SlideShare a Scribd company logo
Material
Requirement
Planning (MRP1)
DEEPAK KU. KUSHWAHA
MTCH-IND,
1
Contributors to MRP
• Joseph Orlicky(1964)
• Oliver Wight(1983)
• MRP started in the late 1960s. The technique was applied
first to mobile and airplane industry. As the technique
became well known, many large and small businesses
adopted MRP method in order to increase their
productivity and decrease the production cost.
INTRODUCTION
• The main function of material requirements planning is to
guarantee material availability, that is, it is used to procure
or produce the required quantities on time both for internal
purposes and for sales and distribution.
• This process involves
- monitoring of stocks,
- automatic creation of procurement proposals for
purchasing and production.
• In doing so, MRP tries to strike the best balance possible
between
- optimizing the service level and
-minimizing costs and capital lockup.
MRP is
• Production Planning System
• Computerized Inventory Control
• Management Information System
• Manufacturing Control System
MRP software- Tuppus, Eci M1, E2 shop system
4
MRP system Gives answer
• What items are required?
• How many are required?
• When are they required?
5
Objectives
• Materials and products are available for
production and delivery to customers.
• Maintain the lowest possible level of
inventory.
• Plan manufacturing activities, delivery
schedules and purchasing activities.
6
When to use MRP?
It is useful for…..
• Independent Demand vs Dependent
Demand
• Lumpy demand
• Lead time( order lead time, manufacturing lead time )
• Common use items
7
8
PRODUCTION
PLANNING
PRODUCTION
PLANNING
CAPACITY
WORK FORCE
PRODUCTION
INVENTORY
INTERNAL
EXTERNAL
EXTERNAL
CAPACITY
COMPETITION
RAW MATERIAL
SUPPLY
DEMAND
ECONOMIC
CONDITIONS
Production Planning Environment
Overview of the MRP System
Product
Structure
File
Master
Production
Schedule
Inventory
Master File
Material
Requirements
Planning
Manufacturing
Orders
Purchase
Orders
Various
Reports
10
MRP Inputs
• Master Production Schedule
• Product Structure File
• Inventory Master File
11
Master Production Schedule
• A master schedule is the result of disaggregation
of an aggregate plan.
• A master schedule show the quantity & timing of
specific end item for a time horizon.
• Schedule of Finished Products
• Represents Production, not Demand
• Combination of Customer Orders and Demand
Forecasts
• What Needs to be Produced
12
Product Structure File
• It shows diagrammatically the component required
to assemble it,their no,& the sequence of assembly.
Bill of Material(BOM)
Documentation of product structure.
13
10
Bicycle(1)
Level 0
Handle Bars (1)
Level -1
Frame Assembly (1)
Level-1
Wheels (2)
Level -2
Frame (1)
Level-2
Product Structure Tree
Product structure & BOM
15
Bicycle(1)
Level 0
Handle Bars (1)
Level -1
Frame Assembly (1)
Level-1
Wheels (2)
Level -2
Frame (1)
Level-2
Itemno. Level product LeadtimepartcodeQuantity
1 level0 bicycle P/N1000 10
2 level1 handlebar 1wk P/N1002 10
3 level1 frameass. 1wk P/N1023 10
4 level2 wheel 2wk P/N1045 20
5 level2 frame 2wk P/N1034 10
Inventory Master File
A database of information contain
• Raw material & purchased component.
• In process inventory
• Finished product
• Lot Sizes
• Safety Stock
• Lead Time
• Past-Usage Figures 16
MRP Outputs
• Planned order report
1. Time for order(Lead time)
2. Helps in preparing founds.
• Order release report
1. Order size*, release date.
2. Purchase order taking care of lead time.
• Order change report
1. Changing demand ,order,leadtime.
17
Order size in MRP
Lot for lot method
EOQ methd
Least total cost method
Least unit cost method
18
MRP PROCESS
19
Terms Defined
• Item – name or number for the item being
scheduled
• Low-Level Code – the lowest level of the item on
the product structure file
• Lot Size – order multiples of quantity
• Lead Time – the time from when an order is
placed to when it is received
• PD – Past Due Time Bucket, orders behind
schedule
20
Terms Defined
• Gross Requirements – demand for an item by
time period
• Scheduled Receipts – material already ordered
• Projected on Hand – expected ending inventory
• Net Requirements – number of items to be
provided and when
• Planned Order Receipts – net requirements
adjusted for lot size
• Planned Order Releases – planned order receipts
offset for lead times
21
MRP format
Item: A Low-Level Code: 1
Lot Size: 25 Lead Time: 1
PD 1 2 3 4 5
Gross Requirements
Scheduled Receipts
Projected on Hand
Net Requirements
Planned Order Receipts
Planned Order Releases
22
MRP PROCESS
23
Masterproduction schedule foritemA
Period(w) 1 2 3 4 5 6 7 8
gross requirement 450 600
MRP report foritemBA LT=1Week
Period in weeks 1 2 3 4 5 6 7 8
Gross requirement 450 600
Schedule receipts
Projecton hand 100 100 100 100
Netrequirement 350 600
Planned orderrecepits 350 600
Planned orderrelease 350 600
• GROSS REQUIREMENT
OF COMPONENT
B=2*350=700
• GROSS REQUIREMENT
OF COMPONENT
C=1*350=350
24
A(1)
LT=1
B (2)
LT=1
C(1)
LT-1
Product structure file
25
Master production schedule for item A
Period(w) 1 2 3 4 5 6 7 8
gross requirement 450 600
MRP report for item BA ,LT=1Week
Period in weeks 1 2 3 4 5 6 7 8
Gross requirement 450 600
Schedule receipts
Project on hand 100 100 100 100
Net requirement 350 600
Planned order recepits 350 600
Planned order release 350 600
MRP report for item BB,LT=1week
Period in weeks 1 2 3 4 5 6 7 8
Gross requirement 700 1200
Schedule receipts
Project on hand
Net requirement 700 1200
Planned order recepits 700 1200
Planned order release 700 1200
MRP report for item BC,LT=2week
Period in weeks 1 2 3 4 5 6 7 8
Gross requirement 350 600
Schedule receipts
Project on hand
Net requirement 350 600
Planned order recepits 350 600
Planned order release 350 600
What can MRP do?
• Reduce Inventory Levels
• Reduce Component
Shortages
• Improve Shipping
Performance
• Improve Customer
Service
• Improve Productivity
• Simplified and Accurate
Scheduling
• Reduce Purchasing Cost
• Improve Production
Schedules
• Reduce Manufacturing
Cost
• Reduce Lead Times
• Less Scrap and Rework
• Higher Production
Quality
26
Limitation of MRP
• No account of capacity(deal with MRP=II)
• Data sensitive
• Lead time
27
28
Case study
PAL MOHAN ELECTRONIX PVT. LIMITED , DELHI produces a line of electric meters
installed in residential buildings by electric utility companies to measure power consumption.
Meters used on single-family homes are of two basic types for different voltage and amperage
ranges. In addition to complete meters, some parts and subassemblies are sold separately for
repair or for changeovers to a different voltage or power load.
 Forecasting demand
•The problem for the MRP system is to determine a production schedule that would identify
each item, the period it is needed, and the appropriate quantities.
•This schedule is then checked for feasibility, and the schedule is modified if necessary.
29
Structure of the study
Section 1. Master Production Schedule
Section 2. Bill of Materials (Product Structure) File
Section 3. Inventory Records (Item Master) File
Section 4. Running the MRP Program
Section 5. Obtainability control
30
Section 1. Master Production Schedule
Forecasting demand
31
Section 2. Bill of Materials (Product Structure) File.
32
Section 3. Inventory Records (Item Master) File
33
Section 4 . Running the MRP Program
34
Section 5-Obtainability Control
• ROUGH-CUT CAPACITY PLANNING(MRP-2)
• PREPARE REPORT
•It should have to be asked after applying the MRP that
whether the MRP schedule was feasible or not. If it is not so,
then the new revised MPS has to be applied with MRP
packages
Refernce
• Cad/Cam-Mikell P. Groover
• Automation & production,CIM-Mikell P.
Groover
• wikipedia.org/wiki/Material requirements
planning
35
Query session
Thank You
36

