BOILER FEED
WATER CONTROL
Presented by Cleaver Brooks’ Steve Connor
and Grundfos’ Jim Swetye
TODAY’S AGENDA
• Again address high pressure boilers (FT & IWT) in the 100 – 1200 HP range
• Where the water level is measured in these boilers
• The ways in which the pressure in the boiler and system is controlled
• Maintaining a reliable and safe level of water in the boiler is critical
• Ways in which the boiler water level is controlled
• Matching this control with (4) distinct pumping strategies
• A couple pump selection exercises
• Summary
• Q&A
2
FIRETUBE
Watertube (IWT)
Integral burner
Gun burner
Maximizing Efficiency with Hydronic Boilers
3
BOILER SIZES AND
FEED PUMP SIZES
Boiler HP
Range
Boiler
Pressure
Range
Typical Feed
Pump Type
Typical
Max. Feed
Pump
Flow
Range
Typical
Max. Feed
Pump
Head
Where
Used?
100 to
1200
150 to 500
psi
Vertical
inline
multistage;
regenerative
turbines
10 to 125
gpm
1250 feet
General
industry;
institutional;
universities;
some
commercial
buildings
4
WATERTUBE OR IWT
Maximizing Efficiency with Hydronic Boilers
5
THE WATERTUBE
BOILER
• Opposite of Firetube
• Water in the Tubes
• Natural and Forced Circulation
• Large Furnace
• Upper & Lower Drums or Headers
Upper Steam Drum
Lower Mud Drum
Furnace
Outlet nozzle location
6
STEAM QUALITY
Steam disengaging area
Water level
IWT Upper Steam drum
Steam outlet
7
THE FIRETUBE
BOILER
8
Steam space
Water level
Steam outlet
9
HEATING SURFACE
Safe water level
2000 Deg. F
900 Deg. F
Steam
10
Operating High Limit Modulating
16
TYPICAL
STEAM SYSTEM
T
T
T
T
T
Legend
Steam
Cond
Vapor
HPCondReturn
D A TankD A Tank
Feed PumpBoiler
Strainer
Trap Trap
Trap
TT
TT
DA Tank
TT
TT
TTT
Legend
Trap
HP Steam
PRV
LP Steam
Trap
LP Condensate Return
Motive
Force
Flash
Modulating Control or Transducer
17
18
PLANT MASTER
18
PLC BASED
BOILER CONTROLS
19
LOW WATER CUTOFF
& PUMP CONTROL
20
Bowl
Float
Armature
Switching head
LOW WATER CUTOFF
& PUMP CONTROL
21
Pump switch
LWCO Switch
22
At 0”= 2”
Section I, High pressure boilers
is first visible point in GG = 2”
above tubes…
23
Magnetostrictive Technology
Retrofitable!
24
MAGNETOSTRICTIVE
BOILER LEVEL CONTROL
TECHNOLOGY
Sensing rod
Titanium float
Sensor head
Display box
25
PLC Platform
Modulating feed water valve
Pump
Loop Controller(s)
26
VFD Controller
Magnetostrictive level control
27
THREE ELEMENT
FEED WATER CONTROL
28
29
BOILER FEED PUMP
CONTROL METHODS
1. On/Off control and fixed speed pumps
2. Feed control valve and fixed speed pumps
3. Feed control valve and variable speed pumps
4. Variable speed pumps only (no control valve)
Method# Name
30
Deaerator
Feed pumps Burner Boiler
Control box
METHOD #1 –
On/off control with fixed speed pump
31
Advantages:
• Inexpensive
• Simple to install
• No bypass
• No feed valve
Disadvantages:
• Mechanical stress on the boiler
• Pumps are liable to cavitate at start-up
• Large number of Starts-Stops can
stress pumps
• Variations in steam production
• Boiler water swell and carry-over
METHOD #1 –
On/off control with fixed speed pump
32
Deaerator
Feed pumps Burner
Boiler
Bypass
Feed valve
METHOD #2 –
Feed valve with fixed speed pumps
33
Advantages:
• Minimize risk of boiler water
swell/carry-over
• Feed is adjusted according to
steam consumption
• Steam quality higher due to
more constant water level
Disadvantages:
• Bypass is required
• Feed valves are expensive
• Pressure loss across the feed
valve requires larger sized
pumps
METHOD #2 –
Feed valve with fixed speed pumps
34
Deaerator
Feed pumps
Boiler
Recirculation line
Feed valve
Transducer
METHOD #3 –
Feedvalvewithvariablespeedpumpswithrecirculationline
Level Sensor
35
Advantages:
• Minimize the risk of water
sink & swell/carry-over
• Feed adjusted according to
steam consumption
• Energy savings on pump
operation
• Steam quality higher due to
more constant water level
Disadvantages:
• Bypass is required
• Feed valve is expensive
• Pressure loss across feed valve requires
larger sized pumps
• Stopping pump at closed valve requires
signal from pressure transducer
METHOD #3 –
Feedvalvewithvariablespeedpumpswithrecirculationline
36
RE-CIRCULATION
FLOW WITH AUTO VALVE
Re-circulation
common manifold
Re-circulation lines
Auto Valve in
recirculation line
Service line with
normally closed
shutoff valve
37
Deaerator
Feed pumps
Boiler
Sensor
METHOD #4 –
Variable speed pumps less feed valve
38
Advantages:
• Feed is adjusted according
to steam consumption
• Even steam production
• Faster reaction with
changed speed
• Energy savings on pump
operation
• No bypass line
• No feed valve and
associated pressure loss
• Minimize risk of
swell/carry-over
Disadvantages:
• Requires precise and qualified
start-up
• Non-return valve required
• Minimum frequency must be
defined to ensure pump can
always overcome the pressure in
boiler – pump MUST stop when
steam consumption is zero
METHOD #4 –
Variable speed pumps less feed valve
39
SUMMARY OF
CONTROL METHODS
Method
#
Name
Pump
Speed
Type
Duty
Uses
feed
valve?
Is orifice flow
recirculation by-pass
line required?
1 On/Off control and fixed speed pumps Fixed Intermittent No No
2 Feed control valve and fixed speed pumps Fixed Continuous Yes Yes
3 Feed control valve and variable speed pumps Variable Continuous Yes Yes
4 Variable speed pumps only (no control valve) Variable Continuous No No
40
CHECKLIST –
Boiler feed pump selection process
Step Action
1 Determine control method to be used
2 Calculate BASE flow rate
3 Add for by-pass flow if required
4 Sum of base flow and by-pass flow is the total flow required
5 Calculate BASE pumping head
6 Add for all suction piping head components
7 Add for all discharge piping system head components (including feed valve if required)
8 Sum of all head components = total pumping head
9 Determine deaerator tank water temperature
10 Perform NPSHa calculation
11 Make preliminary pump selection
12 Check NPSHr versus NPSHa
13 Assure material compatibility - chemical and temperature
14 Make final pump selection
41
BOILER FEED PUMPS:
USEFUL FORMULAS
1. Base flow calculation equation
Boiler maximum capacity horsepower X 0.069 X C = Base flow rate
C = 1.50 for On/Off intermittent operation
C = 1.15 for continuous feed operation
2. Determine BASE head for feed pump
Formula based on Safety Valve setting:
Pump head in feet = Maximum pressure X 2.31 X 1.03 ÷ Liquid Specific Gravity
3. Head components on suction side of piping system
Pressure above atmospheric on deaerator converted to feet of head = feet
Elevation difference between minimum deaerator water level and pump inlet = feet
Suction pipe friction loss = feet
Suction fitting friction loss = feet
Suction line valves and strainer friction loss = feet
Total = feet
4. Head components on discharge side of piping system
Friction loss through discharge piping = feet
Friction loss through discharge fittings = feet
Friction loss through feed valve = feet
Elevation of boiler maximum water level above pump = feet
Total = feet
5. NPSHa equation
± Elevation** + Absolute pressure – Vapor Pressure – Suction Line Friction = NPSHa
(Feet) (psi X 2.31 = Feet) (psi X 2.31 = Feet) (Feet) (Feet)
** Elevation of deaerator tank minimum water level above pump’s first impeller
42
SPECIFICATION
FOR EXERCISE
a) Control method is variable speed pump with
bypass recirculation and feed valve
b) Boiler maximum capacity = 250 HP
c) Boiler safety valve setting – 125 psig
d) Pressure safety factor = 3% above boiler’s safety
valve setting
e) Boiler operating pressure – 100 psig
f) Continuous Boiler Blowdown flow - Required
g) Bypass recirculation flow – Required
h) Altitude – Sea level
i) Pressure in deaerator tank above atmospheric
pressure = 5 psi (14.7 + 5 = 19.7 psi absolute)
j) Height of deaerator tank minimum water level
above pump’s first impeller = 10 feet
k) Friction line loss through suction piping = .5 foot
l) Friction loss through suction side fittings = .5 foot
m) Friction loss through suction side valves = None
n) Friction loss through suction side strainer = 1 foot
