SlideShare a Scribd company logo
Sana’a university
Faculty of engineering
Electrical department
POWER department
Substation





Introduction
Application of auto-reclosing
Auto-reclosing on HV distribution networks
Factors influencing HV auto-reclose
schemes
 Auto-reclosing on EHV transmission lines
 High speed auto-reclosing on EHV systems
14.6
INTRODUCTION
Faults on overhead lines
fall into one of three :
a. transient
b. semi-permanent
c. permanent
80-90% of faults on any overhead line
network are transient in nature.
The remaining 10%-20% of faults
are either semi-permanent or permanent.
Operation OF AUTO-RECLOSING
The most important parameters of an auto-reclose
scheme are:
1. dead time
2. reclaim time
3. single or multi-shot
These parameters are influenced by:
a. type of protection
b. type of switchgear
c. possible stability problems
d. effects on the various types of consumer loads
Dead Time
Several factors affect the selection of system as
follows:
a. system stability and synchronism
b. type of load
c. CB characteristics
d. fault path de-ionisation time
e. protection reset time
.
Circuit breaker characteristics
The time delays imposed by the circuit breaker during
a tripping and reclosing operationespecially when
assessing the possibilityof applying high speed
auto-reclosing.
a. mechanism resetting tim:
time of the order of 0.2s must be allowed for the tripfree mechanism to reset before applying a closing
impulse.
b. closing time:
This is the time interval between the energisation of
closing mechanism and the making of the contacts.
Owing to the time constant of the closing
mechanism may take 0.3s to close.
De-Ionisation of Fault Arc
It is important to know 
the time that must be
allowed for complete
de-ionisation of the
arc, to prevent the arc
restriking when the
voltage is re-applied
. 
HIGH-SPEED AUTO-RECLOSING ON LINES

The first requirement for the application of highspeed auto-reclosing is knowledge of the system
disturbance time that can be tolerated without
loss of system stability. This will normally require
transient stability studies to be conducted for a
defined set of power system configurations and
fault conditions. With knowledge of protection
and circuit breaker operating characteristics and
fault arc de-ionisation times,
For the sketch above
this illustrates for a typical three-zone
distance scheme covering two transmission
lines. For this reason, a fault occurring in
an end zone would protection at one end
of the feeder. However, the CB at be cleared
instantaneously, by the the other end
opens in 0.3-0.4 seconds (Zone 2 time).
High-speed autoreclosing
Number of Shots
There are no definite defining the number of
shots for any particular auto-reclose
application, number of factors must be taken into
rules for
but a factors must be taken into account
accoun
.

account.
Scheme Operation
The sequence of operations of a delayed autoreclose scheme can be best understood by
reference to Figure

More Related Content

What's hot

Protective relay
Protective relay Protective relay
Protective relay
Uday Wankar
 
Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)
Rohini Haridas
 
distance relay
distance relaydistance relay
distance relay
SURAJ PRASAD
 
Protection of alternator
Protection of alternatorProtection of alternator
Protection of alternator
Biswajit Pratihari
 
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
Muhd Hafizi Idris
 
Types of relay
Types of relayTypes of relay
Types of relay
Abdur rehman
 
Power transformer protection
Power transformer protectionPower transformer protection
Power transformer protection
michaeljmack
 
Selection Of Circuit Breaker
Selection Of Circuit BreakerSelection Of Circuit Breaker
Selection Of Circuit Breaker
Raviraj solanki
 
Fundamentals of Microprocessor Based Relays
Fundamentals of Microprocessor Based RelaysFundamentals of Microprocessor Based Relays
Fundamentals of Microprocessor Based Relays
michaeljmack
 
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
jbpatel7290
 
Er rahul sharma feeder protection
Er rahul sharma feeder protectionEr rahul sharma feeder protection
Er rahul sharma feeder protection
Rahul Ruddra
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
vishalgohel12195
 
protection of transmission lines[distance relay protection scheme]
protection of transmission lines[distance relay protection scheme]protection of transmission lines[distance relay protection scheme]
protection of transmission lines[distance relay protection scheme]
moiz89
 