More Related Content

What's hot

Material requirement planning - Production and Operation Management
Material requirement planning - Production and Operation ManagementMaterial requirement planning - Production and Operation Management
Material requirement planning - Production and Operation Management
Suryakumar Thangarasu
 
material requirement planning
material requirement planningmaterial requirement planning
material requirement planning
Naushii Khan
 
Material Requirement Planning (MRP)
Material Requirement Planning (MRP)Material Requirement Planning (MRP)
Material Requirement Planning (MRP)
Konok Mondal
 
Master Production Scheduling (MPS)
Master Production Scheduling (MPS) Master Production Scheduling (MPS)
Master Production Scheduling (MPS)
Pankil Shah
 
MRP Overview
MRP OverviewMRP Overview
MRP Overview
INDUSCommunity
 
Materials requirement planning
Materials requirement planningMaterials requirement planning
Materials requirement planning
Anila Vanguri
 
MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)
Dipesh Pandey
 
Material Requirement Planning
Material Requirement PlanningMaterial Requirement Planning
Material Requirement Planning
Pritesh Mogane
 
Mrp structure
Mrp structureMrp structure
Mrp structure
Amit Verma
 
MRP CASE STUDY
MRP CASE STUDYMRP CASE STUDY
MRP CASE STUDY
Sachin Khandagale
 
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead TimesMRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
ejalgfer
 
