SlideShare a Scribd company logo
Project Management
                  Quick Reference Guide
                                       For
                                   Project 2010
Initiate




                  Assign




                           Close
           Plan




                                             Muthu Swamy S, APSM, PMP, CSM, PM-2008
                                                      Friday, October 1, 2010
                                                     Rms.reddy@hotmail.com
Guideline



This article is to explain Project Management Concept as a quick reference
through step by step guidance using Microsoft Project 2010 tool.

The targeted audience is a beginner to the project management and
experienced with MS Project 2010.




                                  Table of Contents



                            1. Start Project
                            2. Plan the Tasks
                            3. Assign Resources
                            4. Project baseline setup
                            5. Update Progress
                            6. Forecast Information
                            7. Close Project
Step-1: Start Project
Before beginning a new project, an organization must
determine whether the project fits its strategic goals. Executives
should classify proposed projects that focus on mission-critical
activities as high-priority and projects that are peripheral to
organization goals as lower priority.
Before work begins, an executive sponsor should be identified.
The organization should complete a high-level evaluation of the
project’s business case , its limitations, and its technical and
financial requirements. Finally, a project manager should be
identified, who can then set up a project plan in Microsoft
Project 2010.


1. Create a new                  •   To create a new blank project in Project, click the File tab. Click New, and then c
   project file                      Project.
                                 •   To create a new project from a template, click the File tab. Select a template fro
                                     (local), Office Online Templates (Web), or Project Server Templates.

2. Set the project           Click the File tab, and then click Info. On the right side of the Information page, select a
   start date                Date box.

3. Define the                Click the Project tab. In the Properties group, click Change Working Time. Identify wor
   project calendar          working days and times for your project.

4. Save the project          click the File tab. Click Save. In the File name box, type the project name.
   file                      If you are publishing the project to Microsoft Office Project Server 2010, type the name
                             include any values for custom fields that are required by your organization.
Step-2: Plan the Tasks
                             In the planning stage, you devise a workable scheme to accomplish the
                             project’s goals. To do this, you identify the project’s milestones,
                             deliverables, and tasks. This plan can be your work breakdown structure
                             (WBS). You develop and refine the schedule, and identify the resources
                             required to implement the project.
1. Enter tasks     Click the View tab. In the Task Views group, click Gantt Chart. In the Task Name field,
                   enter tasks. Tasks can also include summary tasks, milestones, and WBS items.
2. Decide how      In Project 2010, you can now schedule tasks manually in addition to having Project
   you want to     automatically schedule them. Select the scheduling method after you enter a new task by
   schedule        clicking one of the following in the Task Mode column:
   tasks                • Manually scheduled          With this method, Project won't move a task after it is
                            created, even when resources are assigned to it, or tasks get linked to it, or if the
                            Project calendar changes. New tasks are manually scheduled by default.
                        • Auto scheduled Use this method when you want Project to schedule the task
                            based on dependencies, constraints, calendars, and other factors.

                   Note New tasks are manually scheduled by default. To make new tasks automatically
                   scheduled by default, click the Tasks tab. In the Schedule group, point to Task Mode, and in
                   the list, click Auto Schedule.
3. Outline tasks   Create your task hierarchy, including tasks and milestones under summary tasks, which can
                   represent phases or other work divisions. Click the View tab. In the Task Views group, click
                   Gantt Chart. Select a task (or several tasks), and then in the Tasks group, click the Indent or
                   Outdent button            .
                   Tip If you created a summary task with a duration, start date, or finish date, then the tasks
                   that fall under the summary task will not be rolled up to this summary task. They'll be
                   independent of it. This is known as top-down scheduling.
4. Enter           Click the Duration field for a task and enter a duration. For Project 2010, you can enter
   durations       duration in two different ways, depending on the scheduling method that is being used for
                   the task.
                       • Manually scheduled task            Enter duration as either a number or as text. For
                            example, you can enter "Sometime after June," or "Two days after ship."
                       • Auto scheduled task Enter duration as a number. For example, type 4d to indicate
                            4 days. To specify a milestone without duration, type 0d. To indicate that a duration
                            is an estimate, add a question mark; for example, type 6d?

                   Note When using automatic scheduling, avoid entering start and finish dates for tasks.
                   Instead, enter duration and let Project 2010 automatically set these dates, which might
                   change anyway as resources are assigned to tasks.
5. Link tasks to   Click the View tab. In the Task Views group, click Gantt Chart. Select the tasks that you
   show            want to link, and then click the Link Tasks button        in the Tasks group, which is found
   relationships   under the Tasks tab. To change the default finish-to-start dependency type, double-click
                   the line between the tasks that you want to change, and then select a task link from the
                   Type list.
6. Create          After your project is underway, you might learn that other projects depend on your project
   deliverables    as a deliverable. Click the View tab. In the Task Views group, click Gantt Chart. On the Task
                   tab, in the Insert group, click Manage Deliverables and Dependencies            . This feature
                   requires Project Professional 2010 that is connected to Project Server 2010.
Step-3: Assign Resources
Assignments are the associations between specific
tasks and the resources needed to complete them.
You can assign more than one resource to a task. In
addition to work resources (people), you can assign
material resources (such as cement) and cost
resources (such as travel) to tasks.


1. Add resources
                        Click the View tab. In the Resource Views group, click Resource Sheet            . In the Resource
   to your
                        Name field, type the names of the resources you will use for this project.
   project
                        If you are using Project Professional, you can add resources from the enterprise resource pool.
                        Click the Resources tab. In the Insert group, click Add Resources, and then click Build Team from
                        Enterprise. This feature requires Project Professional 2010 that is connected to Project Server
                        2010.
2. Assign               In the Gantt Chart view, select a task to which you want to assign a resource. On the Resources
   resources to
                        tab, in the Assignments group, click Assign Resources        . Click the resource names, and then
   tasks
                        click Assign.
                        Tip Use the new Team Planner to drag and drop tasks around easily from one person to another
                        within your team, or back and forth in the schedule. Click the View tab. In the Resources group,
                        click Team Planner. You can even create new tasks on the Team Planner, or remove tasks—by
                        just dragging or dropping.
3. Enter the            When scheduling tasks, project managers sometimes prefer to enter the amount of work (or the
   work hours           amount of labor) needed to complete a task, rather than the duration for the task. Entering work
   resources            reflects real-world scheduling.
   spend on tasks       To enter work hours for resources assigned to tasks, add the Work column to the Gantt Chart
                        view. Right click a column, and then click Insert Column. Type "Work", to select the Work column.
4. Know your            As soon as you assign resources to automatically scheduled tasks, Project 2010 determines how to
   task type            schedule the task based on the task type. (Manually scheduled tasks don't use task types.)
                        Durations might change as you assign resources to tasks.
                        How task types work
                        Work, duration, and units (% allocation) are determined by the formula: Work = Duration * Units.
                          In a . . .              If you revise work . . If you revise duration . If you revise units . .
                                                  .                        ..                        .
                         Fixed units task        Duration changes         Work changes                Duration changes
                         Fixed work task         Duration changes         Units change                Duration changes
                         Fixed duration task     Units change             Work changes                Work changes

                            •   To set a default task type for the entire project, click the File tab, and then click Options.
                                In the Default task type box, select Fixed Units (the default), Fixed Duration, or Fixed
                                Work.
                            •   To change the task type for an individual task, click the Task tab, and then in the
                                Properties group, click the Task Information button         . Click the Advanced tab, and
                                then in the Task type box, click the task type that you want to create.

