SlideShare a Scribd company logo
ECNG 6503 -3
Advanced Power Systems Practice



            Lecturer
    Prof Chandrabhan Sharma
     University of the West Indies
         Trinidad and Tobago
Topics:

1 Differential Protection

2 Busbar Protection

3 Linear Couplers

4 Pilot wire Protection
DIFFERENTIAL PROTECTION
                  (Merz-Price Systems)
                    (Unit Protection)

3 Categories of Protection:

•   Input and Output Terminals are close
                            → transformer

•   Where ends are Geographically Separate
                           → overhead/underground cables
                           → pilots at supply frequency used

•   Very long lines           P.L.C.
                              → end → end signalling achieved
                              by modulated carrier waveform.

Main difference is in way signals derived & transmitted.
Why needed?:-

        Overcomes application difficulties of simple O.C. Relays
        when applied to complex networks e.g. Co-ordination
        problems and excessive fault clearance times.

Principle:-

        Measurement of current at each end of feeder and
        transmission of information between each end of feeder.

Protection should operate for fault inside protected Zone only
              →Stable for others.

i.e. Instantaneous Operation Possible!
MERZ-PRICE SYSTEM
       Circulating Current Mode




-   Current confined to series path. No currents in relay




-   Both breakers tripped..
BALANCED VOLTAGE SCHEME




When C.T. secondaries are short, can be applied to transformer,
busbars, machines etc.

Where boundaries are at distance, communication channel required.
SIMPLE LOCAL DIFFERENTIAL PROTECTION
UNIT PROTECTION INVOLVING DISTANCE BETWEEN
             CIRCUIT BREAKERS
EARLY MERZ-PRICE BALANCED VOLTAGE
       SYSTEMS FOR FEEDERS

Two Problems:

1. Maloperation due to unequal open circuit secondary voltages
   of the two transformers for thru fault currents.

2. High Output voltages of CT’s cause capacitance currents to
   flow through relay since capacitive currents are proportional to
   pilot length, relay insensitive for all but very short lines.
ACCURACY OF C.T.s

-   Accuracy of relaying signals (balanced) for faults
    external to protected zone.

-   Depends on characteristics of C.T. and burdens

-   Unequal magnetic saturation in 2 C.T.s due to unequal
    lead burdens

-   Need to define range of unbalance conditions for
    which protection is stable and inoperative

-   Use of complex ratio of IA/N and IB/N
Ideally, under conditions of exact balance, the point (1.0 +j 0.0)
would be the conditions for through faults in relay signal ratio plane

       NOTE: All unbalance defined w.r.t. (1.0 +j 0.0)

Zone of uncertainty is area enclosed by circle.
STABILITY MARGINS
Relay Setting corresponds to minimum value of current for
which relay operates.

OR

     Related to maximum out-of-balance current for which the
     protection (relay) is required to remain stable.

There are two methods to achieve stability margins:

1. Low-impedance relay and a current setting that would give
   the required thru-fault stability

2. High-impedance relay having an inherent low current setting.
By insertion of stabilising resistor (Rs) the stability margin may be
obtained.
SATURATION OF ONE C.T. (Equivalent cct)
Where:           R1, R2 → lead resistances



      RCA, RCB        →     core less

      For Transformer B saturated than:
                    Tx. B does not contribute to relay current



         If RS ›› R2 + RB

                  Neglecting leakage reactance XB, then



 ∴RS is chosen s.t. the largest value of IA will not cause relay
 operation.
For Faults within Zone:

       Let IR0 be the relay minimum current

       ImA, ImB is magnetising current of transformer A and B

       ∵ Minimum fault current referred to primary is

            Ifs = N(IRO + IMA + IMB)

i.e.    for IRO = 0.8 A

            ImA = ImB = 0.1 A

           N    = 500:1

∵      Ifs = 500(0.8 + 0.1 + 0.1)

           = 500 A (min. fault current at which protection operates)
Also:   if protection stable under thru fault condition.

∵       for fault if 16kA, with one transformer saturated

        →      RB=0.3 Ω; R1= R2=2.2 Ω
THROUGH FAULT




FIG 6. SINGLE-PHASE DIFFERENTIAL LOOP
FIG 7. BIASED DIFFERENTIAL RELAY
BIASED DIFFERENTIAL RELAY
CT2 provides phasor addition of currents circulating

Let SO= differential current required to operate relay

       and

   SB = bias

then % bias = B % =      SO/SB x 100
WITH TRANSFORMER B SATURATED




FIG 8(a) EQUIVALENT CIRCUIT OF BIASED DIFFERENTIAL RELAY
(Transformer B saturated)
Neglecting impedance of biased cct and leakage reactance of
saturated transformer.
N.B.
A specified value of fractional (%) bias is set by obtaining/ proportioning the
number of turns on the operate and bias windings.
% WINDING PROTECTED
CIRCULATING CURRENT PROTECTION


For generated voltage V         ∴ x = 1- Is/(V/R)
and for a fault position x




 Let setting current of
 relay be Is
                             ∴ x = 1 - Is/IR

                             Where x = % winding protected

                             and (1-x) = % winding not protected
SPECIAL CONSIDERATIONS
• Phase Shift between primary and secondary

• Winding turn ratios and effect of tap changers

• Different Zero – Phase – Sequence circuits depending on
  connection

• Magnetising Inrush

 Derived signals must take these three concerns into
 account when Differential Relays are applied.
ANALYSIS OF THE MERZ-PRICE UNIT PROTECTION




       Relay operates when IA≠ IB
              but IC = IA- IB            ……… (1)
∴ Relay operates when




 Let Nr = kNo where o<k<1                ………. (3)

 Sub into (2) equations (1) and (3)
        ∴ From which for threshold we have:
Question:
A 1 100kVA 2400/240V transformer is to be differentially protected.
Choose the C.T. ratios. Determine the ratio Nr/No if the relay is to tolerate
a mismatch in current of up to 20% of primary current (bias).
Solution:
Rated Primary Current of T/F : = 100/2.4 = 41.7 A
         ∴ Rated secondary = 41.7 x 10 = 417 A
 For C.T. Secondary = 1A
         Primary C.T. ratio   = 500:5
         Secondary C.T. ratio = 5000:5

For 20% mismatch (bias) → Reduction in Sensitivity
              → IA = 0.8 IB (At threshold)




     or 2 - k = 1.6 + 0.8k          k = 0.222
OVERALL DIFFERENTIAL PROTECTION OF STAR/DELTA
             POWER TRANSFORMER
Must Consider:         *    Magnetising inrush

• Phase shift between primary and secondary

• Turns ratio

• Zero sequence cct.