Over current Relays
Over current RelaysOver current Relays
Over current Relays
ASWANTH6270
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis ppt
karikalan123
 
Fault analysis
Fault analysisFault analysis
Fault analysis
Revathi Subramaniam
 
ETAP - Short circuit ansi standard
ETAP - Short circuit ansi standardETAP - Short circuit ansi standard
ETAP - Short circuit ansi standard
Himmelstern
 
Unit 05 Protection of feeders and bus-bars
Unit  05 Protection of feeders and bus-bars Unit  05 Protection of feeders and bus-bars
Unit 05 Protection of feeders and bus-bars
PremanandDesai
 
Faults in Power System
Faults in Power SystemFaults in Power System
Faults in Power System
Avijit Adhikary
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakers
Kabilesh K
 

What's hot (20)

Protective relay
Protective relay Protective relay
Protective relay
 
Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)
 
distance relay
distance relaydistance relay
distance relay
 
Protection of alternator
Protection of alternatorProtection of alternator
Protection of alternator
 
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
3. INTRODUCTION TO PROTECTIVE RELAYING.pptx
 
Types of relay
Types of relayTypes of relay
Types of relay
 
Power transformer protection
Power transformer protectionPower transformer protection
Power transformer protection
 
Selection Of Circuit Breaker
Selection Of Circuit BreakerSelection Of Circuit Breaker
Selection Of Circuit Breaker
 
Fundamentals of Microprocessor Based Relays
Fundamentals of Microprocessor Based RelaysFundamentals of Microprocessor Based Relays
Fundamentals of Microprocessor Based Relays
 
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
 
Er rahul sharma feeder protection
Er rahul sharma feeder protectionEr rahul sharma feeder protection
Er rahul sharma feeder protection
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
 
protection of transmission lines[distance relay protection scheme]
protection of transmission lines[distance relay protection scheme]protection of transmission lines[distance relay protection scheme]
protection of transmission lines[distance relay protection scheme]
 
Over current Relays
Over current RelaysOver current Relays
Over current Relays
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis ppt
 
Fault analysis
Fault analysisFault analysis
Fault analysis
 
ETAP - Short circuit ansi standard
ETAP - Short circuit ansi standardETAP - Short circuit ansi standard
ETAP - Short circuit ansi standard
 
Unit 05 Protection of feeders and bus-bars
Unit  05 Protection of feeders and bus-bars Unit  05 Protection of feeders and bus-bars
Unit 05 Protection of feeders and bus-bars
 
Faults in Power System
Faults in Power SystemFaults in Power System
Faults in Power System
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakers
 

Viewers also liked

Auto Reclose Testing
Auto Reclose TestingAuto Reclose Testing
Auto Reclose Testing
riam
 
Autoreclose
AutorecloseAutoreclose
Autoreclose
prateek435
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
moiz89
 
Relay and switchgear protection
Relay and switchgear protectionRelay and switchgear protection
Relay and switchgear protection
Binit Das
 
protection and relay scheme
protection and relay schemeprotection and relay scheme
protection and relay scheme
infosaneeshss
 
Distance Relay:->Mho relay
Distance Relay:->Mho relayDistance Relay:->Mho relay
Distance Relay:->Mho relay
mohan_K_M
 
Relay coordination
Relay coordinationRelay coordination
Relay coordination
D Målîk
 
Relay
RelayRelay
Protective Device Coordination
Protective Device CoordinationProtective Device Coordination
Protective Device Coordination
joeengi
 
Safe Operation and Maintenance of Circuit Breakers and Switchgear
Safe Operation and Maintenance of Circuit Breakers and SwitchgearSafe Operation and Maintenance of Circuit Breakers and Switchgear
Safe Operation and Maintenance of Circuit Breakers and Switchgear
Living Online
 
