SlideShare a Scribd company logo
Steps In Using Network Technique
•Plan the project
•Schedule the project
•Monitor the project
Plan the project:
– Analyze the project by determining all the
individual activities that must be performed to
complete it.
– Show the planned sequence of these activities on
a network(graphical representation where arrow
and circle represent the relation among acitivities
in the project ).
Schedule the project
• Estimate how long it will take to perform each
activity.
• Perform calculation to locate the critical path
(the longest time chain of sequential activities
which determines the duration of the project).
• Use this information to develop a more
economical and efficient schedule.
Monitor the project
• Use the plan to control and monitor the
progress.
• Revise and update the schedule through out
the execution of the project so that the
schedule represent the current plans and the
current status of the project.
WBS: Work Break Structure
• Project: Build a 10 storied building
• Task: A) Land acquisition, B) Land Preparation,
C) Design, D)Foundation, E)Structure, F)Walls,
G) Door Window, H) Plumbing, I) Electrical
wiring, J) Painting and decoration.
Precedence relationship
• Some activities cannot be performed until
other activities have been completed. This
type of requirements establish a technical
relationship which is called precedence
relationship.
Assign Activity Duration
• A) Land acquisition,
• B) Land Preparation,
• C) Design,
• D)Foundation,
• E)Structure,
• F)Walls,
• G) Door Window,
• H) Plumbing,
• I) Electrical wiring,
• J) Painting and
decoration.
• 2 Weeks
• 1 Week
• 3 Weeks
• 2 Weeks
• 3 Week
• 2 Weeks
• 2 Weeks
• 1 Week
• 1 Weeks
• 2 Weeks
Network convention
• A network is a graph using circles and arrows
to represent the planned relationship among
the activities required to complete the
project. Either of two conventions can be used
to develop a network:
– Activity on Node (AON): use circle to represent
activities and arrow to link them.
– Activity on Arrow (AOA): use arrow to represent
activities and circle to connect them.
Example 01
Task Predecessor Duration
A None 2
B None 8
C A 4
D A 6
E C,D 9
F B,E 11
G B 3
H F,G 1
Draw AON and AOA diagram of following project
AON
AOA
Task Predecessor Duration
A None 2
B A 6
C B 4
D A 4
E C 5
F E 6
G E 3
H F 3
I D,F 3
J F,G 5
K H 2
L J 3
M I,K,L 1
Task Optimistic time Most likely time Pessimistic time
1-2 2 3 5
2-3 3 4 6
3-6 6 8 11
2-4 5 6 9
4-6 6 8 10
4-5 4 5 6
5-7 5 6 9
6-8 2 3 4
6-7 0 0 0
7-8 1 3 5
8-9 4 5 8
9-10 2 3 5
7-10 5 9 11
• Expected Time = [(Optimistic Time + 4 x Most
likely Time + Pessimistic Time)]/6
• σ2 = [(Pessimistic Time - Optimistic Time)/6]2
Task Optimistic
time
Most likely
time
Pessimistic
time
Expected
Time (Te)
Sigma
Square
Sigma
Activity
Optimistic
Time
Most Likely
Time
Pessimistic
Time
Expected
time Sigma
Sigma
Square
1 – 2 2 3 5 3.17 0.5 0.25
2 – 3 3 4 6 4.17 0.5 0.25
3 – 6 6 8 11 8.17 0.8333 0.69444
2 – 4 5 6 9 6.33 0.6667 0.44444
4 – 6 6 8 10 8 0.6667 0.44444
4 – 5 4 5 6 5 0.3333 0.11111
5 – 7 5 6 9 6.33 0.6667 0.44444
6 – 8 2 3 4 3 0.3333 0.11111
6 – 7 0 0 0 0 0 0
7 – 10 5 9 11 8.67 1 1
7 – 8 1 5 8 4.83 1.1667 1.36111
8 – 9 4 3 5 3.5 0.1667 0.02778
9 – 10 2 3 5 3.167 0.5 0.25
• Expected Time = [(Optimistic Time + 4 x Most
likely Time + Pessimistic Time)]/6
• σ2 = [(Pessimistic Time - Optimistic Time)/6]2
Activity
Optimistic
Time
Most Likely
Time
Pessimistic
Time
Expected
time Sigma
Sigma
Square
1 – 2 2 3 5 3.17 0.5 0.25
2 – 3 3 4 6 4.17 0.5 0.25
3 – 6 6 8 11 8.17 0.8333 0.69444
2 – 4 5 6 9 6.33 0.6667 0.44444
4 – 6 6 8 10 8 0.6667 0.44444
4 – 5 4 5 6 5 0.3333 0.11111
5 – 7 5 6 9 6.33 0.6667 0.44444
6 – 8 2 3 4 3 0.3333 0.11111
6 – 7 0 0 0 0 0 0
7 – 10 5 9 11 8.67 1 1
7 – 8 1 5 8 4.83 1.1667 1.36111
8 – 9 4 3 5 3.5 0.1667 0.02778
9 – 10 2 3 5 3.17 0.5 0.25