These can be compensated for by C.T. Connection

For the above:
TAP CHANGING
This can be represented by Figure (b)

Given a transformer with max. off-nominal position 20%

And fault current = 10 (rated)




            Iob = 2.5 (Rating)

                = normal
MAGNETISING INRUSH




• Harmonic Restraint → 2nd Harmonic to restraint winding

• Application of time delay (usually   0.2s)

• Desensitizing relay

• Mismatch of C.T.’s
Busbar Protection
Busbar Protection


• Purely Earth Fault System.

• Simply a measurement of fault current flowing from switchgear to
  earth.

• No other earth connection should be present.

• Switchgear must be isolated as a whole i.e. standing on
  concrete (grout).
• Resistance earth, connection of frame is as shown

•Ƶ   electrode   < 1Ω ;            Ƶframe ≃ 10Ω

                  I1 ≃ 10% [I1+ I2] = 0.1 IF      ∴ Setting is about ≃ Is=30% IF(normally)

• Foundations bolts should not touch steel reinforcement

• Grouting gives adequate insulation
BUSBAR DIFFERENTIAL SCHEME




                  3




• Two current balance loops.

• Plus check loop → safeguard against incorrect tripping due
                    to faults in differential system.

• Provides for both phase and earth faults.
Summation Schemes   By using different C.T. ratios, can differentiate between faults.




                                                      Phase and earth fault
                                                      circulating current
                                                      scheme using single
                                                      element relay and
                                                      current transformers
                                                      with different ratios in
                                                      each phase
LINEAR COUPLERS - (L.C.)
      -     Use of magnetic C.T. lead to errors in
            reproduction when fault at/near saturation

      -     D.C. saturation even greater problem

Solution:

      -     Linear Couplers (no iron core)

      -     Multi-restraint, variable percentage differential
            relay

      -     High impedance, voltage operated differential
            relay with series resonant cct. To limit
            sensitivity to dc.
L.C. DIFFERENTIAL SYSTEM
Of the 3 systems used (before) L.C. are:
       -      Fastest (operation)
       -      Easiest to apply, set and maintain.
       -      L.C. are air core reactors wound on non-
              magnetic toroidal cores

For L.C.

       Esec = M Ipri (volts)

Where Esec     – induced secondary voltage
      M        - mutual reactance of L.C.
      Ipri     - primary current in cct.

** Since L.C. has negligible response to DC, only s.s.
   conditions need be considered.
OPERATION (Busbar Protection)
∴ From the cct. given before




Where: IR      = current in L.C. secondary and relay
       Esec    = voltage induced L.C. secondary and relay
       Ipri    = primary current in each cct.
       M       = mutual reactance
       ƵC      = self-impedance of L.C. secondary
       ƵR      = relay impedance

N.B. For max. energy transfer, relay tap ≃ total self-impedance of all LC’s
in cct.
Question:
A section of a 230kV bus has 6 circuits (i.e. 3 Tx lines, 2 T/Fs to the 115 kV
system and 1 bus tie). The max. external fault is 23,800 A r.m.s and the
min. internal fault is 1800 A r.m.s. Six linear couplers are to be used in a
differential system to protect the bus. The recommended application range
between max. external fault and min. internal fault is 25:1. The mutual
reactance of each linear coupler is 0.005Ω. Determine the setting of the
relay given its recommended range is 15 mA ∼ 28 mA. The impedances of
each linear coupler cct are:

Transformer #1 = (9.8 + j10.75) Ω

Transformer #2 = (3.9 + j6.6) Ω

Line A = (4.3 + j7.2) Ω ;        Line B = (4.3 + j7.5) Ω

Line C = (3.0 + j3.6) Ω ;        bus tie = (10.7+ j12.7) Ω
PERFORMANCE OF PILOT WIRE
      PROTECTION SCHEMES
As any Differential Scheme, pilot wire may employ either of the
following principles:-
     (a) Balanced Voltage
    (b) Circulating Current

(a) Balanced Voltage (longitudinal differential protection)
                  A Voltage Driven Scheme
Also Vs= Vin ; Is = Iin + I1 = Yc Vin + Iin
Similarly for Vo = VR, Io = IR + I2 = (Yc VR+ IR)




    Sub (1) & (3) into (2)
(b) Circulating Current (transverse differential protection)
                   (Current Driven Scheme)




Note the interchange of the op. and res. windings.

Applications:- (i) Parallel lines

               (ii)Split winding generators

i.e. areas where current usually equal.
BALANCED-VOLTAGE PILOT WIRE
       PROTECTION (FEEDER)
The operating and restraint ccts. take the form of an amplitude
comparator.

For operation:

Effective operating Ampere turns > Effective Restraint Ampere turns

For threshold conditions (Receiving End)

                 k1IR > k2VR Yr

where Yr = admittance of restraint cct.

       (neglecting impedance of operating cct.)
Assuming Linearity of current/voltage relationship

                  IR    VR

              ∴ IR =VRYPR

Where

YPR = admittance presented by pilot cct to the receiving end relay

              ∴ k1 VRYPR > k2VRYr

              or YPR > k Yr for k = k2/ k1

i.e.
Operating and restraint ccts for a 2-input comparator for which
tripping occurs when the admittance of the pilot cct. exceeds k
times the admittance of the restraint cct.
Criterion for threshold:

The centre of the stability circle should be the point 1 0 on the
Vs/VR    plane. In practical pilots, transference of the admittance
characteristic to the IA/IB     plane necessitates compensation to
present zero admittance for Vs/VR= 1 0
PRACTICAL PILOT WIRE SCHEMES




      Comp - Compensation cct.
      Yc   - admittance of compensation cct.