o) Friction loss through discharge piping = 1 foot
p) Friction loss through discharge side fittings = 1
foot
q) Friction loss through feed valve – 15 psi
r) Elevation of boiler maximum water level above
pump’s discharge port = 5 feet
s) Liquid Specific Gravity = 0.955
t) Temperature of water in deaerator tank = 227
degrees F
u) Vapor pressure in deaerator tank = 19.7 psi
v) Pump materials all 316 stainless steel to resist
treatment chemicals
w) Mechanical seal to be silicon carbide/silicon
carbide/EPDM to withstand liquid temperature
43
FROM PREVIOUS
EXERCISE –
Fixed speed pumps with feed valve and recirculation line
Recirculation line
Feed valve
Boiler
Level Sensor
Feed pumps
Deaerator
44
Deaerator
Boiler
Recirculation
line
Feed valve
Feed pumps
Transducer
Level Sensor
FROM CURRENT
EXERCISE – #2
Feed Valve with Variable Speed Pumps with Recirculation line
45
STEP 13 –
Preliminary pump selection
• Conditions of
Service:
• Flow = 28 gpm
• Head = 272 feet
Does this 11
stage pump
pump meet the
required flow
and head
conditions of
service?
YES
46
SUMMARY OF
PERFORMANCE CHARACTERISTICS
Advantages of control via variable speed pump versus a fixed speed pump
when using a feed valve and recirculation:
• More even steam production
• Faster reaction with changed speed consumption
• Fewer losses by variable level
• Carry over
• Reduced energy consumption and operating costs
However, the variable speed unit will be more expensive in initial purchase cost.
For this reason, you must perform a Life Cycle Cost calculation before making
your final decision on which method to use.
Exercise #
Use Feed
Valve?
Reciculation
Line? Speed Type
Duty Point
GPM Flow
Duty Point Feet
of Head Pump Size
Number of
Stages
Efficiency at
Duty Point
BHP at Duty
Point
1 Yes Yes Fixed 28 272 1.25 x 1.25 11 65% 2.96
2 Yes Yes Variable 28 272 1.25 x 1.25 11 65% 2.96
47
CURVE COMPARISON –
FIXED SPEED VS VARIABLE
SPEED
Duty point
operation at
3550 rpm
48
CURVE COMPARISON –
CONT.
Fixed speed reduced flow Variable speed reduced flow
Full speed
BHP
Reduced speed
BHP
49
Check list for boiler feed pump selection
Step Action
1 Determine control method to be used
2 Calculate BASEflow rate
3 Add for ContinuousBoiler Blowdown flow
4 Add for by-passflow if required
5 Sum of base flow,by-passflow,and Blowdown flow isthe total flow required
6 Calculate BASEpumping head
7 Add for all suction piping head components
8 Add for all discharge piping system head components(including feed valve if required)
9 Sum of all head components= total pumping head
10 Calculate head at boiler safety vavle setting plusthree percent
11 Determine deaerator tank water temperature
12 Perform NPSHa calculation
13 Make preliminary pump selection
14 Assure that shutoff head equalsor exceedsthree percent above safety valve setting
15 Check NPSHr versusNPSHa
16 Assure material compatibility - chemical and temperature
17 Make final pump selection
50
BOILER FEED PUMPS:
USEFUL FORMULAS
1. Base flow calculation equation
Boiler maximum capacity horsepower X 0.069 X C = Base flow rate
C = 1.50 for On/Off intermittent operation
C = 1.15 for continuous feed operation
2. Determine BASE head for feed pump
Formula based on Safety Valve setting:
Pump head in feet = Maximum pressure X 2.31 X 1.03 ÷ Liquid Specific Gravity
3. Head components on suction side of piping system
Pressure above atmospheric on deaerator converted to feet of head = feet
Elevation difference between minimum deaerator water level and pump inlet = feet
Suction pipe friction loss = feet
Suction fitting friction loss = feet
Suction line valves and strainer friction loss = feet
Total = feet
4. Head components on discharge side of piping system
Friction loss through discharge piping = feet
Friction loss through discharge fittings = feet
Friction loss through feed valve = feet
Elevation of boiler maximum water level above pump = feet
Total = feet
5. NPSHa equation
± Elevation** + Absolute pressure – Vapor Pressure – Suction Line Friction = NPSHa
(Feet) (psi X 2.31 = Feet) (psi X 2.31 = Feet) (Feet) (Feet)
** Elevation of deaerator tank minimum water level above pump’s first impeller
51
SPECIFICATION
FOR EXERCISE
a) Control Method: Continuous duty variable speed pump (feed valve and recirculation line are not required)
b) Boiler maximum capacity = 250 HP
c) Boiler safety valve setting = 115 psig
d) Pressure safety factor = 3% above boiler’s safety valve setting
e) Boiler operating pressure = 100 psig
f) Continuous Boiler Blowdown flow - Required
g) Bypass recirculation flow – Not required
h) Altitude – Sea level
i) Pressure in deaerator tank above atmospheric pressure = 5 psi (14.7 + 5 = 19.7 psi absolute)
j) Height of deaerator tank minimum water level above pump’s first impeller = 10 feet
k) Friction line loss through suction piping = .5 foot
l) Friction loss through suction side fittings = .5 foot
m) Friction loss through suction side valves = None
n) Friction loss through suction side strainer = 1 feet
o) Friction loss through discharge piping = 1 foot
p) Friction loss through discharge side fittings = 1 foot
q) Pressure drop across feed valve – None – Feed valve is not required
r) Elevation of boiler maximum water level above pump’s discharge port = 5 feet
s) Liquid Specific Gravity = 0.953
t) Temperature of water in deaerator tank = 227 degrees F
u) Vapor pressure in deaerator tank = 19.7 psi
v) Pump materials all 316 stainless steel to resist treatment chemicals
w) Mechanical seal to be silicon carbide/silicon carbide/EPDM to withstand liquid temperature
52
Deaerator
Feed pumps
Boiler
Sensor
FROM CURRENT
EXERCISE – # 3:
Variable speed pumps (without feed valve
and without recirculation line)
53
STEP 1 –
• Determine control method
• A variable speed pump has been specified. Specification excludes feed
valve and recirculation line
X
Step Action
1 Determine control method to be used
2 Calculate BASEflow rate
3 Add for ContinuousBoiler Blowdown flow
4 Add for by-passflow if required
5 Sum of base flow,by-passflow,and Blowdown flow isthe total flow required
6 Calculate BASEpumping head
7 Add for all suction piping head components
8 Add for all discharge piping system head components(including feed valve if required)
9 Sum of all head components=total pumping head
10 Calculate head at boiler safety vavle setting plusthree percent
11 Determine deaerator tank water temperature
12 Perform NPSHa calculation
13 Make preliminary pump selection
14 Assure that shutoff head equalsor exceedsthree percent above safety valve setting
15 Check NPSHr versusNPSHa
16 Assure material compatibility - chemical and temperature
17 Make final pump selection
54
STEP 2 –
Calculate the BASE feed pump flow rate
The formula for this calculation is:
• Boiler maximum capacity in horsepower X 0.069 X C
• The maximum capacity in boiler horsepower is 250
• The C factor is 1.15 for continuous duty
Therefore:
250 X 0.069 X 1.15 = 20 gpm = BASE flow rate
55
STEP 3 –
Continuous Boiler Blowdown Flow
Determination:
1. The BASE flow rate has been established at 20
gpm
2. We will on next slide need to add for bypass
flow, which can add 10 to 20 percent to the
BASE flow rate
3. Blowdown flow is to be approximately 10 percent
of flow at pump’s Best Efficiency Point
4. So the total boiler blowdown flow required is
approximately 3 gpm
56
STEP 4 –
Recirculation by-pass flow
Not required per the specification
57
STEP 5 –
Calculate total flow required
• BASE flow = 20 gpm
• Blowdown flow = 3 gpm
• Recirculation flow = 0 gpm
• Total flow required= 23 gpm
X
X
X
X
X
Step Action
1 Determinecontrolmethodtobeused
2 CalculateBASEflow rate
3 Addfor ContinuousBoiler Blowdownflow
4 Addfor by-passflow if required
5 Sum of baseflow,by-passflow,andBlowdownflow isthetotalflow required
6 CalculateBASEpumpinghead
7 Addfor allsuctionpipingheadcomponents
8 Addfor alldischargepipingsystem headcomponents(includingfeedvalveif required)
9 Sum of allheadcomponents=totalpumpinghead
