SlideShare a Scribd company logo
1 of 48
MS-PROJECT
TUTORIAL
Dam Project
Submitted by:-
Mustafa K. Sonasath: PT-301513
CEPT University
Creating Project
List all the activities with their
durations
Creating WBS
Go to projects-WBS-Define code-
then add column and give prefix
value
Adding Outdent, Indent
Go to task- and click on the
icons as shown(green arrows)
for outdent/ indent.
Auto Scheduling
Select all activities
and click on the
auto-schedule
button as shown
Setting up predecessors
Double
clicking on
predecessor
cell opens up
task
information
dialog, where
one can set
the
predecessors
with type and
lag
Adding detailed Gantt bar chart & bar text
Click on Gantt chart, from
the dropdown, select detail
Gantt
Format-format-from the
drop down select bar-
bar text and accordingly
enter values
Adding formula’s
Right click on column creating
column ‘duration 1’- custom
field-rename as interfering float,
formula- enter formula selecting
from field dropdown= total slack-
free slack
Creating columns
Right click and add new column-
text 1
Setting lookup for columns
Right click- custom field-rename
to responsibility-lookup-where
values can be given
Assigning responsibilities
Assigning various
responsibilities to employees
Completing responsibility column
Cells will give a drop-down
option, where one can select
and assign responsibilities for
all activities
Assigning resources
Go to View- resource sheet, where one can
set up the resources, assign maximum
resources in each category, set std rate for
resources.
Changing default currency
One problem that is
frequently observed is
changing the default
currency. Going to file-
options-display- we can
change the currency as
desired
Adding resources in task detail form
All the resources for the activities should be
entered using the task details form, the effort
driven button should be unchecked as
shown, task type should be ‘fixed duration’.
Clicking the next button will lead to the next
activity, where the same steps have to be
repeated.
This graph shows the allocation of
Resource Labor. It has been over
allocated. Click on View menu 
Other views  Resource Graph
The red portion indicates that
the resource has been over
allocated.
Over-allocated resources
Resource should be leveled
without changing the project
duration by suitably
selecting leveling options
Levelling Over-allocated resources
Single Filter
A similar dialog box opens up, field name can be
set accordingly. Similarly, test and values can be
set. In this case, test- equals, values- 0. The test
has to be logical.
Result of single filter
An example of single filter
Interactive Filters
A similar dialog box opens up, field name can be
set accordingly. Similarly, test and values can be
set. In this case, test- equals, values- 0 and
responsibility contains the name which we have
to enter. The test has to be logical.
Using interactive filters
A pop up dialog asks the users to enter name,
dropdown gives the option to select.
Result of interactive filters
An example of interactive filter
Multiple Filter
A similar dialog box opens up, field name can be
set accordingly. Similarly, test and values can be
set. In this case, test- equals, values- 0 and
responsibility is Kavta-GM The test has to be
logical.
Result of multiple filter
An example of multiple filter
Switch function
Add a new text column-
rename column- formula- and
using fields, function to write
the syntax
Result of switch function
The syntax replaced the old responsibilities with new
ones.
IIf function
Add a new text column-
rename column- formula- and
using fields, function to write
the syntax
Result of iif function
Critical activities were supposed to send
daily reports whereas non-critical activities
have to send weekly reports. Also, iff
function and graphical indicators were
used together to show which activities
were already completed.
Customizing the calendar
Go to project- change working
time- calendar window pops up-
where you can mark exceptions
Changing the
default calendar
setting by including
Saturday as a
working day
Customizing the working days in calendar
Recording Macros
Go to view- macros-start recording
macros- then a dialog will pop-up
where name the macro, give a
shortcut and store macro only in
project file, otherwise all files in msp
will contain this macro. Click on ok to
start recording.
Start recording macro and then after
completing recording click on stop
recording
Recording Macros
After recording the
macros-view-macro-
view macro-then
selecting the macro-
click edit- a VB-pop up
as shown below comes-
copy the syntax.
Editing in Macros
After copying the syntax, insert an
userform where using the command
button create necessary commands.
Creating User forms
Double clicking on the
command button will open
an window similar to the
one above, paste the
syntax copied from the
macro. Then, run userform
as shown.
Running User forms
Running the userform will bring the
command button on the Gantt and
clicking them now will run the macro.
Running User forms
Multiple projects: Saving resource pool file
Open a new Microsoft project file-Go to view- go to resource sheet
Fill in the data in resource sheet and save it as resource pool file.
Open a new Microsoft
project file-Create
activities & enter
duration &
predecessor of each
activity-saved the
project as multiple
project 1-In this way, 3
multiple project files
were created & saved
with different file
name.
Note- Care should be
taken that each
activity should have a
unique name & it
should not be
repeated, among the
multiple project files.
Create Multiple Project files
Create a new file- go to project- subproject-add a
file and subsequently add all the 3 files created
Adding Multiple Project file as a sub-project
After the creation of the file- go to
resource-resource pool- share
resources –use resources-from-
resource pooling
Resource Pooling
Final file after multiple projects and resource pool
Result of Multiple Project & Resource Pooling
Earned Value: Adding Status Date
Insert column- baseline cost-project-
project info-status date-change it to
required date
Editing in Project Options
File-options-schedule-unmark actual costs
are always calculated by project
Adding indicators
Go to view- tables- more tables-
earned value cost indicators. Then,
insert columns of actual cost, BCWP.
SPI, percentage of work done
Result of Earned Value
An example of
earned value
Report Generation
Go to Reports-select any
area where you wish to
generate the report-select
the type of report.
A typical example of Cost
Overview report
Report Generation- An example
THANK YOU
Mustafa K. Sonasath
PT-301513
CEPT University