 Ideally the cct is tuned so that the overall compensated
 pilot cct. (Yp+c) presents zero admittance to the relay for
 condition Vs/VR=1 0.
EVALUATION OF REQUIRED COMPENSATION(Yc)
        -       Assume a symmetrical pilot with network parameters
                A,B,C and D

        -       Let A’, B’, C’ and D’ be the parameters for the
                compensated network

        -       Neglect impedance of series op. cct and given that Yc
                is admittance of compensating network at either end.




where       A’ = A + BYc              ;        B’ = B
            C’ = AYc + C + Yc(BYc +D) ;        D’ = BYc+D
Centre of circle = 1 0
Assuming a symmetrical pilot, the sending end characteristics
can be found from inversion of the receiving end.
CIRCULATING CURRENT FEEDER
             PROTECTION SYSTEM




   Dual of Balanced-voltage scheme

  Note : ** Ƶc      is in series with pilot instead of shunt Yc **


Neglecting impedance of restraint circuit, the threshold condition
is found by equating the operating and restraint quantities, i.e.

                 I1 > I2
CIRCULATING CURRENT FEEDER PROTECTION
               SYSTEM
BRIDGE – Type Comparator Relay
     (circulating current)
General Locus of the fault Performance of the
         Differential Protection Systems




Where k1’ , k2’ ,   k3’ and k4’ may be expressed in terms of
distribution factors C1 and C0 for +ve and zero phase sequence,
the ratio zero to +ve phase sequence impedance and the
constants M, N, P of the summation device.
Determination of k1’ , k2’ , k3’ and k4’ for a S-L-G fault
Assumptions:
                     1. X/R ratio = constant
                     2. Complete transposition of line
                     3. Shunt capacitance neglected
                     4. Ƶ1 = Ƶ2

If Ƶ1 = Ƶ2   C1 = C2
        IA0 = (1 - C0)(IA1 - IB1)
        IB0 =     - C0 (IA1 - IB1)
                                     where Cn = distribution factor
        IA2 = (1 - C1)(IA1 - IB1)
                                               = Impedance ratio
        IB2 =     - C1 (IA1 - IB1)
Where k1 = M(1 - C0) + N + P (1 - C1)
        k2 = - [M(1 - C0) + P (1 - C1)]
         k3 = - [MC0 + PC1]
         k4 =    MC0 + N + PC1
Substitute into equation :    IA1/ IB1   in terms of (EA / EB)
We can simplify the network as :
From analysis of the preceding network
               EA1 = IA1C1Ƶ1 + (IA1 - IB1) C02Ƶ1
      And      EA1 - EB1 = IA1C1Ƶ1 + IB1(1 - C1)Ƶ1




    From which we obtain :




Recall that EA1 = (EA/ 3) i.e. pre-fault line voltage
N.B.   If resistance was not zero but = Rf then




   IA/ IB1   IN TERMS OF (EA / EB)

   Substitute equation(2) into (1) yields
Where
        The poles of the set of orthogonal circles being (k1’ / k3’ )
        and (k2’ / k4’ ) and all   circles will pass through there poles.


Further Reading


Jones, D and Rushton J : “Generalized locus charts for the
evaluation of differential feeder protection performance”
Institute of Electrical Engineers 113 pp 1194 (1966)


GO TO EXAMPLE 7.2 pg. 259 of “Unit Protection” handout and
EXAMPLE 7.3 pg. 265 as well as EXAMPLE 7.4 pg. 273

More Related Content

What's hot

Generator protection calculations settings
Generator protection calculations settingsGenerator protection calculations settings
Generator protection calculations settings
michaeljmack
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design)
SayanSarkar55
 
Protection of power transformer
Protection of power transformerProtection of power transformer
Protection of power transformer
Ritesh Verma
 
Lecture 7 Relay Coordination.pptx
Lecture 7 Relay Coordination.pptxLecture 7 Relay Coordination.pptx
Lecture 7 Relay Coordination.pptx
ssuserb444c3
 
Motor protection
Motor protectionMotor protection
Motor protection
H. Kheir
 
47526172-DIFFERENTIAL-PROTECTION-8.pptx
47526172-DIFFERENTIAL-PROTECTION-8.pptx47526172-DIFFERENTIAL-PROTECTION-8.pptx
47526172-DIFFERENTIAL-PROTECTION-8.pptx
Thien Phan Bản
 
Lineprotection basics june2008
Lineprotection basics june2008Lineprotection basics june2008
Lineprotection basics june2008
lankeshdb
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
SARAVANAN A
 
Electrical Protection Schemes in detail
Electrical Protection Schemes in detailElectrical Protection Schemes in detail
Electrical Protection Schemes in detail
Slides Hub
 
Transformer differential protection
Transformer differential protection Transformer differential protection
Transformer differential protection
michaeljmack
 
Sample calculation-for-differential-relays
Sample calculation-for-differential-relaysSample calculation-for-differential-relays
Sample calculation-for-differential-relays
Roberto Costa
 
Protection schemes and zones
Protection schemes and zonesProtection schemes and zones
Protection schemes and zones
Slides Hub
 
Power system Protection Services in India
Power system Protection Services in IndiaPower system Protection Services in India
Power system Protection Services in India
System Protection
 
Bus Bar protection
Bus Bar protectionBus Bar protection
Bus Bar protection
srini09
 
Power Transformer Differential protection
Power Transformer Differential protectionPower Transformer Differential protection
Power Transformer Differential protection
Rishi Tandon
 