Material requirement planning, MRP.
Material requirement planning, MRP. Material requirement planning, MRP.
Material requirement planning, MRP.
shoaibzaheer1
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and control
Dacanay Elmer
 
Material requirement planning (mrp)
Material requirement planning (mrp)Material requirement planning (mrp)
Material requirement planning (mrp)
Somashekar S.M
 
Material requirement planning presentation
Material requirement planning presentationMaterial requirement planning presentation
Material requirement planning presentation
Pankaj Kumar
 
MRP (Materials Requirements Planning) in ERP
MRP (Materials Requirements Planning) in ERPMRP (Materials Requirements Planning) in ERP
MRP (Materials Requirements Planning) in ERPTom Matys
 
Material requirement planning (mrp1)
Material requirement planning (mrp1)Material requirement planning (mrp1)
Material requirement planning (mrp1)
Ravimohan Rajmohan
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
Rajendran Ananda Krishnan
 
Material requirement planning case study
Material requirement planning case studyMaterial requirement planning case study
Material requirement planning case study
Vaibhav Kadu
 

What's hot (20)

Material requirement planning - Production and Operation Management
Material requirement planning - Production and Operation ManagementMaterial requirement planning - Production and Operation Management
Material requirement planning - Production and Operation Management
 
(Mrp 1) Prsntation Slides
(Mrp 1) Prsntation Slides(Mrp 1) Prsntation Slides
(Mrp 1) Prsntation Slides
 
material requirement planning
material requirement planningmaterial requirement planning
material requirement planning
 
Material Requirement Planning (MRP)
Material Requirement Planning (MRP)Material Requirement Planning (MRP)
Material Requirement Planning (MRP)
 
Master Production Scheduling (MPS)
Master Production Scheduling (MPS) Master Production Scheduling (MPS)
Master Production Scheduling (MPS)
 
MRP Overview
MRP OverviewMRP Overview
MRP Overview
 
Materials requirement planning
Materials requirement planningMaterials requirement planning
Materials requirement planning
 
MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)
 
Material Requirement Planning
Material Requirement PlanningMaterial Requirement Planning
Material Requirement Planning
 
Mrp structure
Mrp structureMrp structure
Mrp structure
 
MRP CASE STUDY
MRP CASE STUDYMRP CASE STUDY
MRP CASE STUDY
 
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead TimesMRP Theory: Master Production Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
 
Material requirement planning, MRP.
Material requirement planning, MRP. Material requirement planning, MRP.
Material requirement planning, MRP.
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and control
 
Material requirement planning (mrp)
Material requirement planning (mrp)Material requirement planning (mrp)
Material requirement planning (mrp)
 
Material requirement planning presentation
Material requirement planning presentationMaterial requirement planning presentation
Material requirement planning presentation
 
MRP (Materials Requirements Planning) in ERP
MRP (Materials Requirements Planning) in ERPMRP (Materials Requirements Planning) in ERP
MRP (Materials Requirements Planning) in ERP
 
Material requirement planning (mrp1)
Material requirement planning (mrp1)Material requirement planning (mrp1)
Material requirement planning (mrp1)
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Material requirement planning case study
Material requirement planning case studyMaterial requirement planning case study
Material requirement planning case study
 

Viewers also liked

Wer oder was ist EazyStock - Bestandsoptimierung (englisch)
Wer oder was ist EazyStock - Bestandsoptimierung (englisch)Wer oder was ist EazyStock - Bestandsoptimierung (englisch)
Wer oder was ist EazyStock - Bestandsoptimierung (englisch)
EazyStock
 
Mrp 2 Manufact Resou Plannin
Mrp 2 Manufact Resou PlanninMrp 2 Manufact Resou Plannin
Mrp 2 Manufact Resou Planninmenonroopesh
 
MRP1 vs MRP2
MRP1 vs MRP2MRP1 vs MRP2
MRP1 vs MRP2
Ari Limpo
 
manufacturing resource planning
manufacturing resource planningmanufacturing resource planning
manufacturing resource planningDinesh Nikam
 
Production planning & control & Forecasting
Production planning & control & ForecastingProduction planning & control & Forecasting
Production planning & control & Forecasting
Jenıstön Delımä
 

Viewers also liked (8)

Wer oder was ist EazyStock - Bestandsoptimierung (englisch)
Wer oder was ist EazyStock - Bestandsoptimierung (englisch)Wer oder was ist EazyStock - Bestandsoptimierung (englisch)
Wer oder was ist EazyStock - Bestandsoptimierung (englisch)
 
Mrp 2 Manufact Resou Plannin
Mrp 2 Manufact Resou PlanninMrp 2 Manufact Resou Plannin
Mrp 2 Manufact Resou Plannin
 
