SlideShare a Scribd company logo
PRODUCTION
SCHEDULING
Unit-4
Production Scheduling
• Production Control has the controlling
Mechanism, tries to take corrective action to
match the planned and actual production.
Thus production control review the progress
of the work, takes and corrective step in order
to ensure that programmed production takes
place.
Functions of Production Control and
Scheduling
Release Order – to the system
Assign Work – to work Centers
Sequencing priority Jobs
Control – the manufac. Lead Time
Monitor Priority Status
Monitor Capacity Status
Six Key
Functio
ns
Production Scheduling & Control Function
Machine Loading
• Loading is also Known as Machine loading,
may be defined as the assignment of work to a
facility ( facility may be machine, group of
men, entire plan, etc.,) without specifying
when the work is to be done and in what
sequence.
Loading Chart
Loading
Loading Provides:
• An information to ensure the efficient
utilization of the plant and labor in a factory:
• An Information to help in setting of reliable
delivery.
• An information to assist in forward planning of
purchase of the new plant.
Objective of Loading
• To Check the feasibility of production
programmes.
• To assist in the efficient planning of new work.
• To assist in balancing the plant to the existing
load.
• To assist in fixing of reliable delivery promises.
PRODUCTION CONTROL
Production Scheduling
• A Production Scheduling is like a timetable
that tells us what machine or department
should be doing what and when.
• The production schedule should be
formulated for the method which satisfactorily
match the system requirement with the
available resources.
Scheduling
• Scheduling refers to the setting of operation
start dates so that jobs will be completed by
their due date.
• In broader sense scheduling establishes the
timing of productive activities that use the
firm’s human and equipment resources to
serve its customers.
Scheduling
• The various function an effective production
scheduling system included:
• Allocating Jobs to facilities.
• Establishing a set of rules of priorities to
sequences the activities on the facilities.
• Dispatching job orders as per the scheduling
to initiate loading of jobs to facilities.
• Expediting the critical job.
Objectives of scheduling
• To meet the due dates.
• To minimize lead time.
• To minimize setup time or cost,
• To minimize work-in-process inventory,
• To maximize machine or labour utilization.
Data Requirement
• The Production Scheduling requires accurate
information on:
• The current status of jobs (e.g., what orders
are in process and where);
• What upcoming jobs are available.
• The adequacy of materials and capacities.
• The equipment and labour utilization.
• Job progress and efficiency.
Type of Scheduling Tools/
Techniques
• Master Scheduling (Master production
Scheduling )
• The master schedule also known as master
production schedule (MPS), Formalize the
production plan and translate it into specific
end-item requirement over a short to
intermediate planning horizon.
Master Scheduling Vs Aggregate
Plan
• Aggregate Planning is the process of Planning
the quality and timing of output the medium
range (often 3 to 18 Months) by adjusting the
production rate, Employment inventory, and
other Controllable Variables.
Inputs to MRP
• The major inputs to the master production
schedule are:
• Forecast of demand of end items,
• Customer orders, and
• Inventory on-hand fro the previous period.
Function of MPS
• The main function of MPS-
• To translate aggregate plans into specific end
items.
• To evaluate alternative schedule.
• To Generate Materials requirements.
• To generate capacity requirement.
• To facilities information processing.
Flow Chart of Master Production
Scheduling
Gantt Chart
• Gantt Chart are simple bar graph that can be
used to schedule any type of operation. These
chart are named after its originator.
• Gantt Chart are usual (Bar Chart) aids used to
depict the sequencing load on facilities or
progress associated with work efforts over a
well-defined time period.
Gantt Chart
• Types of Gantt Chart- Gantt Workload Chart
1. A work load chart is usually used to depict
workload levels for equipment workstations
or departments.
Gantt Chart
• Gantt Scheduling Chart-
Perpetual Scheduling
• The copy of the order remains in the file until
the job is completed
• During the processing, the progress report is
reported with the help of the tickets such as
Inspection tickets, materials requisition
tickets, rework ticket, move tickets etc.,
Step-1 Making of Perpetual
Scheduling
• 1. preparation of load analysis sheet-
Step-2 Making Perpetual
Scheduling
• The total work load against each department
is added up and knowing the weekly capacity
of a department, the number of weeks load
against each department is calculated.
Scheduling n jobs on two Machine
(Johnson’s Rule)
• The objective of Johnson’s Rule is to minimize
the flow time from the beginning of the first
job until the finish of the last.
• In other words, Johnson’s Rule tries to
maximize the concurrent operating time both
the machines.
Problem Content
• The n Job 2-Machine Sequencing problem is