Overview of Grounding for Industrial and Commercial Power Systems
Overview of Grounding for Industrial and Commercial Power SystemsOverview of Grounding for Industrial and Commercial Power Systems
Overview of Grounding for Industrial and Commercial Power Systems
michaeljmack
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
Power System Operation
 
Switch gear and protection
Switch gear and protectionSwitch gear and protection
Switch gear and protection
Dinesh Sharma
 
Generator grounding
Generator groundingGenerator grounding
Generator grounding
michaeljmack
 

What's hot (20)

Generator protection calculations settings
Generator protection calculations settingsGenerator protection calculations settings
Generator protection calculations settings
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design)
 
Protection of power transformer
Protection of power transformerProtection of power transformer
Protection of power transformer
 
Lecture 7 Relay Coordination.pptx
Lecture 7 Relay Coordination.pptxLecture 7 Relay Coordination.pptx
Lecture 7 Relay Coordination.pptx
 
Motor protection
Motor protectionMotor protection
Motor protection
 
47526172-DIFFERENTIAL-PROTECTION-8.pptx
47526172-DIFFERENTIAL-PROTECTION-8.pptx47526172-DIFFERENTIAL-PROTECTION-8.pptx
47526172-DIFFERENTIAL-PROTECTION-8.pptx
 
Lineprotection basics june2008
Lineprotection basics june2008Lineprotection basics june2008
Lineprotection basics june2008
 
Auto recloser
Auto recloserAuto recloser
Auto recloser
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
 
Electrical Protection Schemes in detail
Electrical Protection Schemes in detailElectrical Protection Schemes in detail
Electrical Protection Schemes in detail
 
Transformer differential protection
Transformer differential protection Transformer differential protection
Transformer differential protection
 
Sample calculation-for-differential-relays
Sample calculation-for-differential-relaysSample calculation-for-differential-relays
Sample calculation-for-differential-relays
 
Protection schemes and zones
Protection schemes and zonesProtection schemes and zones
Protection schemes and zones
 
Power system Protection Services in India
Power system Protection Services in IndiaPower system Protection Services in India
Power system Protection Services in India
 
Bus Bar protection
Bus Bar protectionBus Bar protection
Bus Bar protection
 
Power Transformer Differential protection
Power Transformer Differential protectionPower Transformer Differential protection
Power Transformer Differential protection
 
Overview of Grounding for Industrial and Commercial Power Systems
Overview of Grounding for Industrial and Commercial Power SystemsOverview of Grounding for Industrial and Commercial Power Systems
Overview of Grounding for Industrial and Commercial Power Systems
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
 
Switch gear and protection
Switch gear and protectionSwitch gear and protection
Switch gear and protection
 
Generator grounding
Generator groundingGenerator grounding
Generator grounding
 

Similar to ECNG 6503 # 3

ECNG 3015 - Overcurrent Protection
ECNG 3015 - Overcurrent ProtectionECNG 3015 - Overcurrent Protection
ECNG 3015 - Overcurrent Protection
Chandrabhan Sharma
 
substation protection basics.ppt
substation protection basics.pptsubstation protection basics.ppt
substation protection basics.ppt
Salim Palayi
 
ECNG 6503 #2
ECNG 6503  #2ECNG 6503  #2
ECNG 6503 #2
Chandrabhan Sharma
 
Presentation_ON-CHIP CURRENT SENSING TECHNIQUE FOR CMOS MONOLITHIC SWITCH-MOD...
Presentation_ON-CHIP CURRENT SENSING TECHNIQUE FOR CMOS MONOLITHIC SWITCH-MOD...Presentation_ON-CHIP CURRENT SENSING TECHNIQUE FOR CMOS MONOLITHIC SWITCH-MOD...
Presentation_ON-CHIP CURRENT SENSING TECHNIQUE FOR CMOS MONOLITHIC SWITCH-MOD...Manmeet Singh
 
Electronics and Communication Engineering
Electronics and Communication EngineeringElectronics and Communication Engineering
Electronics and Communication Engineering
Ekeeda
 
Simple 100 w inverter circuit
Simple 100 w inverter circuitSimple 100 w inverter circuit
Simple 100 w inverter circuit
Narasimha Reddy
 
CT design aspects - Nageswar-6
CT design aspects - Nageswar-6CT design aspects - Nageswar-6
CT design aspects - Nageswar-6Nageswar Rao
 
Switched capacitor filter
Switched capacitor filter Switched capacitor filter
Switched capacitor filter Minh Anh Nguyen
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
theijes
 
Memristors and their potential applications 2012
Memristors and their potential applications 2012Memristors and their potential applications 2012
Memristors and their potential applications 2012
Md Kafiul Islam
 
CT and VT.pptx
CT and VT.pptxCT and VT.pptx
CT and VT.pptx
MAHMOUDMOHAMED431205
 
Relays and its types - complete guide
Relays and its types - complete guideRelays and its types - complete guide
Relays and its types - complete guide
Slides Hub
 
Apparatus Protection Using Relays for Engineering Students
Apparatus Protection Using Relays for Engineering StudentsApparatus Protection Using Relays for Engineering Students
Apparatus Protection Using Relays for Engineering Students
kannan348865
 
Electrical and Electronics Engineering
Electrical and Electronics EngineeringElectrical and Electronics Engineering
Electrical and Electronics Engineering
Ekeeda
 
CURRENT TRANSFORMER.pptx
CURRENT TRANSFORMER.pptxCURRENT TRANSFORMER.pptx
CURRENT TRANSFORMER.pptx
ManishPandya29
 
Power Electronics 2 mark Questions
Power Electronics 2 mark Questions Power Electronics 2 mark Questions
Power Electronics 2 mark Questions
BALACHANDRAN D
 
Chapter 3 (2).ppt
Chapter 3 (2).pptChapter 3 (2).ppt
Chapter 3 (2).ppt
JeelBhanderi4
 
Devices part 1
Devices part 1Devices part 1
Devices part 1
Taimur Ijaz
 

Similar to ECNG 6503 # 3 (20)