Relays
RelaysRelays
Relays
Ameen San
 
05 ptcc automation overview
05 ptcc automation overview05 ptcc automation overview
05 ptcc automation overview
duytn1
 
PPT ON 400KV GSS HEERAPURA JAIPUR
PPT ON 400KV GSS HEERAPURA JAIPUR PPT ON 400KV GSS HEERAPURA JAIPUR
PPT ON 400KV GSS HEERAPURA JAIPUR
Amit kumar
 
Power-Grid Switchgears Pvt. Ltd., Ahmedabad, Solid Core DO Fuse
Power-Grid Switchgears Pvt. Ltd., Ahmedabad, Solid Core DO FusePower-Grid Switchgears Pvt. Ltd., Ahmedabad, Solid Core DO Fuse
Power-Grid Switchgears Pvt. Ltd., Ahmedabad, Solid Core DO Fuse
IndiaMART InterMESH Limited
 
Protection primer
Protection primerProtection primer
Protection primer
rajivkumarsrivastav
 
Recent AFIS Training on English Language
Recent AFIS Training on English LanguageRecent AFIS Training on English Language
Recent AFIS Training on English Language
Esther Nwogwugwu
 
Technical presentation on protection distance protection
Technical presentation on protection  distance protectionTechnical presentation on protection  distance protection
Technical presentation on protection distance protection
Sujith Mohandas
 
ECNG 6503 # 3
ECNG 6503 # 3ECNG 6503 # 3
ECNG 6503 # 3
Chandrabhan Sharma
 
Technical presentation on protection distance protection
Technical presentation on protection  distance protectionTechnical presentation on protection  distance protection
Technical presentation on protection distance protection
Sujith Mohandas
 
Application Considerations for Power System Grounding
Application Considerations for Power System GroundingApplication Considerations for Power System Grounding
Application Considerations for Power System Grounding
michaeljmack
 

Viewers also liked (20)

Auto Reclose Testing
Auto Reclose TestingAuto Reclose Testing
Auto Reclose Testing
 
Autoreclose
AutorecloseAutoreclose
Autoreclose
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
 
Relay and switchgear protection
Relay and switchgear protectionRelay and switchgear protection
Relay and switchgear protection
 
protection and relay scheme
protection and relay schemeprotection and relay scheme
protection and relay scheme
 
Distance Relay:->Mho relay
Distance Relay:->Mho relayDistance Relay:->Mho relay
Distance Relay:->Mho relay
 
Relay coordination
Relay coordinationRelay coordination
Relay coordination
 
Relay
RelayRelay
Relay
 
Protective Device Coordination
Protective Device CoordinationProtective Device Coordination
Protective Device Coordination
 
Safe Operation and Maintenance of Circuit Breakers and Switchgear
Safe Operation and Maintenance of Circuit Breakers and SwitchgearSafe Operation and Maintenance of Circuit Breakers and Switchgear
Safe Operation and Maintenance of Circuit Breakers and Switchgear
 
Relays
RelaysRelays
Relays
 
05 ptcc automation overview
05 ptcc automation overview05 ptcc automation overview
05 ptcc automation overview
 
PPT ON 400KV GSS HEERAPURA JAIPUR
PPT ON 400KV GSS HEERAPURA JAIPUR PPT ON 400KV GSS HEERAPURA JAIPUR
PPT ON 400KV GSS HEERAPURA JAIPUR
 
Power-Grid Switchgears Pvt. Ltd., Ahmedabad, Solid Core DO Fuse
Power-Grid Switchgears Pvt. Ltd., Ahmedabad, Solid Core DO FusePower-Grid Switchgears Pvt. Ltd., Ahmedabad, Solid Core DO Fuse
Power-Grid Switchgears Pvt. Ltd., Ahmedabad, Solid Core DO Fuse
 
Protection primer
Protection primerProtection primer
Protection primer
 
Recent AFIS Training on English Language
Recent AFIS Training on English LanguageRecent AFIS Training on English Language
Recent AFIS Training on English Language
 