10 Calculateheadat boiler safetyvavlesettingplusthreepercent
11 Determinedeaerator tankwater temperature
12 Perform NPSHacalculation
13 Makepreliminarypumpselection
14 Assurethat shutoff headequalsor exceedsthreepercent abovesafetyvalvesetting
15 CheckNPSHr versusNPSHa
16 Assurematerialcompatibility- chemicalandtemperature
17 Makefinalpumpselection
58
STEP 6 –
Calculate BASE pumping head
• Boiler operating pressure setting + 3%
Formula: BASE head in feet = Boiler operating pressure X 2.31 X 1.03 ÷ Specific Gravity
BASE head = 100 psi X 2.31 X 1.03 ÷ 0.953 = 250 feet
59
STEP 7 –
Add for suction piping system head components
From specification:
Gauge pressure on deaerator tank = 5 psi X 2.31 = - 12 feet
Water elevation above first impeller = - 10 feet
Friction loss through suction piping = + .5 feet
Friction loss through suction fittings = + .5 feet
Friction loss through suction side valves and strainer = + 1 feet
Total = - 20 feet
60
STEP 8 –
Add for discharge piping system head components
From specification:
Friction loss through discharge piping = + 1 foot
Friction loss through discharge fittings = + 1 foot
Friction loss through feed valve = + 0 feet
Elevation of boiler maximum water level above pump = + 5 feet
Total = + 7 feet
61
STEP 9 –
Sum of all head components
BASE head with safety factor = + 250 feet
Suction side piping system head = - 20 feet
Discharge side piping system head = + 7 feet
Total = + 237 feet
62
STEP 10 –
Pressure safety valve considerations
At shutoff head (dead head):
Head in feet = Pressure relief valve setting X 2.31 X 1.03 ÷ Liquid Specific Gravity
Example: Head = 115 psi X 2.31 X 1.03 ÷ 0.953 = 287 feet
X
X
X
X
X
X
X
X
X
X
Step Action
1 Determinecontrolmethodtobeused
2 CalculateBASEflow rate
3 Addfor ContinuousBoiler Blowdownflow
4 Addfor by-passflow if required
5 Sum of baseflow,by-passflow,andBlowdownflow isthetotalflow required
6 CalculateBASEpumpinghead
7 Addfor allsuctionpipingheadcomponents
8 Addfor alldischargepipingsystem headcomponents(includingfeedvalveif required)
9 Sum of allheadcomponents=totalpumpinghead
10 Calculateheadat boiler safetyvavlesettingplusthreepercent
11 Determinedeaerator tankwater temperature
12 Perform NPSHacalculation
13 Makepreliminarypumpselection
14 Assurethat shutoff headequalsor exceedsthreepercent abovesafetyvalvesetting
15 CheckNPSHr versusNPSHa
16 Assurematerialcompatibility- chemicalandtemperature
17 Makefinalpumpselection
63
STEP 11 –
Determine deaerator tank water temperature
From specification: 227°F
64
STEP 12 –
NPSHa calculation
NPSHa equation:
± Elevation + Absolute pressure – Vapor Pressure – Suction Line Friction = NPSHa
10 feet + (19.7 psi X 2.31) - (19.7 psi X 2.31) - 2 feet = NPSHa
10 feet + 46 feet - 46 feet - 2 feet = 8 feet NPSHa
65
STEP 13 –
Preliminary pump selection
• Conditions of
Service:
• Flow = 23 gpm
• Head = 237 feet
Does this 9
stage pump
pump meet the
required flow
and head
conditions of
service?
YES
66
STEP 14 –
Pressure safety valve considerations –
check requirement vs actual
67
STEP 15 –
Check NPSHa vs NPSHr
• Conditions of Service:
• Flow = 23 gpm
• Head = 237 Feet
• NPSHa = 8 Feet
• Pump meets or exceeds
flow/head requirement
• Low-NPSHr first stage = 3.5 feet
required
• NPSHr safety factor = 2 to 4 feet
• Target NPSHr = 7.5 feet
• NPSHa = 8 feet
Does NPSHa equal or exceed NPSHr?
YES
68
STEP 15 –
NPSH - Continued
• Conditions of Service: Flow = 23 gpm Head = 237 feet NPSHa = 8 Feet
• The NPSHa of 8 feet exceeds the NPSHr of 7.5 feet
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Step Action
1 Determine control method to be used
2 Calculate BASEflow rate
3 Add for ContinuousBoiler Blowdown flow
4 Add for by-passflow if required
5 Sum of base flow,by-passflow,and Blowdown flow isthe total flow required
6 Calculate BASEpumping head
7 Add for all suction piping head components
8 Add for all discharge piping system head components(including feed valve if required)
9 Sum of all head components= total pumping head
10 Calculate head at boiler safety vavle setting plusthree percent
11 Determine deaerator tank water temperature
12 Perform NPSHa calculation
13 Make preliminary pump selection
14 Assure that shutoff head equalsor exceedsthree percent above safety valve setting
15 Check NPSHr versusNPSHa
16 Assure material compatibility - chemical and temperature
17 Make final pump selection
69
STEP 16 –
Check material compatibility
• Pump materials: 316 stainless steel
• Mechanical seal materials: Silicon carbide/silicon carbide/EPDM
70
STEP 17 –
Final pump selection
• Pump meets all specification requirements
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Step Action
1 Determine control method to be used
2 Calculate BASEflow rate
3 Add for ContinuousBoiler Blowdown flow
4 Add for by-passflow if required
5 Sum of base flow,by-passflow,and Blowdown flow isthe total flow required
6 Calculate BASEpumping head
7 Add for all suction piping head components
8 Add for all discharge piping system head components(including feed valve if required)
9 Sum of all head components= total pumping head
10 Calculate head at boiler safety vavle setting plusthree percent
11 Determine deaerator tank water temperature
12 Perform NPSHa calculation
13 Make preliminary pump selection
14 Assure that shutoff head equalsor exceedsthree percent above safety valve setting
15 Check NPSHr versusNPSHa
16 Assure material compatibility - chemical and temperature
17 Make final pump selection
71
SUMMARY OF
PERFORMANCE CHARACTERISTICS
Exercise
#
Speed
Type
Use
Feed
Valve?
Reciculatio
n Line?
Duty Point
GPM Flow
Duty Point
Feet of
Head
Pump
Size
Number
of Stages
Efficiency at
Duty Point
BHP at
Duty
Point
1 Fixed Yes Yes 28 272 1.25 x 1.25 11 65% 2.96
2 Variable Yes Yes 28 272 1.25 x 1.25 11 65% 2.96
3 Variable No No 23 237 1.25 x 1.25 9 63% 2.18
Advantages of control via variable speed pump without feed valve and without bypass:
• Even steam production
• Faster reaction with changed speed consumption
• Fewer losses by variable level
• Carryover
• Few stages – lower initial cost
• Eliminate feed valve expense, maintenance, and head loss
• Eliminate bypass line expense and wasted flow recirculation
• Reduced energy consumption and costs
• Particularly at reduced speeds, flows, and heads
• Disadvantage: More complex to commission and start up.
72
6
1
GRUNDFOS TECHNICAL
INSTITUTE
www.grundfos.us/training
• Virtual Classroom
- Self-Paced
- Over 40 courses
- Certificates of Completion
• Webinars
- Live and Recorded
• Face-to-Face Training
73
SUMMARY
• The low water cutoff and pump control is the most important safety device on the boiler.
• It controls the safe level of water in the boiler and shuts it down when the level drops to an unsafe
level
• The level control may include a float with switches or other electronic devices providing safe
monitoring and pump, and/or MFWV energizing.
• These electronic level controls can work in conjunction with VFD’s
• Three element feedwater control involves the interrelationship of level, steam flow, and feedwater flow
• With on/off pump control the signal comes from the LWCO and there is no MFWV or by-pass line.
• Continuous running pump strategy with MFWV includes a by-pass to assure proper operation, and it
may add to the size of the pump.
• A continuous running pump with VFD & MFWV also requires a by-pass line to compensate for no or
low flow conditions.
• With this strategy, the signal for the MFWV normally comes from the level control and a separate loop
controller is used for the VFD.
• With the Auto valve in the by-pass line, the re-circ stops when full flow conditions exist, saving pump
energy, and possibly resulting in a smaller pump size..
• .With VFD and no MFWV, the re-circ line is eliminated resulting in a smaller pump selection
• This strategy requires an expert technician for commissioning.
74
Gregg Achtenhagen
gachtenhagen@cleaverbrooks.com
Jim Swetye
jswetye@grundfos.com
QUESTIONS?