completely described as under-
• Only two machine are involved, say M1 and
M2.
• Each job is processed in the order (M1 and
M2).
• The exact or expected processing times for all
the job that minimizes the total completion
time.
Johnson’s Rule Steps
• Step-1 List the operation times, each job on
the both machines.
• Step-2 Select the shortest operation time.
• Step-3 If the shortest time is for the first
machine, do the job first. If the second
machine does the last job.
• Step-4 Repeat Step 2 and 3 for each remaining
job until the schedule is complete.
Scheduling n jobs on three
machine (n/3 Scheduling )
• Johnson’s method can be extended to yield an
optimal solution for the n/3 scheduling
problems.
• Problem Content: The n-Job 3 Machine
sequencing problems is described as follows.
1. Only three machine are involved say M1,M2
and M3.
2. Each Job is processed in the prescribed order
M1, M2 and M3
Scheduling n jobs on three
machine (n/3 Scheduling )
• No Passing of Jobs is permitted (i.e., the same
order over each machine is maintained).
• The exact or expected processing time on
three machine are known.
• The problem, again is to find the optimum
sequence of the job which minimizes the total
flow time.
Extended Johnson Rule
• The Johnson’s Rule can be extracted to solve
the n/3 scheduling problems where either one
or both of the following conditions hold good:
1. Maximum time on machine M1 ≥ Max time
on Machine M2.
2. Minimum time on machine M3 ≥ Max time
on Machine M2.
Extended Johnson Rule
• The method consist of replacing the given
problem by an equivalent problem involving n
job and two machines.
• The two hypothetical machines are denoted
by G and H and their corresponding
processing times are given by
Scheduling a set numbers of jobs
on the same Number of Machine
• The assignment method is a special case of
transportation method of liner programming.
It can be applied to situation where there are
n supply sources and n demand sources (e.g.,
five jobs on five machines).
• This method is useful in application involving
allocation of jobs to work center.
Graphical Procedure
• Construct a two dimensional graph where x-
axis represent the processing time and
sequence of job 1 on the m machine while y-
axis represent those of jobs 2 ( use the same
scale for both x and y)
• Shade the areas where a machine would be
occupied by the two job at the same time.
Scheduling 2 Jobs in ‘M’ Machine
• The processing of both jobs can be
represented by a continuous path which
consist of horizontal, vertical and 45˚ diagonal
segments.
The Path Starts at lower left corner and stops at
the upper right corner, while avoiding the
shaded area in the graph. In other words the
path is not allowed to pass through the shaded
areas.
BATCH PRODUCTION SCHEDULING
• Batch production scheduling is preferred
when a variety of product are to be made and
the volume are not large enough to demand a
separate line for each product.
• In batch production system, the output is
inventoriable and can be produced in
substantial volume.
Batch Scheduling
• In such situation, it is necessary to determine
the lot size for batch to be produced at one
time in addition to scheduling the batch on
the facilities.
• In other words, the decision to be taken in
batch production scheduling are:
1. The Economic Batch Size Decision, and
2. The scheduling decision (regarding when to
begin the processing of the batch)
Determination of Economic Batch
Quantity (EBQ)
• The EBQ formula can be reproduced as below
Batch Scheduling
• Batch Scheduling also Known as EBQ Scheduling
can be performed by using aggregate run-method.
1.Aggregate Run-out Method-
• Aggregate run out method also known as
aggregate run-out time method (AROT) method,
can be used to determine production runs for a
group of items that requires the same production
facilities.
Procedure for AROT
1. Compute the Aggregate run-out time (AROT)
of Each item required for a product.
2. Rank the items in the ascending order of
their run-out times (ROT’s)
3. Schedule the item with the lowest ROT first,
followed by the item with the next Lowest
ROT.
Line of balance
• Line of Balance (LOB) is charging technique that
uses lead times and assembling sequencing to
compare planned component completions with
actual component completions.
• The Technique is used to compare progress on
each operation with the progress that would
be required to meet the delivery requirement
to cope with market Demand.
Uses of Line of balance
• Source of Each component element (purchase,
Manufacture, Assemble, test, etc.,)
• Sequence of assembly, including sub
assembly, test and inspection, packaging,
shipping and relative activities.
• Comparison of schedule versus actual finished
product deliveries.
• Comparison of schedule versus actual
component showing present and potential
shortage or delay.
Various Charts of LOB
• Operation Chart.
• Objective Chart.
• Progress Chart.
• Line of Balance.
Operation Chart
• Operation Chart is also known as program
plan or production lead time chart or
assembly chart is chart that shows the lead
time for each operation stage/processing step.
Objective Chart
• Objective Chart shows the contrast between