Technical presentation on protection distance protection
Technical presentation on protection  distance protectionTechnical presentation on protection  distance protection
Technical presentation on protection distance protection
 
ECNG 6503 # 3
ECNG 6503 # 3ECNG 6503 # 3
ECNG 6503 # 3
 
Technical presentation on protection distance protection
Technical presentation on protection  distance protectionTechnical presentation on protection  distance protection
Technical presentation on protection distance protection
 
Application Considerations for Power System Grounding
Application Considerations for Power System GroundingApplication Considerations for Power System Grounding
Application Considerations for Power System Grounding
 

Similar to Auto recloser

A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...
A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...
A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...
paperpublications3
 
Auto reclosers
Auto reclosersAuto reclosers
Auto reclosers
Debojyoti Mukherjee
 
Electrical Protection Schemes in detail
Electrical Protection Schemes in detailElectrical Protection Schemes in detail
Electrical Protection Schemes in detail
Slides Hub
 
Pq unit ii
Pq unit iiPq unit ii
Pq unit ii
venki249
 
Power System Protection course - Part I
Power System Protection course - Part IPower System Protection course - Part I
Power System Protection course - Part I
Slides Hub
 
IRJET- Study Over Current Relay (MCGG53) Response using Matlab Model
IRJET- Study Over Current Relay (MCGG53) Response using Matlab ModelIRJET- Study Over Current Relay (MCGG53) Response using Matlab Model
IRJET- Study Over Current Relay (MCGG53) Response using Matlab Model
IRJET Journal
 
Generator protection LEC 2
Generator protection  LEC 2Generator protection  LEC 2
Generator protection LEC 2
Rahaf Waheep
 
Switch gear and protection
Switch gear and protectionSwitch gear and protection
Switch gear and protection
Dinesh Sharma
 
Busbar protection LEC 2.pptx
Busbar protection LEC 2.pptxBusbar protection LEC 2.pptx
Busbar protection LEC 2.pptx
Rahaf Waheep
 
Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)
ingcortez
 
lecture1423723756.pdf
lecture1423723756.pdflecture1423723756.pdf
lecture1423723756.pdf
ssuser564db8
 
Short circuit current calculations
Short circuit current calculationsShort circuit current calculations
Short circuit current calculations
Ronald Santos
 
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
IRJET Journal
 
Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"
michaeljmack
 
EDS Unit 4 (Protection and Coordination).pptx
EDS Unit 4 (Protection and Coordination).pptxEDS Unit 4 (Protection and Coordination).pptx
EDS Unit 4 (Protection and Coordination).pptx
Dr. Rohit Babu
 
Chapter 3 electrical-protection_system (hat, trafo, generatör, bara koruma)
Chapter 3 electrical-protection_system (hat, trafo, generatör, bara koruma)Chapter 3 electrical-protection_system (hat, trafo, generatör, bara koruma)
Chapter 3 electrical-protection_system (hat, trafo, generatör, bara koruma)
Oktay Yaman
 
os-exe3-23-may2011-sr-i-776s21tr-lineprotection-120425095503-phpapp02 (2).ppt
os-exe3-23-may2011-sr-i-776s21tr-lineprotection-120425095503-phpapp02 (2).pptos-exe3-23-may2011-sr-i-776s21tr-lineprotection-120425095503-phpapp02 (2).ppt
os-exe3-23-may2011-sr-i-776s21tr-lineprotection-120425095503-phpapp02 (2).ppt
Thien Phan Bản
 
DigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theoryDigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theory
Himmelstern
 
DigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theoryDigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theory
Himmelstern
 
Switchgear and protection 3
Switchgear and protection 3Switchgear and protection 3
Switchgear and protection 3
Md Irshad Ahmad
 

Similar to Auto recloser (20)

A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...
A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...
A Review on Suppression of Secondary Arc Current Trough Single-Phase Auto-Rec...
 