5. Identify             You can use Project 2010 to help you understand how changes to one task can affect the rest of
   factors              the project. Click the Task tab, and then in the Schedule group, click Inspect Task. A pane opens
   affecting task       on the left showing the factors that affect the scheduling of the selected task.
   schedules            Tip You can also see task scheduling information (such as scheduling mode, duration, and start
                        and stop times) quickly by hovering the mouse over the task's Gantt bar.
Step-4: Set the project Baseline

                           Create a baseline or an interim plan so that later you can compare your
                           up-to-date schedule to your baseline. Saving a baseline plan enables
                           you to identify and solve discrepancies and plan more accurately for
                           similar future projects.




1. Save the          After your project plan is solidly in place
   baseline plan     for the finish date, budget, and scope,
                     you can submit the plan for approval.
                     Once it has been approved, save the
                     baseline plan. Click the Project tab, in
                     the Schedule group, click Set Baseline.
2. View baseline     Click the View tab, and then click the
   data in a Gantt   Gantt Chart button. Click the Format
   Chart view        tab, and then in the Bar Styles group,
                     click Baseline. the baseline information
                     is shown as the lower of the two Gantt
                     bars for each task.
3. View baseline     Click the View tab. In the Task Views
   data in a table   group, click Gantt Chart (or any view
                     that includes columns). Point to Tables,
                     and then select Variance. This table
                     includes fields for baseline and variance
                     start and finish.
Step-5: Update Progress
Updating the progress of your project is the only way to
make sure it stays on track as work is performed. The focus
at this point is on managing changes, updating the
schedule, tracking progress, and communicating project
information.
Note     Project 2010 tracks three sets of dates: current,
baseline, and actual. When you first set the baseline,
current = baseline. When a task is 100% complete, current =
actual. Baseline, current, and actual values exist for the start
date, finish date, duration, cost, and work.

 1. Manage                Managing changes involves modifying durations, dates, dependencies, resource
    changes               assignments, or tasks based on requested changes or new information. Keep the
                          current fields up to date and compare them to the baseline.
 2. Track actual          It’s best to decide on a single method for tracking progress. You can enter
    dates and             percentage complete, actual start and finish dates, actual and remaining durations,
    durations             or actual and remaining work.
                          Click the Task tab, and select the task for which you want to enter actual progress. In
                          the Tasks group, select the amount of progress done on the task
                                              .
 3. Track actual          If you want to enter actual and remaining work hours or costs, use the tracking table.
    hours and             Click the View tab. In the Data group, point Table, and then click Tracking. Enter
    costs                 progress data in the Act. Work or Act. Cost fields for the task.
                          You can also use the tracking table to enter percent complete, actual start and finish
                          dates, and actual and remaining duration.
Step-6: View/report information

                                             Keep stakeholders and team members up-to-date on project
                                             progress by providing them with access to online or printed
                                             views and reports.

                                             Project 2010 provides many ways to print and distribute both
                                             detailed and overview information project information
                                             quickly and efficiently.


1. Select a view   Project 2010 has some old views and some new views to help you see project information and
                   report it to others on your team or organization. Click the View tab. In either the Task Views
                   group or the Resource Views group, select the view you want to use. There are many views, but
                   the most useful ones include:
                       • Team planner view Move tasks easily from one person to another within your team, or
                            back and forth in the schedule. You can create new tasks in the team planner or remove
                            tasks—just by dragging them.
                       • Timeline view Place tasks, subtasks, or milestones onto a single timeline at the top of
                            most views. You can copy the timeline into Word, PowerPoint, Excel, or Outlook. You
                            can instantly create attractive project reports this way. Click the Timeline check box to
                            see how the timeline works.
                       • Gantt Chart view View project tasks in a combination view, with columns on one side
                            and bars along a timeline on the other side.
                       • Calendar view See project information in a familiar monthly or weekly calendar format
                            that can be printed.

2. Add a column    Adding columns to a view is one of the easiest ways to create the view that meets your needs.
                   Click the View tab. In either the Task Views group or the Resource Views group, select the view
                   you want to use. Right click on a column header to the left of where you want to insert a new
                   column, and then click Insert column. Type the name of the column you want to insert.
                   Tip You can also insert a custom column as easily as a built-in column. For example, if you want
                   a column called "Deliveries", type that name when you insert a new column. If you want the new
                   column to contain only numbers (to specify the number of deliveries), then right click the column
                   down-arrow, point to Data Type, and select the type of data that the column should contain.
3. Customize a     Customizing views beyond adding columns has been made considerably easier in Project 2010.
   view            Whether it’s the Team Planner, Timeline, or classic Gantt Chart, all formatting options are
                   available on the Format tab.
                   Select the view you want to customize, and then on the Format tab click the type of view
                   element you want to change, such as the bar styles on the Gantt Chart, callout text on the
                   Timeline, or the gridlines and timescales of any views.
                   Tip If you want to filter, sort, or group tasks prior to printing, Click the View tab, and then in the
                   Data group, click the Sort, Filter, or Group options.
4. Print a view    Set up the current view the way that you want it to look when printed. Click the File tab, and then
   or report       click Print. A preview of the view will be printed appears on the right.
                   Tip Click in the preview part of the view to see the actual size of the view as it will be printed.
5. Generate a      Click the Project tab, and then in the Reports group, click one of the following:
   report               •    Visual Reports Use visual reports to see your project’s data as a PivotTable report in Excel 2010
                             or a PivotDiagram view in Visio Professional 2010.
                        •    Reports Use basic reports to see your project's data in tabular reports that don't require Excel or
                             Visio. These basic reports are collected in categories for easy selecting and printing.
                        •    Compare Projects Use a compare projects report to view a report that displays changes in the
                             current project compared to another project.
Step-7: Close the Project
                                                                                   Just because your project is
                                                                                   almost finished doesn’t mean
                                                                                   that your work is done. You
                                                                                   still need to resolve any final
                                                                                   project details and obtain
                                                                                   customer acceptance of final
                                                                                   deliverables.    Conduct     a
                                                                                   “lessons learned” session,
                                                                                   recording information about
                                                                                   areas for improvement and
                                                                                   best practices. Make any final
                                                                                   updates to the project plan.
                                                                                   Finally, archive the project
                                                                                   plan according to your
                                                                                   organization’s guidelines.