More Related Content

What's hot

Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Chetanraj M
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overviewMaher Almohamad
 
Project Management using MS Project 2010
Project Management using MS Project 2010Project Management using MS Project 2010
Project Management using MS Project 2010Abdul Ghaffar, PMP
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - TutorialRajeev Sharma
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Project management planning
Project management planningProject management planning
Project management planningAlvin Niere
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentationFarrukh Raja
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sAbhik Tushar Das
 
TILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceTILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceM. Tuna
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxGracePentinio1
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 

What's hot (20)

Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013
 
MS Project 2010 Training
MS Project 2010 TrainingMS Project 2010 Training
MS Project 2010 Training
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overview
 
Project Management using MS Project 2010
Project Management using MS Project 2010Project Management using MS Project 2010
Project Management using MS Project 2010
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
 
MS Project Guide.pdf
MS Project Guide.pdfMS Project Guide.pdf
MS Project Guide.pdf
 
Project management planning
Project management planningProject management planning
Project management planning
 
Ms project lectures
Ms project lecturesMs project lectures
Ms project lectures
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentation
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner's
 
TILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceTILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with Confidence
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptx
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 

Viewers also liked

Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMPSubodh Kumar
 
MS Project Svcs Productivity
MS Project Svcs ProductivityMS Project Svcs Productivity
MS Project Svcs Productivityedmahler
 
Project management by MS Project 2010
Project management by MS Project 2010Project management by MS Project 2010
Project management by MS Project 2010Wadhwani Foundation
 
Microsoft project 2007 tutorial
Microsoft project 2007   tutorialMicrosoft project 2007   tutorial
Microsoft project 2007 tutorialMuhammad Umari
 
Getting started with MS Project 2010
Getting started with MS Project 2010Getting started with MS Project 2010
Getting started with MS Project 2010Monica Di Bratto
 
التمارين العملية والتطبيقات دورة دراسة الجدوى و مهارات إدارة المشاريع
التمارين العملية والتطبيقات دورة دراسة الجدوى و مهارات إدارة المشاريعالتمارين العملية والتطبيقات دورة دراسة الجدوى و مهارات إدارة المشاريع
التمارين العملية والتطبيقات دورة دراسة الجدوى و مهارات إدارة المشاريعDr. Fayez ALFarhan
 
Practical Use of Microsoft Project for Project Managers
Practical Use of Microsoft Project for Project ManagersPractical Use of Microsoft Project for Project Managers
Practical Use of Microsoft Project for Project ManagersSteve Gladstone
 
MS-Project - Unleash the Force | Ralf C. Adam
MS-Project - Unleash the Force | Ralf C. AdamMS-Project - Unleash the Force | Ralf C. Adam
MS-Project - Unleash the Force | Ralf C. AdamRalf C. Adam
 
MS Project 2010 Getting Started
MS Project 2010 Getting StartedMS Project 2010 Getting Started
MS Project 2010 Getting Startedmsprojectpros
 
نموذج للامتحان
نموذج للامتحاننموذج للامتحان
نموذج للامتحانu083125
 
Ms Project 2007(advanced)
Ms Project 2007(advanced)Ms Project 2007(advanced)
Ms Project 2007(advanced)Dinesh Singh
 