More Related Content

What's hot

Project management book for mba
Project management book for mbaProject management book for mba
Project management book for mba
Bikramjit Singh
 
Project Management
Project ManagementProject Management
Project Management
Warawut
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
Reetesh Gupta
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
nazi2020
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
Sadhanandavel Ramdoss
 
Project Charter
Project CharterProject Charter
Project Charter
Deborah Obasogie
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
Ajeesh Mk
 
Project Management Plan
Project Management PlanProject Management Plan
Project Management Plan
Kyle Hammon
 
Chap 6 Developing A Project Plan
Chap 6 Developing A Project PlanChap 6 Developing A Project Plan
Chap 6 Developing A Project Plan
project management
 
Project charter-template
Project charter-templateProject charter-template
Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides
SlideTeam
 
Project Planning
Project PlanningProject Planning
Project Planning
Srinivasan Rengasamy
 
Project Management: Importance in Detail
Project Management: Importance in DetailProject Management: Importance in Detail
Project Management: Importance in Detail
NIILM University Online
 
PM Session 5
PM Session 5PM Session 5
PM Session 5
dmdk12
 
Pert analysis
Pert analysisPert analysis
Pert analysis
Hashamuddin Yaakob
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
Abhishek Raj
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
Shivangi Saini
 
Chapter 7 managing risk
Chapter 7   managing riskChapter 7   managing risk
Chapter 7 managing risk
Hammad Hashmi
 
Gantt PERT and CPM
Gantt PERT and CPMGantt PERT and CPM
Gantt PERT and CPM
Gurbakash Phonsa
 
Forecasting
ForecastingForecasting
Forecasting
Ashish Kumar
 

What's hot (20)

Project management book for mba
Project management book for mbaProject management book for mba
Project management book for mba
 
Project Management
Project ManagementProject Management
Project Management
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
Project Charter
Project CharterProject Charter
Project Charter
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Project Management Plan
Project Management PlanProject Management Plan
Project Management Plan
 
Chap 6 Developing A Project Plan
Chap 6 Developing A Project PlanChap 6 Developing A Project Plan
Chap 6 Developing A Project Plan
 
Project charter-template
Project charter-templateProject charter-template
Project charter-template
 
Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides
 
Project Planning
Project PlanningProject Planning
Project Planning
 
Project Management: Importance in Detail
Project Management: Importance in DetailProject Management: Importance in Detail
Project Management: Importance in Detail
 
PM Session 5
PM Session 5PM Session 5
PM Session 5
 
Pert analysis
Pert analysisPert analysis
Pert analysis
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Chapter 7 managing risk
Chapter 7   managing riskChapter 7   managing risk
Chapter 7 managing risk
 
Gantt PERT and CPM
Gantt PERT and CPMGantt PERT and CPM
Gantt PERT and CPM
 
Forecasting
ForecastingForecasting
Forecasting
 

Similar to Network scheduling

PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
salsa moyara
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
Shadina Shah
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
Rahul Dubey
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project management
Ahmad Basim Hamza
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
kongara
 
Aminullah Assagaf_P7-Ch.9_Project management-32.pptx
Aminullah Assagaf_P7-Ch.9_Project management-32.pptxAminullah Assagaf_P7-Ch.9_Project management-32.pptx
Aminullah Assagaf_P7-Ch.9_Project management-32.pptx
Aminullah Assagaf
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
Dr. Divya Khandelwal
 
Aminullah Assagaf_P7-Ch.9_Project management-32.pptx
Aminullah Assagaf_P7-Ch.9_Project management-32.pptxAminullah Assagaf_P7-Ch.9_Project management-32.pptx
Aminullah Assagaf_P7-Ch.9_Project management-32.pptx
Aminullah Assagaf
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
Deepak Paithankar
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management Upload
BhuWan Khadka
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
Sachin Kapoor
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
Baker Khader Abdallah, PMP
 
C03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdfC03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdf
ssuser8babb7
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
ShwetaMahdole
 
project-network-diagram.ppt
project-network-diagram.pptproject-network-diagram.ppt
project-network-diagram.ppt
albert937613
 
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
drennanmicah
 
CPM - Critical Path Method
CPM - Critical Path MethodCPM - Critical Path Method
CPM - Critical Path Method
Parth Desani
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
adeelmunir158
 

Similar to Network scheduling (20)

PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project management
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
Aminullah Assagaf_P7-Ch.9_Project management-32.pptx
Aminullah Assagaf_P7-Ch.9_Project management-32.pptxAminullah Assagaf_P7-Ch.9_Project management-32.pptx
Aminullah Assagaf_P7-Ch.9_Project management-32.pptx
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Aminullah Assagaf_P7-Ch.9_Project management-32.pptx
Aminullah Assagaf_P7-Ch.9_Project management-32.pptxAminullah Assagaf_P7-Ch.9_Project management-32.pptx
Aminullah Assagaf_P7-Ch.9_Project management-32.pptx
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management Upload
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
C03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdfC03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdf
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
 
project-network-diagram.ppt
project-network-diagram.pptproject-network-diagram.ppt
project-network-diagram.ppt
 