ECNG 3015 - Overcurrent Protection
ECNG 3015 - Overcurrent ProtectionECNG 3015 - Overcurrent Protection
ECNG 3015 - Overcurrent Protection
 
substation protection basics.ppt
substation protection basics.pptsubstation protection basics.ppt
substation protection basics.ppt
 
ECNG 6503 #2
ECNG 6503  #2ECNG 6503  #2
ECNG 6503 #2
 
Presentation_ON-CHIP CURRENT SENSING TECHNIQUE FOR CMOS MONOLITHIC SWITCH-MOD...
Presentation_ON-CHIP CURRENT SENSING TECHNIQUE FOR CMOS MONOLITHIC SWITCH-MOD...Presentation_ON-CHIP CURRENT SENSING TECHNIQUE FOR CMOS MONOLITHIC SWITCH-MOD...
Presentation_ON-CHIP CURRENT SENSING TECHNIQUE FOR CMOS MONOLITHIC SWITCH-MOD...
 
Electronics and Communication Engineering
Electronics and Communication EngineeringElectronics and Communication Engineering
Electronics and Communication Engineering
 
K046016266
K046016266K046016266
K046016266
 
Simple 100 w inverter circuit
Simple 100 w inverter circuitSimple 100 w inverter circuit
Simple 100 w inverter circuit
 
CT design aspects - Nageswar-6
CT design aspects - Nageswar-6CT design aspects - Nageswar-6
CT design aspects - Nageswar-6
 
Switched capacitor filter
Switched capacitor filter Switched capacitor filter
Switched capacitor filter
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 
Memristors and their potential applications 2012
Memristors and their potential applications 2012Memristors and their potential applications 2012
Memristors and their potential applications 2012
 
CT and VT.pptx
CT and VT.pptxCT and VT.pptx
CT and VT.pptx
 
Relays and its types - complete guide
Relays and its types - complete guideRelays and its types - complete guide
Relays and its types - complete guide
 
Apparatus Protection Using Relays for Engineering Students
Apparatus Protection Using Relays for Engineering StudentsApparatus Protection Using Relays for Engineering Students
Apparatus Protection Using Relays for Engineering Students
 
Electrical and Electronics Engineering
Electrical and Electronics EngineeringElectrical and Electronics Engineering
Electrical and Electronics Engineering
 
CURRENT TRANSFORMER.pptx
CURRENT TRANSFORMER.pptxCURRENT TRANSFORMER.pptx
CURRENT TRANSFORMER.pptx
 
Power Electronics 2 mark Questions
Power Electronics 2 mark Questions Power Electronics 2 mark Questions
Power Electronics 2 mark Questions
 
Chapter 3 (2).ppt
Chapter 3 (2).pptChapter 3 (2).ppt
Chapter 3 (2).ppt
 
Devices part 1
Devices part 1Devices part 1
Devices part 1
 
Oscillators
OscillatorsOscillators
Oscillators
 

More from Chandrabhan Sharma

ECNG 3015 chapter 6 - switchgear technology
ECNG 3015  chapter 6 - switchgear technologyECNG 3015  chapter 6 - switchgear technology
ECNG 3015 chapter 6 - switchgear technology
Chandrabhan Sharma
 
Ices chapter 8 - illumination engineering
Ices   chapter 8 - illumination engineeringIces   chapter 8 - illumination engineering
Ices chapter 8 - illumination engineering
Chandrabhan Sharma
 
ECNG 3015 chapter 1 - Basics
ECNG 3015  chapter 1 - BasicsECNG 3015  chapter 1 - Basics
ECNG 3015 chapter 1 - Basics
Chandrabhan Sharma
 
ECNH 3015 Examples of PU system
ECNH 3015  Examples of PU systemECNH 3015  Examples of PU system
ECNH 3015 Examples of PU system
Chandrabhan Sharma
 
ECNG 3015 chapter 2 - pu system
ECNG 3015  chapter 2 - pu systemECNG 3015  chapter 2 - pu system
ECNG 3015 chapter 2 - pu system
Chandrabhan Sharma
 
ECNG 3015 Industrial and Commercial Electrical Systems
ECNG 3015   Industrial and Commercial Electrical SystemsECNG 3015   Industrial and Commercial Electrical Systems
ECNG 3015 Industrial and Commercial Electrical Systems
Chandrabhan Sharma
 
ECNG 6509 Transformer Technology
ECNG 6509  Transformer TechnologyECNG 6509  Transformer Technology
ECNG 6509 Transformer TechnologyChandrabhan Sharma
 
ECNG 6509 Switchgear Technology
ECNG 6509    Switchgear TechnologyECNG 6509    Switchgear Technology
ECNG 6509 Switchgear TechnologyChandrabhan Sharma
 
ECNG 3013 A
ECNG 3013 AECNG 3013 A
ECNG 3013 A
Chandrabhan Sharma
 
ECNG 3015- System Earthing
ECNG 3015- System EarthingECNG 3015- System Earthing
ECNG 3015- System Earthing
Chandrabhan Sharma
 
ECNG 3015 Power System Protection
ECNG 3015    Power System ProtectionECNG 3015    Power System Protection
ECNG 3015 Power System Protection
Chandrabhan Sharma
 
ECNG 6503 #4
ECNG 6503 #4ECNG 6503 #4
ECNG 6503 #4
Chandrabhan Sharma
 
ECNG 3015 - PU system and 3Phase Fault calculation
ECNG 3015 - PU system and 3Phase Fault calculation ECNG 3015 - PU system and 3Phase Fault calculation
ECNG 3015 - PU system and 3Phase Fault calculation
Chandrabhan Sharma
 
ECNG 6503 #1
ECNG 6503 #1 ECNG 6503 #1
ECNG 6503 #1
Chandrabhan Sharma
 

More from Chandrabhan Sharma (18)

ECNG 3015 chapter 6 - switchgear technology
ECNG 3015  chapter 6 - switchgear technologyECNG 3015  chapter 6 - switchgear technology
ECNG 3015 chapter 6 - switchgear technology
 