Duration - The Holy Grail of MS Project?
Duration - The Holy Grail of MS Project?Duration - The Holy Grail of MS Project?
Duration - The Holy Grail of MS Project?dmdk12
 

Viewers also liked (20)

Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
 
MS Project Svcs Productivity
MS Project Svcs ProductivityMS Project Svcs Productivity
MS Project Svcs Productivity
 
Project management by MS Project 2010
Project management by MS Project 2010Project management by MS Project 2010
Project management by MS Project 2010
 
Microsoft project 2007 tutorial
Microsoft project 2007   tutorialMicrosoft project 2007   tutorial
Microsoft project 2007 tutorial
 
Getting started with MS Project 2010
Getting started with MS Project 2010Getting started with MS Project 2010
Getting started with MS Project 2010
 
التمارين العملية والتطبيقات دورة دراسة الجدوى و مهارات إدارة المشاريع
التمارين العملية والتطبيقات دورة دراسة الجدوى و مهارات إدارة المشاريعالتمارين العملية والتطبيقات دورة دراسة الجدوى و مهارات إدارة المشاريع
التمارين العملية والتطبيقات دورة دراسة الجدوى و مهارات إدارة المشاريع
 
Practical Use of Microsoft Project for Project Managers
Practical Use of Microsoft Project for Project ManagersPractical Use of Microsoft Project for Project Managers
Practical Use of Microsoft Project for Project Managers
 
Project Management KPIs
Project Management KPIsProject Management KPIs
Project Management KPIs
 
MS-Project - Unleash the Force | Ralf C. Adam
MS-Project - Unleash the Force | Ralf C. AdamMS-Project - Unleash the Force | Ralf C. Adam
MS-Project - Unleash the Force | Ralf C. Adam
 
Ms office 2007 complete
Ms office 2007 completeMs office 2007 complete
Ms office 2007 complete
 
Indian Power Sector
Indian Power SectorIndian Power Sector
Indian Power Sector
 
Microsoft Project
Microsoft ProjectMicrosoft Project
Microsoft Project
 
microsoft project
microsoft projectmicrosoft project
microsoft project
 
Ms project
Ms projectMs project
Ms project
 
Training microsoft project
Training microsoft projectTraining microsoft project
Training microsoft project
 
MS Project 2010 Getting Started
MS Project 2010 Getting StartedMS Project 2010 Getting Started
MS Project 2010 Getting Started
 
نموذج للامتحان
نموذج للامتحاننموذج للامتحان
نموذج للامتحان
 
Ms Project 2007(advanced)
Ms Project 2007(advanced)Ms Project 2007(advanced)
Ms Project 2007(advanced)
 
Duration - The Holy Grail of MS Project?
Duration - The Holy Grail of MS Project?Duration - The Holy Grail of MS Project?
Duration - The Holy Grail of MS Project?
 
Ms project
Ms projectMs project
Ms project
 

Similar to MS Project

Sap business intelligence 4.0 report basic
Sap business intelligence 4.0   report basicSap business intelligence 4.0   report basic
Sap business intelligence 4.0 report basictovetrivel
 
Design Document Sample
Design Document SampleDesign Document Sample
Design Document SampleSteve Smith
 
Sketch Assignment - Task Management
Sketch Assignment - Task ManagementSketch Assignment - Task Management
Sketch Assignment - Task ManagementSuraj Rao
 
Tasks In this assignment you are required to design and imp.pdf
Tasks In this assignment you are required to design and imp.pdfTasks In this assignment you are required to design and imp.pdf
Tasks In this assignment you are required to design and imp.pdfacsmadurai
 
Unit iii vb_study_materials
Unit iii vb_study_materialsUnit iii vb_study_materials
Unit iii vb_study_materialsgayaramesh
 
Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016Rajeev Sharma
 
Enhanced Task Details Page Released 2022
Enhanced Task Details Page Released 2022Enhanced Task Details Page Released 2022
Enhanced Task Details Page Released 2022Orangescrum
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorialRonald Oroya
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iitKushal Patel
 
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013Ong-Art Sanpinit
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013Ong-Art Sanpinit
 
Software engineering modeling lab lectures
Software engineering modeling lab lecturesSoftware engineering modeling lab lectures
Software engineering modeling lab lecturesmarwaeng
 