More Related Content

What's hot

Automatic Recirculation Valve
Automatic Recirculation ValveAutomatic Recirculation Valve
Automatic Recirculation ValveAhmed Abd ElKader
 
Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerVaibhav Paydelwar
 
Cfbc boiler startup and shutdown
Cfbc boiler startup and shutdownCfbc boiler startup and shutdown
Cfbc boiler startup and shutdownAshvani Shukla
 
Uniform heat transfer in fired heaters
Uniform heat transfer in fired heatersUniform heat transfer in fired heaters
Uniform heat transfer in fired heatersAshutosh Garg
 
Flare stack design drawing (25 ft) with structural support
Flare stack design drawing (25 ft) with structural support Flare stack design drawing (25 ft) with structural support
Flare stack design drawing (25 ft) with structural support Design HuB
 
Improve fired heaters performance and reliabilty
Improve fired heaters performance and reliabiltyImprove fired heaters performance and reliabilty
Improve fired heaters performance and reliabiltyAshutosh Garg
 
Fired Heater Operation and Trouble Shooting.pdf
Fired Heater  Operation and Trouble Shooting.pdfFired Heater  Operation and Trouble Shooting.pdf
Fired Heater Operation and Trouble Shooting.pdfMuhammadNaeem191352
 
Fired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
Fired Heaters-Key to Efficient Operation of Refineries and PetrochemicalsFired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
Fired Heaters-Key to Efficient Operation of Refineries and PetrochemicalsAshutosh Garg
 
Feb. 2016 webinar_condensate_return_piping
Feb. 2016 webinar_condensate_return_pipingFeb. 2016 webinar_condensate_return_piping
Feb. 2016 webinar_condensate_return_pipinglorenzo Monasca
 

What's hot (20)

Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
 
Automatic Recirculation Valve
Automatic Recirculation ValveAutomatic Recirculation Valve
Automatic Recirculation Valve
 
Super critical boiler
Super critical boilerSuper critical boiler
Super critical boiler
 
FAQ on Turbines Part 2
FAQ on Turbines Part 2FAQ on Turbines Part 2
FAQ on Turbines Part 2
 
Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam Boiler
 
O&m of boiler
O&m of boilerO&m of boiler
O&m of boiler
 
Cfbc boiler startup and shutdown
Cfbc boiler startup and shutdownCfbc boiler startup and shutdown
Cfbc boiler startup and shutdown
 
Steam Blow out
Steam Blow outSteam Blow out
Steam Blow out
 
Caldeiras
CaldeirasCaldeiras
Caldeiras
 
Uniform heat transfer in fired heaters
Uniform heat transfer in fired heatersUniform heat transfer in fired heaters
Uniform heat transfer in fired heaters
 
Flare stack design drawing (25 ft) with structural support
Flare stack design drawing (25 ft) with structural support Flare stack design drawing (25 ft) with structural support
Flare stack design drawing (25 ft) with structural support
 
Thermax B & W U BEAM TYPE
Thermax B & W                    U BEAM TYPEThermax B & W                    U BEAM TYPE
Thermax B & W U BEAM TYPE
 
Boiler Feedwater Pumps
Boiler Feedwater PumpsBoiler Feedwater Pumps
Boiler Feedwater Pumps
 
Improve fired heaters performance and reliabilty
Improve fired heaters performance and reliabiltyImprove fired heaters performance and reliabilty
Improve fired heaters performance and reliabilty
 
Fired Heater Operation and Trouble Shooting.pdf
Fired Heater  Operation and Trouble Shooting.pdfFired Heater  Operation and Trouble Shooting.pdf
Fired Heater Operation and Trouble Shooting.pdf
 
Fired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
Fired Heaters-Key to Efficient Operation of Refineries and PetrochemicalsFired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
Fired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
 
Boiler Superheater Design Modification
Boiler Superheater Design ModificationBoiler Superheater Design Modification
Boiler Superheater Design Modification
 
Feb. 2016 webinar_condensate_return_piping
Feb. 2016 webinar_condensate_return_pipingFeb. 2016 webinar_condensate_return_piping
Feb. 2016 webinar_condensate_return_piping
 
Boiler book 2005
Boiler book 2005Boiler book 2005
Boiler book 2005
 
Pipe Supports and Expansion Joints for Furnace Applications
Pipe Supports and Expansion Joints for Furnace ApplicationsPipe Supports and Expansion Joints for Furnace Applications
Pipe Supports and Expansion Joints for Furnace Applications
 

Viewers also liked

Cb gf web in sep 2016, feeding chemicals to boilers sfc r3
Cb gf web in sep 2016, feeding chemicals to boilers sfc r3Cb gf web in sep 2016, feeding chemicals to boilers sfc r3
Cb gf web in sep 2016, feeding chemicals to boilers sfc r3lorenzo Monasca
 
Boiler Drum And Its Internals
Boiler Drum And Its InternalsBoiler Drum And Its Internals
Boiler Drum And Its InternalsAshrant Dass
 
Boiler
BoilerBoiler
Boileravik
 
Pumps and piping
Pumps and pipingPumps and piping
Pumps and pipingHashim Khan
 
Practical Boiler Control & Instrumentation for Engineers & Technicians
Practical Boiler Control & Instrumentation for Engineers & TechniciansPractical Boiler Control & Instrumentation for Engineers & Technicians
Practical Boiler Control & Instrumentation for Engineers & TechniciansLiving Online
 
A Brief Introduction to Boilers
A Brief Introduction to BoilersA Brief Introduction to Boilers
A Brief Introduction to BoilersSATYAKAM MOHAPATRA
 
Thermal plant instrumentation and control
Thermal plant instrumentation and controlThermal plant instrumentation and control
Thermal plant instrumentation and controlShilpa Shukla
 
Boiler instrumentation-and-controls
Boiler instrumentation-and-controlsBoiler instrumentation-and-controls
Boiler instrumentation-and-controlsDARSHAN B S
 

Viewers also liked (15)

Boiler equipments
Boiler equipmentsBoiler equipments
Boiler equipments
 
CBEX Firetube Line
CBEX Firetube LineCBEX Firetube Line
CBEX Firetube Line
 
Cb gf web in sep 2016, feeding chemicals to boilers sfc r3
Cb gf web in sep 2016, feeding chemicals to boilers sfc r3Cb gf web in sep 2016, feeding chemicals to boilers sfc r3
Cb gf web in sep 2016, feeding chemicals to boilers sfc r3
 
Boiler Feed Water
Boiler Feed WaterBoiler Feed Water
Boiler Feed Water
 
Boiler Drum And Its Internals
Boiler Drum And Its InternalsBoiler Drum And Its Internals
Boiler Drum And Its Internals
 
Boiler feedwater
Boiler feedwaterBoiler feedwater
Boiler feedwater
 
Boiler
BoilerBoiler
Boiler
 
BOILER INSTRUMENTATION
BOILER INSTRUMENTATIONBOILER INSTRUMENTATION
BOILER INSTRUMENTATION
 
Pumps and piping
Pumps and pipingPumps and piping
Pumps and piping
 
Practical Boiler Control & Instrumentation for Engineers & Technicians
Practical Boiler Control & Instrumentation for Engineers & TechniciansPractical Boiler Control & Instrumentation for Engineers & Technicians
Practical Boiler Control & Instrumentation for Engineers & Technicians
 
A Brief Introduction to Boilers
A Brief Introduction to BoilersA Brief Introduction to Boilers
A Brief Introduction to Boilers
 
Boiler operation
Boiler operationBoiler operation
Boiler operation
 
Thermal plant instrumentation and control
Thermal plant instrumentation and controlThermal plant instrumentation and control
Thermal plant instrumentation and control
 
Boiler Introduction
Boiler IntroductionBoiler Introduction
Boiler Introduction
 
Boiler instrumentation-and-controls
Boiler instrumentation-and-controlsBoiler instrumentation-and-controls
Boiler instrumentation-and-controls
 

Similar to Cb gf web in aug 2016, controls r2 8.23.16 final

Condensate Return Solutions.ppt
Condensate Return Solutions.pptCondensate Return Solutions.ppt
Condensate Return Solutions.pptssuser8006c7
 
Overview of Conflow Products
Overview of Conflow ProductsOverview of Conflow Products
Overview of Conflow ProductsGary Wain
 
Pump and cooling tower energy performance
Pump and cooling tower energy performancePump and cooling tower energy performance
Pump and cooling tower energy performancemaulik610
 
Gas Lift Optimization and Troubleshooting
Gas Lift Optimization and Troubleshooting Gas Lift Optimization and Troubleshooting
Gas Lift Optimization and Troubleshooting Bailey LeRoux
 
280 Series One & Two Stage Turbines/Multi-Stage Vertical In-Line Boiler Feed ...
280 Series One & Two Stage Turbines/Multi-Stage Vertical In-Line Boiler Feed ...280 Series One & Two Stage Turbines/Multi-Stage Vertical In-Line Boiler Feed ...
280 Series One & Two Stage Turbines/Multi-Stage Vertical In-Line Boiler Feed ...Callaghan Pump and Controls, Inc.
 