1. Create a final        Click the Project tab. In the Reports group, click Visual Reports to see your project’s
   report                data as a PivotTable report in Excel 2010 or a PivotDiagram view in Visio Professional
                         2010.
                         You can also view basic reports that don’t require Excel or Visio. Click the Project tab,
                         and in the Reports group, click Reports. Double-click a report category, and then
                         double-click the predefined report. Enter any requested information. A preview of the
                         report appears. To print the report, click Print.
2. Save a project After completing a project, you should leverage what you’ve learned in the project by
   as a template  making it a template for future projects. Click the File tab, click Save As, and then in the
                  Save As Type box, click Template.




                                  Thank You
               Muthu Swamy S, APSM, PMP, CSM, PM-2008
                       rms.reddy@hotmail.com
                      http://linkedin.com/in/msbgl

More Related Content

What's hot

1
11
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS project
Samir Paralikar
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
Anand Bobade
 
Basic of Navis works BIM application
Basic of Navis works BIM applicationBasic of Navis works BIM application
Basic of Navis works BIM application
Ishan Mehta
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
Eder Alves
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
Rajeev Sharma
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
Rahul Sudame
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
ProPM Academy
 
Kazanılmış Değer Analizi - Sunu
Kazanılmış Değer Analizi - SunuKazanılmış Değer Analizi - Sunu
Kazanılmış Değer Analizi - Sunu
Yusuf Yıldız
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
Anand Bobade
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project management
Dr. Pramod Deshpande
 
MICROSOFT PROJECT
MICROSOFT PROJECTMICROSOFT PROJECT
MICROSOFT PROJECT
Smit Patel
 
9.6 Control Resources
9.6 Control Resources9.6 Control Resources
9.6 Control Resources
DavidMcLachlan1
 
Bilişim Teknolojileri Projelerinde Temel Başarı ve Başarısızlık Nedenleri
Bilişim Teknolojileri Projelerinde Temel Başarı ve Başarısızlık NedenleriBilişim Teknolojileri Projelerinde Temel Başarı ve Başarısızlık Nedenleri
Bilişim Teknolojileri Projelerinde Temel Başarı ve Başarısızlık Nedenlericgoze
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
Anand Bobade
 
Ms project 2010 tutorial 1
Ms project 2010 tutorial   1Ms project 2010 tutorial   1
Ms project 2010 tutorial 1
learningquotient
 
MODUL TUTORIAL POWERPOINT 2013
MODUL TUTORIAL POWERPOINT 2013MODUL TUTORIAL POWERPOINT 2013
MODUL TUTORIAL POWERPOINT 2013
tmkinedu
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
Jamil Faraj , PMP
 
Microsoft Project
Microsoft ProjectMicrosoft Project
Qs Approach To Project Cost
Qs Approach To Project CostQs Approach To Project Cost
Qs Approach To Project Cost
Johannes J Merkler AIA
 

What's hot (20)

1
11
1
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS project
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
 
Basic of Navis works BIM application
Basic of Navis works BIM applicationBasic of Navis works BIM application
Basic of Navis works BIM application
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
Kazanılmış Değer Analizi - Sunu
Kazanılmış Değer Analizi - SunuKazanılmış Değer Analizi - Sunu
Kazanılmış Değer Analizi - Sunu
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project management
 
MICROSOFT PROJECT
MICROSOFT PROJECTMICROSOFT PROJECT
MICROSOFT PROJECT
 
9.6 Control Resources
9.6 Control Resources9.6 Control Resources
9.6 Control Resources
 
Bilişim Teknolojileri Projelerinde Temel Başarı ve Başarısızlık Nedenleri
Bilişim Teknolojileri Projelerinde Temel Başarı ve Başarısızlık NedenleriBilişim Teknolojileri Projelerinde Temel Başarı ve Başarısızlık Nedenleri
Bilişim Teknolojileri Projelerinde Temel Başarı ve Başarısızlık Nedenleri
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
 
Ms project 2010 tutorial 1
Ms project 2010 tutorial   1Ms project 2010 tutorial   1
Ms project 2010 tutorial 1
 
MODUL TUTORIAL POWERPOINT 2013
MODUL TUTORIAL POWERPOINT 2013MODUL TUTORIAL POWERPOINT 2013
MODUL TUTORIAL POWERPOINT 2013
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
Microsoft Project
Microsoft ProjectMicrosoft Project
Microsoft Project
 
Qs Approach To Project Cost
Qs Approach To Project CostQs Approach To Project Cost
Qs Approach To Project Cost
 

Viewers also liked

MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project PresentationKhem Singh
 
MS Project 2010 Training
MS Project 2010 TrainingMS Project 2010 Training
MS Project 2010 Training
Vinit Kumar Singh
 
Ms project lectures
Ms project lecturesMs project lectures
Ms project lectures
jillmitchell8778
 
Project Standard and Project Professional 2010 Product Guide
Project Standard and Project Professional 2010 Product GuideProject Standard and Project Professional 2010 Product Guide
Project Standard and Project Professional 2010 Product Guide
EPC Group
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overview
Maher Almohamad
 
Practical Use of Microsoft Project for Project Managers
Practical Use of Microsoft Project for Project ManagersPractical Use of Microsoft Project for Project Managers
Practical Use of Microsoft Project for Project Managers
Steve Gladstone
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013
Ong-Art Sanpinit
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Subodh Kumar
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIAL
Vismay Shah
 
Manual microsoft project professional 2013
Manual microsoft project professional 2013Manual microsoft project professional 2013
Manual microsoft project professional 2013
ALPHIL CONSULTORES SOC.RESP.LIMITADA
 
Microsoft Office Project 2007 Tutorial
Microsoft Office Project 2007 TutorialMicrosoft Office Project 2007 Tutorial
Microsoft Office Project 2007 Tutorial
Anil Purushothaman
 
Microsoft project 2010 (final)
Microsoft project 2010 (final)Microsoft project 2010 (final)
Microsoft project 2010 (final)Isai Perez
 
S curve innovation #BBTwisnu
S curve innovation #BBTwisnuS curve innovation #BBTwisnu
S curve innovation #BBTwisnu
Wisnu Dewobroto
 
Microsoft project 2007 tutorial
Microsoft project 2007   tutorialMicrosoft project 2007   tutorial
Microsoft project 2007 tutorialMuhammad Umari
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
Satish Yadavalli
 
Getting started with MS Project 2010
Getting started with MS Project 2010Getting started with MS Project 2010
Getting started with MS Project 2010
Monica Di Bratto
 
Project management
Project managementProject management
Project management
Satish Yadavalli
 
PPTs on MS Project 2010
PPTs on MS Project 2010PPTs on MS Project 2010
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner's
Abhik Tushar Das
 
microsoft project
microsoft projectmicrosoft project
microsoft project
Annisa Khoerunnisya
 

Viewers also liked (20)

MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
MS Project 2010 Training
MS Project 2010 TrainingMS Project 2010 Training
MS Project 2010 Training
 