Auto reclosers
Auto reclosersAuto reclosers
Auto reclosers
 
Electrical Protection Schemes in detail
Electrical Protection Schemes in detailElectrical Protection Schemes in detail
Electrical Protection Schemes in detail
 
Pq unit ii
Pq unit iiPq unit ii
Pq unit ii
 
Power System Protection course - Part I
Power System Protection course - Part IPower System Protection course - Part I
Power System Protection course - Part I
 
IRJET- Study Over Current Relay (MCGG53) Response using Matlab Model
IRJET- Study Over Current Relay (MCGG53) Response using Matlab ModelIRJET- Study Over Current Relay (MCGG53) Response using Matlab Model
IRJET- Study Over Current Relay (MCGG53) Response using Matlab Model
 
Generator protection LEC 2
Generator protection  LEC 2Generator protection  LEC 2
Generator protection LEC 2
 
Switch gear and protection
Switch gear and protectionSwitch gear and protection
Switch gear and protection
 
Busbar protection LEC 2.pptx
Busbar protection LEC 2.pptxBusbar protection LEC 2.pptx
Busbar protection LEC 2.pptx
 
Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)
 
lecture1423723756.pdf
lecture1423723756.pdflecture1423723756.pdf
lecture1423723756.pdf
 
Short circuit current calculations
Short circuit current calculationsShort circuit current calculations
Short circuit current calculations
 
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
 
Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"
 
EDS Unit 4 (Protection and Coordination).pptx
EDS Unit 4 (Protection and Coordination).pptxEDS Unit 4 (Protection and Coordination).pptx
EDS Unit 4 (Protection and Coordination).pptx
 
Chapter 3 electrical-protection_system (hat, trafo, generatör, bara koruma)
Chapter 3 electrical-protection_system (hat, trafo, generatör, bara koruma)Chapter 3 electrical-protection_system (hat, trafo, generatör, bara koruma)
Chapter 3 electrical-protection_system (hat, trafo, generatör, bara koruma)
 
os-exe3-23-may2011-sr-i-776s21tr-lineprotection-120425095503-phpapp02 (2).ppt
os-exe3-23-may2011-sr-i-776s21tr-lineprotection-120425095503-phpapp02 (2).pptos-exe3-23-may2011-sr-i-776s21tr-lineprotection-120425095503-phpapp02 (2).ppt
os-exe3-23-may2011-sr-i-776s21tr-lineprotection-120425095503-phpapp02 (2).ppt
 
DigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theoryDigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theory
 
DigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theoryDigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theory
 
Switchgear and protection 3
Switchgear and protection 3Switchgear and protection 3
Switchgear and protection 3
 

Recently uploaded

Pushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 daysPushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 days
Adtran
 
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionGenerative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Aggregage
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
Quotidiano Piemontese
 
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
Neo4j
 
PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
ControlCase
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Albert Hoitingh
 
20240609 QFM020 Irresponsible AI Reading List May 2024
20240609 QFM020 Irresponsible AI Reading List May 202420240609 QFM020 Irresponsible AI Reading List May 2024
20240609 QFM020 Irresponsible AI Reading List May 2024
Matthew Sinclair
 
Full-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalizationFull-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalization
Zilliz
 
Uni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdfUni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems S.M.S.A.
 
RESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for studentsRESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for students
KAMESHS29
 
“I’m still / I’m still / Chaining from the Block”
“I’m still / I’m still / Chaining from the Block”“I’m still / I’m still / Chaining from the Block”
“I’m still / I’m still / Chaining from the Block”
Claudio Di Ciccio
 
Mind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AIMind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AI
Kumud Singh
 
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdfUnlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Malak Abu Hammad
 
Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1
DianaGray10
 
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Speck&Tech
 
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AIEnchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Vladimir Iglovikov, Ph.D.
 