Module 1 heating - steam (wecompress.com)
Module 1   heating - steam (wecompress.com)Module 1   heating - steam (wecompress.com)
Module 1 heating - steam (wecompress.com)DeepakSingh1807
 
Plumbing "cold water supply" Workshop
Plumbing "cold water supply" WorkshopPlumbing "cold water supply" Workshop
Plumbing "cold water supply" WorkshopAhmed Kamal
 
Application of Fluid Mechanics in Agriculture
Application of Fluid Mechanics in AgricultureApplication of Fluid Mechanics in Agriculture
Application of Fluid Mechanics in AgricultureSaravanaKumaran17
 
chilled-water-system-presentation.pdf
chilled-water-system-presentation.pdfchilled-water-system-presentation.pdf
chilled-water-system-presentation.pdfbui thequan
 
Concept NoteR1.ppt
Concept NoteR1.pptConcept NoteR1.ppt
Concept NoteR1.pptMILIND569137
 
Learningpowerplantbasics
LearningpowerplantbasicsLearningpowerplantbasics
Learningpowerplantbasicslovelyshree
 
Learningpowerplantbasics
LearningpowerplantbasicsLearningpowerplantbasics
Learningpowerplantbasicsnarayanshree
 
Community water distribution
Community water distributionCommunity water distribution
Community water distributionconsultantpiping
 
Improving Energy Efficiency of Pumps and Fans
Improving Energy Efficiency of Pumps and FansImproving Energy Efficiency of Pumps and Fans
Improving Energy Efficiency of Pumps and Fanseecfncci
 
chapter four_ fluid power system lect.pptx
chapter four_ fluid power system lect.pptxchapter four_ fluid power system lect.pptx
chapter four_ fluid power system lect.pptxnurcam1
 
Y2 PUMPS TRAINING FOR OIL AND GAS OPERATION.ppt
Y2 PUMPS TRAINING FOR OIL AND GAS OPERATION.pptY2 PUMPS TRAINING FOR OIL AND GAS OPERATION.ppt
Y2 PUMPS TRAINING FOR OIL AND GAS OPERATION.pptssuser2ec709
 
Energy conservation related to pumps used in thermal power stations
Energy conservation related to pumps used in thermal power stationsEnergy conservation related to pumps used in thermal power stations
Energy conservation related to pumps used in thermal power stationsManohar Tatwawadi
 

Similar to Cb gf web in aug 2016, controls r2 8.23.16 final (20)

Piping system
Piping systemPiping system
Piping system
 
Condensate Return Solutions.ppt
Condensate Return Solutions.pptCondensate Return Solutions.ppt
Condensate Return Solutions.ppt
 
Overview of Conflow Products
Overview of Conflow ProductsOverview of Conflow Products
Overview of Conflow Products
 
Pump and cooling tower energy performance
Pump and cooling tower energy performancePump and cooling tower energy performance
Pump and cooling tower energy performance
 
Gas Lift Optimization and Troubleshooting
Gas Lift Optimization and Troubleshooting Gas Lift Optimization and Troubleshooting
Gas Lift Optimization and Troubleshooting
 
280 Series One & Two Stage Turbines/Multi-Stage Vertical In-Line Boiler Feed ...
280 Series One & Two Stage Turbines/Multi-Stage Vertical In-Line Boiler Feed ...280 Series One & Two Stage Turbines/Multi-Stage Vertical In-Line Boiler Feed ...
280 Series One & Two Stage Turbines/Multi-Stage Vertical In-Line Boiler Feed ...
 
Module 1 heating - steam (wecompress.com)
Module 1   heating - steam (wecompress.com)Module 1   heating - steam (wecompress.com)
Module 1 heating - steam (wecompress.com)
 
Plumbing "cold water supply" Workshop
Plumbing "cold water supply" WorkshopPlumbing "cold water supply" Workshop
Plumbing "cold water supply" Workshop
 
Application of Fluid Mechanics in Agriculture
Application of Fluid Mechanics in AgricultureApplication of Fluid Mechanics in Agriculture
Application of Fluid Mechanics in Agriculture
 
chilled-water-system-presentation.pdf
chilled-water-system-presentation.pdfchilled-water-system-presentation.pdf
chilled-water-system-presentation.pdf
 
Concept NoteR1.ppt
Concept NoteR1.pptConcept NoteR1.ppt
Concept NoteR1.ppt
 
Learningpowerplantbasics
LearningpowerplantbasicsLearningpowerplantbasics
Learningpowerplantbasics
 
Learningpowerplantbasics
LearningpowerplantbasicsLearningpowerplantbasics
Learningpowerplantbasics
 
Community water distribution
Community water distributionCommunity water distribution
Community water distribution
 
Artificial Lift Methods
Artificial Lift MethodsArtificial Lift Methods
Artificial Lift Methods
 
Improving Energy Efficiency of Pumps and Fans
Improving Energy Efficiency of Pumps and FansImproving Energy Efficiency of Pumps and Fans
Improving Energy Efficiency of Pumps and Fans
 
Efficient Steam Systems -
Efficient Steam Systems -Efficient Steam Systems -
Efficient Steam Systems -
 
chapter four_ fluid power system lect.pptx
chapter four_ fluid power system lect.pptxchapter four_ fluid power system lect.pptx
chapter four_ fluid power system lect.pptx
 
Y2 PUMPS TRAINING FOR OIL AND GAS OPERATION.ppt
Y2 PUMPS TRAINING FOR OIL AND GAS OPERATION.pptY2 PUMPS TRAINING FOR OIL AND GAS OPERATION.ppt
Y2 PUMPS TRAINING FOR OIL AND GAS OPERATION.ppt
 
Energy conservation related to pumps used in thermal power stations
Energy conservation related to pumps used in thermal power stationsEnergy conservation related to pumps used in thermal power stations
Energy conservation related to pumps used in thermal power stations
 

Recently uploaded

How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleCeline George
 
Basic Civil Engineering Notes of Chapter-6, Topic- Ecosystem, Biodiversity G...
Basic Civil Engineering Notes of Chapter-6,  Topic- Ecosystem, Biodiversity G...Basic Civil Engineering Notes of Chapter-6,  Topic- Ecosystem, Biodiversity G...
Basic Civil Engineering Notes of Chapter-6, Topic- Ecosystem, Biodiversity G...Denish Jangid
 
Pragya Champions Chalice 2024 Prelims & Finals Q/A set, General Quiz
Pragya Champions Chalice 2024 Prelims & Finals Q/A set, General QuizPragya Champions Chalice 2024 Prelims & Finals Q/A set, General Quiz
Pragya Champions Chalice 2024 Prelims & Finals Q/A set, General QuizPragya - UEM Kolkata Quiz Club
 
How to the fix Attribute Error in odoo 17
How to the fix Attribute Error in odoo 17How to the fix Attribute Error in odoo 17
How to the fix Attribute Error in odoo 17Celine George
 
Basic Civil Engg Notes_Chapter-6_Environment Pollution & Engineering
Basic Civil Engg Notes_Chapter-6_Environment Pollution & EngineeringBasic Civil Engg Notes_Chapter-6_Environment Pollution & Engineering
Basic Civil Engg Notes_Chapter-6_Environment Pollution & EngineeringDenish Jangid
 
The impact of social media on mental health and well-being has been a topic o...
The impact of social media on mental health and well-being has been a topic o...The impact of social media on mental health and well-being has been a topic o...
The impact of social media on mental health and well-being has been a topic o...sanghavirahi2
 
[GDSC YCCE] Build with AI Online Presentation
[GDSC YCCE] Build with AI Online Presentation[GDSC YCCE] Build with AI Online Presentation
[GDSC YCCE] Build with AI Online PresentationGDSCYCCE
 
UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...
UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...
UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...Sayali Powar
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345beazzy04
 
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdf
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdfINU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdf
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdfbu07226
 
Matatag-Curriculum and the 21st Century Skills Presentation.pptx
Matatag-Curriculum and the 21st Century Skills Presentation.pptxMatatag-Curriculum and the 21st Century Skills Presentation.pptx
Matatag-Curriculum and the 21st Century Skills Presentation.pptxJenilouCasareno
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXMIRIAMSALINAS13
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsCol Mukteshwar Prasad
 
Benefits and Challenges of Using Open Educational Resources
Benefits and Challenges of Using Open Educational ResourcesBenefits and Challenges of Using Open Educational Resources
Benefits and Challenges of Using Open Educational Resourcesdimpy50
 
Research Methods in Psychology | Cambridge AS Level | Cambridge Assessment In...
Research Methods in Psychology | Cambridge AS Level | Cambridge Assessment In...Research Methods in Psychology | Cambridge AS Level | Cambridge Assessment In...
Research Methods in Psychology | Cambridge AS Level | Cambridge Assessment In...Abhinav Gaur Kaptaan
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxEduSkills OECD
 
size separation d pharm 1st year pharmaceutics
size separation d pharm 1st year pharmaceuticssize separation d pharm 1st year pharmaceutics
size separation d pharm 1st year pharmaceuticspragatimahajan3
 
Industrial Training Report- AKTU Industrial Training Report
Industrial Training Report- AKTU Industrial Training ReportIndustrial Training Report- AKTU Industrial Training Report
Industrial Training Report- AKTU Industrial Training ReportAvinash Rai
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersPedroFerreira53928
 
Morse OER Some Benefits and Challenges.pptx
Morse OER Some Benefits and Challenges.pptxMorse OER Some Benefits and Challenges.pptx
Morse OER Some Benefits and Challenges.pptxjmorse8
 

Recently uploaded (20)

How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
 
Basic Civil Engineering Notes of Chapter-6, Topic- Ecosystem, Biodiversity G...
Basic Civil Engineering Notes of Chapter-6,  Topic- Ecosystem, Biodiversity G...Basic Civil Engineering Notes of Chapter-6,  Topic- Ecosystem, Biodiversity G...
Basic Civil Engineering Notes of Chapter-6, Topic- Ecosystem, Biodiversity G...
 