Ms project lectures
Ms project lecturesMs project lectures
Ms project lectures
 
Project Standard and Project Professional 2010 Product Guide
Project Standard and Project Professional 2010 Product GuideProject Standard and Project Professional 2010 Product Guide
Project Standard and Project Professional 2010 Product Guide
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overview
 
Practical Use of Microsoft Project for Project Managers
Practical Use of Microsoft Project for Project ManagersPractical Use of Microsoft Project for Project Managers
Practical Use of Microsoft Project for Project Managers
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIAL
 
Manual microsoft project professional 2013
Manual microsoft project professional 2013Manual microsoft project professional 2013
Manual microsoft project professional 2013
 
Microsoft Office Project 2007 Tutorial
Microsoft Office Project 2007 TutorialMicrosoft Office Project 2007 Tutorial
Microsoft Office Project 2007 Tutorial
 
Microsoft project 2010 (final)
Microsoft project 2010 (final)Microsoft project 2010 (final)
Microsoft project 2010 (final)
 
S curve innovation #BBTwisnu
S curve innovation #BBTwisnuS curve innovation #BBTwisnu
S curve innovation #BBTwisnu
 
Microsoft project 2007 tutorial
Microsoft project 2007   tutorialMicrosoft project 2007   tutorial
Microsoft project 2007 tutorial
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
 
Getting started with MS Project 2010
Getting started with MS Project 2010Getting started with MS Project 2010
Getting started with MS Project 2010
 
Project management
Project managementProject management
Project management
 
PPTs on MS Project 2010
PPTs on MS Project 2010PPTs on MS Project 2010
PPTs on MS Project 2010
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner's
 
microsoft project
microsoft projectmicrosoft project
microsoft project
 

Similar to Project management by MS Project 2010

Pm quick reference guide
Pm quick reference guidePm quick reference guide
Pm quick reference guideGeorge Singer
 
Master MSProject 2010
Master MSProject 2010Master MSProject 2010
Master MSProject 2010
Amr Miqdadi
 
Ms project 2000 tutorial
Ms project 2000 tutorialMs project 2000 tutorial
Ms project 2000 tutorialpaolocollector
 
Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007
Toney Sisk
 
CSCI 714 Software Project Planning and EstimationLec.docx
CSCI 714 Software Project Planning and EstimationLec.docxCSCI 714 Software Project Planning and EstimationLec.docx
CSCI 714 Software Project Planning and EstimationLec.docx
mydrynan
 
Project Management Quick Reference Guide
Project Management Quick Reference GuideProject Management Quick Reference Guide
Project Management Quick Reference Guide
Ahmad Hammoud,CPM,IBA,MSE,NLP
 
Project Management Quick Reference Guide For Microsoft Project 2007
Project Management Quick Reference Guide For Microsoft Project 2007Project Management Quick Reference Guide For Microsoft Project 2007
Project Management Quick Reference Guide For Microsoft Project 2007
Toney Sisk
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
Ronald Oroya
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
Kushal Patel
 
BhadaniS Microsoft Project Manual Training
BhadaniS Microsoft Project Manual TrainingBhadaniS Microsoft Project Manual Training
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013
Ong-Art Sanpinit
 
Microsoft project 2010
Microsoft project 2010Microsoft project 2010
Microsoft project 2010
Santosh Dwivedi
 
Project management teaching
Project management   teachingProject management   teaching
Project management teaching
CHIRANJAN SAHA
 
Odoo project management_casestudy
Odoo project management_casestudyOdoo project management_casestudy
Odoo project management_casestudy
Rishi Pujara
 
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs  devry universityMgmt404 entire class course project + all 7 weeks i labs  devry university
Mgmt404 entire class course project + all 7 weeks i labs devry universitykghkghfh
 
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs  devry universityMgmt404 entire class course project + all 7 weeks i labs  devry university
Mgmt404 entire class course project + all 7 weeks i labs devry universitysacascscasc
 
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs  devry universityMgmt404 entire class course project + all 7 weeks i labs  devry university
Mgmt404 entire class course project + all 7 weeks i labs devry universityiutiuriaolcom
 
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs  devry universityMgmt404 entire class course project + all 7 weeks i labs  devry university
Mgmt404 entire class course project + all 7 weeks i labs devry universityliam111221
 
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs  devry universityMgmt404 entire class course project + all 7 weeks i labs  devry university
Mgmt404 entire class course project + all 7 weeks i labs devry universityfnfgnvcn
 
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs  devry universityMgmt404 entire class course project + all 7 weeks i labs  devry university
Mgmt404 entire class course project + all 7 weeks i labs devry universitysmith54655
 

Similar to Project management by MS Project 2010 (20)

Pm quick reference guide
Pm quick reference guidePm quick reference guide
Pm quick reference guide
 
Master MSProject 2010
Master MSProject 2010Master MSProject 2010
Master MSProject 2010
 
Ms project 2000 tutorial
Ms project 2000 tutorialMs project 2000 tutorial
Ms project 2000 tutorial
 
Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007
 
CSCI 714 Software Project Planning and EstimationLec.docx
CSCI 714 Software Project Planning and EstimationLec.docxCSCI 714 Software Project Planning and EstimationLec.docx
CSCI 714 Software Project Planning and EstimationLec.docx
 
Project Management Quick Reference Guide
Project Management Quick Reference GuideProject Management Quick Reference Guide
Project Management Quick Reference Guide
 
Project Management Quick Reference Guide For Microsoft Project 2007
Project Management Quick Reference Guide For Microsoft Project 2007Project Management Quick Reference Guide For Microsoft Project 2007
Project Management Quick Reference Guide For Microsoft Project 2007
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
 
BhadaniS Microsoft Project Manual Training
BhadaniS Microsoft Project Manual TrainingBhadaniS Microsoft Project Manual Training
BhadaniS Microsoft Project Manual Training
 
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013
 
Microsoft project 2010
Microsoft project 2010Microsoft project 2010
Microsoft project 2010
 
Project management teaching
Project management   teachingProject management   teaching
Project management teaching
 
Odoo project management_casestudy
Odoo project management_casestudyOdoo project management_casestudy
Odoo project management_casestudy
 
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs  devry universityMgmt404 entire class course project + all 7 weeks i labs  devry university
Mgmt404 entire class course project + all 7 weeks i labs devry university
 
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs  devry universityMgmt404 entire class course project + all 7 weeks i labs  devry university
Mgmt404 entire class course project + all 7 weeks i labs devry university
 
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs  devry universityMgmt404 entire class course project + all 7 weeks i labs  devry university
Mgmt404 entire class course project + all 7 weeks i labs devry university
 
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs  devry universityMgmt404 entire class course project + all 7 weeks i labs  devry university
Mgmt404 entire class course project + all 7 weeks i labs devry university
 
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs  devry universityMgmt404 entire class course project + all 7 weeks i labs  devry university
Mgmt404 entire class course project + all 7 weeks i labs devry university
 