expected completion schedule of production
and actual performance.
• The objective Chart Shows-
1. The Difference between the schedule and
actual deliveries,
2. The time lag between the schedule and
actual deliveries.
Objective Chart
Objective Chart
Line of Balance
• The line of Balance chart shows the quantity
of item that should have been completed at
each operation stage in a particular time at
which, progress will be reviewed so as to meet
the delivery schedule for the finished product
and to meet the completion schedule
quantities cumulatively.
Progress Chart
• The progress chart is a type of chart which
shows the actual number of items produced
at each operation stage against the quantities
that should have been produced as indicated
by the line of Balance.
Progress Chart
Material Requirement Planning
(MRP)
• Material Requirement Planning (MRP) is a
computational technique that convert the
master schedule for final product into a
detailed schedule for the raw materials and
parts used in the final product.
Input of MRP
• The three important inputs to MRP are:
1. Master Production Schedule.
2. Bill of Materials.
3. Inventory Record File.
Structure of MRP
Master Production Schedule (MPS)
• Master Production Schedule (MPS) is Detailed
Plan that states how many end items (i.e., the
final product to be sold to the customer) will
be available for sale or distribution during
specific periods.
• Inputs of MPS
1. Market Requirements,
2. Production Plan from Aggregate Planning,
3. Resources Available.
Inventory Record file
• All data related to the inventory are recorded
in the inventory record file.
• The inventory record file contains the
following three segments:
1. Item master Data Segment: It provides a time
phased record of Inventory status.
2. Subsidiary Data Segment; It provides the
subsidiary data such as purchase order, scarp
etc.,
MRP Outputs Report
• Primary Outputs includes-
1. Order Release notice, to place order that
have been Planned by the MRP System.
2. Report of Planned order Releases in future
periods.
3. Rescheduling Notices, to indicate the
changes in due dates for open orders.
Dispatching and Expediting
• Dispatching is the routine of setting
productive activities in motion through the
release of orders and instructions, in
accordance with previously planned times and
sequence, embodied in route sheet and
schedule charts.
Dispatching Activities
• The Following dispatching activities from
stores to the first process, and from process to
process.
• Issue of tool orders instructing, the tool
department to collect and make ready tools,
jigs and fixtures in advance of the time at
which the operation will start.
Dispatching activities
• Issue Job Order, authorizing operation, in
accordance with date and times previously
planned and entered on the machine loading
chart, route sheets and progress control
sheets or boards.
• Issue of time tickets, Issue of Inspection order,
Issue of move order.
Function of Dispatching
• To prepare manufacturing orders (which
consist of shop orders, move orders)
• Issue of materials from the stores.
• Issue of instruction to tool room.
• Issue of order authorizing the commencement
of operation in accordance with the
predicated dates.
Function of Dispatching
• Issue of time, time instruction cards, drawing.
• Issue of the order to the inspection
department.
• Ordering finished products to the finished
stock room.
• Time recording.
• Issue of time ticket to finance department.
• Recording of the idle time of machine and
operation.
Common Form used in Dispatching
• Material requisition.
• Job cards / tickets.
• Labor Cards/ tickets.
• Move Cards/ tickets.
• Inspection Cards / tickets.
Dispatching Rules
• When many Jobs are waiting before an
operation facility, we should have some rules
to decide the priority while dispatching.
• The most commonly used dispatching rules
are-
1. FCFS. 4. STR
2. SOT 5. Critical Ratio
3. Earliest Due date. 6. Queue Ratio
Expediting or Progressing
• Expediting also known as Follow-up
Progressing, is a control that keeps track of
the progress of work in accordance with the
planned.
• This follow-up is to be done at every stage in
production Cycle i.e., to follow-up of work-in-
process, and follow-up-of- assembly.
Expediting or Progressing
• Functions of Expediting-
1. Status reporting.
2. Attending to bottlenecks or holdup in
production and removing the same.
3. Controlling variation or deviation from
planned performance levels.
4. Following up and monitoring progress at
work through all Stages of production.
Expediting or Progressing
• Co-ordinating with purchase, stores, tool room
and Maintenance department.
Types of Progressing-
1. Programme Control.
2. Order Progressing.
3. Shortage Chasing.
4. Daily Plan Progressing.
5. Department progress control.
Recording Progress
• The most widely used one are as follows
1. Gantt Chart- Gantt Chart are used to provide
an immediate comparison between schedule
the actual progress of the work.
2. Visual Chart- Visual Chart is the variations of
the Gantt Chart. Using pin board.
3. Cumulative and weekly Chart- the cumulative
Chart shows how much we have managed to
produce so far.

