institute of Technology
  • 2. Introduction  Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time.  The projects may be extremely large and complex such as construction of a housing , a highway, a shopping complex etc.  introduction of new products and research and development projects.  It is required that managers must have a dynamic planning and scheduling system to produce the best possible results and also to react immediately to the changing conditions and make necessary changes in the plan and schedule.
  • 3. A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects. PERT stands for Project Evaluation and Review Technique developed during 1950’s. The technique was developed and used in conjunction with the planning and designing of the Polaris missile project. CPM stands for Critical Path Method which was developed by DuPont Company and applied first to the construction projects in the chemical industry. Though both PERT and CPM techniques have similarity in terms of concepts, the basic difference is, PERT is used for analysis of project scheduling problems. CPM has single time estimate and PERT has three time estimates for activities and uses probability theory to find the chance of reaching the scheduled time.
  • 4. Project management generally consists of three phases. Planning: Planning involves setting the objectives of the project. Identifying various activities to be performed and determining the requirement of resources such as men, materials, machines, etc. The cost and time for all the activities are estimated, and a network diagram is developed showing sequential interrelationships (predecessor and successor) between various activities during the planning stage. Scheduling: Basd on the time estimates, the start and finish times for each activity are worked out by applying forward and backward pass techniques, critical path is identified, along with the slack and float for the non-critical paths. Controlling: Controlling refers to analyzing and evaluating the actual progress against the plan. Reallocation of resources, crashing and review of projects with periodical reports are carried out.
  • 5. COMPONENTS of PERT/CPM NETWORK PERT / CPM networks contain two major components i. Activities, and ii. Events Activity: An activity represents an action and consumption of resources (time, money, energy) required to complete a portion of a project. Activity is represented by an arrow, (Figure 8.1). Event: An event (or node) will always occur at the beginning and end of an activity. The event has no resources and is represented by a circle. The ith event and jth event are the tail event and head event respectively, (Figure 8.2).
  • 6. Merge and Burst Events One or more activities can start and end simultaneously at an event (Figure 8.3 a, b). Preceding and Succeeding Activities Activities performed before given events are known as preceding activities (Figure 8.4), and activities performed after a given event are known as succeeding activities. Activities A and B precede activities C and D respectively.
  • 7. Dummy Activity An imaginary activity which does not consume any resource and time is called a dummy activity. Dummy activities are simply used to represent a connection between events in order to maintain a logic in the network. It is represented by a dotted line in a network, see Figure 8.5.
  • 8. ERRORS TO BE AVOIDED IN CONSTRUCTING A NETWORK a. Two activities starting from a tail event must not have a same end event. To ensure this, it is absolutely necessary to introduce a dummy activity, as shown in Figure 8.6. b. Looping error should not be formed in a network, as it represents performance of activities repeatedly in a cyclic manner, as shown below in Figure 8.7. c. In a network, there should be only one start event and one ending event as shown below, in Figure 8.8. d. The direction of arrows should flow from left to right avoiding mixing of direction as shown in Figure 8.9.
  • 9. RULES IN CONSTRUCTING A NETWORK 1. No single activity can be represented more than once in a network. The length of an arrow has no significance. 2. The event numbered 1 is the start event and an event with highest number is the end event. Before an activity can be undertaken, all activities preceding it must be completed. That is, the activities must follow a logical sequence (or – interrelationship) between activities. 3. In assigning numbers to events, there should not be any duplication of event numbers in a network. 4. Dummy activities must be used only if it is necessary to reduce the complexity of a network. 5. A network should have only one start event and one end event.
  • 10. Some conventions of network diagram are shown in Figure 8.10 (a), (b), (c), (d) below:
  • 11. PROCEDURE FOR NUMBERING THE EVENTS USING FULKERSON'S RULE Step1: Number the start or initial event as 1. Step2: From event 1, strike off all outgoing activities. This would have made one or more events as initial events (event which do not have incoming activities). Number that event as 2. Step3: Repeat step 2 for event 2, event 3 and till the end event. The end event must have the highest number Example 1: Draw a network for a house construction project. The sequence of activities with their predecessors are given in Table 8.1, below.
