MS Project 2010 Training-Vinit Kumar Singh
Welcome, we have assembled to learn to use MS Project 2010 from effort estimations to planning.Welcome and Introduction
Templates would provide examples for almost all kind of plans, so its good to go through those first.Templates
You can import tasks from Excel and Word.You can also simply copy the list and paste in MPP.You need to map the fields between excel and MPP to import the tasks.You can similarly export to pdf, excel etc.Import & Export
Date would automatically start from today for Project plan, which can be changed as needed.You can change things using proect>project information tool.Start date should only be provided, let MPP decide the end date.Defining project information
Either new calendar can be made or existing can be changed using Project>Change Working time.Either holidays can be accommodated using Exceptions, or overtime can be added using Work weeks tabDefining project calendar
Manually and auto scheduled taskWith manual task, we can put any text instead of durationTasks can be organized using Summary tasks.We can also have recurring tasks, if need be.A non-budgeted task can be made inactiveTasks, Inactive tasks & Summary tasks
Milestone represents a work accomplished like customer acceptance etc., milestone do not have any duration.Milestone
Either new calendar can be made or existing can be changed using Project>Change Working time.Either holidays can be accommodated using Exceptions, or overtime can be added using Work weeks tabSummary tasks
Each task can be associated with a WBS (work breakdown structure) code.We can define our own WBS codes.Highest WBS code should be added as project code in the SEPITS for tracking.Summary tasks can be shown and hidden from Gant chart tools>Format>Summary tasks checkboxWBS Codes, Show\Hide summary
Tasks can be linked to have dependency between themLink tasks
All resources can be seen at View>Resource sheetResources work availability should be set in maximum unit column e.g. 70% of leads.Also cost of resources can be put here.Resources could be work, cost or material.Resources normally gets added automatically but its not a good way. If you want new resources not to be added to the resource pool automatically, open, file>options>advanced and deselect add new resources and tasks check boxResources
Duration = Work \ unitsE.g. if resource works for 50% units then task of 40 hrs is calculated to 80 hrs by MPP    Thus, 80 hours = 40 hours \ 50%Work = Duration X UnitsE.g. If we enter task duration for 5 days at 40% resource usage, MPP would give output of 16 hours 	Thus, 2 days = 5 days X 40%Units = work \ durationE.g. MPP calculates units if work is provided 40 hrs and duration 160hrs.   Thus,  0.25 = 40 hours \ 160 hoursDuration, work and units
If hours assigned are higher than the maximum available time for a resource, over-allocation occurs.Resource over-allocations can be analyzed using resource usage and resource sheet.In resource usage view, all over allocated resources can be filtered.It can be fixed using task inspector, team planner etc.Resource over-allocations
Whenever resource assignments are changed, MPP will trigger to select one of the three options. We need to click the correct option, as per our requirement there.Resource assignments modifications
Using team planner, one can assign tasks to users using drag and drop.This can also be used to fix over-allocations of resources.Team planner
Timeline can be viewed at View>timeline.We can add milestones on timeline and then copy that on email for providing visual treat to client.Timeline
One can create multiple project plans and then to analyze across the projects, one can create master plan and then add all projects plan as sub projects to that.Master & Sub projects
Resources can be leveled, however it can dangerously change the whole if whole project leveling is requested. Leveling delays and splits tasks to remove over-allocations. For that leveling should be done small portion of plan.Leveling resources
Plan can be baselined from Project>Set baseline. There could be 11 baselines for a plan.Scheduled is current plan, that may be same or changed per the progress going on.Also actual can be used for inputting actual values, and then when required variance reports can be generated.Baselined, scheduled and actual
Project > Project information >statisticsView > tables > variance etcProject > reports > overview > summaryUsing other text based and visual reportsProject Status & Reports
http://office.microsoft.com/en-us/project-help/http://www.microsoft.com/project/en/us/default.aspxhttp://www.profsr.com/msproject/msproj01.htmhttp://blogs.msdn.com/b/project/More information
Thank You!

MS Project 2010 Training

  • 1.
    MS Project 2010Training-Vinit Kumar Singh
  • 2.