More Related Content

What's hot

PPC
PPCPPC
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
KunalJagtap5
 
Objectives and function of Production Planning and Control
Objectives and function of Production Planning and ControlObjectives and function of Production Planning and Control
Objectives and function of Production Planning and Control
madhannaveen
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
Dr. Prashant Kalaskar
 
Materials handling
Materials handlingMaterials handling
Materials handling
Rohit Verma
 
types of production system
types of production systemtypes of production system
types of production systemram4181
 
Introduction to Production Planning and control.
Introduction to Production Planning and control.Introduction to Production Planning and control.
Introduction to Production Planning and control.
PraveenManickam2
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planningAtif Ghayas
 
Production planning and scheduling
Production planning and schedulingProduction planning and scheduling
Production planning and schedulingNew Nabin Shrestha
 
Work measurement
Work measurementWork measurement
Work measurement
Ratnadeepsinh Jadeja
 
Facility Layout in production management
Facility Layout in production managementFacility Layout in production management
Facility Layout in production management
Joshua Miranda
 
Production planning & control
Production planning & controlProduction planning & control
Production planning & controlamirthakarthi
 
Method study
Method studyMethod study
Method study
sparsh maheshwari
 
What is master production schedule
What is master production scheduleWhat is master production schedule
What is master production schedule
MRPeasy
 
Production management
Production managementProduction management
Production management
Simran Kaur
 
Production Planning and Control
Production Planning and ControlProduction Planning and Control
Production Planning and ControlSwatanu Satpathy
 

What's hot (20)

PPC
PPCPPC
PPC
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
 
Objectives and function of Production Planning and Control
Objectives and function of Production Planning and ControlObjectives and function of Production Planning and Control
Objectives and function of Production Planning and Control
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
 
Materials handling
Materials handlingMaterials handling
Materials handling
 
types of production system
types of production systemtypes of production system
types of production system
 
Introduction to Production Planning and control.
Introduction to Production Planning and control.Introduction to Production Planning and control.
Introduction to Production Planning and control.
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Production planning and scheduling
Production planning and schedulingProduction planning and scheduling
Production planning and scheduling
 
Work measurement
Work measurementWork measurement
Work measurement
 
Facility Layout in production management
Facility Layout in production managementFacility Layout in production management
Facility Layout in production management
 
Production planning & control
Production planning & controlProduction planning & control
Production planning & control
 
Method study
Method studyMethod study
Method study
 
What is master production schedule
What is master production scheduleWhat is master production schedule
What is master production schedule
 
Production systems
Production systemsProduction systems
Production systems
 
Production management
Production managementProduction management
Production management
 
TIME STUDY
TIME STUDYTIME STUDY
TIME STUDY
 
Production planning and_control-an_introduction
Production planning and_control-an_introductionProduction planning and_control-an_introduction
Production planning and_control-an_introduction
 
Ch17 scheduling
Ch17 schedulingCh17 scheduling
Ch17 scheduling
 
Production Planning and Control
Production Planning and ControlProduction Planning and Control
Production Planning and Control
 

Similar to production scheduling

scheduling in operations Management PPT O and M
scheduling in operations Management PPT O and Mscheduling in operations Management PPT O and M
scheduling in operations Management PPT O and M
ProfessionalDeeksha
 
Ppc unit-4-production scheduling
Ppc   unit-4-production schedulingPpc   unit-4-production scheduling
Ppc unit-4-production scheduling
karthi keyan
 
Scheduling Topic of Production and Operations
Scheduling Topic of Production and OperationsScheduling Topic of Production and Operations
Scheduling Topic of Production and Operations
ProfessionalDeeksha
 
Presentation on scheduling
Presentation on schedulingPresentation on scheduling
Presentation on scheduling
Gunjan Lal
 
Unit 7 production scheduling
Unit 7 production scheduling Unit 7 production scheduling
Unit 7 production scheduling
RASHMIPANWAR10
 
PRODUCTION PLANNING AND CONTROL-Unit 4
PRODUCTION PLANNING AND CONTROL-Unit 4PRODUCTION PLANNING AND CONTROL-Unit 4
PRODUCTION PLANNING AND CONTROL-Unit 4
prakash0712
 
Operation scheduling
Operation schedulingOperation scheduling
Operation schedulingsai precious
 
Unit 4
Unit 4Unit 4
Unit 4
dinesh babu
 
Unit 4
Unit 4Unit 4
Unit 4
Aravind Ra
 
Unit 4 PPC
Unit 4 PPCUnit 4 PPC
Unit 4 PPC
sivaprakash250
 
Unit 4
Unit 4Unit 4
Unit 4
MeganathanJ4
 
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROLUnit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Mohanumar S
 
PRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROLPRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROL
SIVASHANKAR N
 
unit 4.ppt
unit 4.pptunit 4.ppt
unit 4.ppt
rknatarajan
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and controlLaxmikant Deshmukh
 
Operations Scheduling
Operations SchedulingOperations Scheduling
Operations Scheduling
Ashish Jain
 
OPERATIONS SCHEDULING.pptx
OPERATIONS SCHEDULING.pptxOPERATIONS SCHEDULING.pptx
OPERATIONS SCHEDULING.pptx
RajviParmar5
 
Scheduling
SchedulingScheduling
Scheduling
mrinalmanik64
 
Scheduling
SchedulingScheduling
Scheduling
mrinalmanik64
 

Similar to production scheduling (20)

scheduling in operations Management PPT O and M
scheduling in operations Management PPT O and Mscheduling in operations Management PPT O and M
scheduling in operations Management PPT O and M
 
Ppc unit-4-production scheduling
Ppc   unit-4-production schedulingPpc   unit-4-production scheduling
Ppc unit-4-production scheduling
 
Scheduling Topic of Production and Operations
Scheduling Topic of Production and OperationsScheduling Topic of Production and Operations
Scheduling Topic of Production and Operations
 