Mgmt404 entire class course project + all 7 weeks i labs devry university
Mgmt404 entire class course project + all 7 weeks i labs  devry universityMgmt404 entire class course project + all 7 weeks i labs  devry university
Mgmt404 entire class course project + all 7 weeks i labs devry university
 

More from Wadhwani Foundation

Empty Fleet Corporate Profile 2017
Empty Fleet Corporate Profile 2017Empty Fleet Corporate Profile 2017
Empty Fleet Corporate Profile 2017
Wadhwani Foundation
 
4 rce global brochure
4 rce global brochure4 rce global brochure
4 rce global brochure
Wadhwani Foundation
 
Mybon voyage - Digital Intelligent Transport ecoSystem
Mybon voyage - Digital Intelligent Transport ecoSystemMybon voyage - Digital Intelligent Transport ecoSystem
Mybon voyage - Digital Intelligent Transport ecoSystem
Wadhwani Foundation
 
Enterprise Startup to watch in 2015 by CIO Review
Enterprise Startup to watch in 2015 by CIO ReviewEnterprise Startup to watch in 2015 by CIO Review
Enterprise Startup to watch in 2015 by CIO Review
Wadhwani Foundation
 
Integrated with In vehicle infotainment - Public Address System
Integrated with In vehicle infotainment - Public Address SystemIntegrated with In vehicle infotainment - Public Address System
Integrated with In vehicle infotainment - Public Address System
Wadhwani Foundation
 
Motor Sports Race and Rally Tracking by iGateway's Sports Track GPS
Motor Sports Race and Rally Tracking by iGateway's Sports Track GPSMotor Sports Race and Rally Tracking by iGateway's Sports Track GPS
Motor Sports Race and Rally Tracking by iGateway's Sports Track GPS
Wadhwani Foundation
 
Why to chose IGateway as your GPS Partner?
Why to chose IGateway as your GPS Partner?Why to chose IGateway as your GPS Partner?
Why to chose IGateway as your GPS Partner?
Wadhwani Foundation
 
Awards and Achievements - 2013
Awards and Achievements - 2013Awards and Achievements - 2013
Awards and Achievements - 2013
Wadhwani Foundation
 
Awards and Recognition of Year 2014
Awards and Recognition of Year 2014Awards and Recognition of Year 2014
Awards and Recognition of Year 2014
Wadhwani Foundation
 
Vts telematics in public transport conference at Ahmedabad today
Vts telematics in public transport conference at Ahmedabad todayVts telematics in public transport conference at Ahmedabad today
Vts telematics in public transport conference at Ahmedabad today
Wadhwani Foundation
 
Vehicle Tracking system for Government and Logistics by DeepBiz
Vehicle Tracking system for Government and Logistics by DeepBizVehicle Tracking system for Government and Logistics by DeepBiz
Vehicle Tracking system for Government and Logistics by DeepBiz
Wadhwani Foundation
 
School buses turning into smart fleets to provide safety solutions to their s...
School buses turning into smart fleets to provide safety solutions to their s...School buses turning into smart fleets to provide safety solutions to their s...
School buses turning into smart fleets to provide safety solutions to their s...
Wadhwani Foundation
 
iCareU Usage based Insurance in India
iCareU Usage based Insurance in IndiaiCareU Usage based Insurance in India
iCareU Usage based Insurance in India
Wadhwani Foundation
 
Corporate Profile of DeepBiz Technologies for the year 2013-2014
Corporate Profile of DeepBiz Technologies for the year 2013-2014Corporate Profile of DeepBiz Technologies for the year 2013-2014
Corporate Profile of DeepBiz Technologies for the year 2013-2014
Wadhwani Foundation
 
Kmsc green run tsd 17 aug 2014 approved
Kmsc green run tsd 17 aug 2014   approvedKmsc green run tsd 17 aug 2014   approved
Kmsc green run tsd 17 aug 2014 approved
Wadhwani Foundation
 
Final SR for rally of bangalore 2014 by KMSC at Aug 16 and 17
Final SR for rally of bangalore 2014 by KMSC at Aug 16 and 17Final SR for rally of bangalore 2014 by KMSC at Aug 16 and 17
Final SR for rally of bangalore 2014 by KMSC at Aug 16 and 17
Wadhwani Foundation
 
Sponsorship Opportunity in National TSD Rally Round III at Bangalore.
Sponsorship Opportunity in National TSD Rally Round III at Bangalore.Sponsorship Opportunity in National TSD Rally Round III at Bangalore.
Sponsorship Opportunity in National TSD Rally Round III at Bangalore.
Wadhwani Foundation
 
MONSOON RUN 2014 CMSC (Calcutta Motor Sports Club) Result
MONSOON RUN 2014 CMSC (Calcutta Motor Sports Club) ResultMONSOON RUN 2014 CMSC (Calcutta Motor Sports Club) Result
MONSOON RUN 2014 CMSC (Calcutta Motor Sports Club) Result
Wadhwani Foundation
 
iGateway Smart GPS Platform for Telematics Industries
iGateway Smart GPS Platform for Telematics Industries iGateway Smart GPS Platform for Telematics Industries
iGateway Smart GPS Platform for Telematics Industries
Wadhwani Foundation
 

More from Wadhwani Foundation (20)

Empty Fleet Corporate Profile 2017
Empty Fleet Corporate Profile 2017Empty Fleet Corporate Profile 2017
Empty Fleet Corporate Profile 2017
 
ATMCASHBOX
ATMCASHBOXATMCASHBOX
ATMCASHBOX
 
4 rce global brochure
4 rce global brochure4 rce global brochure
4 rce global brochure
 
Mybon voyage - Digital Intelligent Transport ecoSystem
Mybon voyage - Digital Intelligent Transport ecoSystemMybon voyage - Digital Intelligent Transport ecoSystem
Mybon voyage - Digital Intelligent Transport ecoSystem
 
Enterprise Startup to watch in 2015 by CIO Review
Enterprise Startup to watch in 2015 by CIO ReviewEnterprise Startup to watch in 2015 by CIO Review
Enterprise Startup to watch in 2015 by CIO Review
 
Integrated with In vehicle infotainment - Public Address System
Integrated with In vehicle infotainment - Public Address SystemIntegrated with In vehicle infotainment - Public Address System
Integrated with In vehicle infotainment - Public Address System
 
Motor Sports Race and Rally Tracking by iGateway's Sports Track GPS
Motor Sports Race and Rally Tracking by iGateway's Sports Track GPSMotor Sports Race and Rally Tracking by iGateway's Sports Track GPS
Motor Sports Race and Rally Tracking by iGateway's Sports Track GPS
 
Why to chose IGateway as your GPS Partner?
Why to chose IGateway as your GPS Partner?Why to chose IGateway as your GPS Partner?
Why to chose IGateway as your GPS Partner?
 