Mrp ii
Mrp iiMrp ii
Mrp ii
 
MRP1 vs MRP2
MRP1 vs MRP2MRP1 vs MRP2
MRP1 vs MRP2
 
Supply chain relationships and collaboration
Supply chain relationships and collaborationSupply chain relationships and collaboration
Supply chain relationships and collaboration
 
manufacturing resource planning
manufacturing resource planningmanufacturing resource planning
manufacturing resource planning
 
Mrp 1
Mrp 1Mrp 1
Mrp 1
 
Production planning & control & Forecasting
Production planning & control & ForecastingProduction planning & control & Forecasting
Production planning & control & Forecasting
 

Similar to Mrp 1 deepak 12mt07ind009

Material Requirement planning (factors,inputs,outputs,benifits)
Material Requirement planning  (factors,inputs,outputs,benifits)Material Requirement planning  (factors,inputs,outputs,benifits)
Material Requirement planning (factors,inputs,outputs,benifits)
razinbabaria786
 
Session 6-7-8 MRP.pptx PPC MBA Sem IV IB
Session 6-7-8 MRP.pptx PPC MBA Sem IV IBSession 6-7-8 MRP.pptx PPC MBA Sem IV IB
Session 6-7-8 MRP.pptx PPC MBA Sem IV IB
DrDeeptiSharma12
 
5 MRP.ppt
5 MRP.ppt5 MRP.ppt
5 MRP.ppt
YashMorwal
 
Mba ii pmom_unit-2.5 resource planning -mrp a
Mba ii pmom_unit-2.5 resource planning -mrp aMba ii pmom_unit-2.5 resource planning -mrp a
Mba ii pmom_unit-2.5 resource planning -mrp a
Rai University
 
Material requirement planning
Material requirement planningMaterial requirement planning
Material requirement planning
Shree Bhargava and Associate
 
MATERIAL REQUIREMENT PLANNING AND BILLS OF MATERIAL
MATERIAL REQUIREMENT PLANNING AND BILLS OF MATERIAL MATERIAL REQUIREMENT PLANNING AND BILLS OF MATERIAL
MATERIAL REQUIREMENT PLANNING AND BILLS OF MATERIAL
Junaid Hassan
 
Mrp systems & scheduling
Mrp systems & schedulingMrp systems & scheduling
Mrp systems & schedulingvarun0610
 
SCM 304 Supply Chain Management Material Requirements .docx
SCM 304 Supply Chain Management Material Requirements .docxSCM 304 Supply Chain Management Material Requirements .docx
SCM 304 Supply Chain Management Material Requirements .docx
bagotjesusa
 
Managing productions across Supply Chain
Managing productions across Supply ChainManaging productions across Supply Chain
Managing productions across Supply Chain
Sushovan Bej
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Chris Baichoo
 
Material Requirement Planning Presentation.ppt
Material Requirement Planning Presentation.pptMaterial Requirement Planning Presentation.ppt
Material Requirement Planning Presentation.ppt
SaurabhPratap16
 
Material Requirement Planning Presentation.ppt
Material Requirement Planning Presentation.pptMaterial Requirement Planning Presentation.ppt
Material Requirement Planning Presentation.ppt
IdreesGulzar1
 
Managing production across supply chain
Managing production across supply chainManaging production across supply chain
Managing production across supply chain
Sushant Kumar Sinha
 
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi LabbanFiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
CCT International
 
Resource Requirement Planning
Resource Requirement PlanningResource Requirement Planning
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)Mostafa Ewees
 
Production planning and control - Basic concepts
Production planning and control - Basic conceptsProduction planning and control - Basic concepts
Production planning and control - Basic concepts
gokulfea
 
Module11. Material requirement plan..pdf
Module11. Material requirement plan..pdfModule11. Material requirement plan..pdf
Module11. Material requirement plan..pdf
JOHN PAUL ROBERTO
 

Similar to Mrp 1 deepak 12mt07ind009 (20)

Material Requirement planning (factors,inputs,outputs,benifits)
Material Requirement planning  (factors,inputs,outputs,benifits)Material Requirement planning  (factors,inputs,outputs,benifits)
Material Requirement planning (factors,inputs,outputs,benifits)
 
Session 6-7-8 MRP.pptx PPC MBA Sem IV IB
Session 6-7-8 MRP.pptx PPC MBA Sem IV IBSession 6-7-8 MRP.pptx PPC MBA Sem IV IB
Session 6-7-8 MRP.pptx PPC MBA Sem IV IB
 
5 MRP.ppt
5 MRP.ppt5 MRP.ppt
5 MRP.ppt
 
5 MRP.ppt
5 MRP.ppt5 MRP.ppt
5 MRP.ppt
 
Mba ii pmom_unit-2.5 resource planning -mrp a
Mba ii pmom_unit-2.5 resource planning -mrp aMba ii pmom_unit-2.5 resource planning -mrp a
Mba ii pmom_unit-2.5 resource planning -mrp a
 