Ices chapter 8 - illumination engineering
Ices   chapter 8 - illumination engineeringIces   chapter 8 - illumination engineering
Ices chapter 8 - illumination engineering
 
ECNG 3015 chapter 1 - Basics
ECNG 3015  chapter 1 - BasicsECNG 3015  chapter 1 - Basics
ECNG 3015 chapter 1 - Basics
 
ECNH 3015 Examples of PU system
ECNH 3015  Examples of PU systemECNH 3015  Examples of PU system
ECNH 3015 Examples of PU system
 
ECNG 3015 chapter 2 - pu system
ECNG 3015  chapter 2 - pu systemECNG 3015  chapter 2 - pu system
ECNG 3015 chapter 2 - pu system
 
ECNG 3015 Industrial and Commercial Electrical Systems
ECNG 3015   Industrial and Commercial Electrical SystemsECNG 3015   Industrial and Commercial Electrical Systems
ECNG 3015 Industrial and Commercial Electrical Systems
 
ECNG 6509 Transformer Technology
ECNG 6509  Transformer TechnologyECNG 6509  Transformer Technology
ECNG 6509 Transformer Technology
 
ECNG 3013 E
ECNG 3013 EECNG 3013 E
ECNG 3013 E
 
ECNG 6509 Switchgear Technology
ECNG 6509    Switchgear TechnologyECNG 6509    Switchgear Technology
ECNG 6509 Switchgear Technology
 
ECNG 3013 D
ECNG 3013 DECNG 3013 D
ECNG 3013 D
 
ECNG 3013 C
ECNG 3013 CECNG 3013 C
ECNG 3013 C
 
ECNG 3013 B
ECNG 3013 BECNG 3013 B
ECNG 3013 B
 
ECNG 3013 A
ECNG 3013 AECNG 3013 A
ECNG 3013 A
 
ECNG 3015- System Earthing
ECNG 3015- System EarthingECNG 3015- System Earthing
ECNG 3015- System Earthing
 
ECNG 3015 Power System Protection
ECNG 3015    Power System ProtectionECNG 3015    Power System Protection
ECNG 3015 Power System Protection
 
ECNG 6503 #4
ECNG 6503 #4ECNG 6503 #4
ECNG 6503 #4
 
ECNG 3015 - PU system and 3Phase Fault calculation
ECNG 3015 - PU system and 3Phase Fault calculation ECNG 3015 - PU system and 3Phase Fault calculation
ECNG 3015 - PU system and 3Phase Fault calculation
 
ECNG 6503 #1
ECNG 6503 #1 ECNG 6503 #1
ECNG 6503 #1
 

Recently uploaded

TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
Jheel Barad
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
PedroFerreira53928
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
rosedainty
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
Fundacja Rozwoju Społeczeństwa Przedsiębiorczego
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
GeoBlogs
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 

Recently uploaded (20)

TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 

ECNG 6503 # 3

  • 1. ECNG 6503 -3 Advanced Power Systems Practice Lecturer Prof Chandrabhan Sharma University of the West Indies Trinidad and Tobago
  • 2. Topics: 1 Differential Protection 2 Busbar Protection 3 Linear Couplers 4 Pilot wire Protection
  • 3. DIFFERENTIAL PROTECTION (Merz-Price Systems) (Unit Protection) 3 Categories of Protection: • Input and Output Terminals are close → transformer • Where ends are Geographically Separate → overhead/underground cables → pilots at supply frequency used • Very long lines P.L.C. → end → end signalling achieved by modulated carrier waveform. Main difference is in way signals derived & transmitted.
  • 4. Why needed?:- Overcomes application difficulties of simple O.C. Relays when applied to complex networks e.g. Co-ordination problems and excessive fault clearance times. Principle:- Measurement of current at each end of feeder and transmission of information between each end of feeder. Protection should operate for fault inside protected Zone only →Stable for others. i.e. Instantaneous Operation Possible!
  • 5. MERZ-PRICE SYSTEM Circulating Current Mode - Current confined to series path. No currents in relay - Both breakers tripped..
  • 6. BALANCED VOLTAGE SCHEME When C.T. secondaries are short, can be applied to transformer, busbars, machines etc. Where boundaries are at distance, communication channel required.
  • 8. UNIT PROTECTION INVOLVING DISTANCE BETWEEN CIRCUIT BREAKERS
  • 9. EARLY MERZ-PRICE BALANCED VOLTAGE SYSTEMS FOR FEEDERS Two Problems: 1. Maloperation due to unequal open circuit secondary voltages of the two transformers for thru fault currents. 2. High Output voltages of CT’s cause capacitance currents to flow through relay since capacitive currents are proportional to pilot length, relay insensitive for all but very short lines.
  • 10. ACCURACY OF C.T.s - Accuracy of relaying signals (balanced) for faults external to protected zone. - Depends on characteristics of C.T. and burdens - Unequal magnetic saturation in 2 C.T.s due to unequal lead burdens - Need to define range of unbalance conditions for which protection is stable and inoperative - Use of complex ratio of IA/N and IB/N
  • 11. Ideally, under conditions of exact balance, the point (1.0 +j 0.0) would be the conditions for through faults in relay signal ratio plane NOTE: All unbalance defined w.r.t. (1.0 +j 0.0) Zone of uncertainty is area enclosed by circle.
  • 12. STABILITY MARGINS Relay Setting corresponds to minimum value of current for which relay operates. OR Related to maximum out-of-balance current for which the protection (relay) is required to remain stable. There are two methods to achieve stability margins: 1. Low-impedance relay and a current setting that would give the required thru-fault stability 2. High-impedance relay having an inherent low current setting.
  • 13. By insertion of stabilising resistor (Rs) the stability margin may be obtained.
  • 14. SATURATION OF ONE C.T. (Equivalent cct)
  • 15. Where: R1, R2 → lead resistances RCA, RCB → core less For Transformer B saturated than: Tx. B does not contribute to relay current If RS ›› R2 + RB Neglecting leakage reactance XB, then ∴RS is chosen s.t. the largest value of IA will not cause relay operation.
  • 16. For Faults within Zone: Let IR0 be the relay minimum current ImA, ImB is magnetising current of transformer A and B ∵ Minimum fault current referred to primary is Ifs = N(IRO + IMA + IMB) i.e. for IRO = 0.8 A ImA = ImB = 0.1 A N = 500:1 ∵ Ifs = 500(0.8 + 0.1 + 0.1) = 500 A (min. fault current at which protection operates)
  • 17. Also: if protection stable under thru fault condition. ∵ for fault if 16kA, with one transformer saturated → RB=0.3 Ω; R1= R2=2.2 Ω
  • 18. THROUGH FAULT FIG 6. SINGLE-PHASE DIFFERENTIAL LOOP
  • 19. FIG 7. BIASED DIFFERENTIAL RELAY
  • 20. BIASED DIFFERENTIAL RELAY CT2 provides phasor addition of currents circulating Let SO= differential current required to operate relay and SB = bias then % bias = B % = SO/SB x 100
  • 21. WITH TRANSFORMER B SATURATED FIG 8(a) EQUIVALENT CIRCUIT OF BIASED DIFFERENTIAL RELAY (Transformer B saturated)
  • 22. Neglecting impedance of biased cct and leakage reactance of saturated transformer.
  • 23. N.B. A specified value of fractional (%) bias is set by obtaining/ proportioning the number of turns on the operate and bias windings.
  • 25. CIRCULATING CURRENT PROTECTION For generated voltage V ∴ x = 1- Is/(V/R) and for a fault position x Let setting current of relay be Is ∴ x = 1 - Is/IR Where x = % winding protected and (1-x) = % winding not protected
  • 26. SPECIAL CONSIDERATIONS • Phase Shift between primary and secondary • Winding turn ratios and effect of tap changers • Different Zero – Phase – Sequence circuits depending on connection • Magnetising Inrush Derived signals must take these three concerns into account when Differential Relays are applied.
  • 27. ANALYSIS OF THE MERZ-PRICE UNIT PROTECTION Relay operates when IA≠ IB but IC = IA- IB ……… (1) ∴ Relay operates when Let Nr = kNo where o<k<1 ………. (3) Sub into (2) equations (1) and (3) ∴ From which for threshold we have:
  • 28. Question: A 1 100kVA 2400/240V transformer is to be differentially protected. Choose the C.T. ratios. Determine the ratio Nr/No if the relay is to tolerate a mismatch in current of up to 20% of primary current (bias).
  • 29. Solution: Rated Primary Current of T/F : = 100/2.4 = 41.7 A ∴ Rated secondary = 41.7 x 10 = 417 A For C.T. Secondary = 1A Primary C.T. ratio = 500:5 Secondary C.T. ratio = 5000:5 For 20% mismatch (bias) → Reduction in Sensitivity → IA = 0.8 IB (At threshold) or 2 - k = 1.6 + 0.8k k = 0.222
  • 30. OVERALL DIFFERENTIAL PROTECTION OF STAR/DELTA POWER TRANSFORMER
  • 31. Must Consider: * Magnetising inrush • Phase shift between primary and secondary • Turns ratio • Zero sequence cct. These can be compensated for by C.T. Connection For the above:
  • 33. This can be represented by Figure (b) Given a transformer with max. off-nominal position 20% And fault current = 10 (rated) Iob = 2.5 (Rating) = normal
  • 34.
  • 35. MAGNETISING INRUSH • Harmonic Restraint → 2nd Harmonic to restraint winding • Application of time delay (usually 0.2s) • Desensitizing relay • Mismatch of C.T.’s
  • 37. Busbar Protection • Purely Earth Fault System. • Simply a measurement of fault current flowing from switchgear to earth. • No other earth connection should be present. • Switchgear must be isolated as a whole i.e. standing on concrete (grout).
  • 38. • Resistance earth, connection of frame is as shown •Ƶ electrode < 1Ω ; Ƶframe ≃ 10Ω I1 ≃ 10% [I1+ I2] = 0.1 IF ∴ Setting is about ≃ Is=30% IF(normally) • Foundations bolts should not touch steel reinforcement • Grouting gives adequate insulation