Case Study Analysis 2The Cholesterol.xls records cholesterol lev.docx
Case Study Analysis 2The Cholesterol.xls records cholesterol lev.docxCase Study Analysis 2The Cholesterol.xls records cholesterol lev.docx
Case Study Analysis 2The Cholesterol.xls records cholesterol lev.docxwendolynhalbert
 
Student Lab Activity A. Lab # CIS CIS170A-A1B. Lab.docx
Student Lab Activity A. Lab # CIS CIS170A-A1B. Lab.docxStudent Lab Activity A. Lab # CIS CIS170A-A1B. Lab.docx
Student Lab Activity A. Lab # CIS CIS170A-A1B. Lab.docxemelyvalg9
 

Similar to MS Project (20)

Sap business intelligence 4.0 report basic
Sap business intelligence 4.0   report basicSap business intelligence 4.0   report basic
Sap business intelligence 4.0 report basic
 
Vb introduction.
Vb introduction.Vb introduction.
Vb introduction.
 
Design Document Sample
Design Document SampleDesign Document Sample
Design Document Sample
 
Mca 504 dotnet_unit5
Mca 504 dotnet_unit5Mca 504 dotnet_unit5
Mca 504 dotnet_unit5
 
Sketch Assignment - Task Management
Sketch Assignment - Task ManagementSketch Assignment - Task Management
Sketch Assignment - Task Management
 
Tasks In this assignment you are required to design and imp.pdf
Tasks In this assignment you are required to design and imp.pdfTasks In this assignment you are required to design and imp.pdf
Tasks In this assignment you are required to design and imp.pdf
 
Unit iii vb_study_materials
Unit iii vb_study_materialsUnit iii vb_study_materials
Unit iii vb_study_materials
 
Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016
 
Enhanced Task Details Page Released 2022
Enhanced Task Details Page Released 2022Enhanced Task Details Page Released 2022
Enhanced Task Details Page Released 2022
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
 
Login methodology for Primavera V8.3 (EPPM)
Login methodology for Primavera V8.3 (EPPM)Login methodology for Primavera V8.3 (EPPM)
Login methodology for Primavera V8.3 (EPPM)
 
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013
 
PROFILE
PROFILEPROFILE
PROFILE
 
Software engineering modeling lab lectures
Software engineering modeling lab lecturesSoftware engineering modeling lab lectures
Software engineering modeling lab lectures
 
User preference Option in Oracle Primavera EPPM P6
User preference Option in Oracle Primavera EPPM P6User preference Option in Oracle Primavera EPPM P6
User preference Option in Oracle Primavera EPPM P6
 
Case Study Analysis 2The Cholesterol.xls records cholesterol lev.docx
Case Study Analysis 2The Cholesterol.xls records cholesterol lev.docxCase Study Analysis 2The Cholesterol.xls records cholesterol lev.docx
Case Study Analysis 2The Cholesterol.xls records cholesterol lev.docx
 
Student Lab Activity A. Lab # CIS CIS170A-A1B. Lab.docx
Student Lab Activity A. Lab # CIS CIS170A-A1B. Lab.docxStudent Lab Activity A. Lab # CIS CIS170A-A1B. Lab.docx
Student Lab Activity A. Lab # CIS CIS170A-A1B. Lab.docx
 
Vb6.0 intro
Vb6.0 introVb6.0 intro
Vb6.0 intro
 

Recently uploaded

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 

Recently uploaded (20)