Material requirement planning
Material requirement planningMaterial requirement planning
Material requirement planning
 
MATERIAL REQUIREMENT PLANNING AND BILLS OF MATERIAL
MATERIAL REQUIREMENT PLANNING AND BILLS OF MATERIAL MATERIAL REQUIREMENT PLANNING AND BILLS OF MATERIAL
MATERIAL REQUIREMENT PLANNING AND BILLS OF MATERIAL
 
Mrp systems & scheduling
Mrp systems & schedulingMrp systems & scheduling
Mrp systems & scheduling
 
Materials requirement planning
Materials requirement planningMaterials requirement planning
Materials requirement planning
 
SCM 304 Supply Chain Management Material Requirements .docx
SCM 304 Supply Chain Management Material Requirements .docxSCM 304 Supply Chain Management Material Requirements .docx
SCM 304 Supply Chain Management Material Requirements .docx
 
Managing productions across Supply Chain
Managing productions across Supply ChainManaging productions across Supply Chain
Managing productions across Supply Chain
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006
 
Material Requirement Planning Presentation.ppt
Material Requirement Planning Presentation.pptMaterial Requirement Planning Presentation.ppt
Material Requirement Planning Presentation.ppt
 
Material Requirement Planning Presentation.ppt
Material Requirement Planning Presentation.pptMaterial Requirement Planning Presentation.ppt
Material Requirement Planning Presentation.ppt
 
Managing production across supply chain
Managing production across supply chainManaging production across supply chain
Managing production across supply chain
 
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi LabbanFiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
 
Resource Requirement Planning
Resource Requirement PlanningResource Requirement Planning
Resource Requirement Planning
 
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)
 
Production planning and control - Basic concepts
Production planning and control - Basic conceptsProduction planning and control - Basic concepts
Production planning and control - Basic concepts
 
Module11. Material requirement plan..pdf
Module11. Material requirement plan..pdfModule11. Material requirement plan..pdf
Module11. Material requirement plan..pdf
 

More from Akash Maurya

Marketing information system akash deep maurya
Marketing information system akash deep mauryaMarketing information system akash deep maurya
Marketing information system akash deep maurya
Akash Maurya
 
vinay kumar actuators report
vinay kumar   actuators reportvinay kumar   actuators report
vinay kumar actuators report
Akash Maurya
 
vinay kumar actuators presentation
vinay kumar   actuators presentationvinay kumar   actuators presentation
vinay kumar actuators presentation
Akash Maurya
 
ashok mule rapid prototyping questions
ashok mule   rapid prototyping questionsashok mule   rapid prototyping questions
ashok mule rapid prototyping questions
Akash Maurya
 
ashok mule rapid prototyping presentation
ashok mule   rapid prototyping presentationashok mule   rapid prototyping presentation
ashok mule rapid prototyping presentation
Akash Maurya
 
prakash agrawal rapid tooling questions
prakash agrawal   rapid tooling questionsprakash agrawal   rapid tooling questions
prakash agrawal rapid tooling questions
Akash Maurya
 
prakash agrawal rapid tooling presentation
prakash agrawal   rapid tooling presentationprakash agrawal   rapid tooling presentation
prakash agrawal rapid tooling presentation
Akash Maurya
 
shashank soni sensors presentation
shashank soni   sensors presentationshashank soni   sensors presentation
shashank soni sensors presentation
Akash Maurya
 
santosh kumar fuzzy logic presentation
santosh kumar   fuzzy logic presentationsantosh kumar   fuzzy logic presentation
santosh kumar fuzzy logic presentation
Akash Maurya
 
mohsin dalvi artificial neural networks questions
mohsin dalvi   artificial neural networks questionsmohsin dalvi   artificial neural networks questions
mohsin dalvi artificial neural networks questions
Akash Maurya
 
mohsin dalvi artificial neural networks presentation
mohsin dalvi   artificial neural networks presentationmohsin dalvi   artificial neural networks presentation
mohsin dalvi artificial neural networks presentation
Akash Maurya
 
sameer amale edm presentation
sameer amale   edm presentationsameer amale   edm presentation
sameer amale edm presentation
Akash Maurya
 
vivek sharma agv and asrs
vivek sharma   agv and asrsvivek sharma   agv and asrs
vivek sharma agv and asrs
Akash Maurya
 
nakul agarwal micromachining presentation
nakul agarwal   micromachining presentationnakul agarwal   micromachining presentation
nakul agarwal micromachining presentation
Akash Maurya
 
ravi reverseengineeringitsapplication01 121101044845-phpapp02
ravi reverseengineeringitsapplication01 121101044845-phpapp02ravi reverseengineeringitsapplication01 121101044845-phpapp02
ravi reverseengineeringitsapplication01 121101044845-phpapp02
Akash Maurya
 