  • 12.
  • 13. The network diagram in Figure 8.11 shows the procedure relationship between the activities. Activity A (preparation of house plan), has a start event 1 as well as an ending event 2. Activity B (Construction of house) begins at event 2 and ends at event 3. The activity B cannot start until activity A has been completed. Activities C and D cannot begin until activity B has been completed, but they can be performed simultaneously. Similarly, activities E and F can start only after completion of activities C and D respectively. Both activities E and F finish at the end of event 6. Example 2: Consider the project given in Table 8.2 and construct a network diagram. Table 8.2: Sequence of Activities for Building Construction Project
  • 14. Solution: The activities C and D have a common predecessor A. The network representation shown in Figure 8.12 (a), (b) violates the rule that no two activities can begin and end at the same events. It appears as if activity B is a predecessor of activity C, which is not the case. To construct the network in a logical order, it is necessary to introduce a dummy activity as shown in Figure 8.12.
  • 15. Example 3: Construct a network for a project whose activities and their predecessor relationship are given in Table 8.3. Solution: The network diagram for the given problem is shown in Figure 8.14 with activities A, B and C starting simultaneously.
  • 16. Example 4: Draw a network diagram for a project given in Table 8.4. Solution: An activity network diagram describing the project is shown in Figure 8.15, below:
  • 17. CRITICAL PATH ANALYSIS The critical path for any network is the longest path through the entire network. Since all activities must be completed to complete the entire project, the length of the critical path is also the shortest time allowable for completion of the project. Thus if the project is to be completed in that shortest time, all activities on the critical path must be started as soon as possible. These activities are called critical activities. If the project has to be completed ahead of the schedule, then the time required for at least one of the critical activity must be reduced. Further, any delay in completing the critical activities will increase the project duration.
  • 18. The activity, which does not lie on the critical path, is called non-critical activity. These non-critical activities may have some slack time. The slack is the amount of time by which the start of an activity may be delayed without affecting the overall completion time of the project. But a critical activity has no slack. To reduce the overall project time, it would require more resources (at extra cost) to reduce the time taken by the critical activities to complete.
  • 19. Scheduling of Activities: Earliest Time (TE) and Latest Time(TL) Before the critical path in a network is determined, it is necessary to find the earliest and latest time of each event to know the earliest expected time (TE) at which the activities originating from the event can be started and to know the latest allowable time (TL) at which activities terminating at the event can be completed. Forward Pass Computations (to calculate Earliest, Time TE) Step 1: Begin from the start event and move towards the end event. Step 2: Put TE = 0 for the start event. Step 3: Go to the next event (i.e node 2) if there is an incoming activity for event 2, add calculate TE of previous event (i.e event 1) and activity time. Note: If there are more than one incoming activities, calculate TE for all incoming activities and take the maximum value. This value is the TE for event 2. Step 4: Repeat the same procedure from step 3 till the end event.
  • 20. Backward Pass Computations (to calculate Latest Time TL) Procedure : Step 1: Begin from end event and move towards the start event. Assume that the direction of arrows is reversed. Step 2: Latest Time TL for the last event is the earliest time. TE of the last event. Step 3: Go to the next event, if there is an incoming activity, subtract the value of TL of previous event from the activity duration time. The arrived value is TL for that event. If there are more than one incoming activities, take the minimum TE value. Step 4: Repeat the same procedure from step 2 till the start event.
  • 21. DETERMINATION OF FLOAT AND SLACK TIMES As discussed earlier, the non – critical activities have some slack or float. The float of an activity is the amount of time available by which it is possible to delay its completion time without extending the overall project completion time. tij = duration of activity TE = earliest expected time TL = latest allowable time ESij = earliest start time of the activity EFij = earliest finish time of the activity LSij = latest start time of the activity LFij = latest finish time of the activity Total Float TFij: The total float of an activity is the difference between the latest start time and the earliest start time of that activity. TFij = LS ij – ESij ....................(1) or TFij = (TL – TE) – tij …………..(ii)
  • 22. Free Float FFij: The time by which the completion of an activity can be delayed from its earliest finish time without affecting the earliest start time of the succeeding activity is called free float. FF ij = (Ej – Ei) – tij ....................(3) FFij = Total float – Head event slack Independent Float IFij: The amount of time by which the start of an activity can be delayed without affecting the earliest start time of any immediately following activities, assuming that the preceding activity has finished at its latest finish time. IF ij = (Ej – Li) – tij ....................(4) IFij = Free float – Tail event slack Where tail event slack = Li – Ei The negative value of independent float is considered to be zero.