Pragya Champions Chalice 2024 Prelims & Finals Q/A set, General Quiz
Pragya Champions Chalice 2024 Prelims & Finals Q/A set, General QuizPragya Champions Chalice 2024 Prelims & Finals Q/A set, General Quiz
Pragya Champions Chalice 2024 Prelims & Finals Q/A set, General Quiz
 
How to the fix Attribute Error in odoo 17
How to the fix Attribute Error in odoo 17How to the fix Attribute Error in odoo 17
How to the fix Attribute Error in odoo 17
 
Basic Civil Engg Notes_Chapter-6_Environment Pollution & Engineering
Basic Civil Engg Notes_Chapter-6_Environment Pollution & EngineeringBasic Civil Engg Notes_Chapter-6_Environment Pollution & Engineering
Basic Civil Engg Notes_Chapter-6_Environment Pollution & Engineering
 
The impact of social media on mental health and well-being has been a topic o...
The impact of social media on mental health and well-being has been a topic o...The impact of social media on mental health and well-being has been a topic o...
The impact of social media on mental health and well-being has been a topic o...
 
[GDSC YCCE] Build with AI Online Presentation
[GDSC YCCE] Build with AI Online Presentation[GDSC YCCE] Build with AI Online Presentation
[GDSC YCCE] Build with AI Online Presentation
 
UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...
UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...
UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdf
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdfINU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdf
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdf
 
Matatag-Curriculum and the 21st Century Skills Presentation.pptx
Matatag-Curriculum and the 21st Century Skills Presentation.pptxMatatag-Curriculum and the 21st Century Skills Presentation.pptx
Matatag-Curriculum and the 21st Century Skills Presentation.pptx
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
Benefits and Challenges of Using Open Educational Resources
Benefits and Challenges of Using Open Educational ResourcesBenefits and Challenges of Using Open Educational Resources
Benefits and Challenges of Using Open Educational Resources
 
Research Methods in Psychology | Cambridge AS Level | Cambridge Assessment In...
Research Methods in Psychology | Cambridge AS Level | Cambridge Assessment In...Research Methods in Psychology | Cambridge AS Level | Cambridge Assessment In...
Research Methods in Psychology | Cambridge AS Level | Cambridge Assessment In...
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 
size separation d pharm 1st year pharmaceutics
size separation d pharm 1st year pharmaceuticssize separation d pharm 1st year pharmaceutics
size separation d pharm 1st year pharmaceutics
 
Industrial Training Report- AKTU Industrial Training Report
Industrial Training Report- AKTU Industrial Training ReportIndustrial Training Report- AKTU Industrial Training Report
Industrial Training Report- AKTU Industrial Training Report
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
 
Morse OER Some Benefits and Challenges.pptx
Morse OER Some Benefits and Challenges.pptxMorse OER Some Benefits and Challenges.pptx
Morse OER Some Benefits and Challenges.pptx
 