shivkumar pathak web based manufacturing presentation
shivkumar pathak   web based manufacturing presentationshivkumar pathak   web based manufacturing presentation
shivkumar pathak web based manufacturing presentation
Akash Maurya
 
nishit ambule special purpose machines questions
nishit ambule   special purpose machines questionsnishit ambule   special purpose machines questions
nishit ambule special purpose machines questions
Akash Maurya
 
nishit ambule special purpose machines presentation
nishit ambule   special purpose machines presentationnishit ambule   special purpose machines presentation
nishit ambule special purpose machines presentation
Akash Maurya
 
visheshwar oraon robotics presentation
visheshwar oraon   robotics presentationvisheshwar oraon   robotics presentation
visheshwar oraon robotics presentation
Akash Maurya
 
nikhil bhagat cmm presentation
nikhil bhagat   cmm presentationnikhil bhagat   cmm presentation
nikhil bhagat cmm presentation
Akash Maurya
 

More from Akash Maurya (20)

Marketing information system akash deep maurya
Marketing information system akash deep mauryaMarketing information system akash deep maurya
Marketing information system akash deep maurya
 
vinay kumar actuators report
vinay kumar   actuators reportvinay kumar   actuators report
vinay kumar actuators report
 
vinay kumar actuators presentation
vinay kumar   actuators presentationvinay kumar   actuators presentation
vinay kumar actuators presentation
 
ashok mule rapid prototyping questions
ashok mule   rapid prototyping questionsashok mule   rapid prototyping questions
ashok mule rapid prototyping questions
 
ashok mule rapid prototyping presentation
ashok mule   rapid prototyping presentationashok mule   rapid prototyping presentation
ashok mule rapid prototyping presentation
 
prakash agrawal rapid tooling questions
prakash agrawal   rapid tooling questionsprakash agrawal   rapid tooling questions
prakash agrawal rapid tooling questions
 
prakash agrawal rapid tooling presentation
prakash agrawal   rapid tooling presentationprakash agrawal   rapid tooling presentation
prakash agrawal rapid tooling presentation
 
shashank soni sensors presentation
shashank soni   sensors presentationshashank soni   sensors presentation
shashank soni sensors presentation
 
santosh kumar fuzzy logic presentation
santosh kumar   fuzzy logic presentationsantosh kumar   fuzzy logic presentation
santosh kumar fuzzy logic presentation
 
mohsin dalvi artificial neural networks questions
mohsin dalvi   artificial neural networks questionsmohsin dalvi   artificial neural networks questions
mohsin dalvi artificial neural networks questions
 
mohsin dalvi artificial neural networks presentation
mohsin dalvi   artificial neural networks presentationmohsin dalvi   artificial neural networks presentation
mohsin dalvi artificial neural networks presentation
 
sameer amale edm presentation
sameer amale   edm presentationsameer amale   edm presentation
sameer amale edm presentation
 
vivek sharma agv and asrs
vivek sharma   agv and asrsvivek sharma   agv and asrs
vivek sharma agv and asrs
 
nakul agarwal micromachining presentation
nakul agarwal   micromachining presentationnakul agarwal   micromachining presentation
nakul agarwal micromachining presentation
 
ravi reverseengineeringitsapplication01 121101044845-phpapp02
ravi reverseengineeringitsapplication01 121101044845-phpapp02ravi reverseengineeringitsapplication01 121101044845-phpapp02
ravi reverseengineeringitsapplication01 121101044845-phpapp02
 
shivkumar pathak web based manufacturing presentation
shivkumar pathak   web based manufacturing presentationshivkumar pathak   web based manufacturing presentation
shivkumar pathak web based manufacturing presentation
 
nishit ambule special purpose machines questions
nishit ambule   special purpose machines questionsnishit ambule   special purpose machines questions
nishit ambule special purpose machines questions
 
nishit ambule special purpose machines presentation
nishit ambule   special purpose machines presentationnishit ambule   special purpose machines presentation
nishit ambule special purpose machines presentation
 
visheshwar oraon robotics presentation
visheshwar oraon   robotics presentationvisheshwar oraon   robotics presentation
visheshwar oraon robotics presentation
 
nikhil bhagat cmm presentation
nikhil bhagat   cmm presentationnikhil bhagat   cmm presentation
nikhil bhagat cmm presentation
 