  • 39. BUSBAR DIFFERENTIAL SCHEME 3 • Two current balance loops. • Plus check loop → safeguard against incorrect tripping due to faults in differential system. • Provides for both phase and earth faults.
  • 40. Summation Schemes By using different C.T. ratios, can differentiate between faults. Phase and earth fault circulating current scheme using single element relay and current transformers with different ratios in each phase
  • 41. LINEAR COUPLERS - (L.C.) - Use of magnetic C.T. lead to errors in reproduction when fault at/near saturation - D.C. saturation even greater problem Solution: - Linear Couplers (no iron core) - Multi-restraint, variable percentage differential relay - High impedance, voltage operated differential relay with series resonant cct. To limit sensitivity to dc.
  • 42. L.C. DIFFERENTIAL SYSTEM Of the 3 systems used (before) L.C. are: - Fastest (operation) - Easiest to apply, set and maintain. - L.C. are air core reactors wound on non- magnetic toroidal cores For L.C. Esec = M Ipri (volts) Where Esec – induced secondary voltage M - mutual reactance of L.C. Ipri - primary current in cct. ** Since L.C. has negligible response to DC, only s.s. conditions need be considered.
  • 44. ∴ From the cct. given before Where: IR = current in L.C. secondary and relay Esec = voltage induced L.C. secondary and relay Ipri = primary current in each cct. M = mutual reactance ƵC = self-impedance of L.C. secondary ƵR = relay impedance N.B. For max. energy transfer, relay tap ≃ total self-impedance of all LC’s in cct.
  • 45. Question: A section of a 230kV bus has 6 circuits (i.e. 3 Tx lines, 2 T/Fs to the 115 kV system and 1 bus tie). The max. external fault is 23,800 A r.m.s and the min. internal fault is 1800 A r.m.s. Six linear couplers are to be used in a differential system to protect the bus. The recommended application range between max. external fault and min. internal fault is 25:1. The mutual reactance of each linear coupler is 0.005Ω. Determine the setting of the relay given its recommended range is 15 mA ∼ 28 mA. The impedances of each linear coupler cct are: Transformer #1 = (9.8 + j10.75) Ω Transformer #2 = (3.9 + j6.6) Ω Line A = (4.3 + j7.2) Ω ; Line B = (4.3 + j7.5) Ω Line C = (3.0 + j3.6) Ω ; bus tie = (10.7+ j12.7) Ω
  • 46.
  • 47. PERFORMANCE OF PILOT WIRE PROTECTION SCHEMES As any Differential Scheme, pilot wire may employ either of the following principles:- (a) Balanced Voltage (b) Circulating Current (a) Balanced Voltage (longitudinal differential protection) A Voltage Driven Scheme
  • 48. Also Vs= Vin ; Is = Iin + I1 = Yc Vin + Iin
  • 49. Similarly for Vo = VR, Io = IR + I2 = (Yc VR+ IR) Sub (1) & (3) into (2)
  • 50. (b) Circulating Current (transverse differential protection) (Current Driven Scheme) Note the interchange of the op. and res. windings. Applications:- (i) Parallel lines (ii)Split winding generators i.e. areas where current usually equal.
  • 51. BALANCED-VOLTAGE PILOT WIRE PROTECTION (FEEDER) The operating and restraint ccts. take the form of an amplitude comparator. For operation: Effective operating Ampere turns > Effective Restraint Ampere turns For threshold conditions (Receiving End) k1IR > k2VR Yr where Yr = admittance of restraint cct. (neglecting impedance of operating cct.)
  • 52. Assuming Linearity of current/voltage relationship IR VR ∴ IR =VRYPR Where YPR = admittance presented by pilot cct to the receiving end relay ∴ k1 VRYPR > k2VRYr or YPR > k Yr for k = k2/ k1 i.e. Operating and restraint ccts for a 2-input comparator for which tripping occurs when the admittance of the pilot cct. exceeds k times the admittance of the restraint cct.
  • 53. Criterion for threshold: The centre of the stability circle should be the point 1 0 on the Vs/VR plane. In practical pilots, transference of the admittance characteristic to the IA/IB plane necessitates compensation to present zero admittance for Vs/VR= 1 0
  • 54. PRACTICAL PILOT WIRE SCHEMES Comp - Compensation cct. Yc - admittance of compensation cct. Ideally the cct is tuned so that the overall compensated pilot cct. (Yp+c) presents zero admittance to the relay for condition Vs/VR=1 0.
  • 55. EVALUATION OF REQUIRED COMPENSATION(Yc) - Assume a symmetrical pilot with network parameters A,B,C and D - Let A’, B’, C’ and D’ be the parameters for the compensated network - Neglect impedance of series op. cct and given that Yc is admittance of compensating network at either end. where A’ = A + BYc ; B’ = B C’ = AYc + C + Yc(BYc +D) ; D’ = BYc+D
  • 56.
  • 57.
  • 59. Assuming a symmetrical pilot, the sending end characteristics can be found from inversion of the receiving end.
  • 60. CIRCULATING CURRENT FEEDER PROTECTION SYSTEM Dual of Balanced-voltage scheme Note : ** Ƶc is in series with pilot instead of shunt Yc ** Neglecting impedance of restraint circuit, the threshold condition is found by equating the operating and restraint quantities, i.e. I1 > I2
  • 61. CIRCULATING CURRENT FEEDER PROTECTION SYSTEM
  • 62. BRIDGE – Type Comparator Relay (circulating current)
  • 63. General Locus of the fault Performance of the Differential Protection Systems Where k1’ , k2’ , k3’ and k4’ may be expressed in terms of distribution factors C1 and C0 for +ve and zero phase sequence, the ratio zero to +ve phase sequence impedance and the constants M, N, P of the summation device.
  • 64. Determination of k1’ , k2’ , k3’ and k4’ for a S-L-G fault
  • 65. Assumptions: 1. X/R ratio = constant 2. Complete transposition of line 3. Shunt capacitance neglected 4. Ƶ1 = Ƶ2 If Ƶ1 = Ƶ2 C1 = C2 IA0 = (1 - C0)(IA1 - IB1) IB0 = - C0 (IA1 - IB1) where Cn = distribution factor IA2 = (1 - C1)(IA1 - IB1) = Impedance ratio IB2 = - C1 (IA1 - IB1)
  • 66. Where k1 = M(1 - C0) + N + P (1 - C1) k2 = - [M(1 - C0) + P (1 - C1)] k3 = - [MC0 + PC1] k4 = MC0 + N + PC1 Substitute into equation : IA1/ IB1 in terms of (EA / EB) We can simplify the network as :
  • 67. From analysis of the preceding network EA1 = IA1C1Ƶ1 + (IA1 - IB1) C02Ƶ1 And EA1 - EB1 = IA1C1Ƶ1 + IB1(1 - C1)Ƶ1 From which we obtain : Recall that EA1 = (EA/ 3) i.e. pre-fault line voltage
  • 68. N.B. If resistance was not zero but = Rf then IA/ IB1 IN TERMS OF (EA / EB) Substitute equation(2) into (1) yields
  • 69. Where The poles of the set of orthogonal circles being (k1’ / k3’ ) and (k2’ / k4’ ) and all circles will pass through there poles. Further Reading Jones, D and Rushton J : “Generalized locus charts for the evaluation of differential feeder protection performance” Institute of Electrical Engineers 113 pp 1194 (1966) GO TO EXAMPLE 7.2 pg. 259 of “Unit Protection” handout and EXAMPLE 7.3 pg. 265 as well as EXAMPLE 7.4 pg. 273