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 

MS Project

  • 1. MS-PROJECT TUTORIAL Dam Project Submitted by:- Mustafa K. Sonasath: PT-301513 CEPT University
  • 2. Creating Project List all the activities with their durations
  • 3. Creating WBS Go to projects-WBS-Define code- then add column and give prefix value
  • 4. Adding Outdent, Indent Go to task- and click on the icons as shown(green arrows) for outdent/ indent.
  • 5. Auto Scheduling Select all activities and click on the auto-schedule button as shown
  • 6. Setting up predecessors Double clicking on predecessor cell opens up task information dialog, where one can set the predecessors with type and lag
  • 7. Adding detailed Gantt bar chart & bar text Click on Gantt chart, from the dropdown, select detail Gantt Format-format-from the drop down select bar- bar text and accordingly enter values
  • 8. Adding formula’s Right click on column creating column ‘duration 1’- custom field-rename as interfering float, formula- enter formula selecting from field dropdown= total slack- free slack
  • 9. Creating columns Right click and add new column- text 1
  • 10. Setting lookup for columns Right click- custom field-rename to responsibility-lookup-where values can be given
  • 12. Completing responsibility column Cells will give a drop-down option, where one can select and assign responsibilities for all activities
  • 13. Assigning resources Go to View- resource sheet, where one can set up the resources, assign maximum resources in each category, set std rate for resources.
  • 14. Changing default currency One problem that is frequently observed is changing the default currency. Going to file- options-display- we can change the currency as desired
  • 15. Adding resources in task detail form All the resources for the activities should be entered using the task details form, the effort driven button should be unchecked as shown, task type should be ‘fixed duration’. Clicking the next button will lead to the next activity, where the same steps have to be repeated.
  • 16. This graph shows the allocation of Resource Labor. It has been over allocated. Click on View menu  Other views  Resource Graph The red portion indicates that the resource has been over allocated. Over-allocated resources
  • 17. Resource should be leveled without changing the project duration by suitably selecting leveling options Levelling Over-allocated resources
  • 18. Single Filter A similar dialog box opens up, field name can be set accordingly. Similarly, test and values can be set. In this case, test- equals, values- 0. The test has to be logical.
  • 19. Result of single filter An example of single filter
  • 20. Interactive Filters A similar dialog box opens up, field name can be set accordingly. Similarly, test and values can be set. In this case, test- equals, values- 0 and responsibility contains the name which we have to enter. The test has to be logical.
  • 21. Using interactive filters A pop up dialog asks the users to enter name, dropdown gives the option to select.
  • 22. Result of interactive filters An example of interactive filter
  • 23. Multiple Filter A similar dialog box opens up, field name can be set accordingly. Similarly, test and values can be set. In this case, test- equals, values- 0 and responsibility is Kavta-GM The test has to be logical.
  • 24. Result of multiple filter An example of multiple filter
  • 25. Switch function Add a new text column- rename column- formula- and using fields, function to write the syntax
  • 26. Result of switch function The syntax replaced the old responsibilities with new ones.
  • 27. IIf function Add a new text column- rename column- formula- and using fields, function to write the syntax
  • 28. Result of iif function Critical activities were supposed to send daily reports whereas non-critical activities have to send weekly reports. Also, iff function and graphical indicators were used together to show which activities were already completed.
  • 29. Customizing the calendar Go to project- change working time- calendar window pops up- where you can mark exceptions
  • 30. Changing the default calendar setting by including Saturday as a working day Customizing the working days in calendar
  • 31. Recording Macros Go to view- macros-start recording macros- then a dialog will pop-up where name the macro, give a shortcut and store macro only in project file, otherwise all files in msp will contain this macro. Click on ok to start recording.
  • 32. Start recording macro and then after completing recording click on stop recording Recording Macros
  • 33. After recording the macros-view-macro- view macro-then selecting the macro- click edit- a VB-pop up as shown below comes- copy the syntax. Editing in Macros
  • 34. After copying the syntax, insert an userform where using the command button create necessary commands. Creating User forms
  • 35. Double clicking on the command button will open an window similar to the one above, paste the syntax copied from the macro. Then, run userform as shown. Running User forms
  • 36. Running the userform will bring the command button on the Gantt and clicking them now will run the macro. Running User forms
  • 37. Multiple projects: Saving resource pool file Open a new Microsoft project file-Go to view- go to resource sheet Fill in the data in resource sheet and save it as resource pool file.
  • 38. Open a new Microsoft project file-Create activities & enter duration & predecessor of each activity-saved the project as multiple project 1-In this way, 3 multiple project files were created & saved with different file name. Note- Care should be taken that each activity should have a unique name & it should not be repeated, among the multiple project files. Create Multiple Project files
  • 39. Create a new file- go to project- subproject-add a file and subsequently add all the 3 files created Adding Multiple Project file as a sub-project
  • 40. After the creation of the file- go to resource-resource pool- share resources –use resources-from- resource pooling Resource Pooling
  • 41. Final file after multiple projects and resource pool Result of Multiple Project & Resource Pooling
  • 42. Earned Value: Adding Status Date Insert column- baseline cost-project- project info-status date-change it to required date
  • 43. Editing in Project Options File-options-schedule-unmark actual costs are always calculated by project
  • 44. Adding indicators Go to view- tables- more tables- earned value cost indicators. Then, insert columns of actual cost, BCWP. SPI, percentage of work done
  • 45. Result of Earned Value An example of earned value
  • 46. Report Generation Go to Reports-select any area where you wish to generate the report-select the type of report. A typical example of Cost Overview report
  • 48. THANK YOU Mustafa K. Sonasath PT-301513 CEPT University