Cb gf web in aug 2016, controls r2 8.23.16 final

  • 1. BOILER FEED WATER CONTROL Presented by Cleaver Brooks’ Steve Connor and Grundfos’ Jim Swetye
  • 2. TODAY’S AGENDA • Again address high pressure boilers (FT & IWT) in the 100 – 1200 HP range • Where the water level is measured in these boilers • The ways in which the pressure in the boiler and system is controlled • Maintaining a reliable and safe level of water in the boiler is critical • Ways in which the boiler water level is controlled • Matching this control with (4) distinct pumping strategies • A couple pump selection exercises • Summary • Q&A 2
  • 3. FIRETUBE Watertube (IWT) Integral burner Gun burner Maximizing Efficiency with Hydronic Boilers 3
  • 4. BOILER SIZES AND FEED PUMP SIZES Boiler HP Range Boiler Pressure Range Typical Feed Pump Type Typical Max. Feed Pump Flow Range Typical Max. Feed Pump Head Where Used? 100 to 1200 150 to 500 psi Vertical inline multistage; regenerative turbines 10 to 125 gpm 1250 feet General industry; institutional; universities; some commercial buildings 4
  • 5. WATERTUBE OR IWT Maximizing Efficiency with Hydronic Boilers 5
  • 6. THE WATERTUBE BOILER • Opposite of Firetube • Water in the Tubes • Natural and Forced Circulation • Large Furnace • Upper & Lower Drums or Headers Upper Steam Drum Lower Mud Drum Furnace Outlet nozzle location 6
  • 7. STEAM QUALITY Steam disengaging area Water level IWT Upper Steam drum Steam outlet 7
  • 10. HEATING SURFACE Safe water level 2000 Deg. F 900 Deg. F Steam 10
  • 11.
  • 12.
  • 13.
  • 14.
  • 15.
  • 16. Operating High Limit Modulating 16
  • 17. TYPICAL STEAM SYSTEM T T T T T Legend Steam Cond Vapor HPCondReturn D A TankD A Tank Feed PumpBoiler Strainer Trap Trap Trap TT TT DA Tank TT TT TTT Legend Trap HP Steam PRV LP Steam Trap LP Condensate Return Motive Force Flash Modulating Control or Transducer 17
  • 20. LOW WATER CUTOFF & PUMP CONTROL 20
  • 23. At 0”= 2” Section I, High pressure boilers is first visible point in GG = 2” above tubes… 23
  • 25. MAGNETOSTRICTIVE BOILER LEVEL CONTROL TECHNOLOGY Sensing rod Titanium float Sensor head Display box 25
  • 26. PLC Platform Modulating feed water valve Pump Loop Controller(s) 26
  • 29. 29
  • 30. BOILER FEED PUMP CONTROL METHODS 1. On/Off control and fixed speed pumps 2. Feed control valve and fixed speed pumps 3. Feed control valve and variable speed pumps 4. Variable speed pumps only (no control valve) Method# Name 30
  • 31. Deaerator Feed pumps Burner Boiler Control box METHOD #1 – On/off control with fixed speed pump 31
  • 32. Advantages: • Inexpensive • Simple to install • No bypass • No feed valve Disadvantages: • Mechanical stress on the boiler • Pumps are liable to cavitate at start-up • Large number of Starts-Stops can stress pumps • Variations in steam production • Boiler water swell and carry-over METHOD #1 – On/off control with fixed speed pump 32
  • 33. Deaerator Feed pumps Burner Boiler Bypass Feed valve METHOD #2 – Feed valve with fixed speed pumps 33
  • 34. Advantages: • Minimize risk of boiler water swell/carry-over • Feed is adjusted according to steam consumption • Steam quality higher due to more constant water level Disadvantages: • Bypass is required • Feed valves are expensive • Pressure loss across the feed valve requires larger sized pumps METHOD #2 – Feed valve with fixed speed pumps 34
  • 35. Deaerator Feed pumps Boiler Recirculation line Feed valve Transducer METHOD #3 – Feedvalvewithvariablespeedpumpswithrecirculationline Level Sensor 35
  • 36. Advantages: • Minimize the risk of water sink & swell/carry-over • Feed adjusted according to steam consumption • Energy savings on pump operation • Steam quality higher due to more constant water level Disadvantages: • Bypass is required • Feed valve is expensive • Pressure loss across feed valve requires larger sized pumps • Stopping pump at closed valve requires signal from pressure transducer METHOD #3 – Feedvalvewithvariablespeedpumpswithrecirculationline 36
  • 37. RE-CIRCULATION FLOW WITH AUTO VALVE Re-circulation common manifold Re-circulation lines Auto Valve in recirculation line Service line with normally closed shutoff valve 37
  • 38. Deaerator Feed pumps Boiler Sensor METHOD #4 – Variable speed pumps less feed valve 38
  • 39. Advantages: • Feed is adjusted according to steam consumption • Even steam production • Faster reaction with changed speed • Energy savings on pump operation • No bypass line • No feed valve and associated pressure loss • Minimize risk of swell/carry-over Disadvantages: • Requires precise and qualified start-up • Non-return valve required • Minimum frequency must be defined to ensure pump can always overcome the pressure in boiler – pump MUST stop when steam consumption is zero METHOD #4 – Variable speed pumps less feed valve 39
  • 40. SUMMARY OF CONTROL METHODS Method # Name Pump Speed Type Duty Uses feed valve? Is orifice flow recirculation by-pass line required? 1 On/Off control and fixed speed pumps Fixed Intermittent No No 2 Feed control valve and fixed speed pumps Fixed Continuous Yes Yes 3 Feed control valve and variable speed pumps Variable Continuous Yes Yes 4 Variable speed pumps only (no control valve) Variable Continuous No No 40
  • 41. CHECKLIST – Boiler feed pump selection process Step Action 1 Determine control method to be used 2 Calculate BASE flow rate 3 Add for by-pass flow if required 4 Sum of base flow and by-pass flow is the total flow required 5 Calculate BASE pumping head 6 Add for all suction piping head components 7 Add for all discharge piping system head components (including feed valve if required) 8 Sum of all head components = total pumping head 9 Determine deaerator tank water temperature 10 Perform NPSHa calculation 11 Make preliminary pump selection 12 Check NPSHr versus NPSHa 13 Assure material compatibility - chemical and temperature 14 Make final pump selection 41
  • 42. BOILER FEED PUMPS: USEFUL FORMULAS 1. Base flow calculation equation Boiler maximum capacity horsepower X 0.069 X C = Base flow rate C = 1.50 for On/Off intermittent operation C = 1.15 for continuous feed operation 2. Determine BASE head for feed pump Formula based on Safety Valve setting: Pump head in feet = Maximum pressure X 2.31 X 1.03 ÷ Liquid Specific Gravity 3. Head components on suction side of piping system Pressure above atmospheric on deaerator converted to feet of head = feet Elevation difference between minimum deaerator water level and pump inlet = feet Suction pipe friction loss = feet Suction fitting friction loss = feet Suction line valves and strainer friction loss = feet Total = feet 4. Head components on discharge side of piping system Friction loss through discharge piping = feet Friction loss through discharge fittings = feet Friction loss through feed valve = feet Elevation of boiler maximum water level above pump = feet Total = feet 5. NPSHa equation ± Elevation** + Absolute pressure – Vapor Pressure – Suction Line Friction = NPSHa (Feet) (psi X 2.31 = Feet) (psi X 2.31 = Feet) (Feet) (Feet) ** Elevation of deaerator tank minimum water level above pump’s first impeller 42
  • 43. SPECIFICATION FOR EXERCISE a) Control method is variable speed pump with bypass recirculation and feed valve b) Boiler maximum capacity = 250 HP c) Boiler safety valve setting – 125 psig d) Pressure safety factor = 3% above boiler’s safety valve setting e) Boiler operating pressure – 100 psig f) Continuous Boiler Blowdown flow - Required g) Bypass recirculation flow – Required h) Altitude – Sea level i) Pressure in deaerator tank above atmospheric pressure = 5 psi (14.7 + 5 = 19.7 psi absolute) j) Height of deaerator tank minimum water level above pump’s first impeller = 10 feet k) Friction line loss through suction piping = .5 foot l) Friction loss through suction side fittings = .5 foot m) Friction loss through suction side valves = None n) Friction loss through suction side strainer = 1 foot o) Friction loss through discharge piping = 1 foot p) Friction loss through discharge side fittings = 1 foot q) Friction loss through feed valve – 15 psi r) Elevation of boiler maximum water level above pump’s discharge port = 5 feet s) Liquid Specific Gravity = 0.955 t) Temperature of water in deaerator tank = 227 degrees F u) Vapor pressure in deaerator tank = 19.7 psi v) Pump materials all 316 stainless steel to resist treatment chemicals w) Mechanical seal to be silicon carbide/silicon carbide/EPDM to withstand liquid temperature 43
  • 44. FROM PREVIOUS EXERCISE – Fixed speed pumps with feed valve and recirculation line Recirculation line Feed valve Boiler Level Sensor Feed pumps Deaerator 44
  • 45. Deaerator Boiler Recirculation line Feed valve Feed pumps Transducer Level Sensor FROM CURRENT EXERCISE – #2 Feed Valve with Variable Speed Pumps with Recirculation line 45
  • 46. STEP 13 – Preliminary pump selection • Conditions of Service: • Flow = 28 gpm • Head = 272 feet Does this 11 stage pump pump meet the required flow and head conditions of service? YES 46
  • 47. SUMMARY OF PERFORMANCE CHARACTERISTICS Advantages of control via variable speed pump versus a fixed speed pump when using a feed valve and recirculation: • More even steam production • Faster reaction with changed speed consumption • Fewer losses by variable level • Carry over • Reduced energy consumption and operating costs However, the variable speed unit will be more expensive in initial purchase cost. For this reason, you must perform a Life Cycle Cost calculation before making your final decision on which method to use. Exercise # Use Feed Valve? Reciculation Line? Speed Type Duty Point GPM Flow Duty Point Feet of Head Pump Size Number of Stages Efficiency at Duty Point BHP at Duty Point 1 Yes Yes Fixed 28 272 1.25 x 1.25 11 65% 2.96 2 Yes Yes Variable 28 272 1.25 x 1.25 11 65% 2.96 47
  • 48. CURVE COMPARISON – FIXED SPEED VS VARIABLE SPEED Duty point operation at 3550 rpm 48
  • 49. CURVE COMPARISON – CONT. Fixed speed reduced flow Variable speed reduced flow Full speed BHP Reduced speed BHP 49
  • 50. Check list for boiler feed pump selection Step Action 1 Determine control method to be used 2 Calculate BASEflow rate 3 Add for ContinuousBoiler Blowdown flow 4 Add for by-passflow if required 5 Sum of base flow,by-passflow,and Blowdown flow isthe total flow required 6 Calculate BASEpumping head 7 Add for all suction piping head components 8 Add for all discharge piping system head components(including feed valve if required) 9 Sum of all head components= total pumping head 10 Calculate head at boiler safety vavle setting plusthree percent 11 Determine deaerator tank water temperature 12 Perform NPSHa calculation 13 Make preliminary pump selection 14 Assure that shutoff head equalsor exceedsthree percent above safety valve setting 15 Check NPSHr versusNPSHa 16 Assure material compatibility - chemical and temperature 17 Make final pump selection 50
  • 51. BOILER FEED PUMPS: USEFUL FORMULAS 1. Base flow calculation equation Boiler maximum capacity horsepower X 0.069 X C = Base flow rate C = 1.50 for On/Off intermittent operation C = 1.15 for continuous feed operation 2. Determine BASE head for feed pump Formula based on Safety Valve setting: Pump head in feet = Maximum pressure X 2.31 X 1.03 ÷ Liquid Specific Gravity 3. Head components on suction side of piping system Pressure above atmospheric on deaerator converted to feet of head = feet Elevation difference between minimum deaerator water level and pump inlet = feet Suction pipe friction loss = feet Suction fitting friction loss = feet Suction line valves and strainer friction loss = feet Total = feet 4. Head components on discharge side of piping system Friction loss through discharge piping = feet Friction loss through discharge fittings = feet Friction loss through feed valve = feet Elevation of boiler maximum water level above pump = feet Total = feet 5. NPSHa equation ± Elevation** + Absolute pressure – Vapor Pressure – Suction Line Friction = NPSHa (Feet) (psi X 2.31 = Feet) (psi X 2.31 = Feet) (Feet) (Feet) ** Elevation of deaerator tank minimum water level above pump’s first impeller 51