Awards and Achievements - 2013
Awards and Achievements - 2013Awards and Achievements - 2013
Awards and Achievements - 2013
 
Awards and Recognition of Year 2014
Awards and Recognition of Year 2014Awards and Recognition of Year 2014
Awards and Recognition of Year 2014
 
Vts telematics in public transport conference at Ahmedabad today
Vts telematics in public transport conference at Ahmedabad todayVts telematics in public transport conference at Ahmedabad today
Vts telematics in public transport conference at Ahmedabad today
 
Vehicle Tracking system for Government and Logistics by DeepBiz
Vehicle Tracking system for Government and Logistics by DeepBizVehicle Tracking system for Government and Logistics by DeepBiz
Vehicle Tracking system for Government and Logistics by DeepBiz
 
School buses turning into smart fleets to provide safety solutions to their s...
School buses turning into smart fleets to provide safety solutions to their s...School buses turning into smart fleets to provide safety solutions to their s...
School buses turning into smart fleets to provide safety solutions to their s...
 
iCareU Usage based Insurance in India
iCareU Usage based Insurance in IndiaiCareU Usage based Insurance in India
iCareU Usage based Insurance in India
 
Corporate Profile of DeepBiz Technologies for the year 2013-2014
Corporate Profile of DeepBiz Technologies for the year 2013-2014Corporate Profile of DeepBiz Technologies for the year 2013-2014
Corporate Profile of DeepBiz Technologies for the year 2013-2014
 
Kmsc green run tsd 17 aug 2014 approved
Kmsc green run tsd 17 aug 2014   approvedKmsc green run tsd 17 aug 2014   approved
Kmsc green run tsd 17 aug 2014 approved
 
Final SR for rally of bangalore 2014 by KMSC at Aug 16 and 17
Final SR for rally of bangalore 2014 by KMSC at Aug 16 and 17Final SR for rally of bangalore 2014 by KMSC at Aug 16 and 17
Final SR for rally of bangalore 2014 by KMSC at Aug 16 and 17
 
Sponsorship Opportunity in National TSD Rally Round III at Bangalore.
Sponsorship Opportunity in National TSD Rally Round III at Bangalore.Sponsorship Opportunity in National TSD Rally Round III at Bangalore.
Sponsorship Opportunity in National TSD Rally Round III at Bangalore.
 
MONSOON RUN 2014 CMSC (Calcutta Motor Sports Club) Result
MONSOON RUN 2014 CMSC (Calcutta Motor Sports Club) ResultMONSOON RUN 2014 CMSC (Calcutta Motor Sports Club) Result
MONSOON RUN 2014 CMSC (Calcutta Motor Sports Club) Result
 
iGateway Smart GPS Platform for Telematics Industries
iGateway Smart GPS Platform for Telematics Industries iGateway Smart GPS Platform for Telematics Industries
iGateway Smart GPS Platform for Telematics Industries
 

Recently uploaded

What Makes Candle Making The Ultimate Bachelorette Celebration
What Makes Candle Making The Ultimate Bachelorette CelebrationWhat Makes Candle Making The Ultimate Bachelorette Celebration
What Makes Candle Making The Ultimate Bachelorette Celebration
Wick & Pour
 
EXPERIENCE MONSTER BITES STREETWEAR APPAREL
EXPERIENCE MONSTER BITES STREETWEAR APPARELEXPERIENCE MONSTER BITES STREETWEAR APPAREL
EXPERIENCE MONSTER BITES STREETWEAR APPAREL
6ctbkfpdxz
 
Johnny Depp Long Hair: A Signature Look Through the Years
Johnny Depp Long Hair: A Signature Look Through the YearsJohnny Depp Long Hair: A Signature Look Through the Years
Johnny Depp Long Hair: A Signature Look Through the Years
greendigital
 
erevna-influencers-social-media-stin-ellada
erevna-influencers-social-media-stin-elladaerevna-influencers-social-media-stin-ellada
erevna-influencers-social-media-stin-ellada
rvlassopoulou
 
Gujarat Details in Hindi for children's for presentation in school
Gujarat Details in Hindi for children's for presentation in schoolGujarat Details in Hindi for children's for presentation in school
Gujarat Details in Hindi for children's for presentation in school
shouryajoshi5
 
30 Manipulation Techniques to be a smart person in society (1).pdf
30 Manipulation Techniques to be a smart person in society (1).pdf30 Manipulation Techniques to be a smart person in society (1).pdf
30 Manipulation Techniques to be a smart person in society (1).pdf
minaserver6679
 
What To Do If Your Ring Is Too Big? Must Read
What To Do If Your Ring Is Too Big? Must ReadWhat To Do If Your Ring Is Too Big? Must Read
What To Do If Your Ring Is Too Big? Must Read
Andrews Jewelers
 
La transidentité, un sujet qui fractionne les Français
La transidentité, un sujet qui fractionne les FrançaisLa transidentité, un sujet qui fractionne les Français
La transidentité, un sujet qui fractionne les Français
Ipsos France
 
Unique Wedding Bands For Women Who Want To Stand Out.pptx
Unique Wedding Bands For Women Who Want To Stand Out.pptxUnique Wedding Bands For Women Who Want To Stand Out.pptx
Unique Wedding Bands For Women Who Want To Stand Out.pptx
Andrews Jewelers
 
From Stress to Success How Oakland's Corporate Wellness Programs are Cultivat...
From Stress to Success How Oakland's Corporate Wellness Programs are Cultivat...From Stress to Success How Oakland's Corporate Wellness Programs are Cultivat...
From Stress to Success How Oakland's Corporate Wellness Programs are Cultivat...
Kitchen on Fire
 

Recently uploaded (10)

What Makes Candle Making The Ultimate Bachelorette Celebration
What Makes Candle Making The Ultimate Bachelorette CelebrationWhat Makes Candle Making The Ultimate Bachelorette Celebration
What Makes Candle Making The Ultimate Bachelorette Celebration
 
EXPERIENCE MONSTER BITES STREETWEAR APPAREL
EXPERIENCE MONSTER BITES STREETWEAR APPARELEXPERIENCE MONSTER BITES STREETWEAR APPAREL
EXPERIENCE MONSTER BITES STREETWEAR APPAREL
 
Johnny Depp Long Hair: A Signature Look Through the Years
Johnny Depp Long Hair: A Signature Look Through the YearsJohnny Depp Long Hair: A Signature Look Through the Years
Johnny Depp Long Hair: A Signature Look Through the Years
 
erevna-influencers-social-media-stin-ellada
erevna-influencers-social-media-stin-elladaerevna-influencers-social-media-stin-ellada
erevna-influencers-social-media-stin-ellada
 
Gujarat Details in Hindi for children's for presentation in school
Gujarat Details in Hindi for children's for presentation in schoolGujarat Details in Hindi for children's for presentation in school
Gujarat Details in Hindi for children's for presentation in school
 
30 Manipulation Techniques to be a smart person in society (1).pdf
30 Manipulation Techniques to be a smart person in society (1).pdf30 Manipulation Techniques to be a smart person in society (1).pdf
30 Manipulation Techniques to be a smart person in society (1).pdf
 