Presentation on scheduling
Presentation on schedulingPresentation on scheduling
Presentation on scheduling
 
Unit 7 production scheduling
Unit 7 production scheduling Unit 7 production scheduling
Unit 7 production scheduling
 
PRODUCTION PLANNING AND CONTROL-Unit 4
PRODUCTION PLANNING AND CONTROL-Unit 4PRODUCTION PLANNING AND CONTROL-Unit 4
PRODUCTION PLANNING AND CONTROL-Unit 4
 
Operation scheduling
Operation schedulingOperation scheduling
Operation scheduling
 
Unit 4
Unit 4Unit 4
Unit 4
 
Unit 4
Unit 4Unit 4
Unit 4
 
Unit 4 PPC
Unit 4 PPCUnit 4 PPC
Unit 4 PPC
 
Unit 4
Unit 4Unit 4
Unit 4
 
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROLUnit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
 
PRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROLPRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROL
 
unit 4.ppt
unit 4.pptunit 4.ppt
unit 4.ppt
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and control
 
Operations Scheduling
Operations SchedulingOperations Scheduling
Operations Scheduling
 
OPERATIONS SCHEDULING.pptx
OPERATIONS SCHEDULING.pptxOPERATIONS SCHEDULING.pptx
OPERATIONS SCHEDULING.pptx
 
Unit 3 Manufacturing system design
Unit   3 Manufacturing system designUnit   3 Manufacturing system design
Unit 3 Manufacturing system design
 
Scheduling
SchedulingScheduling
Scheduling
 
Scheduling
SchedulingScheduling
Scheduling
 

More from PraveenManickam2

Chemical and Electro Chemical Based process
Chemical and Electro Chemical Based  processChemical and Electro Chemical Based  process
Chemical and Electro Chemical Based process
PraveenManickam2
 
Thermal and Electrical Energy based processes
Thermal and Electrical Energy based processesThermal and Electrical Energy based processes
Thermal and Electrical Energy based processes
PraveenManickam2
 
UCM Unit-1
UCM Unit-1UCM Unit-1
UCM Unit-1
PraveenManickam2
 
EBM
EBM EBM
Basics of UCM
Basics of UCMBasics of UCM
Basics of UCM
PraveenManickam2
 
AJM and WJM
AJM and WJMAJM and WJM
AJM and WJM
PraveenManickam2
 
EDM and Wire Cut EDM
EDM and Wire Cut EDMEDM and Wire Cut EDM
EDM and Wire Cut EDM
PraveenManickam2
 
Electro Chemical Machining Process
Electro Chemical Machining ProcessElectro Chemical Machining Process
Electro Chemical Machining Process
PraveenManickam2
 
Ultrasonic Machining Process
Ultrasonic Machining ProcessUltrasonic Machining Process
Ultrasonic Machining Process
PraveenManickam2
 
Abrasive Jet Machining Process and Water Machining Process
Abrasive Jet Machining Process and Water Machining ProcessAbrasive Jet Machining Process and Water Machining Process
Abrasive Jet Machining Process and Water Machining Process
PraveenManickam2
 
CNC Part Program
CNC Part ProgramCNC Part Program
CNC Part Program
PraveenManickam2
 
case hardening
case hardeningcase hardening
case hardening
PraveenManickam2
 
heat treatment
heat treatmentheat treatment
heat treatment
PraveenManickam2
 
steels
 steels steels
iron carbon system
iron  carbon systemiron  carbon system
iron carbon system
PraveenManickam2
 
cast iron
cast ironcast iron
cast iron
PraveenManickam2
 
cooling curve
cooling curvecooling curve
cooling curve
PraveenManickam2
 
Phase Diagram
Phase DiagramPhase Diagram
Phase Diagram
PraveenManickam2
 
Inventory production and Recent trends in PPC
Inventory production and Recent trends in PPCInventory production and Recent trends in PPC
Inventory production and Recent trends in PPC
PraveenManickam2
 
Production Planning and Process Planning
Production Planning and Process PlanningProduction Planning and Process Planning
Production Planning and Process Planning
PraveenManickam2
 

More from PraveenManickam2 (20)

Chemical and Electro Chemical Based process
Chemical and Electro Chemical Based  processChemical and Electro Chemical Based  process
Chemical and Electro Chemical Based process
 
Thermal and Electrical Energy based processes
Thermal and Electrical Energy based processesThermal and Electrical Energy based processes
Thermal and Electrical Energy based processes
 
UCM Unit-1
UCM Unit-1UCM Unit-1
UCM Unit-1
 
EBM
EBM EBM
EBM
 
Basics of UCM
Basics of UCMBasics of UCM
Basics of UCM
 
AJM and WJM
AJM and WJMAJM and WJM
AJM and WJM
 
EDM and Wire Cut EDM
EDM and Wire Cut EDMEDM and Wire Cut EDM
EDM and Wire Cut EDM
 