Recently uploaded

space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 

Recently uploaded (20)

space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 

Mrp 1 deepak 12mt07ind009

  • 2. Contributors to MRP • Joseph Orlicky(1964) • Oliver Wight(1983) • MRP started in the late 1960s. The technique was applied first to mobile and airplane industry. As the technique became well known, many large and small businesses adopted MRP method in order to increase their productivity and decrease the production cost.
  • 3. INTRODUCTION • The main function of material requirements planning is to guarantee material availability, that is, it is used to procure or produce the required quantities on time both for internal purposes and for sales and distribution. • This process involves - monitoring of stocks, - automatic creation of procurement proposals for purchasing and production. • In doing so, MRP tries to strike the best balance possible between - optimizing the service level and -minimizing costs and capital lockup.
  • 4. MRP is • Production Planning System • Computerized Inventory Control • Management Information System • Manufacturing Control System MRP software- Tuppus, Eci M1, E2 shop system 4
  • 5. MRP system Gives answer • What items are required? • How many are required? • When are they required? 5
  • 6. Objectives • Materials and products are available for production and delivery to customers. • Maintain the lowest possible level of inventory. • Plan manufacturing activities, delivery schedules and purchasing activities. 6
  • 7. When to use MRP? It is useful for….. • Independent Demand vs Dependent Demand • Lumpy demand • Lead time( order lead time, manufacturing lead time ) • Common use items 7
  • 8. 8
  • 10. Overview of the MRP System Product Structure File Master Production Schedule Inventory Master File Material Requirements Planning Manufacturing Orders Purchase Orders Various Reports 10
  • 11. MRP Inputs • Master Production Schedule • Product Structure File • Inventory Master File 11
  • 12. Master Production Schedule • A master schedule is the result of disaggregation of an aggregate plan. • A master schedule show the quantity & timing of specific end item for a time horizon. • Schedule of Finished Products • Represents Production, not Demand • Combination of Customer Orders and Demand Forecasts • What Needs to be Produced 12
  • 13. Product Structure File • It shows diagrammatically the component required to assemble it,their no,& the sequence of assembly. Bill of Material(BOM) Documentation of product structure. 13
  • 14. 10 Bicycle(1) Level 0 Handle Bars (1) Level -1 Frame Assembly (1) Level-1 Wheels (2) Level -2 Frame (1) Level-2 Product Structure Tree
  • 15. Product structure & BOM 15 Bicycle(1) Level 0 Handle Bars (1) Level -1 Frame Assembly (1) Level-1 Wheels (2) Level -2 Frame (1) Level-2 Itemno. Level product LeadtimepartcodeQuantity 1 level0 bicycle P/N1000 10 2 level1 handlebar 1wk P/N1002 10 3 level1 frameass. 1wk P/N1023 10 4 level2 wheel 2wk P/N1045 20 5 level2 frame 2wk P/N1034 10
  • 16. Inventory Master File A database of information contain • Raw material & purchased component. • In process inventory • Finished product • Lot Sizes • Safety Stock • Lead Time • Past-Usage Figures 16
  • 17. MRP Outputs • Planned order report 1. Time for order(Lead time) 2. Helps in preparing founds. • Order release report 1. Order size*, release date. 2. Purchase order taking care of lead time. • Order change report 1. Changing demand ,order,leadtime. 17
  • 18. Order size in MRP Lot for lot method EOQ methd Least total cost method Least unit cost method 18
  • 20. Terms Defined • Item – name or number for the item being scheduled • Low-Level Code – the lowest level of the item on the product structure file • Lot Size – order multiples of quantity • Lead Time – the time from when an order is placed to when it is received • PD – Past Due Time Bucket, orders behind schedule 20
  • 21. Terms Defined • Gross Requirements – demand for an item by time period • Scheduled Receipts – material already ordered • Projected on Hand – expected ending inventory • Net Requirements – number of items to be provided and when • Planned Order Receipts – net requirements adjusted for lot size • Planned Order Releases – planned order receipts offset for lead times 21
  • 22. MRP format Item: A Low-Level Code: 1 Lot Size: 25 Lead Time: 1 PD 1 2 3 4 5 Gross Requirements Scheduled Receipts Projected on Hand Net Requirements Planned Order Receipts Planned Order Releases 22
  • 23. MRP PROCESS 23 Masterproduction schedule foritemA Period(w) 1 2 3 4 5 6 7 8 gross requirement 450 600 MRP report foritemBA LT=1Week Period in weeks 1 2 3 4 5 6 7 8 Gross requirement 450 600 Schedule receipts Projecton hand 100 100 100 100 Netrequirement 350 600 Planned orderrecepits 350 600 Planned orderrelease 350 600
  • 24. • GROSS REQUIREMENT OF COMPONENT B=2*350=700 • GROSS REQUIREMENT OF COMPONENT C=1*350=350 24 A(1) LT=1 B (2) LT=1 C(1) LT-1 Product structure file
  • 25. 25 Master production schedule for item A Period(w) 1 2 3 4 5 6 7 8 gross requirement 450 600 MRP report for item BA ,LT=1Week Period in weeks 1 2 3 4 5 6 7 8 Gross requirement 450 600 Schedule receipts Project on hand 100 100 100 100 Net requirement 350 600 Planned order recepits 350 600 Planned order release 350 600 MRP report for item BB,LT=1week Period in weeks 1 2 3 4 5 6 7 8 Gross requirement 700 1200 Schedule receipts Project on hand Net requirement 700 1200 Planned order recepits 700 1200 Planned order release 700 1200 MRP report for item BC,LT=2week Period in weeks 1 2 3 4 5 6 7 8 Gross requirement 350 600 Schedule receipts Project on hand Net requirement 350 600 Planned order recepits 350 600 Planned order release 350 600
  • 26. What can MRP do? • Reduce Inventory Levels • Reduce Component Shortages • Improve Shipping Performance • Improve Customer Service • Improve Productivity • Simplified and Accurate Scheduling • Reduce Purchasing Cost • Improve Production Schedules • Reduce Manufacturing Cost • Reduce Lead Times • Less Scrap and Rework • Higher Production Quality 26
  • 27. Limitation of MRP • No account of capacity(deal with MRP=II) • Data sensitive • Lead time 27
  • 28. 28 Case study PAL MOHAN ELECTRONIX PVT. LIMITED , DELHI produces a line of electric meters installed in residential buildings by electric utility companies to measure power consumption. Meters used on single-family homes are of two basic types for different voltage and amperage ranges. In addition to complete meters, some parts and subassemblies are sold separately for repair or for changeovers to a different voltage or power load.  Forecasting demand •The problem for the MRP system is to determine a production schedule that would identify each item, the period it is needed, and the appropriate quantities. •This schedule is then checked for feasibility, and the schedule is modified if necessary.
  • 29. 29 Structure of the study Section 1. Master Production Schedule Section 2. Bill of Materials (Product Structure) File Section 3. Inventory Records (Item Master) File Section 4. Running the MRP Program Section 5. Obtainability control
  • 30. 30 Section 1. Master Production Schedule Forecasting demand
  • 31. 31 Section 2. Bill of Materials (Product Structure) File.
  • 32. 32 Section 3. Inventory Records (Item Master) File
  • 33. 33 Section 4 . Running the MRP Program
  • 34. 34 Section 5-Obtainability Control • ROUGH-CUT CAPACITY PLANNING(MRP-2) • PREPARE REPORT •It should have to be asked after applying the MRP that whether the MRP schedule was feasible or not. If it is not so, then the new revised MPS has to be applied with MRP packages
  • 35. Refernce • Cad/Cam-Mikell P. Groover • Automation & production,CIM-Mikell P. Groover • wikipedia.org/wiki/Material requirements planning 35