What To Do If Your Ring Is Too Big? Must Read
What To Do If Your Ring Is Too Big? Must ReadWhat To Do If Your Ring Is Too Big? Must Read
What To Do If Your Ring Is Too Big? Must Read
 
La transidentité, un sujet qui fractionne les Français
La transidentité, un sujet qui fractionne les FrançaisLa transidentité, un sujet qui fractionne les Français
La transidentité, un sujet qui fractionne les Français
 
Unique Wedding Bands For Women Who Want To Stand Out.pptx
Unique Wedding Bands For Women Who Want To Stand Out.pptxUnique Wedding Bands For Women Who Want To Stand Out.pptx
Unique Wedding Bands For Women Who Want To Stand Out.pptx
 
From Stress to Success How Oakland's Corporate Wellness Programs are Cultivat...
From Stress to Success How Oakland's Corporate Wellness Programs are Cultivat...From Stress to Success How Oakland's Corporate Wellness Programs are Cultivat...
From Stress to Success How Oakland's Corporate Wellness Programs are Cultivat...
 

Project management by MS Project 2010

  • 1. Project Management Quick Reference Guide For Project 2010 Initiate Assign Close Plan Muthu Swamy S, APSM, PMP, CSM, PM-2008 Friday, October 1, 2010 Rms.reddy@hotmail.com
  • 2. Guideline This article is to explain Project Management Concept as a quick reference through step by step guidance using Microsoft Project 2010 tool. The targeted audience is a beginner to the project management and experienced with MS Project 2010. Table of Contents 1. Start Project 2. Plan the Tasks 3. Assign Resources 4. Project baseline setup 5. Update Progress 6. Forecast Information 7. Close Project
  • 3. Step-1: Start Project Before beginning a new project, an organization must determine whether the project fits its strategic goals. Executives should classify proposed projects that focus on mission-critical activities as high-priority and projects that are peripheral to organization goals as lower priority. Before work begins, an executive sponsor should be identified. The organization should complete a high-level evaluation of the project’s business case , its limitations, and its technical and financial requirements. Finally, a project manager should be identified, who can then set up a project plan in Microsoft Project 2010. 1. Create a new • To create a new blank project in Project, click the File tab. Click New, and then c project file Project. • To create a new project from a template, click the File tab. Select a template fro (local), Office Online Templates (Web), or Project Server Templates. 2. Set the project Click the File tab, and then click Info. On the right side of the Information page, select a start date Date box. 3. Define the Click the Project tab. In the Properties group, click Change Working Time. Identify wor project calendar working days and times for your project. 4. Save the project click the File tab. Click Save. In the File name box, type the project name. file If you are publishing the project to Microsoft Office Project Server 2010, type the name include any values for custom fields that are required by your organization.
  • 4. Step-2: Plan the Tasks In the planning stage, you devise a workable scheme to accomplish the project’s goals. To do this, you identify the project’s milestones, deliverables, and tasks. This plan can be your work breakdown structure (WBS). You develop and refine the schedule, and identify the resources required to implement the project. 1. Enter tasks Click the View tab. In the Task Views group, click Gantt Chart. In the Task Name field, enter tasks. Tasks can also include summary tasks, milestones, and WBS items. 2. Decide how In Project 2010, you can now schedule tasks manually in addition to having Project you want to automatically schedule them. Select the scheduling method after you enter a new task by schedule clicking one of the following in the Task Mode column: tasks • Manually scheduled With this method, Project won't move a task after it is created, even when resources are assigned to it, or tasks get linked to it, or if the Project calendar changes. New tasks are manually scheduled by default. • Auto scheduled Use this method when you want Project to schedule the task based on dependencies, constraints, calendars, and other factors. Note New tasks are manually scheduled by default. To make new tasks automatically scheduled by default, click the Tasks tab. In the Schedule group, point to Task Mode, and in the list, click Auto Schedule. 3. Outline tasks Create your task hierarchy, including tasks and milestones under summary tasks, which can represent phases or other work divisions. Click the View tab. In the Task Views group, click Gantt Chart. Select a task (or several tasks), and then in the Tasks group, click the Indent or Outdent button . Tip If you created a summary task with a duration, start date, or finish date, then the tasks that fall under the summary task will not be rolled up to this summary task. They'll be independent of it. This is known as top-down scheduling. 4. Enter Click the Duration field for a task and enter a duration. For Project 2010, you can enter durations duration in two different ways, depending on the scheduling method that is being used for the task. • Manually scheduled task Enter duration as either a number or as text. For example, you can enter "Sometime after June," or "Two days after ship." • Auto scheduled task Enter duration as a number. For example, type 4d to indicate 4 days. To specify a milestone without duration, type 0d. To indicate that a duration is an estimate, add a question mark; for example, type 6d? Note When using automatic scheduling, avoid entering start and finish dates for tasks. Instead, enter duration and let Project 2010 automatically set these dates, which might change anyway as resources are assigned to tasks. 5. Link tasks to Click the View tab. In the Task Views group, click Gantt Chart. Select the tasks that you show want to link, and then click the Link Tasks button in the Tasks group, which is found relationships under the Tasks tab. To change the default finish-to-start dependency type, double-click the line between the tasks that you want to change, and then select a task link from the Type list. 6. Create After your project is underway, you might learn that other projects depend on your project deliverables as a deliverable. Click the View tab. In the Task Views group, click Gantt Chart. On the Task tab, in the Insert group, click Manage Deliverables and Dependencies . This feature requires Project Professional 2010 that is connected to Project Server 2010.
  • 5. Step-3: Assign Resources Assignments are the associations between specific tasks and the resources needed to complete them. You can assign more than one resource to a task. In addition to work resources (people), you can assign material resources (such as cement) and cost resources (such as travel) to tasks. 1. Add resources Click the View tab. In the Resource Views group, click Resource Sheet . In the Resource to your Name field, type the names of the resources you will use for this project. project If you are using Project Professional, you can add resources from the enterprise resource pool. Click the Resources tab. In the Insert group, click Add Resources, and then click Build Team from Enterprise. This feature requires Project Professional 2010 that is connected to Project Server 2010. 2. Assign In the Gantt Chart view, select a task to which you want to assign a resource. On the Resources resources to tab, in the Assignments group, click Assign Resources . Click the resource names, and then tasks click Assign. Tip Use the new Team Planner to drag and drop tasks around easily from one person to another within your team, or back and forth in the schedule. Click the View tab. In the Resources group, click Team Planner. You can even create new tasks on the Team Planner, or remove tasks—by just dragging or dropping. 3. Enter the When scheduling tasks, project managers sometimes prefer to enter the amount of work (or the work hours amount of labor) needed to complete a task, rather than the duration for the task. Entering work resources reflects real-world scheduling. spend on tasks To enter work hours for resources assigned to tasks, add the Work column to the Gantt Chart view. Right click a column, and then click Insert Column. Type "Work", to select the Work column. 4. Know your As soon as you assign resources to automatically scheduled tasks, Project 2010 determines how to task type schedule the task based on the task type. (Manually scheduled tasks don't use task types.) Durations might change as you assign resources to tasks. How task types work Work, duration, and units (% allocation) are determined by the formula: Work = Duration * Units. In a . . . If you revise work . . If you revise duration . If you revise units . . . .. . Fixed units task Duration changes Work changes Duration changes Fixed work task Duration changes Units change Duration changes Fixed duration task Units change Work changes Work changes • To set a default task type for the entire project, click the File tab, and then click Options. In the Default task type box, select Fixed Units (the default), Fixed Duration, or Fixed Work. • To change the task type for an individual task, click the Task tab, and then in the Properties group, click the Task Information button . Click the Advanced tab, and then in the Task type box, click the task type that you want to create. 5. Identify You can use Project 2010 to help you understand how changes to one task can affect the rest of factors the project. Click the Task tab, and then in the Schedule group, click Inspect Task. A pane opens affecting task on the left showing the factors that affect the scheduling of the selected task. schedules Tip You can also see task scheduling information (such as scheduling mode, duration, and start and stop times) quickly by hovering the mouse over the task's Gantt bar.