  • 52. SPECIFICATION FOR EXERCISE a) Control Method: Continuous duty variable speed pump (feed valve and recirculation line are not required) b) Boiler maximum capacity = 250 HP c) Boiler safety valve setting = 115 psig d) Pressure safety factor = 3% above boiler’s safety valve setting e) Boiler operating pressure = 100 psig f) Continuous Boiler Blowdown flow - Required g) Bypass recirculation flow – Not required h) Altitude – Sea level i) Pressure in deaerator tank above atmospheric pressure = 5 psi (14.7 + 5 = 19.7 psi absolute) j) Height of deaerator tank minimum water level above pump’s first impeller = 10 feet k) Friction line loss through suction piping = .5 foot l) Friction loss through suction side fittings = .5 foot m) Friction loss through suction side valves = None n) Friction loss through suction side strainer = 1 feet o) Friction loss through discharge piping = 1 foot p) Friction loss through discharge side fittings = 1 foot q) Pressure drop across feed valve – None – Feed valve is not required r) Elevation of boiler maximum water level above pump’s discharge port = 5 feet s) Liquid Specific Gravity = 0.953 t) Temperature of water in deaerator tank = 227 degrees F u) Vapor pressure in deaerator tank = 19.7 psi v) Pump materials all 316 stainless steel to resist treatment chemicals w) Mechanical seal to be silicon carbide/silicon carbide/EPDM to withstand liquid temperature 52
  • 53. Deaerator Feed pumps Boiler Sensor FROM CURRENT EXERCISE – # 3: Variable speed pumps (without feed valve and without recirculation line) 53
  • 54. STEP 1 – • Determine control method • A variable speed pump has been specified. Specification excludes feed valve and recirculation line X Step Action 1 Determine control method to be used 2 Calculate BASEflow rate 3 Add for ContinuousBoiler Blowdown flow 4 Add for by-passflow if required 5 Sum of base flow,by-passflow,and Blowdown flow isthe total flow required 6 Calculate BASEpumping head 7 Add for all suction piping head components 8 Add for all discharge piping system head components(including feed valve if required) 9 Sum of all head components=total pumping head 10 Calculate head at boiler safety vavle setting plusthree percent 11 Determine deaerator tank water temperature 12 Perform NPSHa calculation 13 Make preliminary pump selection 14 Assure that shutoff head equalsor exceedsthree percent above safety valve setting 15 Check NPSHr versusNPSHa 16 Assure material compatibility - chemical and temperature 17 Make final pump selection 54
  • 55. STEP 2 – Calculate the BASE feed pump flow rate The formula for this calculation is: • Boiler maximum capacity in horsepower X 0.069 X C • The maximum capacity in boiler horsepower is 250 • The C factor is 1.15 for continuous duty Therefore: 250 X 0.069 X 1.15 = 20 gpm = BASE flow rate 55
  • 56. STEP 3 – Continuous Boiler Blowdown Flow Determination: 1. The BASE flow rate has been established at 20 gpm 2. We will on next slide need to add for bypass flow, which can add 10 to 20 percent to the BASE flow rate 3. Blowdown flow is to be approximately 10 percent of flow at pump’s Best Efficiency Point 4. So the total boiler blowdown flow required is approximately 3 gpm 56
  • 57. STEP 4 – Recirculation by-pass flow Not required per the specification 57
  • 58. STEP 5 – Calculate total flow required • BASE flow = 20 gpm • Blowdown flow = 3 gpm • Recirculation flow = 0 gpm • Total flow required= 23 gpm X X X X X Step Action 1 Determinecontrolmethodtobeused 2 CalculateBASEflow rate 3 Addfor ContinuousBoiler Blowdownflow 4 Addfor by-passflow if required 5 Sum of baseflow,by-passflow,andBlowdownflow isthetotalflow required 6 CalculateBASEpumpinghead 7 Addfor allsuctionpipingheadcomponents 8 Addfor alldischargepipingsystem headcomponents(includingfeedvalveif required) 9 Sum of allheadcomponents=totalpumpinghead 10 Calculateheadat boiler safetyvavlesettingplusthreepercent 11 Determinedeaerator tankwater temperature 12 Perform NPSHacalculation 13 Makepreliminarypumpselection 14 Assurethat shutoff headequalsor exceedsthreepercent abovesafetyvalvesetting 15 CheckNPSHr versusNPSHa 16 Assurematerialcompatibility- chemicalandtemperature 17 Makefinalpumpselection 58
  • 59. STEP 6 – Calculate BASE pumping head • Boiler operating pressure setting + 3% Formula: BASE head in feet = Boiler operating pressure X 2.31 X 1.03 ÷ Specific Gravity BASE head = 100 psi X 2.31 X 1.03 ÷ 0.953 = 250 feet 59
  • 60. STEP 7 – Add for suction piping system head components From specification: Gauge pressure on deaerator tank = 5 psi X 2.31 = - 12 feet Water elevation above first impeller = - 10 feet Friction loss through suction piping = + .5 feet Friction loss through suction fittings = + .5 feet Friction loss through suction side valves and strainer = + 1 feet Total = - 20 feet 60
  • 61. STEP 8 – Add for discharge piping system head components From specification: Friction loss through discharge piping = + 1 foot Friction loss through discharge fittings = + 1 foot Friction loss through feed valve = + 0 feet Elevation of boiler maximum water level above pump = + 5 feet Total = + 7 feet 61
  • 62. STEP 9 – Sum of all head components BASE head with safety factor = + 250 feet Suction side piping system head = - 20 feet Discharge side piping system head = + 7 feet Total = + 237 feet 62
  • 63. STEP 10 – Pressure safety valve considerations At shutoff head (dead head): Head in feet = Pressure relief valve setting X 2.31 X 1.03 ÷ Liquid Specific Gravity Example: Head = 115 psi X 2.31 X 1.03 ÷ 0.953 = 287 feet X X X X X X X X X X Step Action 1 Determinecontrolmethodtobeused 2 CalculateBASEflow rate 3 Addfor ContinuousBoiler Blowdownflow 4 Addfor by-passflow if required 5 Sum of baseflow,by-passflow,andBlowdownflow isthetotalflow required 6 CalculateBASEpumpinghead 7 Addfor allsuctionpipingheadcomponents 8 Addfor alldischargepipingsystem headcomponents(includingfeedvalveif required) 9 Sum of allheadcomponents=totalpumpinghead 10 Calculateheadat boiler safetyvavlesettingplusthreepercent 11 Determinedeaerator tankwater temperature 12 Perform NPSHacalculation 13 Makepreliminarypumpselection 14 Assurethat shutoff headequalsor exceedsthreepercent abovesafetyvalvesetting 15 CheckNPSHr versusNPSHa 16 Assurematerialcompatibility- chemicalandtemperature 17 Makefinalpumpselection 63
  • 64. STEP 11 – Determine deaerator tank water temperature From specification: 227°F 64
  • 65. STEP 12 – NPSHa calculation NPSHa equation: ± Elevation + Absolute pressure – Vapor Pressure – Suction Line Friction = NPSHa 10 feet + (19.7 psi X 2.31) - (19.7 psi X 2.31) - 2 feet = NPSHa 10 feet + 46 feet - 46 feet - 2 feet = 8 feet NPSHa 65
  • 66. STEP 13 – Preliminary pump selection • Conditions of Service: • Flow = 23 gpm • Head = 237 feet Does this 9 stage pump pump meet the required flow and head conditions of service? YES 66
  • 67. STEP 14 – Pressure safety valve considerations – check requirement vs actual 67
  • 68. STEP 15 – Check NPSHa vs NPSHr • Conditions of Service: • Flow = 23 gpm • Head = 237 Feet • NPSHa = 8 Feet • Pump meets or exceeds flow/head requirement • Low-NPSHr first stage = 3.5 feet required • NPSHr safety factor = 2 to 4 feet • Target NPSHr = 7.5 feet • NPSHa = 8 feet Does NPSHa equal or exceed NPSHr? YES 68
  • 69. STEP 15 – NPSH - Continued • Conditions of Service: Flow = 23 gpm Head = 237 feet NPSHa = 8 Feet • The NPSHa of 8 feet exceeds the NPSHr of 7.5 feet X X X X X X X X X X X X X X X Step Action 1 Determine control method to be used 2 Calculate BASEflow rate 3 Add for ContinuousBoiler Blowdown flow 4 Add for by-passflow if required 5 Sum of base flow,by-passflow,and Blowdown flow isthe total flow required 6 Calculate BASEpumping head 7 Add for all suction piping head components 8 Add for all discharge piping system head components(including feed valve if required) 9 Sum of all head components= total pumping head 10 Calculate head at boiler safety vavle setting plusthree percent 11 Determine deaerator tank water temperature 12 Perform NPSHa calculation 13 Make preliminary pump selection 14 Assure that shutoff head equalsor exceedsthree percent above safety valve setting 15 Check NPSHr versusNPSHa 16 Assure material compatibility - chemical and temperature 17 Make final pump selection 69
  • 70. STEP 16 – Check material compatibility • Pump materials: 316 stainless steel • Mechanical seal materials: Silicon carbide/silicon carbide/EPDM 70
  • 71. STEP 17 – Final pump selection • Pump meets all specification requirements X X X X X X X X X X X X X X X X X Step Action 1 Determine control method to be used 2 Calculate BASEflow rate 3 Add for ContinuousBoiler Blowdown flow 4 Add for by-passflow if required 5 Sum of base flow,by-passflow,and Blowdown flow isthe total flow required 6 Calculate BASEpumping head 7 Add for all suction piping head components 8 Add for all discharge piping system head components(including feed valve if required) 9 Sum of all head components= total pumping head 10 Calculate head at boiler safety vavle setting plusthree percent 11 Determine deaerator tank water temperature 12 Perform NPSHa calculation 13 Make preliminary pump selection 14 Assure that shutoff head equalsor exceedsthree percent above safety valve setting 15 Check NPSHr versusNPSHa 16 Assure material compatibility - chemical and temperature 17 Make final pump selection 71
  • 72. SUMMARY OF PERFORMANCE CHARACTERISTICS Exercise # Speed Type Use Feed Valve? Reciculatio n Line? Duty Point GPM Flow Duty Point Feet of Head Pump Size Number of Stages Efficiency at Duty Point BHP at Duty Point 1 Fixed Yes Yes 28 272 1.25 x 1.25 11 65% 2.96 2 Variable Yes Yes 28 272 1.25 x 1.25 11 65% 2.96 3 Variable No No 23 237 1.25 x 1.25 9 63% 2.18 Advantages of control via variable speed pump without feed valve and without bypass: • Even steam production • Faster reaction with changed speed consumption • Fewer losses by variable level • Carryover • Few stages – lower initial cost • Eliminate feed valve expense, maintenance, and head loss • Eliminate bypass line expense and wasted flow recirculation • Reduced energy consumption and costs • Particularly at reduced speeds, flows, and heads • Disadvantage: More complex to commission and start up. 72
  • 73. 6 1 GRUNDFOS TECHNICAL INSTITUTE www.grundfos.us/training • Virtual Classroom - Self-Paced - Over 40 courses - Certificates of Completion • Webinars - Live and Recorded • Face-to-Face Training 73
  • 74. SUMMARY • The low water cutoff and pump control is the most important safety device on the boiler. • It controls the safe level of water in the boiler and shuts it down when the level drops to an unsafe level • The level control may include a float with switches or other electronic devices providing safe monitoring and pump, and/or MFWV energizing. • These electronic level controls can work in conjunction with VFD’s • Three element feedwater control involves the interrelationship of level, steam flow, and feedwater flow • With on/off pump control the signal comes from the LWCO and there is no MFWV or by-pass line. • Continuous running pump strategy with MFWV includes a by-pass to assure proper operation, and it may add to the size of the pump. • A continuous running pump with VFD & MFWV also requires a by-pass line to compensate for no or low flow conditions. • With this strategy, the signal for the MFWV normally comes from the level control and a separate loop controller is used for the VFD. • With the Auto valve in the by-pass line, the re-circ stops when full flow conditions exist, saving pump energy, and possibly resulting in a smaller pump size.. • .With VFD and no MFWV, the re-circ line is eliminated resulting in a smaller pump selection • This strategy requires an expert technician for commissioning. 74