  • 23. Critical Path: After determining the earliest and the latest scheduled times for various activities, the minimum time required to complete the project is calculated. In a network, among various paths, the longest path which determines the total time duration of the project is called the critical path. The following conditions must be satisfied in locating the critical path of a network. An activity is said to be critical only if both the conditions are satisfied. 1. TL – TE = 0 2. TLj – tij – TEj = 0 Example : A project schedule has the following characteristics as shown in Table i. Construct PERT network. ii. Compute TE and TL for each activity. iii. Find the critical path.
  • 24. (i) From the data given in the problem, the activity network is constructed as shown in Figure given below
  • 25. (ii) To determine the critical path, compute the earliest, time TE and latest time TL for each of the activity of the project. The calculations of TE and TL are as follows:, To calculate TE for all activities TE1 = 0 TE2 = TE1 + t1, 2 = 0 + 4 = 4 TE3 = TE1 + t1, 3 = 0 + 1 =1 TE4 = max (TE2 + t2, 4 and TE3 + t3, 4) = max (4 + 1 and 1 + 1) = max (5, 2) = 5 days TE5 = TE3 + t3, 6 = 1 + 6 = 7 TE6 = TE5 + t5, 6 = 7 + 4 = 11 TE7 = TE5 + t5, 7 = 7 + 8 = 15 TE8 = max (TE6 + t6, 8 and TE7 + t7, 8) = max (11 + 1 and 15 + 2) = max (12, 17) = 17 days TE9 = TE4 + t4, 9 = 5 + 5 = 10 TE10 = max (TE9 + t9, 10 and TE8 + t8, 10) = max (10 + 7 and 17 + 5) = max (17, 22) = 22 days To calculate TL for all activities TL10 = TE10 = 22 TL9 = TE10 – t9,10 = 22 – 7 = 15 TL8 = TE10 – t8, 10 = 22 – 5 = 17 TL7 = TE8 – t7, 8 = 17 – 2 = 15 TL6 = TE8 – t6, 8 = 17 – 1 = 16 TL5 = min (TE6 – t5, 6 and TE7 – t5, 7) = min (16 – 4 and 15 –8) = min (12, 7) = 7 days TL4 = TL9 – t4, 9 = 15 – 5 =10 TL3 = min (TL4 – t3, 4 and TL5 – t3, 5 ) = min (10 – 1 and 7 – 6) = min (9, 1) = 1 day TL2 = TL4 – t2, 4 = 10 – 1 = 9 TL1 = Min (TL2 – t1, 2 and TL3 – t1, 3) = Min (9 – 4 and 1 – 1) = 0
  • 26.
  • 27. (iii) From the Table 8.6, we observe that the activities 1 – 3, 3 – 5, 5 – 7,7 – 8 and 8 – 10 are critical activities as their floats are zero.
  • 28. PROJECT EVALUATION REVIEW TECHNIQUE, (PERT) In the critical path method, the time estimates are assumed to be known with certainty. In certain projects like research and development, new product introductions, it is difficult to estimate the time of various activities. Hence PERT is used in such projects with a probabilistic method using three time estimates for an activity, rather than a single estimate, as shown in Figure 8.22. Optimistic time tO: It is the shortest time taken to complete the activity. It means that if everything goes well then there is more chance of completing the activity within this time. Most likely time tm: It is the normal time taken to complete an activity, if the activity were frequently repeated under the same conditions. Pessimistic time tp: It is the longest time that an activity would take to complete. It is the worst time estimate that an activity would take if unexpected problems are faced.