  • 6. Step-4: Set the project Baseline Create a baseline or an interim plan so that later you can compare your up-to-date schedule to your baseline. Saving a baseline plan enables you to identify and solve discrepancies and plan more accurately for similar future projects. 1. Save the After your project plan is solidly in place baseline plan for the finish date, budget, and scope, you can submit the plan for approval. Once it has been approved, save the baseline plan. Click the Project tab, in the Schedule group, click Set Baseline. 2. View baseline Click the View tab, and then click the data in a Gantt Gantt Chart button. Click the Format Chart view tab, and then in the Bar Styles group, click Baseline. the baseline information is shown as the lower of the two Gantt bars for each task. 3. View baseline Click the View tab. In the Task Views data in a table group, click Gantt Chart (or any view that includes columns). Point to Tables, and then select Variance. This table includes fields for baseline and variance start and finish.
  • 7. Step-5: Update Progress Updating the progress of your project is the only way to make sure it stays on track as work is performed. The focus at this point is on managing changes, updating the schedule, tracking progress, and communicating project information. Note Project 2010 tracks three sets of dates: current, baseline, and actual. When you first set the baseline, current = baseline. When a task is 100% complete, current = actual. Baseline, current, and actual values exist for the start date, finish date, duration, cost, and work. 1. Manage Managing changes involves modifying durations, dates, dependencies, resource changes assignments, or tasks based on requested changes or new information. Keep the current fields up to date and compare them to the baseline. 2. Track actual It’s best to decide on a single method for tracking progress. You can enter dates and percentage complete, actual start and finish dates, actual and remaining durations, durations or actual and remaining work. Click the Task tab, and select the task for which you want to enter actual progress. In the Tasks group, select the amount of progress done on the task . 3. Track actual If you want to enter actual and remaining work hours or costs, use the tracking table. hours and Click the View tab. In the Data group, point Table, and then click Tracking. Enter costs progress data in the Act. Work or Act. Cost fields for the task. You can also use the tracking table to enter percent complete, actual start and finish dates, and actual and remaining duration.
  • 8. Step-6: View/report information Keep stakeholders and team members up-to-date on project progress by providing them with access to online or printed views and reports. Project 2010 provides many ways to print and distribute both detailed and overview information project information quickly and efficiently. 1. Select a view Project 2010 has some old views and some new views to help you see project information and report it to others on your team or organization. Click the View tab. In either the Task Views group or the Resource Views group, select the view you want to use. There are many views, but the most useful ones include: • Team planner view Move tasks easily from one person to another within your team, or back and forth in the schedule. You can create new tasks in the team planner or remove tasks—just by dragging them. • Timeline view Place tasks, subtasks, or milestones onto a single timeline at the top of most views. You can copy the timeline into Word, PowerPoint, Excel, or Outlook. You can instantly create attractive project reports this way. Click the Timeline check box to see how the timeline works. • Gantt Chart view View project tasks in a combination view, with columns on one side and bars along a timeline on the other side. • Calendar view See project information in a familiar monthly or weekly calendar format that can be printed. 2. Add a column Adding columns to a view is one of the easiest ways to create the view that meets your needs. Click the View tab. In either the Task Views group or the Resource Views group, select the view you want to use. Right click on a column header to the left of where you want to insert a new column, and then click Insert column. Type the name of the column you want to insert. Tip You can also insert a custom column as easily as a built-in column. For example, if you want a column called "Deliveries", type that name when you insert a new column. If you want the new column to contain only numbers (to specify the number of deliveries), then right click the column down-arrow, point to Data Type, and select the type of data that the column should contain. 3. Customize a Customizing views beyond adding columns has been made considerably easier in Project 2010. view Whether it’s the Team Planner, Timeline, or classic Gantt Chart, all formatting options are available on the Format tab. Select the view you want to customize, and then on the Format tab click the type of view element you want to change, such as the bar styles on the Gantt Chart, callout text on the Timeline, or the gridlines and timescales of any views. Tip If you want to filter, sort, or group tasks prior to printing, Click the View tab, and then in the Data group, click the Sort, Filter, or Group options. 4. Print a view Set up the current view the way that you want it to look when printed. Click the File tab, and then or report click Print. A preview of the view will be printed appears on the right. Tip Click in the preview part of the view to see the actual size of the view as it will be printed. 5. Generate a Click the Project tab, and then in the Reports group, click one of the following: report • Visual Reports Use visual reports to see your project’s data as a PivotTable report in Excel 2010 or a PivotDiagram view in Visio Professional 2010. • Reports Use basic reports to see your project's data in tabular reports that don't require Excel or Visio. These basic reports are collected in categories for easy selecting and printing. • Compare Projects Use a compare projects report to view a report that displays changes in the current project compared to another project.
  • 9. Step-7: Close the Project Just because your project is almost finished doesn’t mean that your work is done. You still need to resolve any final project details and obtain customer acceptance of final deliverables. Conduct a “lessons learned” session, recording information about areas for improvement and best practices. Make any final updates to the project plan. Finally, archive the project plan according to your organization’s guidelines. 1. Create a final Click the Project tab. In the Reports group, click Visual Reports to see your project’s report data as a PivotTable report in Excel 2010 or a PivotDiagram view in Visio Professional 2010. You can also view basic reports that don’t require Excel or Visio. Click the Project tab, and in the Reports group, click Reports. Double-click a report category, and then double-click the predefined report. Enter any requested information. A preview of the report appears. To print the report, click Print. 2. Save a project After completing a project, you should leverage what you’ve learned in the project by as a template making it a template for future projects. Click the File tab, click Save As, and then in the Save As Type box, click Template. Thank You Muthu Swamy S, APSM, PMP, CSM, PM-2008 rms.reddy@hotmail.com http://linkedin.com/in/msbgl