20 Comprehensive Checklist of Designing and Developing a Website
20 Comprehensive Checklist of Designing and Developing a Website20 Comprehensive Checklist of Designing and Developing a Website
20 Comprehensive Checklist of Designing and Developing a Website
Pixlogix Infotech
 
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
名前 です男
 
A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
sonjaschweigert1
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
shyamraj55
 

Recently uploaded (20)

Pushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 daysPushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 days
 
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionGenerative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to Production
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
 
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
 
PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
 
20240609 QFM020 Irresponsible AI Reading List May 2024
20240609 QFM020 Irresponsible AI Reading List May 202420240609 QFM020 Irresponsible AI Reading List May 2024
20240609 QFM020 Irresponsible AI Reading List May 2024
 
Full-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalizationFull-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalization
 
Uni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdfUni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdf
 
RESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for studentsRESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for students
 
“I’m still / I’m still / Chaining from the Block”
“I’m still / I’m still / Chaining from the Block”“I’m still / I’m still / Chaining from the Block”
“I’m still / I’m still / Chaining from the Block”
 
Mind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AIMind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AI
 
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdfUnlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
 
Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1
 
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
 
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AIEnchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
 
20 Comprehensive Checklist of Designing and Developing a Website
20 Comprehensive Checklist of Designing and Developing a Website20 Comprehensive Checklist of Designing and Developing a Website
20 Comprehensive Checklist of Designing and Developing a Website
 
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
 
A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
 

Auto recloser

  • 1. Sana’a university Faculty of engineering Electrical department POWER department Substation
  • 2.
  • 3.     Introduction Application of auto-reclosing Auto-reclosing on HV distribution networks Factors influencing HV auto-reclose schemes  Auto-reclosing on EHV transmission lines  High speed auto-reclosing on EHV systems 14.6
  • 4. INTRODUCTION Faults on overhead lines fall into one of three : a. transient b. semi-permanent c. permanent 80-90% of faults on any overhead line network are transient in nature. The remaining 10%-20% of faults are either semi-permanent or permanent.
  • 5. Operation OF AUTO-RECLOSING The most important parameters of an auto-reclose scheme are: 1. dead time 2. reclaim time 3. single or multi-shot These parameters are influenced by: a. type of protection b. type of switchgear c. possible stability problems d. effects on the various types of consumer loads
  • 6.
  • 7.
  • 8. Dead Time Several factors affect the selection of system as follows: a. system stability and synchronism b. type of load c. CB characteristics d. fault path de-ionisation time e. protection reset time .
  • 9. Circuit breaker characteristics The time delays imposed by the circuit breaker during a tripping and reclosing operationespecially when assessing the possibilityof applying high speed auto-reclosing. a. mechanism resetting tim: time of the order of 0.2s must be allowed for the tripfree mechanism to reset before applying a closing impulse. b. closing time: This is the time interval between the energisation of closing mechanism and the making of the contacts. Owing to the time constant of the closing mechanism may take 0.3s to close.
  • 10.
  • 11. De-Ionisation of Fault Arc It is important to know  the time that must be allowed for complete de-ionisation of the arc, to prevent the arc restriking when the voltage is re-applied . 
  • 12. HIGH-SPEED AUTO-RECLOSING ON LINES The first requirement for the application of highspeed auto-reclosing is knowledge of the system disturbance time that can be tolerated without loss of system stability. This will normally require transient stability studies to be conducted for a defined set of power system configurations and fault conditions. With knowledge of protection and circuit breaker operating characteristics and fault arc de-ionisation times,
  • 13.
  • 14. For the sketch above this illustrates for a typical three-zone distance scheme covering two transmission lines. For this reason, a fault occurring in an end zone would protection at one end of the feeder. However, the CB at be cleared instantaneously, by the the other end opens in 0.3-0.4 seconds (Zone 2 time). High-speed autoreclosing
  • 15. Number of Shots There are no definite defining the number of shots for any particular auto-reclose application, number of factors must be taken into rules for but a factors must be taken into account accoun . account.
  • 16. Scheme Operation The sequence of operations of a delayed autoreclose scheme can be best understood by reference to Figure