    Welcome, we haveassembled to learn to use MS Project 2010 from effort estimations to planning.Welcome and Introduction
  • 3.
    Templates would provideexamples for almost all kind of plans, so its good to go through those first.Templates
  • 4.
    You can importtasks from Excel and Word.You can also simply copy the list and paste in MPP.You need to map the fields between excel and MPP to import the tasks.You can similarly export to pdf, excel etc.Import & Export
  • 5.
    Date would automaticallystart from today for Project plan, which can be changed as needed.You can change things using proect>project information tool.Start date should only be provided, let MPP decide the end date.Defining project information
  • 6.
    Either new calendarcan be made or existing can be changed using Project>Change Working time.Either holidays can be accommodated using Exceptions, or overtime can be added using Work weeks tabDefining project calendar
  • 7.
    Manually and autoscheduled taskWith manual task, we can put any text instead of durationTasks can be organized using Summary tasks.We can also have recurring tasks, if need be.A non-budgeted task can be made inactiveTasks, Inactive tasks & Summary tasks
  • 8.
    Milestone represents awork accomplished like customer acceptance etc., milestone do not have any duration.Milestone
  • 9.
    Either new calendarcan be made or existing can be changed using Project>Change Working time.Either holidays can be accommodated using Exceptions, or overtime can be added using Work weeks tabSummary tasks
  • 10.
    Each task canbe associated with a WBS (work breakdown structure) code.We can define our own WBS codes.Highest WBS code should be added as project code in the SEPITS for tracking.Summary tasks can be shown and hidden from Gant chart tools>Format>Summary tasks checkboxWBS Codes, Show\Hide summary
  • 11.
    Tasks can belinked to have dependency between themLink tasks
  • 12.
    All resources canbe seen at View>Resource sheetResources work availability should be set in maximum unit column e.g. 70% of leads.Also cost of resources can be put here.Resources could be work, cost or material.Resources normally gets added automatically but its not a good way. If you want new resources not to be added to the resource pool automatically, open, file>options>advanced and deselect add new resources and tasks check boxResources
  • 13.
    Duration = Work\ unitsE.g. if resource works for 50% units then task of 40 hrs is calculated to 80 hrs by MPP Thus, 80 hours = 40 hours \ 50%Work = Duration X UnitsE.g. If we enter task duration for 5 days at 40% resource usage, MPP would give output of 16 hours Thus, 2 days = 5 days X 40%Units = work \ durationE.g. MPP calculates units if work is provided 40 hrs and duration 160hrs. Thus, 0.25 = 40 hours \ 160 hoursDuration, work and units
  • 14.
    If hours assignedare higher than the maximum available time for a resource, over-allocation occurs.Resource over-allocations can be analyzed using resource usage and resource sheet.In resource usage view, all over allocated resources can be filtered.It can be fixed using task inspector, team planner etc.Resource over-allocations
  • 15.
    Whenever resource assignmentsare changed, MPP will trigger to select one of the three options. We need to click the correct option, as per our requirement there.Resource assignments modifications
  • 16.
    Using team planner,one can assign tasks to users using drag and drop.This can also be used to fix over-allocations of resources.Team planner
  • 17.
    Timeline can beviewed at View>timeline.We can add milestones on timeline and then copy that on email for providing visual treat to client.Timeline
  • 18.
    One can createmultiple project plans and then to analyze across the projects, one can create master plan and then add all projects plan as sub projects to that.Master & Sub projects
  • 19.
    Resources can beleveled, however it can dangerously change the whole if whole project leveling is requested. Leveling delays and splits tasks to remove over-allocations. For that leveling should be done small portion of plan.Leveling resources
  • 20.
    Plan can bebaselined from Project>Set baseline. There could be 11 baselines for a plan.Scheduled is current plan, that may be same or changed per the progress going on.Also actual can be used for inputting actual values, and then when required variance reports can be generated.Baselined, scheduled and actual
  • 21.
    Project > Projectinformation >statisticsView > tables > variance etcProject > reports > overview > summaryUsing other text based and visual reportsProject Status & Reports
  • 22.
  • 23.