Electro Chemical Machining Process
Electro Chemical Machining ProcessElectro Chemical Machining Process
Electro Chemical Machining Process
 
Ultrasonic Machining Process
Ultrasonic Machining ProcessUltrasonic Machining Process
Ultrasonic Machining Process
 
Abrasive Jet Machining Process and Water Machining Process
Abrasive Jet Machining Process and Water Machining ProcessAbrasive Jet Machining Process and Water Machining Process
Abrasive Jet Machining Process and Water Machining Process
 
CNC Part Program
CNC Part ProgramCNC Part Program
CNC Part Program
 
case hardening
case hardeningcase hardening
case hardening
 
heat treatment
heat treatmentheat treatment
heat treatment
 
steels
 steels steels
steels
 
iron carbon system
iron  carbon systemiron  carbon system
iron carbon system
 
cast iron
cast ironcast iron
cast iron
 
cooling curve
cooling curvecooling curve
cooling curve
 
Phase Diagram
Phase DiagramPhase Diagram
Phase Diagram
 
Inventory production and Recent trends in PPC
Inventory production and Recent trends in PPCInventory production and Recent trends in PPC
Inventory production and Recent trends in PPC
 
Production Planning and Process Planning
Production Planning and Process PlanningProduction Planning and Process Planning
Production Planning and Process Planning
 

Recently uploaded

CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 

Recently uploaded (20)

CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 

production scheduling

  • 2. Production Scheduling • Production Control has the controlling Mechanism, tries to take corrective action to match the planned and actual production. Thus production control review the progress of the work, takes and corrective step in order to ensure that programmed production takes place.
  • 3. Functions of Production Control and Scheduling Release Order – to the system Assign Work – to work Centers Sequencing priority Jobs Control – the manufac. Lead Time Monitor Priority Status Monitor Capacity Status Six Key Functio ns
  • 4. Production Scheduling & Control Function
  • 5. Machine Loading • Loading is also Known as Machine loading, may be defined as the assignment of work to a facility ( facility may be machine, group of men, entire plan, etc.,) without specifying when the work is to be done and in what sequence.
  • 7. Loading Loading Provides: • An information to ensure the efficient utilization of the plant and labor in a factory: • An Information to help in setting of reliable delivery. • An information to assist in forward planning of purchase of the new plant.
  • 8. Objective of Loading • To Check the feasibility of production programmes. • To assist in the efficient planning of new work. • To assist in balancing the plant to the existing load. • To assist in fixing of reliable delivery promises.
  • 10. Production Scheduling • A Production Scheduling is like a timetable that tells us what machine or department should be doing what and when. • The production schedule should be formulated for the method which satisfactorily match the system requirement with the available resources.
  • 11. Scheduling • Scheduling refers to the setting of operation start dates so that jobs will be completed by their due date. • In broader sense scheduling establishes the timing of productive activities that use the firm’s human and equipment resources to serve its customers.
  • 12. Scheduling • The various function an effective production scheduling system included: • Allocating Jobs to facilities. • Establishing a set of rules of priorities to sequences the activities on the facilities. • Dispatching job orders as per the scheduling to initiate loading of jobs to facilities. • Expediting the critical job.
  • 13. Objectives of scheduling • To meet the due dates. • To minimize lead time. • To minimize setup time or cost, • To minimize work-in-process inventory, • To maximize machine or labour utilization.
  • 14. Data Requirement • The Production Scheduling requires accurate information on: • The current status of jobs (e.g., what orders are in process and where); • What upcoming jobs are available. • The adequacy of materials and capacities. • The equipment and labour utilization. • Job progress and efficiency.
  • 15. Type of Scheduling Tools/ Techniques • Master Scheduling (Master production Scheduling ) • The master schedule also known as master production schedule (MPS), Formalize the production plan and translate it into specific end-item requirement over a short to intermediate planning horizon.
  • 16. Master Scheduling Vs Aggregate Plan • Aggregate Planning is the process of Planning the quality and timing of output the medium range (often 3 to 18 Months) by adjusting the production rate, Employment inventory, and other Controllable Variables.
  • 17.
  • 18. Inputs to MRP • The major inputs to the master production schedule are: • Forecast of demand of end items, • Customer orders, and • Inventory on-hand fro the previous period.
  • 19. Function of MPS • The main function of MPS- • To translate aggregate plans into specific end items. • To evaluate alternative schedule. • To Generate Materials requirements. • To generate capacity requirement. • To facilities information processing.
  • 20. Flow Chart of Master Production Scheduling
  • 21. Gantt Chart • Gantt Chart are simple bar graph that can be used to schedule any type of operation. These chart are named after its originator. • Gantt Chart are usual (Bar Chart) aids used to depict the sequencing load on facilities or progress associated with work efforts over a well-defined time period.
  • 22. Gantt Chart • Types of Gantt Chart- Gantt Workload Chart 1. A work load chart is usually used to depict workload levels for equipment workstations or departments.
  • 23. Gantt Chart • Gantt Scheduling Chart-
  • 24. Perpetual Scheduling • The copy of the order remains in the file until the job is completed • During the processing, the progress report is reported with the help of the tickets such as Inspection tickets, materials requisition tickets, rework ticket, move tickets etc.,
  • 25. Step-1 Making of Perpetual Scheduling • 1. preparation of load analysis sheet-
  • 26. Step-2 Making Perpetual Scheduling • The total work load against each department is added up and knowing the weekly capacity of a department, the number of weeks load against each department is calculated.
  • 27. Scheduling n jobs on two Machine (Johnson’s Rule) • The objective of Johnson’s Rule is to minimize the flow time from the beginning of the first job until the finish of the last. • In other words, Johnson’s Rule tries to maximize the concurrent operating time both the machines.
  • 28. Problem Content • The n Job 2-Machine Sequencing problem is completely described as under- • Only two machine are involved, say M1 and M2. • Each job is processed in the order (M1 and M2). • The exact or expected processing times for all the job that minimizes the total completion time.
  • 29. Johnson’s Rule Steps • Step-1 List the operation times, each job on the both machines. • Step-2 Select the shortest operation time. • Step-3 If the shortest time is for the first machine, do the job first. If the second machine does the last job. • Step-4 Repeat Step 2 and 3 for each remaining job until the schedule is complete.
  • 30. Scheduling n jobs on three machine (n/3 Scheduling ) • Johnson’s method can be extended to yield an optimal solution for the n/3 scheduling problems. • Problem Content: The n-Job 3 Machine sequencing problems is described as follows. 1. Only three machine are involved say M1,M2 and M3. 2. Each Job is processed in the prescribed order M1, M2 and M3
  • 31. Scheduling n jobs on three machine (n/3 Scheduling ) • No Passing of Jobs is permitted (i.e., the same order over each machine is maintained). • The exact or expected processing time on three machine are known. • The problem, again is to find the optimum sequence of the job which minimizes the total flow time.
  • 32. Extended Johnson Rule • The Johnson’s Rule can be extracted to solve the n/3 scheduling problems where either one or both of the following conditions hold good: 1. Maximum time on machine M1 ≥ Max time on Machine M2. 2. Minimum time on machine M3 ≥ Max time on Machine M2.
  • 33. Extended Johnson Rule • The method consist of replacing the given problem by an equivalent problem involving n job and two machines. • The two hypothetical machines are denoted by G and H and their corresponding processing times are given by
  • 34. Scheduling a set numbers of jobs on the same Number of Machine • The assignment method is a special case of transportation method of liner programming. It can be applied to situation where there are n supply sources and n demand sources (e.g., five jobs on five machines). • This method is useful in application involving allocation of jobs to work center.
  • 35. Graphical Procedure • Construct a two dimensional graph where x- axis represent the processing time and sequence of job 1 on the m machine while y- axis represent those of jobs 2 ( use the same scale for both x and y) • Shade the areas where a machine would be occupied by the two job at the same time.