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
 
CPM - Critical Path Method
CPM - Critical Path MethodCPM - Critical Path Method
CPM - Critical Path Method
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOL
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 

Recently uploaded

Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 

Recently uploaded (20)

Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 

Network scheduling

  • 1. Steps In Using Network Technique •Plan the project •Schedule the project •Monitor the project
  • 2. Plan the project: – Analyze the project by determining all the individual activities that must be performed to complete it. – Show the planned sequence of these activities on a network(graphical representation where arrow and circle represent the relation among acitivities in the project ).
  • 3. Schedule the project • Estimate how long it will take to perform each activity. • Perform calculation to locate the critical path (the longest time chain of sequential activities which determines the duration of the project). • Use this information to develop a more economical and efficient schedule.
  • 4. Monitor the project • Use the plan to control and monitor the progress. • Revise and update the schedule through out the execution of the project so that the schedule represent the current plans and the current status of the project.
  • 5. WBS: Work Break Structure • Project: Build a 10 storied building • Task: A) Land acquisition, B) Land Preparation, C) Design, D)Foundation, E)Structure, F)Walls, G) Door Window, H) Plumbing, I) Electrical wiring, J) Painting and decoration.
  • 6. Precedence relationship • Some activities cannot be performed until other activities have been completed. This type of requirements establish a technical relationship which is called precedence relationship.
  • 7. Assign Activity Duration • A) Land acquisition, • B) Land Preparation, • C) Design, • D)Foundation, • E)Structure, • F)Walls, • G) Door Window, • H) Plumbing, • I) Electrical wiring, • J) Painting and decoration. • 2 Weeks • 1 Week • 3 Weeks • 2 Weeks • 3 Week • 2 Weeks • 2 Weeks • 1 Week • 1 Weeks • 2 Weeks
  • 8. Network convention • A network is a graph using circles and arrows to represent the planned relationship among the activities required to complete the project. Either of two conventions can be used to develop a network: – Activity on Node (AON): use circle to represent activities and arrow to link them. – Activity on Arrow (AOA): use arrow to represent activities and circle to connect them.
  • 9. Example 01 Task Predecessor Duration A None 2 B None 8 C A 4 D A 6 E C,D 9 F B,E 11 G B 3 H F,G 1 Draw AON and AOA diagram of following project
  • 10. AON
  • 11. AOA
  • 12. Task Predecessor Duration A None 2 B A 6 C B 4 D A 4 E C 5 F E 6 G E 3 H F 3 I D,F 3 J F,G 5 K H 2 L J 3 M I,K,L 1
  • 13. Task Optimistic time Most likely time Pessimistic time 1-2 2 3 5 2-3 3 4 6 3-6 6 8 11 2-4 5 6 9 4-6 6 8 10 4-5 4 5 6 5-7 5 6 9 6-8 2 3 4 6-7 0 0 0 7-8 1 3 5 8-9 4 5 8 9-10 2 3 5 7-10 5 9 11
  • 14. • Expected Time = [(Optimistic Time + 4 x Most likely Time + Pessimistic Time)]/6 • σ2 = [(Pessimistic Time - Optimistic Time)/6]2
  • 16. Activity Optimistic Time Most Likely Time Pessimistic Time Expected time Sigma Sigma Square 1 – 2 2 3 5 3.17 0.5 0.25 2 – 3 3 4 6 4.17 0.5 0.25 3 – 6 6 8 11 8.17 0.8333 0.69444 2 – 4 5 6 9 6.33 0.6667 0.44444 4 – 6 6 8 10 8 0.6667 0.44444 4 – 5 4 5 6 5 0.3333 0.11111 5 – 7 5 6 9 6.33 0.6667 0.44444 6 – 8 2 3 4 3 0.3333 0.11111 6 – 7 0 0 0 0 0 0 7 – 10 5 9 11 8.67 1 1 7 – 8 1 5 8 4.83 1.1667 1.36111 8 – 9 4 3 5 3.5 0.1667 0.02778 9 – 10 2 3 5 3.167 0.5 0.25
  • 17.
  • 18.
  • 19. • Expected Time = [(Optimistic Time + 4 x Most likely Time + Pessimistic Time)]/6 • σ2 = [(Pessimistic Time - Optimistic Time)/6]2
  • 20. Activity Optimistic Time Most Likely Time Pessimistic Time Expected time Sigma Sigma Square 1 – 2 2 3 5 3.17 0.5 0.25 2 – 3 3 4 6 4.17 0.5 0.25 3 – 6 6 8 11 8.17 0.8333 0.69444 2 – 4 5 6 9 6.33 0.6667 0.44444 4 – 6 6 8 10 8 0.6667 0.44444 4 – 5 4 5 6 5 0.3333 0.11111 5 – 7 5 6 9 6.33 0.6667 0.44444 6 – 8 2 3 4 3 0.3333 0.11111 6 – 7 0 0 0 0 0 0 7 – 10 5 9 11 8.67 1 1 7 – 8 1 5 8 4.83 1.1667 1.36111 8 – 9 4 3 5 3.5 0.1667 0.02778 9 – 10 2 3 5 3.17 0.5 0.25