Introduction
• What is Project?
– A project is a set of inter-related activities which are
initiated to achieve an objective. As soon as the objective
is achieved the project is deemed to be over.
– A project is not an objective in itself (it has an objective),
nor is it the end-result (It results into something)
– It has a definite beginning and a definite end
• How does MS Project help?
– Manage Schedule, Resources, cost
– Easy tracking and update
• Focus of this session
– Project schedule creation and tracking
32. 32
PMmentor
Task Type
Task Type Work Duration Units
Fixed Work Fixed Change Change
Fixed Duration Change Fixed Change
Fixed Units Change Change Fixed
34. 34
PMmentor
Constraint Type
• As Late As Possible
• As Soon As Possible
• Finish No Earlier Than
• Finish No Later Than
• Must Finish On
• Must Start On
• Start No Earlier Than
• Start No Later Than