  • 29. Taking all these time estimates into consideration, the expected time of an activity is arrived at. The average or mean (ta) value of the activity duration is given by, The variance of the activity time is calculated using the formula, The probability of completing the project within the scheduled time (Ts) or contracted time may be obtained by using the standard normal deviate where Te is the expected time of project completion. Probability for Project Duration Probability of completing the project within the scheduled time is,
  • 30. An R & D project has a list of tasks to be performed whose time estimates are given in the Table 8.11, as follows. Example a. Draw the project network. b. Find the critical path. c. Find the probability that the project is completed in 19 days. If the probability is less that 20%, find the probability of completing it in 24 days.
  • 31. Time expected for each activity is calculated using the formula (5): Similarly, the expected time is calculated for all the activities. The variance of activity time is calculated using the formula (6). Similarly, variances of all the activities are calculated.
  • 32. calculate the time earliest, TE and time Latest TL for all the activities. Construct a network diagram: From the network diagram Figure 8.24, the critical path is identified as 1-4, 4-6, 6-7, with a project duration of 22 days.
  • 33. The probability of completing the project within 19 days is given by, P (Z< Z0) To find Z0 , we know, P (Z <Z Network Model 0) = 0.5 – z (1.3416) (from normal tables, z (1.3416) = 0.4099) = 0.5 – 0.4099 = 0.0901 = 9.01% Thus, the probability of completing the R & D project in 19 days is 9.01%. Since the probability of completing the project in 19 days is less than 20% As in question, we find the probability of completing it in 24 days.
  • 34. COST ANALYSIS The two important components of any activity are the cost and time. Cost is directly proportional to time and vice versa. For example, in constructing a shopping complex, the expected time of completion can be calculated using be time estimates of various activities. But if the construction has to the finished earlier, it requires additional cost to complete the project. We need to arrive at a time / cost trade-off between total cost of project and total time required to complete it. Normal time: Normal time is the time required to complete the activity at normal conditions and cost. Crash time: Crash time is the shortest possible activity time; crashing more than the normal time will increase the direct cost. Cost Slope Cost slope is the increase in cost per unit of time saved by crashing. A linear cost curve is shown in Figure 8.27.
  • 35. An activity takes 4 days to complete at a normal cost of Rs. 500.00. If it is possible to complete the activity in 2 days with an additional cost of Rs. 700.00, what is the incremental cost of the activity? Example Incremental Cost or Cost Slope It means, if one day is reduced we have to spend Rs. 100/- extra per day. Project Crashing Procedure for crashing Step1: Draw the network diagram and mark the Normal time and Crash time. Step2: Calculate TE and TL for all the activities. Step3: Find the critical path and other paths. Step 4: Find the slope for all activities and rank them in ascending order.
  • 36. Step 5: Establish a tabular column with required field. Step 6: Select the lowest ranked activity; check whether it is a critical activity. If so,crash the activity, else go to the next highest ranked activity. Note: The critical path must remain critical while crashing. Step 7: Calculate the total cost of project for each crashing Step 8: Repeat Step 6 until all the activities in the critical path are fully crashed. Example The following Table 8.13 gives the activities of a construction project and other data. If the indirect cost is Rs. 20 per day, crash the activities to find the minimum duration of the project and the project cost associated.
  • 37. From the data provided in the table, draw the network diagram (Figure 8.28) and find the critical path. Solution From the diagram, we observe that the critical path is 1-2-5 with project duration of 14 days The cost slope for all activities and their rank is calculated as shown in Table 8.14
  • 38. The available paths of the network are listed down in Table 8.15 indicating the sequence of crashing (see Figure 8.29). The sequence of crashing and the total cost involved is given in Table 8.16 Initial direct cost = sum of all normal costs given = Rs. 490.00
  • 39. It is not possible to crash more than 10 days, as all the activities in the critical path are fully crashed. Hence the minimum project duration is 10 days with the total cost of Rs. 970.00.
  • 41.
  • 42.
  • 43. a. Draw the project network diagram. b. Calculate the length and variance of the critical path. c. What is the probability that the jobs on the critical path can be completed in 41 days?