Editor's Notes

  1. Today we will discuss what Material Requirements Planning is and how we can use it in our organization.
  2. Material Requirements Planning was introduced in the 1970’s. Much of the credit goes to three individuals by the names of Joseph Orlicky, George Plossl, and Oliver Wight. The American Production and Inventory Control Society (APICS), which was endorsed by Orlicky, Plossl, and Wight, was also credited with the introduction of MRP.
  3. MRP is a system that controls inventory levels, plans production, helps supply management with important information, and helps with the manufacturing control system with respect to the production of assembled parts.
  4. The is an overview of how the MRP system works. The Orange boxes indicate the inputs into the MRP system. The MRP system then processes the information and delivers outputs as indicated by the yellow boxes.
  5. The three main inputs into the MRP system are product structure files, master production schedules, and inventory master files. These three main inputs summarize the input requirements described earlier.
  6. The master production schedule specifies which end items or finished products the company is to produce, how many are needed, and when they are needed. The numbers that are on the master production schedule represent production, not demand, may be a combination of customer orders and demand forecasts, and gives what needs to be produced.
  7. The master production schedule specifies which end items or finished products the company is to produce, how many are needed, and when they are needed. The numbers that are on the master production schedule represent production, not demand, may be a combination of customer orders and demand forecasts, and gives what needs to be produced.
  8. This file includes all the numbers from inventory. The MRP system keeps track of your inventory and when more items need to be ordered. It is important that you inventory numbers are accurate from the beginning in order for the MRP system to work properly.
  9. The MRP system delivers two main outputs along with various other reports. The two main outputs are manufacturing orders which can be released to shop floors for in-house production and purchasing orders which are sent to outside suppliers. The various reports offer suggested changes in previous plans or existing schedules.
  10. Some of the terms that are used with the MRP matrix are defined above. This should help the user understand how the MRP calculates everything.
  11. More terms defined.
  12. Here’s an example of how the MRP process works. This is a preliminary schedule that the MRP system gathered from the master production schedule, inventory master file, and product structure file. The question now is in what period should orders be released and what should be the size of those orders?
  13. MRP can do many things to help your company succeed. Probably the most important quality of MRP is the fact that it will help your company with inventory. It plans production so that the right materials are at the right place at the right time.