  • 36. Scheduling 2 Jobs in ‘M’ Machine • The processing of both jobs can be represented by a continuous path which consist of horizontal, vertical and 45˚ diagonal segments. The Path Starts at lower left corner and stops at the upper right corner, while avoiding the shaded area in the graph. In other words the path is not allowed to pass through the shaded areas.
  • 37. BATCH PRODUCTION SCHEDULING • Batch production scheduling is preferred when a variety of product are to be made and the volume are not large enough to demand a separate line for each product. • In batch production system, the output is inventoriable and can be produced in substantial volume.
  • 38. Batch Scheduling • In such situation, it is necessary to determine the lot size for batch to be produced at one time in addition to scheduling the batch on the facilities. • In other words, the decision to be taken in batch production scheduling are: 1. The Economic Batch Size Decision, and 2. The scheduling decision (regarding when to begin the processing of the batch)
  • 39. Determination of Economic Batch Quantity (EBQ) • The EBQ formula can be reproduced as below
  • 40. Batch Scheduling • Batch Scheduling also Known as EBQ Scheduling can be performed by using aggregate run-method. 1.Aggregate Run-out Method- • Aggregate run out method also known as aggregate run-out time method (AROT) method, can be used to determine production runs for a group of items that requires the same production facilities.
  • 41. Procedure for AROT 1. Compute the Aggregate run-out time (AROT) of Each item required for a product. 2. Rank the items in the ascending order of their run-out times (ROT’s) 3. Schedule the item with the lowest ROT first, followed by the item with the next Lowest ROT.
  • 42. Line of balance • Line of Balance (LOB) is charging technique that uses lead times and assembling sequencing to compare planned component completions with actual component completions. • The Technique is used to compare progress on each operation with the progress that would be required to meet the delivery requirement to cope with market Demand.
  • 43. Uses of Line of balance • Source of Each component element (purchase, Manufacture, Assemble, test, etc.,) • Sequence of assembly, including sub assembly, test and inspection, packaging, shipping and relative activities. • Comparison of schedule versus actual finished product deliveries. • Comparison of schedule versus actual component showing present and potential shortage or delay.
  • 44. Various Charts of LOB • Operation Chart. • Objective Chart. • Progress Chart. • Line of Balance.
  • 45. Operation Chart • Operation Chart is also known as program plan or production lead time chart or assembly chart is chart that shows the lead time for each operation stage/processing step.
  • 46. Objective Chart • Objective Chart shows the contrast between expected completion schedule of production and actual performance. • The objective Chart Shows- 1. The Difference between the schedule and actual deliveries, 2. The time lag between the schedule and actual deliveries.
  • 49. Line of Balance • The line of Balance chart shows the quantity of item that should have been completed at each operation stage in a particular time at which, progress will be reviewed so as to meet the delivery schedule for the finished product and to meet the completion schedule quantities cumulatively.
  • 50. Progress Chart • The progress chart is a type of chart which shows the actual number of items produced at each operation stage against the quantities that should have been produced as indicated by the line of Balance.
  • 52. Material Requirement Planning (MRP) • Material Requirement Planning (MRP) is a computational technique that convert the master schedule for final product into a detailed schedule for the raw materials and parts used in the final product.
  • 53. Input of MRP • The three important inputs to MRP are: 1. Master Production Schedule. 2. Bill of Materials. 3. Inventory Record File.
  • 55. Master Production Schedule (MPS) • Master Production Schedule (MPS) is Detailed Plan that states how many end items (i.e., the final product to be sold to the customer) will be available for sale or distribution during specific periods. • Inputs of MPS 1. Market Requirements, 2. Production Plan from Aggregate Planning, 3. Resources Available.
  • 56. Inventory Record file • All data related to the inventory are recorded in the inventory record file. • The inventory record file contains the following three segments: 1. Item master Data Segment: It provides a time phased record of Inventory status. 2. Subsidiary Data Segment; It provides the subsidiary data such as purchase order, scarp etc.,
  • 57. MRP Outputs Report • Primary Outputs includes- 1. Order Release notice, to place order that have been Planned by the MRP System. 2. Report of Planned order Releases in future periods. 3. Rescheduling Notices, to indicate the changes in due dates for open orders.
  • 58. Dispatching and Expediting • Dispatching is the routine of setting productive activities in motion through the release of orders and instructions, in accordance with previously planned times and sequence, embodied in route sheet and schedule charts.
  • 59. Dispatching Activities • The Following dispatching activities from stores to the first process, and from process to process. • Issue of tool orders instructing, the tool department to collect and make ready tools, jigs and fixtures in advance of the time at which the operation will start.
  • 60. Dispatching activities • Issue Job Order, authorizing operation, in accordance with date and times previously planned and entered on the machine loading chart, route sheets and progress control sheets or boards. • Issue of time tickets, Issue of Inspection order, Issue of move order.
  • 61. Function of Dispatching • To prepare manufacturing orders (which consist of shop orders, move orders) • Issue of materials from the stores. • Issue of instruction to tool room. • Issue of order authorizing the commencement of operation in accordance with the predicated dates.
  • 62. Function of Dispatching • Issue of time, time instruction cards, drawing. • Issue of the order to the inspection department. • Ordering finished products to the finished stock room. • Time recording. • Issue of time ticket to finance department. • Recording of the idle time of machine and operation.
  • 63. Common Form used in Dispatching • Material requisition. • Job cards / tickets. • Labor Cards/ tickets. • Move Cards/ tickets. • Inspection Cards / tickets.
  • 64. Dispatching Rules • When many Jobs are waiting before an operation facility, we should have some rules to decide the priority while dispatching. • The most commonly used dispatching rules are- 1. FCFS. 4. STR 2. SOT 5. Critical Ratio 3. Earliest Due date. 6. Queue Ratio
  • 65. Expediting or Progressing • Expediting also known as Follow-up Progressing, is a control that keeps track of the progress of work in accordance with the planned. • This follow-up is to be done at every stage in production Cycle i.e., to follow-up of work-in- process, and follow-up-of- assembly.
  • 66. Expediting or Progressing • Functions of Expediting- 1. Status reporting. 2. Attending to bottlenecks or holdup in production and removing the same. 3. Controlling variation or deviation from planned performance levels. 4. Following up and monitoring progress at work through all Stages of production.
  • 67. Expediting or Progressing • Co-ordinating with purchase, stores, tool room and Maintenance department. Types of Progressing- 1. Programme Control. 2. Order Progressing. 3. Shortage Chasing. 4. Daily Plan Progressing. 5. Department progress control.
  • 68. Recording Progress • The most widely used one are as follows 1. Gantt Chart- Gantt Chart are used to provide an immediate comparison between schedule the actual progress of the work. 2. Visual Chart- Visual Chart is the variations of the Gantt Chart. Using pin board. 3. Cumulative and weekly Chart- the cumulative Chart shows how much we have managed to produce so far.